Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

28
Post-Fall AGU SWT Meeting 1 UCB/SSL – Dec. 20, 2008 THEMIS ARTEMIS Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

description

Constellation Status, Plans for Future Manfred Bester University of California - Berkeley. Overview. Overview Prime Mission Constellation Status Science Operations Maneuver Summary Fuel Budget Extended Mission ARTEMIS Concept of Operations Top Level Schedule Network Communications - PowerPoint PPT Presentation

Transcript of Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Page 1: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 1 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS

Constellation Status,Plans for Future

Manfred Bester

University of California - Berkeley

Page 2: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 2 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Overview

Overview• Prime Mission• Constellation Status• Science Operations• Maneuver Summary• Fuel Budget• Extended Mission• ARTEMIS Concept of Operations• Top Level Schedule• Network Communications• Roles and Responsibilities• Navigation Plans• Summary of Future Plans

Page 3: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 3 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Prime Mission

5 Probes in synchronized Earth orbits with periods of 4, 2 and 1 days

Conjunctions are formed in magnetospheric tail every 4 days

Time History of Events and Macroscale Interactions during Substorms (THEMIS)

NASA Medium-class explorer mission Managed in PI Mode by UCLA/UCBhttp://themis.ssl.berkeley.eduhttp://www.nasa.gov/themis

Page 4: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 4 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Successful Launch Campaign

Launch:February 17, 2007

Probe Release: L + 70 min

Responsibility for Constellation Operations Transitioned to MOC at UCB

Page 5: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 5 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Prime Mission Status Summary

• Prime Mission Status• Completed LEOP, coast phase, tail 1 and dayside 1• Upcoming tail 2 and dayside 2 seasons• Answered primary scientific questions already

• Constellation Status• All probes very healthy and collecting science data• Fuel reserves allow for ambitious mission extension

• Ground Systems & Operations Status• All ground systems processing nominally• Executed 248 individual thrust operations to date• Completed 10,000 passes on December 3, 2008• All routine passes supported in lights-out mode

Page 6: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 6 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Constellation Status Page

Page 7: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 7 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Science Operations

• Science Instrument Commanding• Configuration changes discussed in ops meetings• All instruments command sequences typically tested

on FlatSat prior to upload• Ops team implemented 75 ICCRs to date

• Science Data Recovery Metrics• Data dumps near perigee at 512K or 1024K• Outer probes get two passes whenever possible• Recovered / acquired data volume: 98 - 99% • Recovered / required data volume: 111 - 147%• Tohban monitors data quality and completeness

Page 8: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 8 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Flight Systems Status

Flight Systems StatusSystem Subsystem Probe Status Comments

Spacecraft Bus

Bus Subsystems A - E Nominal

BAU FSW A - E Occasional glitches in on-board spin rate calculation

New BAU FSW version 0x3500 currently tested on FlatSat, upload scheduled for early 2009

Telecom A - E Antennas weaker than expected

Degraded operational link budgets(B: -3 dB; A,C,D: -4 dB; E: -5 dB)

Power A - E Nominal Power systems allow operation through 4-h shadows

Thermal A - E Nominal No issues in nominal mission attitude

E Thermal leak near Service Valve 2

Analysis shows no risk of freezing fuel lines

Thermistor on Solar Array 3 has open circuit in shadow

Thermistors on SA 1,2,4 provide redundant information

Instruments Instrument Suite A - E Nominal

IDPU FSW A - E Nominal All probes run IDPU FSW version 0x50

ESA A - E Small degradation in sensitivity of electron sensor below 30 eV in certain angle sectors

Localized MCP degradation in angle sectors looking along the spin axis may be caused by emission of photo electrons from axial booms – probes A and B have least amount of degradation, had booms deployed later

SST A - E Small degradation of sensitivity

Increased sensor bias once to restore nominal sensitivity

Page 9: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 9 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Anomaly Tracking

• Anomaly Tracking & Resolution• Tiger Team assigned for each flight system or major

ground system anomaly• Investigate and determine cause of anomaly• Recommend solutions, work-arounds and/or

mitigations• Provide final report

• Anomaly Tracking List• Items closed out when anomaly report released and

recommended actions were performed• Currently tracking 29 items (20 closed)

Page 10: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 10 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS THEMIS Orbit Determination

• Orbit determination (OD) for the THEMIS constellation is based on two-way Doppler tracking data and the Goddard Trajectory Determination System (GTDS).

• Tests are underway to characterize the THEMIS ranging capabilities for use during ARTEMIS.

Parameter THEMIS A/P5

THEMIS B/P1 THEMIS C/P2 THEMIS D/P3

THEMIS E/P4

Arc Length [d] 7 12 9 7 7

Number of Passes in Arc

25 40 32 25 25

Pass Duration [min] 20 - 30 20 - 30 20 - 30 20 - 30 20 - 30

Typical Achieved Accuracy

< 50 m

< 5 mm/s

< 50 m

< 5 mm/s

< 50 m

< 5 mm/s

< 50 m

< 5 mm/s

< 50 m

< 5 mm/s

Number of Orbit Solutions as of 11/24/2008

328 344 342 326 330

Page 11: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 11 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Executed Maneuver Summary

* ARTEMIS Probes

ParameterTHEMIS A

P5THEMIS B

P1*THEMIS C

P2*THEMIS D

P3THEMIS E

P4

Initial Fuel Load [kg] 48.800 48.780 48.810 48.810 48.820

Expended Fuel [kg] 23.412 33.508 27.029 20.208 19.944

Remaining Fuel [kg] 25.388 15.272 21.781 28.602 28.876

Total Expended ΔV [m/s]

452.600 694.618 537.979 390.927 377.661

Attitude Precessions 20 21 9 11 10

Spin Rate Changes 16 17 16 10 10

ΔV Maneuvers 23 22 27 17 19

Total Executed Maneuvers

59 60 52 38 39

Total executed thrust operations: 248

Page 12: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 12 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P1 Large Plane Change Maneuver

ΔV: 296.5 m/sFuel: 13.2 kg

Page 13: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 13 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P2 Large Plane Change Maneuver

ΔV: 227.7 m/sFuel: 10.5 kg

Page 14: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 14 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P1 Planned Maneuvers

* Spin target is 20.2105 ± 0.0130 rpm

THEMIS B/P1 Time (UTC) ΔV [m/s] Fuel Used [kg] Purpose

M03_T2 2008/347 23:58:04.658 1.417 0.058 Apogee - 1463 km

M03_T2 Spin Control Post M03_T2 0.020 0.001 Spin Control*

M04_T2 2009/017 05:50:00.028 4.581 0.188 Apogee - 4721 km

M04_T2 Attitude Change 2009/017 10:06:26.055 0.333 0.014 Attitude Change to Nominal

M04_T2 Spin Control Post M04_T2 0.033 0.001 Spin Control*

M05_T2 2009/062 16:37:09.413 6.428 0.263 Apogee + 6388 km

M05_T2 Spin Control Post M05_T2 0.040 0.002 Spin Control*

M1A_D2 2009/130 06:43:43.412 2.567 0.105 Apogee + 2494 km

M1A_D2 Attitude Change 2009/130 10:52:58.172 0.315 0.013 Attitude Change to Nominal

M1A_D2 Spin Control Post M1A_D2 0.047 0.002 Spin Control*

M03_D2 2009/158 14:33:14.154 3.444 0.141 Apogee - 3392 km

M03_D2 Spin Control Post M03_D2 0.073 0.003 Spin Control*

Contingency 10.674 0.5

Total 19.298 1.291

Page 15: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 15 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P2 Planned Maneuvers

* Spin target is 20.2105 ± 0.0130 rpm

THEMIS C/P2 Time (UTC) ΔV [m/s] Fuel Used [kg] Purpose

M03_T2 2008/346 01:30:27.968 3.664 0.164 Apogee +1384 km

M03_T2 Spin Control Post M03_T2 0.033 0.001 Spin Control*

M04_T2 2009/015 16:05:40.741 1.641 0.074 Apogee - 644 km

M04_T2 Spin Control Post M04_T2 0.020 0.001 Spin Control*

M05_T2 2009/062 19:23:31.781 2.468 0.110 Apogee + 957 km

M05_T2 Spin Control Post M05_T2 0.033 0.001 Spin Control*

M1A_D2 2009/128 07:33:27.684 4.581 0.205 Apogee + 1730 km

M1A_D2 Attitude Change 2009/128 11:43:39.382 0.247 0.011 Attitude Change to Nominal

M1A_D2 Spin Control Post M1A_D2 0.053 0.002 Spin Control*

M03_D2 2009/156 15:24:45.789 4.634 0.207 Apogee - 1761 km

M03_D2 Spin Control Post M03_D2 0.053 0.002 Spin Control*

Contingency 10.046 0.500

Total 27.473 1.278

Page 16: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 16 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P1 & P2 Remaining Fuel

THEMIS C/P2 Remaining ΔV [m/s] Remaining Fuel [kg]

End of THEMIS D2 468.1 20.5

ARTEMIS ACS / Contingency 20.2 1.0

Net Remaining 447.9 19.5

THEMIS B/P1 Remaining ΔV [m/s] Remaining Fuel [kg]

End of THEMIS D2 326.0 14.0

ARTEMIS ACS / Contingency 21.5 1.0

Net Remaining 304.5 13.0

Page 17: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 17 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Extended Mission

Time History of Events and Macroscale Interactions during Substorms (THEMIS)3 Probes (A/P5, D/P3, E/P4) in synchronized Earth orbits with 1-day periods

Acceleration, Reconnection, Turbulence and Electrodynamics of the Moon’s Interaction with the Sun (ARTEMIS)2 Probes (B/P1, C/P2) in lunar orbits

Page 18: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 18 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS ARTEMIS ConOps

• ARTEMIS Concept of Operations• Transfer of outer two probes (B/P1 and C/P2) into

lunar orbits via Weak Stability Boundary trajectory using Earth and lunar gravity assist

• Communications with these two probes via DSN• Data recovery from lunar distances up to 128K• Attitude determination with sun sensor data only• No required flight software changes

• THEMIS Concept of Operations• THEMIS mission continues with inner three probes

(A/P5, D/P3, E/P4) in tighter formationNOTES: For all operational purposes all five probes shall continue to be referred to as THEMIS A-E.

New capabilities at the MOC shall be considered an upgrade, not a transition.

Page 19: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 19 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS

Berkeley Multi-mission Operations Center

White SandsComplex

GSFC NMC

THEMISProbes

SecureIntranet

TDRS

Open IONet T1 Line

HBK

Isolated Dial-up ISDN Line

WS1, AGO, MILA, WGS

THEMIS/ARTEMIS Network Links

USNHI, USNAU

BGS JPL DSN

GDSCC DSS-24, 27CDSCC DSS-34, 45MDSCC DSS-54, 65

USN NMC

Network Communications

Page 20: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 20 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS

Spacecraft Constraints Impacting ARTEMIS Operations

Constraint Operational Impact / Risks Work-around / Mitigation

Thruster locations on spacecraft

Thrust direction only in one hemisphere Insert bias maneuvers into navigation plan

No thrust operations in shadow due to RCS design

Cannot execute maneuvers in Earth or lunar shadows

Shift maneuvers outside of shadows

Survival of long shadows Spacecraft designed for maximum shadow duration of 180 min. Power systems performance allows shadows up to 240 min duration.

Design trajectory to avoid shadows longer than 240 min

EIRP of spacecraft transmitter with omni antenna

Spacecraft telecomm subsystem designed to work with 11-m class ground stations

Utilize DSN 34-m antennas and adjust telemetry rates to close link with positive margin, based on range and spacecraft attitude

Available sensor data for attitude determination

ACS and ADS designed to work with sun sensor and FGM data, requiring Earth’s magnetic field

Implement ADS based only on sun sensor data

Spacecraft Constraints

Page 21: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 21 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS

Thruster Firing Modes

Maneuver Type

Thrusters InvolvedDepiction of

Operational ModePurpose of Maneuver

Axial Thrust A1 and A2 continuous firing

Perigee or apogee change or combined in-plane and out-of-plane orbit change with stowed EFI booms

Side Thrust T1 and T2pulsed firing

Perigee or apogee changewith deployed EFI booms

Beta Thrust A1 and A2 continuous firing alternating withT1 and T2 pulsed firing

In-plane and out-of-plane orbit change with deployed EFI booms

Attitude Precession

A1 or A2 pulsed firing Attitude change

Spin-up / Spin-down

T1 or T2 continuous or pulsed firing

Spin rate adjustment

Thruster Firing Modes

Page 22: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 22 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Roles and Responsibilities

• ARTEMIS Navigation Team• Mission Design & Baseline Trajectories

• JPL/GNC

• Trajectory Verification & Validation• GSFC/FDAB

• Navigation Plans & Error Analysis• GSFC/FDAB

• Maneuver Targeting & Operations• GSFC/FDAB & UCB/SSL

• Orbit Determination & Error Analysis• GSFC/FDF & UCB/SSL

• Attitude Determination• UBC/SSL with software provided by GSFC/FDAB and a.i. solutions

Page 23: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 23 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMISTop Level Schedule

Page 24: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 24 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P1 Impulsive ORM Sequence

ORM 1

ORM 8

THEMIS D2

Page 25: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 25 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS P1 Lunar Approaches

Page 26: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 26 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS

Thruster CMD SheetsAcquisition Data

Planning Products

Ephemeris Products

Orbit Determination Predictive Ephemeris

GSFC/FDF

Maneuver Verification

UCB

Finite Trajectory Design

JPL/NAV

Initial Trajectory

Trajectory Verification and

Correction

GSFC/FDAB

Validated Trajectory

Maneuver Planning

GSFC/FDAB

GMAN/GMAT Config

Telemetry Data

Maneuver Reconstruction

UCB

Post Execution State

Orbit Determination Definitive Ephemeris

GSFC/FDF

Maneuver Calibration

GSFC/FDAB & UCB

Ephemeris Products

Maneuver Operations

UCB

Navigation Work Flow

Page 27: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 27 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Summary

• Near Term Plans• Complete second tail season by April 2009• Outer probes maneuvered close to neutral sheet• Finalize ARTEMIS mission design

• Mid Term Plans• Complete second dayside season by July 2009• Start orbit raise maneuver sequence for P1 & P2

• Long Term Plans• Execute translunar trajectory phase for ARTEMIS

(P1 & P2)• Operate THEMIS (P3, P4, P5) in closer formation

Page 28: Constellation Status, Plans for Future Manfred Bester University of California - Berkeley

Post-Fall AGU SWT Meeting 28 UCB/SSL – Dec. 20, 2008

THEMIS

ARTEMIS Going Back to the Moon

Launch:July 16, 1969

40 Years Later …

Landing:July 20, 1969