Generation of electricity from dye industry wastewater in ...
Consolidated Report on the Audit Findings of the Electricity Generation Industry ... ·...
Transcript of Consolidated Report on the Audit Findings of the Electricity Generation Industry ... ·...
I
Consolidated Report on the Audit Findings of the
Electricity Generation Industry Compliance
Audits Conducted in 2014
Audit year: 2014
I
All enquiries and correspondence to be directed to the Head of Department unless
indicated otherwise by means of a formal letter signed by the Head of Department:
Electricity Licensing, Compliance and Dispute Resolution.
Tel : +27 (0)12 401 4794
National Energy Regulator
Kulawula House
526 Madiba Street
Arcadia, Pretoria
0083
PO Box 40343
Arcadia
0007
Tel : +27 (0)12 401 4600
Fax : +27 (0)12 401 4700
Website : www.nersa.org.za
II
TTAABBLLEE OOFF CCOONNTTEENNTTSS
ABBREVIATIONS ......................................................................................................................................... III
DEFINITIONS ............................................................................................................................................. IV
EXECUTIVE SUMMARY .............................................................................................................................. VI
1. INTRODUCTION .............................................................................................................................. 1
2. AUDIT OBJECTIVES .......................................................................................................................... 1
3. AUDIT PROCESS .............................................................................................................................. 2
4. AUDIT METHODOLOGY ................................................................................................................... 2
5. SCOPE OF WORK ............................................................................................................................. 3
6. CHALLENGES AND AREAS OF CONCERN .......................................................................................... 4
6.1. TSB KOMATI ............................................................................................................................................ 4 6.2. TSB MALELANE ........................................................................................................................................ 4 6.3. SAPPI NGODWANA .................................................................................................................................... 4 6.4. SAPPI SAICCOR ......................................................................................................................................... 4 6.5. SAPPI TUGELA ........................................................................................................................................... 4 6.6. MERINO POWER STATION .......................................................................................................................... 5 6.7. SOL PLAATJE POWER STATION ..................................................................................................................... 5 6.8. LYDENBURG HYDRO ................................................................................................................................... 5
7. FACTS AND FIGURES ....................................................................................................................... 5
8. SUMMARY OF OBSERVATIONS AND AUDIT FINDINGS .................................................................... 5
8.1. COMPLIANCE WITH THE ELECTRICITY GENERATION LICENCE ................................................................................ 6 8.2. COMPLIANCE WITH THE DISTRIBUTION INFORMATION EXCHANGE CODE .............................................................. 7 8.3. COMPLIANCE WITH THE DISTRIBUTION NETWORK CODE ................................................................................... 7 8.4. COMPLIANCE WITH THE TRANSMISSION NETWORK CODE .................................................................................. 8 8.5. COMPLIANCE WITH THE DISTRIBUTION SYSTEM OPERATING CODE ...................................................................... 9 8.6. GENERATION MAINTENANCE STRATEGY ........................................................................................................ 9 8.7. PLANT PERFORMANCE AND KEY PERFORMANCE INDICATORS (KPIS) ................................................................. 10 8.8. OUTAGE MANAGEMENT .......................................................................................................................... 10 8.9. ASSET MANAGEMENT .............................................................................................................................. 10 8.10. REFURBISHMENT AND EXPANSION PLANS ..................................................................................................... 11 8.11. PRIMARY ENERGY ................................................................................................................................... 11
9. PLANT INSPECTION ....................................................................................................................... 11
9.1. SCOPE OF PLANT INSPECTION .................................................................................................................... 11 9.2. ON-SITE OBSERVATIONS ........................................................................................................................... 12
10. CONCLUSION ................................................................................................................................ 15
III
AABBBBRREEVVIIAATTIIOONNSS
GCR Grid Code Requirement
GO General Overhaul
HV High Voltage
LTA Loss Time Availability
MTPPP Medium-Term Power Purchase Programme
MW Mega Watt
NERSA National Energy Regulator
OEM Original Equipment Manufacturer
OTE Overall Time Efficiency
PPA Power Purchase Agreement
SAGC South African Grid Code
SAP System Application and Production
UNIPEDE Union Internationale des Producteurs et Distributeurs dEnergie Electrique
IV
DDEEFFIINNIITTIIOONNSS
Embedded Generator (as defined in the South African Grid Code)
A legal entity that operates a unit, other than a co-generator, that is not connected to
the Transmission System.
Generator (as defined in the South African Grid Code)
A legal entity licensed to engage in the production of electricity through a unit or power
station.
Grid Code (as defined in the South African Grid Code)
The ‘South African Grid Code’, which consists of the following documents, as
approved by NERSA and updated from time to time by the Secretariat.
Preamble
Governance Code
Network Code
System Operation Code
Metering Code
Tariff Code
Information Exchange Code
Licensees (in this document)
TSB Sugar RSA (Pty) Ltd;
Sappi Southern Africa (Pty) Ltd;
Bethlehem Hydro (Pty) Ltd; and
Thaba Chweu Local Municipality.
Participant (as defined in the South African Grid Code)
A legal entity registered with or licensed by the NERSA in terms of the Electricity Act,
and as listed in the Governance Code. Participants are defined as the following
entities:
Generators with power stations where the total installed generating capacity is
greater than 50MVA or any unit where the installed generating capacity is greater
than 20 MVA, and who participates in the wholesale electricity market.
Generators with power stations connected to the transmission system.
Generators providing ancillary services for system operation purposes.
Distributors connected to the transmission system.
End-use customers connected to the transmission system, or their respective
distributor acting on their behalf.
A retailer or other wholesale market participant required to contract for the use of
the transmission system.
Transmission network service providers.
The System Operator.
Other participants in the ancillary services market; e.g. persons with interruptible
loads.
The Market Operator.
VI
EEXXEECCUUTTIIVVEE SSUUMMMMAARRYY
The Electricity Regulation Act, 2006 (Act No. 4 of 2006) (‘the Act’), stipulates that the
Regulator must enforce performance, compliance and take appropriate steps in the
case of non-performance.
Pursuant to Section 4(a)(vii) of the Act, all licensed entities are subject to an audit for
compliance with licence conditions imposed by the Energy Regulator. The audit
objectives are to assess compliance with applicable regulatory requirements, validate
evidence of self-reported non-compliances, document the licensees’ compliance level
and plans, and monitor the implementation of corrective action plans.
There are approximately 102 electricity generation licensees and the total number of
power stations includes 86 operational, 10 non-operational and 41 new builds (under
construction). The selection criteria for the representative sample of power stations
audited is based on:
the type of licensee e.g. municipal generators may be audited together so as to
establish common practices and challenges;
information submitted to NERSA through G-forms, production figures or any other
form;
the power contribution or impact of the power station on the national grid;
research or data collected through desktop monitoring or media; and
a mixture of age, type of technology and location.
The Nersa team conducted compliance audits for the licensees listed in Table 1
below.
Table 1: List of licensees audited and audit dates
Licensee
Power Station Name
Status of the
Power Station
Audit Date
TSB Sugar RSA
(Pty) Ltd
TSB Komati Operational 28 July 2014
TSB Malelane Operational 29 July 2014
Thaba Chweu
Local Municipality
Lydenburg Hydro
Power Station
Operational 30 July 2014
Sappi Southern
Africa (Pty) Ltd
Sappi Ngodwana Operational 31 July to 01 August
2014
Sappi Saiccor Operational 11 August 2014
Sappi Tugela Non-operational 13 August 2014
Bethlehem Hydro
(Pty) Ltd
Merino Power Station Operational 03 to 04 November
2014
Sol Plaatje Power
Station
Operational 03 to 04 November
2014
The twofold audit included a compliance assessment and plant inspection. The
audited licensees are in compliance with most of their licence conditions. Table 2a and
2b below represents a snap-shot of the compliance status of the licensees.
VII
Table 2a: A snap-shot of compliances
Compliance requirement Licensees’ compliance status
Compliance with the electricity
generation licence – validity of the
electricity generation licence
All licensees have valid electricity generation
licences.
Compliance with the electricity
generation licence – submission of
production figures
All licensees comply with the licence condition and
submit production figures for the Power Plants in a
manner prescribed by NERSA.
Compliance with the Distribution
Network Code
All licensees comply with the minimum protection
requirements of the code.
Table 2b: A snap-shot of non-compliances
Compliance requirement Licensees’ compliance status
Compliance with the electricity
generation licence – maintain
separate accounts for generation
business and submit audited
financials.
Three of the audited licensees do not maintain
separate accounts for the generation business and
do not submit the Power Plant(s) audited financials
to NERSA.
Compliance with the Distribution
Information Exchange Code – Data
storage and archiving
Though all licensees have data storage facilities
on-site, store data in hard copies and soft copies
and the storage period is longer than five years;
three of the licensees do not have a data and
archiving procedure in place, data storage and
archiving is only done as an inherent custom.
Compliance with the Transmission
Network Code – Testing and
compliance
The Power Plants do not keep records of
compliance with the requirements of the Network
Code for each of the generation units.
1
11.. IINNTTRROODDUUCCTTIIOONN
The National Energy Regulator (NERSA) derives its mandate to conduct compliance
audits for licensed electricity Generators from the Electricity Regulation Act, 2006 (Act
No. 4 of 2006) ('the Act'). The Act empowers the National Energy Regulator as the
custodian and enforcer of the regulatory requirements.
The Regulator is empowered to execute functions such as to enforce performance and
compliance, and take appropriate steps in the case of non-performance.
There are approximately 102 electricity generation licensees and the total number of
power stations includes 86 operational, 10 non-operational and 41 new builds (under
construction). The selection criteria for the representative sample of power stations
audited is based on:
the type of licensee e.g. municipal generators may be audited together so as to
establish common practices and challenges;
information submitted to NERSA through G-forms, production figures or any other
form;
the power contribution or impact of the power station on the national grid;
research or data collected through desktop monitoring or media; and
a mixture of age, type of technology and location.
In 2014, the NERSA team conducted audits for the electricity generation industry,
specifically the Embedded Generators operated by private entities and one operated
by a municipality. The following licensees (‘the Licensees’) were selected for the audit:
Table 3: audited licensees
Licensee Power Station
TSB Sugar RSA (Pty) Ltd TSB Komati
TSB Malelane
Sappi Southern Africa (Pty) Ltd Sappi Ngodwana
Sappi Saiccor
Sappi Tugela
Bethlehem Hydro (Pty) Ltd Merino Power Station
Sol Plaatje Power Station
Thaba Chweu Local Municipality Lydenburg Hydro
22.. AAUUDDIITT OOBBJJEECCTTIIVVEESS
All licensed entities are subject to an audit for compliance with licence conditions as
imposed by the Energy Regulator. The audit objectives are to:
assess compliance with the requirements of the Electricity Generation Licence
conditions and the applicable South African Grid Code;
validate evidence of self-reported non-compliances;
document the Licensees’ compliance level and plans; and
monitor and enforce the implementation of corrective action plans.
2
33.. AAUUDDIITT PPRROOCCEESSSS
The audit team conducts audits which serve as information gathering processes and
analyses the information together with the evidence that is submitted by the
Licensees. Subsequently, an audit report that details the record of observations,
findings and recommendations is compiled for each Licensee according to the number
of its power stations. The report(s) is/are sent to the Licensees for comments. On
receipt of the comments, a consolidated audit report is prepared for approval by the
Energy Regulator and thereafter, the Licensees are required to develop corrective
action plans to address the findings of the audit. The National Energy Regulator will
then monitor and enforce the implementation of the corrective action plans to assist
the Licensees to comply.
The various stages of the audit process involve the following activities depicted in
Table 4 below:
Table 4: The various stages of the audit process
Stage 1: pre-site visit
activities
Establish an audit team.
Establish communication with the Licensees to be audited.
Prepare audit questionnaire.
Compile audit program, agenda, and presentation.
Prepare audit packages.
Travel logistics.
Stage 2: on-site visit
activities
Make presentations to inform the Licensees about the aim of
the audit and the audit process.
Conduct compliance audits on the Licensees and take notes.
Plant Inspection.
Stage 3: post-site
visit activities
Consolidate Licensees’ responses.
Compile individual audit reports.
Send individual audit reports to the audited Licensees for
comments.
Compile consolidated audit report.
Prepare submissions to the Energy Regulator.
Request Licensees to submit corrective action plans.
Monitor the implementation of the corrective action plans.
44.. AAUUDDIITT MMEETTHHOODDOOLLOOGGYY
A detailed audit questionnaire was the main document used to facilitate the audit and
to determine the level of the Licensees' compliance. It was sent to the Licensees
before the day of the audit for preparation. The following documents formed the basis
for the audit questionnaire:
the Electricity Regulation Act, 2006 (Act No. 4 of 2006);
the Generation Compliance Monitoring Framework;
the Electricity Generation Licences issued to the Licensees; and
3
the South African Grid Code (Version 8.0 of July 2010), including the Distribution
Code (version 5.1 of September 2007).
The questionnaire is divided into eleven sections; the five compliance requirement
sections relate to:
the Electricity Generation Licence conditions;
the South African Grid Code – Distribution Information Exchange Code;
the South African Grid Code – Distribution Network Code;
the South African Grid Code – Transmission Network Code; and
the South African Grid Code – Distribution System Operating Code.
The other six sections of the questionnaire are aimed at establishing whether the
Licensees align themselves with industry standard and best practice with regard to the
safe and sustainable operation of the licensed facilities. The sections are as follows:
Generation Maintenance Strategy;
Plant Performance;
Outage Management;
Asset Management;
Refurbishments and Expansion Plans; and
Primary Energy.
55.. SSCCOOPPEE OOFF WWOORRKK
The scope of work involved the activities detailed in Section 3 Audit Process, of this
report. Table 5 below indicates the power stations that were audited:
Table 5: The Power Stations audited
Licensee Power Station Technology Installed
Capacity
Operational
Capacity
TSB Sugar RSA
(Pty) Ltd
TSB Komati Steam turbine:
coal and bagasse
20.00MW 20.00MW
TSB Malelane Steam turbine:
bagasse
32.80MW 32.80MW
Sappi Southern
Africa (Pty) Ltd
Sappi Ngodwana Steam turbine:
spent pulping
liquor and coal
117.60MW 117.60MW
Sappi Saiccor Steam turbine:
spent pulping
liquor and coal
46.00MW 46.00MW
Sappi Tugela Steam turbine:
spent pulping
liquor and coal
20.00MW -
Bethlehem Hydro
(Pty) Ltd
Merino Power Station Hydro 4.00MW 4.00MW
Sol Plaatje Power
Station
Hydro 3.00MW 3.00MW
Thaba Chweu
Local Municipality
Lydenburg Hydro
Power Station
Hydro 3.35MW 3.35MW
4
Licensee Power Station Technology Installed
Capacity
Operational
Capacity
Total capacity 246.75MW 226.75MW
66.. CCHHAALLLLEENNGGEESS AANNDD AARREEAASS OOFF CCOONNCCEERRNN
All Licensees are experiencing challenges; some are common to a number of them
whereas others are unique to a particular licensee or generation station. For example,
the inability to secure long-term coal contracts with suppliers is common among the
plants which use coal, whereas the hydro plants are faced with the issue of scarcity of
water during some seasons of the year or the water pressure drop in some instances.
The subsections below discuss the challenges experienced by each station.
6.1. TSB KOMATI
The Komati Power Plant uses coal and bagasse (a by-product of sugar cane) as its
primary energy. Supply of bagasse is predictable and it is readily available since it is
an in-house by-product. However, the supply of coal is a challenge as the generator
competes for coal with other coal consuming industries and the export market. Most
coal suppliers only offer short-term coal supply contracts, such as one year contracts.
6.2. TSB MALELANE
The Power Plant’s primary energy is 95% bagasse and only 5% coal is used mostly
when the plant is started up. The supply and reserves for bagasse is predictable since
it is supplied within TSB. Similar to TSB Komati, the supply of coal is a challenge as
the generator competes for coal with other coal consuming industries and the export
market. Most coal suppliers only offer short-term coal supply contracts, such as one
year contracts.
6.3. SAPPI NGODWANA
The Power Plant battles to secure long-term coal contracts as it cites competition from
coal consuming industries and the export market as the reason for failure to obtain a
long-term contract.
6.4. SAPPI SAICCOR
There are no challenges identified or reported.
6.5. SAPPI TUGELA
The Power Plant faces the following challenges:
it is 60 years old, therefore most of its components have become obsolete;
5
its cost of generation exceeds the tariff for buying power from the grid, as a result,
the two steam turbine generators were mothballed in 2013 as it became too
expensive to keep them operational;
prior to mothball, the plant used Grade A coal as primary fuel, which is very
expensive; and
it battled to secure long-term coal supply agreements, as most suppliers only offer
one to three-year contracts.
6.6. MERINO POWER STATION
The amount of power generated from Merino depends on the rate of water flow and
the head or pressure of the water. Water is supplied from Lesotho Highlands Water
Scheme; its flow rate and pressure varies from time to time on different seasons.
6.7. SOL PLAATJE POWER STATION
The amount of power generated from Sol Plaatje depends on the amount and
pressure of the water, which varies from time to time.
6.8. LYDENBURG HYDRO
The Power Plant faces the following challenges:
Thaba Chweu Local Municipality, the plant owner, has been financially struggling
to keep Lydenburg Hydro in operation and its account with the operator of the
plant is in arears.
the Municipality does not have reserve funds for plant maintenance.
77.. FFAACCTTSS AANNDD FFIIGGUURREESS
All Power Plants, except for Lydenburg Hydro, are contracted to supply power (in
excess of own consumption) to the national grid at Wholesale Electricity Pricing
System (WEPS) tariff and Short-Term Power Purchase Programme (STPPP) tariff,
except for Lydenburg Hydro, which supplies Thaba Chweu Local Municipality
customers at Municipality rates.
The total contribution from the audited embedded generators was 158 583MWh and
272 195MWh in 2013 and 2014. The total capacity is 226MW, which makes up a
contribution of 0.4% to national capacity.
88.. SSUUMMMMAARRYY OOFF OOBBSSEERRVVAATTIIOONNSS AANNDD AAUUDDIITT FFIINNDDIINNGGSS
Observations and findings related to compliance with the South African Grid Code, the
licence conditions and best engineering practices were identified and brought to the
attention of the Licensees. Where applicable, possible options for corrective actions
were discussed with the Licensees during the audit process. Furthermore, the
6
individual audit reports present recommendations to address the audit findings or non-
compliances. Each sub-heading below briefly discusses the findings and status of
compliance of the Licensees.
In each compliance requirement section, the total compliance rating equates to 100%,
and the compliance rating is apportioned equally according to the number of
compliance items within the section.
8.1. COMPLIANCE WITH THE ELECTRICITY GENERATION LICENCE
Table 5 below contains a summary of electricity generation compliance requirements
and the Licensees’ compliance status.
Table 5: Licensees’ compliance status with electricity generation licence
Licence condition requirement Compliance
rating (%)
Compliance Status
Compliant Non-
Compliant
Maintain separate accounts and
submit audited financials for the
Power Plant.
16.7
A
B, C, D
Submit production figures in a
manner prescribed by NERSA.
16.7
A, B, C, D
Validity of the electricity generation
licence.
16.7
A, B, C, D
Changes of details of Licensee.
16.7
A, B, C, D
Changes in operational status of the
Power Plant.
16.7
A, C
B, D
Validity of PPA and contracted
capacity in line with Schedule 1 and
2
16.7
A, B, C
D
Total compliance rating
100% (16.7 x 6)
Key to Table 5
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality
The Licensees submit production figures on a quarterly basis as prescribed by
NERSA. However, most Power Plants’ finances are not ring-fenced as they are
consolidated together with the finances of other operations of the Licensees.
7
8.2. COMPLIANCE WITH THE DISTRIBUTION INFORMATION EXCHANGE CODE
Table 6 below contains a summary of Distribution Information Exchange Code
compliance requirements and the Licensees’ compliance status.
Table 6: Licensees’ compliance status with the Distribution Information Exchange Code
Distribution Information Exchange
Code requirements
Compliance
rating (%)
Compliance Status
Compliant Non-
Compliant
Procedures to address the requirements of
the Distribution Information Exchange
Code e.g. appointment of designated
person to facilitate communication with the
Distributor or Network operator, method of
communication.
25
A, B, C, D
Operational data storage procedure to
address the provision of a storage facility,
access control and data retention period.
25
B
A, C, D
Submission of information to the
Distributor regarding new or altered
equipment at point of connection.
25
B, C, D
A
Commissioning and notification procedure
in place.
25
A, C
B, D
Total compliance rating
100% (25 x 4)
Key to Table 5
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality
All Licensees do not have a formal procedure related to data storage and archiving of
operational information, as well as the exchange of information of newly installed
equipment. However, all have established appropriate data storage facilities with
access control features and have been retaining data for more than five years. The
Power Plants established liaison meetings with the Distributor where any changes,
alterations or installation and commissioning of new equipment, as well as
commissioning dates are discussed.
8.3. COMPLIANCE WITH THE DISTRIBUTION NETWORK CODE
The code requires a Power Plant and the network operator to conclude a connection
and supply agreement, whereby the parties agree on the connection conditions and
responsibilities of each party in terms of maintenance and operation of equipment at
the point of connection. The network operator stipulates the protection equipment
requirements for the generators prior to connection to the network. Table 7 below
depicts the compliance status of the Licensees.
8
Table 7: Licensees’ compliance status with the Distribution Network Code
Distribution Network Code
requirements
Compliance rating
(%)
Compliance Status
Compliant Non-
Compliant
Maintenance agreement for
equipment at point of connection.
25
A, B, C, D
Connection and supply agreement
in place.
25
A, B, C, D
Capability to remotely report any
status change of any critical
function that may negatively impact
on the quality of supply on the
Distribution system (telemetry).
25
A, B, C, D
Does the Power Plant dispatch or
synchronise its generators using
appropriate equipment and in line
with the code requirements.
25
A, B, C, D
Total compliance rating
100% (25 x 4)
Key to Table 5
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality
8.4. COMPLIANCE WITH THE TRANSMISSION NETWORK CODE
The code defines minimum requirements for the generating units of the participants
that are connected to the Transmission System and other generators defined in the
Governance Code, Section 4, which are required to comply with the Grid Code.
Compliance with a Grid Code Requirement (GCR) shall be applicable to a unit/power
station depending on rated capacity as specified in tables 1(a) and (b) of the
Transmission Network Code. See the Table 8 below for the Licensees’ compliance
status.
Table 8: Licensees’ compliance status with the Transmission Network Code
Compliance rating
(%)
Compliant Non-compliant
GCR1 (Unit protection system) 14.3 A, B,C, D
GCR3 (Excitation system) 14.3 A, B,C, D
GCR6 (Governing system) 14.3 A, B,C, D
GCR9 (External supply withstand
capability)
14.3 A, B,C, D
Testing and Compliance 14.3 A, B,C, D
Unit Modifications 14.3 A, B,C, D
Monitoring of unit performance 14.3 A, D B,C
9
Compliance rating
(%)
Compliant Non-compliant
Total compliance rating
100% (14.3 x 7)
Key to Table 5
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality
All Licensees comply with all the requirements of the Transmission Network Code.
However, the monitoring of the units to confirm ongoing compliance with the
applicable parts of the code is not performed, nor do the stations communicate
compliance information to the Network Operator.
8.5. COMPLIANCE WITH THE DISTRIBUTION SYSTEM OPERATING CODE
The code sets out the responsibilities and roles of the participants as far as the
operation of the Distribution System is concerned and more specifically, issues such
as economic operation, reliability and security of the Distribution System, operation
under normal and abnormal conditions, maintenance coordination/outage planning
and safety of personnel.
Table 9 below contains a summary of Distribution System Operating Code compliance
requirements and the Licensees’ compliance status.
Table 9: Licensees’ compliance status with the Distribution System Operating Code
Distribution Network Code
requirements
Compliance
rating (%)
Compliance Status
Compliant Non-
Compliant
Procedure for responsibilities of
generator during emergency
generation condition.
33.3 A, B, C, D
Procedure for outage scheduling and
safety co-ordination.
33.3 A, B, C, D
Procedure for fault reporting and
analysis/Incident Investigations.
33.3 A, B, D C
Total compliance rating
100% (33.3 x 3)
Key to Table 5
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality
8.6. GENERATION MAINTENANCE STRATEGY
The basis for plant maintenance scheduling is Original Equipment Manufacturer
(OEM) recommendations for all Licensees. Some of the Licensees use the System
Application and Production (SAP) maintenance planning system to schedule and keep
records of proactive, preventive and reactive maintenance, whereas others do not
have a maintenance planning system but use Microsoft Office Software. This is in line
10
with international best practice aimed at ensuring that maintenance of equipment is
carried out timeously and in an orderly manner, deriving optimal performance and
preserving the life of equipment.
There is sufficient time to schedule proactive and preventative maintenance as some
of the Power Plants are not operational for the rest of the year. For example,
maintenance for the Power Plants at sugar mills is scheduled to coincide with the mill’s
off crop season.
8.7. PLANT PERFORMANCE AND KEY PERFORMANCE INDICATORS (KPIS)
The Power Plants do not set technical performance targets that are aligned with the
international industry standards such as the Union Internationale des Producteurs et
Distributeurs dEnergie Electrique (UNIPEDE), due to their operating regime and
dispatch philosophy. The plants generate whatever they are capable of generating in
excess of their own consumption. However, the Licensees track the availability of the
Power Plants in terms of generated power as opposed to available power.
TSB Malelane calculates the percentage Loss Time Availability (LTA), that is, the time
that the Power Plant is not generating; and the Overall Time Efficiency (OTE) which
takes into account the planned production time and scrutinizes efficiency and
productivity losses that occur, with the goal of reducing or eliminating these losses.
The production target for selling to the grid is 50MWh per day.
8.8. OUTAGE MANAGEMENT
The Power Plants that are co-generators schedule major outages to coincide with
those of the process plant. For example, a major General Overhaul (GO) for the
Power Plant is scheduled when it is the process plant shutdown period for
maintenance. Every fourth year, a sugar mill and its steam generation equipment is
due for major GO. This is a requirement from the OEM and it is also a statutory
requirement. Minor GOs are scheduled during low demand periods, December to
March.
To mitigate outage risks such as outage slip, the Licensees ensure that a detailed
outage plan is completed months ahead of the start of an outage to ensure that all
resources are identified and made available, whereas, the implementation of bi-weekly
meetings held during the outage period assist in identifying any emerging risks.
One of the tools used by the Licensees to assess the success of the outage work is to
conduct performance tests prior shut-down and after shut-down, and then compare
the test results.
8.9. ASSET MANAGEMENT
The plant equipment in most Power Plants is partially labelled so as to identify the
equipment on the asset register. Some use the SAP system to manage plant assets.
11
The Power Plants use a functional location system to identify equipment and a coding
system for identification of components. Some of the portable plant equipment such as
small motors are regarded as routable spares, and they are coded so that it is possible
to use the code to track the equipment and its maintenance records.
8.10. REFURBISHMENT AND EXPANSION PLANS
The remaining life of equipment, refurbishments and replacements are estimated on
the basis of condition-based monitoring test results, equipment performance and OEM
recommendations.
The Power Plants do not have any future expansion plans, but consider
refurbishments and replacements of some of the plant items to maintain plant
performance.
8.11. PRIMARY ENERGY
Fuel is the major operational expense of the cost of generation for the Power Plants
that use coal. Even though coal is supplemented by the by-product from the process
plant, it makes up a bigger portion of the primary energy fuel. The inability to secure
long-term coal contracts and competition with the export market contributes to the
increasing price of coal.
The coal-fired Power Plants keep some coal stockpile on site, depending on the
capacity of the coal handling facility. The coal handling facilities of the audited Power
Plants can hold up to 30 days of stockpile. However, the coal handling facilities do not
always have stockpile because the coal that is delivered on-site is not always
sufficient.
99.. PPLLAANNTT IINNSSPPEECCTTIIOONN
9.1. SCOPE OF PLANT INSPECTION
The main objective of the plant inspection is to assess the condition of the plant as
well as its safety and environmental aspects.
The plant inspection covered the following aspects:
safety of equipment, for example moving equipment safeguarded;
display of safety signs and emergency evacuation routes;
environmental issues, for example water, steam or oil leaks;
housekeeping e.g. cleanliness; and
plant labelling.
The following areas were inspected, some applicable to the coal-fired plants and
others to the hydro plants:
boiler, mills and associated plant equipment;
12
steam turbine, generator and associated plant equipment;
generator transformers and unit transformers;
switch gear;
upper and lower dam monitoring;
coal handling plant;
ash plant;
fire protection system;
station control room; and
critical spares storage.
9.2. ON-SITE OBSERVATIONS
The Merino and Sol Plaatje Power Plants were recently constructed and
commissioned in 2011 and 2009 respectively. All the equipment is fairly new and its
life span is estimated at 25 years. The plants are in good condition and can operate at
full capacity. A facility for remote reporting, in case of abnormal operation such as
generator trip is installed on both plants. Firefighting and fire protection equipment is
installed in the whole plant and the extinguishers that were inspected were serviced.
Figure 1 below indicates one of the fire extinguishers installed in the control room. The
silica gel glass container on one of the generator step-up transformers needs to be
changed or cleaned as it makes it difficult to see the colour of the silica gel, see Figure
2 below. Equipment labelling is not implemented throughout the plant and in some
areas, emergency evacuation routes are not clearly marked.
Figure 1: Merino control room firefighting equipment Figure 2: Merino generator step-up
transformer
TSB Komati’s generators were installed in 1994 and 1998, whereas Malelane’s
generators were installed in the 1980’s. The steam turbines and generators are in
good physical condition; there are no obvious signs of deterioration and they are
capable of generating up to the full capacity of 32.8MW and 20MW. The Malelane
generator step-up transformers are in good physical condition; there are no oil leaks,
the silica gel is in good condition and the oil is at acceptable levels. However, the
Malelane generator step-up transformers are not labelled with an equipment identifier
code or functional location code, see Figure 3 below.
13
Figure 3: Malelane generator step-up transformer Figure 4: Malelane ash plant conveyor belt
The ash plant conveyor belt at Malelane is well guarded as it is covered so that there
is no unwitting physical contact with the moving belt, see Figure 4 above.
Fire protection is implemented at both plants. There is firefighting equipment
throughout most of the power plant. A high pressure water pipeline is installed in most
parts of the plant and it is activated by fire detectors which are installed along the
conveyor belts and other parts of the plant, see Figure 5 below.
Figure 5: TSB Komati bagasse conveyor belt Figure 6: Diffuser discharge magnet
Plant labelling at TSB Komati is partially implemented, as the generator step-up
transformer is not labelled. See Figure 6 above for an example of functional location
plant labelling on the conveyor belt.
The units at Sappi Ngodwana Power Plant were installed in 1985 and 1988
respectively. They have been in operation for at least 28 years. The performance of
the plant is acceptable and within original parameters. Availability of steam is the only
limitation to delivering full capacity from the generators. Plant equipment labelling is
visible and clearly marked. Moving equipment, such as conveyor belts, is well
guarded. However, there are no visible safety and emergency evacuation signs. There
are very minor steam and oil leaks in some parts of the plant. By visual inspection, the
plant is in good condition. Figures 7 and 8 below indicate Sappi Ngodwana’s generator
step up transformer and turbine generator.
14
Figure 7: Sappi Ngodwana Generator Step-up Figure 8: Sappi Ngodwana Turbine Generator 2
Transformer 2 nameplate with plant labelling
At Sappi Saiccor Power Plant, equipment labelling is visible and clearly marked.
Moving equipment, such as conveyor belts, is well guarded. Similar to Ngodwana,
there are no visible safety and emergency evacuation signs. There are very minor
steam and oil leaks in some parts of the plant. By visual inspection, the plant is in
good condition.
The Sappi Tugela turbine generators were installed in 1954 and 1959, which means
the oldest turbine generator remained operational for 61 years until it was
decommissioned in the year 2012 whereas the younger one was decommissioned in
2013, after 56 operational years. It has many steam and water leaks in the piping
leading to the boiler. The steam turbine generator set has signs of deterioration.
Figure 9: Tugela steam turbine and generator set Figure 10: Tugela step down transformer with oil
leaks at the bottom of the main tank
Lydenburg Hydro’s first unit was commissioned in 1932 and the last unit was
commissioned in 1983. It is able to generate only up to 2.1MW from its 2.6MW
generator that was commissioned in 1983. The other turbine-generators are in need of
major maintenance and repairs. Equipment labelling is not implemented throughout
the plant and emergency evacuation routes are not clearly marked. Figure 11 and 12
below represents the Lydenburg hydro switchgear and generator with no visible plant
labelling.
15
Figure 11: Lydenburg Hydro switchgear Figure 12: Lydenburg generator
1100.. CCOONNCCLLUUSSIIOONN
Detailed findings and recommendations of the audit for each Licensee are presented
in the individual audit reports of the Licensees. From the audit findings, it is evident
that the Licensees have systems in place to implement the requirements of the licence
conditions, however, most do not have systems in place or programme of compliance
with the South African Grid Code. The licensees align their power plant operations
with international standards and codes; therefore, comply with the South African Grid
Code mainly because the code is also aligned with the international standards such as
those published by the National Grid Company of the United Kingdom.
Figure 13 represents the compliance status of the Licensees with the five compliance
requirement items, namely:
(a) Compliance with the Electricity Generation Licence – Table 5;
(b) Compliance with the Distribution Information Exchange Code – Table 6;
(c) Compliance with the Distribution Network Code – Table 7;
(d) Compliance with the Transmission Network Code – Table 8 and
(e) Compliance with the Distribution System Operating Code – Table 9.
From Tables 5 to 9, the Licensee names are denoted as follows:
A: Bethlehem Hydro (Pty) Ltd;
B: Sappi Southern Africa (Pty) Ltd;
C: TSB Sugar RSA (Pty) Ltd; and
D: Thaba Chweu Local Municipality.
In interpreting the graph of Figure 13, the following example is made:
In Table 5, Bethlehem Hydro (Pty) Ltd is compliant with all of its Electricity Generation
Licence compliance requirements, hence, on the graph of Figure 13 its compliance
status is 100% (16.7 x 5) whereas Sappi Southern Africa (Pty) Ltd is compliant with
four of its Electricity Generation Licence compliance requirements and therefore its
compliance status is 67% (16.7 x 4). The aforementioned interpretation method is
applicable to the rest of the Licensees compliance status on the graph.
16
Electricity
Generation
Licence
Distribution
Information
Exchange Code
Distribution
NetworkCode
Transmission
NetworkCode
Distribution
SystemOperating Code
A: Bethlehem Hydro (Pty) Ltd 100 50 100 100 100
B: Sappi Southern Africa (Pty) Ltd 67 65 100 86 100
C: TSB Sugar RSA (Pty) Ltd 84 75 100 86 67
D: Thaba Chweu Local Municipality 50 50 100 100 100
0
20
40
60
80
100
120
% C
om
plia
nce
Sta
tus
Figure 13: Licensee compliance status
A: Bethlehem Hydro (Pty) Ltd
B: Sappi Southern Africa (Pty) Ltd
C: TSB Sugar RSA (Pty) Ltd
D: Thaba Chweu Local Municipality