Connection to the Grid of AD Generation in the ROI
Eur Ing Carlos Galvan - Managing Director - Gridconnect
![Page 2: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/2.jpg)
Connecting your AD generation tothe ESB owned network?
1. The connection process, are you planning to export power?
2. Connection types depending on generator electrical output
3. Our services
![Page 3: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/3.jpg)
Connection process at present
Good news: you will be processed outside the GPA (Group processing approach AKA “gate system” CER/09/099)
Bad news: until the so-called “enduring access regime” is implemented, you will be processed in the same queue asThe 4,300+ megawatts of solar applications
![Page 4: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/4.jpg)
Do I need to submit a connection applicationto ESBN?
• YES, even if you are not exporting into the grid
• If no export no application fee required, no queuing
• If exporting power, the application fee will depend on the output (MEC).Starting at €772 for 11<kW<50
Example: 500<kW<4000 MEC application fee €8,947
• Slightly different for micro-generators (6kW – 11kW). No application fee
![Page 5: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/5.jpg)
Do I need a licence to generate?
If your output is less than 1MW you are not required to apply to theCER in order to receive an Authorisation to Construct/Licence toGenerate.
You are authorised by Order under Article 5 (1)(b) of S.I. No. 383 of2008/ licensed by Order under Article 5 (1)(b) of S.I. No. 384 of 2008
……happy days
![Page 6: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/6.jpg)
Connection types:
• Most projects will connect into existing rural network (10kV or 20kV)
• Existing rural network (distribution system) overhead lines (woodenpoles)
• There are many connection types depending on the output of yoursite depending on MEC, available nearby grid access, etc
• There could be a few variations depending on existing installation i.e.metering arrangement, etc.
![Page 7: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/7.jpg)
Option 1: <500kW
M
G
ESBAssets
HV Network(OHL/UC)
A.D Plant
Local loads
IPPAssets
ESB side costs:Approximately €13k* forexisting demand site andallowing €48k for greenfield site with good gridaccess
*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc
![Page 8: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/8.jpg)
Option 2: <500kW to be added to existingdemand installation
M
G
ESBAssets
HV Network(OHL/UC)
A.D Plant
Local loads
IPPAssets
ESB side costs:Changes to allowimport/export meteringincluding insertion of extraswitchgear on MV side(Nu-Lec or EGIP)
![Page 9: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/9.jpg)
Option 3: 500kW<MEC<2MW
M
ESBAssets
MV Network(OHL/UC)
G
Disconnect (KKK TYPE RMU)Nulec
Local loads
G10
MV
ESB side costs:Approximate total €45k*
IPPAssets
*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc
![Page 10: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/10.jpg)
Option 4: >2MW
M
IPPAssets
MV Network(OHL/UC)
EGIP
G
Local loads
MV
ESBAssets
ESB side costs:Approximate total: €203k*
*depends on existinginfrastructure, connectionmethod, capacity ofexisting lines, etc
![Page 11: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/11.jpg)
Our services:PRE-CONSTRUCTION SERVICES:
GRID CONNECTION FEASIBILITY STUDIES:-HOW MUCH FOR MY GRID?-WHEN? Timelines
Difficult to establish until enduring access regime is implemented
![Page 12: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/12.jpg)
• SITE SURVEY (A “MUST” FOR EXISTING SITES)
• PREPARATION OF HIGH LEVEL DESIGN AND SUBMISSION OF NC5 FORMSTO ESBN
• PREPARATION OF SCOPE OF WORKS, SPECIFICATIONS AND EMPLOYER’SREQUIREMENTS
“YOU CAN SAVE THOUSANDS OF €€€€€ WITH A CAREFUL ASSESSMENT OF EXISTING ELECTRICAL ASSETS”
![Page 13: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/13.jpg)
Our services:
CONSIDER THIS:1-Your electrical installation needs to comply with ETCI regulations, is your site safe and does it comply with regulations?2-Can I reduce my CAPEX/OPEX through an optimised electrical design?
Example:Your electrical losses can be minimised, this translates into thousands of euro over the lifetime of the project, example:Saving by electrical contractor reducing cable size (300mm² to 185mm² on a 50 m run) in 200kW outputinstallation:……………..approximately €250Value of added electrical losses over 25 year period with €0.10/kWh tariff:…………….€16,898 !!
ELECTRICAL ENGINEERING DESIGN:-Cable, transformer, protections and switchgear specification-Grid code compliance studies, earthing design, arc flash studies, etc.
![Page 14: Connection to the Grid of AD Generation in the ROI€¦ · Connection process at present Good news: you will be processed outside the GPA (Group processing approach AKA “gate system”](https://reader034.fdocuments.in/reader034/viewer/2022042213/5eb7fd7857bf3958102871a0/html5/thumbnails/14.jpg)
IN A NUTSHELL…….
• Feasibility study considering interactions, grid capacity, existinginstallation, etc.
• Site survey highly recommended
• NC5 form submission including high level design
• Review of connection offer once received (enduring access regimewill fix current mess…)
• Preparation of scope of works and detail design