Conditions of the Contract Review Questions

Transcript of Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make...

Page 1: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

Conditions of the Contract

Review Questions

Page 2: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

1. General Conditions and Supplementary Conditions make up the:

a. Specifications

b. Bidding Requirements

c. Conditions of the Contract

d. Special Conditions

Page 3: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

1. General Conditions and Supplementary Conditions make up the:

a. Specifications

b. Bidding Requirements

c. Conditions of the Contract

d. Special Conditions

Page 4: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

2. All of the following are true regarding the General Conditions EXCEPT:

a. Contains specific administrative and procedural requirements

b. Are broad contractual conditions

c. Contain the contracts

d. Normally remain constant from project to project

Page 5: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

2. All of the following are true regarding the General Conditions EXCEPT:

a. Contains specific administrative and procedural requirements

b. Are broad contractual conditions

c. Contain the contracts

d. Normally remain constant from project to project

Page 6: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

3. Which of the following is considered as part of the specifications?

a. General Conditionsb. Supplementary Conditionsc. Division 1d. Bidding Requirements

Page 7: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

3. Which of the following is considered as part of the specifications?

a. General Conditionsb. Supplementary Conditionsc. Division 1d. Bidding Requirements

Page 8: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

4. Supplementary Conditions:

a. Do not contain contractual/legal provisions

b. Modify General Conditions to suit specific project requirements

c. Are not part of the Conditions of the Contract

d. Include contractual/legal requirements provisions which supplement the General Provisions.

Page 9: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

4. Supplementary Conditions:

a. Do not contain contractual/legal provisions

b. Modify General Conditions to suit specific project requirements

c. Are not part of the Conditions of the Contract

d. Include contractual/legal requirements provisions which supplement the General Provisions.

Page 10: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

5. All of the following subjects are usually included in Supplementary Conditions EXCEPT:

a. Insurance requirements

b. Liquidated damages

c. Tax exempt status of Owner

d. Submittal requirements

Page 11: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

5. All of the following subjects are usually included in Supplementary Conditions EXCEPT:

a. Insurance requirements

b. Liquidated damages

c. Tax exempt status of Owner

d. Submittal requirements

Page 12: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

6. Published General Conditions prepared by professional societies should:

a. Be included by reference in Project Manual to save paper

b. Be copied in Project Manual

c. Have original bound into Project Manual

d. Be used on all projects

Page 13: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

6. Published General Conditions prepared by professional societies should:

a. Be included by reference in Project Manual to save paper

b. Be copied in Project Manual

c. Have original bound into Project Manual

d. Be used on all projects

Page 14: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

7. General and Supplementary Conditions must have the approval of which of the following?

a. Owner and Owner's counsel

b. Owner and Architect/Engineer

c. Owner, Architect/Engineer, and Contractor

Page 15: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

7. General and Supplementary Conditions must have the approval of which of the following?

a. Owner and Owner's counsel

b. Owner and Architect/Engineer

c. Owner, Architect/Engineer, and Contractor

Page 16: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

8. The General Conditions of the Contract for Construction apply to the contractual relationship between:

a. Owner and Architect/Engineer

b. Owner and Contractor

c. Owner and Subcontractor

d. Contractor and Subcontractor

Page 17: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

8. The General Conditions of the Contract for Construction apply to the contractual relationship between:

a. Owner and Architect/Engineer

b. Owner and Contractor

c. Owner and Subcontractor

d. Contractor and Subcontractor

Page 18: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

9. The Supplementary Conditions must be carefully coordinated with all of the following EXCEPT:

a. General Conditions

b. Bidding Requirements

c. Owner - Contractor Agreement

d. Owner - Architect Agreement

Page 19: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

9. The Supplementary Conditions must be carefully coordinated with all of the following EXCEPT:

a. General Conditions

b. Bidding Requirements

c. Owner - Contractor Agreement

d. Owner - Architect Agreement

Page 20: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.

Answers

1. c2. a3. c4. b5. d6. c7. a8. b9. d