Conditions of the Contract
Review Questions
![Page 2: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/2.jpg)
1. General Conditions and Supplementary Conditions make up the:
a. Specifications
b. Bidding Requirements
c. Conditions of the Contract
d. Special Conditions
![Page 3: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/3.jpg)
1. General Conditions and Supplementary Conditions make up the:
a. Specifications
b. Bidding Requirements
c. Conditions of the Contract
d. Special Conditions
![Page 4: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/4.jpg)
2. All of the following are true regarding the General Conditions EXCEPT:
a. Contains specific administrative and procedural requirements
b. Are broad contractual conditions
c. Contain the contracts
d. Normally remain constant from project to project
![Page 5: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/5.jpg)
2. All of the following are true regarding the General Conditions EXCEPT:
a. Contains specific administrative and procedural requirements
b. Are broad contractual conditions
c. Contain the contracts
d. Normally remain constant from project to project
![Page 6: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/6.jpg)
3. Which of the following is considered as part of the specifications?
a. General Conditionsb. Supplementary Conditionsc. Division 1d. Bidding Requirements
![Page 7: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/7.jpg)
3. Which of the following is considered as part of the specifications?
a. General Conditionsb. Supplementary Conditionsc. Division 1d. Bidding Requirements
![Page 8: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/8.jpg)
4. Supplementary Conditions:
a. Do not contain contractual/legal provisions
b. Modify General Conditions to suit specific project requirements
c. Are not part of the Conditions of the Contract
d. Include contractual/legal requirements provisions which supplement the General Provisions.
![Page 9: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/9.jpg)
4. Supplementary Conditions:
a. Do not contain contractual/legal provisions
b. Modify General Conditions to suit specific project requirements
c. Are not part of the Conditions of the Contract
d. Include contractual/legal requirements provisions which supplement the General Provisions.
![Page 10: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/10.jpg)
5. All of the following subjects are usually included in Supplementary Conditions EXCEPT:
a. Insurance requirements
b. Liquidated damages
c. Tax exempt status of Owner
d. Submittal requirements
![Page 11: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/11.jpg)
5. All of the following subjects are usually included in Supplementary Conditions EXCEPT:
a. Insurance requirements
b. Liquidated damages
c. Tax exempt status of Owner
d. Submittal requirements
![Page 12: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/12.jpg)
6. Published General Conditions prepared by professional societies should:
a. Be included by reference in Project Manual to save paper
b. Be copied in Project Manual
c. Have original bound into Project Manual
d. Be used on all projects
![Page 13: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/13.jpg)
6. Published General Conditions prepared by professional societies should:
a. Be included by reference in Project Manual to save paper
b. Be copied in Project Manual
c. Have original bound into Project Manual
d. Be used on all projects
![Page 14: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/14.jpg)
7. General and Supplementary Conditions must have the approval of which of the following?
a. Owner and Owner's counsel
b. Owner and Architect/Engineer
c. Owner, Architect/Engineer, and Contractor
![Page 15: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/15.jpg)
7. General and Supplementary Conditions must have the approval of which of the following?
a. Owner and Owner's counsel
b. Owner and Architect/Engineer
c. Owner, Architect/Engineer, and Contractor
![Page 16: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/16.jpg)
8. The General Conditions of the Contract for Construction apply to the contractual relationship between:
a. Owner and Architect/Engineer
b. Owner and Contractor
c. Owner and Subcontractor
d. Contractor and Subcontractor
![Page 17: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/17.jpg)
8. The General Conditions of the Contract for Construction apply to the contractual relationship between:
a. Owner and Architect/Engineer
b. Owner and Contractor
c. Owner and Subcontractor
d. Contractor and Subcontractor
![Page 18: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/18.jpg)
9. The Supplementary Conditions must be carefully coordinated with all of the following EXCEPT:
a. General Conditions
b. Bidding Requirements
c. Owner - Contractor Agreement
d. Owner - Architect Agreement
![Page 19: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/19.jpg)
9. The Supplementary Conditions must be carefully coordinated with all of the following EXCEPT:
a. General Conditions
b. Bidding Requirements
c. Owner - Contractor Agreement
d. Owner - Architect Agreement
![Page 20: Conditions of the Contract Review Questions. 1.General Conditions and Supplementary Conditions make up the: a.Specifications b.Bidding Requirements c.Conditions.](https://reader036.fdocuments.in/reader036/viewer/2022083004/56649da75503460f94a93727/html5/thumbnails/20.jpg)
Answers
1. c2. a3. c4. b5. d6. c7. a8. b9. d