B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Conditional Resales NAESB Assignment Update April 16th, 2014 Bob Zerfing, Rebecca Berdahl

description

Conditional Resales NAESB Assignment Update. April 16th , 2014 Bob Zerfing, Rebecca Berdahl. Response to the NAESB OS Request. The NAESB OS requested information to clarify the following issues: - PowerPoint PPT Presentation

Transcript of Conditional Resales NAESB Assignment Update

Page 1: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Conditional ResalesNAESB Assignment Update

April 16th, 2014Bob Zerfing, Rebecca Berdahl

Page 2: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Response to the NAESB OS Request

The NAESB OS requested information to clarify the following issues: For Option 1 – what are the complexities associated with

implementing C&P for Resales (e.g. make WEQ 013 consistent with WEQ 001) and describe if/why this option might be ‘unworkable’

For Option 2 – what is FERC’s general policy with regard to Resales and does their guidance provide NAESB an opportunity to modify the current C&P standards to align with this overall guidance

Is there merit in completing the Reservation Merge Project R09015 as part of the STCP project

Page 3: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Option 1 Components Option 1- treat Resales as Scheduling Rights only

• ROFR remains on the conditional parent• Resales lose scheduling rights if the parent loses

capacity• Implementation Guide (WEQ-013) mirrors the

Business Practices (WEQ-001)– Current WEQ-013 is not aligned with WEQ-001– Realigning WEQ-013 requires significant redesign and

industry-wide implementation changes.– This realignment effort must be taken on by the

NAESB OS.– The timeframe for this has not yet been identified.

Page 4: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

4

Option 1 Complexities1. Current Implementation Guides and Templates (WEQ-013)

do not support C&P of Conditional Resales (WEQ-001).• Resales are Scheduling Rights Only• ROFR (and thus encumbering capacity) remains with the parent

of the Resale• Resales are permissible from conditional parents• The Resale inherits the conditionality of the parent• Resales can be resold or redirected• Resales are a temporary tool for consolidation of reservations for

ease of scheduling• If the conditional parent loses capacity to a P&C, then the TP has

the right to annul any Resales associated with that lost capacity to guard against over scheduling.

Page 5: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

5

Option 1 Complexities (cont’d)2. Industry-wide commercial systems are built upon the WEQ-

013 implementation guide where the capacity moves from the original reservation to the resale. These systems are foundational for the commercial viability of the market. The impact of changing these foundational systems to accommodate the Preemption and Competition of conditional reservation is significant.• OASIS• ATC/AFC Calculation and Evaluation • Transmission Scheduling• Data Warehouses• Ancillary Services• TP and Customer Custom Applications

Page 6: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

6

Option 1 Complexities (cont’d)3. Industry-wide Business Models and Practices supporting a

robust secondary market are built upon these Industry-wide Systems.

4. To modify the current implementation to match the WEQ-001 Preemption and Competition Standards for Resales would be a major impact to the industry and a major disruption to the NW Regional Secondary Market.

5. These foundational commercial systems need to separate ‘scheduling capacity’ from ‘encumbering capacity’ which requires a change to WEQ-013.

6. The ability to track ‘encumbering capacity’ with ‘scheduling capacity’ both upstream and downstream through the daisy-chain of possibilities with the secondary market is critical and challenging.

Page 7: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

7

Option 1 Complexities (cont’d)7. Tracking aggregations to determine which scheduling capacity is

tied to which original reservation if:• The aggregated reservation is partially redirected, or if• one of the parents loses capacity due to STCP.

8. A massive data conversion effort is needed to take the existing capacity residing on the resale reservations and creating the encumbering capacity on the original parent.

9. The financial middleman aspect of tracing who paid what to whom would be complex given the daisy chain of potential resales and redirects of resales allowed by the current standards.

10. The complexity of the above items require that NAESB OS determine the time needed to address the implementation modifications and additions to OASIS and impacts to other commercial systems

Page 8: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Major Challenge for the OS for Option 1NAESB OS must provide an assessment of the changes needed to WEQ-013 to make it consistent with WEQ-001.11 ‘Resales’ Ability to Comply concern

• Once FERC adopts the BPs, TPs need to comply • If the NAESB Implementation Guide is inconsistent with the BPs or

does not address the BPs, then TPs cannot fully comply with the BPs• The NAESB OS STCP should include the development of the

implementation to enable compliance with the BPs• The NAESB OS STCP project should include modification to the

Implementation Guide to ensure consistency with WEQ-001 Because of the compliance exposure, NAESB OS STCP project

completion must consider the implementation templates and systems

TP must be able to ‘unwind’ and ‘track’ secondary transactions including multiple downstream transactions resulting in a ‘daisy-chain’ affect.

Page 9: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

9

Option 1 Questions????

Page 10: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Option 2 – Treat Resale as a capacity reassignment

Change WEQ 001-11 to align with WEQ-013 FERC Guidance history analysis supports that a Resale is

both scheduling and capacity reassignments C&P Rules for Resales

• Inherits the conditionality of the parent• Transaction is ‘delinked’ from the parent reservation• Cannot be a Challenger• Can be a defender if the parent is conditional and can ‘extend’ if

challenged• Parent Reservation continues to be billed under it’s original

agreement with the TP• Assignee is billed separately for the matching extension (same

billing issue as Motion 11)

Page 11: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Option 2 - FERC Description of ResalesFERC history (as far back as Order 888) refers to Resale as ‘capacity reassignment’ Order 888, Page 178: ‘…a public utilities tariff must explicitly permit the voluntary

reassignment of all or part of a holder’s transmission capacity right to any eligible customer.

Order 888 Page 179: ‘In effecting reassignment, the assignor does not have to return it’s capacity entitlement to the TP but may deal directly with the assignee without involvement of the TP.

Order 890 P 808: ‘In Order No. 888, the Commission found that allowing holders of firm transmission capacity rights to reassign capacity would help parties manage the financial risks associated with their long-term commitments, reduce the market power of transmission providers by enabling customers to compete, and foster efficient capacity allocation.’

FERC Order 676C ¶ 46 “The assumption of a customer's scheduling rights by an assignee for one or more hours does not mean the transmission provider is offering hourly service to the assignee. As the Commission explained in Order No. 890-A, the reassignment of transmission capacity simply results in the reseller obtaining the right to schedule the reserved capacity during the period of the reassignment, consistent with the original customer's reservation. Indeed, permitting such resales is consistent with the Commission's determination in Order No. 888 that “a public utility's tariff must explicitly permit voluntary reassignment of all or a part of a holder's firm transmission capacity rights to any eligible customer.

Page 12: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Key Points Concerning FERC Language1. FERC does not divorce scheduling and capacity rights in their

discussion of Resale and therefore lends credence to the argument that NAESB OS should reconsider it’s current treatment of Resales as scheduling rights apart from capacity.• To have separate scheduling rights apart from the corresponding

capacity right is meaningless. • Current WEQ-001 standards treat them as separate, WEQ-013

implementation (and current systems) treat them as the same, as two sides of the same coin.

Encumbering Capacity

Scheduling Capacity

Page 13: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Key Points Concerning FERC Language

2. FERC implies that the Assignee has the same right to resell excess scheduling capacity that the reseller has• 890A ¶’s

– 427 ‘…Just as the original transmission customer may find that it has excess capacity it can reassign, so may an assignee. Denying the assignee's right to further assign its scheduling rights would inhibit customers who value the capacity most from accessing it and thereby contradict the Commission goal of creating a competitive secondary market for transmission capacity. …’

Page 14: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Key Points Concerning FERC Language3. FERC implies that transmission should go to

the customer who values it the most• This is the whole justification of Preemption and

Competition• The Assignee values the reassigned capacity

more than the Reseller• The Assignee should therefore be allowed to

make the decision on defending that scheduling capacity

• It would seem that the Resale, not the original reservation, should have ROFR rights since they value it most.

Page 15: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Key Points Concerning FERC Language

4. There appears to be a FERC Priority Conflict• FERC would like a robust secondary market,

including resales from conditional reservation • FERC would like a robust Preemption and

Competition market.• The two don’t mix. Preemption and Competition

actions for a conditional reservation with secondary transactions associated with it is in conflict with a robust secondary market. In fact, it suppresses or discourages a robust secondary market due to inherent uncertainties.

Page 16: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Implementation Advantages of Option 2

The majority of Option 1 complexities listed above are greatly reduced for Option 2

Much of the implementation processes used today are unaffected

It requires minimal changes to existing WEQ-001 BPs

Auditing and Tracking of Resale activity is easier

Page 17: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

For Further Consideration (Next Steps)

NAESB OS discussion with FERC• Straw Poll of support at the OS• Request FERC Staff attendance at the OS May

2013 meeting to further evaluate an Option 2 approach

Parking Lot Re-evaluation:• Option 2: Rescind Resale Motion 14

Do we need a mitigation plan• Suspend conditional resales• Annul all associated downstream transactions• Neither are popular with the NW Region

Page 18: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

18

Option 2 Questions????

Page 19: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

OS Project R09015Does tackling the Reservation Merge Project make sense to be worked on as part of the

STCP?

Page 20: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

Reference Material for R09015

R09015 Restated BPA 2012 Service Increment Transaction

Volumes Transaction Reservation Merge Project

value considered for conditional Resale C&P

Page 21: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

21

Transmission Reservation Merge (R09015)

‘Transmission Customers may from time-to-time have a portfolio of transmission service reservations from a single provider on a single path. For ease of tracking and efficiency, the customers desire to combine or merge like reservations (i.e., firm, non-firm, etc) into a single reservation. Under existing OASIS business practices and protocols, customers must use the Resale mechanisms to merge two or more like reservations under a single assignment reference number. In other words, customers sell their reservations back to themselves.’

Page 22: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

22

Revised Volumes for BPA’s Secondary Transaction A recent BPAT review of 2012 secondary transaction

volume lends support to a third Option for C&P issues associated with Resales.

Page 23: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

23

Why Tackle the ‘Tx Reservation Merge’ Project? Daily Resale Activity - Summary

38% of Daily Resales were done on the same day as the start day of the parent. (Parent Reservation is Unconditional, e.g. Resale cannot lose scheduling rights.) 

18% were done after the start date of the parent.  (Parent Reservation is Unconditional, e.g.,  the Resale cannot lose scheduling rights.) 

28% were done within 1 calendar day before the start date of the parent.  (Really close to having the Parent Reservation Unconditional, lowers the probability that the Resale would lose scheduling rights.)

This means that 84% of Daily Resale activity is done within 1 calendar day of the start day of the parent

Another 11% of Daily Resales are done more than 1 calendar day ahead of the start day of the parent (but these 11% are also safe because they are within 1 pre-schedule day of the parent start time).  So, more than 95% of Resales are done within 1 pre-Schedule day or later.

Of the 5% of Daily Resales that are done in the conditional window, 45% are Resale to self.  Mitigate the 2.7% of the total Daily Resales addressing the ‘Transmission Reservation Merge’ NAESB request e.g., for Resales that could be recalled due to a Conditional Parent, the ‘Transmission Reservation Merge’ project would mitigate 45% of this exposure.

Page 24: Conditional  Resales NAESB Assignment Update

B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

R09015 value in the C&P project Utilities with a high volume of secondary transactions may

reduce C&P exposure to conditional Resales that are used for the consolidating of transmission inventory. For BPAT,• Addressing the R09015 project now apart from option 1 and limiting

conditional reservations only solves half of the problem. To fully address the issues with Option 1, you would need both the reservation merge and limiting resales to unconditional reservations.

• It might simplify the ‘fix’ to the inconsistencies between 001 and 013 if Option 1 is chosen.

• The volumes are low enough in the pro forma markets that though it is a good idea, doing R09015 now does not provide a lot of value to the STCP project.

BPA recommends that R09015 stand on its own merit and not be taken on as part of the STCP.