Concrete Centre - Scheme Manual to EC2
-
Upload
nabil-atta -
Category
Documents
-
view
218 -
download
10
description
Transcript of Concrete Centre - Scheme Manual to EC2
cement concrete
Since its publication in 2006, the Concrete building scheme design manual has proved a popular publication and this update is intended to assist the transition to Eurocode 2 for the design of concrete structures by showing how to carry out initial design to the Code. As before it will greatly assist candidates for the Institution of Structural Engineers chartered membership examination by drawing together in one place useful information including design aids that are specifically prepared for Eurocodes.
Andrew Minson was the originator of the concept for this book, but the final format and content have evolved over time with input gratefully received by the author, Owen Brooker, from a number of people. The book contains some new material but many of the ideas and much of the data have been developed from many sources over several years. It is not possible to credit every source; indeed many are unknown, but wherever possible, references have been made to relevant documents.
Particular thanks are due to Jenny Burridge and Bob Wilson who have spent considerable time reviewing and commenting on drafts and providing useful guidance on what the examiners are expecting. Thanks are also due John Brazier, Andrew Cotter, Bryan Magee and Matt Obst, who have commented or made useful contributions in more specialised areas.
Gillian Bond, Issy Harvey, Sally Huish and Michael Burbridge Ltd have also made essential contributions to the production of this handbook.
All advice or information from MPA –The Concrete Centre is intended only for use in the UK by those who will evaluate the significance and limitations of its contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting from such advice or information is accepted by MPA –The Concrete Centre or its subcontractors, suppliers or advisors. Readers should note that MPA –The Concrete Centre publications are subject to revision from time to time and should therefore ensure that they are in possession of the latest version.
Printed by Michael Burbridge Ltd, Maidenhead, UK.
i
Contents
ii
Symbols used in this handbook
Symbol Definition
D
iii
without
iv
a
a a
b
b
b b
b b
g
g
g
g
g
d
d
y
l
l
m
r
r
r
r
r r
s
s
s
f
f
f
c
1
Introduction
How to use this handbook
Text on a pale blue background provides information to help candidates prepare for
the examination and is not intended for use in the examination itself.
Assumptions
2
The examination
Timing
Further information
3
Development of solutions (section 1)
Viable structural solutions
two
■ ■
■ ■
■ ■
■ ■
■ ■
■ ■
■ ■
■ ■
■
Functional framing
Load transfer
■
■
■
4
Pilecap
Pile
Tie/strut
Long-span roof
Stiff floor Load-bearingconcreteblock wall
Upstandbeam
Column
Column
Raft
Shearwall
Transfer beam
b) Gable shear wall
c) Reservoir
Retainingwall
Flat slab (min. 3 bays)
Slendercolumns
Floor slab ‘on grade’
d) Precast concrete terracing
GLGL
a) Building section
5
Partition load
Uniform load
Wall reaction
Load from beam= load on wall
Foundation reaction
Foundation load
column
Deflection, bendingand shear in beamleads to reactionsat the end of thebeam
Foundation reaction
Pile cap
Pile reaction
Pile load
Friction reaction
End reaction
Pile
Stress =LoadArea
Load on pilecap
Ground reaction
Load onto ground
B
1.5B
sBulb of pressurefor /5
Load on rock
Brickwork wall
s = bearingpressure
a) Vertical loads
Reinforced concrete
6
Bearing pressures
W2
W1Soil at rest
GWL
Water load
Surcharge
Passiveresistance
GL
GL
Hogging
TensionExtra compressionwith bending
Supportremoved
Wallsdisplaced
Tieac
tion
Floor sag
c) Effect of accidental impact
d) Retaining wall
Wind
b) Plan view of diaphragm action
Tension
7
Stability
Lateral stability
■
■
■
■
■
■
■
Movementjoint
a) Walls resist bending in one plane, frame action in other plane. Good tortional stiffness.
b) Walls resist bending in both planes. Good tortional stiffness.
c) Core resists bending in both planes. Poor tortional behaviour due to eccentricity.
d) Cores resist bending in both planes. Good tortional stiffness.
e) Cores resist bending on each section of the building independently. Relative shear displacement at movement joint.
8
■
■
■
Uplift
Concrete frame options
Foundations and retaining structures
Ground-bearing slabs
■
■
■
■
■
Foundation solutions
■
■
9
One-way slab
P/T flat slab Hybrid hollowcore and topping
Key
a) Imposed load Qk = 2.5 kN/m2
b) Imposed load Qk = 5.0 kN/m2
c) Imposed load Qk = 7.5 kN/m2
100
300
400
500
4 5 6 7 8 9 10 11 12 13 14 15Span in m
Dep
th in
mm
200
Troughed slab Flat slab
600
100
300
400
500
4 5 6 7 8 9 10 11 12 13 14 15Span in m
Dep
th in
mm
200
600
100
300
400
500
4 5 6 7 8 9 10 11 12 13 14 15Span in m
Dep
th in
mm
200
600
10
✓ ✓
✓
✗
Solid flat slab (Continuity improves economy) ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗
Solid flat slab with drops ✓ ✓ ✓ ✓ ✓✓ ✓ ✓ ✓ ✓✓ ✓✓ ✓✓ ✗
Solid flat slab with column heads (Forming column head
disrupts cycle times and interferes with holes adjacent to
columns)
✓ ✓ ✓ ✓✓ ✓✓ ✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗
Waffle slab ✓✓ ✓ ✓ ✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗
Biaxial voided slab (Can be used with in-situ or with
precast soffit slab, which would act as permanent
formwork)
✓✓ ✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓
Solid one-way slab with beams ✓ ✓✓ ✗ ✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗
Solid slab with band beams ✓✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓✓ ✓✓ ✓✓ ✗
Ribbed slab with beams ✓ ✓ ✓ ✗ ✓✓ ✓✓ ✓ ✓✓ ✓✓ ✓✓ ✗
Ribbed slab with integral band beams ✓ ✓✓ ✓ ✓ ✓ ✓ ✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗
Tunnel form (One-way slab on walls) a ✗ ✗ ✓✓ ✓✓ ✓✓ ✓✓ ✗ ✓✓ ✗ ✓✓ ✓✓ ✓✓ ✗ ✓✓ ✓✓ ✗
Composite lattice girder soffit slab b ✗ ✗ ✓✓ ✓ ✓✓ ✓ ✗ ✓ ✓✓ ✓✓ ✓✓ ✓ ✓
Precast hollowcore slab ✗ ✗ ✓✓ ✓ ✓✓ ✓ ✗ ✓✓ ✓✓ ✓✓ ✓✓
Composite precast slab ✗ ✗ ✓✓ ✓ ✓✓ ✓ ✗ ✓ ✓✓ ✓✓ ✓ ✓
Precast double ‘T’ units ✗ ✗ ✓✓ ✓ ✓ ✗ ✓✓ ✓✓ ✓ ✓✓ ✓✓
Precast crosswall and solid prestressed slab ✗ ✗ ✓✓ ✓ ✓✓ ✓✓ ✗ ✓ ✗ ✓✓ ✓ ✓✓ ✗ ✓✓ ✓✓ ∏
Solid two-way slab with beams ✗ ✗ ✓ ✓ ✓ ✗ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✗
Two-way waffle slab with beams ✗ ✗ ✓ ✗ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✗
Waffle slab with integral beams ✗ ✗ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✗
Precast twin wall and lattic girder soffit slab with
in-situ infill and topping
✗ ✗ ✓✓ ✓ ✓✓ ✓✓ ✓✓ ✓✓ ✗ ✓✓ ✓ ✓✓ ✗ ✓✓ ✓✓ ✓
Precast columns and edge beams with in-situ floor
slab✓✓ ✓✓ ✓✓ ✓✓ ✓✓ ✓ ✓✓ ✓ ✓✓ ✓✓ ✓
Precast columns and floor units with in-situ beams b ✗ ✗ ✓✓ ✓ ✓✓ ✓✓ ✓✓ ✓ ✗ ✓✓ ✓✓ ✓✓ ✓ ✓ ✓✓
In-situ columns and beams with precast floor units b ✗ ✗ ✓✓ ✓ ✓✓ ✓✓ ✓✓ ✓ ✗ ✓✓ ✓✓ ✓ ✓ ✓✓
In-situ columns and floor topping with precast
beams and floor units
✗ ✗ ✓✓ ✓ ✓ ✓ ✗ ✓✓ ✓✓ ✓ ✓ ✓
11
12
13
Piling options
Retaining walls
14
15
Ground improvement
■
■
■
■
■
■
16
Remediation using soil stabilisation/solidification
Stabilisation
Solidification
l
l
l
l
l
l
l
l
l
l
l
l
l
l l
17
Design appraisal
Safety
■
■
■
■
■
18
■
■
■
■
■
■
■
■
■
■
■
Economy
Foundations ■
Cladding ■
Partitions ■
Airtightness ■
Services ■
19
Buildability
Using flat soffits ■
Repetition of design elements ■
Simplification ■
Standardisation ■
Rationalisation of reinforcement ■
■ precast prefabricated
Using in-situ concrete ■
Robustness
Durability
Site constraints
■
■
■
■
■
■
■
20
Speed of construction
Aesthetics
Acoustics
Footfall-induced vibration
21
mm % change mm % change mm % change mm % change
kg/m2 % change kg/m2 % change kg/m2 % change kg/m2 % change
Thermal mass
Sustainability
22
23
210020902080207020602050204020302020201020000
20
40
60
80
100
120
140
160
180
200Cumulative CO emissions2
Cpr
oduc
ed(t
onne
s)O
2
Embodied CO2
COin
use
2
Year
NoteThis graph assumes solar shading used and air-conditioning will be installed in homes whentemperatures become uncomfortable, but will be used with natural ventilation whenever possible.
Heavy (cavity walls, precast concrete floors, dense block partitions)Medium-heavy (cavity walls, precast concrete floors, block partitions)Medium (cavity walls, timber floors,Light (timber frame & floors,
Key
lightweight partitions) lightweight partitions)
Building movements
■
■
■
■
■
24
■
■
■
■
me me
me me
me me
me me
me me
me me
me
Fire resistance
25
Typical loads
a) Favourable layout of restraining walls (low restraint)
b) Unfavourable layout of restraining walls (high restraint)
26
27
28
Total 4.0 Total 3.6
Total 2.8
Total 0.4
Total 2.4
Total 1.8
Total 0.9
Total 0.5
Total 2.40
Total 0.5
Total 4.0
Total 0.4
Total 0.8
29
30
Typical spatial requirements
Car parks
6.0 m 4.8 m
Bin width
4.8 m
3 x 2.4 mbays3
bins
reco
mm
ende
dm
inim
um
BA
A: 0.46 m minimum0.8 m to 1.0 mpreferred range
B: 3.3 m minimum3.6 m desirable
Acceptablesupport positions
Typical baydimensions
*
*
Interbin support zone
Services
Preliminary sizing
31
Duct leaving riser / coreconsider universalcolumns as beams
H
Below deep beamsfinal terminal device only
Main duct run-outsbelow normalmaximum beam size
FFL
FFL
AB
CD
E
F
G
VAV terminal box
400 500
A Structural zoneB 50 mm deflection and toleranceC Approx. 500 mm HVAC duct or terminal deviceD 50 mm support and toleranceE 5 150 mm sprinkler zone (if required)F 150 mm lighting and ceiling zoneG Floor to ceiling heightH Raised floor
a) Flat soffit
Raisedfloor
Floor toceilingheight
Serviceszone
Structuralzone A
BC
D E
F
G
H
b) Downstand beams
Key
32
Beams
Simply supported
End-bay
Cantilever
Transfer beams
One-way spanning slabs
Two-way spanning slabs
33
Flat slabs
Ribbed slabs
a
Waffle slabs
34
1
2
3
4
Squarecolumn
Imposed load
h
Superimposed deadload =1.5 kN/m2
Post-tensioned slabs and beams
35
Precast concrete floor units
300
200
1003.0 4.0 5.0 6.0 7.0 8.0 9.0
Span (m)
Slab
dept
h(m
m)
KeyCharacteristic imposed load (IL)
2.5 kN/m2
5.0 kN/m2
7.5 kN/m2
10.0 kN/m2
36
Columns
■
■
■
■
■
■
■
Shear walls
37
Depth
Tension
Compression
Span
The letter
not
■
■
■
■
■
38
Engineering Consultants99 High StreetNewtownNW9 9AA
Your ref:Our ref: 1099/OB/1.01/21-11-06 21 November 2006
FAO Mr J Client
Dear Mr ClientCall Centre – Implications of Recent Minor Seismic Activity
As we are sure you are aware there has recently been a minor earthquake in the region of the recently completed Call Centre. We would like to address the concerns you may have regarding the strength of your building if faced with a similar event.
Initially we would like to confirm that the structure has been designed to the latest Building Regulations and Codes of Practice. There is no requirement to explicitly consider the effects of seismic activity because historically the most significant horizontal forces on structures in this region are wind forces, rather than forces arising from seismic activity.
We would suggest that, before making any decisions about strengthening the structure, we wait for a consensus amongst the experts as to whether this type of event is likely to occur more frequently in the area and what they recommend as the design requirements. We would expect that, if changes are necessary, the Building Regulations will be revised and that clear guidance will emerge on whether existing buildings should be strengthened. The Call Centre is just one of many buildings that could be affected by a similar earthquake in this region.
In the meantime, we would like to reassure you that the building as it stands will have reasonable strength to resist to a minor seismic event. It has been designed with ties to ensure that ‘progressive collapse’ does not occur and these will act to strengthen the building in the event of an earthquake. There are, however, a number of specific areas where localised damage could occur as a result of a small earthquake; these are detailed below.
precast units and topping screed are designed to act as a stiff diaphragm. However, depending on the intensity of the earthquake, this system may have insufficient strength to carry the forces. A design check can be carried out when there is agreement on the design forces that should be used for an earthquake in this region.
earthquake the structures will move laterally and the width of the joint is unlikely to be sufficient to prevent the two structures from making contact. We think there are two options for overcoming this; either the joint could be made wider by making alterations to the existing structure, or the lateral stiffness of the building could be increased by incorporating more stability walls. The latter would reduce the sideways sway during a seismic event. It may also be the preferred solution if the floor diaphragm requires strengthening. We will need to have a discussion so we can find an acceptable solution that provides minimal disruption to your business and the minimum effect on the architecture.
we will need to review the strength of the foundations to resist lateral forces, for which they were not designed. The building has a suspended ground floor, which means that there are beams tying the foundations together. This is beneficial in the event of an earthquake, because it prevents the foundations moving apart possibly causing major damage to the frame.
generally left to the precast manufacturer to design. This is usually beneficial because he can carry out the work more efficiently and to suit his working methods. On this project the manufacturer has used a ‘billet’ type connection, which is perfectly adequate for the job it was designed to do. However, it offers less spare capacity to resist the forces from an earthquake and strengthening may be required.
during an earthquake is almost certain to damage the glazing. The current glazing is laminated glass, which means that it will not break into small pieces. However, there is a risk that whole panes will come away from their fixings with the potential to cause loss of life. To overcome this, strengthening of the column–to-roof beam connections will be necessary to reduce lateral sway.
We cannot be certain about how design guidance will change as a result of the earthquake, but the above comments should give you an appreciation of the preventive measures that are likely to be necessary. If you would like to discuss the situation further then please contact us.
Yours sincerely
39
Design calculations (section 2c)
Expectations of the examiners
sufficient
principal
Principal elements
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
40
Durability and fire resistance
■
■
■
X0
XC1
XC2 AC-1
XC3 XC4
XF1
XF3
XF3
XD1
XD3
XF2
XF4
XF4
XS1 XF1
XF3 or XF4
a
b
c
d D
e
41
D D D D D D D D
f
g
h
j
42
a
b
c
d
e
f
43
Assessing the design moments
Flexure
d d
d
d
44
Shear
Slabs
r
r
r
r
45
Beams
START
No
Yes (cot y = 2.5)
Determine y from:
y = 0.5 sin-1vEd
0.20 fck (1 – fck/250)
Yes
No
Determine vEd where:
vEd = design shear stress [vEd = VEd/(bwz) = VEd/(0.9 bwd)]
IsvEd < vRd,max cot y = 2.5? Redesign
section
IsvEd < vRd,max cot y = 1.0?
(see Table 3.7)
Determine the concrete strut capacity vRd,max cot y = 2.5from Table 3. 7
Calculate area of shear reinforcement:
Check maximum spacing for vertical shear reinforcement: sl,max = 0.75 d
Asw
s=
vEd bw
fywd cot y
Procedure for determining vertical shear reinforcement
y y
46
Deflection
Notes
1 For two-way spanning slabs, the check
should be carried out on the basis of the
shorter span.
2 This graph assumes simply supported span condition (K = 1.0).K = 1.5 for interior span conditionK = 1.3 for end span conditionK = 1.2 for flat slabsK = 0.4 for cantilevers
3 Compression reinforcement, r',has been taken as 0.
4 Curves based on the following expressions:
where r ≤ r0
and
where r > r0
11 + + 3.2 –1= Kr
fck
r01.5
d
l fck
r
r0[ ( ) ]
11 + += K( r – r ')
fck
r01.5
d
l12
fck
r0
r '[ ]
1.5
Percentage of tension reinforcement (As,req/bd)
12
0.40% 0.60% 0.80% 1.00% 1.20% 1.40% 1.60% 1.30% 2.00%
14
16
18
20
22
24
26
28
30
32
34
36Sp
an t
o d
epth
rat
io (
l/d)
fck = 50
fck = 45
fck = 40
fck = 35
fck = 32
fck = 30
fck = 28
fck = 25
fck = 20
Basic span-to-effective-depth ratios
■
■
s s
47
600
750
900
1200
1500
2000
Beams and slabs
Flat slabs
4.03.02.01.0
Ratio Gk/Qk
c2 = 0.8, gG = 1.35
c2 = 0.6, gG = 1.35
c2 = 0.3, gG = 1.35
c2 = 0.6, gG = 1.25
c2 = 0.3, gG = 1.25
c2 = 0.2, gG = 1.25
c2 = 0.2, gG = 1.35
App
roxi
mat
e st
eel s
tres
s at
SLS
for
A s,re
q, s
su
180
200
220
240
260
280
300
320
To determine stress in the provided reinforcement (ss), calculate the ratio Gk/Qk,
read up the graph to the appropriate curve and read across to determine ssu.
ss can be calculated from the expression: ss = ssu f
As,req pf
1p
As,prov d
Determination of steel stress
48
Estimating reinforcement quantities
■
■
■
■
Detailing
Maximum and minimum areas of reinforcement
Minimum spacing of bars
&f
f
49
f f
f
300
350
400
450
500
550
600
650
700
750
800
900
1000
1100
1200
1300
1400
1500
Maximum spacing of bars
Design of beams
Governing criteria
50
Analysis
Flanged beams
Fire resistance
f f
51
OB CCIP - 018
MS TB1
TCC Aug 09
Gk = 1500 kN, Qk = 1000 kN
1.5 m 9.0 m
Initial sizing Shear stress not to exceed 4 N/mm2 (to avoid reinforcement congestion).
Ultimate load = 1.35 x 1500 + 1.5 x 1000 = 3525 kN (ignoring self-weight)
Take b = 600
d = VEd
vEdb
Take overall depth as 1650 mm (d = 1550)
Bending Mmax = 3525 x 1.5 = 5288 kNm For Mmax = 5288, b = 600, d = 1550, fck = 32 N/mm2
K = 0.115, As = 8858 mm2 (z = 1297 mm)
Use 8 H40 (10100 mm2) in 2 layers.
Shear vEd = 3525 x 103/(0.9 x 600 x 1550) = 4.21 MPa
Assuming the strut is at 45°
Asw ≥ 4.21 x 600s 435 x cot 45°
≥ 5.81 mm
Try H12 linkss = 452/5.81 = 78 mm
Say 4 H12 links @ 75 mm ctrs
Comments Remember to check headroom beneath the beam
H40 bars will be heavy; if there is no reasonable alternative, ensure that the contractor is aware so he may take steps to safeguard the health and safety of the steel fi xers.
= 3525 x 103 = 1469 mm 4 x 600
8H40barsSlab
reinforcement
1650
600
4 H12 links@ 75 ctrs
Section 2.10.2
Figure 3.1
Figure 3.1
Table 3.7
Worked example 1Transfer beam
52
One-way spanning slabs
Governing criteria
Analysis
1
2
3
4
5
1
2
Fire resistance
f f
REI 60
REI 90
REI 120
REI 240
1
2
53
OB CCIP - 018
MS OW1
TCC Aug 09
Worked example 2One-way slab
6000 6000 6000 6000
Initial sizing From Economic concrete frame elements – 167 Section 2.10 or 6000/32 = 187.5, say 200 mm
Loading ULS = 1.35 (0.2 x 25 + 1.5) + 1.5 x 2.5 = 12.5 kN/m2
Bending Check first support from end M = – 0.086Fl Table 3.14 = – 0.086 x 12.5 x 62
= – 38.7 kNm
For b = 1000, d = 200 − 25 − 10 = 165, fck = 28 Then K = 0.051, As, req = 567 mm2 (z = 157 mm) Use H12 @ 175 ctrs (As,prov = 646 mm2)
Shear VEd = 0.6F = 0.6 x 12.5 x 6 = 45.0 kN Table 3.14
vEd = VEd = 45.0 x 103 bd 1000 x 165
= 0.27 N/mm2
100 As = 100 x 646 = 0.39 bd 1000 x 165
vRd,c = 0.57 Table 3.6 vEd < vRd,c no shear links required
Deflection Maximum sagging moment = 0.075 Fl Table 3.14 = 0.075 x 12.5 x 62 = 33.75 kNm
For fck = 28, d = 165, b = 1000 Then K = 0.044, As,req = 494 mm2 (z = 157 mm)
r = As,req/bd = 494 x 100/(1000 x 165) = 0.30%Basic l/d = 35.2 x 1.3 = 45.8 (K = 1.3 for end span condition) Figure 3.2actual l/d = 6000/165 = 36.4 OK
Use H16 @ 200 ctrs As,prov = 566 mm2
Imposed load = 2.5 kN/m2
Superimposed dead load = 1.5 kN/m2
Concrete class C28/35cnom = 25 mm
Two-way spanning slabs
Governing criteria
Analysis
54
a
a
a
a
b
b
■
■
55
bb
b b
56
b
b
b b
Fire resistance
f f
REI 60
REI 90
REI 120
REI 240
Flat slabs
Governing criteria
Analysis
■
■
■
■
■
57
OB CCIP - 018
MS TW1
TCC Aug 09
Worked example 3Two-way slab
l x =7200 7200 72007200
l y=
900
090
00
Initial sizing From Economic concrete frame elements: 213 mm Section 2.10 or 9000/36 = 250 mm say 250 mm
Loads n = 1.35 (1.5 + 6.25) + 1.5 x 5 = 18.0 kN/m2 (ULS)
Check short span d = 250 − 25 − 8 = 217 mm
ly = 9.0
= 1.3 lx 7.2
bsx = – 0.069 and bsx = 0.051 Table 3.17
Support moment msx = bsx n lx2 = – 0.069 x 18.0 x 7.22 = – 64.4 kNm/mcritical in bending For msx = 64.4, b = 1000, d = 217, fck = 28
Then As = 718 mm2/m (K = 0.049 & z = 206 mm) Use H12s @ 150 ctrs (As,prov = 754 mm2/m)
Shear bvx = 0.50 Table 3.18 Vsx = bvx n lx = 0.5 x 18.0 x 7.2 = 64.8 kN/m width vEd =
VEd = 64.8 x 103 = 0.30 N/mm2 bd 1000 x 217
100 As = 100 x 754 = 0.35 bd 1000 x 217
vRd.c = 0.57 N/mm2 > 0.30 no shear links required Table 3.6
Deflection Maximum sagging moment = 0.051 x 18.0 x 7.22 = 47.6 kN/m For b = 1000, d = 217, fck = 28 Then K = 0.036, As req = 531 mm2 (z = 206 mm)
r = As,req/bd = 531 x 100/(1000 x 217) = 0.24%Basic l/d = 35.2 x 1.3 = 45.8 (K = 1.3 for end span condition) Figure 3.2actual l/d = 7200/217 = 33.2 OK
Use H12 @ 200 ctrs As,prov = 566 mm2
Superimposed dead load = 1.5 kN/m2
Imposed load = 5 kN/m2
cnom = 25 mm
Concrete class C28/35
58
1
2
Negative
Positive
Punching shear reinforcement
b
b
b = 1.5
b = 1.4 b = 1.15
Internal column
Corner column
Edge column
b
59
lx (longerspan)
Columnstrip
Co
lum
nst
rip
Middlestrip = lx -
Mid
dle
str
ip
ly
ly
lyly
ly
ly
2
2
44
4
4
l y (s
ho
rter
span
)
Middlestrip = lx – dropsizeDrop
Dro
p
Ignore drop if
dimension < ly/3
Ignore drop if
dimension < ly/3
ly
Co
lum
n s
trip
=
lx
Column strip =dropsize
dro
psi
ze
a) Slab without drops
b) Slab with drops
rr r
p
60
Transfer moments
61
Fire protection
f f
d d
Ribbed slabs
Governing criteria
Geometry
T
R
W
bc
xa
Self-weight = cRy ( + ) + + ( + ) kN/mW Z T H a b
225x
Z
y
H
62
OB CCIP - 018
MS FS1
TCC Aug 09
Worked example 4Flat slab
9000 9000 9000 9000
700
070
00
Initial sizing Using Economic concrete frame elements: 284 mm
Or 8000/26 = 307 mm, say 300 mm Section 2.1
Loading ULS = 1.35 (1.5 + 0.3 x 25) + 1.5 x 5 = 19.65 kN/m2
Bending Check long span end bay condition
M = – 0.086Fl = – 0.086 x 19.65 x 7 x 92 = – 958 kNm Table 3.20
Centre strip Design moment = 0.75 x 958 = 718 kNm Table 3.21critical
For b = 3500, d = 300 − 30 − 10 = 260 mm, fck = 28
Then K = 0.108, As = 7110 mm2
Centre column strip = 4740 mm2 (2708 mm2/m)
Use T20 @ 100 ctrs (As,prov = 3140 mm2/m)
Outer column strip = 2370 mm2 (1354 mm2/m)
Use T20 @ 200 ctrs (As,prov = 1570 mm2/m)
Punching shear VEd = 19.65 x 7.0 x 9.0 = 1238 kN
At column face, vEd = b VEd
= 1.15 x 1238 x 103
= 4.07 < 4.98 uideff 4 x 350 x 250Table 3.22
Shear resistance without links: 100 As
= 100 x 3140
= 1.26% bd 1000 x 250
vRd,c = 0.75 MPaArea of steel at first control perimeter, 2d = 2 x 250 = 500 mm from column face.Length of perimeter = 4 x 350 + 2 x 500 = 4542 mmRadial spacing sr = 0.75 x 250 = 188 mmAsw = (vEd – 0.75 vRd,c)sr u1/(1.5 fywd,ef)
= d1.15 x 1238 x 103 – 0.75 × 0.75m x 188 x 4542 /(1.5 x 313)
4542 x 250 = 1257 mm2/perimeter
Using 10 mm dia. links, no of links = 1257/78.5 = 16, spacing = 4542/16 = 284 < 1.5d
Deflection Maximum sagging moment = 0.075 Fl = 0.075 x 19.65 x 7 x 92
= 836 kNm
Imposed load = 5 kN/m2
Superimposed dead load = 1.5 kN/m2
Concrete class C28/35
cnom = 30 mm
Supported by 350 mm square columns
63
Analysis
2
3
Bending reinforcement
Reinforcement in the topping
Centre strip Design moment = 0.55 x 836 = 460 kNmcritical
For b = 3500, d = 260 and fck = 28
K = 0.069, As = 4351 mm2 Or As = 1243 mm2/m
r = As,req/bd = 1243 x 100/(1000 x 260) = 0.48%Basic l/d = 20.3 x 1.2 = 24.4 (K = 1.2 for flat slab condition) Figure 3.2actual l/d = 9000 / 260 = 34.6Increase area of steel to reduce steel stress, assume H20 @ 225 ctrs (1400 mm2)Approximate steel stress at SLS = 236 MPa Figure 3.3Therefore approximate steel stress, ss, when As,prov = 1400 mm2
ss = 236 x 1243/1400 = 210 MPaIncreased basic l/d = 24.4 x 310/210 = 36 > 34.6 OK
Use H20 @ 225 ctrs As,prov = 1400 mm2
Comments 1. The design in the orthogonal direction has not been included.2. For the design of the strips across two panels only, coefficients from Table 3.20 are not appropriate.
64
20
25
28
30
32
35
40
45
50
Fire protection
f f
REI 60
REI 90
REI 120
REI 240
65
OB CCIP - 018
MS RS1
TCC Aug 09
Worked example 5Ribbed slab
750
7200
1000
Initial sizing Using Economic concrete frame elements: 255 mm
or 7200/29 = 248 mm, say 250 mm
Assume self-weight = 4.0 kN/m2 Table 2.9c
Loading ULS = 1.35 (4.0 + 1.5) + 1.5 (2.5) = 11.2 kN/m2
Bending Check sagging moment in end bay
d = 250 – 26 – 6 – 8 = 210 mm
Effective length = 6.2 + 2 x 1/2 x 0.210 = 6.41 m
M = 0.075Fl = 0.075 x 11.2 x 6.412 x 0.75 = 25.9 kN/m per rib Table 3.20
For b = 750, d = 210, fck = 28
K = 0.030, As,req = 291 mm2 (z = 200 mm)
x = 2.5 (210 – 200) = 25 mm
N.A. in flange – design as rectangular section
Deflection r = As,req/Ac = 291 x 100/(125 x 110 + 750 x 100) = 0.33%Reduction factor for flanged section = 1 – 0.1 x ((750/125) – 1) = 0.5 use 0.8. Table 3.25Basic l/d = 0.8 x 33 x 1.3 = 34.3 (K = 1.3 for end span condition)actual l/d = 7200 / 210 = 34.3 OK
Imposed load = 2.5 kN/m2
Superimposed load = 1.5 kN/m2
Concrete class: C28/35
cnom = 26 mm
Topping thickness = 100 mm
A142 mesh
100
150
H16
10 125 10
H6
BS EN 1992-1-1: Fig 5.4
66
Waffle slabs
Governing criteria
Geometry
x
y
b
a
c H
N = number of waffles Self-weight = - + +xyH N a b a b2 2 2 225xy
c3 kNm2,
Analysis
Bending reinforcement
67
Reinforcement in the topping
Fire protection
f f
a a a a
a a
Precast flooring systems
68
■
■
■
Post-tensioning
12.9 ‘Super’
15.7 ‘Super’
15.7 ‘Euro’
15.2 ‘Drawn’
Restraint
Load balancing
69
OB CCIP - 018
MS WS1
TCC Aug 09
Worked example 6Waffl e slab
9000
720
0
Initial sizing Using Economic concrete frame elements: 425 mm thick (i.e. 325 moulds + 100 topping)
or 9000/20 = 450, say 425 thick Section 2.9
Assume self-weight = 7.3 kN/m2 Table 2.9c
Ultimate load n = 1.35 (7.3 + 1.5) + 1.5 (2.5) = 15.6 kN/ m2
There is a substantial beam along the column strips, which can therefore resist torsion at the corners. Design as a two-way spanning slab.
ly = 9.0 = 1.25 lx 7.2 Interpolating for a corner panel
Hogging moments bsx = − 0.066, Sagging moments bsx = 0.049 Table 3.17
Bending at support Msx = bsx nlx2 = − 0.066 x 15.6 x 7.22 = − 53.4 kN/m width
For ribs @ 900 ctrs
M = 53.4 x 0.9 = 48.0 kNm/rib
For d = 425 − 26 − 6 − 8 = 385 mm, b = 900, fck = 28
Then As,req = 299 mm2 (Taking z = 0.95d and therefore N.A. is in fl ange)
Defl ection r = As,req/Ac = 299 x 100/(180 x 285 + 900 x 100) = 0.21%Defl ection not critical by inspection Figure 3.2
Use 2 x H16 per rib (As,prov = 402)
Imposed load = 2.5 kN/m2
Superimposed load = 1.5 kN/m2
Concrete class: C28/35
cnom = 26 mm
Stresses
s
s
70
Unstressed
slab
Prestressed
slab
Proposed
loading
Final
condition
a)
b)
c)
d)
Cover
Cover
70 x 19 mm ductLongitudinal duct
a) Transverse directionCover
Transverse duct
b) Longitudinal direction
70 x 19 mm duct
71
Stress limits
b
Initial design
72
OB CCIP - 018
MS PT1
TCC Aug 09
Worked example 7Post-tensioned slab
9000 9000 9000 9000
700
070
00
Initial sizing 9000/36 = 250 mm thick (Economic concrete frame elements: 249 mm)
Geometry Area of concrete, Ac = 7000 x 250 = 1750 x 103 mm2
Second moment of area, Ic = 7000 x 2503/12 = 9.11 x 109 mm4
Distance to extreme fibres from neutral axis, yb = yt = 125 mmSection modulus, Zb = Zt = 9.11 x 109/125 = 72.9 x 106
Strand diameter = 12.9 mmMinimum cover = 20 mmDistance to centre of strand = 60 mmTendon profile for end span (most critical):
Number of Characteristic value of maximum force, 186 kNstrands required Initial prestress = 0.8 x 186 = 149 kN (allow for 80% of characteristic force)
Prestress in service condition = 0.7 x 149 = 104 kN (allow for 10% loss at transfer and 20% loss at service, check in detailed design)Balance dead loads with prestressingP = ws2/(8a) = 7 x 6 x 92/(8 x 0.098) = 4339 kN
No. of tendons required = 4339/104 = 41.7, try 9 x 5 strands per duct Total force = 4680 kN
Moments (SLS) Applied loads wa = 7 x (6.25 + 1.25 + 5) = 87.5 kN/mBalancing load wb = 8aP/s2 = 8 x 0.098 x 4160 / 92 = 40.2 kN/mBalanced moment M ≈ (wa – wb) l
2/10 = (87.5 – 40.2) x 92/10 = 383.1 kNm
Mid-span stresses st = P + M = 4680 x 103 + 383.1 x 106 = 2.7 + 5.3 = 8.0 N/mm2
Act Zt 1750 x 103 72.9 x 106
For class C32/40 allowable compressive stress is 12.8 N/mm2 OK
sb = P – M = 4680 x 103 – 383.1 x 106 = 2.7 – 5.3 = – 2.6 N/mm2
Act Zb 1750 x 103 72.9 x 106
For class C32/40 allowable tensile stress is 2.7 N/mm2 OK
Comments Stresses at the support and punching shear should also be checked at this stage for a flat slab (see 3.12.3)It is assumed that deflection, the ULS requirements and transfer requirements can be met with passive reinforcement in detailed design, as is usually the case.
Imposed load = 5 kN/m2
Superimposed dead load = 1.25 kN/m2
Concrete class C32/40
Idealised tendonshape a = 250 – 60– 60– = 98
125a
125
60
60
652 for initial
design only
Table 2.22
Table 3.29
Section 3.16.2
Section 3.16.3
Table 3.30
Section 3.16.3
Table 3.30
73
Columns
Design
b
b
Condition 1 ■
Condition 2 ■
Condition 3 ■
ll
l
l
l
l l
74
Detailing
75
OB CCIP - 018
MS C1
TCC Aug 09
Worked example 8Column
300
Column
9000 9000
750
075
00
Loads Column supports 4 storeys
Ultimate load per floor = 1.35 (0.3 x 25 + 1.5) + 1.5 x 5 = 19.7 kN/m2
Total ultimate axial load = 4 x 19.7 x 7 x 9
N = 4952 kN
Initial sizing Using Economic concrete frame elements – 450 mm square
Column design NEd/bhfck = 4952 x 103/(4502 x 32) = 0.76
Take minimum moment as 4952 x 0.02 = 99 kNm (assume column is not slender)MEd/bh2fck = 99 x 106/(4503 x 32) = 0.03d2 = 35 + 8 +16 = 59 mmd2/h = 59/450 = 0.13
Use column graph for d2/h = 0.15Asfyk/bhfck = 0.35
As = 0.35 x 4502 x 32/500 = 4536 mm2
Use 6 H32 (As,prov = 4830 mm2)
Imposed load = 5 kN/m2
Superimposed load = 1.5 kN/m2
Concrete class: C32/40
cnom = 35 mm
H25
H8 links@ 300 ctrs
450
450
76
Fire resistance
f f
Shear walls
Design issues
s
77
s
Walls with unequal stiffness
e Lateral load
Shearcentre
y
78
Detailing
Fire resistance
f f
OB CCIP - 018
MS SW1
TCC Aug 09
Worked example 9Shear walls
40 kN
75 kN
75 kN
75 kN
gk = 35kN/m
gk = 35kN/m
gk = 35kN/m
gk = 35kN/m
2.5
200 mmthick wall
3.0 m
3.0 m
3.0 m
3.0 m
m
Q k,w
Comment This design assumes that the base is sufficient to resist overturning. When designing the base for overturning the EQU category should be used rather than STR as used here.
Assume critical combination is 1.0 Gk + 1.5 Qk,w where Qk,w is wind load.
Assuming the floor load is 4000 kN supported on 8 columns, the horizontal action due to imperfections = 0.25% x 4000 = 10 kN
ft = N − M Lt (tL2/6)
N = 1.0 x 35 x 4 x 2.5 + 0.200 x 12 x 2.5 x 25 = 500 kN
MEd = 1.5((40 + 10) x 12 + (75 + 10)(9 + 6 + 3)) = 3195 kNm
ft = 500 x 103 − 3195 x 106 2500 x 200 (200 x 25002/6)
= 1.0 − 15.3
= − 14.3 N/mm2
Assume that the tension is resisted by 1 m at the end of the wall.
As = 0.5 ft Lt t
fyd
= 0.5 x 14.3 x 1000 x 200 = 3287 mm2 or 1644 mm2/face 435
Use T20s @ 175 ctrs (1800 mm2/face)
79
OB CCIP - 018
JB SW2
TCC Dec 06
Worked example 10Shear walls with varying stiffness
60.0y 5.0
8.0
25.0
Shearcentre
W 4W 2
10.0
5.0 e
W 1
W 3
Wind force, take as 1.0 kN/m2
The relative stiffness of the walls can be calculated as follows (note as the walls are rectangular and the same thickness we can use the depth only)
W1 = 103 = 1000 m3
W2 = 83 = 512 m3
Total = 1512 m3
y = 0.1 x 1000 + 59.9 x 512 = 20.3 m 1512
Eccentricity, e = 30 – 20.3 = 9.7 m
Twisting moment, Mt = 9.7 x 1.0 x 60 x 3.6 = 2095 kNm per floor
In the worst case this moment can be resisted by the walls W3 and W4 only, the force (F) in each wall is:
F = 2095/24.8 = 84.5 kN per floor
To check for the critical case the direct design force on the walls W3 and W4 from the wind parallel to these walls = 1.0 x 3.6 x 25/2 = 45 kN, and therefore the forces imposed by the twisting action are more onerous and should be used for design.
Comments This layout is not particularly eccentric and yet still imposes large torsional forces.
Floor-to-floor height = 3.6 m
80
Ground-bearing slabs
1
2
■
■
■
■
■
Shallow foundations
Key considerations
■
■
■
■
Allowable bearing pressure
81
Fully weathered
Partially
weathered
Unweathered
82
700
600
500
400
300
200
100
00 1 2 3 4 5 6
Very dense
Dense
Medium dense
Loose
Foundation width (m)
Allo
wab
lebe
arin
gpr
essu
re(k
N/m
)2
tolim
itse
ttle
men
tto
25m
m
N = 10
N = 20
N = 30
N = 40
N = 50
Piled foundations
Pilecap design
■
■
83
ya
whereN = number of pi le s in g roupP = total load appli ed M = bendi ng moment a ppli edy = local di stance of the pi l e
fr om the neutral axis of the groupy = loc al di stance of pi l e ‘a’
from the neutral axis of the g roup
The force in pil e ‘a’ is given by :
±
a
a
aa
2 l
2 l
2l
A B
C D
2 l
2 l
Piles in cohesive material
a
g g gg
84
a
p ggg
p g
Sand orsandygravel
L Stiff clayB
Soft clay
Stiff clayLB
L < 10B
L = 20B
L > 40B
1.00
1.00
1.00
0.75
0.75
0.75
0.50
0.50
0.50
0.25
0.25
0.25
0
0
0
0
0
0
50
50
50
100
100
100
150
150
150
200
200
200
Adhe
sion
fact
orAd
hesi
onfa
ctor
Adhe
sio n
fact
or
Undrained shear strength, (kN/m )cu2
Undrained shear strength, (kN/m )cu2
Undrained shear strength, (kN/m )cu2
L > 20B
L = 10B
L > 40B
L = 10B
Stiff clayL
B
85
g
g
Group action – bored piles in clay
_ i
86
Piles in granular soil
d
ggg
ddggg
ffff
OB CCIP - 018
JB BP1
TCC Dec 06
Worked example 11Bored pile in clay
10 m
0 m c = 70 kN/mu2
c = 170 kN/mu2
Find safe working load of a 450 mm diameter bored pile in clay
Qf = ac As + cu Nc Ab gs gb
Qf = 0.45 (70 + 170)/2 p x 0.45 x 10 + 170 x 9 x p x 0.2252
3.0 2.5
= 254 + 97.3
= 351 kN
87
dddd
ffffdddd
a dd
ff
Piles in chalk
88
gggg gggg
Piles into rock
a
Basement construction
89
■
■
■
■
OB CCIP - 018
JB BP2
TCC Dec 06
Worked example 12Bored pile in sand
0 m
10 m
Mediumdensesand
Find safe working load of a 450 mm diameter bored pile in sand
Qa = Nq* Ab qo´ + As qo´,mean ks tand
gf
Take h´ = 33°, l/d = 10000/450 = 22.2
Nq* ≈ 41
Qa = 41 x p x 0.2252 x 18 x 10 + p x 0.45 x 10 x 18 x 5 x 0.387 x tan 33
3
Qa = 1174 + 320
3
= 498 kN
90
91
Plans, sections, elevations and critical
details (section 2d)
■
■
■
■
Plans, sections and elevations
■
■
■
■
■
■
■
■
■
Critical details
92
600150
300600
SFL = 112.150
600
FLOOR LAYOUT
SECTION X - X
All columns 300 x 300, centred on grid unless noted otherwise
150
150150
600 dp x 300
600
dpx
300
600
dpx
300
600
dpx
300
400 dp x 300
Up Down
1100
150
300
dpx
250
1501650
3450
400 dp x 300
200wall
150
150
600 dp x 300150
7000
150 3750 4250 150
B CA30
00
X
Column500 x 300
2
3
X
SFL = 112.150
1
200
500 250
93
Foundations
B
L
L
L
Y
X
L
Z
B
75 mm Blinding
L-bars to provide anchorage,attached to pile reinforcementwith couplers
Pile cut down tocut-off level
Pile reinforcement
75 mm
Damp-proofmembrane
b) Pile and pilecap connection forlarge diameter bars
Top ofpilecap
a) Pile and pilecap connection
94
Resin-anchored starter bars
b) Perimeter strip foundation
Facade
Damp-proofcourse
Blinding
Blinding
Concrete strip foundation
Precast hollowcore unit
In-situ screed
100 mm
d) Strip foundation supporting pre-cast unit
450min 75
f) Connection of column to pad foundation
Internal wall
FFL
Well compactedsub-base
Screed
In-situ RCslab
Insulation
Blinding
Blinding
Damp-proofmembrane
Mesh reinforcement
a) Internal strip foundation
Insulation
Well compactedsub-base
Blinding
Damp-proofmembrane
Damp-proofcourse
Façade
Top of pilecap
In-situ RC slab on sub-base
TOC
Blinding Well compactedsub-base
Insulation
Damp-proofmembrane
Blinding
Damp-proofcourse
c) Typical perimeter pile cap and ground bearingslab interface
Existingcolumn
New RC column
Sub-base
Resin-anchored dowelbars
New concretefoundation
Existingconcretefoundation
Damp-proofmembrane
Blinding
RC slab
e) Strengthening existing foundation
In-situ concrete
Reinforcement
95
Sub-base
Compressiblematerial
Mass concreteDamp-proofmembrane
Foundation
20 mm soft jointExistingmasonry wall
Mass concrete
Assumed foundationto existing wall
50 mm soft jointfilled withcompressiblematerial
Blinding
f) New structure isolated from existing buildingfoundations
Damp-proofmembrane
Damp-proofmembrane
RC wall
Concrete foundation
Blinding
Mass concreteAssumed foundationto existing wall
Existingmasonrywall
Longitudinal joint
Outline of columnbase below slab
a) Isolation joint around concrete column: plan
Reinforcedconcrete column
Transverse joint(where provided)
Isolation joint(See SectionA A below)
d) Wall isolation joint
Proprietary joint sealant 20 mm wide
Compressible filler board 20 mm wide
Longitudinal joint
Outline of basebelow slab
b) Isolation joint at steel stanchion: plan
Transverse joint(where provided)
Compressible filler board20 mm wide, joint sealedwith proprietary sealant
Sub-base
c) Section A A
A A
Blinding
Isolation joint
Concrete surround tostanchion baseplateconstructed to finishedfloor level
e) New structure allowed to load existing buildingfoundations
Reinforced concrete
DPC
96
Retaining walls
c) Precast concrete crib wall d) Mass concrete gravity wall
a) Reinforced concrete cantilever wall
Mass concrete
b) Reinforced concrete basement wall
Precast concrete
In-situ concretebase
Large radius bendif required
300 mm widegranular backfill
Weep hole
Drainage pipe
Large radius bendif required
Water-bar
y
d
x
z
y
97
Basement walls
Pile
Pile
Superstructure
Ground floor slabReinforcedconcretecapping beam
Reinforced concretecolumn
Z Z
Contiguouspile wall
Reinforcedconcretebasement wall
Waterproofing to internalor external surface ofbasement wall asrequired
Basement slabIn-situconcreteinfill
Section Z Z
Section Y Y
b) Temporary contiguous pile wall
Superstructure
Ground floor slab
Reinforced concretecolumn
King post
YYReinforced concretebasement wall
Waterproofing to internal orexternal surface of basementwall as required
Basement slab
Precast concretelagging panels
c) Temporary king post wall
Section X X
In-situ concreteSecant pilewall
Connection between basement slaband secant wall if required
a) Secant pile wall used as part of permanent structure
Basement slab
Secant pilewall
In-situ concrete to giveflush surface forwaterproofing system
XX
Superstructure
Ground floor slab
Reinforcedconcreteground beam
98
Waterproofing
150 min sealedoverlap
225 min
Drainage pipe
Concretebase
Sub-base
Fillet
c) Externally applied bitumen sheet tanking
Gradeddrainagematerial
40 space flushedup with mortar
Outerwall
Asphalt
Fillet
50 protective screedon insulating layer
d) Internally applied asphalt tanking:vertical loading with masonry
50 protectivescreedof selected
600 mm zone
Bitumen sheeting
Masonry wall or protectiveboard
In-situconcretewall
Graded drainagematerial
Sub-base
Drainagepipe
Fillet
Blindingconcrete
Externalconcretewall
300 mmzone ofselectedbackfill
DPM applied to innerface of external wall
Concrete floor
Horizontal DPM protectedwith 50 screed
200min
Gradeddrainagematerial
a) Internal damp proof membrane
b) Example of damp proof membrane applied externally
Drainage pipe
600 mm zonebackfilled withselected fill
20 min render mortar
In-situ concrete wall
Masonry wallor protectiveboard
DPM applied tomortar render
In-situ concrete floor
Horizontal DPMprotected with50 screed
Blinding concrete
Sub-base
backfill
DPM
Structural walland floor
Fillet
99
Protection
Fillet
Tanking
Fillet
Isolated pile groups
Stabilising beam
Pile cap
150
Slab reinforcement
Cavity drain formerColumn
Cavity former cutaround columns
Pile
SSLTOC
50
Laid to falls
Drainage gulley
Foundation
Reinforcedconcretewall
b)Junction of floor and wall cavitiy systems
Blockwork wall
ScreedCavity drainage former
a)Cavity system at column position
Screed
100 mm min.
Drainage channel
Reinforced in-situconcrete
Floor finishes
Waterproofrender
Tanked waterproofingsystem
Chamfer at internaland external corners
Blinding
Selected backfill
Graded drainage material
Drainage pipeBlinding
100
Cladding
f) Fixing detail to allow movement
Horizontal restraintbrackets
Horizontal restraintbracket
Steel angle supporting claddingpanel fixed to RC frame
Shims for verticaltolerance
Claddingpanel
Fixing between bracketand RC frame
a) Cladding panel fixed to reinforced concrete upstand b) Precast concrete cladding supported by concrete beam
Precast concretecladding panels
Cladding bracket allowsfor vertical and horizontaladjustment
Cast-in socketwith cross pin(or vertical cast-in channel)
c) Horizontal fixing for precast concrete claddingpanel
RC concrete
e) Cladding bracket with three degrees of adjustment
Cladding bracket
Precast concretecladding panels
Range ofmovement
Serrated face for verticaladjustment
d) Load bearing and horizontal restraint fixingfor precast cladding panels
Expansion anchor or cast-inchannel and serrated cleat,and plate washer for lateraladjustment
RC frame
Precastconcretepanel
Precast concretecladding panel
In-situ concrete frame
Soft joint
Shims
In-situ concrete frame
CladdingpanelCladding bracket
Adjustment
Note: any steel connected to external elements should be galvanised or, more durably, stainless steel.
101
Insulation
Fixing toRC frame
Soft joint
Cavity tray
a) Brickwork supported at floor level
Continuous formedangle brickworksupport system
b) Retained façade
Insulation
Retainedfaçade
Soft joint
In-situ concrete
In-situ concrete
Fixing to frame allowsvertical movement
Tie
(stainless steel)
Lateralrestraintfixing
Tie intobrickwork
Lateralrestraint fixing
Waterstops
Blinding
a) Construction floor jointwith external waterstop
b) Construction wall jointwith external waterstop
c) Construction joint withhydrophilic strip
d) Floor-to-wall joint withexternal waterstop
Recess cast inconcrete
Hydrophilicstrip
InsideOutside
102
Movement joints
Soft joint
Sealant
Sealant
Expansion joint suitablefor traffic
Waterstop
f) Movement joint suitable for trafficc) Partial contraction joint
Waterstop
Joint sealingcompound
Steelcontinuity50%
No concrete continuityand no initial gap
Sealant
e) Movement joint at column location
Soft joint
Reinforcedconcretecolumn
d) Movement joint in a suspended slab with shear transfer
Shear connector
b) Complete contraction joint
Waterstop
Joint sealingcompound
No steelcontinuity
No concrete continuityand no initial gap
Expansion typewaterstop
a) Expansion joint
Initial gap forexpansion
No steelcontinuity
Non-absorbentjoint filterSealing compound
103
Superstructure
New RC slab
Existing column
15 mm soft joint
10 mm steel plate
Plan Section X X
c) Detailing to avoid new slab loading existing column
a) Reinforced beam to column connection b) Transfer beam connection
X X
d) Precast unit supported on in-situ beam (hybrid construction)
Hollowcore unitReinforcement projecting fromin-situ beam bent down intostructural topping
Reinforcement to2 cores per unit
Minimum 100 mmbearing
In-situ beam
Structural topping
New reinforcedconcrete slab
Screed
104
Method statement and programme
(section 2e)
Method statement
General contents of the method statement
■
■
■
■
■
■
■
■
■
■
Detailed considerations
■ work at height
■ excavations confined spaces
■ difficult to handle
■ stability requirements
■ noise
■ vibration
■ groundwater
■ contaminants
■ utility services
■ buoyancy
105
■ adjacent properties
Refurbishment ■
Weight of elements ■
■ lifting equipment
Temporary propping ■
Programme
not
Starton site
Flat slab
Ribbed slab
Waffle slab
One-way slab and band beam
Two-way beam and slab
P/T flat slab
Hybrid beam and slab
Hybrid twin wall
Column/slab construction
Wall/slab construction
Precast crosswall
Tunnel form
Lead-in time (weeks) Speed on site (weeks/1000 m2/crane) 1 1 2 3 423456789101112
If designed by P/T contractor
106
Example programmes
6
5
4
3
2
1
A B C D
E F G H I
7500
750075007500
75007500
750 07500
7500
7500 7500 7500 7500
87654321 161514131211109 20191817 2221
Substructure 8 weeks
Remove topsoil and reduced level dig 2 weeks
Pad foundations 4 weeks
Underslab drainage 3 weeks
Ground floor slab 3 weeks
Site set up 2 weeks
Activity Duration
Superstructure 10 weeks
Walls/columns grd to 1st 3 weeks
1st floor slab 4 weeks
Walls/columns 1st to 2nd 3 weeks
2nd floor slab 4 weeks
Walls/columns 2nd to 3rd 3 weeks
3rd floor slab 3 weeks
Roof upstands and bases 2 weeks
107
Substructure 8 weeks
Remove topsoil and reduced level dig 2 weeks
Pad foundations 4 weeks
Underslab drainage 3 weeks
Ground floor slab 3 weeks
Site set up 2 weeks
Activity Duration
Superstructure 13 weeks
Walls/columns grd to 1st 2 weeks
1st floor RC beams 2 weeks
Walls/columns 1st to 2nd 2 weeks
2nd floor RC beams 2 weeks
Walls/columns 2nd to 3rd 2 weeks
3rd floor RC beams 2 weeks
Roof upstands and bases 2 weeks
87654321 161514131211109 20191817
1st floor PC planks 1 week
2nd floor PC planks 1 week
3rd floor PC planks 1 week
2221
108
Robustness requirements
for precast concrete frames
■
■
■
■
■
Internal ties
Perimeter floor ties(everywhere)
Continuousperipheraltie(s)
Floor ties either uniformalydistributed or collectedat columns
Continuousperipheralgable tie
Continuity tie
Ties anchored intocolumns wherecontinuity cannotbe provided
h
Horizontal ties
■
■
Vertical ties
109
NoteNot suitable for Class 2B and Class 3 buildings in accordancewith Approved Document A [36]
Concrete topping
Precast hollowcoreunit
Support
In-situ concrete
In-situconcrete
110
Gablebeam
In-situconcrete
Floor
slabTie bar
Edge beam
Reinforcement anchoredinto precast columnusing alternatives shownin Figure A.9
Tie bar diameter
In-situ concrete Minimum + 2 + 10 mmHagg
b) Sectiona) Plan
In-situinfill
Projecting barsGable beam
At least one (often two) core(s)opened for approximately 300 m m
Plug in open cores
111
Slot formed in column
Site-placed bars positionedinside projecting loops
Grouted sleeve
Fully anchoredcast-in-socket
Anchor plate
112
Design aids
d
s
s g d
g
d
113
r
r
R r
r
y y
114
r
115
r
116
r
117
0.1250.070 0.070
0.100 0.1000.080 0.025 0.080
0.107 0.071 0.1070.077 0.036 0.036 0.077
0.105 0.079 0.079 0.1050.078 0.033 0.046 0.033 0.078
0.1560.095 0.095
0.125 0.1250.108 0.042 0.108
0.134 0.089 0.1340.104 0.056 0.056 0.104
0.132 0.099 0.099 0.132
0.105 0.051 0.068 0.051 0.105
0.1880.156 0.156
0.150 0.1500.175 0.100 0.175
0.161 0.107 0.161
0.170 0.116 0.116 0.170
0.158 0.118 0.118 0.1580.171 0.112 0.132 0.112 0.171
0.1670.111 0.111
0.133 0.1330.122 0.033 0.122
0.143 0.095 0.1430.119 0.056 0.056 0.119
0.140 0.105 0.105 0.1400.120 0.050 0.061 0.050 0.120 0.144 0.108 0.115 0.108 0.144
0.159 0.148 0.148 0.159
0.143 0.111 0.111 0.1430.160 0.144 0.160
0.144 0.100 0.1440.156 0.156
0.139 0.139
0.167
0.211 0.181 0.191 0.181 0.2110.179 0.167 0.167 0.179
0.210 0.183 0.183 0.2100.181 0.161 0.181
0.213 0.175 0.2130.175 0.175
0.203 0.2030.188
0.135 0.109 0.117 0.109 0.1350.150 0.139 0.139 0.150
0.134 0.111 0.111 0.1340.151 0.134 0.151
0.136 0.104 0.1360.146 0.146
0.129 0.1290.156
0.100 0.079 0.086 0.079 0.1000.120 0.111 0.111 0.120
0.099 0.081 0.081 0.0990.121 0.107 0.121
0.101 0.075 0.1010.117 0.117
0.096 0.0960.125
Uni
form
lydi
stri
bute
d0.
5l0.
5lCo
ncen
trat
edat
mid
span
Conc
entr
ated
atth
ird
poin
ts
118
0.4060.406
0.3750.375
0.6250.625
0.4000.400
0.5000.500
0.6000.600
0.3930.393
0.5360.536
0.4640.464
0.6070.607
0.3950.395
0.5260.526
0.5000.500
0.4740.474
0.6050.605
0.3440.344
0.6560.656
0.3750.375
0.5000.500
0.6250.625
0.3660.366
0.5450.545
0.4550.455
0.6340.634
0.3690.369
0.5320.532
0.5000.500
0.4680.468
0.6310.631
0.3130.313
0.6880.688
0.3500.350
0.5000.500
0.6500.650
0.3390.339
0.5540.554
0.4460.446
0.6610.661
0.3420.342
0.5400.540
0.5000.500
0.4600.460
0.6580.658
0.3330.333
0.6670.667
0.367 0.500 0.6330.633 0.500 0.367
0.357 0.548 0.452 0.6430.643 0.452 0.548 0.357
0.6400.3600.535
0.4650.500
0.5000.465
0.5350.3600.640 0.659 0.602 0.621
0.6210.6310.430 0.6020.631
0.6590.480
0.4290.661
0.6370.595
0.433
0.433
0.5950.6610.429 0.637
0.611
0.611
0.656
0.656
0.4170.417
0.6670.667
0.421 0.647 0.6360.679 0.615 0.636
0.6150.647
0.6790.421
0.4200.681
0.654 0.6070.607 0.654
0.6810.420
0.4250.675
0.6250.625
0.6750.425
0.6880.688
0.6490.649
0.5950.595
0.6140.614
0.6220.622
0.4340.434
0.4330.433
0.6280.628
0.5890.589
0.6510.651
0.4370.437
0.6050.605
0.6460.646
0.4220.422
0.6560.656
0.447 0.598 0.591 0.576 0.6200.620 0.576 0.591 0.598 0.447
0.6210.621
0.571 0.603 0.4460.446 0.5710.603
0.617 0.583 0.4500.6170.5830.450
0.6250.4380.625
0.438
Uni
form
lydi
stri
bute
dTr
iang
ular
lydi
stri
bute
dCo
ncen
trat
edat
mid
span
Conc
entr
ated
atth
ird
poin
ts
119
Moment
Moment
0.277 0.277
0.025 0.223 0.025
2l ll
Shear
0.2230.777 1.000
1.000 0.7770.223
0.311 0.311
0.357 0.186 0.357
2l l 2l
Shear
0.845
1.155
1.1550.5000.500 0.845
0.277 0.2770.109 0.257 0.109
2l ll
0.466 1.000 0.5340.534 1.000 0.466
0.311 0.311
0.373 0.273 0373
2l l 2l
0.864 0.500 1.1361.136 0.500 0.864
Uni
form
lydi
stri
bute
dU
nifo
rmly
dist
ribu
ted
120
c) Beam overhanging one support - concentrated load at end of overhang
R VA A= =Pal
R V VB A B= + = Pl( + )l a
V PB =
M Pamax =
Pa2
3EI( + )l a
Moment
Shear
VA
VB
Mmax
l a
P
CBA
b) Beam overhanging one support - uniformly distributed load on overhang
l a
A BC
VBVA
Shear
Moment
Mmax
R VA A= =
VB= + =
V waB =
Mmax =
wa2
wa3
wa2
wa2l
2
2l(2 )l + a
24EI(4 + 3 )l a
l a
A B C
VB2
VB1
V1
Mhog,max
Msag, max
Moment
Shear
a) Beam overhanging one support - uniformly distributed load
R VA A= = ( )l a2 2
2l
2l
2l
R V VB B 1 B2= + =
w
w
w
( + )l a2
V w aB1 =
VB2 = ( + )l a2 2
Msag, max =
wa2
2
8l2 ( + ) ( )l a l a
2 2
Mhog, max=
dC =
dC =
dC =
wa
24EI(4a l l3 + 3a3)
2 3 3
Loading
Loading
Loading
R VB A
w
121
MA
MA
MB
MB = /4F h1
MB MA
MAMA
MA= /8F h1MA
MA
MD= (2 + ) /8F F h1 2
MDMD
MDMD
MC = ( + ) /4F F h1 2
MC
MCMCMC
MCMC
ME = ( + + ) /4F F F h1 2 3
ME
ME
ME
M F F F hF 1 2 3 = (2 + 2 + ) /8
MFMF
MFMF
2
2
2
2
2
2
b b
h
h
h
F1
F1 + F2
4
4
F1 + F2
4
F1
4
F1
2F1
2
F1 + F2
2
F1
4
b) Forces
F1
F2
F3
F1
4
F1 + F2
4
F1 + F2
4 F1 + F2
2
F1 + +F2 F3
2F1 + +F2 F3
4
4
(3 +2 + )hF1 F2 F3
2b
4
2
c) Moments
0
2
F1 + +F2 F3
4
F4
(3 +2 + )hF1 F2 F3
2b
4
Deflectedshape
Assumed pinconnection
a) Frame and deflections
NoteColumns and beams have equal stiffness
/
F/
F/
F/F/
F/
122
Compression reinforcement required
Key
–– 25 fck
–– 30 fck
–– 35 fck
–– 40 fck
–– 50 fck
0.25
0.20
0.15
0.10
0.05
0.00
0.0 0.5 1.0 1.5 2.0
Compression reinforcement often advised (x/d > 0.45)
z < 0.95d
MEd
/bd2
f ck
100 As/bd
As
b
x
d
123
124
125
1.2
1.1
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
00 0.005 0.010 0.015 0.020 0.025 0.030 0.035 0.040 0.045 0.050
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
Kr = 1
Ratio = 0.5d/h
dh
As fyk/h2fck
NEd
/h2
f ck
MEd /h3fck
126
127
128
References
129
Further reading
■
■
■
■
■
■
■
■
■
■
■
130
Index
131
132
8
10
12
16
20
25
32
40
8
10
12
16
20
25
32
40
8
10
12
16
20
25
32
40
8
10
12
16
20
25
32
40