Concepts for Ultra Wideband Radio Systems
(CUBS)
Steering group kick-off meetingTuesday, Jan. 27, 2004
9.15-11.00CWC, TL246
CUBS Steering group Kick-off meeting, Jan 27, 20042
Agenda1. Opening2. Acceptance of the agenda3. Confirmation of the steering group and nomination of
the steering group chair, vice chair and secretary4. Project organization
- responsible leader, project manager, project secretary - separate tsg, sponsors' tsg members
5. Overall and detailed research plan for 20046. 2004 budget and financing7. Consortium agreement8. Project practices9. FUBS simulator release10.AoB11.Next meeting12.Closing
CUBS Steering group Kick-off meeting, Jan 27, 20043
Nomination of the steering group, chair, vice chair and
secretary• Proposal for SG members
– Defence Forces: Heikki Rantanen (chair), Tuomo Reili
– Elektrobit: Petteri Heino (vice chair), • Tommi Jämsä (deputy SG member)
– Tekes: Kari Markus – CWC: Ian Oppermann, Jari Iinatti
secretary: Matti Hämäläinen
CUBS Steering group Kick-off meeting, Jan 27, 20044
Project organization
Proposal
• Responsible leader: prof. Jari Iinatti• Project manager: Lich.Tech. Matti
Hämäläinen• Project secretary: M.Sc. Raffaello Tesi
CUBS Steering group Kick-off meeting, Jan 27, 20045
Overall and detailed research plan for 2004
• CUBS extends the research started in FUBS with – old work packages– new work packages– application of interest: military sensor network
• Planned to last three years (2004-2006)• Goal: demonstrate UWB sensor network
operation at the end of 2006• Currently, the funding is approved only for 2004
CUBS Steering group Kick-off meeting, Jan 27, 20046
• During 2004, the preliminary research work for sensor network demonstration will be carried out by CWC
• At 2005, a subcontractor will be involved to the project– hardware design and implementation– PJMicrowave is the most probable
candidate to be a subcontractor due to the good co-operation in FUBS
CUBS Steering group Kick-off meeting, Jan 27, 20047
Work packages• WP1: Multiband UWB system
– In FUBS only single-band UWB concepts have been studied
– IEEE802.15.3 promoted MB-UWB for high data rate applications
– Performance with interference in AWGN and real channels
• Models based on FUBS can be used
– Schedule: months I-XII– Work amount: 15 mm– Output: journal paper, two conference
papers
CUBS Steering group Kick-off meeting, Jan 27, 20048
• WP2: Single band UWB systems – the original UWB PHY approach– continues the work started in FUBS– simpler and more cost effective than
MB-UWB
– Schedule: months I-XII– Work amount: 13 mm– Output: journal paper, two conference
papers, two M.Sc. Thesis (channel modeling)
CUBS Steering group Kick-off meeting, Jan 27, 20049
• WP3: UWB sensor networks– LPD/LPI capable military sensor network concept– low power consumption, low PSD– aiming for demonstrator at 2006
• T-MIL: Requirement specification for the future UWB sensor communication development to be carried out on 2005-2006. (2 mm)
• T-LOC: Development of UWB based location algorithm for sensor network (7 mm)
• T-POW: Power efficient communication protocols
(8 mm)
– Schedule: months I-XII – Work amount: 17 mm– Output: journal paper, two conference papers
CUBS Steering group Kick-off meeting, Jan 27, 200410
• WP4: Co-existence – using the second generation UWB
transmitters• FCC capable• adjustable PRF and TX power• bipolar pulses, Tp is about 200 ps
– Schedule: months I-XII– Work amount: 8 mm– Output: one journal paper, one
conference paper
CUBS Steering group Kick-off meeting, Jan 27, 200411
• WP5: Capacity – single band and multi-band UWB – information theoretic approach
– Schedule: months I-XII– Work amount: 6 mm– Output: 1 journal paper, 1 conference
paper
• Administration: 1 mm
CUBS Steering group Kick-off meeting, Jan 27, 200412
• Channel modelling– hospital– forest
• supplementary path loss measurements
– do we need?– own WP or to be included in existing
WP?– man months need to be transferred
from somewhere else
CUBS Steering group Kick-off meeting, Jan 27, 200413
2004 budget and financing
BUDGET
Labour costs (60 mm) 145.678,00 €Side costs (68%) 93.234,00 €Total 238.912,00 € 238.912,00 €
Overhead (75.1%) 179.422,00 €Equipments and software 5.000,00 €Travel costs 10.000,00 €TOTAL BUDGET 433.334,00 €
CUBS Steering group Kick-off meeting, Jan 27, 200414
Financing for 2004Tekes (60%) 260.000,00 € 260.000,00 €Industrial partners (40%) 173.334,00 €
CWC (15,4%) 66.667,00 €
Elektrobit (9,2%) 40.000,00 €
Defence Forces (15,4%) 66.667,00 € TOTAL: 433.334,00 € 433.334,00 €
CUBS Steering group Kick-off meeting, Jan 27, 200415
Consortium agreement• University has a new contract form for
Tekes projects
CUBS Steering group Kick-off meeting, Jan 27, 200416
Project practices• Do we separate the steering group and the
technical group meetings?• Regularity• Secured directory for information dissemination
– http://www.cwc.oulu.fi/cubs– login: cubs– password:– includes:
• plans• documents• publications• admin documents• meeting slides, minutes• etc.
CUBS Steering group Kick-off meeting, Jan 27, 200417
• FUBS simulator
• AoB
• Next meeting