Concept Design- Gavin Orton, MADE City Builder Academy 2013

61
BPN ARCHITECTS GAVIN ORTON

Transcript of Concept Design- Gavin Orton, MADE City Builder Academy 2013

BPN ARCHITECTSGAVIN ORTON

DARTMOUTH PARK PAVILIONPROJECT OVERVIEW

1. Brief development2. Concept Design3. Developed Design4. Technical Design5. Construction6. Post-construction

1. BRIEF DEVELOPMENT

The local community including residents, schools, groups and organisations

2. CONCEPT DESIGN

“Pythagoras of Samos was the first to fashion the letter Y into a pattern of human life. The straight portion at the bottom signifies the first, uncertain age, which at that point has been given over neither vices nor virtues. The bifurcation at the top, however, begins at adolescence. The path to the right is difficult, but it tends toward a blessed life. The path to the left is easier, but leads to ruin and destruction.”

Isidore of Serville (c.560-636 CE)

The Choice of Hercules

“…on the verge of manhood, he is contemplating his future when two women appear to him.

One, Vice, eager and seductive, shows him a path which seems to offer easy progress to a life of indolent pleasure. The other, tall and beautiful and identified as Virtue, warns Hercules that what is truly good can only be obtained through hard effort; and only then can Hercules gain supreme glory.”

the programme

the woodland walk

the woodland walk

the woodland walk

the tree house

the tree house

3. DETAILED DESIGN

4. TECHNICAL DESIGN

04

161.200

S07

toiletsrefer to drawing 1770.2001 for details 160.200

t

fold

dow

nba

by c

hang

e

wash basinSD

Disabled W.C. (left handarrangement) / Baby

Change

Male W.C.

SD SD

light well over

communal wash area

HD

t

t

t

FemaleW.C.

100 2000 100 925

1690100 778

1000

100

100

900

100

bins / storage / plant

events roomrefer to drawing 1770.2038 for details

conc

eale

d dr

op d

own

proj

ectio

n sc

reen

disabledW.C.

(right hand arrangementN13/311)

store

store

boiler

vendingmachine

vendingmachine

power & mainsdrinking watersupply required forvending machines

roller shutterelectrical

equipment store

LANDING160.200

159.500

ramp 1 : 20500mm rise

159.520

S06

officerefer to drawing 1770.2036 for detailssnack bar

refer to drawing 1770.2035 for details

wall

mou

nted

tv

S05

foyer

additional storage above vending machines

void area underramp

ramp 1 : 20500mm rise

ramp 1 : 15330mm rise

ramp 1 : 15330mm rise

161.200159.500

159.500

160.200

160.050

161.200

projector recessed within suspended ceiling

wall mounted display cabinet

timberbench

Office a/c unitSnack Bar a/c unit Events room a/c unit

basinN13/331a

ENTRANCE LEVEL159.500

'slot

ted'

dra

inag

e ch

anne

ls in

floo

r. Ar

mte

c or

sim

ilar a

ppro

ved

beam and blockfloor construction

spaced to allow fordrainage channel

'slot

ted'

dra

inag

e ch

anne

l in fl

oor.

Arm

ocHe

x Dr

ain

or s

imila

r app

rove

d

RWP

AAV

SVP

SVP

SVP

RWP

1022.5

S04

159.500

HD

staff roomrefer to drawing 1770.2037 for details

stai

nles

s st

eel

mes

h to

clo

se o

ffvo

id a

rea

unde

rra

mp

D03(FD30s)

D04

D05(FD30s)

D06

D08(FD60s)

D09

D10

D11

D12

D13

D14(FD30s)

D15

D16

D17

D18(FD30s)

D19

W01

W03

W04

W05

W06

S01

S02S03

W02

Handrail centrallylocated on stair to

divide width

Cleaner'sstore

store

D07

RWP

W01

w.c., shower andstaff changing area

t

SVP RWP

D01(FD30s)

D02

4no. lockers

HD

high

leve

l she

lving

powe

r soc

kets

abo

ve d

esk

heig

ht

power sockets above desk height

plasterboard on timber battens with a skim coat and paint finish

stackable chair store

D20b D20a

stackable chair store

LANDING159.710

ramp 1 : 20210mm rise

ramp 1 : 20210mm rise

LANDING159.990 ramp 1 : 20

280mm rise

4 steps@170mm/rise

LANDING161.200

LANDING161.530

LANDING160.700

161.530

10 no. secure cycle spaces

refer to bpn drawing 1770.2058

dashed line indicates external trunking above

dashed line indicates external trunking above

2485 2000 2000 2000 2000 2000 2500 1700 2000 2000 2100

2100

2000

2100

1000

2000

2260

1000

2000

2000

1000

2000

2100

2100

2000

2000

2000

2000

2000

2000

2100

2100

2000

1300

2000

303

2000

1227.5

2485

3590

1585

1418

1115 1810 3497.5

5045

2300

1022.5

2915

1565 1585 2710

1902.5

4195

1810

2240

9091585

4000

10000

2000

5000

1585

2018

4715

49404397.51002.5

1115

1810

1340

3160

1564

.910

22.5

9658

7179

.5

175

3035

2270

3610

3

2

1

A CB D

826160504290

10340

1782

1810

2

10.0

A

B

A

B

4

C

C

Facing brickworkF10/110, F10/110a

BlockworkF10/355

Softwood vertical timber board (100mm) lining with paint finishK21/160

FP

FP

FP

FB

FP

FP

FB

Fire point stand with 2.5kg carbon dioxide & 9 litre water and fire proceedure signage over

Fire blanket fitted to wall and fire proceedure signage over

brya

ntpr

iest

new

man

©. Do not scale off drawing. Check all dimensions on site and advise any discrepancies before commencing work. All figured dimensions are millimetres unless otherwise stated. Location plans subject to © Crown Copyright. dr = drawn by, ch = checked by

b r y a n t p r i e s t n e w m a n l t da r c h i t e c t s 3 m a r y s t r e e tb i r m i n g h a m B 3 1 U Dt : 0 1 2 1 2 3 3 1 8 1 8 f : 0 1 2 1 2 3 3 1 1 1 8w w w . b r y a n t p r i e s t n e w m a n . c o mm a i l @ b r y a n t p r i e s t n e w m a n . c o m

1:50 @A11:100@A3

C10drawing revision

scale date

revisions drawn by

checked by

Dartmouth Park Community Pavilion - West Bromwich

Ground Floor Plan

1770.1001

10.09

TD

LP

C1 - Construction issue - 110118 (dr TD/ch RS) C2 - Revisions as indicated - 110204 (dr GO/ch RS)C3 - Revisions as indicated + timber cladding profiles indicated - 110304 (dr MC/ch RS)C4 - Revisions as indicated - 110404 (dr MC/ch RS)

C5 - Revisions as indicated - 110608 (dr MC/ch RS)C6 - Revisions as indicated - 110614 (dr MC/ch RS)C7 - Revisions as indicated - 110616 (dr MC/ch RS)C8 - Revisions as indicated - 110819 (dr MC/ch RS)

C9 - Revisions as indicated - 110608 (dr MC/ch RS)C10 - FINAL CONSTRUCTION ISSUE - 111028

02

04

04

04

04

05

03

03

03

Identified construction hazard

01. Working within a park enviroment which will be partially open to the public.

Risk

Members of the public and particularly children moving in close proximity to site, and potentially attempting to enter site itself. Dangers associated with moving materials through populated park environment.

Potential construction hazards identified by Architect

02. It is understood that the remains of a former park pavilion building may be located below ground level on the site.

The full extent of this is unknown, There is a also a slight risk that there are old basements from the building and possibly services infastructure

Guidance

Risk assessment to be undertaken by contractor to establish safe strategy for securing site and transporting materials from the road to the site. Strategy to be developed and coordinated with wider park regeneration and SMBC Park's Manager.

Due care and attention to be paid whilst initial excavation works are carried out.

03. Handling and fixing of steel structure to tower, large lintels and steel beams. Risk of steel falling. Risks associated with working at height. Safe working procedures, exclsuion zones and risk assessments to be in place

04. Handling and fixing of large timber elements to ramped walkway that can not be safely carried / fixed by one indivdual. Also fixing of oversized timber elements at height.

Risk of timber falling, injuries due to carrying heavy items. Risk of falling from height.

05. Handling of large beam and block floor elements. Risk of large items falling and injuring construction workers.

06. Working in close proximity to existing trees. Restricted crane access/maneuverability due to proximity of trees, danger of collision with tree canopies.

Adequate protection of tree canopies and work to be carried out in accordance with BS 5837Debris falling from trees onto site.

07. Handling and fixing of large timber cladding elements to tower at height Risk of construction workers and/or large timbers falliing .

Risk assessments and method statement to the erectling of large timber section to ensure safe handling by operates within permissible manual handling limits

Ensure operatve have adequate PPE and appropriate working methods to protect against falling / injury

Risk assessments and method statement to the erectling of large timber section to ensure safe handling by operates within permissible manual handling limits. Timber to be designed to allow cranage where necessary

REFER TO EXTERNAL WORKS DRAWING 1770.1000 FOR DETAILS OF TERRACE AREA

REFER TO EXTERNAL WORKS DRAWING 1770.1000 FOR DETAILS OF ENTRANCE AREA

N

brya

ntpr

iest

new

man

©. Do not scale off drawing. Check all dimensions on site and advise any discrepancies before commencing work. All figured dimensions are millimetres unless otherwise stated. Location plans subject to © Crown Copyright. dr = drawn by, ch = checked by

b r y a n t p r i e s t n e w m a n l t da r c h i t e c t s 3 m a r y s t r e e tb i r m i n g h a m B 3 1 U Dt : 0 1 2 1 2 3 3 1 8 1 8 f : 0 1 2 1 2 3 3 1 1 1 8w w w . b r y a n t p r i e s t n e w m a n . c o mm a i l @ b r y a n t p r i e s t n e w m a n . c o m

1:50 @A11:100 @A3

C5drawing revision

scale date

revisions drawn by

checked by

Dartmouth Park Community Pavilion - West Bromwich

Section A-A

1770.1010

10.09

RS

LP

C1 - Construction issue - 110118 (dr TD / ch RS)C2 - General revisions throughout - 110304 (dr MC / ch RS)C3 - Revisions as indicated - 110314 (dr MC / ch RS)C4 - Revisions as indicated + detail removed from internal elevations to avoid confilcting information - 110408 (dr MC / ch RS)

C5 - FINAL CONSTRUCTION ISSUE - 111028

1st FFL 162.580(TOS 162.540)

2nd FFL 164.880(TOS 164.840)

3rd FFL 167.180 (TOS 167.140)

4th FFL 169.480(TOS 169.440)

159.500 entrance

3080

2300

2300

2300

1800

160.200 entrance landing

161.200 events space

171.280

161.200 161.200

161.950

163.460

165.325

164.805

timber cladding not shown for clarity. For timber cladding setting out see BPN drawings 1770.2021-2027

events roomfor details see BPN drawing 1770.2038

3225

159.500

160.560

161.910

163.700

162.580

2625

2625

159.500

'woodland walk'for cladding details see BPN drawing 1770.2020

snack barfor details see BPN drawing 1770.2035

officefor details see BPN drawing 1770.2036

'woodland walk'

160.1375

150

125

100

120

13

Aluminium coping

150mm minimum upstand above sedum to the underside of the aluminium coping

insulated cavity closer to the top of all cavity walls

12.5 mm plasterboard / acoustic plasterboard with taped and filled joints on metal frame system to create a 120mm service void for small power and small bore piped services and to enable linear light fittings to be recessed - refer to ceiling plan for detail of plaster finishes

concrete plank roof

plaster, skim coat and paint finish to walls

window frames - refer to separate window schedule for details

door, frame and architraves

Concrete plank roof

Cavity trays preformed cavity tray to the perimeter of the roof terrace - see adjacent specification

300

cavity insulation to overlap roof insulation by a minimum 300mm to minimise cold bridging

300

Metal deck to terrace - fixing details to be confirmed

ground bearing slab to structural engineers details

Hyload Original damp proof course at finished floor level and a minimum 150mm above adjoining ground level - DPC to inner leaf to be lapped and continuously sealed to below slab DPM

concrete cavity fill up to ground level and with 150mm of slab level

150

25mm thick perimeter insulationto the edge of the slab to minimise cold bridging

softwood vertical boarding with a painted finish on 25mm timber horizontal battens at max 400mm centres fixed to inner leaf of blockwork

Metal deck to roof terrace - fixing details to be confirmed

102 100 102

toiletsrefer to drawing 1770.2001 for details 160.200

t

fold

dow

nba

by c

hang

e

wash basin

SD

Cleaner'sstoreDisabled W.C. (left hand

arrangement) / BabyChange

Male W.C.

SD SD

light well over

communal wash area

HD

t

t

t

FemaleW.C.

100 100

100

100

100

100

basin

bins / storage / plant

events roomrefer to drawing 1770.2038 for details

conc

eale

d dr

op d

own

proj

ectio

n sc

reen

disabledW.C.

(right hand arrangementN13/311 )

store

store

boile

r

store

large vendingmachine700x920mm

large vendingmachine700x920mm

power & mainsdrinking watersupply required forvending machinesroller shutter

electricalequipment store

LANDING160.200

159.500

ramp 1 : 20500mm rise

159.520

S06

officerefer to drawing 1770.2036 for detailssnack bar

refer to drawing 1770.2035 for details

S05

foyer

timber bench

void area underramp

ramp 1 : 20500mm rise

ramp 1 : 15330mm rise

ramp 1 : 15330mm rise

161.200159.500

159.500

160.200

160.050

159.990

161.200161.200

6 steps@167mm/rise

stackable chair store

projector recessed within suspended ceiling

S07

timberbench

timberbench

Office a/c unitSnack Bar a/c unit Events room a/c unit

ENTRANCE LEVEL159.500

'slot

ted'

dra

inage

cha

nnel

s in

floo

r. Ar

mte

c or

sim

ilar a

ppro

ved

'slot

ted'

dra

inage

cha

nnel

in fl

oor.

Arm

tec

or s

imila

r app

rove

d

RWP

AAV

SVP

SVP

SVP

RWP

RWP

S04

159.500

raised section of timber bench to form back rest

HD

w.c., shower andstaff changing area

staff roomrefer to drawing 1770.2037 for details

t

SVP RWP

stai

nles

s st

eel

mes

h to

clo

se o

ffvo

id a

rea

unde

rra

mp

D01

D02

D03

D04

D05

D06

D07(FD30s)

D08

D09

D10

D11

D12

D13

D14(FD30s)

D15(FD30s)

D16

D17

D18

D19

D20

W01

W03

W04

W05

W06

S01

S02S03

W02

4no. lockers

LANDING159.710

ramp 1 : 20210mm rise

ramp 1 : 20210mm rise

LANDING159.990 ramp 1 : 20

280mm rise

4 steps@170mm/rise

LANDING161.200

LANDING161.530

LANDING160.700

161.530

2485

2000

9658

7179

.5A

B

A

BE E

C

C

D

D

Section A-A

Preformed weep holes

Beak weep by Cavity Trays of Yeovil, Somerset, BA22 8HU. (01935 474769). Build into perp joints over lintels, trays and DPCs at 450mm centres.

Installation/site work - Position in perp on DPC, in accordance with manufacturers instructions. Spacing at 450mm centres in accordance with NHBC andBRE recommendations.

Cavity Trays

Type P cavitray from Cavity Trays of Yeovil, Somerset. BA228HU (01935) 474769. Lay preformed Type P parapet cavitray lengths and angles within appropriate mortar bed as work proceeds.

Glove lap and seal adjoining lengths. Incorporate roof lead flashing to detail. Observe accompanying fitting instructions at all times.

Apron flashings

Ubiflex non-lead flashing by Ubbink (UK) Ltd. Borough Road, Brackley, Northants NN13 7TB Tel: 0845 456 3499

When installing with DPC / Cavity Tray Ubiflex should be installed at the same time, the Ubiflex should be fitted to a depth of not less than 50mm with the edge turned back into a single welt to anchor it into the mortar. Ubiflex should then be held in place with Ubiflex fixing clips, spaced not more than 450mm apart and then the joint filled with Ubiflex Gap-Seal

Ubiflex should cover the upstand by at least 75mm and be sealed to it with a continuous bead of High-Tack sealant. The height of the upstand should be at least 150mm. Overlap joints of 150mm are required in all flashings and must be sealed with Ubiflex High-Tack.

steel angle with pre-drilled holes (85mm centres) fixed back to UB to S.E. specification

steel angle with pre-drilled holes (85mm centres) fixed back to UB to S.E. specification

position of metal floor planks where appropriate

Steelwork to S.E. details

Oak cladding piece coach bolted back to steel angles

Oak cladding piece coach bolted back to steel angles

SECTION 1

steel angle with pre-drilled holes (85mm centres) fixed back to UB to S.E. specification

steel angle with pre-drilled holes (85mm centres) fixed back to UB to S.E. specification

position of metal floor planks where appropriate

Steelwork to S.E. details

Oak cladding piece coach bolted back to steel angles

Oak cladding piece coach bolted back to steel angles

SECTION 2

162.580 First floor terrace

164.880 Second floor

167.180 Third floor

169.480 Fourth floor

thick line denoting parapet / roof level of brick accomodation blocks below

Detail 2

Detail 1

thick line denoting parapet / roof level of brick accomodation blocks below

14270

6250

875

2290

3065

8260

1655

2290

2290

1990

Feature graphics stained onto timber

S12

brick pavers

Timber deck laid onto brick plinth

159.500t e r r a c e ramped

d o w n to meet path

t e r r a c e level withg rass

159.500

160.315

159.650

159.800

159.950

160.150

Timber decked seating area

timber decked terrace

Brick pavers to match foyer

toilets160.200

fold

do

wn

baby

ch

ange

w a s h basin

S D

Cleaner 'ss t o r eD i s a b l e d W.C. (left hand

a r rangemen t ) / BabyC h a n g e

Male W. C.

S D S D

roof l ighto v e r

c o m m u n a l wash area HD

bin &storagea b o v e

t

t

t

Fema leW. C.

1 0 0 2 0 0 0 1 0 0 9 2 5

1 6 9 01 0 0 7 7 8

1 0 0 0

100

1 0 0

1300

1 0 0

b a s i n

bins / storage / plant

events room

conc

eale

d dr

op

dow

n pr

ojec

tion

scre

en

t i m b e r bench seating around perimeter

d isabled W. C.( r i g h t hand

a r rangemen t )

s t o r e

s t o r e

boi ler

s t o r e

l a r g e vendingmach ine7 0 0 x 9 2 0 m m

l a r g e vendingmach ine7 0 0 x 9 2 0 m m

p o w e r & ma insd r i n k i n g watersupp ly required forv e n d i n g machinesr o l l e r shutter

e lec t r ica le q u i p m e n t store

LANDING160.200

159.500

ramp 1 : 20500mm rise

159.520

p ivo ted oak doort o match timber

s c r e e n

o a k door to matcht i m b e r screen

office

snack bar hi g

h le

vel

shel

ving

ba

r co

unte

r

b in /c leaning

storage

hig

h le

vel

coun

ter

with

sh

elvi

ng wal

l /

cupb

oard

do

ors

with

m

agne

tic w

hite

bo

ard

finis

h

wal

lm

o un t

e d tv

d i s h w a s h e r

wal

l m

ount

ed

i ns e

c t k

iller

hand-w a s h

stor

age

/c o

a ts

etc

s torage

CC

TV

mon

itors

po

we

r so

cket

s ab

ove

tab l

e he

ight

s a f e withshelvesa b o v e

ga l van i sedsteel

s e c u r i t ys c r e e n

s t a b l e door

ga l van i sedsteel

s e c u r i t ys c r e e n

foyer

b e n c h &c o a t

h o o k s

b a s i na n d

m i r r o r

tea po in t

fullh e i g h tl o c k e r

fullh e i g h tl o c k e r

fullh e i g h tl o c k e r

2 x halfh e i g h tl ocke rs

fr idge

storage

storage

b i n s /c leaning

c o a th o o k sf o r wet

c l o t hes /boo t s

w . c. and staffchang ing area

staff room

b e n c h

add i t i ona l storage above vending machines

t i m b e r bench / display unit

v o i d area underr a m p

ramp 1 : 20500mm rise

ramp 1 : 1 5330mm rise

ramp 1 : 1 5330mm rise

161.200

159.500159.500

159.500

160.200

160.050 159.990

tim

ber

benc

h se

a tin

g ar

o und

pe

rimet

er

161.200161.200

6 steps @ 167mm/rise

s t a c k a b l e chair store

ed

ge

of

boxe

d ou

t be

am

ove r

head

p r o j ec to r r ecessed within suspended ce i l ing

l o w e r timber bench / step

+ 5 0 0 m m

+ 2 5 0 m m

steel security gate

fridge

hot dr inksm a k e r

ch i l ledd i s p l a ycab ine t withstorageb e l o w

storageb e l o wcounter

cash register

a c c e s s

mic

ro- w

av e

g lazed display cabinetb u i l t into wall

slid

ing

win

dow

s l id ing window

t i m b e rb e n c h

t i m b e rb e n c h

O f fi c e a/c unitS n a c k Bar a/c unit E v e n t s room a/c unit

drai

nage

ch

anne

l in

floo

r be

l ow

pivo

ted

door

d r a i n a g e channel in floor

b a s i n

t i m b e rb e n c h

t i m b e rb e n c h

ENTRANCE LEVEL159.500

LANDING159.710

ramp 1 : 20210mm rise

ramp 1 : 20210mm rise

LANDING159.990 ramp 1 : 20

280mm rise

4 steps @ 170mm/rise

LANDING161.200

LANDING161.530

LANDING160.700

161.530

brya

ntpr

iest

new

man

©. Do not scale off drawing. Check all dimensions on site and advise any discrepancies before commencing work. All figured dimensions are millimetres unless otherwise stated. Location plans subject to © Crown Copyright. dr = drawn by, ch = checked by

b r y a n t p r i e s t n e w m a n l t da r c h i t e c t s 3 m a r y s t r e e tb i r m i n g h a m B 3 1 U Dt : 0 1 2 1 2 3 3 1 8 1 8 f : 0 1 2 1 2 3 3 1 1 1 8w w w . b r y a n t p r i e s t n e w m a n . c o mm a i l @ b r y a n t p r i e s t n e w m a n . c o m

1:25 @A11:50 @A3

C5drawing revision

scale date

revisions drawn by

checked by

Dartmouth Park Community Pavilion - West Bromwich 1770.2025

07.10

TD

LPWest Tower Elevation Cladding

C1 - Construction issue - 110118 (dr TD / ch RS)C2 - Revisions as indicated + cladding quantities and spacing revised - 110304 (dr MC / ch RS)C3 - Revisions as indicated + painted feature graphics removed - 110613 (dr MC / ch RS)C4 - Revisions as indicated - 110617 (dr MC / ch RS)

C5 - FINAL CONSTRUCTION ISSUE - 111028

Typical fixing detail 1 Scale: 1:10

West Elevation Tower Cladding

Typical fixing detail 2Scale: 1:10

'STACKED' CONDITION 'OVERLAP' CONDITION

Notes:

Refer to BPN drawing 1770.2020 for further details of timber screen

KEY TO TIMBER CLADDING

NOTE:

Any treated surfaces of large section timbers exposed by unavoidable cross cutting should be liberally brushed with ENSELE end grain preservative solution.

Oak cladding element. 100mm (D) x 75mm (W) x as drawn (H).

Oak cladding element. 75mm (D) x 75mm (W) x as drawn (H).

Oak cladding element. 50mm (D) x 75mm (W) x as drawn (H).

ALL TIMBER CLADDING TO TOWER TO BE GREEN OAK WITH NO FIRE PROTECTION TREATMENT

FINAL CONSTRUCTION ISSUE

Wall Finishes

Exposed blockwork with masonry paint finish - paint colour tbc (F10/355) Exposed brickwork (F10/110) T&G, square edge, softwood lining with 'Arch Chemicals' - 'Dricon' fire retardency

and eggshell paint finish - paint colour tbc Plasterboard, skim and paint - paint colour tbc

Floor Finishes

Brick pavers (F10/110a)

Marmoleum (Product: Walton uni or cirrus range, 2m sheets with welded joints)

400

2500

boiler to mechanical engineers spec

wall mounted fold down baby change unit

brickwork beyond

blockwork beyond

Female W.C.

Disabled W.C.

Male W.C.

Store

exposed blockwork walls to be painted

Gyproc Wallboard on MF system with a clear service void above.

brickwork beyond brickwork beyondFemale W.C.

Male W.C.

Store

1960

100

D08 D10

SD SD SD

brickwork beyond brickwork beyond

blockwork beyond

Wash area

recess in suspended ceiling with feature lighting (detail tbc)

800

275

D10 D08

painted softwood lining

painted softwood lining

TP

ARPTSDHD2500

brickwork beyond

blockwork beyond

Disabled W.C.

Gyproc Wallboard on MF system with a clear service void above

painted softwood lining

brickwork beyond

blockwork beyond

Male W.C.Wash area

painted softwood lining

TP

AR PT SD HD

blockwork beyond

Female W.C.

Disabled W.C.

exposed blockwork walls to be painted

D11D12D13

100mm marmoleum upstand

2400

service void

HD HD

blockwork beyond

Male W.C. Wash area

recess in suspended ceiling with feature lighting

2135

1100

800

2500

painted softwood lining

Disabled W.C.

exposed blockwork walls to be painted

Gyproc Wallboard on MF system with 120mm clear void above to allow for services and light fittings.

light well over

communal wash area

disabledW.C.

(right hand arrangement

N13/311) store

boiler

Office a/c unitSnack Bar a/c unit Events room a/c unit

SVP

RWP

RWP

D16

Cleaner'sstore

FemaleW.C.

toilets

t

fold

dow

nba

by c

hang

e

wash basinSD

Disabled W.C. (left handarrangement) / Baby

Change

Male W.C.

SD SD

t

t

t

2000 100

925 1687 100 778100

889

100

D8

D9

D10

D11

D12

D13

410

488

HD

HD

1000

2300

100 2077 128 900

1120

1695

705103036418201000

100

753

100

753

100

753

100

322

100

753

709

359

2200

925

1285

BoilerRoom

1498

1285

2200

600x600access hatch

600x600access hatch

150

150

==

600

B

AA

B

C

C

DD

E

E

F F

GG

H

H

brya

ntpr

iest

new

man

©. Do not scale off drawing. Check all dimensions on site and advise any discrepancies before commencing work. All figured dimensions are millimetres unless otherwise stated. Location plans subject to © Crown Copyright. dr = drawn by, ch = checked by

b r y a n t p r i e s t n e w m a n l t da r c h i t e c t s 3 m a r y s t r e e tb i r m i n g h a m B 3 1 U Dt : 0 1 2 1 2 3 3 1 8 1 8 f : 0 1 2 1 2 3 3 1 1 1 8w w w . b r y a n t p r i e s t n e w m a n . c o mm a i l @ b r y a n t p r i e s t n e w m a n . c o m1:50 @A1

C6drawing revision

scale date

revisions drawn by

checked by

Dartmouth Park Community Pavilion - West Bromwich

Toilet Details - Plan / Elevation

1770.2001

07.04.10

MC

LP

C1 - Construction issue - 110118 (dr TD / ch RS)C2 - General revisions - 110404 (dr MC / ch LP)C3 - General revisions - 110613 (dr MC / ch LP)C4 - Dimensions added to toilet layout - 110803 (dr GO / ch LP)

C5 - Access hatch shown on plan - 110819 (dr MC / ch LP)C6 - FINAL CONSTRUCTION ISSUE - 111028

Elevation A Elevation B Elevation C

Elevation D Elevation E Elevation F

Elevation G Elevation H

Toilet roll dispenser:to Williams Ironmongery schedule

Coat hook:to Williams Ironmongery schedule

Room / Fitting

Male WC

Female WC

WCs Washbasins

Wall mounted urinal by Armitage Shanks from the Contour range or similarN13/315a

Urinals

N/A

Wall mounted WC by Armitage Shanks from the Braemar range or similar. Colour: WhiteN13/300b

Taps

Wall mounted WC by Armitage Shanks from the Braemar range or similar. Colour: WhiteN13/300b

N/A

Accessories

N/A

N/A

Wall mounted stainless steel wash trough.N13/346

Hand washarea

N/AN/A Contour 21 Basin mixer by Armitage Shanks.

Soap dispenser:to Williams Ironmongery schedule

Semi recesssed Velocity high speed hot air hand dryer by Dolphin - satin stainless steelN13/472a

N/A Toilet roll dispenser:to Williams Ironmongery schedule

Coat hook:to Williams Ironmongery schedule

Standard doc M packN13/311

Disabled WC N/AStandard doc M packN13/311

Standard doc M packN13/311

Standard doc M packN13/311

Baby changing unitN13/449a

Armitage Shanks 310mm Alder sinkN13/331a

Cleaners Store N/AN/A N/A N/A

IPS

Armitage Venesta Tough Wall system with solid laminate access panels

Armitage Venesta Tough Wall system with solid laminate access panels

N/A

N/A

N/A

light well over

communal wash area

disabledW.C.

(right hand arrangement

N13/311) store

boiler

Office a/c unitSnack Bar a/c unit Events room a/c unit

SVP

RWP

RWP

D16

Cleaner'sstore

FemaleW.C.

toilets

t

fold

dow

nba

by c

hang

e

wash basinSD

Disabled W.C. (left handarrangement) / Baby

Change

Male W.C.

SD SD

t

t

t

2000 100

925 1687 100 778100

889

100

D8

D9

D10

D11

D12

D13

410

488

HD

HD

1000

2300

100 2077 128 900

1120

1695

705103036418201000

100

753

100

753

100

753

100

322

100

753

709

359

2200

925

1285

BoilerRoom

1498

1285

2200

600x600access hatch

600x600access hatch

150

150

==

600

10010

10010

Timber lining details1:5

MF suspended ceiling

stud wall

T&G square edge softwood lining with paint finish

stud wall fixed through DPM

10mm shadow gap to top and bottom of lining

10mm shadow gap to top and bottom of lining

brya

ntpr

iest

new

man

©. Do not scale off drawing. Check all dimensions on site and advise any discrepancies before commencing work. All figured dimensions are millimetres unless otherwise stated. Location plans subject to © Crown Copyright. dr = drawn by, ch = checked by

C1 - Initial construction issue - 110805C2 - Revisions as indicated - 111017C3 - FINAL CONSTRUCTION ISSUE - 111028

b r y a n t p r i e s t n e w m a n l t da r c h i t e c t s 3 m a r y s t r e e tb i r m i n g h a m B 3 1 U Dt : 0 1 2 1 2 3 3 1 8 1 8 f : 0 1 2 1 2 3 3 1 1 1 8w w w . b r y a n t p r i e s t n e w m a n . c o mm a i l @ b r y a n t p r i e s t n e w m a n . c o m

DARTMOUTH PARK PAVILION | WEST BROMWICH

1:25 @ A3

1770.2058

06.2011

MC

GOFOYER STAIT BALUSTRADE DETAIL

C3drawing revision

scale date

revisions drawn by

checked by

1290300

handrail to have 300mm minimum overun

SHS post to SE specification

Galvanised steel plate

18x150 oak patress following gradient of stair

75x75 green oak sections @ 140mm centres fixed to internal face of galvanised plate

10mm galvanised string at handrail level to SE specification

Galvanised steel plate fixed concrete sub base (to SE details) before brick pavers are laid over

75x75mm timber sections

Galvanised steel plate

timber handrail fixed to 18x150mm oak patress

Steel column

Galvanised steel plate fixed concrete sub base (to SE details) before brick pavers are laid over

251150

75x75mm hollow steel section

TYPICAL ELEVATION A

TYPICAL ELEVATION B

PLAN

primary structure timber cladding

timber handrail

1150

950

EXPLODED AXONOMETRIC

5. CONSTRUCTION

6. POST-CONSTRUCTION

BPN ARCHITECTSGAVIN ORTON

Questions?