Comprehensive Design & Implementation Approach of
Solar Power System in Subtropical Hong Kong
Ir Dr Tony Lam
Associate Director of ArupCEng, CPEng, MHKIE, WELL Faculty, LEED AP, BEAM Pro ND NB
13 December 2018
CIBSE One-day Seminar on Renewable Energy New Development and Technologies in Hong Kong
![Page 2: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/2.jpg)
• Context and Role of solar power system
• Approach of designing a solar power system
• Post-installation evaluation
Agenda
![Page 3: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/3.jpg)
Climate change is real!
![Page 4: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/4.jpg)
The “Hong Kong's Climate Action Plan
2030+” report, published by the
Environment Bureau on January 2017
Context and Role of Solar energy system
![Page 5: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/5.jpg)
Solar power system can:• To achieve the goals of
carbon emissions• To respond government
policies
Context and Role of Solar energy system
Source: www.climatereadt.gov.hkCarbon Footprint of Hong Kong
![Page 6: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/6.jpg)
Context and Role of Solar energy system
World Green Building Council – The Net Zero Carbon Buildings Commitment
• 2030 – to reach net zero carbon operating emissions within their portfolios
• 2050 – to advocate for all buildings to be net zero carbon in operation
![Page 7: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/7.jpg)
Context and Role of Solar energy system
25% PV
coverage of
HK land
100% LNG
+ 15% PV
coverage
50% better BEC for
all bldgs
+ 15% PV coverage
70% LNG
+ 10% PV coverage
+ 50% better BEC for all bldgs
+ 50% GV Bus
1 2 3
How to make Hong Kong Net Zero Carbon?
Proposed Solutions:
Existing Condition:
PV LNG Efficient
BuildingGreen
TransportationHong Kong climate Action Plan 2030+
4
![Page 8: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/8.jpg)
Context and Role of Solar energy system
25% PV
coverage of
HK land
100% LNG
+ 15% PV
coverage
50% better BEC for
all bldgs
+ 15% PV coverage
70% LNG
+ 10% PV coverage
+ 50% better BEC for all bldgs
+ 50% GV Bus
1 2 3
How to make Hong Kong Net Zero Carbon?
Proposed Solutions:
Existing Condition:
PV LNG Efficient
BuildingGreen
TransportationHong Kong climate Action Plan 2030+
4
Solar PV System plays a
KEY ROLE
![Page 9: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/9.jpg)
Building:• Zero/Low Carbon Design Steps• Sub-tropical Climate• Architectural Design• Energy Efficient System• Renewable Energy
Context and Role of Solar energy systemDrivers
Avoid energy use
Use energy efficiently
Decarbonize
![Page 10: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/10.jpg)
Context and Role of Solar energy systemDrivers
Korea Zero Energy House:• Year 2010• Resort House• 425 m2 floor area• 163 m2 rooftop PV• PV 44% contribution of total energy
![Page 11: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/11.jpg)
Context and Role of Solar energy systemDrivers
Singapore Zero Energy Building:• Building and Construction Authority
(BCA)• Office Building• 4,500 m2 floor area• 1,540 m2 rooftop PV
![Page 12: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/12.jpg)
Context and Role of Solar energy systemDrivers
HK Zero Carbon Building:• Year 2012• Construction Industry Council (CIC)• Exhibition/Office Building• 1,520 m2 floor area• 1,015 m2 rooftop PV
![Page 13: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/13.jpg)
Regulations/Incentives:• To take advantage of Feed-in Tariff• Effective date:
• CLP – October 2018
• HEC – Jan 2019
• Commitment period: 15 years• FiT rate for solar energy:
• Under 10kW – HKD5 per kWh
• 10kW to 200kW– HKD4 per kWh
• 200kW to 1MW– HKD3 per kWh
Context and Role of Solar energy systemDrivers
![Page 14: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/14.jpg)
Approach of designing a solar power system
![Page 15: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/15.jpg)
Approach of designing a solar power system
Scale fits the demand?
Fixing and Safety?
Electrical connection Safety?
Affect surroundings?
![Page 16: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/16.jpg)
Step 1: Building and Location Analysis• Architectural layout plan study• Site visit• Propose potential location
Step 2: Solar Resource Assessment• Solar resource simulation• Shading and glare analysis• Identify orientation and inclination of
PV panel
6 Steps in Designing a PV System
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 17: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/17.jpg)
6 Steps in Designing a PV System
Step 3: Selection of Solar Technology• Conventional Photovoltaic (PV)• Thin-Film Solar Cells (TFSC)• Building Integrated PV• Hybrid PV (PV + Thermal)
Step 4: PV System Design• PV Schematic System Design• Metering Design• Plantroom Design• Other Issues for Implantation of
Existing Building
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 18: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/18.jpg)
6 Steps in Designing a PV System
Step 6: Statutory Submission and Approval• Application of CLP/ HKE for Feed-in
Tariff (FiT)• Submission and Approval for Building
Department • Issuance of Work Completion Certificate
(WR1)
Step 5: Structural Aspect Assessment• Dead load and live load assessment• Propose installation method
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 19: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/19.jpg)
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 20: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/20.jpg)
Steps 1 & 2
Building 3D model with
topography and surrounding
buildings
Annual solar availability
Annual glare study
Optimization of PV orientation and tilt angle
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 21: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/21.jpg)
3D Building Modelling with Surroundings
• Surrounding buildings/ self shading/ topography
• Request GIS information from Lands Department
http://www.hkmapservice.gov.hk/OneStopSystem/map-search?product=OSSCatB&series=iB1000
![Page 22: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/22.jpg)
3D Building Modelling with Surroundings
• Topography, Building massing andBuilding height variations are modelled
• Together with the proposed buildingmassing and PV panel layout, this formthe foundation of later studies.
• Surrounding model by 3D modellingsoftware
![Page 23: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/23.jpg)
Annual Solar AvailabilityPrescriptive Approach
• Solar chart to determine the preliminary PV panel orientation and tilt angle
• Data measurement results show that the optimal setting is around 20-23deg tilted due south orientation
• Use performance approach to determine the preliminary location of PV panel
Annual total solar yield (kWh/m2) for various tilt angles and orientations in Hong Kong
Source: Tony Lam’s PhD Thesis 2008
![Page 24: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/24.jpg)
Annual Solar AvailabilityPerformance Approach
Shading above
High
Mid
Low
• With self shading/ surrounding buildings shading effect,
• Annual solar availability
Recommended PV installation area
![Page 25: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/25.jpg)
Annual Glare Study
![Page 26: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/26.jpg)
Annual Glare Study
• Geometric analysis based on Hong Kong solar path
• It is not SIMPLE!
![Page 27: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/27.jpg)
Site Building
Sensitive Receivers
Surrounding Buildings
• Reflection from PV panels may result inundesirable glare for pedestrian,occupants of neighboring buildings
• Sensitive receivers include:➢ Office➢ Residential➢ School➢ Hotel➢ Hospitals➢ Shopping Centre➢ Shops➢ Air flight path➢ Etc.
Annual Glare Study
![Page 28: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/28.jpg)
Annual Glare Study
• Geometric analysis based on Hong Kong solar path in Grasshopper software
• Glare study is carried out from 7am to 6pm throughout the whole year
• Visual the potential glare problem for sensitive receivers
![Page 29: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/29.jpg)
PV Panel Scale Design• After knowing the basic information such as solar availability variation, glare issue, PV orientation and tilt angle,
the next step is to determine the PV panel scale
• PV panel scale depends on➢ Site constraint (space)
➢ Energy saving target (green building certification requirement)➢ FiT Scheme (Incentive)➢ E&M limitation (for existing building)
![Page 30: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/30.jpg)
PV Panel Scale Design• Determine the whole building energy consumption• By Energy Modelling• Increase the % of renewable energy contribution
MAXIMIZE ENERGY GENERATION % BY PV
![Page 31: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/31.jpg)
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 32: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/32.jpg)
Type of PV Technology• Mono- and Poly-crystalline• Thin-Film Solar Cells (TFSC)• Hybrid PV (PV + Thermal)
Building Integrated PV
Mono-crystalline PV
Job reference: Zero Carbon Building
Selection of PV Technology
Design consideration:• Performance at ambient temperature• Module efficiency• Space requirement
![Page 33: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/33.jpg)
Conventional PV
Selection of PV Technology
Monocrystalline Silicon Solar Cells• Power range: 290-365W• Efficiency : 15-23%• Dimensions:
1600mm(L)x1000mm(W)x50mm(H)
• Weight: 18~19kg (~12kg/m2)
Polycrystalline Silicon Solar Cells• Power range: 250-270W• Efficiency : 13-16%• Dimensions:
1600mm(L)x1000mm(W)x50mm(H)
• Weight: 18~19kg (~12kg/m2)
Walkable PV panel at floor Application:PV panel at traditional roof, flat surface
For Example:PV at rooftop, PV wall mounted at building façade, PV at floor
PV panel at rooftop
![Page 34: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/34.jpg)
Thin-Film Solar Cells (TFSC)
• Categorized by which photovoltaic material
➢ Amorphous silicon (a-Si)
➢ Cadmium telluride (CdTe)
➢ Copper indium gallium selenide (CIS/CIGS)
Selection of PV Technology
Thin-film CIGS solar cells• Power range: 70W-310W• Efficiency : 10-16%• Dimensions:
1700/2590/5900mm(L)x350mm(W)x2.5mm(D) • Flexible Weight: <2.4kg/m² (less structural requirement)
Application:PV at curved surface, structures, low load capacity roofs, building integrated PV module
For Example:PV at curved rooftop surface
![Page 35: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/35.jpg)
Building Integrated PV (BiPV)
• Thick crystal products
➢ Solar cells by crystalline silicon (150x150 mm2)
➢ Deliver 10-12 watts per ft² of PV array
• Thin-film products
➢ Thin layers of photovoltaicly active material placed on a glass superstrate or a metal substrate
➢ Deliver 4-5 watts per ft² of PV array area
Application:PV panel integrated in building materials
For Example:Solar paving block at pavement, BiPV Skylight, BiPVGlazing
Solar Paving Block
Photovoltaics in glazing
Selection of PV Technology
Photovoltaics in glazing
![Page 36: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/36.jpg)
Hybrid PV and Thermal (PVT)
• Increase electricity output performance by around 10%
• Backside of the panel is composed of a heat exchanger. The water that circulates through the exchanger is warmed by the heat dissipated from the photovoltaic cells and can reach temperatures up to 70°C
• Reuse the heated water in different ways
• Space saving
Application:Building with hot water demandFor example:Commercial building, hotel, hospital , clubhouse, etc…
Power out
Hot waterout
Cold waterin
Selection of PV Technology
![Page 37: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/37.jpg)
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 38: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/38.jpg)
PV Schematic System Design
Power Distribution
Board
CLP / HKE Meter
Electrical Equipment
Inverter
PV System Design
$
Sale to Power Company
Transformer
![Page 39: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/39.jpg)
Feed-in Tariff Metering Requirement for CLP
• Simplified Single-Line Electrical Diagram for FiT Meter Arrangement for a RE System
PV System Design
![Page 40: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/40.jpg)
Feed-in Tariff Metering Requirement for CLP
PV System Design
![Page 41: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/41.jpg)
PV System Design
Feed-in Tariff Metering Requirement for HKE
• Simplified Single-Line Electrical Diagram for FiT Meter Arrangement for a RE System
![Page 42: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/42.jpg)
PV System Design
Feed-in Tariff Metering Requirement for HKE
![Page 43: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/43.jpg)
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 44: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/44.jpg)
Structural/ Roofing Design Issue
Concrete Building Roof Sheet Metal Roofing Structure
• Roof made by solid concrete• Withstand higher loading• Less strengthening required• Flat roof surface
• Roof made by sheet metal• Withstand lower loading• More strengthening by roof truss steel members• Corrugated shape with inclined angle
![Page 45: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/45.jpg)
Structural/ Roofing Design Issue
• Types of roofing system – Concrete Building Roof
Concrete plinth
Solar panelMetal frame
![Page 46: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/46.jpg)
Structural/ Roofing Design Issue
Direct Screw Fixing Type Standing Seam Type
• Types of roofing system – Sheet metal Roof Structure➢ Direct Screw Fixing Type (Corrugated Metal Roof)➢ Standing Seam Type
![Page 47: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/47.jpg)
Structural/ Roofing Design Issue
• Strategy of installation ➢ Screw Fixing(punch through) for Direct Screw Fixing Roofing system➢ Proprietary Add-on Clamp for Standing Seam Roofing System
Direct Screw Fixing Type Standing Seam Type
Waterproofing – Screw Fixing vs Add-on Clamp
![Page 48: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/48.jpg)
Structural/ Roofing Design Issue
• Sample of PV panels installation for Standing Seam Roofing System
![Page 49: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/49.jpg)
Structural/ Roofing Design Issue
• Other Issues➢ Dead load on PV panels and supporting frame
➢ Wind load on PV panels
➢ Waterproofing – Screw Fixing vs Add-on Clamp
➢ Testing of the Special Add-on Clamp (BD requirement)
➢ Warranty – Warranty Period and Validity of Warranty (for existing building)
![Page 50: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/50.jpg)
1. Building and Location
Analysis
2. Solar Resource
Assessment
3. Selection of Solar
Technology
4. PV System Design
5. Structural Aspect
Assessment
6. Statutory Submission
and Approval
![Page 51: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/51.jpg)
Application of Feed-in Tariff (FiT) to CLP/ HKE
Submit application and required documents
Technical assessment, system test and installation before CLP smart meter installation
Completion and grid connection
Application Process for CLP
Application Process for HKE
Statutory Submission and Approval
![Page 52: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/52.jpg)
New building• General Building Plan submission
Existing Building• Minor Works Submission (Class I or III)
• For Class I item 1.19
➢ Step 1 - Appoint Prescribed Buildings Professional and Prescribed Registered Contractor (Class I of Type A, E)
➢ Step 2 - Submit MW01 - Notice of Commencement, documents, photos 7 days before commencement of work
➢ Step 3 - Submit MW02 - Certificate of Completion, documents, photos within 14 days after completion of work
Statutory Submission and Approval
Submission and Approval for Building Department
![Page 53: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/53.jpg)
Existing Building
• For Class III item 3.15
Step 1 - Appoint Prescribed Buildings Professional and Prescribed Registered Contractor (Class III of Type A, E)
Step 2 - Submit MW05 - Notice and Certificate of Completion, documents, photos within 14 days after completion of work
Statutory Submission and Approval
Submission and Approval for Building Department
![Page 54: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/54.jpg)
Statutory Submission and Approval
Issuance of Work Completion Certificate (WR1)
Completion of Electrical Work
Electrical Inspection
Issuance of Work Completion Certification(WR1)
Power Energization
![Page 55: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/55.jpg)
Post-installation Evaluation & Optimization
![Page 56: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/56.jpg)
Conventional PV System Performance monitoring• Data analysis by comparing energy data
monitored by PV inverter and microclimate station
Microclimate Station
BMS System
InverterPower
DistributionBox
CLP / HKE Meter
Data Analysis
Post-installation Evaluation & Optimization
Transformer $
Dashboard
Solar Radiation
Data
![Page 57: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/57.jpg)
• Using power optimizer to maximum energy yield• Carry out maximum power point tracking (MPPT) at module level
Traditional String Inverter• Suit for roof where ideal for solar • Simple and most affordable• MPPT per string • Power losses due to module mismatch• Weak panel and faulty panel is not easy to be
identified
Power Optimizer plus Inverter• Suit for roof have shading• Higher cost• MPPT per PV module• More equipment means more effort on
maintenance and replacement• Power monitored from each module individually
Post-installation Evaluation & Optimization
![Page 58: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/58.jpg)
Operation concept of power optimizer
Post-installation Evaluation & Optimization
Under ideal condition Under partial shading condition
inverter inverter
Source: xx
![Page 59: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/59.jpg)
Advanced PV System Performance monitoring• Data monitored by power optimizer
BMS System
InverterPower
DistributionBox
CLP / HKE Meter
Data Analysis
Power Optimizer
Power Optimizer
Post-installation Evaluation & Optimization
Transformer $
Manufacturer cloud
Microclimate Station
Solar Radiation
Data
![Page 60: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/60.jpg)
Solar Power System
• Reduce the building electricity demand
• Optimised Solar PV System• RE Output target• Scale optimization• Disturbance of surroundings• Structural loading• Electrical connection• Financial model
• Monitoring and Maintain Performance
Source: CCC Kei Wai Primary School Ma Wan
Demonstration + Make it as common practices!
![Page 61: Comprehensive Design & Implementation Approach of Solar Power System … · 2019-11-15 · Comprehensive Design & Implementation Approach of Solar Power System in Subtropical Hong](https://reader031.fdocuments.in/reader031/viewer/2022011905/5f31e2bccce2fc18fe3367ac/html5/thumbnails/61.jpg)
Thank You!
Ir Dr. Tony Lam
Associate Director of ArupCEng, CPEng, MHKIE, WELL Faculty, LEED AP, BEAM Pro ND NB
13 December 2018
CIBSE One-day Seminar on Renewable Energy New Development and Technologies in Hong Kong