Kevin B Hunter1265 30th Street
Cedar Rapids, Iowa 52402-4060(563) 340-5522
Work History (Assembly, Manufacturing, Operations & Maintenance)
Traveling Wind Turbine Maintenance Technician July 2014-PresentPower Equipment Maintenance, Piedmont, SC
Related Experience Two-year Services on Vestas V112’s CIM 2777 – Ladder and Nacelle Platforms Install CIM 2779 – Main Bearing Grease Catcher Trays Install CIM 2904 – 8A Breaker Install (to replace 4A breakers) CIM 3050 – Fire Suppression Upgrade CIM 3116 – Install Lugs on Grid Cables CIM 3358 – Grid Filter Cabinet Inspection T15 – Fast Acting Fuses Install Updated Arc Flash Stickers Install Nacelle Hatch Upgrade Kit Install
Marble River Wind Project, Churubusco, New York Commissioning of Vestas V110’s NCR 38 – Tower Feet Install NCR 70 – Azimuth Sensor Install Generator Alignment Assistant Generator Grease Catcher Pans Install Generator Ventilation Tube Protector Install Hydraulic Brake System Ventilation Line (TIS) Install Blade Pitch Blocks & Pitch Rams Inspection Removal of Blade Locks & Blade Socks Coolant Level Inspection & Fill Hydraulic Oil Level Inspection & Fill
Origin Wind Project, Hennepin, Oklahoma 3 ½-year Services on Vestas V100’s CIM 2665 – Slip Ring CIM 1498 – Rotating Unit CIM 3169 – Cooler Fan CIM 3087 – Pitch Rams CIM 2041 – Pitch Ram End Seals CIM 2858 – Cooling Pump Inspect, Remove & Replace Pitch Ram Bailiffs and “J” Cables Inspect & Tighten High Voltage (HV) Cable Clamps Coolant Level Inspection & Fill Gearbox Oil Level Inspection & Fill Hydraulic Brake System Ventilation Line (TIS) Install Blade Vortex Generators (VG’s) Removal & Application Blade Copper Strip Removal
Timber Road II, Payne, Ohio