Competitive_Bidding.pdf

50
Power Trading & Tariff Based Tariff Based Competitive Bidding

Transcript of Competitive_Bidding.pdf

  • Power Tradingg&

    Tariff Based Tariff Based Competitive Biddingp g

  • ElectricityMarketElectricityMarketyyConceptsConceptspp

  • Electricity Market Electricitymarketbroadlymeansacollectionofarrangementsforsaleandpurchaseofelectricity

    CompetitiveElectricitymarketimpliesanarrangementwherepriceisdeterminedbydemandandsupply

    3

  • Power Market Structure in India

    LongTermk

    ShortTermMarkets(up Realtime

    b l iMarkets( p

    to1year) balancing

    RegulatedLicensed

    UIAssetsInterstateandas

    State level

    LicensedTraders/Bilateral

    mechanismCostcurve+penalty

    Statelevel

    CompetitiveBiddingcase 1 and

    PowerExchange

    case1andcase2

  • PowerMarketStructure

    CompetitiveBidding

    Case1

    Case2LongTerm

    Case 2CostPlusExpansionProjects

    BilateralwithOAConsumers

    PowerMarket

    ConsumersGenerator/Trader

    ToDiscoms

    ThroughTraders

    AtExchangesDirect Among

    ShortTerm

    (upto 1year)

    DirectAmongDiscoms

    PowerExchange

    CompetitiveBidding

  • Electricity contracts can be of a large varietyElectricity Market

    Electricitycontracts canbeofalargevariety Longterm,Shortterm,Realtime Physical,financial Energy,transmissionrights,ancillaryservices

    Differenttypesofcontractsservedifferentneeds Longer term contracts are for securing supply for base Longertermcontractsareforsecuringsupplyforbase

    loadwithhedgingofpriceriskforbuyerandsecuringreturnoninvestmentbygenerator

    Shortertermcontractsareforoptimizingactualdemandandsupply

    Realtime markets are for managing imbalances and forReal time marketsareformanagingimbalancesandforsecuresystemoperationinrealtime

    Differentsubmarketsarelinked.Marketplayersuseallthedifferentsubmarkets

    6

  • How DISCOMs Procure Power LongtermregulatedCostPlusPPA LongTermCompetitivebiddingbasedpricePPA

    di Mediumtermcontracts>1yeartoupto7yearsthroughPPA

    Short term contracts for 1 year Shorttermcontractsfor1year Shorttermseasonalcontracts(nonstandardcontractsthroughTradersordirectly)g y )

    Termaheadcontracts(throughPX) Dayaheadcontracts(throughOpenAccess/PX)y ( g p ) RealtimemarketUnscheduledInterchange

    7

  • DISCOM Portfolio Actual Load Forecasted Load Real Time Market / UI

    Day ahead C

    2 - 3 %>0.5 %

    Medium Term Contracts > 1year up to 7 years

    Short Term Contracts< 1 yr

    Contracts

    10-15 %

    5-10%

    Long Term Contracts 7-25 yrs

    70-85%

    D

    e

    m

    a

    n

    d

    Time Varies from country to country Norway 50-60 % Spot, Brazil 103 % Long term

  • Arrangement for Sale of Power in India

    CPSUs IPPSState Gencos

    a

    t

    e

    d

    /

    i

    a

    t

    e

    d

    %%3%3%2%2%

    Structure of power market

    Power exchangesUI mechanism

    Direct consumersTraders

    R

    e

    g

    u

    l

    a

    N

    e

    g

    o

    t

    Discoms

    5%5%

    L t

    Trading traders/ direct

    consumersTraders

    Long Term Short Term

    o

    m

    p

    e

    t

    i

    t

    i

    v

    e

    B

    i

    d

    Discoms90%

    Long term

    Long Term Short Term

    C

    o

    Memorandum of Understanding (MOU)History of Power

    Bulk Power Supply Agreement (BPSA)Single agreement with all beneficiaries of station

    Po er P rchase Agreement (PPA)

    History of Power Supply Agreements in India

    Power Purchase Agreement (PPA)Separate Agreement for each station and beneficiary

    9

  • Trend of Short Term Power Sale in India

    14.0%

    16.0%

    10.0%

    12.0%

    6.0%

    8.0%

    2.0%

    4.0%

    0.0%

    A

    u

    g

    0

    8

    S

    e

    p

    0

    8

    O

    c

    t

    0

    8

    N

    o

    v

    0

    8

    D

    e

    c

    0

    8

    J

    a

    n

    0

    9

    F

    e

    b

    0

    9

    M

    a

    r

    0

    9

    A

    p

    r

    0

    9

    M

    a

    y

    0

    9

    J

    u

    n

    0

    9

    J

    u

    l

    0

    9

    A

    u

    g

    0

    9

    S

    e

    p

    0

    9

    O

    c

    t

    0

    9

    N

    o

    v

    0

    9

    D

    e

    c

    0

    9

    J

    a

    n

    1

    0

    F

    e

    b

    1

    0

    M

    a

    r

    1

    0

    A

    p

    r

    1

    0

    M

    a

    y

    1

    0

    J

    u

    n

    1

    0

    J

    u

    l

    1

    0

    A

    u

    g

    1

    0

    S

    e

    p

    1

    0

    O

    c

    t

    1

    0

    N

    o

    v

    1

    0

    D

    e

    c

    1

    0

    J

    a

    n

    1

    1

    F

    e

    b

    1

    1

    M

    a

    r

    1

    1

    A

    p

    r

    1

    1

    M

    a

    y

    1

    1

    J

    u

    n

    1

    1

    J

    u

    l

    1

    1

    A

    u

    g

    1

    1

    S

    e

    p

    1

    1

    O

    c

    t

    1

    1

    N

    o

    v

    1

    1

    D

    e

    c

    1

    1

    J

    a

    n

    1

    2

    F

    e

    b

    1

    2

    M

    a

    r

    1

    2

    10

  • Need of Power Trading

    Tofulfilsurplusanddeficitgaps Essential for resource optimization, noEssentialforresourceoptimization,nobackingdownofgeneratingstations

    I d PLF ti l l f St t P ImprovedPLF,particularlyofStatePowerUtilities

    Reductioninloadshedding

    11

  • ( f d ) l

    Trading Margin CERC(FixationofTradingmargin)Regulations2010

    dated11thJan2010

    Toapplyonshorttermbuyshorttermselltransactions

    Tradingmarginshallnotbechargedexceeding7p/kWhincasethesalepriceisexceedingRs3/kWhand 4 p/kWh in case the sale price is less or equal toand4p/kWhincasethesalepriceislessorequaltoRs3/kWh

    S i b ki t ti d t f ll i Swappingorbankingtransactionsdonotfallincategoryoftrading purchaseofelectricityforresaleas no resale is involvedasnoresaleisinvolved

    12

  • ( f d ) l

    Trading Margin CERC(FixationofTradingmargin)Regulations2010 Longtermriskscannotbemitigatedthroughatrading

    margin,thesamecanbedecidedbymarketforces.

    Tradingmargintoapplyonscheduledenergy&notoncontractedordeliveredquantum

    TradingmarginspecifiedaboveisthecumulativevalueofmarginchargedbyalltradersinvolvedinthetransactionbetweentheGeneratorandtheUltimateBBuyer

    UltimateBuyerincludesaDistributionLicensee

    13

  • Overview of Bilateral Trading

    Agreements Quantumofpower,meteringpoint,transmissionlosses

    i d f l ( h i bl k) Periodofsupply(Days,hours,timeblock) Price Transmission(OA)charges,operatingcharges

    Traders margin Trader smargin Paymentsecuritymechanism Billing&payment Default handling/ penaltyDefaulthandling/penalty

    14

  • Overview of Bilateral Trading

    15

  • Overview of Bilateral Trading

    16

  • A common platform for trading of electricity on day What is Power Exchange?

    Acommonplatformfortradingofelectricityondayaheadbasis

    Neutralandtransparent welldefinedrulesp Confidentialityofbids Financialcounterpartyfortrades paymentsecurityfor

    participants Coexistswithlong/shorttermbilateralcontracts Competitive price discoveryCompetitivepricediscovery Simultaneoushandlingofcontractsandtransmissionaccess

    Electronicplatformfast&efficient Promotessystembalance Lowtransactioncost

    17

  • Price and Volume Determination

    )

    Demand

    P

    r

    i

    c

    e

    (

    R

    s

    .

    /

    M

    W

    h

    )

    Supply

    18

    P

    Volume (MW)

  • Hourly Price Index

    19

  • PX will be a separate Company registered under Companies Act

    Power Market Regulations 2010 PXwillbeaseparateCompanyregisteredunderCompaniesAct PXshallberegisteredwithCERC(AnnualFee) Byelaws and rules of PX to be approved by CERCBye lawsandrulesofPXtobeapprovedbyCERC Restrictionsonshareholdingpatternandstaffing ContractstobeapprovedbyCERC NetworthnormsforPX(Rs.25crores) Normsformembership Separateclearinghousemustforaderivativeexchange ClosureormergerofPX,ifmarketshareis

  • f h d l f llTimeLineforschedulingofCollectiveTransaction

    10:00 14:00 18:0012:00 13:00 15:00 17:30

    RLDCs/SLDCsto

    MarketParticipantstoplace their Bids

    incorporateCollectiveTransactionsintheDailyh d l

    NLDCtocheck

    NLDCtoconfirmacceptance.PXto send files toplacetheirBids

    PXtosendScheduling

    SchedulePXtosendprovisionalunconstrainedsolution to

    forcongestion.IncaseofcongestionshallintimatePX

    tosendfilestoSLDCsforscheduling

    RequesttoNLDCbasedonmarginspecifiedbyNLDC

    solutiontoNLDCandflowonTSasinformedbyNLDC

    regardingtotheperiodforcongestionandavailable

    NLDC margins

  • I di E E h (IEX)

    Power Exchanges in India IndianEnergyExchange(IEX)

    PromotedbyFTIL&PTCFinancialServicesLtd InoperationsinceJune2008

    PowerExchangeIndiaLimited(PXIL) PromotedbyNSE&NCDEX InoperationsinceOct2008

    NationalPowerExchangeLimited(NPEX) Promoted by NTPC, NHPC, PFC & TCSPromotedbyNTPC,NHPC,PFC&TCS HasreceivedpermissionfromCERCtosetupPX

    22

    No.ofLicensedTraders>40

  • TariffBasedTariffBasedCompetitiveBiddingCompetitiveBiddingp gp g

  • Section 63 of the EA 2003 provides that the appropriateBackground

    Section 63 of the EA2003 provides that the appropriatecommission shall adopt the tariff if such tariff has beendetermined through transparent process of bidding inaccordance with the guidelines

    Section 61 of Electricity Act 2003 stipulates that theCommission shall be guided by the tariff policy whileCommission shall be guided by the tariff policy whiledetermining the tariff

    As empowered by section 3(1) of Electricity Act 2003 CentralGovernment has formulated the Tariff Policy on 06/01/2006

    The Tariff Policy stipulates that all future requirement of powershould be procured competitively by distribution licenseesshould be procured competitively by distribution licensees

    Even for Public Sector Projects tariff shall be decided on basis ofcompetitive bidding after 5 yrs or when Commission is satisfiedfor introduction of such competition

  • The guidelines are applicable for procurement of power

    Tariff Based Bidding GuidelinesThe guidelines are applicable for procurement of powerthrough competitive bidding through the followingmechanismmechanism

    PeriodofProcurement

    LongTerm MediumTerm

    M h i

    7years&above >1yearupto7years

    Mechanisms

    Case 1 Case 2Case Case

  • C titi T iff B d Biddi i C lC titi T iff B d Biddi i C l ff J 2011J 2011

    BiddingMechanismsBiddingMechanisms

    CompetitiveTariffBasedBiddingisCompulsoryCompetitiveTariffBasedBiddingisCompulsoryw.e.fw.e.f.January2011.January2011

    C IC I C IIC IICaseICaseI CaseIICaseII

    Location/Location/BidderisBidderis

    responsibleforresponsibleforll lll l

    Land/FuelLand/Fuelspecifiedbyspecifiedbyprocurerprocurer

    ClearancesClearancesprovidedbyprovidedby

    Technology/Technology/FuelunspecifiedFuelunspecified(PowerBlock)(PowerBlock)

    allclearancesallclearancesetc.etc.

    HighRiskforHighRiskfordevelopersdevelopers

    MoreapplicableMoreapplicableforstateswithforstateswithfuelsourcesandfuelsourcesand

    statestate

    HighriskforHighriskforstatestate

    developersdevelopers coastalareascoastalareas

    Source:CERC

  • Mechanism

    MechanismofTariffBasedBidding

    CaseI

    Location,Technologyorfuelnotspecified

    CaseII

    Location,Technology&Fuelarrangement specifiedp arrangementspecified

    CaptivecoalblocktobedevelopedbytheSeller

    SpecificCoallinkageprovidedbyProcurer

    ImportedCoaltobearrangedby

    thesellerFuelSource

    Energy Energychargesbasedon quoted Net Heat

    Importedfuel&Transportationcomponentin

    USD/unitEnergy ChargesinRs/KWh

    onquotedNetHeatRate

    USD/unit.

    InlandfuelhandlingcomponentinIndian

    Rupees/unit

    EnergyCharge

  • BiddingProcessCase1

    SingleStage SingleStage

    Case2

    TwoStage TwoStage Medium&LongTerm RequestforProposal Max Time: 195 days

    Medium&LongTerm RequestforProposal Max Time: 195 days

    LongTerm RequestforQualification&Request for Proposal

    LongTerm RequestforQualification&Request for Proposal MaxTime:195days MaxTime:195days RequestforProposal

    MaxTime:730daysRequestforProposal

    MaxTime:730days

    PeriodofProcurementPeriodofProcurement

    LongTerm:Above7Years Medium Term: 1 Year to 7 Years(Usuallyupto lifeofplant) MediumTerm:1Yearto7Years

    Approval of the Appropriate Regulatory Commission isDeviation ApprovaloftheAppropriateRegulatoryCommissionisrequiredintheeventofthedeviationfromthebiddingconditionscontainedintheguidelines

    Deviationfrom

    Guidelines

  • Bidding Process Two stage bidding process is to be adopted forLong Term procurement of electricity biddingunder case2i. Request for Qualification (RFQ)ii. Request for Proposal (RFP)

    Single stage bidding process combining the RFPSingle stage bidding process combining the RFP& RFQ process may be adopted for biddingunder Case1 for Medium/Long Termunder Case 1 for Medium/Long Termprocurement of electricity

  • Preparation for Inviting BidsFor Long term procurement under Case2 Procurer orAuthorized Representative shall complete the followingactivities before issue of RFQ documentsactivities before issue of RFQ documents

    Site identification and land acquisition: Issue ofSite identification and land acquisition: Issue ofNotification under Section4 of Land AcquisitionAct, 1894 Environmental clearance for Power Station: Rapid EIAreport should be availableF l li k C ti l i Sh ld b il bl Fuel linkage or Captive coal mine: Should be available(If bidders to arrange the same shall be clearlyspecified in the RFQ)specified in the RFQ) Water linkage should be available

  • 1 Fi i l Q lifi ti

    RFQ Bid Submission for Project1. FinancialQualification

    InternalResourceGeneration 1140CrsN t W th 1000 C NetWorth 1000Crs

    AnnualTurnOver 2400Crs

    2 Technical Qualification2. TechnicalQualification AggregateCapitalCostofProjectsundertakeninLast10

    years 3000 Crs (with 26% equity stake)years 3000Crs(with26%equitystake)

    CapitalCostofatleastoneProject 500Crs

    3 Executive Summary3. ExecutiveSummary

    4. DisclosureStatements

    5 P f A5. PowerofAttorney

    6. CoveringLetter

  • UMPP Case2

    Qualifying RequirementsS.N. RFQ:

    URsCrs

    CaseRsCr/MW

    FinancialRequirements

    1 InternalResourceGeneration 1140 0.3

    2NetWorth(forcapacityupto2000MW) 0.5 ForCase1(0.5Cr/MW)

    3NetWorth(forcapacity>2000MW) 1000 0 25 1000 C hi h i hi h3 MW) 1000 0.25 or1000Crwhicheverishigher

    4AnnualTurnover(forcapacityupto 2000MW) 1.2

    Annual Turnover (for capacity5

    AnnualTurnover(forcapacity>2000MW) 2400 0.6 or2400Crwhicheverishigher

    6 TechnicalRequirements 3000 0.75AggregateCapitalCostofProjectsundertakeninLast10years

    500 0.125 Capitalcostofatleast1project

    GuaranteesRFP:

    RsLakh/MW

    1 BidBond 120 3 ForCase1(3Lakh/MW)

    2 PerformanceGuarantee 300* 7.5 ForCase1(30Lakh/MW)

  • Preparation for Inviting BidsFor Long term procurement under Case2 Procurer orAuthorized Representative shall complete the followingactivities before issue of RFP documentsactivities before issue of RFP documents

    Site identification and land acquisition: Issue of Notification underqSection 6 of Land Acquisition Act, 1894 Environmental clearance & Forest clearance for the PowerStation: Proposal should be submitted before concernedStation: Proposal should be submitted before concernedAuthority (Environment clearance should be obtained before PPAbecomes effective)

    il d j ( ) i i Detailed Project Report (DPR): RequisiteHydrological, geological, meteorological and seismological datanecessary for preparation of DPR (bidder to verify these data asfthe geological risk lie with the developer)

  • f dd d l h ll

    Preparation for Inviting BidsFor Case1 if Bidder intends to set new power plant shallsubmit documentary evidence w.r.t the following activitiesalong with RFP bidalong with RFP bid

    Site identification and land acquisition: Should possess 50% ofrequired land (If land is to be acquired under LA Act 1894, copy ofNotification under Section 4 to be submitted) Environmental clearance & Forest clearance for the PowerEnvironmental clearance & Forest clearance for the PowerStation: Proposal should be submitted before concernedAuthorityF l A t C ti i / l li k / i t d l/ Fuel Arrangements: Captive mine/coal linkage/ imported coal/Domestic gas/ RLNG Water Linkage: Shall have acquired approval from concerned stateirrigation department /relevant authority

  • The RFP bid to be submitted in two parts Financial and Non

    RFP Bid Submission for ProjectThe RFP bid to be submitted in two parts, Financial and Nonfinancial bidsNonFinancial Bid

    Board Resolution from bidding company committingBoard Resolution from bidding company committing100% equity requirement

    Bid Bond Bidder Undertaking along with scheduled COD date andBidder Undertaking along with scheduled COD date and

    Contract Capacity of each unit Covering letter

    Power of Attorney Power of Attorney Disclosure Statement

    Financial BidThe financial bid shall consist of quote for the capacity charges andThe financial bid shall consist of quote for the capacity charges andenergy charges in two parts, NonEscalable Charges and EscalableChargesThe Bidder has the option to quote firm Quoted Energy ChargesThe Bidder has the option to quote firm Quoted Energy Chargesand/or firm Quoted Capacity Charges for the term of the PPA

  • Event Elapsed Time from Zero date

    Time Table for Two Stage Bid ProcessEvent Elapsed Time from Zero date

    Publication of RFQ Zero date

    Submission of Responses of RFQ 45 days

    Issuance of RFP 75 days

    Bid clarification, bidders conf. etc.and revision of RFQ/RFP

    *

    RFP bid b i i dRFP bid submission 225 days

    Evaluation of bids and issue of LOI 240 days

    Si i f A t dSigning of Agreements 270 days

    If bidding process is likely to take more than 730 days approval ofA i t C i i h t b bt i dAppropriate Commission has to be obtained.

  • Time Table for Single Stage Bid Process

    Event Elapsed Time from Zero date

    Publication of RFP Zero datePublication of RFP Zero date

    Bid clarification, bidders conf. etc.and revision of RFQ/RFP

    **and revision of RFQ/RFP

    RFQ/RFP bid submission 75days

    Evaluation of bids and issue of LOI 100 daysEvaluation of bids and issue of LOI 100 days

    Signing of Agreements 120 days

    If bidding process is likely to take more than 195 days approval ofAppropriate Commission has to be obtained.

  • TARIFFSTRUCTURE A multitariff structure with separate capacity and energy

    charges forms the basis of the bidding process

    In case of Case2 projects where the procurer provides the fuellinkage, bidder is required to submit the capacity charges alongwith the net heat rate

  • Tariff BidsScenario-1 (Captive Coal Block Allocated)

    ContractYear

    Commencement Date ofContract Year

    End Date ofContractYear

    Quoted NonEscalableCapacity

    QuotedEscalableCapacity

    Quoted NonEscalableEnergy

    QuotedEscalableEnergy

    ( p )

    Charges(Rs./kwh)

    Charges(Rs./kwh)

    Charges(Rs./kwh)

    Charges(Rs./kwh)

    1 S h d l d M h 311 ScheduledCOD of 1st

    Unit

    March 31

    2 April 1 March 31 Same as Same as2 April 1 March 31 Same asabove

    Same asabove

    April

    March 31 Same asabove

    . Same asabove

    26 April 1 25th

    anniversaryof theScheduled

    Same asabove

    Same asabove

    ScheduledCOD of 1st

    Unit

  • Tariff BidsScenario-2 (Imported Coal)

    ContractYear

    Commencement Dateof

    EndDateofContra

    QuotedNonEscalableCapacity

    QuotedEscalableCapacity

    QuotedNonEscalable Fuel

    QuotedEscalableFuelEnergy

    QuotedNonEscalableTransporta

    QuotedEscalableTransportation Energy

    QuotedNonEscalableFuel

    QuotedEscalableFuelHandling

    ( p )

    Contract Year

    ct Year Charges(Rs./kwh)

    Charges(Rs./kwh)

    EnergyCharges(US$/kwh)

    Charges(US$/kwh)

    tion EnergyCharges(US$/kwh)

    Charges(US$/kwh)

    HandlingEnergyCharges(Rs./kwh)

    EnergyCharges(Rs./kwh)

    1 Schedul Marched CODof 1stUnit

    31

    2 April 1 March31

    Same asabove

    Same asabove

    Same asabove

    Same asabove31 above above above above

    . April

    March31

    Same asabove

    Same asabove

    Same asabove

    Same asabove

    26 April 1 25th Same as Same as Same as Same asanniversaryof theScheduledCOD

    above above above above

    40

    CODof 1st

    Unit

  • Tariff BidsScenario-3 (Coal Arranged by Seller)

    Contract

    Commencement Date of

    End Dateof Contract

    QuotedNon

    QuotedEscalable

    Quoted NonEscalable

    QuotedEscalable

    ( g y )

    actYear

    t Date ofContract Year

    of ContractYear

    NonEscalableCapacityCharges(Rs./kwh)

    EscalableCapacityCharges(Rs./kwh)

    EscalableEnergyCharges(Rs./kwh)

    EscalableEnergyCharges(Rs./kwh)

    (Rs./kwh)

    1 Scheduled CODof first Unit

    March 31

    l h2 April 1 March 31 Same asabove

    Same asabove

    April

    March 31 Same asabove

    . Same asabove

    26 April 1 25th

    anniversaryof theScheduled

    Same asabove

    Same asabove

    ScheduledCOD of firstUnit

  • Tariff BidsScenario-4 (Coal Arranged by Procurer)

    ContractYear

    CommencementDate of Contract

    End Date ofContract Year

    Quoted NonEscalable

    QuotedEscalable

    Quoted HeatRate

    ( g y )

    Year Date of ContractYear

    Contract Year EscalableCapacityCharges(Rs./kwh)

    EscalableCapacityCharges(Rs./kwh)

    Rate(Kcal/kwh)

    h d l d f h1 Scheduled COD of1st Unit

    March 31

    2 April 1 March 31 Same as above Same as above

    April. March 31 Same as above Same as above

    26 April 1 25th

    anniversaryof theS h d l d

    Same as above Same as above

    ScheduledCOD of 1st

    Unit

  • Th l t d Q t d T iff ( R kWh) f h f th

    Bid Evaluation for the ProjectThe escalated Quoted Tariffs ( Rs per kWh) of each of thecontract year for the term of PPA calculated as per theRFP shall be discounted by the discount factors and suchRFP shall be discounted by the discount factors and suchaggregate discounted value for the term of the PPA shallbe divided by the sum of such discount factors tobe divided by the sum of such discount factors tocalculate the levelised tariff of each Bidder

    Di)(Ti

    The Levelised Tariff calculated as above shall be ranked

    =Di

    Di).(TiLT

    The Levelised Tariff calculated as above shall be rankedfrom the lowest to the highest and the Bidder withlowest Levelised Tariff shall be declared as the SuccessfulBidder

  • LEVELISEDTARIFF

    LEVELISED TARIFF = Net Discounted Tariff* Net Discount Factor**

    *Net Discounted Tariff = Tariff / (1+ Discount factor) ^n**Net Discount Factor = 1/ (1+ Discount Factor) ^n

    CERC NOTIFICATIONS:Discount rate Escalation rate for coal Dollar Rupee FERVDiscount rate , Escalation rate for coal, Dollar Rupee FERV,

    Inflation rate updated by CERC every six months

  • Year Commen.of Contract

    End Date of Contract

    Non-Escalabl

    Escalable C.C

    Non-Indexed

    Indexed E.C

    Total Tariff

    Financial Bid for Tilaiya- Reliance

    1 24-Nov-14 31-Mar-15 0.51 0.17 0.38 0.13 1.192 1-Apr 31-Mar 0.50 0.18 0.86 0.14 1.683 1-Apr 31-Mar 0.68 0.19 0.85 0.15 1.874 1-Apr 31-Mar 0.68 0.20 0.84 0.16 1.885 1-Apr 31-Mar 0 68 0 20 0 83 0 17 1 895 1 Apr 31 Mar 0.68 0.20 0.83 0.17 1.896 1-Apr 31-Mar 0.68 0.22 0.82 0.18 1.907 1-Apr 31-Mar 0.68 0.23 0.81 0.19 1.918 1-Apr 31-Mar 0.68 0.24 0.80 0.20 1.929 1-Apr 31-Mar 0.51 0.25 0.79 0.21 1.9310 1 A 31 M 1 9410 1-Apr 31-Mar 0.68 0.26 0.77 0.23 1.9411 1-Apr 31-Mar 0.68 0.27 0.85 0.24 1.9612 1-Apr 31-Mar 0.68 0.29 0.74 0.26 1.9713 1-Apr 31-Mar 0.39 0.30 0.73 0.27 1.7014 1-Apr 31-Mar 0.38 0.32 0.71 0.29 1.7015 1-Apr 31-Mar 0.36 0.33 0.69 0.31 1.7016 1-Apr 31-Mar 0.35 0.35 0.67 0.33 1.7017 1-Apr 31-Mar 0.34 0.37 0.65 0.35 1.7018 1-Apr 31-Mar 0.31 0.39 0.63 0.37 1.7019 1-Apr 31-Mar 0.31 0.40 0.60 0.40 1.7220 1-Apr 31-Mar 0.31 0.42 0.58 0.42 1.7421 1-Apr 31-Mar 0.31 0.45 0.55 0.45 1.7622 1-Apr 31-Mar 0.31 0.47 0.52 0.48 1.7823 1-Apr 31-Mar 0.29 0.49 0.49 0.51 1.7824 1-Apr 31-Mar 0 27 0 52 0 46 0 54 1 7924 1 Apr 31 Mar 0.27 0.52 0.46 0.54 1.7925 1-Apr 31-Mar 0.25 0.54 0.43 0.57 1.7926 1-Apr 25th

    f0.41 0.56 0.40 0.60 1.97

    Levelised Tariff (Rs./kWhr) 1.77

  • Sites Selected for UMPP Development

    UltraMegaPowerProjectsbasedonCaptiveMineallocation

    Project NameoftheShellCompany( ) dSasan (M.P) Sasan PowerLimited.

    AwardedtoReliancePowerLimitedwithLevellisedtariffofRs1.196/kWh

    Tilaiya(Jharkhand) JharkhandIntegratedPowerLimited

    AwardedtoReliancePowerLimitedwithLevellisedtariffofRs1.77/kWh

    Surguja(Chhattisgarh) ChhattisgarhSurguja PowerLimited

    Bedabahal(Orissa) OrissaIntegratedPowerLimited

    O i S khi l I d P C Li i dOrissa Sakhigopal IntegratedPowerCompanyLimited

    Orissa Ghogarpalli IntegratedPowerCompanyLimited

  • Sites Selected for UMPP Development

    CoastalUltraMegaPowerProjectsbasedonImportedCoal

    Project NameoftheShellCompanyd ( ) l dMundra (Gujrat) CoastalGujaratPowerLimited

    AwardedtoTataPowerLimitedwithLevellised tariffofRs2.260/kWh

    Krishnapatnam(A.P) CoastalAndhraPowerLimited

    AwardedtoReliancePowerLtd.withLevellised tariffofRs2.333/kWh

    Cheyyur(Tamilnadu) CoastalTamilNaduPowerLimited

    Nainapalli(A.P) Tatiya AndhraMegaPowerLtd.

    (M h h ) C l M h h M P Li i d(Maharashtra) CoastalMaharashtraMegaPowerLimited

    (Karnataka) CoastalKarnatakaPowerLimited

    The Govt. of Gujrat has requested for Second UMPP in the State.

  • A Glance at Awarded Power ProjectsThrough Case 2 Competitive Bidding Route

  • A Glance at Awarded Power ProjectsThrough Case 1 Competitive Bidding Route

  • 50