Competitive_Bidding.pdf
-
Upload
rajeevagrawal -
Category
Documents
-
view
9 -
download
0
Transcript of Competitive_Bidding.pdf
-
Power Tradingg&
Tariff Based Tariff Based Competitive Biddingp g
-
ElectricityMarketElectricityMarketyyConceptsConceptspp
-
Electricity Market Electricitymarketbroadlymeansacollectionofarrangementsforsaleandpurchaseofelectricity
CompetitiveElectricitymarketimpliesanarrangementwherepriceisdeterminedbydemandandsupply
3
-
Power Market Structure in India
LongTermk
ShortTermMarkets(up Realtime
b l iMarkets( p
to1year) balancing
RegulatedLicensed
UIAssetsInterstateandas
State level
LicensedTraders/Bilateral
mechanismCostcurve+penalty
Statelevel
CompetitiveBiddingcase 1 and
PowerExchange
case1andcase2
-
PowerMarketStructure
CompetitiveBidding
Case1
Case2LongTerm
Case 2CostPlusExpansionProjects
BilateralwithOAConsumers
PowerMarket
ConsumersGenerator/Trader
ToDiscoms
ThroughTraders
AtExchangesDirect Among
ShortTerm
(upto 1year)
DirectAmongDiscoms
PowerExchange
CompetitiveBidding
-
Electricity contracts can be of a large varietyElectricity Market
Electricitycontracts canbeofalargevariety Longterm,Shortterm,Realtime Physical,financial Energy,transmissionrights,ancillaryservices
Differenttypesofcontractsservedifferentneeds Longer term contracts are for securing supply for base Longertermcontractsareforsecuringsupplyforbase
loadwithhedgingofpriceriskforbuyerandsecuringreturnoninvestmentbygenerator
Shortertermcontractsareforoptimizingactualdemandandsupply
Realtime markets are for managing imbalances and forReal time marketsareformanagingimbalancesandforsecuresystemoperationinrealtime
Differentsubmarketsarelinked.Marketplayersuseallthedifferentsubmarkets
6
-
How DISCOMs Procure Power LongtermregulatedCostPlusPPA LongTermCompetitivebiddingbasedpricePPA
di Mediumtermcontracts>1yeartoupto7yearsthroughPPA
Short term contracts for 1 year Shorttermcontractsfor1year Shorttermseasonalcontracts(nonstandardcontractsthroughTradersordirectly)g y )
Termaheadcontracts(throughPX) Dayaheadcontracts(throughOpenAccess/PX)y ( g p ) RealtimemarketUnscheduledInterchange
7
-
DISCOM Portfolio Actual Load Forecasted Load Real Time Market / UI
Day ahead C
2 - 3 %>0.5 %
Medium Term Contracts > 1year up to 7 years
Short Term Contracts< 1 yr
Contracts
10-15 %
5-10%
Long Term Contracts 7-25 yrs
70-85%
D
e
m
a
n
d
Time Varies from country to country Norway 50-60 % Spot, Brazil 103 % Long term
-
Arrangement for Sale of Power in India
CPSUs IPPSState Gencos
a
t
e
d
/
i
a
t
e
d
%%3%3%2%2%
Structure of power market
Power exchangesUI mechanism
Direct consumersTraders
R
e
g
u
l
a
N
e
g
o
t
Discoms
5%5%
L t
Trading traders/ direct
consumersTraders
Long Term Short Term
o
m
p
e
t
i
t
i
v
e
B
i
d
Discoms90%
Long term
Long Term Short Term
C
o
Memorandum of Understanding (MOU)History of Power
Bulk Power Supply Agreement (BPSA)Single agreement with all beneficiaries of station
Po er P rchase Agreement (PPA)
History of Power Supply Agreements in India
Power Purchase Agreement (PPA)Separate Agreement for each station and beneficiary
9
-
Trend of Short Term Power Sale in India
14.0%
16.0%
10.0%
12.0%
6.0%
8.0%
2.0%
4.0%
0.0%
A
u
g
0
8
S
e
p
0
8
O
c
t
0
8
N
o
v
0
8
D
e
c
0
8
J
a
n
0
9
F
e
b
0
9
M
a
r
0
9
A
p
r
0
9
M
a
y
0
9
J
u
n
0
9
J
u
l
0
9
A
u
g
0
9
S
e
p
0
9
O
c
t
0
9
N
o
v
0
9
D
e
c
0
9
J
a
n
1
0
F
e
b
1
0
M
a
r
1
0
A
p
r
1
0
M
a
y
1
0
J
u
n
1
0
J
u
l
1
0
A
u
g
1
0
S
e
p
1
0
O
c
t
1
0
N
o
v
1
0
D
e
c
1
0
J
a
n
1
1
F
e
b
1
1
M
a
r
1
1
A
p
r
1
1
M
a
y
1
1
J
u
n
1
1
J
u
l
1
1
A
u
g
1
1
S
e
p
1
1
O
c
t
1
1
N
o
v
1
1
D
e
c
1
1
J
a
n
1
2
F
e
b
1
2
M
a
r
1
2
10
-
Need of Power Trading
Tofulfilsurplusanddeficitgaps Essential for resource optimization, noEssentialforresourceoptimization,nobackingdownofgeneratingstations
I d PLF ti l l f St t P ImprovedPLF,particularlyofStatePowerUtilities
Reductioninloadshedding
11
-
( f d ) l
Trading Margin CERC(FixationofTradingmargin)Regulations2010
dated11thJan2010
Toapplyonshorttermbuyshorttermselltransactions
Tradingmarginshallnotbechargedexceeding7p/kWhincasethesalepriceisexceedingRs3/kWhand 4 p/kWh in case the sale price is less or equal toand4p/kWhincasethesalepriceislessorequaltoRs3/kWh
S i b ki t ti d t f ll i Swappingorbankingtransactionsdonotfallincategoryoftrading purchaseofelectricityforresaleas no resale is involvedasnoresaleisinvolved
12
-
( f d ) l
Trading Margin CERC(FixationofTradingmargin)Regulations2010 Longtermriskscannotbemitigatedthroughatrading
margin,thesamecanbedecidedbymarketforces.
Tradingmargintoapplyonscheduledenergy¬oncontractedordeliveredquantum
TradingmarginspecifiedaboveisthecumulativevalueofmarginchargedbyalltradersinvolvedinthetransactionbetweentheGeneratorandtheUltimateBBuyer
UltimateBuyerincludesaDistributionLicensee
13
-
Overview of Bilateral Trading
Agreements Quantumofpower,meteringpoint,transmissionlosses
i d f l ( h i bl k) Periodofsupply(Days,hours,timeblock) Price Transmission(OA)charges,operatingcharges
Traders margin Trader smargin Paymentsecuritymechanism Billing&payment Default handling/ penaltyDefaulthandling/penalty
14
-
Overview of Bilateral Trading
15
-
Overview of Bilateral Trading
16
-
A common platform for trading of electricity on day What is Power Exchange?
Acommonplatformfortradingofelectricityondayaheadbasis
Neutralandtransparent welldefinedrulesp Confidentialityofbids Financialcounterpartyfortrades paymentsecurityfor
participants Coexistswithlong/shorttermbilateralcontracts Competitive price discoveryCompetitivepricediscovery Simultaneoushandlingofcontractsandtransmissionaccess
Electronicplatformfast&efficient Promotessystembalance Lowtransactioncost
17
-
Price and Volume Determination
)
Demand
P
r
i
c
e
(
R
s
.
/
M
W
h
)
Supply
18
P
Volume (MW)
-
Hourly Price Index
19
-
PX will be a separate Company registered under Companies Act
Power Market Regulations 2010 PXwillbeaseparateCompanyregisteredunderCompaniesAct PXshallberegisteredwithCERC(AnnualFee) Byelaws and rules of PX to be approved by CERCBye lawsandrulesofPXtobeapprovedbyCERC Restrictionsonshareholdingpatternandstaffing ContractstobeapprovedbyCERC NetworthnormsforPX(Rs.25crores) Normsformembership Separateclearinghousemustforaderivativeexchange ClosureormergerofPX,ifmarketshareis
-
f h d l f llTimeLineforschedulingofCollectiveTransaction
10:00 14:00 18:0012:00 13:00 15:00 17:30
RLDCs/SLDCsto
MarketParticipantstoplace their Bids
incorporateCollectiveTransactionsintheDailyh d l
NLDCtocheck
NLDCtoconfirmacceptance.PXto send files toplacetheirBids
PXtosendScheduling
SchedulePXtosendprovisionalunconstrainedsolution to
forcongestion.IncaseofcongestionshallintimatePX
tosendfilestoSLDCsforscheduling
RequesttoNLDCbasedonmarginspecifiedbyNLDC
solutiontoNLDCandflowonTSasinformedbyNLDC
regardingtotheperiodforcongestionandavailable
NLDC margins
-
I di E E h (IEX)
Power Exchanges in India IndianEnergyExchange(IEX)
PromotedbyFTIL&PTCFinancialServicesLtd InoperationsinceJune2008
PowerExchangeIndiaLimited(PXIL) PromotedbyNSE&NCDEX InoperationsinceOct2008
NationalPowerExchangeLimited(NPEX) Promoted by NTPC, NHPC, PFC & TCSPromotedbyNTPC,NHPC,PFC&TCS HasreceivedpermissionfromCERCtosetupPX
22
No.ofLicensedTraders>40
-
TariffBasedTariffBasedCompetitiveBiddingCompetitiveBiddingp gp g
-
Section 63 of the EA 2003 provides that the appropriateBackground
Section 63 of the EA2003 provides that the appropriatecommission shall adopt the tariff if such tariff has beendetermined through transparent process of bidding inaccordance with the guidelines
Section 61 of Electricity Act 2003 stipulates that theCommission shall be guided by the tariff policy whileCommission shall be guided by the tariff policy whiledetermining the tariff
As empowered by section 3(1) of Electricity Act 2003 CentralGovernment has formulated the Tariff Policy on 06/01/2006
The Tariff Policy stipulates that all future requirement of powershould be procured competitively by distribution licenseesshould be procured competitively by distribution licensees
Even for Public Sector Projects tariff shall be decided on basis ofcompetitive bidding after 5 yrs or when Commission is satisfiedfor introduction of such competition
-
The guidelines are applicable for procurement of power
Tariff Based Bidding GuidelinesThe guidelines are applicable for procurement of powerthrough competitive bidding through the followingmechanismmechanism
PeriodofProcurement
LongTerm MediumTerm
M h i
7years&above >1yearupto7years
Mechanisms
Case 1 Case 2Case Case
-
C titi T iff B d Biddi i C lC titi T iff B d Biddi i C l ff J 2011J 2011
BiddingMechanismsBiddingMechanisms
CompetitiveTariffBasedBiddingisCompulsoryCompetitiveTariffBasedBiddingisCompulsoryw.e.fw.e.f.January2011.January2011
C IC I C IIC IICaseICaseI CaseIICaseII
Location/Location/BidderisBidderis
responsibleforresponsibleforll lll l
Land/FuelLand/Fuelspecifiedbyspecifiedbyprocurerprocurer
ClearancesClearancesprovidedbyprovidedby
Technology/Technology/FuelunspecifiedFuelunspecified(PowerBlock)(PowerBlock)
allclearancesallclearancesetc.etc.
HighRiskforHighRiskfordevelopersdevelopers
MoreapplicableMoreapplicableforstateswithforstateswithfuelsourcesandfuelsourcesand
statestate
HighriskforHighriskforstatestate
developersdevelopers coastalareascoastalareas
Source:CERC
-
Mechanism
MechanismofTariffBasedBidding
CaseI
Location,Technologyorfuelnotspecified
CaseII
Location,Technology&Fuelarrangement specifiedp arrangementspecified
CaptivecoalblocktobedevelopedbytheSeller
SpecificCoallinkageprovidedbyProcurer
ImportedCoaltobearrangedby
thesellerFuelSource
Energy Energychargesbasedon quoted Net Heat
Importedfuel&Transportationcomponentin
USD/unitEnergy ChargesinRs/KWh
onquotedNetHeatRate
USD/unit.
InlandfuelhandlingcomponentinIndian
Rupees/unit
EnergyCharge
-
BiddingProcessCase1
SingleStage SingleStage
Case2
TwoStage TwoStage Medium&LongTerm RequestforProposal Max Time: 195 days
Medium&LongTerm RequestforProposal Max Time: 195 days
LongTerm RequestforQualification&Request for Proposal
LongTerm RequestforQualification&Request for Proposal MaxTime:195days MaxTime:195days RequestforProposal
MaxTime:730daysRequestforProposal
MaxTime:730days
PeriodofProcurementPeriodofProcurement
LongTerm:Above7Years Medium Term: 1 Year to 7 Years(Usuallyupto lifeofplant) MediumTerm:1Yearto7Years
Approval of the Appropriate Regulatory Commission isDeviation ApprovaloftheAppropriateRegulatoryCommissionisrequiredintheeventofthedeviationfromthebiddingconditionscontainedintheguidelines
Deviationfrom
Guidelines
-
Bidding Process Two stage bidding process is to be adopted forLong Term procurement of electricity biddingunder case2i. Request for Qualification (RFQ)ii. Request for Proposal (RFP)
Single stage bidding process combining the RFPSingle stage bidding process combining the RFP& RFQ process may be adopted for biddingunder Case1 for Medium/Long Termunder Case 1 for Medium/Long Termprocurement of electricity
-
Preparation for Inviting BidsFor Long term procurement under Case2 Procurer orAuthorized Representative shall complete the followingactivities before issue of RFQ documentsactivities before issue of RFQ documents
Site identification and land acquisition: Issue ofSite identification and land acquisition: Issue ofNotification under Section4 of Land AcquisitionAct, 1894 Environmental clearance for Power Station: Rapid EIAreport should be availableF l li k C ti l i Sh ld b il bl Fuel linkage or Captive coal mine: Should be available(If bidders to arrange the same shall be clearlyspecified in the RFQ)specified in the RFQ) Water linkage should be available
-
1 Fi i l Q lifi ti
RFQ Bid Submission for Project1. FinancialQualification
InternalResourceGeneration 1140CrsN t W th 1000 C NetWorth 1000Crs
AnnualTurnOver 2400Crs
2 Technical Qualification2. TechnicalQualification AggregateCapitalCostofProjectsundertakeninLast10
years 3000 Crs (with 26% equity stake)years 3000Crs(with26%equitystake)
CapitalCostofatleastoneProject 500Crs
3 Executive Summary3. ExecutiveSummary
4. DisclosureStatements
5 P f A5. PowerofAttorney
6. CoveringLetter
-
UMPP Case2
Qualifying RequirementsS.N. RFQ:
URsCrs
CaseRsCr/MW
FinancialRequirements
1 InternalResourceGeneration 1140 0.3
2NetWorth(forcapacityupto2000MW) 0.5 ForCase1(0.5Cr/MW)
3NetWorth(forcapacity>2000MW) 1000 0 25 1000 C hi h i hi h3 MW) 1000 0.25 or1000Crwhicheverishigher
4AnnualTurnover(forcapacityupto 2000MW) 1.2
Annual Turnover (for capacity5
AnnualTurnover(forcapacity>2000MW) 2400 0.6 or2400Crwhicheverishigher
6 TechnicalRequirements 3000 0.75AggregateCapitalCostofProjectsundertakeninLast10years
500 0.125 Capitalcostofatleast1project
GuaranteesRFP:
RsLakh/MW
1 BidBond 120 3 ForCase1(3Lakh/MW)
2 PerformanceGuarantee 300* 7.5 ForCase1(30Lakh/MW)
-
Preparation for Inviting BidsFor Long term procurement under Case2 Procurer orAuthorized Representative shall complete the followingactivities before issue of RFP documentsactivities before issue of RFP documents
Site identification and land acquisition: Issue of Notification underqSection 6 of Land Acquisition Act, 1894 Environmental clearance & Forest clearance for the PowerStation: Proposal should be submitted before concernedStation: Proposal should be submitted before concernedAuthority (Environment clearance should be obtained before PPAbecomes effective)
il d j ( ) i i Detailed Project Report (DPR): RequisiteHydrological, geological, meteorological and seismological datanecessary for preparation of DPR (bidder to verify these data asfthe geological risk lie with the developer)
-
f dd d l h ll
Preparation for Inviting BidsFor Case1 if Bidder intends to set new power plant shallsubmit documentary evidence w.r.t the following activitiesalong with RFP bidalong with RFP bid
Site identification and land acquisition: Should possess 50% ofrequired land (If land is to be acquired under LA Act 1894, copy ofNotification under Section 4 to be submitted) Environmental clearance & Forest clearance for the PowerEnvironmental clearance & Forest clearance for the PowerStation: Proposal should be submitted before concernedAuthorityF l A t C ti i / l li k / i t d l/ Fuel Arrangements: Captive mine/coal linkage/ imported coal/Domestic gas/ RLNG Water Linkage: Shall have acquired approval from concerned stateirrigation department /relevant authority
-
The RFP bid to be submitted in two parts Financial and Non
RFP Bid Submission for ProjectThe RFP bid to be submitted in two parts, Financial and Nonfinancial bidsNonFinancial Bid
Board Resolution from bidding company committingBoard Resolution from bidding company committing100% equity requirement
Bid Bond Bidder Undertaking along with scheduled COD date andBidder Undertaking along with scheduled COD date and
Contract Capacity of each unit Covering letter
Power of Attorney Power of Attorney Disclosure Statement
Financial BidThe financial bid shall consist of quote for the capacity charges andThe financial bid shall consist of quote for the capacity charges andenergy charges in two parts, NonEscalable Charges and EscalableChargesThe Bidder has the option to quote firm Quoted Energy ChargesThe Bidder has the option to quote firm Quoted Energy Chargesand/or firm Quoted Capacity Charges for the term of the PPA
-
Event Elapsed Time from Zero date
Time Table for Two Stage Bid ProcessEvent Elapsed Time from Zero date
Publication of RFQ Zero date
Submission of Responses of RFQ 45 days
Issuance of RFP 75 days
Bid clarification, bidders conf. etc.and revision of RFQ/RFP
*
RFP bid b i i dRFP bid submission 225 days
Evaluation of bids and issue of LOI 240 days
Si i f A t dSigning of Agreements 270 days
If bidding process is likely to take more than 730 days approval ofA i t C i i h t b bt i dAppropriate Commission has to be obtained.
-
Time Table for Single Stage Bid Process
Event Elapsed Time from Zero date
Publication of RFP Zero datePublication of RFP Zero date
Bid clarification, bidders conf. etc.and revision of RFQ/RFP
**and revision of RFQ/RFP
RFQ/RFP bid submission 75days
Evaluation of bids and issue of LOI 100 daysEvaluation of bids and issue of LOI 100 days
Signing of Agreements 120 days
If bidding process is likely to take more than 195 days approval ofAppropriate Commission has to be obtained.
-
TARIFFSTRUCTURE A multitariff structure with separate capacity and energy
charges forms the basis of the bidding process
In case of Case2 projects where the procurer provides the fuellinkage, bidder is required to submit the capacity charges alongwith the net heat rate
-
Tariff BidsScenario-1 (Captive Coal Block Allocated)
ContractYear
Commencement Date ofContract Year
End Date ofContractYear
Quoted NonEscalableCapacity
QuotedEscalableCapacity
Quoted NonEscalableEnergy
QuotedEscalableEnergy
( p )
Charges(Rs./kwh)
Charges(Rs./kwh)
Charges(Rs./kwh)
Charges(Rs./kwh)
1 S h d l d M h 311 ScheduledCOD of 1st
Unit
March 31
2 April 1 March 31 Same as Same as2 April 1 March 31 Same asabove
Same asabove
April
March 31 Same asabove
. Same asabove
26 April 1 25th
anniversaryof theScheduled
Same asabove
Same asabove
ScheduledCOD of 1st
Unit
-
Tariff BidsScenario-2 (Imported Coal)
ContractYear
Commencement Dateof
EndDateofContra
QuotedNonEscalableCapacity
QuotedEscalableCapacity
QuotedNonEscalable Fuel
QuotedEscalableFuelEnergy
QuotedNonEscalableTransporta
QuotedEscalableTransportation Energy
QuotedNonEscalableFuel
QuotedEscalableFuelHandling
( p )
Contract Year
ct Year Charges(Rs./kwh)
Charges(Rs./kwh)
EnergyCharges(US$/kwh)
Charges(US$/kwh)
tion EnergyCharges(US$/kwh)
Charges(US$/kwh)
HandlingEnergyCharges(Rs./kwh)
EnergyCharges(Rs./kwh)
1 Schedul Marched CODof 1stUnit
31
2 April 1 March31
Same asabove
Same asabove
Same asabove
Same asabove31 above above above above
. April
March31
Same asabove
Same asabove
Same asabove
Same asabove
26 April 1 25th Same as Same as Same as Same asanniversaryof theScheduledCOD
above above above above
40
CODof 1st
Unit
-
Tariff BidsScenario-3 (Coal Arranged by Seller)
Contract
Commencement Date of
End Dateof Contract
QuotedNon
QuotedEscalable
Quoted NonEscalable
QuotedEscalable
( g y )
actYear
t Date ofContract Year
of ContractYear
NonEscalableCapacityCharges(Rs./kwh)
EscalableCapacityCharges(Rs./kwh)
EscalableEnergyCharges(Rs./kwh)
EscalableEnergyCharges(Rs./kwh)
(Rs./kwh)
1 Scheduled CODof first Unit
March 31
l h2 April 1 March 31 Same asabove
Same asabove
April
March 31 Same asabove
. Same asabove
26 April 1 25th
anniversaryof theScheduled
Same asabove
Same asabove
ScheduledCOD of firstUnit
-
Tariff BidsScenario-4 (Coal Arranged by Procurer)
ContractYear
CommencementDate of Contract
End Date ofContract Year
Quoted NonEscalable
QuotedEscalable
Quoted HeatRate
( g y )
Year Date of ContractYear
Contract Year EscalableCapacityCharges(Rs./kwh)
EscalableCapacityCharges(Rs./kwh)
Rate(Kcal/kwh)
h d l d f h1 Scheduled COD of1st Unit
March 31
2 April 1 March 31 Same as above Same as above
April. March 31 Same as above Same as above
26 April 1 25th
anniversaryof theS h d l d
Same as above Same as above
ScheduledCOD of 1st
Unit
-
Th l t d Q t d T iff ( R kWh) f h f th
Bid Evaluation for the ProjectThe escalated Quoted Tariffs ( Rs per kWh) of each of thecontract year for the term of PPA calculated as per theRFP shall be discounted by the discount factors and suchRFP shall be discounted by the discount factors and suchaggregate discounted value for the term of the PPA shallbe divided by the sum of such discount factors tobe divided by the sum of such discount factors tocalculate the levelised tariff of each Bidder
Di)(Ti
The Levelised Tariff calculated as above shall be ranked
=Di
Di).(TiLT
The Levelised Tariff calculated as above shall be rankedfrom the lowest to the highest and the Bidder withlowest Levelised Tariff shall be declared as the SuccessfulBidder
-
LEVELISEDTARIFF
LEVELISED TARIFF = Net Discounted Tariff* Net Discount Factor**
*Net Discounted Tariff = Tariff / (1+ Discount factor) ^n**Net Discount Factor = 1/ (1+ Discount Factor) ^n
CERC NOTIFICATIONS:Discount rate Escalation rate for coal Dollar Rupee FERVDiscount rate , Escalation rate for coal, Dollar Rupee FERV,
Inflation rate updated by CERC every six months
-
Year Commen.of Contract
End Date of Contract
Non-Escalabl
Escalable C.C
Non-Indexed
Indexed E.C
Total Tariff
Financial Bid for Tilaiya- Reliance
1 24-Nov-14 31-Mar-15 0.51 0.17 0.38 0.13 1.192 1-Apr 31-Mar 0.50 0.18 0.86 0.14 1.683 1-Apr 31-Mar 0.68 0.19 0.85 0.15 1.874 1-Apr 31-Mar 0.68 0.20 0.84 0.16 1.885 1-Apr 31-Mar 0 68 0 20 0 83 0 17 1 895 1 Apr 31 Mar 0.68 0.20 0.83 0.17 1.896 1-Apr 31-Mar 0.68 0.22 0.82 0.18 1.907 1-Apr 31-Mar 0.68 0.23 0.81 0.19 1.918 1-Apr 31-Mar 0.68 0.24 0.80 0.20 1.929 1-Apr 31-Mar 0.51 0.25 0.79 0.21 1.9310 1 A 31 M 1 9410 1-Apr 31-Mar 0.68 0.26 0.77 0.23 1.9411 1-Apr 31-Mar 0.68 0.27 0.85 0.24 1.9612 1-Apr 31-Mar 0.68 0.29 0.74 0.26 1.9713 1-Apr 31-Mar 0.39 0.30 0.73 0.27 1.7014 1-Apr 31-Mar 0.38 0.32 0.71 0.29 1.7015 1-Apr 31-Mar 0.36 0.33 0.69 0.31 1.7016 1-Apr 31-Mar 0.35 0.35 0.67 0.33 1.7017 1-Apr 31-Mar 0.34 0.37 0.65 0.35 1.7018 1-Apr 31-Mar 0.31 0.39 0.63 0.37 1.7019 1-Apr 31-Mar 0.31 0.40 0.60 0.40 1.7220 1-Apr 31-Mar 0.31 0.42 0.58 0.42 1.7421 1-Apr 31-Mar 0.31 0.45 0.55 0.45 1.7622 1-Apr 31-Mar 0.31 0.47 0.52 0.48 1.7823 1-Apr 31-Mar 0.29 0.49 0.49 0.51 1.7824 1-Apr 31-Mar 0 27 0 52 0 46 0 54 1 7924 1 Apr 31 Mar 0.27 0.52 0.46 0.54 1.7925 1-Apr 31-Mar 0.25 0.54 0.43 0.57 1.7926 1-Apr 25th
f0.41 0.56 0.40 0.60 1.97
Levelised Tariff (Rs./kWhr) 1.77
-
Sites Selected for UMPP Development
UltraMegaPowerProjectsbasedonCaptiveMineallocation
Project NameoftheShellCompany( ) dSasan (M.P) Sasan PowerLimited.
AwardedtoReliancePowerLimitedwithLevellisedtariffofRs1.196/kWh
Tilaiya(Jharkhand) JharkhandIntegratedPowerLimited
AwardedtoReliancePowerLimitedwithLevellisedtariffofRs1.77/kWh
Surguja(Chhattisgarh) ChhattisgarhSurguja PowerLimited
Bedabahal(Orissa) OrissaIntegratedPowerLimited
O i S khi l I d P C Li i dOrissa Sakhigopal IntegratedPowerCompanyLimited
Orissa Ghogarpalli IntegratedPowerCompanyLimited
-
Sites Selected for UMPP Development
CoastalUltraMegaPowerProjectsbasedonImportedCoal
Project NameoftheShellCompanyd ( ) l dMundra (Gujrat) CoastalGujaratPowerLimited
AwardedtoTataPowerLimitedwithLevellised tariffofRs2.260/kWh
Krishnapatnam(A.P) CoastalAndhraPowerLimited
AwardedtoReliancePowerLtd.withLevellised tariffofRs2.333/kWh
Cheyyur(Tamilnadu) CoastalTamilNaduPowerLimited
Nainapalli(A.P) Tatiya AndhraMegaPowerLtd.
(M h h ) C l M h h M P Li i d(Maharashtra) CoastalMaharashtraMegaPowerLimited
(Karnataka) CoastalKarnatakaPowerLimited
The Govt. of Gujrat has requested for Second UMPP in the State.
-
A Glance at Awarded Power ProjectsThrough Case 2 Competitive Bidding Route
-
A Glance at Awarded Power ProjectsThrough Case 1 Competitive Bidding Route
-
50