Construction Update Meeting
March 16, 2016
Oakland Children’s Hospital
3
• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland
• Richard West and Tony Solano – JLL
• Darrel Graef, Tyler Hester – Project Superintendent, Turner Construction Company
• Ed Walsh and Abhishek Gupta – Turner Construction Company
Welcome
4
UCSF Benioff Children’s Hospital / Turner – General Discussion
Project Communication
Upcoming Construction Activities
Agenda
5
• Project Communication
• Project Communication– Darrel Graef (Turner Supt) 510-764-3059– Flyers and Project Website
• notifications of change to site conditions as it pertains to the neighborhood
• http://chonext100.org
• Concerns/Issue Reporting—Contact information are posted on Site Signage and Project Website
Communication & Reporting
6
• Complete pile operation at OPC 2 site.• Start installing pile caps.• The new crosswalk/traffic light update.• Structural Steel to start at the end of March.
Upcoming Major Construction Activities
Overall Site Plan
New Proposed Crosswalk
9
Video presentation by Chris BroomeQuestions/Discussion?
10
Projected Business Participation*Local Goal = 47% Projected = 44%
Oakland Contractors = 18%Small Contractors = 36%
Minority Contractors = 9%Women Contractors = 1%
*based on actual and expected contract awards to 31 prime subcontractors through March 2016
Oakland Children’s Hospital
Oakland Children’s Hospital