Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug...

15
Commissioning of an office building Guruprakash Sastry Regional Manager Infrastructure [email protected]

Transcript of Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug...

Page 1: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Commissioning of an office building

Guruprakash Sastry

Regional Manager – Infrastructure

[email protected]

Page 2: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

A typical office building 2

Time

Design phase

Construction phase

Occupancy

Page 3: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

The problem

• Commissioning of a building is the most neglected

– No time?

– No interest? (O&M teams are happy if comfort is met)

– No understanding – commissioning for most people is ‘switching on’ equipments.

• Efficiency is a design issue only !

• Commissioning agent – one more vendor?

• HVAC contract split into many vendors for “commercial reasons” – single point

responsibility for the system missing.

3

Page 4: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Examples

Case 1

• VAVs

– VAV supplied by one vendor

– VAV installation by another vendor

– BMS integration by a third vendor

– How to ensure efficiency of the

system?

4

Page 5: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Examples

Case 2

• Chilled beams

– Technical details sometimes missed out

by consultants

– Chamber pressure Vs air flow Vs

nozzle type

– How to ensure efficiency of the

system?

5

Page 6: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

HVAC Optimization

Reduce Heat Gain

Energy simulation

Efficient heat

transfer mechanism

Efficient system

Equipment configuration

Efficient equipment

Control strategy

Continuous monitoring

HVAC energy

6

Optimization strategy

Page 7: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Day lighting and Glare control – Glass and shading

Day light pane

View pane

External shading

Smart glazing

7

Page 8: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

8

I Innovation-x Impact of day lighting 8

Page 9: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Lighting system design & operation 9

1,2

0,68

0,5 0,45

0

0,2

0,4

0,6

0,8

1

1,2

1,4

Average 2007levels

SDB-5 MYS SDB-1 TVM SDB-1 HYD

W/s

qft

Installed Lighting Power (W/sqft)

0,45

0,17

0

0,2

0,4

0,6

0,8

1

1,2

1,4

Average 2007 levels SDB-1 HYD

W/s

qft

Operating Lighting power (W/sqft)

Page 10: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Design Vs Actual

Efficiencies

Benchmarking

Monitoring of key parameters – over time 10

Page 11: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

11

Monitoring of key parameters – over time

16 11 2013

11

Page 12: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

12

Monitoring of key parameters – over time

Page 13: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Recommendations

• Get the commissioning team on board at design stage – earlier the better

• Commissioning should be followed by continuous monitoring

• Energy meters for every major equipment

– HVAC system – chillers, pumps, fans

– Lighting feeder

– Other feeders like UPS, plug loads, misc.

• Continuous monitoring of key parameters (hourly) Vs design.

– kW/TR of HVAC system

– Operating LPD of lighting

– EPI of the building (kWh/sqm per year) to be monitored against design/simulation

– Acceptable deviation to be defined

13

Page 14: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

Building energy performance 14

An

nu

al

kW

h/s

qm

2008

Page 15: Commissioning of an office building - REHVA · 2014-06-23 · –Other feeders like UPS, plug loads, misc. •Continuous monitoring of key parameters (hourly) Vs design. –kW/TR

© 2013 Infosys Limited, Bangalore, India. All Rights Reserved. Infosys believes the information in this document is accurate as of its publication date; such information is subject to change without notice. Infosys acknowledges the proprietary rights of other companies to the trademarks, product names and such other intellectual property rights mentioned in this document. Except as expressly permitted, neither this documentation nor any part of it may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, printing, photocopying, recording or otherwise, without the prior permission of Infosys Limited and/ or any named intellectual property rights holders under this document.

Thank You