Comments of CLECA on RETI Draft Phase 1A Report of CLECA on RETI Draft Phase 1A Report ......
Transcript of Comments of CLECA on RETI Draft Phase 1A Report of CLECA on RETI Draft Phase 1A Report ......
Comments of CLECA on RETI Draft Phase 1A Report
The California Large Energy Consumers Association, California Manufacturers & Technology Association, and The Utility Reform Network (TURN) (hereafter called the Customer Group) jointly offer these comments on the Renewable Energy Transmission Initiative (RETI) Draft Phase 1A Report. The California Large Energy Consumers Association (CLECA) represents the interests of a group of large, high load-factor, process-type, industrial electricity consumers on electricity regulatory matters. The California Manufacturers & Technology Association (CMTA) represents the interests of a diverse group of manufacturers operating in California on numerous policy matters. The Utility Reform Network (TURN) represents the interests of residential and small commercial consumers on a broad array of utility matters.. As customers, we are greatly interested in the cost and benefits of the entire array of electricity resources available to serve the state. Each member of the Customer Group has been actively involved in proceedings before the California Public Utilities Commission addressing cost-effectiveness and valuation of supply- and demand-side resources. Against this background, the Customer Group offers these brief comments on the methodology proposed to address the costs and value associated with adding renewable resources to the mix serving California.
The Customer Group’s concerns lie in three areas:
1. Evaluation of resources in the entire west in terms of what % they represent of 2020 California Load.
This concept implies an assumption that all of these resources are available to serve California load. However, this is clearly not the case. The Customer Group believes it would be better to factor in an assumption that other western state and British Columbia will adopt their own renewable portfolio requirements (RPS) and that only a portion of these resources will be available to serve California load.
2. Lack of assumptions for integration costs.
Recent studies performed by the CEC and the CAISO indicate that there will be substantial integration issues associated with incorporating intermittent renewable resources into the supply mix in California, including substantial additional requirements for ramping and quick-start capability. CLECA believes that information on integration costs must be developed in order to properly conduct evaluations among renewables resources. We have attached a study done for ERCOT on wind integration which includes some preliminary cost estimates. However, we agree that more analysis is needed.
3. Incorrect formulation of Capacity Value of New Resources
The Phase 1A Report values the capacity of new generation resources using a $204/kW-year figure from the CEC Cost of new Generation report. We have two concerns with the use of this figure. First, it is widely believed to be too high. As a contrast, Southern California Edison Company (SCE) has used an annualized value of a new CT of $102/kW-year, in 2009 $. The installed cost used by SCE is $705/kW. In contrast, the installed cost used by the CEC is $800-1053/kW in 2007 $ and the levelized cost is $212-253/kW-year. In the PJM RTO, there have been major protests to an effort by PJM to raise the cost of new entry in 2010-2011 (a figure based on the cost of a new CT), to $104/kW-year from $72.2/kW-year. While recognizing that levelized cost and RECC cost are not equivalent, there is enough of a difference here and enough debate over the CEC figure that, at a minimum, there should be a sensitivity analysis done around the capacity value used.
Second, it has become a commonly-used methodology to subtract the value of energy and ancillary services sold by a CT (this is sometimes called the “gross margin”) from the cost of a CT in order to determine the marginal capacity cost or avoided capacity cost, which may be considered the capacity value. Otherwise, the argument is made that the energy value is included twice, first in the capacity value unless the adjustment for sale of energy and ancillary services is made, and then again in the separate determination of energy value. For example, a settlement submitted by numerous parties to the CPUC on cost-effectiveness for demand response, stated the following:
“The generation capacity costs avoided by a DR program will be based on the annual market price ($/kW-year) of the capacity of a new combustion turbine The generation capacity costs avoided by a DR program will be based on the annual market price ($/kW-year) of the capacity of a new combustion turbine (CT), annualized using a real economic carrying charge rate that takes into account return, income taxes, and depreciation, with O&M, ad valorem and payroll taxes, insurance, and similar incremental costs added, and reduced to reflect expected “gross margins” earned by selling energy (“CT cost”). PG&E proposes to calculate “gross margins” based on an options pricing methodology, whereas SCE proposes to calculate “gross margins” based on the results of production cost modeling exercises.” (“JOINT COMMMENTS OF CALIFORNIA LARGE ENERGY CONSUMERS ASSOCIATION, COMVERGE, INC., DIVISION OF RATEPAYER ADVOCATES, ENERGYCONNECT, INC., ENERNOC, INC., ICE ENERGY, INC., PACIFIC GAS AND ELECTRIC COMPANY (U 39-M), SAN DIEGO GAS & ELECTRIC COMPANY (U 902-E), SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) AND THE UTILITY REFORM NETWORK RECOMMENDING A DEMAND RESPONSE COST EFFECTIVENESS EVALUATION FRAMEWORK”, dated November 19, 2007, in R. 07-01-041, pp. 2-3 in Attachment A, emphasis added).
In conclusion, the Customer Groups agree with the draft report that it is important to develop a method to “measure the economics of resources on a consistent basis” (page 3-24). Customers will be best served by a resource valuation process that allows an “apples to apples” comparison to be applied in the selection process for renewable resources. Such a valuation process should also be consistent with valuation processes used for other resources in the state. The valuation method developed by Black & Veatch is a good starting point, but we believe that the methodology needs to be revised as we have described in order to identify the resources “with the lowest cost and highest value” to the California grid. Since customers bear ultimate responsibility for all the costs of acquiring renewables, customers also have an interest in assuring that any valuation methodology is complete and accurate. Dr. Barbara R. Barkovich, on behalf of the California Large Energy Consumers Association Karen Lindh, on behalf of the California Manufacturers &Technology Association Michael Florio, on behalf of The Utility Reform Network
2 /
Project Scope
Evaluate the impacts of wind development in the ERCOT system on ancillary services requirements and related practices.Specifically:• Evaluate the suitability of ERCOT’s existing
practices for determining A/S procurement• Recommend improvements to accommodate wind
penetration• Determine amount and estimated cost of A/S
requirements for various wind scenarios• Recommend procedures for impending severe
weather
3 /
A Few Words About Net Load
Net Load is the instantaneous system consumer load, minus the generation output of non-dispatchable wind generation
Net load* is the amount of generation required from dispatchable units
The study is concentrated on net load, instead of the wind generation in isolation, because some amount of the variations in each cancel
* Net load is also called “Load – Wind” in parts of this presentation
4 /
Project Overview
Phase 1 - Net Load Variability and Predictability CharacterizationObjective is to obtain fundamental qualitative and quantitative information on
the characteristics and predictability of net load in the ERCOT system.– Comparison of wind development scenarios– Correlations of variability and predictability with load level,
season, time of dayThe insights obtained in this analytic investigation help to identify system
operating challenges and determine when they will occur
Phase 2 - Ancillary Services EvaluationEvaluate A/S requirements and recommend improvements to ERCOT’s A/S
procedures– A/S requirements as a function of wind penetration– Evaluate existing methodologies to determine A/S needed– Recommend changes to accommodate wind– Evaluate and improve practices for impending severe weather
5 /
Analysis Approach
• Construct system load, wind generation, and net load model time series database
• Time series analysis– Characterize impact on load curve– Daily maxima and minima– Net load ramp rates
• Statistical analysis of variability– Analyze variations over different timeframes– Analysis of operating periods with particular challenges
• Model and analyze regulation requirements– Regulation requirements– Regulation procurement procedure
• Extreme wind analysis – responsive reserves • Analysis of day-ahead prediction error
– Impacts on non-spin reserve requirements
6 /
Net Load Model
• Two years of data used– More accuracy and consistency– Two consecutive years needed later in Phase 2 for testing A/S
methodology• Essential for system load and wind generation data to be for consistent
time period– Common factors affect both wind and load
• System one-minute load data– Based on 2005 and 2006 ERCOT historical recordings– 2006 data scaled up to achieve average load (energy) consistent
with 2008 ERCOT predictions – “Study Year”– 2005 data scaled by the same factor – “Previous Year”– Scale factor = 1.037, computed from the average ratio of forecasted
2008 load to 2006 actual load across all hours – Day-ahead load forecasts provided by ERCOT
7 /
Wind Generation Model
• Wind data developed for 2005 and 2006 by AWS Truewind– Hourly meso-scale weather model– Wind generation output defined for multiple individual hypothetical
wind plants in each CREZ– Minute-by-minute variations synthesized based on ERCOT wind
data for seventeen existing sites (2 years of data)– Wind data for other time-frames (5-minute, 15-minute, 30-minute)
obtained by integrating 1-minute data• CREZ scenarios developed
– 5000 MW, 15000 MW and two 10000 MW scenarios – Wind capacity totals per CREZ per ERCOT selection (next slide)– Wind plants added to CREZ portfolio in order of decreasing annual
capacity factor (most productive sites used first)– Plant capacity scaled up to produce desired output for CREZ
• Day-ahead wind generation predictions synthesized by AWS Truewind
8 /
CREZ Scenarios
Wind Development Scenario CREZ Zone 5000 MW 10,000 MW (1) 10,000 MW (2) 15,000 MW
none 120 120 120 120 2 60 1,560 1,560 2,340 4 0 1,500 0 0 5 355 1,355 1,355 1,355 6 400.5 400.5 400.5 1,278.3 7 65 65 65 97.5 9 814 1,314 1,314 1,971
10 2,464.5 2,964.5 2,964.5 4,446.8 12 400 400 400 600 14 160 160 160 240 15 60 60 60 90 19 101 101 101 211.5 24 0 0 1,500 2,250
Difference in two 10,000 MW scenarios is that the second has 1,500 MW of wind generation in the Gulf coastal area, substituting for a like amount in the panhandle
11 /
In this next set of slides, we will show how wind and load interact to create the net load curves.
Key issues are:• Impacts on net load peaks and valleys• Increases in ramp rates• Common factors affecting wind and load
12 /
Wind and Load (15,000 MW Wind Scenario) (Study Year Hourly Data)
Load-15,000 MW Wind - April Time Series Plot
0
10000
20000
30000
40000
50000
60000
70000
1-Apr
8-Apr
15-Apr
22-Apr
29-Apr
Day
MW
-1000
4000
9000
14000
19000
24000
29000
34000
LoadWind
Load
MW
Win
d M
W
Both wind and load have variability(note that the wind curve is on the right-hand scale and thus its dynamic range is amplified two times)
13 /
Average April Daily Load and Wind Profile (15,000 MW Wind)2008 Load-15,000 MW Wind - April Daily Profile
20000
25000
30000
35000
40000
45000
50000
55000
60000
65000
0 4 8 12 16 20 24Hour
MW
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
LoadWind
(Study Year Hourly Data)
Load
MW
Win
d M
W
• Wind is generally out-of-phase with load• Sharp drop in wind in the morning when load is rising• Sharp wind increase when load drops sharply in the
evening
14 /
Daily Curve From One-Minute Data (Study Year Hourly Data, 15000 MW Scenario)
Typical Spring Day (April 23)
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 0:00
Hour of Day
Load
, Win
d, a
nd N
et L
oad
(MW
)LoadWindLoad-Wind
• Curves are quite smooth, wind appears smoother• Diversity smoothes out wind, just as it does for loads
15 /
Net Load (15,000 MW Wind Scenario) (Study Year Hourly Data)
Load-15,000 MW Wind - April Time Series Plot
0
10000
20000
30000
40000
50000
60000
70000
1-Apr
8-Apr
15-Apr
22-Apr
29-Apr
Day
MW
WindLoadNet Load
• Load peaks are reduced, some days more than others• Valleys are greatly deepened
16 /
Net Load Comparisons – One January Week (Study Year Hourly Data)
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
15-Jan
16-Jan
17-Jan
18-Jan
19-Jan
20-Jan
21-Jan
22-Jan
Day
MW
Load5,000 MW10,000 MW (1)10,000 MW (2)15,000 MW
Increased ramp rate
Increased daily range
• Curve shape is relatively similar for all scenarios• Peak-to-valley change increases with wind generation• Result is ramp rates increasing with more wind
17 /
Net Load Comparisons – One April Week (Study Year Data)
10000
15000
20000
25000
30000
35000
40000
45000
50000
55000
60000
13-Apr
14-Apr
15-Apr
16-Apr
17-Apr
18-Apr
19-Apr
20-Apr
Day
MW
Load5,000 MW10,000 MW (1)10,000 MW (2)15,000 MW
Thursday Wednesday
0
10000
20000
30000
40000
50000
MW
Load
Wind (15 GW Scenario)
Net Load
Load dip
Wind spike
• Perturbation in both wind and load at the same time, likely from common source (e.g., cold front)
• Valid analysis requires synchronized load and wind data
18 /
In summary:
• Both wind and load are variable– Daily wind generation cycle is generally out-of-phase
with load– Shorter term variations tend to be less correlated
• Common factors affect both wind and load– Wind impacts cannot be correctly considered
independently of load behavior
20 /
In the next series of slides, time periods with critical operating situations are identified and the impacts of wind are illustrated by time series plots (all with the 15000 MW scenario to more clearly demonstrate wind impacts)Critical situations include: • Maximum system load• Minimum net load• Maximum net load• Most variable day
21 /
Profiles of Daily Average Load and Net Load and 1-Hour Deltas(Study Year Data, 15000 MW Scenario)
-18000
-12000
-6000
0
6000
12000
18000
24000
30000
36000
42000
48000
54000
Load
and
Net
Loa
d (M
W)
-8000
-5000
-2000
1000
4000
7000
10000
13000
16000
19000
22000
25000
28000
Max
/Min
of O
ne-H
our D
elta
s (M
W)
LoadLoad-WindMax Load-Wind 1Hr DeltasMin Load-Wind 1Hr Deltas
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Winter
Spring
Summer
Fall
Largest Net-Load Delta Day May 8th
Peak Load Day August 17th
Min Load Day Mar 27th
These are the maximum and minimum deltas (derivative of hourly load curve) for each day
These are average loads and net loads for each day (equal to daily MWh/24)
• Basis for selection of key dates for further illustration and analysis
22 /
Largest Net-Load Delta Day - Profiles and Deltas (Study Year Data, 15000 MW Scenario)
Largest Net-Load Delta Day (May 8)
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour of Day
Load
and
Net
Loa
d (M
W)
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
12000LoadLoad-WindWind (15000 MW)Load 1Hr DeltasLoad-Wind 1Hr Deltas
4-hr peak shift
~5900 MW
~6300 MW
~5000 MW
One
-Hou
r Del
tas
(MW
)
• Wind drop in evening before load drop causes a late peak in net load, with resulting increases in ramp rates
23 /
Most Variable* Day - Profiles and 1-Hour Deltas (Study Year Data, 15000 MW Scenario)
Most Variable Net Load Day (July 12)
0
7000
14000
21000
28000
35000
42000
49000
56000
63000
70000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour of Day
Load
and
Net
Loa
d (M
W)
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
10000
12000
One
-Hou
r Del
tas
(MW
)
LoadLoad-WindWind (15000 MW)Load 1Hr DeltasLoad-Wind 1Hr Deltas
34350 MW rise over 12 hours (~2900 MW/Hr)
27560 MW drop over 8 hours (~3500 MW/Hr)
* Largest net-load sigma
• Anti-correlation of diurnal load and wind curves cause severe morning and evening ramps
24 /
In summary:• Wind has the greatest impact on hour-to-hour net load
variation in the late spring and summer– Strong coincidence of wind drop-off with
morning load pickup– Strong coincidence of wind pickup with evening load
drop-off– Larger day vs. night net load swing results in greater
ramp rates • Variations in the winter and early spring may be more
operationally significant, however, due to low net load levels• Net load peaks can be shifted to unusual times of day by
wind changes with high penetration
26 /
Statistical analysis of the load and net load variability is shown in the next series of slides, for different timeframesSome explanations and points to consider:• Deltas are the changes in average net load
for successive periods – (1, 5, 15, and 60 minutes considered in this study)
• Average deltas over a day or longer period are inherently near zero, so the standard deviation of the deltas are used as a measure of variability
• Deltas include both the effects of longer-cycle ramping as well as random “jitter”
27 /
One-Minute Load-Wind Variability (Study Year Data, 15000 MW Scenario)
-39.2 / 38.1-33.6 / 33.0Mean(-/+ Deltas)
491.6
-513.7
43.22
Load-alone (MW)
-552.6Min. Delta
Max. Delta
Sigma (Delta)
538.3
49.67
With Wind (MW)
Statistical Summary
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
< -240
-240 – -224
-224 – -208
-208 – -192
-192 – -176
-176 – -160
-160 – -144
-144 – -128
-128 – -112
-112 – -96
-96 – -80
-80 – -64
-64 – -48
-48 – -32
-32 – -16
-16 – 0
0 – 16
16 – 32
32 – 48
48 – 64
64 – 80
80 – 96
96 – 112
112 – 128
128 – 144
144 – 160
160 – 176
176 – 192
192 – 208
208 – 224
224 – 240
> 240
MW
Num
ber o
f One
-Min
ute
Perio
ds Load - WindLoad
Greatest difference between net load and load alone is in the downward change direction
111 / 13979 / 87105 / 129>µ ± 6σ (−/+)
3593 / 27691517 / 12391711 / 1435>µ ± 3σ (−/+)
571 / 551247 / 297338 / 391>µ ± 4σ (−/+)
9277 / 74084604 / 35474696 / 3805>µ ± 2.5σ (−/+)
1.61%
147 / 203
Load-alone (Delta-MW)σ = 43.22
3.17%1.55%% > 2.5σ
>µ ± 5σ (−/+) 175 / 225117 / 159
With Wind(Delta-MW)Using load σ
With Wind (Delta-MW)σ = 49.67
Extreme 1-Minute Deltas
1-minute standard deviation (σ ) increases by 14.9%Maximum 1-minute rise increases by 46.4 MWMaximum 1-minute drop increases by 38.9 MWNumber of 1-minute deltas greater than 2.5 (load)σincreases 96%
28 /
Hourly Load-Wind Variability (Study Year Data, 15000 MW Scenario)
0
200
400
600
800
1000
1200
< -7000-7000 – -6500-6500 – -6000-6000 – -5500-5500 – -5000-5000 – -4500-4500 – -4000-4000 – -3500-3500 – -3000-3000 – -2500-2500 – -2000-2000 – -1500-1500 – -1000-1000 – -500-500 – 00 – 500500 – 10001000 – 15001500 – 20002000 – 25002500 – 30003000 – 35003500 – 40004000 – 45004500 – 50005000 – 55005500 – 60006000 – 65006500 – 7000> 7000
MW
No.
1-H
our P
erio
ds
Load - WindLoad
Again, the downward variations are most changed
-1741 / 1677-1366 / 1425Mean(-/+ Deltas)
5203
-4838
1758
Load-alone (MW)
-7507Min. Delta
Max. Delta
Sigma (Delta)
6861
2159
With Wind (MW)
78 / 366 / 50 / 0>µ ± 3σ (−/+)
224 / 1616 / 2643 / 26>µ ± 2.5σ (−/+)
0.79%
0 / 0
Load-alone (Delta-MW)σ = 1758
4.39%0.37%% > 2.5σ
>µ ± 4σ (−/+) 1 / 00 / 0
With Wind(Delta-MW)Using load σ
With Wind (Delta-MW)σ = 2159
Extreme 1-Hour Deltas
1-hr standard deviation (σ ) increases by 22.8% Maximum 1-hour rise increases by 1658 MWMaximum 1-hour drop increases by 2669 MWNumber of 1-hr deltas greater than 2.5 (load)σincreases 458%
29 /
Variability as a Function of Wind Penetration
10
100
1000
10000
0 5000 10000 15000
Wind Generation (MW)
Sigm
a (M
W)
1 515 60
Delta Timeframe
• Variability increases with wind penetration. • Increase is very slight on this scale
30 /
Normalized Variability as a Function of Wind Penetration
10
15
2025
30
35
4045
50
55
0 5000 10000 15000
Wind Generation (MW)
Nor
mal
ized
Sig
ma
(MW
/min
) 1 5 15 60
Delta Timeframe
• Sigmas normalized in terms of MW/min (e.g., σ5 / 5)• Increase is linear, but with a shallow slope
31 /
Normalized Sigma as a Function of Timespan
0
10
20
30
40
50
60
1 10 100
Timespan (minutes)
Nor
mal
ized
Sig
ma
(MW
/min
)
Load Only5,000 MW10,000 MW10,000 MW15,000 MW
`
• There is a baseline of variability that is a function of the longer-term load cycle.
• An incremental amount of variation appears at the shortest timeframes (1 & 5 min.)
32 /
Increase in Variability Relative to Time Span
For all wind scenarios, the relative increase in variability (sigma), relative to sigma of load alone, becomes more significant for longer time windows
0%
5%
10%
15%
20%
25%
1 10 100
Timespan (minutes)
% In
crea
se in
Var
iabi
lity
5,000 MW 10,000 MW 10,000 MW 15,000 MW
33 /
In summary:• Variations over timespans of 10+ minutes are primarily due
to load cycle• Shorter timespans have an incremental component due to
random “noise” variations• Wind causes a slight, linear increase in period-to-period
variability over all timespans• Impact is somewhat more significant for longer timespans
– I.e., wind adds to variability primarily due to creating larger daily net load swings
– Addition to the random “noise” is less significant• Small differences in statistical metrics between “study year”
(based on 2006) and “previous year” (based on 2005) indicate stability of results
35 /
The ability of the system to accommodate net load variations is greatly a function of the absolute net load level.
System maneuverability tends to increase with the generation level because:• Variations of a given magnitude are larger in
proportion to the committed generators• Units lower on the dispatch stack tend to be
base load units that are less maneuverable
The following slides correlate variability with load level
36 /
Wind Duration and Penetration (15000 MW) (Study Year Data)
0
2500
5000
7500
10000
12500
15000
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours of Year
Tota
l Win
d O
utpu
t(MW
)
0%
10%
20%
30%
40%
50%
60%
Win
d Pe
netr
atio
n (%
)
Total Wind (MW)
Penetration (%)
Note: Data for these curves were independently sorted
Wind generation is above 75% of installed capacity only 10% of the year
Median instantaneous penetration is only 16%, compared to 23% on a capacity basis
Wind Scenario Max Instantaneous Penetration
5000 21%10000 (1) 39%10000 (2) 39%15000 57%
37 /
Load and Net Load Variability by Load Level (Study Year Hourly Data, 15000 MW Scenario)(Average +/- x*sigma, Minimum, Maximum)
LoadLoad-Wind
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
MW
1 2 3 4 5 6 7 8 9 10Load Decile
Mean + Sigma
Mean - 2.5*Sigma
Mean - Sigma
Mean + 2.5*SigmaMax
Min
Very little impact on variability at very high load levels
• Variability is changed little at lower loads• Same variability, but with fewer dispatchable generators
38 /
Net Load Duration Curves for Various Wind Scenarios (Study Year Data)
0
10000
20000
30000
40000
50000
60000
70000
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours of Year
Net
Loa
d (M
W)
Load-AloneLoad-5000 MWLoad-10000 MW(1)Load-10000 MW(2)Load-15000 MWMin Load (22426 MW)
Low net load periods
Min Load 22426 MW
Note: Data for these curves were independently sorted
Note: Data for these curves were independently sorted
• Net loads below current minimum load may be a real operational challenge
• Average wind output is double during low net-load hours
39 /
Net Load Duration Curves for Low Load Periods (Study Year Data)
8000
12000
16000
20000
24000
28000
32000
6700 6900 7100 7300 7500 7700 7900 8100 8300 8500 8700
Hours of Year
Net
Loa
d (M
W)
Load-AloneLoad-5000 MWLoad-10000 MW(1)Load-10000 MW(2)Load-15000 MWMin Load (22426 MW)
1945 hrs (35.7% of Wind Energy)
1141 hrs (21.4%E)
470 hrs (9.7%E)
1209 hrs (23.3%E)
8760
Wind energy lost if wind is curtailed to hold min net load same (5,000 MW scenario)
• There are inherent tradeoffs between costs of generation flexibility and energy lost to curtailment
Curtailment to hold current minimum for 15 GW of wind results in excessive energy loss
40 /
In summary:• In general, variability is relatively constant over the range of
load levels• Wind contribution to variability is also relatively constant• Net loads can be driven to low levels with large wind
capacity– Instantaneous penetration reaches 55% with 15,000 MW
of wind and 2008 load levels• It is not feasible to maintain the same minimum load levels
Ability of the ERCOT system to meet ramping requirements will be specifically studied in Phase 2
42 /
The next slides examine how load variability varies over the hours of the day for different seasons
43 /
April, Hourly Load and Net Load Deltas (Study Year Data, 15000 MW Scenario)
(Avg. +/- sigma, Minimum, Maximum)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250
6000
12000
18000
24000
30000
36000
42000
48000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
Hour of Day
Load
and
Net
Loa
d D
elta
(MW
)
Tota
l Loa
d (M
W)
Wind is a large contributor to ramping requirements during morning load rise and evening load drop off in the spring
5900 MW/hr drop
5700 MW/hr rise
Load DeltasLoad-Wind DeltasTotal LoadLoad-Wind
44 /
July, Hourly Load and Net Load Deltas (Study Year Data, 15000 MW Scenario)
(Avg. +/- sigma, Minimum, Maximum)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250
7500
15000
22500
30000
37500
45000
52500
60000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
Hour of Day
Load
and
Net
Loa
d D
elta
(MW
)
Load
and
Net
Loa
d (M
W)
In summer, wind makes the largest impact during the early morning load rise and evening load drop off
6650 MW/hr rise
6400 MW/hr drop
Load DeltasLoad-Wind DeltasTotal LoadLoad-Wind
46 /
Summer Morning Load Rise Variability – 15,000 MW (Study Year Data)
32372797Mean (Delta)
2509Min. Delta
Max. Delta
Sigma (Delta)
65284160
1122732
with Wind (MW)
Load-alone (MW)
2008 Load-15,000 MW Wind - Summer Morning Load Rise (Jun-Sep, 7-11 AM)
0
10
20
30
40
50
60
70
< 200
200 – 400
400 – 600
600 – 800
800 – 1000
1000 – 1200
1200 – 1400
1400 – 1600
1600 – 1800
1800 – 2000
2000 – 2200
2200 – 2400
2400 – 2600
2600 – 2800
2800 – 3000
3000 – 3200
3200 – 3400
3400 – 3600
3600 – 3800
3800 – 4000
4000 – 4200
4200 – 4400
4400 – 4600
4600 – 4800
4800 – 5000
5000 – 5200
5200 – 5400
5400 – 5600
5600 – 5800
> 5800
MW
No.
of 1
hr p
erio
ds
Load - WindLoad
Mean 1-hour delta increases by 15.7% due to wind
Sigma increases by 53.3%
Number of 1-hour rises greater than 4000 MW increases from 9 to 123
2910> µ +2.5σ
0
0
Load-alone (Delta-MW)σ = 732
10> µ + 4σ
> µ +3σ 150
With Wind(Delta-MW)Using load σ
With Wind (Delta-MW)σ = 1122
Extreme 1-Hour Rises
47 /
Summer Morning Load Rise Variability (Study Year Data)
Summer Morning Load Rise
0
1000
2000
3000
4000
5000
6000
7000
0 5000 10000 15000 20000
Wind Penetration (MW)
MW
µ
σ
µ + 2.5 σExtreme
• Extrema increase more quickly with additional wind generation than mean + 2.5 s.d.
• Distribution is less characterized by a normal distribution; more outliers
49 /
Winter Afternoon Load Rise Variability (Study Year Data)
15731517Mean (Delta)
-2768-886Min. Delta
Max. Delta
Sigma (Delta)
68613678
1556866
with Wind (MW)
Load-alone (MW)
2008 Load-15,000 MW Wind - Winter Afternoon Load Rise (Nov-Feb, 4-6PM)
0
5
10
15
20
25
30
35
< -2800-2800 – -2700-2700 – -2400-2400 – -2100-2100 – -1800
-1800 – -1500-1500 – -1200-1200 – -900-900 – -600
-600 – -300-300 – 00 – 300300 – 600600 – 900
900 – 12001200 – 15001500 – 18001800 – 2100
2100 – 24002400 – 27002700 – 30003000 – 33003300 – 3600
3600 – 39003900 – 42004200 – 45004500 – 4800
4800 – 51005100 – 54005400 – 57005700 – 6000> 6000
MW
No.
of 1
hr p
erio
ds
Load - WindLoad
More outliers, both directions Mean 1-hour delta increases by
3.7% due to wind
Sigma increases by 79.7%
Number of 1-hour rises greater than 3000 MW increases from 11 to 36
2250> µ +2.5σ
0
0
Load-alone (Delta-MW)σ = 866
70> µ + 4σ
> µ +3σ 144
With Wind(Delta-MW)Using load σ
With Wind (Delta-MW)σ = 1550
Extreme 1-Hour Rises
50 /
• Wind variability increases linearly with penetration– 1-hour sigma increases by 23% with 15,000 MW of wind– Greater variability and extreme ramps observed during
certain morning, afternoon and evening periods– Greater net load variability in the spring and summer
• The more significant impact is that minimum net loads are greatly reduced– Greater relative variability at light load– Less system responsiveness
• Wind impact on variability is primarily due to multi-hour cycles, increment due to “noise” is small
• Wind has incremental impact on average and extreme errors, especially during early mornings and afternoons in winter & spring– On average, net load is nearly as predictable as load alone
Variability Analysis Summary
52 /
Impact of Extreme Weather Conditions
• ERCOT’s current “extreme” weather conditions are largely defined by temperature … – Regulation reserves may be increased by a
factor of two– Responsive reserves and non-spinning reserves
may be procured• With large amounts of wind, other weather
conditions may create abnormal net load deviations– Investigate most severe events in wind and Net-
Load– Develop modified procedures or requirements for
identifying and responding to the ancillary service needs driven by extreme weather.
53 /
Impact on Responsive Reserve Services (RRS) (Spinning Reserves)
• Used to restore ERCOT system frequency within the first few minutes of an event …
• Set at 2300 MW for normal conditions– based on simultaneous loss of largest two
generation units• May be increased under “extreme conditions”• Non-spinning reserves (NSRS) may be deployed
when “large” amounts of spin are not available– NSRS can be ramped to output level within 30-
minutes
Extreme drops in wind production within 30 minsare investigated to determine impact on RRS
54 /
In this next set of slides, we will show:• AWST analysis of ramp events in existing wind
– Causes, frequency and predictability– Implications for wind scenarios
• Probability of “large” wind transitions/ramp events• Impact of diversity on wind ramp events• Distribution, timing and magnitude of events• Implications for RRS requirements
55 /
Analysis of West Texas Wind Plant Ramp EventsTo identify and classify events, AWS Truewind:• Examined two years of one-minute plant output data provided by
ERCOT– Identified 30-minute periods with aggregate wind generation
changes > 200 MWTotal 976 MW rated capacity for plants in analysisObvious cases of non-weather curtailments and shutdowns excluded
– Examined available meteorological records for the periods – Categorized the events by meteorological causes
• Analyzed significant 2005-2006 weather events identified by ERCOT, determined those were associated with large changes in wind generation
• Analyzed the event of 24 February 2007 and established the causefor the decrease in energy production.
From the results, AWS Truewind estimated the maximum likely change in a 30-minute period for the 15,000 MW scenario
56 /
Meteorological Causes of Wind Ramp-Up Events• Frontal system/trough/dry line
– Density fronts or air mass discontinuities – Accompanying fall/rise pressure couplet, results in rapid wind-
speed change, – Mostly move west to east or northwest to southeast – Up to 1000 km long and 100-200 km wide– Propagate at over 15 m/s (34 mph)
• Convection-induced outflow or gust fronts – Occur on the mesoscale (tens to hundreds of square km) – Usually propagate radially outward from thunderstorm clusters – Propogation speeds in excess of 25 m/s
• Low-level jet (LLJ) – Occur regularly year-round in the Southern Great Plains– Two types:
1) Nocturnal LLJ – maximum at 5 AM2) Pre-frontal LLJ – ahead of cold front
57 /
Meteorological Causes of Wind Ramp-Down Events
• Slackening of a pressure gradient • Passage of a local pressure couplet • Each can occur for same events causing ramp-up• High wind speeds that exceed wind turbine cut-out
– Threshold (22-25 m/s) – Responsible for February 24, 2007 event
58 /
Event Propagation Example (August 11, 2006)
• LEFT: NEXRAD (radar) image from Midland TX (KMAF) for 1801 LT on 11 August 2006 - Red arrows show outflow from thunderstorm complex to the west
• RIGHT: Outflow boundary an hour later (1901 LT) now approaching cluster of wind plants south and northeast of KMAF
• Shortly after, ramp event of +600 MW was observed within a 30 minute period • Lower arrows indicate boundary traversed about 100 km (62 miles) in an hour
59 /
Extreme Wind Events* in Existing Data (2006)**
* 200 MW excursion within 30 minutes
** Based on approximately 976 MW of installed capacity
60 /
Summary of Ramp Events for Existing Wind Data (2005/2006)
• 59 ramp events identified (60% up, 40% down)• Largest ramp-up event on 9 July 2005
– nearly 400 MW increase (over 300% from 200 MW)
• Largest ramp-down event on 12 May 2005 – 331 MW decrease, (more than 58% from 571 MW)
• Primary causes: (1) convective (2) frontal passages (3) weakening pressure gradients
• Distinct diurnal increase in the frequency of ramp-up events during the evening hours, particularly around 5 PM local time, due to convection, especially strong to severe thunderstorms
• Seasonal increase in frequency of ramp-up events from late winter through summer, while ramp-down events show no clear pattern.
61 /
Ramp Event Case Study (December 28, 2006)
• Weak gradient ahead of cold front– An area of weak pressure gradient moves
eastward across west-central Texas between 14:00 and 15:00 LST
– Since wind speed is proportional to the pressure gradient, there is a significant reduction in wind power output and wind speed as this feature passes
– The drop in wind speed is most notable at Fort Stockton (KFST), Lubbock (KLBB) and Odessa (KODO)
– There is a secondary drop in power output around 16:00 LST as winds continue to diminish (to below the cut-in value of 4 m/s at the stations)
• Frontal passage– Following the weak pressure field, a
stronger gradient moves into the area after the frontal passage (approximately 15:00 –16:00 LST)
– Wind speeds and output increase rapidly by 18:00
– Plant output, which had decreased to about 100 MW (or 10% of the rated capacity), then rapidly rose as wind speeds rose above the cut-in value.
62 /
Ramp Event Case Study (February 24, 2007)• Strong upper-level storm system passed over
northern New Mexico and the panhandle of Texas substantially tightening the pressure gradients over west Texas, resulting in strong to severe winds along a straight line across much of the area
– 8 AM - high wind speeds seen by most wind projects, maximum wind gust reported was 94 mph
– 9 AM - aggregate output increased from just over 1100 MW to nearly 2000 MW (rated capacity)
– 10 AM - sustained winds exceeded 25 m/s (55 mph) output at most wind farms, output declined as turbine-cutoff threshold reached
– 11 AM - most intense pressure gradients and winds moved eastward, wind speeds relaxed, turbines resumed power production, resulting in a gradual increase in total output to pre-event levels
• Total drop in plant output was more than 1500 MW over a 90 minute period
• Most rapid declines occurred at the Horse Hollow interconnections
• Largest 30-minute drop of 450 MW (between 1104 and 1134 LST) represents about 22.5% of the plant rated capacity
• The event was unusual both in the magnitude of the 90-minute drop and the large geographic area affected
• Arrival of such fronts is generally forecastable, several hours ahead within a 30-minute window
64 /
Probability and Predictability of Ramp Events• Frontal passages/troughs/dry lines of any severity
occur every 3-5 days during cold season, and every 5-7 days during warm season– Fast ramp-up events (as defined for 2005/2006 existing data)
likely to occur 20 times/year or every 2-3 weeks– Fast down-ramps likely to occur once every 2 months
• Convective events occur with varying frequency– Number of severe thunderstorms (winds over 29 m/s) in
ERCOT territory over last 10 years varies from 32 in 2000 to 134 in 2003
• All weather phenomena causing ramp events can be forecasted– Lead time and accuracy varies considerably– Frontal passages (winter) can be forecasted several days in
advance with limited accuracy and timing, but to within a 30-minute window several hours in advance
– Severe thunderstorms (summer) more difficult to forecast, better for active periods – average lead time in West Texas is 20 minutes, 70-85% accuracy, but only 30-40% dependability
65 /
Analysis of 15,000 MW Wind Scenario
Pressure Gradient Strengthening
• Additionally, since CREZ 10 has by far the largest wind capacity(4607 MW), a system affecting this entire zone could conceivablyresult in a 30-minute excursion of more than 1100 MW
• An event of the magnitude and coverage of 24 February 2007 could produce over a 20% reduction in power over most of theCREZs (see row 4 in table) once every 3 - 5 years.
66 /
15-Minute Wind State Transition Probabilities (15,000 MW*)Probability that wind output will change from one level to another within 15 minutes
Next State (Output, % rated capacity)
Cur
rent
Sta
te (O
utpu
t)
0-10% 11-20% 21-30% 31-40% 41-50% 51-60% 61-70% 71-80% 81-90% 91-100%
0-10% 0.8386 0.1614 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
11-20% 0.0225 0.8602 0.1173 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
21-30% 0.0000 0.0486 0.8445 0.1069 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
31-40% 0.0000 0.0000 0.0598 0.8232 0.1170 0.0000 0.0000 0.0000 0.0000 0.0000
41-50% 0.0000 0.0000 0.0000 0.0655 0.8176 0.1169 0.0000 0.0000 0.0000 0.0000
51-60% 0.0000 0.0000 0.0000 0.0000 0.0667 0.8079 0.1253 0.0000 0.0000 0.0000
61-70% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0641 0.8495 0.0864 0.0000 0.0000
71-80% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0514 0.8701 0.0785 0.0000
81-90% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0516 0.9134 0.0350
91-100% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0791 0.9209
• Diagonal probabilities show that on average there is a 85% chance that wind output will persist – change by no more that 10% of rated capacity in fifteen minutes
– Average probability of <7% that wind output will drop by more than 10% of rated in 15 minutes• Negligible chance that wind will change by more than 20% of rated in 15 minutes
*From AWST wind production data
67 /
30-Minute Wind State Transition Probabilities (15,000 MW*)Probability that wind output will change from one level to another within 30 minutes
Next State (Output, % rated capacity)
Cur
rent
Sta
te (O
utpu
t)
0-10% 11-20% 21-30% 31-40% 41-50% 51-60% 61-70% 71-80% 81-90% 91-100%
0-10% 0.8139 0.1861 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
11-20% 0.0199 0.8094 0.1707 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
21-30% 0.0000 0.0595 0.7698 0.1699 0.0008 0.0000 0.0000 0.0000 0.0000 0.0000
31-40% 0.0000 0.0000 0.0820 0.7324 0.1835 0.0021 0.0000 0.0000 0.0000 0.0000
41-50% 0.0000 0.0000 0.0000 0.0916 0.7247 0.1832 0.0005 0.0000 0.0000 0.0000
51-60% 0.0000 0.0000 0.0000 0.0000 0.0939 0.7209 0.1847 0.0005 0.0000 0.0000
61-70% 0.0000 0.0000 0.0000 0.0000 0.0011 0.0879 0.7840 0.1270 0.0000 0.0000
71-80% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0013 0.0583 0.8362 0.1042 0.0000
81-90% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0477 0.9019 0.0503
91-100% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0658 0.9342
• Diagonal probabilities show that on average there is a 80% chance that wind output will persist – change by no more that 10% of rated capacity in 30 minutes
– Average probability of <10% that wind output will drop by more than 10% of rated in 30 minutes• Minute chance that wind will change by more than 20% of rated in 30 minutes• Persistence is greater at high and low output levels
*From AWST wind production data
68 /
1-Hour Wind State Transition Probabilities (15,000 MW*)Probability that wind output will change from one level to another within 60 minutes
Next State (Output, % rated capacity)
Cur
rent
Sta
te (O
utpu
t)
0-10% 11-20% 21-30% 31-40% 41-50% 51-60% 61-70% 71-80% 81-90% 91-100%
0-10% 0.7244 0.2742 0.0014 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
11-20% 0.0590 0.6881 0.2419 0.0103 0.0007 0.0000 0.0000 0.0000 0.0000 0.0000
21-30% 0.0000 0.1398 0.6106 0.2250 0.0246 0.0000 0.0000 0.0000 0.0000 0.0000
31-40% 0.0000 0.0043 0.1845 0.5527 0.2355 0.0221 0.0009 0.0000 0.0000 0.0000
41-50% 0.0000 0.0000 0.0066 0.1915 0.5315 0.2357 0.0347 0.0000 0.0000 0.0000
51-60% 0.0000 0.0000 0.0000 0.0161 0.1847 0.5432 0.2390 0.0171 0.0000 0.0000
61-70% 0.0000 0.0000 0.0000 0.0000 0.0149 0.1943 0.5934 0.1890 0.0085 0.0000
71-80% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0039 0.1399 0.7242 0.1320 0.0000
81-90% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0077 0.1231 0.8077 0.0615
91-100% 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0286 0.1429 0.8286
• Diagonal probabilities show that on average there is a 66% chance that wind output will persist – change by no more that 10% of rated capacity in 60 minutes
– Average probability of <18% that wind will change by more than 10% of rated in 60 minutes• Small chance that wind will change by more than 20% of rated in 60 minutes• Persistence is significantly greater at high and low output levels
*From AWST wind production data
69 /
Largest One-Hour Wind Drop in 15,000 MW Wind (Jan 28 ’06)January 28, 2006 Wind Negative Ramp Event
0.0
500.0
1000.0
1500.0
2000.0
2500.0
3000.0
3500.0
4000.0
4500.0
5000.0
3:00 PM
4:00 PM
5:00 PM
6:00 PM
7:00 PM
8:00 PM
9:00 PM
Time (CST)
CR
EZ O
utpu
t (M
W)
0.0
2000.0
4000.0
6000.0
8000.0
10000.0
12000.0
14000.0
15,0
00 M
W W
ind
Scen
ario
Out
put (
MW
)
2567910121415192324Total
TOTAL
CREZ 10
CREZ 2
CREZ 9CREZ 24
CREZ 6CREZ 5CREZ 12
Wind drops by 3340 MW in one hour, driven largely by an almost 2000 MW one-hour drop in CREZ 10
70 /
Largest One-Hour Wind Drop in CREZ 10 Wind (Jan 28 ’06)January 28 Event in CREZ 10
0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
400.0
9:00 PM
10:00 PM
11:00 PM
12:00 AM
1:00 AM
2:00 AM
3:00 AMSi
te O
utpu
t (M
W)
0.0
600.0
1200.0
1800.0
2400.0
3000.0
3600.0
4200.0
4800.03 29 93 96 148 183 195198 224 225 237 260 288 311321 375 388 389 403 426 431442 462 465 473 491 494 498524 527 528 536 542 Total
CREZ TOTAL
SITE 237
SITE 96SITE 462
SITE 321
SITE 198
SITE 465SITE 3 C
REZ
Out
put (
MW
)
Most sites in CREZ 10 are similarly impacted by the event
71 /
0
400
800
1200
1600
2000
2400
2800
3200
3600
4000
4400
4800
< -1500-1500 – -1400-1400 – -1300-1300 – -1200-1200 – -1100-1100 – -1000-1000 – -900-900 – -800-800 – -700-700 – -600-600 – -500-500 – -400-400 – -300-300 – -200-200 – -100-100 – 00 – 100100 – 200200 – 300300 – 400400 – 500500 – 600600 – 700700 – 800800 – 900900 – 10001000 – 11001100 – 12001200 – 13001300 – 14001400 – 1500> 1500
MW
30-M
inut
e Pe
riods
5000 MW Wind10000 MW Wind (1)10000 MW Wind (2)15000 MW Wind
Distribution of Thirty-Minute Wind Output Changes (Deltas)(Study Year)
Variability (σ) does not increase linearly with wind penetration, but Impact of diversity is less pronounced for longer time periods
78 / 117
197 / 270
314
-224 / 237
10000 MW (1)
81 / 103
189 / 258
288
-208 / 215
10000 MW (2)
-304 / 313-128 / 138Mean (-/+)
203 / 262171 / 318> µ ± 2.5σ (−/+)
> µ ± 3.0σ (−/+)
Sigma
83 / 9875 / 128
420183
15000 MW5000 MW
130% increase in σfor 200% increase in wind
72 /
0
200
400
600
800
1000
1200
1400
1600
1800
2000
< -3000-3000 – -2800-2800 – -2600-2600 – -2400-2400 – -2200-2200 – -2000-2000 – -1800-1800 – -1600-1600 – -1400-1400 – -1200-1200 – -1000-1000 – -800-800 – -600-600 – -400-400 – -200-200 – 00 – 200200 – 400400 – 600600 – 800800 – 10001000 – 12001200 – 14001400 – 16001600 – 18001800 – 20002000 – 22002200 – 24002400 – 26002600 – 28002800 – 3000> 3000
MW
30-M
inut
e Pe
riods
Delta LoadDelta L-5000Delta L-15,000
Distribution of Thirty-Minute Net Load Changes (Deltas)(Study Year)
9 / 10
104 / 79
1013
-797 / 801
L-10000 MW (2)
10 / 1312 / 95 / 131 / 19> µ ± 3.0σ (−/+)
102 / 8886 / 7596 / 7671 / 80> µ ± 2.5σ (−/+)
967
-755 / 771
L-5000 MW
1031
-816 / 811
L-10000 MW (1)
-857 / 850-695 / 741Mean (-/+)
Sigma (σ) 1083911
L-15000 MWLoad-alone
73 /
0
10
20
30
40
50
60
70
80
90
100
-2600 -2200 -1800 -1400 -1000 -600 -200
Wind Delta (MW)
Num
ber o
f 30-
Min
ute
Perio
ds
5000 MW10000 MW(1)10000 MW(2)15000 MW
Extreme Thirty-Minute Wind Drops (Down-Ramps) (Study Year)
2300 MW(Spinning Reserves)
Wind down-ramp equals or exceeds online reserves (2300 MW) three times with15,000 MW of wind production
24936635No. Drops > 1000 MW
3000No. Drops > 2300 MW
-2563-1771-2053-1167Max Neg Delta
1629
10,000 MW Wind (2)
1611
10,000 MW Wind (1)
23701079Max Pos Delta
5000 MW Wind
15,000 MW Wind
74 /
0
10
20
30
40
50
60
2200 2400 2600 2800 3000 3200 3400 3600 3800 4000
Net-Load Delta (MW)
Num
ber o
f 30-
Min
ute
Perio
ds
Load-AloneL-5000 MWL-10000 MW(1)L-10000 MW(2)L-15000 MW
Extreme Thirty-Minute Net-Load Rises (Up-Ramps) (Study Year)
3101 MWMax load-alone
30-min up-rampNet load up-ramp equals or exceeds the max load-alone up-ramp (3101 MW) 24 times, with 15,000 MW of wind
168
2916
-3300
3805
L-10,000 MW Wind (2)
3092298627692557No. Rises > 1000 MW
28919111478No. Rises > 2300 MW
-3612-3360-3138-2756Max Neg Delta
3928
L-10,000 MW Wind (1)
3271
L-5000 MW Wind (1)
45023101Max Pos Delta
Load-alone L-15,000 MW Wind
75 /
Timing of Extreme Thirty-Minute Wind Drops (Study Year)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24JanFebMarAprMayJunJulAugSepOctNovDec
Hour of Day
Mon
th o
f Yea
r
-800--200-1400--800-2000--1400-2600--2000
Largest 30-minute wind drops tend to occur in the morning 6-9 AM and late afternoon 5-7 PM (except in the Summer)
Corresponds with REG observations
-2563 MW
-2479 MW
-2300 MW
76 /
Conclusions – Extreme Weather Conditions
• Large sudden wind excursions (greater than 20% of rated capacity within 30 minutes) are infrequent– Changes occur as fast ramps, not steps
• When sudden changes do occur, CREZ diversity significantly reduces the impact of any single change on the aggregate output
• Weather events causing widespread impact are reasonably predictable
• Local convective events are less predictable– Tend to have a limited geographic extent– Large wind concentrations increase vulnerability
77 /
Conclusions - Impact on Spinning Reserves
• Maximum 15 minute wind drop for 15,000 MW scenario is 1337 MW; well within present 2300 MW RRS
• Across the year, three observed cases when wind drops by over 2300 MW in 30 minutes– Late afternoon September 21, January 28, December 30– Some severe drops will inherently fall in periods of
“uncertain weather” where reserves are already boosted• Load-alone has extreme up-ramps, but wind creates
incremental requirements in net load, mostly in mornings and late winter afternoons
• Alternative approaches:– Increase RRS for periods of forecast “meteorological risk”– Revise the NSRS definition to provide for a 15-minute
response service; procure this service at periods of designated risk
79 /
In this next set of slides, we will show:• How regulation in the ERCOT nodal market is
calculated in this study• Regulation required (deployed)Key issues are:• Differences with regulation requirements in the
present zonal market• Changes in regulation requirements with increased
wind penetration
80 /
Dispatch Procedure in the ERCOT Nodal Market
• Economic dispatch is on a 5-minute basis; • ERCOT is considering predictive tuning factors to reduce
regulation requirements driven by load following– Dispatch setpoint is initial actual load + k times expected change
over 5-minute period– Tuning factors have not yet been resolved
• Scope of this study focuses on wind, not operating practices independent of wind– Regulation results are intended for relative comparison between
wind scenarios– Comparison with present regulation requirements are not
appropriate
• Assuming k = 0 maximizes impact of ramp rate; most conservative with respect to wind impact
81 /
Regulation Calculation in the Nodal Market
• Units on economicdispatch “step” to setpointsat discrete 5-minute points
• Difference between actual load and economic setpoints is defined as regulation– Positive deviations defined
as “Up Reg” (+REG)– Negative deviations
defined as “Down Reg” (-REG)
37,660
37,680
37,700
37,720
37,740
37,760
37,780
37,800
910 915 920 925 930
Minute
MW
LoadSetpoint
-100
-50
0
50
Regu
latio
n (M
W)
82 /
28,000
28,200
28,400
28,600
28,800
29,000
29,200
29,400
10 20 30 40 50 60
Minutes
MW
LoadSetpoints
-REG
-500
-400
-300
-200
-100
0
100
200
300
400
500
0 5 10 15 20 25Hours
MW
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
Inst. Regulation+REG-REGLoadDispatched Gen.
Regulation Through a Typical Day (without wind)
• Regulation is biased by load ramp rate – not just the“random jitter” component– Virtually no Down Reg during load rise– Virtually no Up Reg during load drop
83 /
Terminology and Abbreviations
The following terminology and abbreviations regarding regulation are used in this presentation:
Deployed Regulation – Maximum difference over each 5-minute period between the net load and the dispatch base point (actual net load at the beginning of period)
Procured Regulation – Amount of regulation “reserved” based on statistical analysis of prior deployments
+REG – Up Regulation – Positive difference between net load and base point.
-REG – Down Regulation - Difference between net load and base point (expressed in this presentation as a negative number)
84 /
Max. Hourly Deployed Regulation – January Example
• ~4 day time period plotted• Diurnal patterns visible
• ~4 days plotted• Diurnal pattern in REG are
visible• Significant impact of outliers
– A few driven by wind– Most outliers changed
incrementally– Some not changed at all
January
-800
-600
-400
-200
0
200
400
600
800
25 35 45 55 65 75 85 95 105 115 125
Hour
Max
. Hou
rly +
/-REG
Load Alone Load-5000Load-10000(1) Load-10000(2)Load-15000
0
200
400
600Peak caused by wind
Peak is ~same
85 /
Deployed Regulation Statistics
Up-Regulation
1124.9 MW1112.7 MW1105.6 MW1075.9 MW1072.5 MW
Maximum
23.1%12.7%14.2%6.4%
% Change
3.7%261.5 MW10.2%81.4 MW10,000 (2)4.9%285.8 MW16.5%86.1 MW15,000
3.1%265.2 MW11.7%82.5 MW10,000 (1)0.3%247.0 MW5.8%78.1 MW5,000
232.1 MW73.8 MW0
% Change
98th Percentile of 5-min Periods
% Change
Average Max of 5-min Periods
Wind (MW)
-566.4-565.9-554.9-538.9-522.2
Minimum
20.7%11.8%12.8%5.9%
% Change
8.4%-260.4 MW9.7%-81.5 MW10,000 (2)8.5%-281.2 MW16.5%-86.6 MW15,000
6.3%-262.7 MW11.7%-83.0 MW10,000 (1)3.2%-246.7 MW5.8%-78.6 MW5,000
-233.0 MW-74.3 MW0
% Change
98th Percentile of 5-min Periods
% Change
Average Min of 5-min Periods
Wind (MW)
Down-Regulation
86 /
Cumulative Distributions of Maximum Hourly Up-Regulation
0
50
100
150
200
250
300
350
400
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours
+REG
(MW
)
Load AloneL-5000L-10000(1) L-10000(2) L-15000
Expansion of 0-400 MW range
0
200
400
600
800
1000
1200
1400
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours
+REG
(MW
)
Load AloneL-5000L-10000(1) L-10000(2) L-15000
87 /
-400
-350
-300
-250
-200
-150
-100
-50
0
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours -REG More Negative Than Value
-REG
(MW
)
Load AloneL-5000L-10000(1)L-10000(2) L-15000
Cumulative Distributions of Maximum Hourly Down-Regulation
Expansion of 0 - -400 MW range
-1400
-1200
-1000
-800
-600
-400
-200
0
0 876 1752 2628 3504 4380 5256 6132 7008 7884 8760
Hours
-REG
(MW
)
Load AloneL-5000L-10000(1)L-10000(2) L-15000
88 /
Extreme Up-Regulation and Down-Regulation
-1500
-1400
-1300
-1200
-1100
-1000
-900
-800
-700
-600
-500
0 20 40 60 80 100
Hours
-REG
(MW
)
Load AloneL-5000L-10000(1)L-10000(2) L-15000
600
700
800
900
1000
1100
1200
1300
1400
0 20 40 60 80 100
Hours
+REG
(MW
)
Load AloneL-5000L-10000(1) L-10000(2) L-15000
Except for an extreme outlier in one 10GW wind scenario, maximum, extreme +/-REG is increased modestly.
Increase ≈ proportionate with the amount of wind resources
≈ 100 MW increase
100 hrs is ≈ 1.2% of year
89 /
Hourly Maximum Regulation Increase with 15,000 MW Wind
0%
5%
10%
15%
20%
25%
−280 → −300
−260 → −280
−240 → −260
−220 → −240
−200 → 220
−180 → −200
−160 → −180
−140 → −160
−120 → −140
−100 → −120
−80 → −100
−60 → −80
−40 → −60
−20 → −40
0 → −20
0 → 20
20 → 40
40 → 60
60 → 80
80 → 100
100 → 120
120 → 140
140 → 160
160 → 180
180 → 200
200 → 220
220 → 240
240 → 260
260 → 280
280 → 300
Change in Regulation
Perc
ent o
f Hou
rs+REG-REG
Difference between hourly max. regulation for load only and load –15GW wind
-18.217.7Mean
-287.2
444.2
64.9
+REG
265.3Maximum
Minimum
Sigma
-453.1
65.1
-REG
Results are ≈ symmetric
These statistics describe the maximum regulation within each 1-hr period
90 /
Up Regulation Correlation with Time of Day and Month98.8th Percentile of +REG Deployed
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
600-800400-600200-4000-200
Load Alone
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
800-1000600-800400-600200-4000-200
Load – 5000 MW Wind
Load – 10,000 MW Wind (1) Load – 15,000 MW Wind
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
800-1000600-800400-600200-4000-200
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
800-1000600-800400-600200-4000-200
91 /
Differential Up Regulation Requirements for 15 GW Wind1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov 250-300200-250150-200100-15050-1000-50-50-0-100--50
98.8th Percentile of +REG Deployed
• Increases during morning load ramp due to wind decline• Increases during early evening during spring and fall
92 /
Differential Down Regulation Requirements for 15 GW Wind98.8th Percentile of –REG Deployed
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov 50-1000-50-50-0-100--50-150--100-200--150-250--200-300--250
• More down regulation in the evening, particularly in fall, winter and spring
• Decreased down regulation during summer mornings
93 /
Variation in Up Regulation for Selected Periods
0
100
200
300
400
500
600
0 5000 10000 15000Wind Capacity (MW)
+REG
(a
vera
ge m
onth
ly 9
8.8th
per
cent
ile)
Morning (0700 - 1000)Evening (1800)Mid-Day (1400)Night (2300)
+16.3%
+52.0%
+65.2%
+25.6%
• Relative impact is not uniform, wind does substantially increaseregulation requirements at times when regulation requirements had been small to moderate
• Linearity allows scale-up of regulation procurement to accommodate year-to-year wind additions
94 /
Increase of Evening Down Regulation Requirements
-600
-500
-400
-300
-200
-100
0
0 5000 10000 15000
Wind Capacity (MW)
-REG
(a
vera
ge m
onth
ly 9
8th
perc
entil
e)
31.9%
Evening wind increase coincides with load drop
95 /
Impact of Wind Penetration on Regulation
• Regulation peaks caused by load ramping are incrementally increased due to added ramp caused by wind
• Relative to load alone, 98th percentile of regulation increases on the order of 20% - 23% at 15 GW of wind
• Regulation increases linearly with wind penetration
• Extrema appear both with and without wind, with magnitudes incrementally greater with 15 GW of wind
• Largest changes are concentrated in particular times of day and seasons -- +REG in the evenings increases 65%
97 /
In this next set of slides, we will show:• How ERCOT presently determines the amount of
regulation to procure• The robustness of this methodology to increased
wind penetrationKey issues are:• Frequency of under-procurement• Severity of under-procurement
98 /
ERCOT Regulation Procurement Methodology
0
100
200
300
400
500
600
700
800
25 35 45 55 65 75
Hour
Max
. Hou
rly +
REG
Deployed +REG, Load AloneProcured +REG, Load Alone
Deployed > Procured
• Regulation procurement algorithm seeks to cover most, but not all time periods; occasional “misses” are expected
• Procurement based on 98.8th percentile of maximum deployment in 5-minute intervals for same hour of day in:– Same month, prior year– Prior month, same year
99 /
Regulation Deployed vs. Procured Time Series Example January with 15,000 MW Wind
January
0
100
200
300
400
500
600
700
800
25 35 45 55 65 75
Hour
Max
. Hou
rly +
REG
Depl., Load Depl., L-15GW
Proc., Load Proc., L-15GW
• Procurement modified (generally increased) due to wind (historical presence of wind assumed)
“Miss” caused by wind
Peak incrementally increased
100 /
Changes in Deployed and Procured Regulation
0
200
400
600
800
1000
1200
0 5000 10000 15000
Wind Capacity (MW)
Up
Reg
ulat
ion
(MW
)
Max Deployed98.8 pct DeployedMean DeployedMean ProcuredMax. Procured
+4.9%
+23.1%
+16.5%-800
-700
-600
-500
-400
-300
-200
-100
0
0 5000 10000 15000
Wind Capacity (MW)
Dow
n R
egul
atio
n (M
W)
Min Deployed98.8 pct DeployedMean DeployedMean ProcuredMin. Procured
16.5%
20.7%
8.5%
• Gap between maximum deployed and maximum procured narrows as wind penetration increases
• Point of comparison: sigma of 5-min delta increased 18% from load alone to load minus 15 GW of wind
101 /
Up Regulation Frequency Distribution Examples
January - 1400
0
20
40
60
80
100
120
140
160
0 100
200
300
400
500
600
700
800
900
1000
MW
Num
ber o
f 5 m
in P
erio
ds
LoadLoad - 15000 MW
209 MW +REG Procured for Load - 15GW
140 MW +REG Procured for Load Alone
April - 1300
0
10
20
30
40
50
60
0 100
200
300
400
500
600
700
800
900
1000
MWN
umbe
r of 5
min
Per
iods
LoadLoad - 15000 MW
259 MW +REG Procured for Load - 15GW
224 MW +REG Procured for Load Alone
Large Under-Procurement Magnitude
High Frequency of Under-Procuremeent
102 /
Percentage of Hours with +REG Under-Procurement
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov5.0%-6.0%4.0%-5.0%3.0%-4.0%2.0%-3.0%1.0%-2.0%0.0%-1.0%
Load Alone
Load – 15,000 MW Wind
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov5.0%-6.0%4.0%-5.0%3.0%-4.0%2.0%-3.0%1.0%-2.0%0.0%-1.0%
14.7% peak
11.7% peak
Present approach has a relatively large number of misses in the spring (morning to mid-afternoon) and autumn evenings
Increased overall +REG deployment with 15 GW of wind diminishes the high concentration of misses during these periods
A few limited points were somewhat more severe
10.3% peak
103 /
Root Mean Square of +REG Under-ProcurementLoad Alone Load – 15,000 MW Wind
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
300-400200-300100-2000-100
0000
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
400-50300-40200-30100-200-100
1 3 5 7 9 11 13 15 17 19 21 23
Jan
Mar
May
Jul
Sep
Nov
0-100
-100-0
-200--100
Difference
104 /
Regulation Under-Procurement Statistics
• Present methodology produces regulation requirements consistent with current accuracy
• Growth in absolute magnitude of deficiencies commensurate with regulation increase
88.5 MW84.2 MW85.0 MW82.1 MW80.1 MW
RMSof Deficiency
643 MW50.8 MW6,0041.35%10,000 (2)632 MW55.9 MW6,7121.37%15,000
638 MW52.0 MW6,2011.36%10,000 (1)634 MW48.2 MW5,3201.26%5000653 MW45.5 MW5,1411.29%0
ExtremeDeficiency
AverageUnder-Proc.
Total MWhUnder-Proc.
Percentage of Periods
WindUp-Regulation
90.1 MW89.2 MW87.9 MW90.4 MW89.2 MW
RMSof Deficiency
940 MW52.2 MW5,3011.16%10,000 (2)927 MW54.7 MW5,5621.16%15,000
946 MW51.7 MW5,4391.20%10,000 (1)911 MW52.5 MW5,1481.12%5000886 MW48.5 MW5,0111.18%0
ExtremeDeficiency
AverageUnder-Proc.
Total MWhUnder-Proc.
Percentage of Periods
WindDown-Regulation
105 /
In summary:• Regulation requirements for net load with high wind
penetration are statistically as “well behaved” as load only• The present ERCOT methodology for determining the
amount of regulation to procure remains effective with 15 GW of wind
• Linearity allows scale-up of regulation procurement to accommodate year-to-year wind additions
• Under-procurements are not substantially more severe• There may be improvements which might be made to the
methodology to reduce the amount of regulation procured while maintaining accuracy of procurement
107 /
In this next set of slides, we will show:• Hour-by-hour power production simulations for the wind
scenarios, using GE Multi-Area Production Simulation (MAPS) program– Unit commitment– Dispatch
• Program outputs– Production costs– Spot prices– Spinning reserve prices– Ramping capability and range– Emissions
Issues:• How wind affects unit commitment and production• Impact on market prices (energy and ancillary services)
108 /
Energy Output Commitment Based on State-of-Art Forecast
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
CC GT STCOAL STNG WIND
Ener
gy (G
Wh)
Zero Wind5 GW Wind10 GW Wind - Case 110 GW Wind - Case 215 GW Wind
Major impact is on combined cycle unit operation, consistent with results observed in other studies
109 /
Peak Load Week (Aug 11-18) - State of the Art Forecast
0
10000
20000
30000
40000
50000
60000
70000
80000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
HYDRO NUCLEAR STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
0
10000
20000
30000
40000
50000
60000
70000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106
113
120
127
134
141
148
155
162
Hour
MW
HYDRO NUCLEAR STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
Zero Wind - DispatchZero Wind - Commitment
15 GW Wind - Commitment 15 GW Wind - Dispatch
0
10000
20000
30000
40000
50000
60000
70000
80000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
0
10000
20000
30000
40000
50000
60000
70000
80000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
HYDRO NUCLEAR STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
110 /
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
NUCLEAR HYDRO STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
HYDRO NUCLEAR STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
Zero Wind - DispatchZero Wind - Commitment
15 GW Wind - Dispatch
05000
100001500020000250003000035000400004500050000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
05000
100001500020000250003000035000400004500050000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162
Hour
MW
Peak Wind Week (April 2-9) - State of the Art Forecast
15 GW Wind - Commitment
HYDRO NUCLEAR STEAM COAL WIND COMB. CYCLE STEAM GAS GAS TURBINE
111 /
Production Cost Reductions Due to Wind
0.00
10.00
20.00
30.00
40.00
50.00
60.00
5 GW Wind 10 GW Wind - Case 1 10 GW Wind - Case 2 15 GW Wind
Cos
t Sav
ings
($/M
Wh)
Value of wind decreases slightly with increased wind penetration
112 /
Total Annual Emissions (State-of-Art Wind Forecast Assumed)
54,000
56,000
58,000
60,000
62,000
64,000
66,000
68,000
Zero Wind 5 GW Wind 10 GWWind -Case 1
10 GWWind -Case 2
15 GWWind
NOx (TONS)
160,000,000165,000,000170,000,000175,000,000180,000,000185,000,000190,000,000195,000,000200,000,000205,000,000
Zero Wind 5 GWWind
10 GWWind -Case 1
10 GWWind -Case 2
15 GWWind
CO2 (TONS)
590,000
600,000
610,000
620,000
630,000
640,000
650,000
660,000
Zero Wind 5 GW Wind 10 GWWind -Case 1
10 GWWind -Case 2
15 GWWind
SO2 (TONS)
113 /
Energy Spot Prices – Assumes State of the Art Forecast
0
20
40
60
80
100
120
140
160
180
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
Hours
Spot
Pric
e($/
MW
h)
No Wind5 GW10 GW - Case 110 GW - Case 215 GW
114 /
Impact of Wind Forecast on Energy Prices – 15 GW Wind
0
20
40
60
80
100
120
140
160
180
0 1000 2000 3000 4000 5000 6000 7000 8000
Hour
Spot
Pric
e ($
/MW
h)
Zero WindNo ForecastStudy Year ForecastPerfect Forecast
Good forecasts minimize reductions in spot prices and reduce overall energy cost; due to less over-commitment
S-o-A Forecast
115 /
In summary:
• Emissions and nodal energy prices decrease as wind penetration increases
• Value of wind per MWh decreases slightly with increased wind penetration
• Bulk of energy displacement is from combined cycle units
• Lack of wind forecast results in significant over commitment of units – depressing nodal prices
117 /
In this next set of slides, we will show:• How the changes in unit commitment and dispatch
affect the ability to meet regulation requirements with increased wind penetration
Key issues are:• Displacement of conventional generation• Flexibility of committed units
118 /
Down Regulation Resources Based on state of the art forecast
0
200
400
600
800
1000
1200
1400
1600
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162Hour
MW
/Min
GAS TURBINE
STEAM GAS
COMB. CYCLE
STEAM COAL
HYDRO
0
500
1000
1500
2000
2500
3000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162Hour
MW
/Min
Gas TurbineSteam GasCombined CycleSteam CoalHydro
Zero Wind
0
500
1000
1500
2000
2500
3000
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162Hour
MW
/Min
Gas TurbineSteam GasCombined CycleSteam CoalHydro
15 GW Wind
0
200
400
600
800
1000
1200
1400
1600
1800
1 8 15 22 29 36 43 50 57 64 71 78 85 92 99 106 113 120 127 134 141 148 155 162Hour
MW
/Min
GAS TURBINESTEAM GASCOMB. CYCLESTEAM COALHYDROZero Wind 15 GW Wind
Min Load Week (March 20-27)
Peak Load Week (August 11-18)
Hydro Steam Coal Combined Cycle Steam Gas Gas Turbine
119 /
System Regulation CapacityLoad Alone Load – 5000 MW Wind
Load – 10,000 MW Wind (1) Load – 15,000 MW Wind
Range is limited to the amount which can be supplied in five minutes
-15000
-10000
-5000
0
5000
10000
15000
0 1752 3504 5256 7008 8760
Hour
MW
5 x Up RampUp Reg (Procured)Down Reg (Procured)5 x Down Ramp
-15000
-10000
-5000
0
5000
10000
15000
0 1752 3504 5256 7008 8760
Hour
MW
5 x Up RampUp Reg (Procured)Down Reg (Procured)5 x Down Ramp
-15000
-10000
-5000
0
5000
10000
15000
0 1752 3504 5256 7008 8760
Hour
MW
5 x Up RampUp Reg (Procured)Down Reg (Procured)5 x Down Ramp
-15000
-10000
-5000
0
5000
10000
15000
0 1752 3504 5256 7008 8760
Hour
MW
5 x Up RampUp Reg (Procured)Down Reg (Procured)5 x Down Ramp
120 /
Down Regulation Range DeficienciesDown-regulation requirements increase slightly.
System flexibility is decreased due to reduced net load
Result: system cannot accommodate down-regulation needs without adjusting dispatch
Tradeoff between costs of adjusting dispatch versus curtailment or ramp limit of wind generators.
-6000
-4000
-2000
0
500 550 600 650 700 750 800Hour
MW
5 x Down Ramp Down Reg (Procured)
3161571097710,000 (2)
712202103085115,000
48224627091110,000 (1)
00005,000
00000
MaximumShortfall (MW)
AverageDeficiency (MW)
Total MWhDeficient
HoursDeficient
Wind (MW)
121 /
Regulation Range
• Up-regulation range margin is reduced, but remains ample– Assuming 5-minute delivery– Margin could be less if a faster delivery is required
• Down-regulation range becomes an occasional issue for > 5,000 MW of wind– Committed conventional units are pushed toward their minimum
load levels– Relatively few hours are involved for wind levels investigated
• Alternatives– Conventional units can be de-committed to provide range,
can adversely impact economics during the next day– Allow wind plants to provide down-regulation– Apply up-ramp limits on wind generation– Curtail wind output
• Future operations will require increased flexibility from balance of generation
123 /
In this next set of slides, we will show:• The impact of wind on per-unit costs of regulation
services• The costs of increased regulation services to
accommodate wind penetration• Emphasis on relative metrics
124 /
0
10
20
30
40
50
60
70
80
90
100
0 1000 2000 3000 4000 5000 6000 7000 8000Hours
Cos
t of S
pin
($/M
Wh)
Zero Wind5 GW Wind10 GW Wind - Case 110 GW Wind - Case 215 GW Wind
State of Art Forecast
0
10
20
30
40
50
60
70
80
90
100
0 1000 2000 3000 4000 5000 6000 7000 8000Hours
Cos
t of S
pin
($/M
Wh)
Zero Wind5 GW Wind10 GW Wind - Case 110 GW Wind - Case 215 GW Wind
No Forecast
0
10
20
30
40
50
60
70
80
90
100
0 1000 2000 3000 4000 5000 6000 7000 8000Hours
Cos
t of S
pin
($/M
Wh)
Zero Wind5 GW Wind10 GW Wind - Case 110 GW Wind - Case 215 GW Wind
Perfect Forecast
Spin Cost for Various Wind Penetrations
125 /
Regulation Cost Assumptions
• REG cost is the greater of $5/MWh or the cost of spinning reserve
• Cost of wind curtailment added when –REG exceeds available range (spot price)
• Results most useful when considered on a relative basis
126 /
Cost of Meeting Regulation Service Requirements – S-o-A Forecast
• Reduction of net load slightly decreases per MWh cost of +REG and –REG, up through 10,000 MW scenarios
• Excess unit commitments due to load forecast errors, and reduced net load sharply drops regulation cost at 15,000 MW
0
2,000,000
4,000,000
6,000,000
0 5000 10000 15000Wind Capacity (MW)
Proc
ured
REG
MW
h
Total+REG-REG
75%
80%
85%
90%
95%
100%
105%
None 50
0010
,000 (
1)10
,000 (
2)15
,000
Wind Capacity (MW)
Rel
ativ
e C
ost o
f REG
pe
r MW
h Pr
ocur
ed
+REG-REG
0%
20%
40%
60%
80%
100%
120%
None 5000 10,000(1)
10,000(2)
15,000
Wind Scenario
Rel
ativ
e C
ost o
f Pro
cure
d R
EG
Total+REG-REG
127 /
Cost of Meeting Regulation Service Requirements –Perfect Forecast
• Reduced unit over-commitment allows unit costs of regulation to decrease gradually as net load is reduced by increased wind
• Total cost of +/- REG increases at a much lower rate than linear with respect to wind capacity
0
2,000,000
4,000,000
6,000,000
0 5000 10000 15000Wind Capacity (MW)
Proc
ured
REG
MW
h
Total+REG-REG
75%
80%
85%
90%
95%
100%
105%
None 50
0010
,000 (
1)10
,000 (
2)15
,000
Wind Capacity (MW)
Rel
ativ
e C
ost o
f REG
pe
r MW
h Pr
ocur
ed
+REG-REG
0%
20%
40%
60%
80%
100%
120%
None 5000 10,000(1)
10,000(2)
15,000
Wind Scenario
Rel
ativ
e C
ost o
f Pro
cure
d R
EG
Total+REG-REG
128 /
Regulation Costs Summary
• Per-unit costs of regulation are highly dependent on impacts of wind on dispatch
• Imperfect wind forecast leads to unit excess unit commitment, reducing regulation costs
• Results are volatile, makeup of future generation portfolio is critical
$0.07636,180,453$143.05$72.49$69.3610,000 (2)
$0.10737,037,236$142.30$72.93$70.1210,000 (1)
-$0.18053,933,379$129.37$67.94$61.4415,000
$0.17917,940,311$139.09$72.76$69.545,000
$0.14453,933,379$141.85$74.83$72.0115,000
$0.20036,180,453$146.33$76.21$70.1210,000 (2)
$0.27737,037,236$149.35$78.14$71.2210,000 (1)
$0.11217,940,311$141.11$73.21$67.905,000
0$139.09$72.21$66.880
Inc. Cost of Regulation
($/MWh)
Total Wind Generation
(MWh)
Total Reg. Cost
($MM)
Reg-DownCost
($MM)
Reg-Up Cost
($MM)
Wind Capacity
(MW)
State-of-Art Wind Forecast
Perfect Wind
Forecast
-$0.30
-$0.20
-$0.10
$0.00
$0.10
$0.20
$0.30
5000 10,000 (1) 10,000 (2) 15,000
Wind Scenario (MW)
Incr
emen
tal C
ost o
f REG
($/M
Wh)
(MW
h of
Tot
al W
ind
Prod
uctio
n)
S-o-A ForecastPerfect Forecast
131 /
Day-ahead predictability of net load is important to unit commitment; inaccuracies increase operating costs and may require greater A/S procurement.The next slides analyze net load predictability
133 /
Load Yearly Average Profile and Largest Forecast ErrorsStudy Year Load with 15000 MW of Wind
-18000
-12000
-6000
0
6000
12000
18000
24000
30000
36000
42000
48000
54000
Act
ual a
nd D
ay-A
head
Loa
d (M
W)
-9000
-6000
-3000
0
3000
6000
9000
12000
15000
18000
21000
24000
27000
Max
/Min
For
ecas
t Err
or (M
W)
Load ActualLoad ForecastMax Pos Forecast ErrorMax Neg Forecast Error
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Winter
Spring
Summer
Fall
May 20th: Largest Neg Load Forecast Error
Aug 28th: Largest Pos Load Forecast ErrorMarch 27th
Min Load Day
August 17th
Peak Load Day
Max L-W Error = 10294 MW (Aug 28th)MAE = 1296 MW (3.5% of Average)RMSE = 1792 MW (4.9% of Average)Sigma = 1755 (4.8% of Average)
Greater tendency to over-forecast load during the summer months
134 /
Net Load Yearly Average Profile and Largest Forecast ErrorsStudy Year Load with 15000 MW of Wind
-18000
-12000
-6000
0
6000
12000
18000
24000
30000
36000
42000
48000
54000
Act
ual a
nd D
ay-A
head
Loa
d-W
ind
(MW
)
-9000
-6000
-3000
0
3000
6000
9000
12000
15000
18000
21000
24000
27000
Max
/Min
For
ecas
t Err
or (M
W)
Load-Wind ActualLoad-Wind ForecastMax Pos Forecast ErrorMax Neg Forecast Error
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Winter
Spring
Summer
Fall
Mar 11th: Largest Neg L-W Forecast Error
Aug 28th: Largest Pos L-W Forecast Error
March 27th
Min Net Load Day
July 17th Peak Net Load Day
Max L-W Error = 9675 MW (Aug 28th)MAE = 1698 MW (5.5% of Average)RMSE = 2199 MW (7.2% of Average)Sigma = 2149 (7.0% of Average)
Wind generally increases net-load forecast errors in Winter and Spring more than Summer
135 /
Net Load and Wind Day-Ahead Predictability – Summary (Study Year Data)
5,000 MW 10,000 MW 15,000 MW
0
300
600
900
1200
1500
1800
Erro
r (M
W)
20
30
40
50
60
70
80
% E
rror
MAE (MW)RMSE (MW)%MAE%RMSE
2149(7.0)
1887(5.8)
1928(5.9)
1762(5.1)
1755 (4.8)
Std DevMW(%)
1698(5.5)
1467(4.5)
1505(4.6)
1338(3.8)
1296(3.5)
MAE*MW(%)
9765
9786
9763
9951
10294
Max Error (MW)
1936(5.9)
Load w/ 10,000 MW Wind (2)
1792(4.9)
Base Case: Load w/ no Wind
1805(5.2)
Load w/ 5000 MW Wind
2199(7.2)
1974(6.0)
RMSE**MW(%)
Load w/ 15,000 MW Wind
Load w/ 10,000 MW Wind (1)
Case
* Mean absolute error ** Root mean square error – more affected by large deviations
-59211614(26.3)
1294(21.1)
1611(26.2)
15,000 MW Wind
-40781096(26.6)
876(21.3)
1093(26.5)
10,000 MW Wind (2)
-42641169(27.7)
935(22.2)
1167(27.7)
10,000 MW Wind (1)
-2529639(31.3)
511(25.0)
638(31.2)
5000 MW Wind
Error = forecast – actual
500
1000
1500
2000
2500
Erro
r (M
W)
3%
6%
9%
12%
15%
% E
rror
MAE (MW)RMSE (MW)%MAE%RMSE
Load L-5,000 MW L-10,000 MW L-15,000 MW
Wind absolute error (MW) increases slower than average output
Absolute error (MW) and percent error increase linearly
Net Load
Wind
NB: Percent errors based on average output
136 /
Hourly Wind Predictability (Forecast Errors*) (Study Year Data)
0
200
400
600
800
1000
1200
1400
1600
1800
< -4500-4500 – -4200-4200 – -3900-3900 – -3600-3600 – -3300-3300 – -3000-3000 – -2700-2700 – -2400-2400 – -2100-2100 – -1800-1800 – -1500-1500 – -1200-1200 – -900-900 – -600-600 – -300-300 – 00 – 300300 – 600600 – 900900 – 12001200 – 15001500 – 18001800 – 21002100 – 24002400 – 27002700 – 30003000 – 33003300 – 36003600 – 39003900 – 42004200 – 4500> 4500
MW
Hou
rs
5000 MW Wind10000 MW Wind (1)10000 MW Wind (2)15000 MW Wind
Wind forecast error increases with wind, skewed to the left … tendency to under-forecast wind
Extreme Forecast Errors* Error = forecast – actual
Over-Commitment
Under-Commitment
910 / 364296 / 19384 / 418 / 0> ± 2300 MW (−/+)
67 / 00 / 00 / 00 / 0> ± 4600 MW (−/+)
43 / 048 / 038 / 033 / 0>µ ± 3σ (−/+)
121 / 1
10,000 MW Wind (2)
125 / 2
10,000 MW Wind (1)
114 / 1107 / 9>µ ± 2.5σ (−/+)
5000 MW Wind
15,000 MW Wind
137 /
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
< -6000-6000 – -5600-5600 – -5200-5200 – -4800-4800 – -4400-4400 – -4000-4000 – -3600-3600 – -3200-3200 – -2800-2800 – -2400-2400 – -2000-2000 – -1600-1600 – -1200-1200 – -800-800 – -400-400 – 00 – 400400 – 800800 – 12001200 – 16001600 – 20002000 – 24002400 – 28002800 – 32003200 – 36003600 – 40004000 – 44004400 – 48004800 – 52005200 – 56005600 – 6000> 6000
MW
Hou
rs
Load-aloneLoad-5000 MWLoad-15000 MW
Hourly Load-Wind Predictability (Forecast Errors*) (Study Year Data)
Wind adds to overall net load forecast error and increases number of extreme deviations … tendency to over-forecast net load
* Error = forecast – actual
Under-Commitment
Over Commitment
731 / 1591547 / 1357413 / 1048> ± 2300 MW (−/+)
51 / 217
17 / 74
67 / 152
W/ 5000 MW Windσ = 1762 Using load σ
17 / 77
66 / 160
51 / 12910 / 4315 / 95>µ ± 3σ (−/+)
132 / 27151 / 11164 / 185>µ ± 2.5σ (−/+)
26 / 186
Load-alone σ = 1755
> ± 4600 MW (−/+) 72 / 316
W/ 15000 MW Windσ = 2149 Using load σ
Extreme Forecast Errors
138 /
-6000
-4000
-2000
0
2000
4000
6000
-8000 -4000 0 4000 8000 12000
Load Forecast Error
Win
d Fo
reca
st E
rror
WinterSpringSummerFall
Correlation of Load and Wind Forecast Errors By Season (Study Year Load and 15000 MW of Wind)
10294 MW-6291 MW
R2 = .034
Over-commitment
Under-commitment
Under-commitment
Over-commitment
Increase L-W over-forecast
Increase L-W under-forecast Load and Wind
errors offset
Load and Wind errors offset
Q1Q2
Q3
Q4Q3
139 /
Correlation of Load and Wind Forecast Errors By Season (Study Year Load W/ 15000 MW)
-6000
-4000
-2000
0
2000
4000
6000
-8000 -4000 0 4000 8000 12000
Load Error
Win
d Er
ror
Winter
-6000
-4000
-2000
0
2000
4000
6000
-8000 -4000 0 4000 8000 12000
Load Error
Win
d Er
ror
Spring
-6000
-4000
-2000
0
2000
4000
6000
-8000 -4000 0 4000 8000 12000
Load Error
Win
d Er
ror
Summer
-6000
-4000
-2000
0
2000
4000
6000
-8000 -4000 0 4000 8000 12000
Load Error
Win
d Er
ror
Fall
Over-commitment
Under-commitment
Under-commitment
Over-commitment
Increase L-W Over-forecast
Increase L-W Under-forecast
Load and Wind errors offset
Load and Wind errors offset
Risk of simultaneousunder-commitment error is very small
Q1Q2
Q3 Q4
140 /
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24JanFebMarAprMayJunJulAugSepOctNovDec
Hour of Day
Mon
th o
f Yea
r
-2000-0-4000--2000-6000--4000-8000--6000
Timing of Negative Load Forecast Errors (Under-Commitment) (Study Year)
Largest load under-forecasts typically occur in the afternoon and early evening during Winter and early Spring
-6291 MW
-6272 MW
141 /
Timing of Negative Net-Load (Under-Commitment) Forecast Errors(Study Year Load with 15000 MW of Wind)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24JanFebMarAprMayJunJulAugSepOctNovDec
Hour of Day -2000-0-4000--2000-6000--4000-8000--6000
Large net-load under-forecasts much more spread with over the year due to spread in wind forecast errors. Extreme errors tend to occur in Winter and early Spring.
-7781 MW
-7322 MW
-6099 MW
-6083 MW
Mon
th o
f Yea
r
142 /
Incremental Under-Forecast Errors Due to Wind (Study Year Load with 15000 MW of Wind)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24JanFebMarAprMayJunJulAugSepOctNovDec
Hour of Day
Mon
th o
f Yea
r
1000-2500-500-1000-2000--500-3500--2000
15000 MW of wind tends to cause a moderately widespread increase in forecast uncertainty
-3028 MW
-2965 MW
-2605 MW
-2229 MW
-2338 MW
-2463 MW
-2631 MW
143 /
January Hourly Load and Net Load Forecast Errors (Study Year Load with 15000 MW of Wind)
(Avg. +/- sigma, Minimum, Maximum)
Hour of Day
Fore
cast
Err
ors
(MW
)
Tota
l Loa
d (M
W)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250
4500
9000
13500
18000
22500
27000
31500
36000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
Load ErrorsLoad-Wind ErrorsTotal LoadLoad-Wind
Risk that wind curtailmentcould be infrequently needed
Tends to be available resources
144 /
July Hourly Load and Net Load Forecast Errors (Study Year Load with 15000 MW of Wind)
(Avg. +/- sigma, Minimum, Maximum)
Hour of Day
Fore
cast
Err
ors
(MW
)
Tota
l Loa
d (M
W)
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250
7500
15000
22500
30000
37500
45000
52500
60000
-8000
-6000
-4000
-2000
0
2000
4000
6000
8000
Load ErrorsLoad-Wind ErrorsTotal LoadLoad-Wind
145 /
Observations and Conclusions
• Risk of under-commitment tends to occur off-peak when impact is low– Under-commitment aggravated by using a higher
confidence level wind forecast• During summer peak hours, wind forecast error tends to
partially cancel apparent bias in mean load forecast towards over-commitment
• Increased wind penetration does not create an obvious requirement for across-the-board non-spin reserve requirements increase– Periods where uncertainty is high and resources are tight
may require addition of NSRS– Consider a longer-term NSRS service
146 /
• Addition of wind requires a moderate increase of ancillary service requirements
• At certain low-load, high-wind conditions, providing down-regulation can be a challenge
• Present ERCOT procurement methodologies:– Regulation algorithm adequate, some incremental improvements are
possible– Responsive reserve procedure adequate, may need to account
for predicted wind risk periods– Non-spin can be a preferable alternative to carrying large amounts
of RRS during high-risk periods• Increased regulation services create a small increment (1%) in cost
relative to value of MWh supplied by wind
Overall Conclusions