Collaboration and Planning for Successful Stream ManagementDenise Cameron, Woodard & CurranJohn Livsey, Town of Lexington, MA
![Page 2: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/2.jpg)
The Original Green Infrastructure:The Stream Channel
![Page 3: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/3.jpg)
A Typical New England Stream History
![Page 4: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/4.jpg)
Circa 1930
![Page 5: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/5.jpg)
1930 - Today
Route 2
1930
TODAY
![Page 6: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/6.jpg)
The Need
▀ Persistent flooding and complaints from public▀ Sediment buildup in streams and wetlands▀ Old and deteriorated drainage infrastructure▀ Desire to improve water quality and protect
wildlife habitats ▀ Consistently increasing stormwater
regulatory requirements
![Page 7: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/7.jpg)
Driving Action through Planning: Development of Stream Management Plans
![Page 8: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/8.jpg)
Conservation
Public Works
A Collaborative Approach
![Page 9: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/9.jpg)
A Plan for Action
Town of Lexington worked with Woodard & Curran to develop a plan for both watershed restoration anddrainage enhancement.
![Page 10: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/10.jpg)
A Phased Implementation
The plan was implementedin three phases,per major watershed:
▀ Charles River▀ Mystic River▀ Shawsheen River
![Page 11: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/11.jpg)
It starts with data…
A multi-year,comprehensivedrainage study,including both:
▀ Desktop Assessment▀ Field Surveys
![Page 12: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/12.jpg)
...it grows through public involvement…
▀ Began collaboration early▀ Formal and informal meetings:
Director of Conservation Watershed Stewards Capital Expenditure Committee TMMA (Town Meeting Members Association) Board of Selectmen
▀ Build support for program to getfunding at Town Meeting
![Page 13: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/13.jpg)
…it is refined through prioritization…
Conducted a pair-wise comparisonwith the following scoring criteria
Health & Safety Flood Mitigation Coordination with other
Town Projects Environmental Benefits Social Impact Improved O&M Regulatory Compliance
![Page 14: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/14.jpg)
…and it leads to a consensus for CIP
▀ From the three watershedstream management plans,a single, Capital ImprovementsPlan was developed
![Page 15: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/15.jpg)
A Balanced Funding Approach
Infrastructure Project Funding
Ecological Drainage Restoration Funding
![Page 16: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/16.jpg)
The Plan’s Foundation:Field Surveys
![Page 17: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/17.jpg)
Structures and Crossings
Stream Reaches
Stormwater Outfalls
What We Looked For In The Field…
![Page 18: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/18.jpg)
What we found in the field…
![Page 19: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/19.jpg)
What we found in the field…Culverts in
good shape…
…and culverts with structural and safety
issues
![Page 20: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/20.jpg)
What we found in the field…Trash and debris…
…hydraulic restrictions
![Page 21: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/21.jpg)
What we found in the field…Sediment buildup…
…and straightened channels
![Page 22: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/22.jpg)
What we found in the field…Stormwater Inputs…
…and drainagetrouble spots.
![Page 23: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/23.jpg)
The Plan’s Recommendations: Project Identification
![Page 24: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/24.jpg)
Categories of Recommendations
▀ Infrastructure & drainage restoration▀ Wetlands protection▀ Drainage investigation▀ Roadway and drainage system O&M▀ Long-term O&M for streams
![Page 25: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/25.jpg)
Fact Sheets
▀ One per recommendation▀ Summarizes existing
conditions andproposed project
▀ Detailed maps
![Page 26: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/26.jpg)
Putting the Plan into Action:Project Case Studies
![Page 27: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/27.jpg)
Willard’s Woods Stream Restoration
![Page 28: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/28.jpg)
Willard’s Woods Stream Restoration
![Page 29: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/29.jpg)
Willard’s Woods Stream Restoration
▀ Rather than replacing thefailed culvert, the Townopted to daylight the stream
![Page 30: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/30.jpg)
Willard’s Woods Stream Restoration
▀ A rock vane wasconstructed forenergy dissipationand grade control
![Page 31: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/31.jpg)
Willard’s Woods Stream Restoration
![Page 32: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/32.jpg)
Willard’s Woods Stream Restoration
▀ A headwall was constructed for the stream crossing under North Street
![Page 33: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/33.jpg)
Willard’s Woods Stream Restoration
▀ Pedestrian bridge was constructed at trail crossing
![Page 34: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/34.jpg)
Willard’s Woods Stream Restoration
▀ To save an existing tree, a stone wall was created using stones from the failed culvert
![Page 35: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/35.jpg)
Willard’s Woods Stream Restoration
▀ The stone was alsoused to reconstructthe stone wall alongNorth Street
![Page 36: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/36.jpg)
Willard’s Woods Stream Restoration:A Multi-disciplinary Approach
▀ Successful streamrestoration ismultidisciplinary Scientists Engineers Landscape Architects, Contractors experienced in
ecological restoration
![Page 37: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/37.jpg)
Willard’s Woods Stream Restoration:Creating a Natural Stream…not a Ditch
▀ Construction documents were developed to allow for flexibility during construction to better mimic the irregular conditions of a natural stream.
![Page 38: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/38.jpg)
Willard’s Woods Stream Restoration: Reference Reach Model
![Page 39: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/39.jpg)
Willard’s Woods Stream Restoration:Which one is the New Stream?
![Page 40: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/40.jpg)
Willard’s Crossing:
![Page 41: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/41.jpg)
▀ Sediment buildup at the trail culvert restricts culvert flow, contributing to upstream flooding
Willard’s Crossing: Culvert Removal
![Page 42: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/42.jpg)
Willard’s Crossing: Bridge Construction
▀ Vehicular Bridge to improve emergency access▀ Stone channel to manage flooding both upstream
and down
![Page 43: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/43.jpg)
Willard’s Crossing: Bridge Construction
![Page 44: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/44.jpg)
Vine Brook – Streambank Stabilization
![Page 45: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/45.jpg)
Vine Brook – Streambank Stabilization
▀ Bank failure led to sediment buildup in Vine Brook
![Page 46: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/46.jpg)
Vine Brook – Streambank Stabilization
![Page 47: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/47.jpg)
Vine Brook – Streambank Stabilization
![Page 48: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/48.jpg)
Vine Brook – Streambank Stabilization
![Page 49: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/49.jpg)
Whipple Hill Culvert
Replacement
Pleasant Street Drainage
Improvements
Valleyfield Drainage
Assessment
Upcoming Projects
![Page 50: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/50.jpg)
Conclusions: Keys to Success
![Page 51: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/51.jpg)
Keys to Success
▀ Engage community, municipal departments, and environmental groups to make it one all-encompassing project
▀ Don’t separate water quantity and quality▀ Make it an active plan – not just a study sitting
on shelf▀ Don’t lose momentum!
![Page 52: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/52.jpg)
Contacts
▀ Woodard & Curran Denise Cameron ([email protected]) Zach Henderson ([email protected])
▀ Town of Lexington John Livsey ([email protected]) David Pavlik ([email protected]) Karen Mullins ([email protected])
▀ Town of Lexington web site http://www.lexingtonma.gov/stormwater
![Page 53: Collaboration and Planning for Successful Stream Management](https://reader033.fdocuments.in/reader033/viewer/2022041819/625477a1df3b2d6c6e5ed923/html5/thumbnails/53.jpg)
Questions &Discussion