18 August 2009 1
FORT BELVOIRDEVELOPMENT BRIEFING
FOR
SOUTH FAIRFAX DEVELOPMENT CORPORATION
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009 2
~24,000 PERSONNEL (Main Post and Rivanna Station) ~7,000 RESIDENTS ~8,500 ACRES (7,700 acres Main Post; 800 acres FBNA; 29 acres Rivanna Station) ~100 DIVERSE AGENCIES:
• 1 Major U.S. Army Command Headquarters, 10 U.S. Army Commands, 19 Agencies and reporting units of the D.A.
• 8 elements of U.S. Army Reserve and Army National Guard
• 26 DoD Agencies
• Davison Army Airfield
ORGANIZED INTO 9 FUNCTIONAL AREAS: • Humphreys Engineer Center (HEC): 600 acre post
• Upper North Post: home of major DoD Agencies, 1,930 acres
• Davison Army Airfield: fixed and rotary aircraft, 800 acres
• Lower North Post: barracks & Reserve training, 320 acres
• Fort Belvoir North Area (FBNA): home of NGA, 800 acres
• Southwest Area: training area/ranges, 2,100 acres
• South Post: admin, Hospital & Town Center, 2,550 acres
• South Post Core: FB historic district, 100 acres
• Sub-installation: Rivanna Station, 29 acres
Fort Belvoir Functional Area Map
WHERE WE ARE TODAY
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
3
2011-2030 Planning Accomplishments: BRAC is implemented Buildings are modernized PX & Commissary upgraded Recreation master plan implemented Major on and off post roads improved Town Center realized
44,100 PERSONNEL (Main Post, FBNA, Mark Center, Rivanna Station)
9,000 RESIDENTS ~8,600 ACRES (7,700 acres Main Post; 800 acres FBNA; 16 acres Mark Center, 76 acres Rivanna Station) ~160 Diverse Agencies INCOMING:
▫ BRAC projects:NGA, Army Lease, Community Hospital, Dental Clinic, NARMC, MDA, PEO-EIS, WHS (Mark Center), JUIAF (Rivanna Station), Infrastructure
▫ BRAC-related projects:Emergency Services Center (FBNA), USANCA, South Post CDC, ACP upgrade
▫ New Missions:Warrior Transition (WT), National Museum of the U.S. Army, Office of the Chief of Army Reserves (OCAR), Family Travel Camp, Medical Guest House
▫ DD 1391 Programmed Projects:North Post CDC, Expand and replace Commissary & PX, South Post Fire Station Replacement, Museum Support Center, SCIF, Flight Control Tower, modernize barracks
WHERE WE ARE GOING: BRAC AND PROGRAMMED PROJECTS
Over 150 projects within BRAC timeframe
Over 150 projects within BRAC timeframe
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
4
Net Gain ~19,300-Main Post: ~3400
-FBNA: ~8500-Mark Center: ~6400
-Rivanna Station: ~1000
(Main Post Current: ~23,000 )
INCOMING
OUTGOING
2006 2007 2008 2009 2010 2011
Soldier’s Mag (~20)
DLA Mgt Ctrl (~20)
Army Lease (~2800)
21,517
2,140
WHS(~6400 @Mark Center)
JUIAF – DIA (~1000-- @ Rivanna Station)
FBCH (~2050)
DTRA, AR (~21)
Prime Power School (~100)
Seabees (~16) CID (~130)
C4ISR Elements (~400) AMC/USASAC
(~1440)
HQ MDA (~292) PEO EIS (~400)
NGA (~8500--@ FBNA)
DTRA, CB (~50)
AGENCY TIMELINES
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
FORT BELVOIR COMMUNITY HOSPITAL
HOSPITAL CAMPUS
18 August 2009
5
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
6
Warrior Transition Complex
Community Hospital
North Atlantic Region Medical Command (NARMC)
Dental Clinic
Screen shot from 4D model showing Medical Campus at full build-out.
Screen shot from 4D model showing Medical Campus at full build-out.
ChildDevelopment
Center
AmbulanceShelter
Central Utility Plant (CUP)(Hospital)
Helipad
Gu
nsto
n R
oad
Belvoir Road
6th Street
Route 1
9th Street
MEDICAL CAMPUS OVERVIEW, 2009-2011
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
7
SCOPE: 1.275M SF hospital complex with 120 inpatient beds, clinics, central energy plant, helipad, and 3500 parking spaces
PERSONNEL: 3,200 (2,069 new; 1,131 currently at DeWitt Community Hospital)
MILCON PROGRAMMED AMOUNT: $806.9M BRAC FY07-10 CONSTRUCTION AGENT: Norfolk District CONTRACT: Awarded to Turner-Gilbane (Integrated Design-
Bid-Build) STATUS:
▫ Erecting steel for Clinics A, B, C, D and E▫ Design 100% complete; construction 36% complete
MILESTONES:▫ Tracking toward final major slab placements in both garages
NLT end of JUL 09▫ Clinic Transitions begin AUG 10▫ Construction complete 31 MAR 11▫ Initial Operating Capability APR 11
E(Meadows Pavilion)
D(Sunrise Pavilion)
C(Oak
Pavilion)
B(Eagle
Pavilion)
A(River
Pavilion)
FBCH (BRAC 169) PROJECT PROFILE
14 AUG 09
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
8
FORT BELVOIR COMMUNITY HOSPITAL (BRAC 169) CONSTRUCTION
14 APR 09
14 AUG 09
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
9
SCOPE: Two 4-story barracks (194.4K SF total) buildings with various room configurations for wounded warriors; 30.7K SF Company HQ, 8K SF Battalion HQ, 15K SF Soldier and Family Assistance Center (SFAC).
PERSONNEL: Complex supports 412 total troops; Facility supports 276 wounded warriors and 130 administrative staff
MILCON PROGRAMMED AMOUNT: $76M FY09 (Supplemental – 12 DEC 08 Directive; PA increased 6 MAR 09)
CONSTRUCTION AGENT: Baltimore District (Site Development)▫ Fort Worth District is Center of Standardization (COS) (Design-Build)
CONTRACT: Design-Build to be awarded under 2 Multiple Award Task Order Contracts (MATOC) STATUS:
▫ Design-Build RFP 100%▫ Re-designated as FY09 Supplemental
Project▫ 30-day public review period of EA
began 23 JUL 09▫ Solicitation posted 30 JUN 09
MILESTONES: ▫ Target award DB contract 15 SEP 09▫ Beneficial occupancy date (BOD)
15 JUL 11 PERCENT COMPLETE: 0%
WARRIOR TRANSITION COMPLEX (BRAC-Related – Hospital)
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
10
Screen shot from 4D model showing Warrior in Transition Complex at full build-out
Screen shot from 4D model showing Warrior in Transition Complex at full build-out
Vernondale VillageHousing Area
South Side Grill(existing)
Belvoir Road
9th Street
138 PN BarracksHospitalBldgs. D & EHospitalBldgs. C, D & E
HospitalSouth Garage
138 PN Barracks138 PN Barracks
6th StreetWT Admin HQ
Soldier and Family Assistance Center (SFAC)
WARRIOR TRANSITION COMPLEX (BRAC-Related – Hospital)
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
OTHER BRAC PROJECTS
UPDATE ON OTHER BRAC AND BRAC RELATED PROJECTS
18 August 2009
11
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
12
SCOPE: 99K SF multi-story highly secure headquarters facility, with surface parking
PERSONNEL: 292 MILCON PROGRAMMED AMOUNT: $37.8M
BRAC FY08 CONSTRUCTION AGENT: Baltimore District CONTRACT: $33M awarded to Foulger-Pratt
(Design-Build) 18 AUG 08 STATUS:
▫ Construction 7% complete MILESTONES:
▫ Begin vertical construction JUL 09▫ Beneficial occupancy date (BOD) 8 JUN 10
PERCENT COMPLETE: Construction 7%
MISSILE DEFENSE AGENCY (BRAC 134) PROJECT PROFILE
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
13
MILESTONES:▫ Garage construction complete 30 JUL 10▫ Main Building occupation—South Wing JAN 11▫ All construction complete APR 11▫ North Wing occupation MAY 11
PERCENT COMPLETE:▫ Design 90%; Overall Construction 25%▫ Overall Site/Civil completion ~38%▫ Main Building construction 32%▫ Tech Center construction 98%▫ CUP construction 98%
PERCENT COMPLETE (Continued): ▫ Garage completion 45%▫ Remote Inspection Facility 0%▫ Visitor Control Center 0%
SCOPE: 2.41M sq. ft. office with SCIF, tech center, utility plant, visitor control center, structured parking for 5,100 vehicles, and remote inspection facility
PERSONNEL: 8,500 MILCON PROGRAMMED AMOUNT: $1.7B CONSTRUCTION AGENT: Baltimore District CONTRACT: Awarded to Clark, Balfour Beatty (Integrated Design-Bid-Build) STATUS: Fast tracked and on schedule
▫ Groundbreaking SEP 07 ▫ First Operational Building Ceremony 10 JUL 09▫ See “Percent Complete” data
NGA (BRAC 168) PROJECT PROFILE
“Know the Earth…Show the Way”
4 AUG 09
4 AUG 09
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
14
NGA (BRAC 168) CONSTRUCTION
4 AUG 09
COL Jerry L. Blixt/IMNE-BEL-ZA/[email protected]/(703) 805-2052)//COL Mark Moffatt/IMNE-BEL-BRAC/(703) 805-1660/ [email protected]
UNCLASSIFIED
18 August 2009
15
PHASE I
PHASE II
PHASE IIIStimulus funded
PHASE IVStimulus funded
OPTION 1 DAR 2009
BRAC Infrastructure
OPTION 1 DAR 2009
OPTION 2I-95 HOV Access
DAR 2010
FORT BELVOIR NORTH AREA
FAIRFAX COUNTY PARKWAY & I-95 HOV ACCESS CONSTRUCTION PHASING