Cobar Management Pty Ltd - CSA · CMPL 2011 AEMR ii Cobar Management Pty Ltd CSA Mine Annual...

125
COBAR MANAGEMENT PTY LTD CSA Mine Annual Environmental Management Report AEMR 2011

Transcript of Cobar Management Pty Ltd - CSA · CMPL 2011 AEMR ii Cobar Management Pty Ltd CSA Mine Annual...

COBAR MANAGEMENT PTY LTD

CSA Mine

Annual Environmental Management Report

AEMR 2011

i

Blank Page

CMPL 2011 AEMR

ii

Cobar Management Pty Ltd

CSA Mine

Annual Environmental Management Report

2011

Name of Mine CSA Mine

Mining Leases CML 5

MOP Commencement Date: 01/01/2008 MOP Completion Date: 31/12/2012

AEMR Commencement Date: 01/01/2011 AEMR End Date: 31/12/2011

Name of Leaseholder: Isokind Pty Ltd.

Name of Mine Operator: Cobar Management Pty Ltd

Reporting Officer: Tanya Gilbert

Title: Manager - Health, Safety, Environment and Training

Signature

Date 31 January 2012

Cobar Management Pty Ltd

ABN: 38 083 171 546

PO Box 31, Cobar, NSW 2835

Tel: (02) 6836 5100

Fax: (02) 6836 2146

www.cmpl.com.au

CMPL 2011 AEMR

iii

CONTENTS 1 INTRODUCTION ....................................................................................................................................... 1

1.1 History of Operations ............................................................................................................................... 1

1.2 Consents, Leases and Licenses ................................................................................................................. 2

Mine Contacts .................................................................................................................................................... 5

1.3 Actions required from 2010 AEMR review ............................................................................................... 6

2 SUMMARY OF OPERATIONS DURING THE REPORTING PERIOD .......................................... 10

2.1 Mineral Exploration ............................................................................................................................... 11

2.2 Land Preparation.................................................................................................................................... 13

2.3 Construction ........................................................................................................................................... 14

2.4 Mining ..................................................................................................................................................... 16

2.5 Mineral Processing ................................................................................................................................. 22

2.6 Waste Management ................................................................................................................................. 25

2.7 Ore and Product Stockpiles .................................................................................................................... 28

2.8 Water Management ................................................................................................................................. 31

2.9 Hazardous Materials .............................................................................................................................. 43

2.10 Other Infrastructure Management ..................................................................................................... 48

3 ENVIRONMENTAL MANAGEMENT AND PERFORMANCE ........................................................ 51

3.1 Air Pollution ........................................................................................................................................... 51

3.2 Erosion and Sedimentation ..................................................................................................................... 61

3.3 Surface Water Quality ............................................................................................................................ 62

3.4 Ground Water ......................................................................................................................................... 66

3.5 Contaminated Polluted Land .................................................................................................................. 74

3.6 Threatened Flora .................................................................................................................................... 75

3.7 Threatened Fauna ................................................................................................................................... 76

3.8 Weeds ...................................................................................................................................................... 77

3.9 Blasting ................................................................................................................................................... 78

3.10 Operational Noise .............................................................................................................................. 78

3.11 Visual, Stray Light ............................................................................................................................. 78

3.12 Aboriginal Heritage ........................................................................................................................... 79

3.13 Natural and European Heritage ........................................................................................................ 80

3.14 Spontaneous Combustion ................................................................................................................... 81

3.15 Bushfire .............................................................................................................................................. 81

3.16 Mine Subsidence ................................................................................................................................ 81

3.17 Hydrocarbon Contamination ............................................................................................................. 82

3.18 Methane Drainage / Ventilation......................................................................................................... 82

3.19 Public Safety ...................................................................................................................................... 83

3.20 Other Issues and Risks ....................................................................................................................... 83

4 COMMUNITY RELATIONS .................................................................................................................. 91

CMPL 2011 AEMR

iv

4.1 Environmental Complaints ..................................................................................................................... 91

4.2 Community Liaison ................................................................................................................................. 91

5 REHABILITATION ................................................................................................................................. 99

5.1 Buildings ................................................................................................................................................. 99

5.2 Rehabilitation of Disturbed Land ........................................................................................................... 99

5.3 Other Infrastructure .............................................................................................................................. 103

5.4 Rehabilitation Trials and Research ...................................................................................................... 104

5.5 Further Development of the Final Rehabilitation Plan ........................................................................ 110

6 ACTIVITIES PROPOSED FOR 2012 ................................................................................................... 114

7 REFERENCES ........................................................................................................................................ 116

7.1 Plans ..................................................................................................................................................... 117

7.2 Appendices ............................................................................................................................................ 117

TABLES

Table 1 MOP Amendments during the 2008 - 2012 MOP Period ...................................................................... 2 Table 2 CMPL Mining and Exploration Leases (as at 31/12/11) ........................................................................ 3 Table 3 CMPL Land Tenure (as of 31/12/11) ..................................................................................................... 4 Table 4 CMPL Licences and Permits (as of 31/12/2011) ................................................................................... 4 Table 5 CSA Mine Management and Environmental Contacts .......................................................................... 5 Table 6 Actions Required from the 2010 AEMR Review .................................................................................. 7 Table 7 Update on Proposed activities for the 2011 AEMR Period .................................................................... 8 Table 8 Actual and Forecast Production (dmt) (as of 31/12/2011) ................................................................... 17 Table 9 Backfill Production and Final Tailings 2011 ....................................................................................... 18 Table 10 CMPL Current Mining Equipment (as of 31/12/11) .......................................................................... 19 Table 11 CSA Budget versus Actual Mine Production 2011 ............................................................................ 22 Table 12 Metal Recovery 2011 ......................................................................................................................... 23 Table 13 Reagent Consumption 2011 ............................................................................................................... 24 Table 14 CSA Identified Topsoil Stockpiles ..................................................................................................... 29 Table 15 CSA Cumulative Waste and Stockpile Production ............................................................................ 30 Table 16 Summary of Catchment Areas ........................................................................................................... 33 Table 17 CSA Mine Water Storage................................................................................................................... 36 Table 18 CSA 2011 Water Balance .................................................................................................................. 41 Table 19 CSA Bulk Hazardous and Dangerous Goods Storage (as of 31/12/11) ............................................. 45 Table 20 Comparison of NPI Emission Sources by Activity Levels for 2009-10 and 2010-11 ........................ 55 Table 21 Summary of CMPL Energy Consumption and Greenhouse Gas Emissions ...................................... 56 Table 22 Short-Medium Term Energy Saving and Carbon Emission Reduction Opportunities ....................... 58 Table 23 Long Term Energy Saving and Carbon Emission Reduction Opportunities ...................................... 58 Table 24 Priority Management Practice Actions .............................................................................................. 60 Table 25 CSA Surface Water Monitoring Results 2010 and 2011 .................................................................... 63 Table 26 STSF Piezometers and Trigger Depths .............................................................................................. 67 Table 27 CSA Piezometer Water Quality Monitoring Results 2011 ................................................................. 72 Table 28 CSA Environmental Incidents 2011 ................................................................................................... 89 Table 29 Land Use Options............................................................................................................................... 93 Table 30 CMPL Donation Recipients 2011 ...................................................................................................... 98 Table 31 LFA Rehabilitation Monitoring Results 2011 .................................................................................. 109 Table 32 Summary of Proposed Rehabilitation .............................................................................................. 112 Table 33 Maintenance Activities on Rehabilitated Land 2011 ....................................................................... 113 Table 34 Proposed activities for 2012 ............................................................................................................. 114

CMPL 2011 AEMR

v

FIGURES

Figure 1 CMPL Organisation Chart 2011 ........................................................................................................... 5 Figure 2 CSA Mine General Waste Management Performance 2011 ............................................................... 26 Figure 3 CSA Topsoil Stockpile Locations ....................................................................................................... 29 Figure 4 Burrendong Dam Water Storage Level (%) and Cumulative Rainfall (mm) 2011 ............................. 31 Figure 5 CSA Mine Catchment Boundaries 2011 ............................................................................................. 33 Figure 6 Long Term Raw Water Used per Tonne Milled ................................................................................. 40 Figure 7 CSA Mine Water Balance 2011 .......................................................................................................... 42 Figure 8 Backfill Sump Upgrade Design and Completed backfill Sump November 2011 ............................... 49 Figure 9 2011 Cobar Mean temperatures and CSA Mine Rainfall ................................................................... 51 Figure 10 CSA Depositional Dust Monitoring Results 2011 ............................................................................ 53 Figure 11 CSA Mine Total Energy Consumption (GJ) 2010 – 2011 ................................................................ 56 Figure 12 CSA Mine Total Greenhouse Gas Emissions (t CO2-e) 2010 - 2011 ............................................... 56 Figure 13 Management Practices Assessments – Level of Development ......................................................... 60 Figure 14 Erosion and Sediment Control Inspections 2011 .............................................................................. 61 Figure 15 CSA Piezometer Depths 2011 .......................................................................................................... 66 Figure 16 Cross Section of TSF Piezometer Setup ........................................................................................... 69 Figure 17 CSA Ground Water Monitoring Results 2011 .................................................................................. 73 Figure 18 CSA Contaminated Sites Register (as of 31/12/11) .......................................................................... 75 Figure 19 Due Diligence Process for the Protection of Aboriginal Heritage .................................................... 79 Figure 20 CMPL Environmental Incidents by Type 2010 and 2011 ................................................................ 88 Figure 21 Conceptual Stages of Sustainable Ecosystem Development........................................................... 111

PLANS

1 Mine Context

2 Land Preparation and Mining Activities

3 Rehabilitation

4 Mining Plan - Vertical Section

5 Site Layout

APPENDICES

A Environmental Protection Licence 1864

B 2010 AEMR Review Meeting Minutes

C Stormwater Drainage Improvement Works Report

D CMPL Environment and Community Policy

E CSA Air and Water Quality Monitoring Data 2011

F Contaminated Sites Sampling Report 2011

G Industrial Heritage Site Listing Report

H STSF Surveillance Report 2010

I 2011 Annual Return EPL 1864

J 2011CSA Rehabilitation Monitoring Report

K Rehabilitation Monitoring Methodology and Determination of Completion Criteria for

Rehabilitation Ecosystems report

CMPL 2011 AEMR

vi

ABBREVIATIONS

ANZECC Australia and New Zealand Conservation

Council

LPMA Land and Property Management Authority

ARPANSA Australian Radiation Protection and Nuclear

Safety Authority

LFA Landform Function Analysis

CHF Cemented Hydraulic Fill Mt Mega Tonne

CMPL Cobar Mining Pty Ltd m Meter

CML Consolidated Mining Lease mm Milli meter

Cu Copper MOP Mining Operations Plan

CSA Cornish, Scottish, Australian Mine NATA National Association of Testing Authorities

DSC Dam Safety Committee NGER National Greenhouse and Energy Reporting

Act 2007

DSEWPC Department of Sustainability, Environment,

Water, Population and Communities

NPI National Pollutant Inventory

DTIRIS Department of Trade and Investment,

Regional Infrastructure and Services

NORM Naturally Occurring radioactive materials

DMP Derelict Mines Program NTSF North Tailings Storage Facility

DEM Digital Elevation Model OEH Office of Environment and Heritage

DRE Division of Energy and Resources PJ Pentajoule

dmt Dry Metric Tonnes PET Polyethylene Terephthalate

EEO Energy Efficiency Opportunities Act PAF Potentially Acid Forming

ESAP Energy Savings Action Plan REMP Rehabilitation and Environment Management

Plan

ESS Energy Savings Scheme RC Reverse Circulation

EPA Environment Protection Authority SWMP Site Water Management Plan

EPL Environment Protection Licence STSF South Tailings Storage Facility

EL Exploration Lease SG Specific Gravity

ft Foot TSF Tailings Storage Facility

GJ Gigajoules t Tonnes

HDPE High Density Polyethylene WRF Waste Rock Fill

KPI Key Performance Indicator wmt Wet Metric Tonne

CMPL 2011 AEMR

vii

Blank Page

1

1 INTRODUCTION

This document has been written in line with the Guidelines to the Mining, Rehabilitation and Environmental

Management Process (MREMP)1 provided by the New South Wales (NSW) Department of Trade and

Investment, Regional Infrastructure and Services (DTIRIS) (formerly the Department of Industry and

Investment).

Under the Mining Act 1992, environmental protection and rehabilitation are regulated by mining lease

conditions, including requirements for the leaseholder to prepare two main documents:

A Mining Operations Plan (MOP) which describes the manner in which the leaseholder proposes to

conduct mining, processing and rehabilitation consistent with development consent, and the conditions

imposed by the DPI and other agencies; and

An Annual Environmental Management Report (AEMR) which reports on the performance of the

leaseholder and ‘fine tunes’ the MOP.

Collectively, the MREMP aims to facilitate the development of mining in NSW and to ensure all mining

operations are safe, the resources are efficiently extracted, the environment is protected and rehabilitation

achieves a stable, satisfactory outcome.

This document will be provided to the following regulatory bodies for review:

NSW Department of Trade and Investment, Regional Infrastructure and Services (DTIRIS) (formerly

the Department of Industry and Investment) ;

Land and Property Management Authority (LPMA);

NSW Office of Environment and Heritage (OEH) (formerly the Department of Environment, Climate

Change and Water);

NSW Dam Safety Committee (DSC); and

Cobar Shire Council (CSC).

1.1 History of Operations

Cobar Management Pty Ltd (CMPL) operates the Cornish, Scottish and Australian (CSA) Mine located 11 km

north of Cobar in the west of NSW.

Mining has occurred intermittently on the CSA leases since the discovery of copper, lead and zinc in 1871.

However, it was not until 1961 that a significant resource was proven by Broken Hill South Pty Ltd. Medium-

scale mechanised underground mining subsequently commenced in 1965. The mine was acquired by CRA in

1980 and sold to Golden Shamrock Mines Pty Ltd (GSM) in 1993. GSM was in turn acquired by Ashanti Gold

Fields in the same year. The mine continued to operate until 1997, when the operation ran into financial

difficulties and was placed in receivership. The mine was placed on care and maintenance on the 20 January

1998.

1 DTIRIS (2006) Guidelines to the Mining, Rehabilitation and Environmental Management Process. EDG03 version 3

CMPL 2011 AEMR

2

Conditions for reopening the mine were negotiated with the liquidator, and concessions were obtained from the

Government, including the excision of three areas of concern from the lease: the North Tailings Dam; the

subsidence hole and adjacent old spoil material; and, a major coarse rejects stockpile (Big Mt Brown). CMPL

committed to reopening the mine in February 1999 with current underground and processing operations

commencing in July 1999 following the purchase of the leases and site facilities.

CMPL, a wholly owned Australian subsidiary of Glencore International AG (Switzerland) continues to operate

the CSA Mine, which is currently the highest grade Copper and second deepest mine in Australia.

1.2 Consents, Leases and Licenses

CMPL has a large number of statutory approvals and associated legal obligations that regulate mining activities

on site. The status of CMPL main statutory approvals are listed in Table 2 to Table 4.

CMPL holds Consolidated Mining Lease 5 (CML5) for the CSA Mine operations and two small mining

purposes leases 1093 and 1094 (MPL1093 and MPL1094). CML5 occupies portions of five Western Land

Leases and Crown Land including parts of the Cobar Regeneration Belt. MPL1093 and MPL1094 occupy

Crown Land. These details are shown in Plan 1. Throughout this document these leases are collectively referred

to as the CSA Mine.

The CSA Mine operates in accordance with the CMPL 2008 – 2012 MOP and its associated amendments

displayed in Table 1. Nil amendments were made during 2011. The current MOP remains in effect until 31

December 2012.

Table 1 MOP Amendments during the 2008 - 2012 MOP Period

Date Section of MOP

Amended Description

Approved:

8/07/2009

3.7 - Ore &

Product

Stockpiles

Temporary Surface Ore Stockpiling

During periods of approved special circumstances (for example, lack of

water supply to the Ore Processing Mill, emergency mill shutdowns,

major shut downs of the underground mine due to infrastructure

upgrades, etc), CMPL are permitted to surface stockpile ore. In all such

cases, CMPL will inform I&I prior to any special circumstances that

may necessitate the surface stockpiling of ore at the CSA Mine.

Application:

21/07/2010

3.6 - Waste

Management South Tailings Storage Facility 3m wall raise Granted approval to amend the MOP to include a 3 metre wall raise lift

to the South Tailings Storage Facility (STSF).

CMPL 2011 AEMR

3

Table 2 CMPL Mining and Exploration Leases (as at 31/12/11)

Lease

Number Details Issue Date

Expiry

Date

CML5 CSA mine site. Licensed for Group 1 minerals (Sb, Cu, Zn, Pb, Fe,

In, Au, Ge, Co, Cd, Bi & Fe minerals) 2/12/1993 24/6/2028

MPL1093 Mining Purposes Lease for Water Harvesting. Not licensed for

minerals 5/2/1947 5/2/2029

MPL1094 Mining Purposes Lease for Water Harvesting. Not licensed for

minerals 5/2/1947 5/2/2029

EL5693 Exploration Lease (CSA Regional) 20 km north of Cobar. The lease

surrounds CML5 8/2/2002 7/2/2012

2

EL5983 Exploration Lease (Delta) 20 km north of Cobar and lies wholly

within EL5693 30/8/2006 29/8/2012

2

EL6140 Exploration Lease (Restdown) 40 km east southeast of Cobar. Joint

Venture (JV) project with Oxley Exploration Pty Ltd 22/10/2003 21/10/11

1

EL6501 Exploration Lease (South Restdown) 40 km southeast of Cobar. JV

project with Oxley Exploration Pty Ltd 5/1/2006 4/1/2012

1

EL6739 Exploration Lease (Horseshoe 2) 65 km east of Cobar. JV project

with Oxley Exploration Pty Ltd 26/3/2011 26/3/2011

1

EL6223 Exploration Lease (Shuttleton) 75km south southeast of Cobar. JV

project with AuriCular Mines Pty Ltd 5/4/2004 4/4/2012

2

EL6907 Exploration Lease (Mt Hope) 145 km south of Cobar. JV project with

AuriCular Mines Pty Ltd 11/10/2007 10/10/2011

1

EL6868 Exploration Lease (Mt Hope) 160km south of Cobar. JV project with

AuriCular Mines Pty Ltd 6/9/2007 5/9/2011

1

EL6381

Exploration Lease (Captain’s Flat) 15 km south of Captain’s Flat in

south-eastern NSW. JV project with Forge Resources Ltd and

Ironbark Zinc Limited

22/2/2005 21/2/20122

EL6840

Exploration Lease (Captain’s Flat North) 17 km north of Captain’s

Flat in south-eastern NSW. JV project with Forge Resources Ltd and

Ironbark Zinc Limited

19/7/2007 19/7/2013

Notes:

1. Renewal applications have been submitted

2. Renewal applications will be submitted during 2012

CMPL 2011 AEMR

4

Table 3 CMPL Land Tenure (as of 31/12/11)

Property

Name Locality WLL County Parish

Plan

Number

Lot

Number

Red Tank CSA Mine 9565 Robinson Kaloogleguy 766965 4277

Red Tank East of mine 731 Robinson Kaloogleguy 766922 6336

Red Tank Immediately south of mine 13844 Robinson Kaloogleguy 766965 4278

Gattaca South of mine 13844 Robinson Kaloogleguy 766741 4174

Gattaca South of mine 13844 Robinson Kaloogleguy 765641 927

Mopone Northeast of tailings facility 1009 Robinson Mullimutt 768325 5414

Terramia South and east of tailings facility 3667 Robinson Mopone 763396 1594

Table 4 CMPL Licences and Permits (as of 31/12/2011)

Licence Details Renewal Date

Environment Protection

Licence No. 1864

Licence held with the NSW Environment Protection Authority

(EPA) (Appendix A)

Review Date:

28/04/111

Radiation Licence

No. 29023

Licence to sell/possess radiation apparatus and/or radioactive

substances or items containing radioactive substances.

Expires:

28/11/12

Local Development

Consent No. 31/95 CSC Permit for use of CSA Mine Site by CMPL

Granted

26/6/1998

Local Development

Consent No. 2006/LDA-

00009

CSC Permit for Construction & Operation of South Tailings

Dam Extension.

Granted

22/6/2006

Local Development

Consent No. 2009/LDA-

00035

CSC Permit for South Tailings Storage Facility Wall Raise

Granted

7/4/2010

Bonded Asbestos

Removal Licence No.

204696

Granted by NSW WorkCover for on-site removal of bonded

asbestos only

12/12/2010

(Renewed)

Expiry Date

12/12/12

Bore Licence No.

85BL256081

Bore licence certification under Section 115 of the Water Act,

1912. For the purposes of Test Bores

Expiry Date

8/10/13

Note: 1 Nil correspondence received to date on OEH Review

5

Mine Contacts

The management structure at the CSA Mine is displayed in the organisational chart in Figure 1. The structure

was revised during the 2011 AEMR reporting period with the appointment of a new Mine Manager and the

merging of three departments and creation of the Health, Safety, Environment and Training Manager role. The

CMPL management team and environmental contacts are listed in Table 5.

Table 5 CSA Mine Management and Environmental Contacts

Title Name Phone Email

General Manager Rubens de Figueiredo 6836 5111 [email protected]

Acting Ore Processing Manager Derek Beehan 6836 5394 [email protected]

Mining Manager Geoffrey Hender 6836 5178 [email protected]

Health Safety Environment & Training Manager Tanya Gilbert 6836 5357 [email protected]

Finance Manger Michael Cox 6836 5124 [email protected]

Shaft Project Manager Les Kennedy 6836 5367 [email protected]

Human Resources Superintendent Brien Obray 6836 5136 [email protected]

CSA Pollution Complaints Line CSA switchboard 6836 5100 [email protected]

Figure 1 CMPL Organisation Chart 2011

General Manager Rubens de Figueiredo

Manager Ore Processing

Derek Beehan

Manager Finance

Michael Cox

Manager Health, Safety

Environment & Training

Tanya Gilbert

Manager Mining

Geoffrey Hender

Shaft Project Manager

Les Kennedy

Accounts

Supply & Contracts

Mining

UG Maintenance

Geology & Exploration

Technical Services

Records

Management

Health & Safety

Training

Environmental

Ore Processing

Surface Maintenance

Tailings Dam

Project Mining Engineers

Project Cost Controller

6

1.3 Actions required from 2010 AEMR review

The 2010 AEMR review meeting and site inspection was held at the CSA Mine on 31 March 2011 and was

attended by representatives from DTIRIS, OEH, LPMA, CSC, NSW Office of Water (NOW), Peak Gold Mine

(PGM), and Straits Tritton Copper Mine (Tritton).

The 2010 AEMR review meeting minutes are provided in Appendix B. Actions arising from the meeting and the

Sections of this report in which they are addressed are listed in Table 6. Table 7 provides an update on all

activities proposed for 2011 as listed in Section 6 of the 2010 AEMR.

CMPL 2011 AEMR

7

Table 6 Actions Required from the 2010 AEMR Review

Action required Status Update

and Reference

Surface water management

Prepare and submit updated Surface Water Management Plan when completed

In Progress: Due

Feb 2012

Section 2.8.2

Old smelter site catchment area

Provide further explanation of the re-classification of Catchment Area C19 from

contaminated to clean, supporting data to be provided

Complete 15/4/11

Appendix C

Contaminated soil register

Provide Contaminated Soil Register to DTIRIS and OEH

Complete 15/4/11

Appendix F

Eloura site

Investigate requirements to manage the Eloura site and determine if it is within the

Mining Lease or CMPL owned property

Incomplete.

Rescheduled 2012

Tailings rehabilitation trial

Provide Tailings Rehabilitation Trial Report to DTIRIS and OEH when completed

Complete 2/6/11.

Section 5.4.2

Development consent

Meeting with CSC to discuss the Development Consent Conditions Complete 29/4/12

Exploration drill sites

Rehabilitation of exploration CML5 drill sites to be conducted immediately

Complete 15/5/11

Section 2.1

Test water bore sites

Clean up and removal of sample bags from the Water Bore drilling sites surrounding the

TSF

Complete 30/6/11

Piping

Complete a site wide audit of the current piping requirements, remove redundant pipes

and ensure adequate bund capacity is available for all necessary pipes

Incomplete.

Rescheduled 2012

Backfill plant

Construct planned backfill bunding upgrade to ensure compliant bund capacity,

implement automation to prevent ongoing spillage issues, clean silted drain at entrance to

backfill MCC building

Complete 1/11/11

Sections 2.3.1 &

2.8.2

Big Mount Brown area

Remove remaining pile of crushed Big Mount Brown contaminated waste material

In progress.

Remaining

material due 2012

Tailings storage facility

Inform DTIRIS and OEH when TSF wall raise construction and final clean up works are

completed, introduce management measures to ensure exposed external tailings areas do

not become dust issues

Complete 30/6/11

Section 3.1.3

Lined decant water storage dam

Provide details to DTIRIS and OEH on pending decision for the removal of tailings

material in the base of the lined decant water storage dam

Complete 16/5/11

Borrow pit dam

Repair erosion damage at Borrow Pit Dam, remove tailings material from the drying pad

and isolate the dedicated drying pad area to ensure future disturbance is minimised

Complete 30/5/11

Section 2.3.1 &

2.8.2

Operational water storage dams

Rock line the inlet drain at the new dams to prevent future erosion issues, lower the

overflow pipe to ensure it is effective when required and clean up historic tailings spillage

behind these dams

Complete 30/5/11

Section 2.8.2 &

2.8.3

CMPL 2011 AEMR

8

Table 7 Update on Proposed activities for the 2011 AEMR Period

Proposed Activity Priority

Ranking

Status Update and

Reference

5 yearly Tailings Dam Surveillance Inspection to be conducted by qualified

Dam Engineer H

Complete 15/2/11

Section 3.20

Further pursue MOP amendment application for temporary surface

stockpiling ore during special circumstances H No longer required.

Emergency and Operational Water Storage Dam and settling bund

construction behind the Ore Processing Plant H

Complete 1/3/11

Sections 2.3.1, 2.8.2

& 2.8.3

CMPL to document a plan for the management or removal of the Mirrlees

diesel engines located in the CSA Mine Power Station and inform all other

interested parties of the outcome

H Complete 1/10/11

Section 3.1.3

Expand and continue monitoring the TSF Wind Erosion Trial H Complete 2011

Section 3.13

Clean rockfill material generated from Decant Dam Extension to be placed

on STSF outer embankment at batter angles ≥ 17°. Grass seed to be applied

when complete

H Complete 30/8/11

Section 5.2.3

Establish Tailings Rehabilitation Trials on the north west corner of the

STSFE H

Complete 1/10/11

Section 5.4.2

Continue Tailings Thickener Upgrade including secondary pump H Complete 30/6/11

Section 2.3.1

Full site external Energy and Emissions Audit of CSA Mine H Complete 5/5/11

Section 3.1.6

Develop and implement a revised CSA Mine Site Water Management Plan H In progress.

Section 2.8.2

Complete actions arising from Tailings Dam surveillance inspections and

submit report to NSW DSC H

Complete 22/6/11

Section 3.20

Installation of backfill bund level sensors, connection to the backfill control

system and automation of the floatation tails pipeline valve to resolve

inadequacies of the current backfill containment bund

H

Complete 1/11/11

Sections 2.3.1 &

2.8.2

Further investigate the viability of the groundwater test bore holes and

determine sustainability H

Complete 30/10/11

Section 2.8.4

Progress with removal of redundant infrastructure and equipment, such as

old thickener tanks and column cells at the Ore Processing Plant and all

infrastructures requiring removal prior to works progressing on the No. 1

Shaft Extension Project

H Complete 30/10/11

Section 5.1

Analogue Monitoring Program (RAP and LFA) annual assessment and data

analysis H

Complete 30/11/11

Section 5.4.3

CMPL 2011 AEMR

9

Proposed Activity Priority

Ranking

Status Update and

Reference

Continue to progress the No. 1 Shaft Extension Project H Ongoing

Section 2.3.2

Develop an underground settling and pumping system to allow effective

reuse of recycled water underground M

In progress

Budgeted 2012

Section 2.8.6

Decommissioned high voltage electricity transformers containing PCB are

to be removed off site and disposed of by licensed contractor M

Complete 30/12/11

Section 2.9.3

Liaise with the I&I NSW Derelict Mines department to further progress the

potential for a NTSF rehabilitation project M

On Going

Section 5.3

Relocate and upgrade bunding for the Hydrocarbon Storage Area at the Ore

Processing Plant M

Complete 16/05/11

3.2.1

Work with I&I NSW Derelict Mines to plan for the rehabilitation of the

excised Big Mount Brown area and surrounding CSA Mine disturbed land M

Incomplete

Section 5.3

Sample and analyse sites of suspected contamination and monitor

contamination through the soil profile in known areas of contamination in

order to update the CSA Mine Contaminated Soils Register

M Complete 22/11/11

Section 3.5

Complete remaining earthworks associated with the Stormwater Network

Improvement Plan M

Complete 30/6/11

Section 3.2

Investigate alternative backfilling methodologies to optimise the use of

waste rock fill underground and minimise any requirement to hoist waste in

the future

M In progress

Section 2.3.2

Ongoing educational campaigns to achieve a recycling rate

consistently greater than 30% M

Ongoing

Section 2.6.1

Continue internal Energy Team Meetings and Actions implementation M Ongoing

Section 3.1.5

Redundant radiation gauges to be removed and disposed off site by licensed

contractor L

Complete 30/4/11

Section 2.9.2

Dust Collection System for the Backfill Circuit and Liming Circuit L Not required

Section 2.10

CMPL 2011 AEMR

10

2 SUMMARY OF OPERATIONS DURING THE REPORTING PERIOD

In 2011 the production rate was maintained above 1,000,000 tonnes (t); this was an excellent result for the third

year running. Prior to 2009 the previous five years production average was 720,000 t.

2011 budgeted production rates were set at 1,150,000 dry metric tonnes (dmt) of ore which would produce

181,419 dmt of concentrate and 51,705 t of copper (Cu). Actual production achieved in 2011 was just below

target with 1,038,913 dmt ore milled, 162,533 dmt concentrate produced and 44,698 t of Cu.

The primary focus of the Ore Processing department for 2011 was to modify the plant and services to an extent

that long-term production and budget throughput could be maintained consistently. To this extent a number of

major projects were undertaken and completed during the year including:

Improved housekeeping standards;

Mill HV Upgrade;

Feeder impact bed replacement;

150ft Thickener repairs;

Flotation floor concrete removal;

Powerhouse HV Upgrade;

Power factor correction stage 1;

MCC 01 power & distribution upgrade; and,

C2/C3 Diverter chute installation.

Works to upgrade the grinding circuit in the mill in conjunction with the ongoing shaft extension project will

commence in 2012 with a scheduled completion date of quarter four 2013. Projects include:

The construction and installation of a new surface coarse ore stockpile on surface;

Installation of a new grinding mill; and,

Installation of overland conveyors and associated equipment.

The primary focus for the Mining Department for 2011 was achieving budget ore production at grade and cost.

A number of projects were completed or commenced in 2011, these included:

Commenced No1 Shaft Extension Project;

Development of the infrastructure for, and support of, the No1 Shaft Extension Project;

Upgrade of the existing surface refrigeration plant;

End of life change out of key pieces of fleet including, 2 trucks, 2 loaders, 2 concrete agitators, 1

production drill and 1 development jumbo; and,

Power supply ring main.

CMPL 2011 AEMR

11

Key projects for the underground mine in 2012 and 2013 include:

Progression of the No1 Shaft Extension Project;

Development of the drives and chambers required for the No1 Shaft Extension Project including

construction of new crusher, conveyors, drives and workshops;

Changing stope void fill medium from cemented hydraulic (CHF) fill to paste fill;

Introduction of a proximity detection technology underground;

End of life change out of key pieces of fleet including 3 trucks, 2 loaders, 1 Tele-handler;

Expand refrigeration capacity; and,

Extend fibre optic capability to the bottom of the mine.

Projects completed in 2011 coupled with those to be completed in 2012 will ensure an increase in sustainability

and a reduction in major process disruptions thus providing more positive improvements and opportunities to the

operation.

2.1 Mineral Exploration

CMPL’s 2011 exploration activities were principally focussed on underground drilling at the CSA Mine.

Limited surface exploration programmes were completed. A summary of all surface exploration activities is

summarised in the following sections.

Improved environmental management of exploration operations was achieved in 2011 through the fostering of

close links between the Environment and Geology Teams and the continued adherence to improved

environmental management procedures first implemented in 2010. During 2011, pre-disturbance baseline

studies for all new exploration programs requiring ground disturbance and an annual inspection of rehabilitated

exploration programs were completed by the Environment Team. Both programs will be continued in 2012.

Detailed exploration proposals specific to exploration activities during the 2012 AEMR period will be submitted

as appropriate to DTIRIS for approval prior to commencement, either as Surface Disturbance Notices, Review of

Environmental Factors, or other formats as required by the department.

2.1.1 CML5

Four diamond drill holes were completed on CML5 over 2010 targeting the underground Western Gossan

mineralisation and potential extensions to mineralisation. Three of these drill holes were rehabilitated in 2011

with the fourth planned to be rehabilitated early in 2012. Exploration drill hole sites are inspected on the

completion of rehabilitation works and annually thereafter to monitor the progress and success of rehabilitation.

Further diamond drilling and Reverse Circulation (RC) percussion drilling is scheduled to occur on CML5

during 2012.

CMPL 2011 AEMR

12

2.1.2 EL5693 CSA Regional

EL5693 field work during 2011 involved non-invasive ground geophysical surveys. Planned drilling for 2011

was not carried out due to scheduling issues resulting from delays in the engagement of contractors at the

beginning of the year. The exploration drilling schedule for 2012 will see a total of 2,200 m RC drilling take

place on the EL5693 lease.

2.1.3 EL5983 Delta

Four RC holes were drilled on EL5983 in 2010. All four drill sites were fully rehabilitated during 2011 Planned

drilling for 2011 was not carried out due to scheduling issues resulting from delays in the engagement of

contractors at the beginning of the year. Approximately 300 m of RC drilling is planned within the lease during

2012.

2.1.4 EL6140, EL6501, EL6739 (Restdown, South Restdown and Horseshoe)

No field work has been conducted by CMPL on EL6140, EL6501, or EL6739 since 2009. These leases are

subject to a farm-out arrangement with Oxley Exploration NL. Sixty two RC holes were completed by Oxley

within the EL6140 during 2011. Of these, 10 holes have been rehabilitated. The remainder will be rehabilitated

during the first quarter of 2012.

A total of 1,981 soil samples were collected across the three tenements. Sample sites were rehabilitated

immediately following collection of the sample; as per standard practice.

2.1.5 EL6223 (Shuttleton)

The two diamond drill holes drilled in 2010 were rehabilitated during 2011. Drilling planned for 2011 was not

completed due to scheduling issues resulting from delays to the engagement of contractors at the beginning of

the year. Drill Sites were inspected by the CSA Environmental Team in December 2011 and were found to be

safe, stable and non-polluting. Pioneer species including Cooper and Galvanised Burr, Corkscrew Grass were

present on the sites. The site will be monitored annually until the relinquishment of the EL to monitor the

progress of rehabilitation and implement any required works.

Non-invasive ground geophysics, a further 1,000 m diamond drilling and 1,000 m RC drilling are planned for the

Shuttleton lease during 2012.

2.1.6 EL6907, EL6868 (Mount Hope)

The three diamond drill holes completed on lease EL6907 during 2010 were rehabilitated in early 2011. Non-

invasive soil sampling, surface geophysical surveys and three diamond drill holes were completed within

EL6907 during 2011. One of these holes has been rehabilitated while the remaining two will be rehabilitated in

early 2012. Work proposed for 2011 for EL6868 was not completed due to scheduling issues resulting from

delays to the engagement of contractors at the beginning of the year. These works have been postponed to 2012.

Drill sites were inspected by the CSA Environmental Team in December 2011 and were found to be safe, stable

and non-polluting. Pioneer species (including some weeds) were found to be colonising on drill sites, providing

CMPL 2011 AEMR

13

the initial cover for perennial shrub and pasture species to establish. This site will be inspected in the 2012

reporting period to track rehabilitation progress and implement any required works.

2.1.7 EL6381, EL6840 (Captain’s Flat)

One diamond drill hole was completed on EL6381 during 2011. This site will be rehabilitated early in 2012.

Further diamond drilling, RC drilling and non-invasive surface geophysical surveys are planned for Captain’s

Flat during 2012. Sites will be inspected by the CSA Environment Team at the completion of rehabilitation and

annually thereafter to monitor the progress of rehabilitation and to ensure sites are safe, stable and non-polluting.

Surface exploration activities for the 2012 AEMR period will cover all tenements and will include diamond and

RC drilling as well as the basic non-invasive ground surveys and soil sampling. Sites will be rehabilitated as

soon as practicable after completion of programs, in line with departmental guidelines. Rehabilitation activities

will include cleaning up the site, filling sumps, ripping (where appropriate), and capping drill holes.

2.2 Land Preparation

Mining operations at the CSA Mine during 2011 were conducted in accordance with the 2008 – 2012 MOP.

CMPL activities continue to minimise land clearing as best practice in order to preserve the natural vegetation

and stability of the surrounding environment. Where clearing is required, it is managed through the CSA Work

Permit System. Permission to excavate is granted through this procedure and associated form to ensure that the

proposed area of disturbance has been checked for underground services (power and water) and approved for

vegetation clearing by the Environment Team.

This system applies to all employees and contractors at the CSA Mine and ensures considerations such as the

size of the proposed site, the stockpiling of soil and vegetation, search for any historical or cultural sites, and

drainage are all accounted for prior to approval of the works. Any actions or conditions associated with the

works are documented and signed off on the permit.

2.2.1 Topsoil

Land preparation and surface material stockpiling is assessed in all CMPL operations to ensure long term storage

requirements are met without further disturbance or unnecessary clearing. Approximately 29,700 m3

of

previously cleared areas at the CSA Mine have been identified as potential topsoil stockpile locations. The

majority of the areas are located in cleared areas surrounding the Tailings Storage Facility (TSF), hence

minimising potential future losses due to double handling and transport during rehabilitation works.

The management of all topsoil on site is carried out in accordance with the CMPL Topsoil Management Plan

which has been developed to ensure all topsoil handling, stockpiling and use is carried out in line with Mining

Lease conditions and Environmental Protection Licence (EPL) requirements.

Permanent stockpile height restrictions exist on site, with a maximum of 3 m for topsoil and 5 m for waste rock

stockpiles. CMPL encourages the establishment of vegetation on all topsoil stockpiles to enhance soil viability

CMPL 2011 AEMR

14

and minimise erosion losses. Cleared vegetation around project sites or surrounding areas is often spread over

the topsoil stockpile sites to assist with revegetation.

No projects requiring land clearing occurred over the 2011 AEMR period.

2.2.2 Underground Waste Rock

Underground mining operations at the CSA Mine produce approximately 400,000 t of waste rock annually.

Waste rock produced is predominantly disposed of into underground voids left by stoping operations. There are

occasionally cases in which the volume of waste rock generated by development exceeds the volume of void

produced by stoping operations (generally during the development of accesses to new resources). In order to

prevent production loss from development curtailment, surface hoisting of development waste has been

permitted during such times. Material permitted for hoisting is only from areas pre-assessed for acid generation

potential. Material identified as potentially acid forming (PAF) or acid forming (AF) is not permitted for

hoisting to surface. Non acid forming (NAF) material that is hoisted to surface is used as a resource in projects

on site where possible.

2.2.3 Contaminated Land

Waste from the clean up of contaminated materials, process spills and the de-silting of dirty or contaminated

catchment dams are disposed of at the South Tailings Storage Facility (STSF). During 2011 fifteen overflow

incidents involving tailings, backfill, hydrocarbons or process water were recorded at the CSA Mine.

These incidents resulted in a combined total of approximately 4,000 m3 of contaminated material being disposed

of at the STSF. Information on these incidents is displayed in Section 3.20.

2.3 Construction

2.3.1 Construction Activities

Several construction projects were completed at the CSA Mine in 2011 including:

Emergency and operational water storage dam and settling bund construction:

Works occurred in January 2011 to construct an operational water storage dam behind the tailings thickener

at the Mill. The dam increased the mills water storage capacity and will be used as emergency back-up

storage during a tailings thickener failure. This project included construction of an earthen storage dam, a

significant capacity increase and improvement to the concrete settling bund, installation of a new pump,

piping and electrics.

A number of design inadequacies were identified after the installation of the concrete settling bund

including its inability to be regularly maintained by plant available on site and its capacity and functionality

to capture tailings and sediments. These design inadequacies are scheduled to be addressed in January

2012 with the upgrade of the concrete settling bund detailed in Section 2.3.2.

CMPL 2011 AEMR

15

Backfill area:

In November 2011 a 22 m3 sump was installed and a bund was upgraded at the backfill plant to increase its

overall capacity to 56 m3 or 112% of the mixing tank. These works have significantly reduced the

likelihood of uncontrolled spills occurring from the backfill plant. Spillages of backfill in this area reduced

dramatically from 7 incidents in 2010 to only 1 in 2011. Additional information is included in Section

2.10.

Nitric Acid bund resealing

In 2011 it was identified that corrosion of the concrete bund housing the nitric acid tank had occurred due

to spills nitric acid occurring over a number of years. CMPL engaged specialist contractors to supply and

install a sealing system that would ensure the integrity of the bund for the life of the mine. Works included

the installation of an acid resistant fibre glass coating followed by a sealing product.

Before and After Resealing the Nitric Acid Bund

Tailings thickener upgrade:

An upgrade of the Mill Control Centre (MCC02) was completed in June 2011. This upgrade ensures the

electrical capacity to operate a secondary pump from the tailings thickener. Surface protection of the

internal and external walls of the tailings thickener was completed in January 2011.

2.3.2 Scheduled Construction Activities 2012

Several construction works and smaller infrastructure improvement upgrades are planned for 2012, these

include:

Underground internal shaft extension:

Works commenced in early 2010 to extend the No. 1 Shaft by approximately 500 m and install a new

winder. These works will enable hoisting of ore and waste rock to the surface from a lower level in the

mine, deliver fresh air to the bottom of the mine, and enable efficient transport of personnel to and from

their workplaces.

During 2011,horizontal development of the No. 1 shaft access (8740 L) and vertical development of the 1.5

diameter raise bore (9240L – 9000 L) was completed. Works on surface associated with the project

included the establishment of two lay down areas (3,600 m2

and 4,500 m2), the addition of demountable

CMPL 2011 AEMR

16

offices and the removal of surface infrastructure such as old winders and fans and their associated concrete

and electrical structures.

Further works will continue throughout 2012 and 2013 with commissioning of the new No. 1 Shaft

expected in December 2013. Works scheduled for completion in 2012 include the establishment of a

laydown yard at the portal (3,000 m2), the addition of a new change house, and ongoing horizontal and

vertical progression of the shaft.

Concrete settling bund upgrade

A number of design inadequacies were identified following the installation of the concrete settling bund at

the mill in 2011. The bunds ability to capture tailings and sediments from the residue pit, and its ability to

be regularly maintained by onsite equipment was found to be inadequate. The sump is scheduled to be

upgraded to address these inadequacies in January 2012. The sump will be enlarged to allow access by

onsite plant and the residence time of water in the bund will be increased to improve settling and allow the

passing of clean water.

Backfill area

A feasibility study on the use of paste fill in underground operations will be conducted in 2012. Pending

the outcome of the feasibility study, CMPL will seek to implement paste fill to replace the current fill

medium of Cemented Hydraulic Fill (CHF). The proposed works will involve a significant alteration of the

current plant and an associated stockpile. An application to amend the MOP will be submitted to DTIRIS

prior to works commencing should they be proposed for the 2008-2012 MOP period.

Tailings thickener replacement:

An 18 m diameter thickener is proposed to be installed to replace the existing 150 foot (ft) thickener. The

existing thickener utilises out-dated technologies and is in need of major repairs to ensure ongoing

operation. Initial project scoping, design and risk assessments have been completed and works are

anticipated to commence in quarter four 2012.

2.4 Mining

2.4.1 Underground Resource Status

The current resource is estimated at 11.3 Mt with 6.0% Cu between 9275 m relative level (RL) to 8400 m RL.

The 8400m RL is approximately 1900 m below the surface. There is potential for further resources to exist at

depth and also within this RL range.

The current proved and probable reserves in the CSA Mine active ore bodies (QTS North and South systems)

from 9250 m RL to 8400 m RL stand at 5.6 Mt with 4.79% Cu. There is also potential for further reserves in

other systems, which are yet to be evaluated.

CMPL 2011 AEMR

17

2.4.2 Production History and Production Forecast

Table 8 summarises the CSA’s mining history from 2008 and the forecast for the next five years. Annual

production was maintained during 2011. Copper metal production for 2011 was 56,500 dmt; this is down from

2010 due to a lower head grade during 2011. Forecast mine production for the next five years is based on the

shaft extension works progressing during 2012 and finishing in 2013 allowing an increase in production.

Table 8 Actual and Forecast Production (dmt) (as of 31/12/2011)

Year 2008 2009 2010 2011 2012 2013 2014 2015 2016

Ore 877,240 1,067,927 1,067,459 1,035,000 1,100,000 1,100,000 1,200,000 1,300,000 1,400,000

Grade 5.24% 5.00% 4.88% 4.33% 4.72% 4.87% 4.44% 4.56% 4.54%

Cu

Metal 44,328 53,936 50,059 56,500 49,700 51,977 42,660 55,568 60,126

Ore mined over the period 2009, 2010, 2011 and forecast through to 2012 is between 30 – 40% greater than

originally predicted in the 2007-2012 MOP. The Grade however has been 10 – 12% lower than predicted in the

MOP, with the overall Cu metal production therefore 38% greater than MOP predictions for 2011. If the

forecast ore production and grade are achieved in 2012, the overall Cu Metal will likely be 34% greater than

previously predicted in the MOP. The increased production and lower grades experienced over the past three

years will be reflected in future predictions and the updated CSA Mine MOP which is due in 2012.

2.4.3 Estimated Mine Life

The short term plan is to continue mining at the current rate of approximately 1.1 Mt/a (dmt) to the 8670 level

(1600 m below surface) in the QTS North and between the 9045 and 8985 levels (between 1195 m and 1255 m

below surface) in the QTS South. Proved and probable reserves can sustain this rate for approximately 4 years,

while there appears to be adequate resource below this depth in the QTS North and within the QTS South eastern

and western systems to sustain the current mining rate for at least a further six years. The current mining rate

equates to approximately 50 m vertical advance per year.

During 2012, work will continue on the No. 1 Shaft to extend it down to the 8790 m RL which will enable

hoisting entirely up this shaft to the surface. The key benefits of this extension are to provide a far more efficient

hoisting and ventilation system for the mine. By hoisting ore from lower levels in the mine, there will be

reduced truck haulage distances and truck fleet numbers. It is anticipated that this shaft extension will allow the

mine production rate to increase to approximately 1.4 Mt/a (dmt) for the long term. With this mine production

rate and with current resource estimates, mine life is expected to be approximately 10 years.

2.4.4 Backfilling and Tailings

The CSA Mine continues to use CHF and waste rock to fill underground openings created by production

activities. Hydraulic fill is obtained by separating a suitable fraction of tailings and cement addition as required.

The target for contained fines in hydraulic fill is no greater than 10% less than 10 microns (µm), and this is

consistently achieved or bettered.

CMPL 2011 AEMR

18

Over 300,000 t of cemented and un-cemented hydraulic fill was placed into underground voids during the 2011

period, representing 51.08% of flotation tailings produced by milling operations. In addition, approximately

125,000 t of waste rock was used to supplement the hydraulic fill and to fill other voids not requiring cemented

fill. The average (± standard deviation) size of the backfill product was 4.36% (± 0.43) passing 10 microns and

the average specific gravity was 1.78 (± 0.01). Total backfill placed was lower during 2011 due to issues with

the underground reticulation. This also contributed to lower production. Backfilling is planned to be back to

over 450,000t per annum in 2012. Table 9 shows the total backfill production and final tailings loads for 2011.

Table 9 Backfill Production and Final Tailings 2011

2011

Backfill Production Final Tailings

Cemented

(dmt)

Un-

cemented

(dmt)

%

passing

10

microns

Specific

Gravity (dmt)

%

Flotation

Tailings

Jan 5,427 259 4.67 1.78 73,962 7.14

Feb 19,682 2,434 4.26 1.79 40,749 35.18

Mar 22,733 1,854 4.38 1.79 41,348 37.29

Apr 29,901 2,760 4.48 1.79 44,972 42.07

May 26,892 3,796 4.49 1.78 39,056 44.00

Jun 39,366 3,339 4.84 1.79 31,238 57.75

Jul 23,522 2,382 4.58 1.80 50,815 33.76

Aug 24,021 2,729 4.93 1.79 49,390 35.13

Sep 27,078 3,345 4.77 1.79 33,708 47.44

Oct 20,373 1,758 4.62 1.79 38,651 36.41

Nov 34,310 3,466 4.42 1.80 46,486 44.83

Dec 32,388 6,377 4.07 1.79 45,812 45.83

Total 305,693 34,499 4.54 1.79 536,188 38.90

2012

Estimate 480,632 <10

1.78 -

1.82 443,660 52.00

Note: 1. dmt = dry metric tonnes

During 2012 CMPL will continue to investigate alternative backfilling methodologies to optimise the use of

waste rock fill and minimise any requirement to hoist waste, therefore decreasing the cycle time of the stoping

sequence. See Section 2.3.2 for information on the paste fill feasibility study planned for 2012.

2.4.5 Mining Equipment

There have been no significant changes in the number of mining equipment used at the CSA Mine during 2011.

In 2011 CMPL added several new pieces of mining equipment to the CSA fleet as part of the site equipment

management process. This includes: 2 Atlas 6020 dump trucks; 2 Normet Concrete Agitator trucks; 1 Sandvik

CMPL 2011 AEMR

19

Jumbo; 1 Production Drill Simba L6C; and, 2 Elphinstone R2900 Loaders. Extra equipment used during 2011

operations included a contract Cable-Bolt Rig and contract Jaycon Shotcrete Rig.

Plans for 2012 will see an additional dump truck introduced to the underground fleet to compensate for the

additional haulage distance. It will see the replacement of an Atlas MT5010 Ejector Truck with the latest model

from Atlas, as well as the replacement of 2 CAT AD55B with an Atlas 6020.

With the shaft extension project continuing through 2012 and into 2013 there is likely to be an increase in the

number of contractors associated with these projects, and therefore an increase in the number of contractor light

vehicles.

The current status of surface and underground equipment at CSA is shown in Table 10.

Table 10 CMPL Current Mining Equipment (as of 31/12/11)

CMPL Equipment 2010 2011 Projected

2012

Atlas Copco M2D Rocket Boomer Drill 1 0 0

Atlas Copco Simba L6C Production Drill Rig 2 2 2

Atlas Copco MT5010 Dump Truck 3 1 1

Atlas Copco MT5010 Ejector Truck 2 2 2

Caterpillar AD55B Dump Truck 3 2 0

Atlas Copco MT6020 Dump Truck 0 2 4

Caterpillar 980G Loader 1 1 1

Caterpillar IT28F Tool Carrier 2 0 0

Caterpillar IT28G Tool Carrier 1 2 2

Caterpillar 930H 0 2 2

Caterpillar 12G Grader 2 2 2

Caterpillar TH460B Telehandler 2 1 1

Caterpillar TH360 Telehandler 1 0 0

Caterpillar D25-D Cement Agitator 1 0 0

JCB Agitator CMPL 1 0 0

Caterpillar Elphinstone AD40 dump truck 1 1 0

Caterpillar Elphinstone R2900 Loader (LHD) 6 7 7

Coles 25 tonne Crane 1 0 0

Tadano 25 Tonne Crane 1 1 1

Forklifts 4 4 4

Isuzu FTS 750 Water Truck 0 1 2

Isuzu FTS 550 Explosives Truck 1 1 1

Isuzu FSS 550 Stores Truck 1 1 1

CMPL 2011 AEMR

20

CMPL Equipment 2010 2011 Projected

2012

Isuzu FSR 700 Stores Truck 1 1 1

Isuzu MPR300 0 1 1

Light Vehicles 56 56 56

Merlo Telehandler 1 1 1

Sandvick DD420 Jumbo 2 3 3

Tamrock Cabolter 1 1 1

Terex UC15 Franna Crane 1 1 1

Normet Spraymec 1 1 1

Normet Scamec 1 0 0

Normet Chamec 1 1 1

Normet Agitator 0 2 2

Contractor Equipment

Caterpillar R2900 Loader (Pybar) 0 1 2

Caterpillar AD45 Haul Truck 0 2 2

Solo Production Drill 1 1 1

Robbins 32R Raise Drill (Raisebore Australia) 1 1 1

Caterpillar IT28B Loader (Raisebore Australia) 1 1 1

Caterpillar 926 Front End Loader 1 0 0

Cement Agitator Surface 1 0 0

Hino Cement Agitator (EDMS) 0 0 0

Caterpillar Telehandler (EDMS) 0 0 0

Fibre Crete Maxi jet 0 1 1

Light Vehicles 25 30 35

Tamrock Cabolter 7-5 (Macmahons) 0 1 1

CMPL 2011 AEMR

21

2.4.6 Mining Method

The mining method used at CSA for the majority of stoping remains the same as in previous years, that is, top

down, continuous advance, long-hole open stoping. Most stopes are filled with CHF and the balance is filled

with development waste. Some bottom up long-hole open stoping was carried out in 2011 and this will continue

in the 2012 reporting period.

2.4.7 Mine Development

During the 2011 AEMR period, underground horizontal development advance totalled 3,510 m. The Mine

vertical section provided (Plan 4) details mine development over 2011 and the outlook for 2012. Section 3.2.3

provides further detail on the shaft extension development project.

Mining has focused on the K, O and S lenses of the QTS North system and from the QR1 lens in the QTS South

system during the past five years and will continue to do so for the 2012 AEMR period. Ore has been extracted

as required from other smaller QTS North lenses to supplement ore supply and to provide an optimal feed grade

to the mill, as allowed by mining sequences and ground stress management. A similar approach will be taken

over the 2012 mining period. In addition it is planned to mine crown pillars from the upper sections of the QTS

north ore bodies as required.

Stoping is almost complete above the 8850 level in the QTS North except for some crown recoveries. The QTS

South mining is complete above the 9190 level, with a new stoping block will be developed below 9045 in the

QTS South, the bottom of the ore body is currently estimated at 8985. During the 2012 reporting period mining

will continue below the 8890 level in the QTS North and below 9045 level in the QTS South.

2.4.8 Mine Production

Actual stope performance and metal output for 2011 was below the budgeted figures. This was mainly the result

of lower utilisation of equipment, issues with the stoping and unplanned delays. Variations in monthly grades,

against budgeted figures, reflect timing fluctuations of individual stopes. Table 11 shows the comparison of

monthly budget and actual production performance during 2011.

Mine production was sourced from a variety of stopes within the mine. The QTS North Ore System provided

80% of the ore produced, while the remaining 20% came from the QTS South Ore System.

CMPL 2011 AEMR

22

Table 11 CSA Budget versus Actual Mine Production 2011

2011 Budget Actual

Tonnes (dmt) % Cu Tonnes (dmt) % Cu

Jan 98,380 4.80% 91,540 3.76%

Feb 80,509 3.72% 70,184 4.62%

Mar 98,380 3.27% 75,650 3.37%

Apr 95,207 4.72% 95,328 5.25%

May 98,380 5.43% 80,304 2.97%

Jun 95,207 4.54% 87,046 5.00%

Jul 98,380 4.80% 93,932 4.70%

Aug 98,380 5.52% 93,507 4.77%

Sep 95,207 5.08% 72,190 3.75%

Oct 98,380 4.44% 73,964 4.01%

Nov 95,207 5.26% 102,228 4.79%

Dec 98,380 4.17% 99,127 4.44%

2011 Total 1,150,000 4.66% 1,035,000 4.33%

Note:

1. dmt = dry metric tonnes

2.5 Mineral Processing

2.5.1 Ore Characteristics

Minerals present in the CSA ores are mainly chalcopyrite, with lesser cubanite, pyrite and pyrrhotite and very

minor bornite, sphalerite and galena with traces of silver. Quartz, siltstone clasts, calcite, magnetite and chlorite

form the gangue to the sulphide minerals.

2.5.2 Metallurgy

The milling circuit consists of two primary semi-autogenous mills (SAG) in either open or closed circuit as

required, with hydrocyclones, and a third mill of same size that originally operated as a SAG mill but is now

used as a secondary ball mill. After grinding, ore slurry is pumped to the flotation circuit comprising of rougher,

scavenger, cleaner and re-cleaner stages that use mechanically agitated flotation cells. Two banks of Wemco

rougher cells and one bank of Outotec scavenger tank cells float the sulphides until generating a final tail that is

sent to the tailings thickener. Two banks of Denver cells and two banks of Dorr Oliver cells perform cleaning

and re-cleaning flotation of rougher concentrate. Recovery of Cu minerals, mainly chalcopyrite, is excellent

with typically 95% to 98% of the Cu and around 83% of the silver reporting to the concentrate. The concentrate

grade generally ranges between 26.5% and 29.0% Cu and 58% and 92% silver (Ag). Metal Recovery for 2011 is

shown in Table 12.

CMPL 2011 AEMR

23

Table 12 Metal Recovery 2011

2011 Tonnes

treated

Feed Metal Concentrate

Grade Recovery Production

dmt Cu (%) Ag (g/t) Cu (%) Ag (g/t) dmt Cu (%) Ag (g/t)

Jan 91,308 3.77 13.08 95.87 79.16 11,660 28.30 81.06

Feb 74,897 4.64 16.22 95.88 79.65 12,032 27.72 80.41

Mar 74,920 3.47 12.08 96.18 73.79 8,985 27.82 74.34

Apr 95,475 5.33 15.24 96.82 80.97 17,843 27.61 66.02

May 77,964 3.03 10.29 96.29 84.46 8,220 27.63 82.45

Jun 90,101 5.16 18.66 96.98 82.41 16,158 27.89 85.76

Jul 93,107 4.89 17.81 96.35 83.39 16,388 26.78 84.40

Aug 93,135 4.94 18.51 97.17 85.56 16,995 26.32 86.79

Sep 74,053 3.84 13.79 97.79 89.40 9,922 28.05 92.04

Oct 70,286 3.97 9.58 97.49 81.82 9,504 28.63 57.98

Nov 102,874 4.99 14.41 97.29 84.82 18,612 26.85 67.54

Dec 100,792 4.57 15.19 97.45 86.58 16,215 27.70 81.77

Total/Avg 1,038,913 4.38 14.57 96.80 82.67 162,533 27.61 78.38

(+/- SD) ( - ) 0.74 2.99 0.66 4.06 ( - ) 0.66 9.95

2012

Estimate 1,100,000 4.72 17.64 96.44 80.00 175,708 28.50 88.35

Note:

1. dmt = dry metric tonnes 2. %= percent

3. g/t= grams per tonne

Flotation concentrate is pumped to a conventional thickener where it is dewatered. Thickener underflow is

pumped to a Filter Feed Tank. This slurry is pumped to two Ceramic Vacuum Disc Filters where water is

removed. The filtered concentrate is discharged by conveyor to stockpiles located within either of two

concentrate storage sheds. The concentrate has a moisture content of approximately 9.5%. Reagent

consumption figures for ore processing in 2011 are provided in Table 13.

CMPL 2011 AEMR

24

Table 13 Reagent Consumption 2011

2011

Reagent Consumption (t)

Cement Grinding

Media Flocculent Lime Collector Frother

Nitric

Acid Delvocrete

Jan 335.77 69.20 0.15 -2.95 1.13 0.14 8.02 0.29

Feb 647.92 98.97 0.07 8.84 1.07 0.04 3.87 1.71

Mar 2,231.53 61.20 0.20 0.00 1.01 0.10 3.92 1.43

Apr 1,993.83 75.19 0.33 0.00 1.47 0.09 9.47 2.08

May 1,989.30 68.72 0.30 0.00 1.02 0.04 9.25 1.11

Jun 2,788.50 82.78 0.15 0.00 1.54 0.05 7.17 1.54

Jul 1,224.76 74.46 0.13 0.00 1.24 0.08 9.20 0.39

Aug 2,332.59 89.60 -0.20 0.00 1.77 0.07 5.17 1.24

Sep 1,229.75 73.87 0.23 0.00 1.10 0.07 5.03 0.62

Oct 1,659.38 64.44 0.25 0.00 0.98 0.30 3.72 0.52

Nov 1521.02 84.52 0.75 0.00 1.65 0.08 5.81 0.07

Dec 2289.68 72.58 0.25 0.00 1.43 0.06 7.04 2.17

Total 20,244.03 915.51 2.60 5.90 15.40 1.13 77.67 13.16

2012

Estimate 25,790 979.00 15.53 110.00 16.50 3.08 65.88 12.5

2.5.3 Concentrate Storage, Handling and Transport

Concentrate is loaded by a Front End Loader into purpose built, fully enclosed, steel containers on railway flat

cars (wagons). An automatic lid lifter assists with the container loading process. The trains currently in service

can carry approximately 2,313 wet metric tonnes (wmt) of concentrate. This is railed to ConPorts Pty Ltd’s

(previously CBH Resources Ltd) ship loader at Port Waratah, Newcastle, for storage and export shipment by

ocean freight. This concentrate is exported to overseas smelters in India, China and Malaysia.

CMPL 2011 AEMR

25

2.6 Waste Management

CMPL have long recognised the need for a reliable and regular waste removal and recycling service for the CSA

Mine that meets environmental, safety, operational, future growth and financial requirements. The CMPL Waste

Management System aims to achieve the following objectives:

Cost effective waste management and recycling system;

A holistic approach to waste minimisation and recycling;

Maximise recycling outcomes where possible to minimise waste to landfill;

Provide accurate invoicing and waste tracking receipts; and

Assist where possible to enable the provision of recycling for the town of Cobar.

2.6.1 General Waste

General waste at the CSA Mine is separated into co-mingled recyclables and non-recyclable / putrescibles waste.

Dubbo based company JR Richards & Sons Waste and Recycling Services (JRR) is contracted for the collection

of both waste streams from the CSA Mine. This service includes the supply and servicing of separate, colour-

coded general waste and co-mingled recycle bins.

All non-recyclable and putrescibles waste is taken to the Cobar landfill facility for disposal, while all co-mingled

recyclable waste is transported to the JRR Material Recovery Facility in Dubbo for processing and eventual sale.

This co-mingled service allows for all recycle materials to be collected together, including paper, cardboard,

PET/HDPE plastics, aluminium, glass and tin.

The average recycling rate for 2011 was 26%, fluctuating from 34% in July to a low of 17% in September. The

increase in average rate from 2010 (22%) to 2011 (26%) can be attributed to the increased number of recycling

receptacles available on site. The recycling capacity was doubled at most locations on site through the

introduction of larger 3 m3 bins. Through ongoing education and awareness campaigns 2011 has also seen a

significant rise in the use of recycling bins located in the car park provided by CSA for employees to bring their

recycling from home. These bins are consistently filing despite the capacity being doubled with the introduction

of another bin to cope with the increased demand. Thirty 60 L recycling bins were introduced in crib rooms,

offices and work areas during 2011. Figure 2 below shows the monthly general waste volumes and the

recyclable component as a percentage.

The aim over in the 2012 reporting period is to achieve a recycling rate consistently greater than 30% recycled.

Ongoing educational campaigns in 2012 will include National Recycling Week and Clean Up Australia Day.

CMPL 2011 AEMR

26

Figure 2 CSA Mine General Waste Management Performance 2011

2.6.2 Industrial Waste

Industrial waste at the CSA Mine is split into the main waste streams: metals, rubber, hydrocarbons, and

sewerage waste. Each of these waste streams is managed and tracked separately.

Metal waste includes steel and Cu cables, both of which are removed off site for recycling. A total of 132 t of

scrap steel was sold to external contractors during 2011 for recycling.

54 t of steel and rubber mill liners were removed off site by contract recyclers who separate the rubber from the

metal to ensure the recyclable components are maximised. Most of the CSA Mine’s rubber tyre recycling is

managed through a returns arrangement with the local tyre supplier. In addition to this arrangement, 328 rubber

tyres were sent off site to The Tyre Doctor (licensed contractor based in Leeton) for recycling in 2011.

Hydrocarbons are recycled where possible from surface (processing plant and workshops) and underground

(workshops). An EPA licensed contractor collects the waste oil on an as needs basis. During 2011 106,500 L of

waste oil was collected by Renewable Oil Services Pty Ltd (EPA Transport Licence No. 12991; EPA Depot

Licence No. 13092). Waste grease and other mixed oily products (rags, plastic liners, gloves, filters, filters etc.)

are collected by the same licensed contractor on an as need basis. A total of 34 drums (205 L each) and 12 IBC

pods (1000 L each) of waste grease and associated contaminated products were removed from site during 2011,

producing a total of 11,758kg of recyclable product. A further 2,640 kg of waste batteries were removed from

site for recycling over the 2011 period.

Underground sewage waste is removed from site by a licensed contractor and disposed of at a designated pit

provided at the CSC landfill. During 2011 approximately 222,000 L of sewage waste was removed by Every

CMPL 2011 AEMR

27

Day Mine Services (EDMS) and Cobar Mining Contractors. Due to regulation changes in 2011, sewage waste is

only required to be tracked if it is being transported interstate hence transportation to the CSC landfill does not

require a Transport Certificate or an EPL.

2.6.3 Underground Waste Rock

Waste rock produced by underground mining operations is disposed of into underground voids left by stoping

operations, or hoisted to the surface (only during periods of low void inventory). Cumulative mine waste

production is provided in Table 15 in Section 2.7.4. A total of 396,476 t of waste rock production is budgeted

underground for the 2012 period.

2.6.4 Tailings Waste

Backfill fines, or flotation tailings when backfill is not required, are sent to the Final Tailings Thickener for

dewatering prior to pumping to the TSF. Target moisture content of final tailings is Specific Gravity (SG) = 1.5.

Tailings are pumped approximately 2.2 km in a High Density Polyethylene (HDPE) pipeline to the TSF and

deposited from a central raised causeway. The TSF comprises the STSF of approximately 82 ha and the North

Tailings Storage Facility (NTSF) of 103 ha. The NTSF has not been used since CMPL took over the CSA

operation and is excised from CML5.

The amount of tailings deposited is regularly monitored; a monthly summary is provided in Table 9 of

Section 2.4. A total of 536,188 t of tailings was deposited between 1 January and 31 December 2011 at an

average production rate of just over 1,468 t per day. This accounted for 61.1% of flotation tailings. The

remaining 38.9% of the flotation tailings was backfilled into the underground workings.

Thickened tailings will continue to be deposited in the STSF over the 2012 AEMR period. Tailings will be

deposited in thin discrete layers, approximately 100 mm in thickness from the end of the discharge causeway.

Discharge is distributed between 13 spigots close to the end of the causeway to limit the discharge velocity of

tailings from the pipes. The distribution of flow via at least three spigots has resulted in the development of a

well defined beach.

Deposition of tailings will be alternated between the North West side and South East side of the causeway. This

approach is intended to maximise evaporative drying by sun and wind exposure of the non-active tailings beach

area. This structured deposition method will help reduce rate of rise of the tailings by allowing tailings on the

beach to dry and desiccate before it is subsequently covered with fresh wet tailings. This will achieve a high dry

density of the tailings, increase water recovery and optimise storage capacity.

CMPL 2011 AEMR

28

2.7 Ore and Product Stockpiles

2.7.1 Ore Stockpiles

Ore hoisted to surface is stored in any of four concrete, open topped storage bins. Total capacity is

approximately 6,000 wmt.

A scoping study is budgeted in 2012 which will aim to determine the options for introducing a surface ore

stockpile as part of the works associated with the Mill Grinding Circuit upgrade. This is required to occur in

conjunction with the shaft project. Further details and options will be presented to the relevant regulators for

approval towards quarter four 2012.

2.7.2 Product Stockpiles

Flotation concentrate is stored in either of two concentrate storage sheds, with combined storage capacity of

approximately 25,000 wmt. The sheds are covered and partially enclosed which assists in the minimisation of

dust generation. Each shed has a concrete floor and wall bunds which minimises losses to the environment.

Run-off from the sheds is contained and directed to a contaminated water collection dam (Borrow Pit Dam).

Approximately 6,425 dmt of Cu concentrate was stored in the concentrate storage sheds as at 31 December 2011.

A stockpile of approximately 15,992 dmt was stored at the port awaiting shipment.

2.7.3 Topsoil Stockpiles

A comprehensive review of all topsoil resources was conducted in 2011 with volumes updated based on

construction records (where available) and GIS software. Current stockpiles of topsoil at the CSA Mine total

approximately 63,329 m3. An estimated 5,500 m

3 of topsoil is stockpiled behind the NTSF from operations prior

to CMPL taking over in 1999. All remaining topsoil on site resulted from the development of the STSFE in

2006 (50,969 m3) and the extension to the TSF Decant Dam in 2010 (6,680 m

3).

Topsoil and subsoil was handled according to best practice procedures by separating topsoil and subsoil in two

separate stockpiles during the construction of the Decant Dam Extension in 2010. Topsoil from the STSFE

development is stockpiled along the TSF access road (18,714 m3) and at the site of the original interim stockpile

adjacent to Railway Dam (32,255 m3), while the new stockpile resulting from the Decant Dam extension is

stockpiled adjacent to the southern wall of the Decant Dam facility. These small stockpiles (based on a

maximum height of 3 m) are located close to the TSF to ensure potential losses due to excessive handling are

minimised. This topsoil will remain stockpiled until required for rehabilitation purposes on site. Where

available, green waste has been placed on topsoil stockpiles and stockpiles seeded to encourage organic matter

and the maintenance of a viable seed bank.

Table 14 displays CSA topsoil stockpile information and Figure 3 displays topsoil stockpile locations.

CMPL 2011 AEMR

29

Table 14 CSA Identified Topsoil Stockpiles

Figure 3 CSA Topsoil Stockpile Locations

Stockpil

e No. Stockpile Location

Volume

(m3)

Storage

Capacity

Remaining

(m3)

Source Date

Placed Treatment

1 TSF Access Road 18,474 18,823 Development of STSF Extension 2006 Green waste placed

2

Adjacent TSF

Decant Dams

(topsoil)

3,420 0 Extension of the TSF Decant Dam

required for STSF wall lift 2010

Oat cover crop seeding

(June 2011)

Adjacent TSF

Decant Dams (clay) 3,440 0

Extension of the TSF Decant Dam

required for STSF wall lift 2010

Oat cover crop seeding

(June 2011)

3 Adjacent Railway

Dam 32,255 3,577 Development of STSF Extension. 2006 n/a

4 NTSF 5,500 0 Unknown (placed prior to CMPL

taking over operations in 1999)

Prior to

1999 n/a

TOTAL 63,089 22,400

CMPL 2011 AEMR

30

No major excavation works are planned for 2012, therefore no significant volumes of topsoil are expected to be

generated. Any useful quantities of topsoil from any land disturbance activities will continue to be stripped and

stored with existing stockpiles to provide suitable material to facilitate future rehabilitation.

2.7.4 Waste rock Stockpiles

Nil underground waste rock was hoisted to the surface in 2011. The volume of waste rock hoisted to the surface

is a function of underground mine development progress. Development progress achieved led to a deficit in

available underground waste storage capacity. Prior to hoisting to surface any material is tested to ensure it is

not potentially acid generating.

A new Acid Rock Drainage (ARD) Management Plan (PLN-050) and Classification and Management of Waste

Rock Procedure (PRO-309) were developed during 2011 to ensure a consistent approach to waste rock

management continues in the future.

In addition to these temporary stockpiles created in 2011, a permanent waste rock stockpile remains on the

surface of the NTSF. This stockpile (totalling 87,000 m3) was established in 2007 under an agreement with

DTIRIS (Derelict Mines Program) as a source of future capping and rehabilitation material for the NTSF. The

permanent waste rock stockpile is located in the north-western corner of the NTSF. This location was deemed

appropriate due to its close proximity to the tailings facility, hence preventing double handling of the material in

the future. No waste rock was placed or removed from the NTSF stockpile during the 2011 AEMR period.

Table 15 summarises stockpile estimates and waste production at the CSA Mine for 2011 and the forecast for

2012.

Table 15 CSA Cumulative Waste and Stockpile Production

Cumulative Waste & Stockpile Production

Start of 2011

reporting period

End of 2011

reporting period

End of 2012 reporting

period (estimate)

Topsoil stripped (m3) 63,329 63,089 62,909

Topsoil used / spread (m3) 1,100 1,340 1,700

Waste Rock (t) (surface hoisted) 318,836 0 515,826

Ore (t) 8,243,654 9,278,654 10,378,654

Processing Waste (tailings) (t) 5,024,781 5,560,969 6,004,629

Backfill (t) 2,276,519 2,616,711 3,097,343

Cu Concentrate (t) 1,475,041 1,637,574 1,813,282

In comparison to the predicted waste and stockpile production figures estimated in the 2007 – 2012 MOP for the

2011 period, actual production volumes of ore, backfill and copper concentrate were higher than predicted in the

MOP due to better than forecast grades. These differences are expected to continue into 2012 as the production

rates remain similar, if not further increased for these areas of mining operations.

CMPL 2011 AEMR

31

2.8 Water Management

2.8.1 External Water Sources

The CSA Mine lies within the Darling River Basin with the nearest tributary being the Bogan River located

approximately 120 km to the east of the mine. CMPL purchase bulk raw water from the Cobar Water Board.

Cobar raw water comes from Burrendong Dam via the Macquarie River and the Albert Priest Channel, and is

supplemented by the ground catchment area around the Cobar storages during periods of rainfall. Water from

the Macquarie River is diverted at Warren via a 73 km open channel (Albert Priest Channel) to the Bogan River

Weir Pools in Nyngan. From here it is pumped via a dual underground 130 km long steel pipeline that can

deliver 200 l/s or 17.2 ML per day to the 1.4 ML storage tank at Fort Bourke and the Cobar reservoir

approximately 4 km north west of Cobar.

Water from the Cobar storages is pumped to the local mines via an underground pipeline. The mine water

allocation is part of a water entitlement which is shared between CMPL, Peak Gold Mine and CBH Resources

(Endeavor). The CSA Mine site is entitled to a raw water allocation of 1,356 ML per annum (determined by the

period of July – June each year) and processes raw water to produce potable water on site.

During periods of drought and low rainfall, the Cobar Township, and therefore CMPL, relies on this external

supply of raw water to maintain operations. Figure 4 shows the water storage level and rainfall for the

Burrendong Dam over 2011.

Figure 4 Burrendong Dam Water Storage Level (%) and Cumulative Rainfall (mm) 2011

CMPL 2011 AEMR

32

2.8.2 Surface Water Sources

In 2011 expert consultants were commissioned by CMPL to develop a Site Water Management Plan (SWMP).

The SWMP is currently in draft, finalisation is expected in quarter one 2012. The plan will be submitted to

DTIRIS and OEH on finalisation. The SWMP strategically manages water onsite in order to:

Avoid discharge of contaminated water;

Reduce reliance of water from external sources;

Reduce losses from evaporation and seepage;

Maximise water re-use on site by recycling where practicable;

Separate clean, contaminated and dirty water sources where practicable.

The SWMP outlines operational procedures to cover critical water management issues and events (e.g. forecast

high rainfall events and water storage dams are at capacity). These procedures ensure there are appropriate

responses to events with controls put in place to prevent breaches of EPL1864 including the discharge of

contaminated water. The procedures also outline measures to ensure there is maximum efficiency in water re-

use.

As part of the SWMP CSA Mine catchment boundaries were detailed and mapped using the Digital Elevation

Model (DEM). There are thirty five catchments within the mine lease boundaries for which rainfall runoff is

controlled and prevented from leaving site. These catchments are summarised in Table 16 and displayed in

Figure 5.

CMPL 2011 AEMR

33

Clean Catchment Contaminated Catchment

Existing Drainage Line

Water Catchment Dam

Figure 5 CSA Mine Catchment Boundaries 2011

Table 16 Summary of Catchment Areas

Catchment

Identification

Catchment Area

(m2)

Classification Direction of

Flow

Is Rainfall

utilised

C1 15,110 Clean Borrow Pit Dam Borrow Pit Dam

C2A 17,790 Clean C2B Yes

C2B 9,645 Contaminated C4 Yes

C3A 2,855 Clean C4 Yes

C3B 32,280 Clean C4 Yes

C4 15,040 Contaminated C4 Yes

C5A 37,935 Dirty C2B Yes

CMPL 2011 AEMR

34

C5B 9,645 Dirty C1 Yes

C6 33,830 Clean C2A Yes

C7A 8,025 Dirty C8B Yes

C7B 6,325 Dirty C8C Yes

C8A 9,145 Dirty C7A Yes

C8B 16,420 Dirty C8C Yes

C8C 14,550 Dirty C9B Yes

C9A 5,705 Dirty C8C Yes

C9B 15,195 Dirty Borrow Pit Dam Yes

C10 7,454 Dirty C9B Yes

C11 9,695 Dirty C10 Yes

C12A 14,815 Dirty C12B Yes

C12B 14,880 Dirty C11 Yes

C13 30,130 Dirty C9B Yes

C14A 10,940 Dirty C12B Yes

C14B 24,345 Dirty C13 Yes

C15 24,115 Clean - No

C16A 17,055 Clean C20B Yes

C16B 29,146 Clean C12B Yes

C17A 52,350 Dirty C17B, C17C No

C17B 13,520 Contaminated C17C No

C17C 82,205 Dirty - No

C18 116,155 Dirty - No

C19A 19,290 Clean - No

C19B 13,785 Clean - No

C19C 21,775 Clean - No

C20A 11,990 Dirty C8A Yes

C20B 9,920 Dirty C20C Yes

C20C 10,725 Dirty C12B Yes

Catchment areas classified as contaminated or dirty make up the bulk of the catchment areas (approximately 57

ha) and lie generally around the Ore Processing Mill and site infrastructure areas. These areas all currently drain

to the Operational Water Dam and Borrow Pit Dam. The catchment areas for the clean water runoff lie to the

south and west of the mill area and comprise approximately 2 ha. These catchments also currently drain to the

Borrow Pit Dam. Water from the Borrow Pit Dam is pumped directly into the Pork Pie Dam. This is the process

water dam which makes up the Pork Pie catchment (C16). The Borrow Pit Dam is the key storm water

catchment dam, while Pork Pie Dam and the Operational Water Dam are the key water storages.

In addition to the surface water catchment dams within CML5, the two old mine dams (sample locations S15 and

S16) located on the MPL’s to the north-west of the site were constructed as a water supply for mine operations

prior to the 1960’s. Both catchment areas are large and relatively undisturbed comprising open grass areas and

CMPL 2011 AEMR

35

scattered to dense scrub, hence both dams are used to monitor baseline water quality. These dams act as a

potential alternative water supply for the CSA Mine operations in the future. Water is able to be pumped to site

into the process water system if required.

A summary of all current water storages at the CSA Mine is shown in Table 17. Plan 2 shows the location of

these existing water catchment and storage dams.

CMPL 2011 AEMR

36

Table 17 CSA Mine Water Storage

Volumes Held (ML)

Stored Water Storage

Capacity

Start of 2011

Reporting Period

End of 2011

Reporting Period

Clean Water

Old Mine Dam (N) MPL1093 (S15)

Old Mine Dam (S) MPL 1094 (S16)

TSF Stormwater Collection Dam (S11)

Raw Water Storage Tank (S2)

240*

240*

5*

25

180*

180*

5*

25

180*

180*

0

25

Dirty Water

Railway Dam (S8)

Wash Bay Evaporation Pond

4.79

0.03*

0

0.03*

0

0.03*

Contaminated Water

Borrow Pit Dam (S4)

Retention Dam (S9)

Old Smelter Runoff Dam (S13)

North Runoff Dam (S10)

Old CSA Spoils Dam (S1) Excised Area

Pork Pie Dam (S14)

North TSF (Excised Area)

South TSF (S3)

STSF Extension

TSF Decant Dams (combined) (S5)

Operational Water Dam

17.57

2.99

2.04

1.34

4.66

25.9

1060*

17

5*

93

7*

15

0

0

0

3*

25

120*

0

0

30

n/a

0

0

0

0

0

15.9

0

0

0

0

3.5

Total 1751.32 583.03 404.43

Notes:

1. Values marked * are estimates based on rudimentary site measurements as up to date survey data and other relevant

information is not available

To improve the long term water management of the Borrow Pit Dam and to increase the site water storage

capacity, a new Operational Water Storage was constructed behind the tailings thickener in February 2011. The

combined capacity of the new Operational Water Storage Dam and the Borrow Pit Dam was designed to enable

the capture of the contents of an emergency release from the tailings thickener and critical runoff resulting from

a 20 year and 100 year storm event (this is the standard required criterion as per the Soil Construction Manual

(Blue Book) as directed by OEH). Additionally, a new concrete bund was installed at the inlet to the Operational

Water Dam in 2011 to provide additional storage capacity which will allow greater settling times for recycled

water, and most importantly, allow machinery access for the regular clean up of operational silt build up while

the system is still on line. Operational inadequacies were identified in the design of bund throughout 2011 and

subsequently the bund will be upgraded. Works are expected in early 2012 to address problems with the initial

design including the steep angle preventing machine access and the deepening of the bund to allow additional

settling time. Water from the new Operational Water Storage Dam feeds directly via pipes to the Mill Raw

CMPL 2011 AEMR

37

Water Tank and Pork Pie Dam. An overflow spillway feeds into an existing drainage channel and diverts into

the Borrow Pit Dam. By implementing these changes, the storage capacity for runoff and recycled water on site

has increased by approximately 9,000 m3.

The STSF catchments, despite the huge surface areas, do not store any water on site. All water from the STSF

catchment reports to the STSF Decant Dams to be pumped back to Pork Pie Dam for use as process water. A

new discharge drain was built in the STSF in March 2010, designed to allow for gravity release of supernatant

water and stormwater from the toe of the tailings mound into the lined compartment of the Decant Dam. Due to

operational issues with low density material and flushing of blocked lines, excess tailings have flowed into this

drain and subsequently into the lined decant dam. The construction of the additional compartment of the Decant

Dam in 2010 means there is still adequate capacity to provide environmental flood containment under the DSC

(DSC) guidelines (i.e. rainfall runoff resulting from a 1 in 10 year 72 hour design storm event). There are

currently plans in place to clean out in the discharge drain and add additional filter berm to prevent tailings

material entering the decant dam.

2.8.3 Surface Water Drainage

Improvement of the surface water drainage system at the CSA Mine continued in 2011. Works were completed

at eleven key locations where erosion was evident including: rock armouring of drains carrying high velocity

water; placement of energy dissipaters; and, cleaning out of culverts. A report of the work completed during the

2011 drainage improvement program can be found in Appendix C. Works including the installation of 12

culverts were completed to address the erosion of the North Eastern corner of the Borrow Pit, an issue raised at

the 2010 AEMR inspection).

CMPL 2011 AEMR

38

Examples of Before (May 2011) and After (June 2011) drainage improvement works.

The construction of the new Operational Water Storage Dam behind the tailings thickener in 2011 has also

improved site water drainage. The main drainage channels transporting contaminated runoff from the

concentrator area and other surface disturbance areas now report directly to the Operational Water Storage Dam,

where previously they reported directly to the Borrow Pit Dam. This ensures that run off from the main

contaminated catchments will be separated and contained in the new dam and the majority of water feeding the

Borrow Pit Dam will be clean runoff. In the event of an extreme rainfall event or a major failure of the

thickener, the new Operational Water Storage Dams will overflow into an existing drain and feed into the

Borrow Pit Dam.

New Operational Water Storage Dam with Rock Armoured Inlet Drain

2.8.4 Groundwater Sources

Exploration for near mine groundwater sources at CSA began in June 2007 following raw water allocation

reductions due to serious drought. The exploration program primarily focussed on the area to the east of the TSF

in the interpreted area of the Chesney Fault. The aim of the program was to secure a groundwater supply

through either existing boreholes, or by discovering new productive water extraction points. The investigation

led to the discovery of a potential aquifer at a depth of 79 m.

CMPL 2011 AEMR

39

Two water bore test holes and eighteen test pilot holes were drilled in the study area in 2007 and 2010

respectively. The test pilot holes did not show any indication of sufficient groundwater to justify drilling of

further water bore holes.

In 2010, a series of pump tests were conducted on each test bore in order to evaluate the risk of leakage from the

TSF, as well as establish the long term sustainable pumping rates and whether the aquifer could be developed for

water supply. Results indicated pumping from these bores is not likely to induce leakage from the TSF.

Recommendations were made including the drilling of additional production holes for test purposes in areas

where the Great Chesney fault or Cobar fault intersects lineaments. Investigations of rainfall recharge to

groundwater, mathematical models and long term groundwater monitoring may be undertaken to evaluate the

long term pumping effects and the reliability of long term water resource yield projections.

During 2011, a study was completed to provide a structural and hydrogeological evaluation of the Great Chesney

fault2. The aim of the study was to determine the aquifer properties and characteristics where the Great Chesney

Fault is the main structural control of groundwater storage, recharge and flow. The study also assists in the

identification for areas of further hydrogeological interest. Results indicate that the Great Chesney Fault no

longer forms a lithological boundary in the north, adjacent to the CSA Mine, as it is south of Cobar, and:

Exists as a broad fault zone, primarily made of two types of fractured rock: permeable fractures that act

as fluid pathways, and impermeable fractures due to silicification;

The direction of groundwater flow is completely constrained by the direction of fractures; in directions

not parallel to the fault, there is close to zero permeability;

The fault zone consists of small, discrete aquifers which, despite being laterally close to one another,

are sub-parallel and are not hydraulically connected.

The study identified the need for further work to confirm the fracture geometry in the region, while a better

understanding of the response of local aquifers to pumping would serve to identify additional sources of water in

the basin.

Further investigations into the suitability of an alternate water resource will continued as opportunities arise.

Currently there are no plans to progress this research in 2012.

2.8.5 Site Water Balance

A total of 758 ML of raw water was consumed at the CSA mine in 2011. This represents a reduction in

consumption of 15% from 2010 (895 ML) and 25% from 2009 (1,011 ML). The reduction from 2010 to 2011

was achieved with corresponding production rates (t milled) only decreasing by 2.7% bringing the rate of raw

water consumed per t of production down from 838 kl/t milled 2010 to 730 kl/t milled in 2011. The efficiency

gain in 2011 reflects the overall long term trend displayed Figure 6.

2 Doos, Stephanie (Oct 2011) A Geophysical and Hydrogeological Approach to Delineating the Great Chesney Fault, Cobar, NSW The

Australian National University

CMPL 2011 AEMR

40

Figure 6 Long Term Raw Water Used per Tonne Milled

The total site usage of water (which includes both raw water and recycled water usage) during the reporting

period increased by 13% from 2010 (1,390 ML) to 2011 (1,568 ML). Therefore the reduction in raw water

consumed can be attributed to a significant increase in the volume of recycled water used at the CSA Mine in

2011 with 52% of all water used on site coming from a recycled source. This represents an increase from the

previous reporting period where 35%3 of water was from a recycled source. There has been an improvement in

underground dewatering recovery and increased utilisation of pork pie return water which can be attributed to

increased storage capacity through the construction of the Operational Water Dams, installation of new pumps

and improved operational practices returning water to the process water dam for re-use.

Due to the likelihood of changes to assumptions contained in the water balance and possible metering issues

CMPL has engaged expert consultants to review the site water balance as part of works underway to develop the

SWMP. This review is expected to be completed in February 2012.

Table 18 summarises site water usage at the CSA Mine for 2011 and Figure 7 shows the 2011 Site Water

Balance.

3 Recycled water figures reported in the 2010 AEMR were incorrect due incorrect assumptions in the water balance. Recycled water was

reported at 155% when it should have been 32%.

CMPL 2011 AEMR

41

Table 18 CSA 2011 Water Balance

Water Recycling

Total Site Input 758,127 kL

Total Site Usage 1,568,163 kL

Total Recycle 207%

Water Losses

Mine Ventilation Losses 20,456 kL 3%

Water Retained in Backfill 88,241 kL 12%

Water Retained in Tailings 224,170 kL 32%

Tailings Dam Evaporation Losses 360,428 kL 5%

Water in Concentrate 17,055 kL 2%

Total 710,350 kL 100%

Water Recovery

Underground Dewatering 88%

Tailings Dam Dewatering 101.5% *

Note:

1. Includes rainfall runoff collected and reclaimed from TSF

42

Figure 7 CSA Mine Water Balance 2011

43

CMPL aims to continue minimising the reliance on external raw water supplies to ensure the operation can

remain sustainable into the future, and to ensure we are prepared for future onset of drought conditions and

potential allocation restrictions that have been experienced in the past.

2.8.6 Additional Water Saving Initiatives

CMPL commissioned specialist water treatment consultants and distributors Pro-Active Water Solutions in 2011

to investigate the treatment and reuse of alternate sources of water available at CSA to potentially reduce

dependence on the external water supply and increase water use efficiency. Alternative sources include ground

water, sewerage water, process water and mine water.

An innovative water treatment technology was trialled at CSA using the process of Electrolytic Activation of

effluent which produces powerful biocides (hydrogen peroxide and ozone) treating the water without the need

for chemical inputs. Initial results from the trial were promising, with effluents treated to a standard acceptable

for re-use underground and in the ore processing circuit.

CMPL Mining Engineers in conjunction with Pro-Active Water Solutions developed a design for a potential

underground recycling system to prevent the need to pump underground effluent to the surface. A

comprehensive Net Present Value (NPV) analysis on the system was completed which found the system would

not provide a financial benefit to CMPL. The issue of an underground recycling system will be further

investigated when other water treatment technologies and alternate designs become available.

Arctic Green Water Treatment Unit Pre and Post Treatment of CSA Ground Water

2.9 Hazardous Materials

Current WorkCover licensing requirements for Hazardous materials and Dangerous Goods management in NSW

requires CMPL to annually submit a Notification of Dangerous Goods on Premises form to notify WorkCover of

Hazardous and Dangerous Goods stored on the premises. CMPL submitted the notification form in September

2011 following an annual update of the CSA Mine Dangerous Goods Register and Site Manifest.

The minimum requirements for storage of Hazardous and Dangerous Goods at the CSA Mine site are:

Bunding to contain at least 110% of the largest container;

CMPL 2011 AEMR

44

The display of signs for each hazardous product stored within the facility illustrating the substance

name, dangerous goods class, packaging group and emergency response details;

The display of labels on all individual containers (product name, UN number, dangerous goods class

and packaging group);

Material Safety Data Sheets (MSDS) to be available within immediate storage area;

Effective measures to exclude rain and surface stormwater runoff from the storage area;

Spill containment kits and/or fire extinguisher within the vicinity of storage areas appropriate to the

volume of hazardous material stored; and,

Easy access for emergency response and spill clean-up kits.

Hydrocarbons are stored in underground workshops and fuelling facilities and in surface workshops, bulk diesel

self bunded tanks, and designated waste hydrocarbon collection areas. These areas and all other major

Hazardous and Dangerous Goods storage locations are detailed in Table 19.

CMPL 2011 AEMR

45

Table 19 CSA Bulk Hazardous and Dangerous Goods Storage (as of 31/12/11)

Location Dangerous Goods Tank

Product Name Class Un No. PG Tank Capacity

Refrigeration Plant Ammonia Anhydrous 1005 2.3 (8) I a/g 2,450 kg

Flam Gd Shed Interfroth 4500 1993 3 II a/g 1,000 L

Dyno Nobel Yard Titan 7000 Emulsion Matrix 3375 5.1 II a/g 2,400 L

Dyno Nobel Yard Acetic Acid N17 2790 8 III a/g 1,000L

Frother Station Interfroth 4500 1993 3 II a/g 1,000 L

Nitric Acid Tank Nitric Acid 60% 2031 8 II a/g 18,500 L

Backfill Plant Delvocrete Stabiliser 1760 8 II a/g 1,000 L

Stores Yard Delvocrete Stabiliser 1760 8 II a/g 3,000 L

Stores Yard Oxalic Acid 3261 8 III a/g 1000 kg

Stores Yard Oxygen, Compressed 1072 2.2 III a/g 1,800 L

Bulk Storage Tanks Diesel Fuel N/A C1 N/A a/g 180,000L

Brace Transfer Tanks Diesel Fuel N/A C1 N/A a/g 5000 L

L 8960 UG Tank Diesel Fuel N/A C1 N/A u/g 2,500 L

L 10 UG Tank Diesel Fuel N/A C1 N/A u/g 10,000 L

L9 UG tank Diesel Fuel N/A C1 N/A u/g 10,000 L

L 10 UG Roofed Store Mineral Oil N/A C2 N/A u/g 3,000 L

L9 UG Roofed Store Mineral Oil N/A C2 N/A u/g 15,000 L

L 11 UG Roofed Store Mineral Oil N/A C2 N/A u/g 13,000 L

L11 UG Magazine Explosive, blasting, type B 0331 1.5D II u/g 22,000 kg

L11 UG Magazine Explosive, blasting, type B 0082 1.1D II u/g 5,200 kg

L11 UG Magazine Explosive, blasting, type E 0241 1.1D II u/g 7,500 kg

Stores Yard Mineral Oil N/A C2 N/A a/g 25,000 L

Note:

u/g = underground

a/g = above ground or surface

2.9.1 Hazardous and Dangerous Goods Audit

A Hazardous and Dangerous Goods Audit was conducted at the CSA Mine in September 2011 to ensure the

CMPL Dangerous Goods Register is up to date and all handling and storage of Hazardous and Dangerous Goods

remains compliant with legislative requirements. No major storage issues were identified during the audit with

all areas meeting compliance requirements. Issues highlighted in the audit included the need to update MSDS

information on the internal chemical register (ChemAlert), prompt removal and disposal of empty or redundant

containers, replacing out-of-date MSDS documents, and general housekeeping of signage and MSDS documents

to ensure they are visible and accessible. The site Dangerous Goods Audit Report was distributed to each

department with all audit actions successfully addressed by the end of 2011.

CMPL 2011 AEMR

46

2.9.2 Radiation

CMPL is licensed to sell/possess radiation apparatus and radioactive substances or items containing radioactive

substances. See Table 4 in Section 2.1 for licence details. A small amount of radioactive material is held on site

in “in-stream-analysis” probes and density level gauges. These are stored according to the recommended

procedures and locked away from general access. All qualified electrical personnel at CMPL are trained and

certified in Industrial Radiation Safety which allows the electrical team to work with radiation devices on site in

relation to safety and maintenance. A total of 23 redundant gauges were removed from site by licensed

contractor SN Technologies Pty Ltd in April 2011. Consent was granted by the Department of Environment,

Climate Change and Water (DECCW) at the time under clause 23 of the Radiation Control Regulation 2003 to

dispose of the radioactive substances.

The CSA Mine also participated in the state-wide Naturally Occurring Radioactive Materials (NORMs) test

program in May 2011, which was run by the Inspector of Mines (Mine Safety Operations) from the NSW

Department of Trade & Investment.

The program was developed to fulfil a gap in data from the NSW mining industry, due to no requirements to

address the matter of NORMs in the past as there was an exemption in some legislation. As part of the Council

of Australian Governments (COAG) agreement between Australian States, and significant work to standardise

many Occupational Health and Safety (OHS) matters across the country (e.g. National Mine Safety Framework),

NSW now needs to get up to speed on this matter.

One of the consequences of this is that all NSW mines, quarries or coal mines will need to do radiation testing,

which may lead to the requirement to develop Radiation Management Plans. As there are thousands of such

sites, this would clearly require a lot of work and expense of getting radiation expert reports and so on. In the

vast majority of cases, the reports are likely to come back with the findings that radiation doses are below any

trigger thresholds requiring significant action by the mines.

The Chief Inspector of Mines has therefore recognised that it would save the industry a lot of expense if the

Department completed a sample test program. The aim would then be to hopefully exempt mines or sectors of

the industry, based on the results of the test program.

The Commonwealth agency ARPANSA (Australian Radiation Protection and Nuclear Safety Authority) carried

out the sampling of the NSW mining industry throughout 2011. Field work for the Cobar area was carried out in

May 2011, with a one day site visit to the CSA Mine on 3 May 2011. Liquid and solid samples were collected

from mill feed, copper concentrate, tailings, process water, mine de-watering, and underground the exhaust

ventilation air sample.

The Department did some sampling at CSA Mine in 1995. Apparently the sampling was done on 6 Level and 9

Level West at that time. The same ARPANSA laboratory did the previous work. The results from this project

CMPL 2011 AEMR

47

are therefore being sourced to allow for comparison. ARPANSA intends to publish the work as a scientific

paper, using generic data which does not identify mines or companies.

2.9.3 Polychlorinated biphenyls (PCBs)

The last of the transformers testing positive for the presence of PCB levels above the allowable limit (as per tests

conducted in 2009) were removed from site during 2011. This work was completed by a licensed contractor,

with all oil removed from the units prior to relocating from the mine site. A further six alternator transformers

were also removed from site in September 2011 which were previously located at the surface Powerhouse. All

high voltage electricity transformers will continue to be PCB tested as part of routine oil testing process.

2.9.4 Asbestos

Due to the age of numerous structures on the CSA Mine site there are some materials containing asbestos

present. CMPL therefore has an obligation to ensure that such Asbestos Containing Materials (ACM) is

managed in accordance with legislative requirements to prevent health and environment related risks.

All ACM present at the CSA Mine is in a bonded form and includes concrete and fibro walls on the surface

industrial buildings, the majority of building roofs, and the majority of concrete pipes on site. ACM in a bonded

form does not present an immediate health risk, if it remains undisturbed and in good condition

The CSA Mine Asbestos Management Plan is maintained to assist CMPL workers to comply with asbestos

prohibitions and prevent exposure to airborne asbestos fibres. While the ultimate goal is for all work areas to be

free of ACM, it is generally impracticable, especially with the limited life of mine timeframe. Due consideration

is given to the removal of ACM during any refurbishment or maintenance where practicable, in preference to

other control measures such as enclosure, encapsulation or sealing.

CMPL conducts an inspection of each building and structure on surface at the CSA mine on an annual basis.

The CSA Mine Asbestos Register is maintained with regular updates of the results from these inspections. The

register contains details of the location, type and condition of any asbestos products found on site. Where no

asbestos is found, a record of such a finding is also kept. The Asbestos Register is available on the CMPL

intranet, and is made available for inspection by employees, contractors, maintenance personnel and government

representatives. All asbestos material and air samples are analysed by a National Association of Testing

Authorities (NATA) accredited laboratory with all results included in the appendix of the register.

The most recent Annual Asbestos Site Audit and Air Monitoring were carried out in all surface buildings that

contain asbestos material during September and October 2011. Results showed that all samples remain well

below exposure limits and indicate CSA workplaces remain safe from asbestos exposure. The annual

monitoring results were used to update the Site Asbestos Register in November 2011.

The long term outlook for bonded asbestos products on site is to monitor, maintain and replace as required.

There are no plans to replace any buildings at this stage. Any building modifications or repairs will see the

CMPL 2011 AEMR

48

removal of any associated asbestos material and replaced with new materials. This approach has seen a

progressive reduction of asbestos material on site since the program began in 2006.

2.10 Other Infrastructure Management

Additional activities undertaken by CMPL during the reporting period that did not require any changes to the

MOP include:

Backfill Plant Bunding Upgrade:

Ongoing backfill spill incidents during 2009, 2010 and early 2011 clearly identified the inadequacy of the

backfill bunds capacity to contain spillages generated at the backfill plant. Occasional releases of backfill

to the outside environment surrounding plant occurred causing an environmental hazard.

In 2010 a complete review of the current backfill system and bund infrastructure was undertaken. At the

backfill plant the bund volume was found to be 34 m3 and the mixing transfer tank, identified as the major

item holding slurry, had a capacity of 50 m3. Therefore the bunds capacity could only capture 68% of the

mixing tank material (when full) in the event of a spill. As such the bund was not compliant with AS4681

(The storage & handling of Class 9 miscellaneous dangerous goods and articles) which stipulates the bund

must have 110% capacity of the tank.

To rectify this issue a 22 m3 sump was installed and the bund was upgraded in November 2011 to increase

the overall capacity to 56 m3 or 112% of the mixing tank. A diagram of works completed is provided in

Figure 8. The backfill plant is now compliant and the likelihood of uncontrolled spills at the backfill plant

is now greatly reduced.

Spillages at the backfill plant have reduced dramatically from 7 reported in 2010 to 1 reported in 2011.

CMPL 2011 AEMR

49

Figure 8 Backfill Sump Upgrade Design and Completed backfill Sump November 2011

In 2011 CMPL also reviewed automation options for the backfill plant and the potential installation of level

sensors to signal when the bund reaches 75% capacity so tailings feed flow could be redirected. Following

review it was decided not to proceed with the automation upgrades given the likelihood of replacing the

current backfill plant with a paste fill plant in quarter one 2013. Planning and design of the proposed paste

fill plant will progress throughout 2012.

CMPL 2011 AEMR

50

Nitric Acid Bund Resealing

In 2011 it was identified that corrosion of the concrete bund housing the nitric acid tank had occurred due

to spills of nitric acid occurring over a number of years. In 2011 CMPL engaged specialist contractors to

supply and install a sealing system that would ensure the integrity of the bund for the life of the mine.

Works were completed in December 2011 and included the installation of an acid resistant fibre glass

coating followed by a sealing product.

Before and After Resealing the Nitric Acid Bund

Dust Collection System for the Backfill Circuit:

The issue of build up of dust around the backfill plant has been another unresolved issue for the past two

reporting periods. The visible spread of dust outside of the bunded area has decreased around the plant over

2011. This is attributable only to the reduced backfill production over the past 12 months.

The dust collection system that was proposed and budgeted for installation in 2011 did not go ahead. Following

review of the cost and benefits compared to the timeframe before the replacement of the current backfill plant

with a paste fill plant in quarter one 2013, this project has not been rescheduled for 2012. Temporary exhaust

fans are being installed in early 2012 to provide a short term solution while the plant is still in use.

Dust Collection System for the Lime System:

It was highlighted during 2010 that the current bag filter system on the floatation ground floor of the Ore

Processing Mill is not capable of fully containing the generated lime dust. The current system was hard to

maintain as it required direct exposure to the lime which is a hazardous material. The inadequacy of the system

caused high dust levels around the flotation area, offices and mill facilities which was causing corrosion of the

supporting steel work. The use of lime has been decommissioned from the floatation system since mid-2011,

therefore the proposed new lime dust collection system that was to be installed to address the dust issue was no

longer required. The lime pumps were instead disconnected; with any future lime requirements likely to be in

very limited amounts which would be via manual additional if the circuit requires it.

This small process change has seen an improvement to the health and safety for operators in this area, a

reduction in the build up of material causing corrosion and the elimination of excess dust emissions at the

flotation ground and surroundings.

CMPL 2011 AEMR

51

3 ENVIRONMENTAL MANAGEMENT AND PERFORMANCE

Ongoing improvements to the CSA Mine Environmental Management System (EMS) continued over the 2011

period, including an update of the CMPL Environmental and Community Policy which is included as Appendix

D.

3.1 Air Pollution

3.1.1 Meteorological Monitoring

The semi-arid climate of Cobar has a median annual rainfall of 390 mm4. Two rainfall monitoring gauges are

located at the CSA Mine site, one west of the administration building and the other at the TSF. Total rainfall on

site for 2011 (measured at the administration building rain gauge) was 369.2 mm representing a return to average

rainfall after 720.5 mm was recorded in 2010. Figure 9 provides an overview of 2011 monthly average rainfall

and temperatures at the CSA Mine.

Figure 9 2011 Cobar Mean temperatures and CSA Mine Rainfall

4 Measured at the Cobar Meteorological station (site reference no. 048027

CMPL 2011 AEMR

52

3.1.2 Dust Emissions

Operations at the CSA Mine potentially contribute to air pollution through dust emissions generated from the

operation of equipment and other emissions generated from the usage of fuel and explosives.

The principal dust-generating activities associated with the CSA operation include:

Long term drought conditions resulting in minimal groundcover on the lease and surrounding district;

Operation of mobile machinery on unsealed roads and tracks;

Topsoil stripping and spreading;

Exposed stockpiles of waste rock, topsoil and/or additional materials;

Surface exploration drilling operations; and

Underground mine ventilation exhaust.

CMPL is committed to ensuring dust generation is minimised from all operations on site. Water sprays and

water trucks are utilised in the underground mine to supress dust in work areas and hence minimise dust emitted

to the air through the ventilation fans. The exception is after a blast when the ventilation system is designed to

clear the dust from the workings as quickly as possible to mitigate health risks to employees. The amount of

dust reaching the surface vents under these circumstances is limited and for short periods only.

All roads and tracks on the CSA Mine have a restricted speed limit imposed to reduce the amount of dust

generated by traffic. When unsealed roads are being used intensively, the roads are sprayed with a water cart to

suppress dust. Recycled water is used for dust suppression sourced from the Process Water Dam; its suitability

for use is determined using monthly water quality results.

Continuous improvements to minimise dust pollution are investigated and implemented at the CSA where

possible and monthly monitoring is undertaken to assist. A total of ten dust gauges are monitored on the mine

site. The locations of the CSA Mine dust monitors are listed below and also shown in Plan 2:

D1: north-east corner of the STSF;

D2: northern boundary of the NTSF;

D3: 100m north-east of concentrate storage and train loading station;

D4: west of the administration building (undisturbed control site);

D5: beside TSF access road before the booster hopper;

D6: southern corner of STSF Extension;

D7: opposite Railway Dam alongside the TSF access road;

D8: north-west corner of the NTSF (adjacent to the waste rock stockpile site);

D9: Decline access road; and

D10: North of the Backfill Plant.

Samples are collected monthly and are analysed by an external NATA accredited laboratory for determination of

dust composition and metals content. The results of dust deposition from the ten sample sites are summarised in

Figure 10.

CMPL 2011 AEMR

53

Figure 10 CSA Depositional Dust Monitoring Results 2011

The EPA recommended limit for dust deposition of 4 g/m2/month was not been exceeded in 2011. There have

been two small spikes in dust deposition at D4 during January and April in 2011 (greater than 2g/m2/month).

This site is located west of the administration building on a control site not affected by mining activity or traffic.

This therefore reflects natural environmental conditions, with wind gusts experienced upwards of 65 km/h during

January and April, and dry weather towards the end of January and throughout April.

There was also a small spike (well below the 4g/m2/month limit) in dust deposition in D1 during February. This

dust monitor is located on the north east corner of the STSF and can be attributed to ongoing construction

activities and completion of the STSF wall lift in addition to progressive rehabilitation of the STSF walls.

Raw air quality monitoring data, including historical data, is tabulated in Appendix E.

3.1.3 Tailings Dust Emissions

In 2010 observations suggested windblown dust from the TSF surface was being deposited outside the footprint

of the TSF as a result of prevailing winds and limited perimeter bunding. Investigations were completed in 2010

to map the extent of windblown dust and sample topsoil and subsoil from areas surrounding the TSF to

determine potential contamination.

CMPL 2011 AEMR

54

Following the findings of this investigation a TSF wind erosion trial was commissioned by CMPL in December

2010. Monitoring of this trial was undertaken throughout 2011 to assess the effectiveness of potential mitigation

strategies to limit the extent of windblown dust.

The trial involved the placement of oversize waste rock on the north east corner of the STSF and the installation

of four fences behind areas of waste rock emplacement and areas with no waste rock emplacement, on the

eastern and northern wall of the STSF, to capture dust generated from the tailings surface. Black conveyor belt

material was placed at the toe of each fence to assist in the identification of dust deposition.

The objective of waste rock emplacement is to reduce the near surface velocity of the wind so it does not have

the energy to lift any but the finest particles by increasing the roughness of the surface rather than creating a

cover. It was anticipated that dust deposition on fences located behind areas of waste rock emplacement would

be reduced compared to fences located behind areas with no waste rock.

Monitoring results from the trial indicated no significant reduction of windblown dust due the emplacement of

waste rock. Fences located on the eastern wall of the STSF have received additional dust deposition compared

with fences located the northern wall, indicating the direction of prevailing winds as the dominant factor for dust

deposition.

As the current waste rock emplacement has not proved effective in mitigating dust generation from the TSF,

additional mitigation measures will be investigated in 2012 including:

Increasing the size, thickness and extent of waste rock emplacement on the STSF;

Investigating potential chemical treatments to minimise dust.

Dust deposition gauges surrounding the CSA Mine STSF and NTSF (D6, D8, D9 and D10) have not indicated

any compliance issues as discussed in Section 3.1.2. The EPA guidance criterion for depositional dust of

4 g/m2/month was not breached at any stage during the 2011 reporting period.

3.1.4 National Pollution Inventory

The CSA mining operation generates emissions to air through the use of machinery (diesel emissions) and other

various chemical substances. These emissions are quantified on an annual basis via the National Pollutant

Inventory (NPI). The NPI is the national public database designed to provide the community, industry and

government with information on the types and amounts of substances being emitted to the environment. The

NPI is managed by the Australian Government Department of Sustainability, Environment, Water, Population

and Communities (DSEWPC). The CSA Mine NPI report was submitted in September 2011 and will be on

public display on the DSEWPC website5 31 March 2012.

5 http://www.npi.gov.au/

CMPL 2011 AEMR

55

During the 2010 - 2011 reporting period (July 1 2010 – June 30 2011) 28 substances were triggered by activities

at the CSA Mine. These substances have been predominantly triggered due to fuel and energy use, explosives

and onsite tailings transfers. Table 20 compares key emission sources by activity levels on site, for the 2009 –

2010 and 2010 -2011 reporting periods.

Table 20 shows all emissions for the NPI sources reduced in the last reporting period, with the exception of dust

generated from combustion and wheel dust associated with vehicle travel on unsealed roads. An increase in the

number of workers on site and therefore the number of vehicles travelling on site (particularly contractors) has

seen the use of vehicles travelling on site increase significantly. This level of activity is expected to continue

until the end of 2013 when the shaft project is completed and the number of workers on site again decreases to

the normal workforce average.

Table 20 Comparison of NPI Emission Sources by Activity Levels for 2009-10 and 2010-11

Emission Source 2009 – 2010 2010 - 2011 % Change Emission Type

Diesel fuel combustion (L) 3,552,687 3,387,699 -4.64% Combustion

Concentrate exported (t) 204,404 151,564 -25.85% Dust

Ore handled - dry (t) 1,093,843 1,028,493 -5.97% Dust

Waste handled (t) 265,980 203,463 -23.50% Dust

Vehicle travel on unsealed

roads (km) 35,042 82,173 134.50%

Combustion & wheel

dust

Exposed Areas (Ha) 103.93 104 0.07% Wind Erosion

Explosives (t) 998.23 856 -14.20% Mainly CO & NOx

3.1.5 National Greenhouse and Energy Reporting

The National Greenhouse and Energy Reporting Act 2007 (NGER) is a single national framework for energy use

and greenhouse gas emissions. It sets a mandatory system for companies to assess their energy use and

greenhouse gas emissions and report them if they exceed set thresholds. The Act is administered by the

Australian Department of Climate Change and Energy Efficiency.

The CSA Mine has total emissions that exceed the threshold for a single site; hence it is mandatory to submit

energy consumption and greenhouse gas emissions data annually. CSA data was submitted in September 2011

for the 2010 – 2011 reporting period (1 July 2010 to 30 June 2011). Energy consumption decreased by 5% from

the 2009-2010 period (469,354 GJ) to the 2010-2011 period (444,900 GJ). This resulted in the CSA Mine

improving its energy efficiency using less energy (GJ) per unit of production (t ore milled) in 2010-11 (0.42

CMPL 2011 AEMR

56

GJ/t) than in 2009-10 (0.50 GJ/t). A summary of the data submitted is included in Table 21. Total energy

consumption and total greenhouse gas emissions for the 2010 – 2011 reporting period are shown in Figure 11

and Figure 12.

Table 21 Summary of CMPL Energy Consumption and Greenhouse Gas Emissions

CMPL NGER

2010 -2011 Energy Carbon Emissions

Units GJ t CO2-e

Electricity 304,093 75,179

Diesel 130,765 9,088

LPG 35 2

Waste Oil / Grease 10,007 693

Refrigerant HFC-134A 944

Total 444,901 84,962

Figure 11 CSA Mine Total Energy Consumption (GJ) 2010 – 2011

Figure 12 CSA Mine Total Greenhouse Gas Emissions (t CO2-e) 2010 - 2011

CMPL 2011 AEMR

57

Electricity, predominantly used in crushing and grinding, is the dominant energy use and source of emissions at

the CSA Mine. CMPL is committed to undertaking investigations into energy use with the intent of identifying

opportunities to improve efficiency and reduce the overall carbon footprint of the mine.

The CSA Mine Energy Team, established in August 2010 continued to meet throughout 2011. The Energy

Team provides a forum for monitoring energy usage, reviewing energy savings suggestions, and scoping and

progressing implementation of energy efficiency projects. All key areas on site are represented in the team.

Energy efficiency projects commenced or completed in 2011 include:

Energy efficiency education campaign;

Flotation cell equipment and procedural changes;

Procedural changes to reduce lime used in flotation cells;

Installation of efficient tailings thickener.

3.1.6 Compressive Emissions and Energy Audit

During 2011 CMPL engaged external consultants to undertake an assessment of overall energy usage and carbon

emissions at CSA in order to develop a suitable action plan for the implementation of cost effective projects

validated by the CMPL management team. The assessment:

Identified the range of energy savings available to improve energy performance and achieve cost

savings;

Determined opportunities to obtain and trade Energy Savings Certificates under the NSW Energy

Savings Scheme (ESS) from viable energy projects;

Reviewed CMPL’s various compliance and reporting obligations at State and Federal level including

the Energy Efficiency Opportunities (EEO) program and confirming obligations under the Energy

Savings Action Plan (ESAP) program;

Assessed CMPL’s carbon emission profile including Scope 1 and 2 covered in the NGER Act as well as

the potential exposure due to Scope 3 emissions;

Focussed on management opportunities to ensure appropriate steps are taken to facilitate continuous

improvement in the future; and,

Incorporated previously identified energy saving opportunities.

The assessment identified short to medium and long term energy savings and carbon emission reduction

opportunities, these are listed in Table 22 and Table 23.

CMPL 2011 AEMR

58

Table 22 Short-Medium Term Energy Saving and Carbon Emission Reduction Opportunities

Notes:

1. To be estimated upon availability of additional project cost data

2. Projected carbon cost savings through the replacement of diesel with B10 biodiesel 3. Projected carbon cost savings through the replacement of diesel with B20 diesel

Table 23 Long Term Energy Saving and Carbon Emission Reduction Opportunities

Notes:

1. To be estimated upon availability of additional project information

CMPL 2011 AEMR

59

The assessment determined CMPL has fulfilled some of its ESAP obligations by submitting an initial report in

June 2007. However, CMPL has not submitted required annual progress reports or the final report due at the

end of the four year cycle in June 2011. A number of energy saving projects implemented during the 2007-2011

reporting period were identified for inclusion in the final ESAP report to demonstrate compliance with ESAP

these included: power factor correction and flotation circuit improvements. During 2012 CMPL will consult

with OEH and fulfil its commitments under ESAP by submitting a final report.

CMPL has not yet reached the threshold for EEO participation (0.5 PJ) as identified in the energy assessment.

With the expansion of the mine and deepening of the No.1 shaft it is anticipated CMPL will trigger the EEO

threshold in the next financial year. The energy assessment recommends steps for preparation and participation

in the EEO program once the threshold has been triggered. If EEO is triggered in the 2011-2012 financial year

CMPL will fulfil its commitments by registering by March 2013 and submitting an assessment plan by

December 2013.

The energy assessment analysed CMPLs liability under the Clean Energy Act 2011 which comes into effect in

July 2012. CMPL will not be a direct participant in the scheme as the Scope 1 emissions threshold has not been

met. However CMPL incur increased electricity costs and increased fuel costs through a reduction in fuel tax

credits.

The assessment outlined steps for CMPL to achieve an integrated approach to energy management based on

continuous improvement principles. Steps include the implementation of management practices alongside

traditional technical approaches to energy efficiency. Current performance was assessed against a set of best

practice criteria of 25 key elements, results are shown in Figure 13. A gap analysis of energy management at the

CSA Mine was conducted and priority actions were identified, these are shown in Table 24.

In 2012 CMPL will prioritise and assess the feasibility of energy efficiency projects identified through the

energy assessment. An action plan for implementation will be developed. CMPL will also address key actions

identified in the gap analysis in order to further develop sustainable energy and carbon management practices.

CMPL 2011 AEMR

60

Figure 13 Management Practices Assessments – Level of Development

Table 24 Priority Management Practice Actions

CMPL 2011 AEMR

61

3.2 Erosion and Sedimentation

CMPL has numerous bunds, water diversion drains and catchment dams within the CSA Mine to control erosion

and sedimentation on site. The Stormwater Drainage Improvement Plan sets out improvement objectives to the

system. Improvement works completed in 2011 (see Section 2.8.2) were aimed at re-establishing site drainage

facilities to efficiently convey stormwater through the site, reduce erosion, reduce build-up of sediment within

the existing dams, and improve environmental management.

The TSF is not included in the Stormwater Drainage Improvement Plan because all drainage, erosion and water

catchment issues are dealt with through the TSF Operations Plan, dam engineers, surveyors and DSC

Surveillance reports. The TSF is monitored for structural erosion in the 3 monthly compliance surveys, in

addition to weekly monitoring, and inspections after rainfall events exceeding 25 mm in a 24 hour period by the

Ore Processing Superintendent. Furthermore, a general TSF inspection occurs twice per 12 hour shift by Mill

Operators.

Access tracks are kept to a minimum on site and are positioned so that they do not cause any unnecessary

damage to the land. Temporary access tracks are ripped, topsoiled and revegetated where necessary when they

are no longer required for mining operations.

Within 24 hours of a large rainfall event (greater than 25 mm over 24 hours) an erosion and sediment control

inspection is conducted by a member of the Environment Department. A visual inspection is completed of key

water storages, drainage channels and bunds across site to identify erosion damage, drainage issues, blockages,

storage capacities and risks of overflow or discharge. Corrective actions are assigned with priority given to

those that maintain the capacity of storages and minimise the risk of damage to the structural integrity of

facilities. Four inspections were completed in 2011, three of which were conducted after rainfall events of

greater than 25 mm and one, in November, occurred after a rainfall event of 21 mm. There were no incidents of

sediment overflow or discharge in 2011. Figure 14 shows the monthly rainfall events and inspections completed

in 2011.

Figure 14 Erosion and Sediment Control Inspections 2011

CMPL 2011 AEMR

62

3.3 Surface Water Quality

Surface water quality samples are collected monthly from active water storage structures around the site (Plan 2).

Many parts of the site and associated dams only become wet immediately after large rainfall events therefore the

number of water quality samples for each catchment varies. All samples are tested for pH and electrical

conductivity in the on-site laboratory before sending off site to a NATA approved laboratory for determination

of Cu, iron, lead, zinc, and sulphate concentrations. Water quality is compared to the Australian and New

Zealand Conservation Council (ANZECC) guidelines for irrigation and general use water. Stock is not

permitted on the mine site, and the only use for these catchment dams is currently either reclaim back to the plant

for use as process water, or simple evaporation, hence the comparison with general use water guidelines. In the

absence of ANZECC general water use guidelines, ANZECC stock water guidelines have been used.

The locations of surface water quality monitoring sites are shown in Plan 2. The surface water quality results for

2010 and 2011 are summarised in Table 25. Raw data is included in Appendix E.

Sampling sites S1, S10, S13 and S9 surround the base of the catchments associated with the excised old

Subsidence Area and the old Smelter Area. Therefore these locations often show signs of contamination.

Samples collected from site S2 are taken directly from the Raw Water Tank. This is CMPL’s incoming external

water supply from the Cobar Water Board, and therefore provides a comparative analysis for surface water

catchment samples collected from other dams around the mine site. Any exceedances detected in these S2

samples are therefore assumed to be the naturally occurring levels in the uncontaminated water supply.

Sample site S4, the Borrow Pit Dam, generally receives clean rainfall runoff, but can also receive surface runoff

from the mine site in cases of overflows and spills. It is therefore expected to show levels indicative of

contaminated water. Pork Pie dam (S14) is the process water dam and receives the water from Borrow Pit and

the new operational water dam, thus is likely to show similar water quality characteristics.

63

Table 25 CSA Surface Water Monitoring Results 2010 and 2011

Sampling Location Parameter

pH Conductivity (μS/cm) Total Cu (mg/L) Total Iron (mg/L) Total Lead (mg/L) Sulphates (mg/L) Total Zinc (mg/L)

ANZECC: 6-8.5 ANZECC: 7,700 ANZECC : 5 ANZECC: 10 ANZECC: 5 ANZECC: 1,000 ANZECC: 5

2010 2011 2010 2011 2010 2011 2010 2011 2010 2011 2010 2011 2010 2011

S1 - Catch dam North of old CSA spoils

(n = 7)

Average

(± Std Dev)

3.88 3.48 14.40 34.9 14 20 9.97 9.85 0.08 0.04 1,607 1,267 76.98 76.16

0.37 0.42 17.4 13.3 8.60 7.34 10.63 4.61 0.03 0.02 1,413 453 63.29 29.33

Minimum 3.36 3.14 0.30 16.5 6.42 8.34 1.51 5.70 0.04 0.01 653 699 29 31.60

Maximum 4.38 4.13 46 56 33.00 31.80 32.00 18.30 0.12 0.08 4,930 2,020 234 121.00

S2 - Raw Water Tank (n = 12 )

Average 7.43 7.36 8.23 24.03 0.02 0.02 5.95 2.30 0.00 0.01 10.33 18.50 0.33 0.44

(± Std Dev) 0.54 0.70 8.49 22.15 0.02 0.02 8.74 3.25 0.00 0.01 6.97 11.43 0.15 0.37

Minimum 6.60 6.45 0.20 1.80 0.00 0.00 0.62 0.09 0.00 0.00 2.00 2.00 0.09 0.11

Maximum 8.27 8.18 23.10 85.40 0.08 0.07 30.40 9.09 0.01 0.03 29.00 32.00 0.64 1.42

S4 - Borrow Pit Dam (n = 3)

Average 5.93 6.14 13.31 57.40 11.34 3.58 1.54 0.82 0.15 0.03 732.75 632.33 9.22 6.50

(± Std Dev) 0.68 0.50 22.91 44.11 22.91 2.79 2.67 0.69 0.21 0.03 405.66 342.40 4.85 3.40

Minimum 4.94 5.56 0.20 12.80 0.20 1.32 0.05 0.35 0.01 0.01 196.00 242.00 0.03 3.52

Maximum 7.18 6.45 67.50 101.00 67.50 6.69 8.53 1.62 0.62 0.06 1420.00 882.00 14.10 10.20

S5 - TSF Decant Dam (n = 9)

Average 6.53 7.02 16.37 45.71 0.48 0.12 13.23 0.76 0.01 0.00 1347.30 1290.67 1.89 0.25

(± Std Dev) 1.03 0.44 24.97 47.18 0.66 0.09 41.39 0.56 0.02 0.00 442.55 301.05 2.49 0.41

Minimum 4.96 6.55 0.10 0.40 0.01 0.02 0.28 0.05 0.00 0.00 828.00 858.00 0.03 0.04

Maximum 7.62 7.68 77.00 143.70 2.21 0.29 138.00 1.92 0.07 0.00 2060.00 1680.00 5.62 1.34

S8 - Railway Dam (n = 0)

Average 4.12

No Samples

2011

4.56

No Samples

2011

26.38

No Samples

2011

1.93

No Samples

2011

0.03

No Samples

2011

287.00

No Samples

2011

6.76

No Samples

2011

(± Std Dev) 0.32 3.49 10.42 1.16 0.01 66.32 1.10

Minimum 3.61 0.40 15.20 0.75 0.02 209.00 4.86

Maximum 4.47 8.80 41.30 3.59 0.04 390.00 7.62

S9 - Retention Basin (n = 0)

Average

(± Std Dev)

4.61

No Samples

2011

4.30

No Samples

2011

1.64

No Samples

2011

0.52

No Samples

2011

1.00

No Samples

2011

231.25

No Samples

2011

9.73

No Samples

2011 0.32 3.79 0.23 0.18 0.52 45.75 1.77

Minimum 4.14 0.40 1.38 0.29 0.44 177.00 7.51

Maximum 4.87 8.70 1.94 0.72 1.64 286.00 11.20

S10 - North Run Off Dam (n = 3)

Average

(± Std Dev)

5.66 6.20 9.03 26.77 1.29 0.95 0.34 0.76 0.16 0.15 162.17 109.67 5.86 3.96

0.52 0.59 8.30 21.53 0.62 0.34 0.40 0.46 0.12 0.10 69.76 34.00 2.15 0.72

Minimum 4.76 5.61 0.40 6.40 0.88 0.73 0.06 0.26 0.04 0.05 90.00 76.00 3.99 3.27

Maximum 6.32 6.78 23.50 49.30 2.53 1.34 0.98 1.17 0.31 0.25 276.00 144.00 10.10 4.70

S11 - STDE Stormwater Catchment

(n = 12)

Average

(± Std Dev)

6.94 7.41 15.26 25.18 0.11 0.17 0.28 0.33 0.00 0.00 275.90 122.00 0.05 0.03

0.53 0.41 12.57 21.27 0.08 0.13 0.23 0.34 0.00 0.00 140.03 17.06 0.05 0.03

Minimum 6.21 6.79 0.30 3.30 0.02 0.05 0.05 0.05 0.00 0.00 100.00 93.00 0.01 0.01

Maximum 7.73 7.94 36.80 66.70 0.26 0.51 0.67 1.07 0.00 0.00 553.00 151.00 0.16 0.11

S13 - Western Run-off Dam

(n =0)

Average

(± Std Dev)

5.18

No Samples 2011

6.28

No Samples 2011

2.25

No Samples 2011

0.35

No Samples 2011

0.22

No Samples 2011

260.20

No Samples 2011

8.48

No Samples 2011

0.32 6.04 0.93 0.54 0.20 56.94 1.83

Minimum 4.88 0.30 1.21 0.05 0.08 178.00 7.08

Maximum 5.69 14.90 3.38 1.32 0.57 305.00 11.60

S14 - Pork Pie Dam (n = 12)

Average

(± Std Dev)

6.38 7.25 20.19 46.77 1.70 1.65 0.28 0.73 0.02 0.02 691.75 667.08 3.82 2.39

0.72 1.09 24.16 32.23 1.71 2.54 0.21 0.69 0.03 0.03 155.77 182.47 1.86 2.03

Minimum 4.93 4.84 0.30 5.30 0.18 0.05 0.05 0.05 0.00 0.00 432.00 451.00 0.66 0.10

Maximum 7.47 9.14 71.20 132.40 5.14 8.81 0.70 1.84 0.12 0.09 994.00 992.00 6.83 6.82

S15 - Old Mine Water Dam (MPL 1093)

(n = 8)`

Average

(± Std Dev)

7.46 7.67 8.05 18.35 0.01 0.02 0.91 1.68 0.00 0.01 4.35 16.38 0.09 0.39

0.51 0.71 5.63 14.19 0.02 0.01 0.80 1.62 0.01 0.01 5.40 10.85 0.10 0.54

Minimum 6.67 6.98 0.20 2.60 0.00 0.00 0.27 0.46 0.00 0.00 0.50 8.00 0.01 0.02

Maximum 8.46 8.58 16.30 47.10 0.06 0.02 3.09 5.27 0.03 0.03 14.00 37.00 0.31 1.49

S16 - Old Mine Water Dam (MPL 1094)

(n = 12)

Average

(± Std Dev)

7.11 7.71 6.68 9.33 0.03 0.09 1.02 3.94 0.04 0.20 5.08 1.50 0.02 0.06

0.87 0.54 4.82 4.58 0.01 0.04 0.70 2.30 0.04 0.11 11.99 0.90 0.01 0.03

Minimum 5.26 6.93 0.20 1.30 0.02 0.04 0.23 0.85 0.01 0.05 0.50 1.00 0.01 0.01

Maximum 8.49 8.46 13.40 18.40 0.06 0.16 2.35 8.24 0.14 0.44 42.00 4.00 0.06 0.10 Notes: 1. n represents the number of months sampled (samples unable to be taken when dam is dry, therefore n<12. No samples indicates water storage was dry;

2. Values outside ANZECC guideline limits are highlighted in red. Water quality is compared to the ANZECC guidelines for irrigation and general use water, if absent ANZECC stock water guidelines have been used.

64

Each parameter of surface water quality summarised in Table 25 is briefly discussed below in terms of the

potential effects if an overflow or runoff was to occur onto uncontaminated vegetated areas.

3.3.1 pH

The pH of water is a measure of its acidity or alkalinity and should be maintained between 6 and 9 for surface

waters. Generally, pH itself is not a water quality issue of concern, but it can indicate the presence of a number

of related problems. Soil and animal health will not generally be affected by water with pH in the range 4 – 9.

All sampling locations recorded an average pH within upper and lower guidance limits, with the exception of S1.

Samples from S1 had an average pH reading (pH 3.48) lower than the guidance lower limit of pH 6. The 2011

average (pH 3.48) was also slightly below the 2010 average (pH 3.88). This dam is within a known

contaminated catchment (excised old subsidence zone and smelter site), therefore it is essential that runoff is

captured on site and allowed to evaporate. The S1 dam is closely monitored during wet weather periods, as it

has been known to overflow in past times of heavy rainfall. All overflows are contained within the CML5

boundaries, and have not shown any negative impacts on the surrounding vegetation as a result of such runoff in

the past.

Improvements in pH have been recorded in catchment dams S4 (Borrow Pit) and S10 (North Run Off Dam).

The average pH recorded has increased at both sample sites to be within the stock and general water guideline

limits. Improvement in water quality at the Borrow Pit is a likely indication of the improvement of the site water

drainage system and construction of the new Operational Water Storage Dam capturing the majority of

contaminated run-off (discussed in Section 2.8.3).

3.3.2 Electrical Conductivity (Salinity)

Salinity is the presence of soluble salts in soils or waters. High salinity levels in soils may result in reduced plant

productivity, development of salt scald areas, and in extreme cases, and the elimination of native vegetation.

The surface water salinity concentrations for surface water catchment dams within the CSA Mine site were

consistently below the ANZECC guideline value of 7,700 uS/cm in 2011 and are therefore unlikely to negatively

impact if an overflow was to occur.

3.3.3 Copper

Cu is an essential trace element for vegetation with an ANZECC guideline for irrigation and general water of

5 mg/L. Cu is an enzyme activator, therefore a lack of this element leads to vegetation mottling and yellowing in

leaves. Only S1 recorded elevated Cu concentrations in 2011. The average Cu concentration of 20 mg/L

recorded in S1 was higher than the irrigation and general water guideline limit of 5 mg/L and higher than the

average of 14 mg/L recorded in 2010. Given S1 captures contaminated runoff from the contaminated old

subsidence zone (as explained above) this is not surprising, and all water captured is evaporated.

Improvements in water quality were recorded in S4 (Borrow Pit), with the average Cu concentration showing a

marked reduction from 11.34 mg/L recorded in 2010 to 3.58 mg/L in 2011, below the irrigation and general

water guideline of 5 mg/L.

CMPL 2011 AEMR

65

3.3.4 Iron

Iron (Fe) is also an essential trace element of vegetation and must be present in small quantities for plant

formation. The recommended Fe concentration for irrigation and general use water supplies should remain

below 10 mg/L. There were no exceedences of Fe during 2011.

3.3.5 Lead

The ANZECC irrigation and general water guideline for Lead (Pb) concentration is 5 mg/L. No surface water

monitoring results exceeded this limit in 2011.

3.3.6 Sulphates

ANZECC guidelines for irrigation and general use water do not have a recommended value for sulphates. The

guideline for stock drinking water states that no adverse effects to soil and animal health are expected if the

concentration of sulphate does not exceed 1,000 mg/L. The average concentration of sulphates for only two

sampling sites at the CSA mine were over this recommended value in 2011. S1 recorded sulphate levels above

the ANZECC guideline, with an average concentration of 1,267mg/L. This average concentration was less than

the average recorded in 2010 (1,607 mg/L) indicating an improvement in water quality. Elevated sulphates levels

are a typical component of mine run-off (ANZECC, 2000). All runoff from this area is captured and evaporated;

no runoff leaves the immediate area and is very well contained.

S5 also showed elevated levels of sulphate (1,260 mg/L) over the stock drinking water trigger. S5 is the STSF

Decant Dam and receives run-off from the STSF. S5 is lined and fenced to prevent animal access, therefore is

not used for stock drinking water. The 2011 data (1, 260mg/L) indicates a small improvement on 2010 data

(1,347mg/L).

3.3.7 Zinc

Zinc (Zn) is an essential trace element that acts as an enzyme activator for vegetation growth, and therefore a

lack of this element leads to leaf mottling and yellowing in younger leaves. The ANZECC guidelines low risk

trigger value for zinc concentrations (5 mg/L) was used to compare CSA surface water results. Catchment dam

S1 is again high in concentration (76.16 mg/L); however has remained stable compared to 2010 results (76.98

mg/L). This average concentration is significantly reduced from 125 mg/L recorded in 2008. Catchment Dam

S10 also located in this same contaminated catchment (excised subsidence zone and old smelter site) has

recorded an improvement in 2011, now with averages below the guideline (3.96 mg/L).

Borrow Pit Dam (S4) recorded an average slightly above the guideline (6.50 mg/L), however indicates an

improvement in water quality compared with 2010 results (9.22 mg/L). This improvement can be contributed to

the improvements in surface water drainage and construction of the operational water dam intercepting a

majority of contaminated water from the Ore Processing Plant.

Elevated Zn concentrations do not cause any major health problems when taken up by plants or consumed by

stock, however it does contribute to cosmetic and aesthetic effects on water quality. Therefore, while it is not

ideal to have concentrations exceeding guideline values, it is not detrimental.

CMPL 2011 AEMR

66

3.4 Ground Water

3.4.1 TSF Embankment Phreatic Surface Monitoring

There are 42 piezometer monitoring sites positioned around the TSF to measure the phreatic surface of the TSF

embankment walls, this includes the 7 new locations installed in February. These are used to monitor the depth

and quality of any water generated by seepage from the TSF. Of these monitoring sites, 20 recorded water

variations during 2011, while the remainder were dry for the entire year. Wet piezometers indicate water as

shallow as 2.93 m below surface and as deep as 23 m.

Locations of piezometers are displayed in Plan 2. Figure 15 shows the depths of the wet piezometers around the

TSF. The raw data is provided in Appendix E.

0.00

5.00

10.00

15.00

20.00

25.00

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Dep

th (

m)

P1 P7 P8 P14 P15 P17 P26 P27 P33 P34 P35

P37 P38 MB1 MB2 MB3 P41 P43 P44 P45 P57 P56

Notes:

1. (---) indicates a piezometer dried up during 2011

Figure 15 CSA Piezometer Depths 2011

CMPLs consultant TSF Dam Engineers (Golder Associates) identified trigger levels for 16 key piezometers

surrounding the STSF in 2011 to comply with DSC requirements from the 2010 TSF surveillance report; these

are displayed in Table 26 . These trigger levels were based on a stability analysis undertaken for the STSF wall

raise design. If trigger levels are breached, the risk of seepage from toe of the embankment wall and local

sloughing may be increased. None of these triggers levels have been breached in 2011 indicating the STSF is

CMPL 2011 AEMR

67

being operated safely and well within design limits. Piezometers will be continued to be monitored monthly in

2012.

Table 26 STSF Piezometers and Trigger Depths

Piezometer Trigger Depth

(m)

2011 Minimum Depth

Recorded

Date Minimum Depth

Recorded

P1 4.60 6.10 18/02/2011

P5 4.40 10.80 22/12/2011

P6 4.30 10.73 25/05/2011

P7 4.40 6.58 24/01/2011

P9 4.20 11.09 3/08/2011

P35 2.00 3.25 31/08/2011

P26 4.60 8.80 28/09/2011

P27 4.30 7.62 18/02/2011

P28 4.40 8.60 22/12/2011

P38 4.40 11.97 24/01/2011

P41 6.00 9.21 22/12/2011

P42 4.00 4.75 22/12/2011

P43 6.00 10.33 28/09/2011

P44 4.00 4.90 26/10/2011

P45 6.00 9.60 31/08/2011

P46 4.00 5.10 22/12/2011

P51 2.00 4.15 22/12/2011

P52 2.00 5.15 22/12/2011

P53 6.00 10.15 22/12/2011

P54 6.00 9.00 22/12/2011

P55 6.00 10.23 22/12/2011

P56 6.00 8.66 31/08/2011

P57 6.00 9.97 22/12/2011

All piezometers with the exception of P14, P15 and P17, are located around the STSF. Piezometers 14, 15 and

17 are located on the north-eastern wall of the NTSF. The water level remained stable at these three sites for

most of the year, with any slight variations generally correspondent with rainfall. P17 was only wet for one

month in February however has since dried out.

Water levels recorded for P1 and P7 remained wet throughout 2011, however the water level remained very

stable and well below the trigger levels outlined in the STSF Operation Manual and identified in Table 26. P8

was wet for two months in January and February and ranged from 2.93 m - 3.2 m. P8 however has since dried

out. This is a promising sign as P8 was the location of the old penstock and there has been tailings deposition in

the STSF since the piezometer has dried out, indicating previous seepage issues around the penstock may be

resolved.

CMPL 2011 AEMR

68

Piezometers 26 (variation 1.05 m) and 27 (variation 0.05 m) increased in 2011 and is likely due to the

corresponding rainfall and storm events.

Piezometer 35 has varied throughout 2011, fluctuating between levels of 3.25 m to 6.78 m and has risen

consistently since 2009. An investigation was commissioned by CMPL to investigate the fluctuation in the

piezometer depths and complete a stability analysis of the South Slope Embankment of the STSF. The

investigation completed by Golders’ Engineers established a trigger level of 1 m for the piezometer which when

breached, may increase the risk of seepage from the toe of the embankment wall. Piezometer P35 is located at

the downstream toe of the southern embankment of the STSF. The increase in water level can be attributed to

water ponding at the toe of the embankment with limited drainage. The depth of P35 has remained steady at 3.5

m well below the trigger level and will continue to be monitored monthly to ensure the trigger level is not

breached.

Piezometer 37 slightly varied during the year, fluctuating between levels of 9.84 m and 10.7 m, and drying out

during May 2011. This site is located on the wall between the STSF and the dam extension. Water level

fluctuations are therefore explained by discharge of wet tailings along this wall and subsequent drying out since

the construction of the new wall lift completed in 2010. Monitoring of P37 was ceased from October 2011 on

the recommendation of the TSF dam engineers in the STSF Annual Surveillance Report.

Piezometer 38 was wet in January, however subsequently dried out for the remaining months of 2011. The

minimum depth of piezometer 38 (11.74 m) was recorded in January, however was significantly below the

trigger depth (4.4 m) set in the STSF operations plan and is also likely associated with the pooling of water

stormwater during the construction of the TSF wall lift.

Piezometer 41, 43, 44, 45 and 46 (surrounding the STSFE) fluctuated very little in 2011 and remained

significantly below trigger levels set in the STSF operations manual.

Fluctuations in piezometers MB1, MB2 and MB3 are minor (less than 2.7 m) and likely due to rainfall as these

are located well away from the TSF embankment and are very deep bores (92 m, 54 m and 14.8 m respectively)

thought to be associated with separate water fractures or aquifers as discussed in Section 2.8.4. Water quality

results from MB3 also show no connection with seepage water recorded in TSF wall piezometers and were

within ANZECC water quality guidelines as outlined above.

Figure 16 shows a cross-sectional drawing of the typical set up of piezometers around the TSF illustrating how

piezometer readings can be influenced by the discharge of wet tailings material and periods of rainfall. As

indicated in Figure 16, the position of a wet piezometer on the tailings embankment assist with an assessment

whether water detected is due to moisture in the tailings material below or if it is moisture below ground level.

CMPL 2011 AEMR

69

Figure 16 Cross Section of TSF Piezometer Setup

The list below indicates which of the wet piezometers are located on the embankment walls or on ground level:

Location / Position:

Ground Level P8, P17, P33, P35, MB1, MB2, MB3

Original Wall P41, P43, P44, P45

Wall Raise 1 P7, P15, P26, P27, P38

Wall Raise 2 P14, P37

Wall Raise 3 P56, P57

CMPL 2011 AEMR

70

Figure 17 Sulphate, Iron and pH levels

Figure 18 Copper, Lead and Zinc levels

Note: The values in brackets are the depth of the piezometers and not the distance from tailings.

CMPL 2011 AEMR

71

Figure 17 and 18 illustrates the quality of tailings seepage water collected from piezometer sites around the

STSF. The seepage water shows elevated sulphate levels and is high in iron and zinc around the STSF. The pH

is acidic in most samples excluding P33 and MB3 which are within ANZECC irrigation and general water

guidelines. P38 and P38 have elevated Cu compared to the others.

Most importantly, the water quality parameters of the sample collected from piezometer MB3 (located on the

ground level outside the TSF walls) are all within ANZECC guidelines. This clearly indicates there is no link

between water found in the TSF walls and groundwater outside the TSF footprint. This is confirmed by the

monitoring of ground water bores discussed in the sections below.

72

Table 27 CSA Piezometer Water Quality Monitoring Results 2011

Piezometer

Location Parameter

pH Electrical Conductivity

(uS/cm)

Copper

(mg/L)

Iron

(mg/L)

Lead

(mg/L)

Sulphates

(mg/L)

Zinc

(mg/L)

ANZECC: 6-8.5 ANZECC: 7,700 ANZECC: 5 ANZECC: 10 ANZECC: 5 ANZECC: 1000 ANZECC: 5

2010 2011 2010 2011 2010 2011 2010 2011 2010 2011 2010 2011 2010 2011

P35 (n = 12)

Average 5.32 5.31 84.09 126.74 0.05 0.15 1,128.92 909.93 0.01 0.01 12,649.09 9,982.73 22.42 26.24

(± Std Dev) 0.25 0.41 134.15 115.22 0.02 0.20 144.98 520.74 0.01 0.01 2,784.24 2,559.00 8.64 7.31

Minimum 4.79 4.79 0.70 9.30 0.02 0.03 954.00 35.40 0.00 0.00 7,650.00 6,470.00 0.02 14.90

Maximum 5.64 5.94 442.00 458.00 0.09 0.74 1,440.00 1,440.00 0.05 0.05 17,400.00 13,200.00 33.30 39.60

P37 (n = 4)

Average 4.50 4.09 51.11 107.55 11.45 30.38 4,309.75 2,757.50 0.08 4.64 21,166.67 9,642.50 357.07 160.95

(± Std Dev) 0.77 0.09 70.90 86.16 21.73 52.53 5,263.59 1,449.65 0.12 8.98 19,381.48 1,113.20 473.83 69.47

Minimum 3.75 4.02 2.30 55.20 0.66 1.30 722.00 1,370.00 0.01 0.01 6,680.00 8,170.00 42.10 93.80

Maximum 6.80 4.22 199.00 236.00 68.50 109.00 16,300.00 4,500.00 0.41 18.10 66,200.00 10,600.00 1,370.00 255.00

P33 (n = 10)

Average 7.31 6.75 106.60 141.12 0.11 0.05 9.19 1.81 0.01 0.01 2,550.00 2,324.00 0.12 0.07

(± Std Dev) 0.18 0.53 11.88 100.94 0.11 0.04 4.68 1.98 0.01 0.01 169.71 234.62 0.04 0.12

Minimum 7.18 5.64 98.20 5.00 0.03 0.01 5.88 0.39 0.00 0.00 2,430.00 1,760.00 0.10 0.01

Maximum 7.43 7.23 115.00 458.00 0.19 0.13 12.50 5.90 0.01 0.02 2,670.00 2,610.00 0.15 0.39

P26 (n = 7)

Average 2.93 2.63 149.17 117.39 0.48 0.50 2,107.35 2,771.43 0.02 0.02 11,109.00 11,315.71 44.81 49.71

(± Std Dev) 0.27 0.10 214.83 87.99 0.26 0.14 960.06 280.32 0.03 0.01 4510.56 3504.32 19.26 5.46

Minimum 2.54 2.47 0.80 16.00 0.25 0.34 23.50 2,330.00 0.00 0.00 1,050.00 8,440.00 1.47 39.90

Maximum 3.36 2.74 691.00 243.00 1.09 0.78 3110.00 3090.00 0.11 0.04 17,200.00 17,600.00 68.80 56.70

P38 (n = 1)

Average 2.82 2.19 180.08 556.00 26.00 35.80 833.60 2640.00 0.06 0.06 8,830.00 9,010.00 56.46 66.20

(± Std Dev) 0.38 n/a 174.30 n/a 11.29 n/a 773.51 n/a 0.02 n/a 7,635.28 n/a 27.67 n/a

Minimum 2.16 2.19 6.00 556.00 17.20 35.80 227.00 2,640.00 0.03 0.06 4,490.00 9,010.00 35.80 66.20

Maximum 3.13 2.19 404.00 556.00 45.30 35.80 2,140.00 2,640.00 0.09 0.06 22,400.00 9,010.00 103.00 66.20

MB3 (n = 4)

Average 5.95 6.13 50.37 52.68 0.21 0.09 4.97 2.21 0.04 0.01 252.00 244.50 0.39 0.44

(± Std Dev) 0.30 0.08 20.70 12.07 0.12 0.04 1.43 1.97 0.03 0.01 86.81 136.11 0.06 0.09

Minimum 5.66 6.07 35.00 35.00 0.08 0.05 3.63 0.43 0.01 0.00 196.00 163.00 0.32 0.36

Maximum 6.25 6.25 73.90 62.20 0.30 0.15 6.48 4.18 0.07 0.03 352.00 448.00 0.44 0.56

P34 (n = 11)

Average

No Samples

2010

5.48

No Samples

2010

100.06

No Samples

2010

0.21

No Samples

2010

4.10

No Samples

2010

0.01

No Samples

2010

5,416.25

No Samples

2010

0.57

(± Std Dev) 2.01 97.47 0.24 4.68 0.01 1,333.73 0.44

Minimum 0.57 4.50 0.04 0.05 0.00 8,380.00 0.17

Maximum 6.73 220.00 0.69 14.30 0.02 4,050.00 1.37

P56 (n = 5)

Average

No Samples

2010

5.82

No Samples

2010

65.34

No Samples

2010

0.28

No Samples

2010

2,919.60

No Samples

2010

0.74

No Samples

2010

12,032.00

No Samples

2010

1.37

(± Std Dev) 0.50 37.73 0.39 1,759.30 1.12 3,676.43 1.92

Minimum 5.15 6.20 0.01 528.00 0.01 8,000.00 0.07

Maximum 6.31 100.00 0.89 4,820.00 2.58 17,100.00 4.51

P37 (n = 2)

Average

No Samples 2010

4.09

No Samples 2010

107.55

No Samples 2010

30.38

No Samples 2010

2,757.50

No Samples 2010

4.64

No Samples 2010

9,642.50

No Samples 2010

160.95

(± Std Dev) 0.09 86.16 52.53 1,449.65 8.98 1,113.20 69.47

Minimum 4.02 55.20 1.30 1,370.00 0.01 8,170.00 93.80

Maximum 4.22 236.00 109.00 4,500.00 18.10 10,600.00 255.00

P5 (n = 2)

Average

No Samples

2010

6.80

No Samples

2010

18.30

No Samples

2010

0.37

No Samples

2010

29.90

No Samples

2010

0.09

No Samples

2010

4,895.00

No Samples

2010

0.75

(± Std Dev) 0.42 2.26 0.40 24.47 0.07 388.91 0.17

Minimum 6.50 16.70 0.09 12.60 0.04 4,620.00 0.63

Maximum 7.10 19.90 0.65 47.20 0.13 5,170.00 0.87 Notes:

1. n represents the number of months sampled (samples unable to be taken when dam is dry, therefore n<12. No samples indicates piezometer was dry; 2. Values outside ANZECC guideline limits are highlighted in red. Water quality is compared to the ANZECC guidelines for irrigation and general use water, if absent ANZECC stock water guidelines have been used.

73

3.4.2 Ground Water Monitoring

CMPL established a monitoring program in 2011 to measure the depth of ground water from pilot holes drilled

in 2010 surrounding the STSF and NTSF. Consultants were commissioned to investigate the potential for

ground water harvesting in local ground water systems. The report by consultants Aquaterra completed in 2010

(included in the 2010 AEMR) concluded that there was no likely connection between the TSF and local ground

water systems.

To confirm the findings of the report and understand local ground water conditions over an extended period of

time, water bores were measured monthly. The measured depths of the 17 pilot holes in 2011 are shown in

Figure 17. The recorded depths indicate the groundwater bores were very stable throughout 2011, with the

maximum variation in depth recorded at 3.25 m in WERC10014. The small variations (0 m – 3 m) recorded in

deep pilot holes (80 m – 100 m) are a likely result of infiltration from rainfall. The results of the ground water

monitoring confirm the findings of the AquaTerra report indicating no connection between the TSF and local

ground water systems. Pilot holes will continued to be monitored in 2012 to provide baseline data of local

ground water systems and used in supporting evidence for any future TSF upgrades.

Figure 19 CSA Ground Water Monitoring Results 2011

CMPL 2011 AEMR

74

3.5 Contaminated Polluted Land

Surface contamination of soils has occurred throughout the CSA Mine site from various previous mining

activities including old tailings deposits, decline waste stockpiles, and wastes from a surface smelter. Elevated

levels of Cu, lead, zinc and other heavy metals are likely to remain in these areas although the dumps have since

been removed.

Site observations suggest that current mining operations are only one contributor to rehabilitation requirements,

with undocumented legacy issues also relevant. There is high variability in soil quality across the CSA mining

lease, and within individual areas, with minimal vegetation in most areas.

CMPL commissioned a progressive soil sampling program in December 2010 to investigate areas of known and

suspected contamination on the CSA Mine Site in order to update the CSA Mine Contaminated Soils Register.

A total of 15 sites with suspected soil contamination were sampled along with five background sites. These

background sites were sampled to build a robust dataset of baseline metal concentrations, pH, salinity and acid

production potential of soils within CML5 that are unaffected by mining activities.

To build on the sampling that was conducted in 2010, a further ten sites were sampled in 2011 to determine

whether sites were contaminated and the level and type of contamination. A further five background sites were

sampled to build the analogue database of local soil conditions. A full copy of the report is available in

Appendix F.

Soil samples were analysed for acid generating potential, pH, metal concentrations and salinity. These

parameters were compared with undisturbed background sites and National Environmental Protection Measure

for Site Investigations Ecological Investigation Levels (NEPM EILs). NEPM EILs are based on threshold levels

for phytotoxicity and uptake of contaminants which may result in impairment of plant growth and reproduction

or unacceptable residue levels.

Leading Practice guidelines were used to determine if soils were PAF or Non Acid Generating (NAG) using

Acid Base Accounting (ABA) techniques.

Given these sites will ultimately be rehabilitated, additional reference data on the success of vegetation growth

were in addition to NEPM EILs and background data, to provide an indication of the potential success of

vegetation establishment at each site for given pH and salinity levels.

Of the 10 sites targeted, a total of 8 areas were confirmed as sites of known contamination and two areas were

confirmed as having contamination not significant enough to prohibit rehabilitation and vegetation growth.

These areas are displayed in Figure .

Confirmed sites of contamination were primarily the result of elevated Pb, Cu and Zn concentrations above

NEPM EILs and background levels. Contaminated sites were PAF and exhibited a lower pH likely to prohibit

the establishment of vegetation. Contaminated sites also had higher salinity levels compared to measured

CMPL 2011 AEMR

75

background levels; however in the majority of contaminated sites salinity levels were not high enough to be a

limiting factor in rehabilitation.

Figure 20 CSA Contaminated Sites Register (as of 31/12/11)

In 2012, the remaining 4 areas on site suspected of contamination will be further investigated. In addition,

background sites will continue to be sampled in order to capture local baseline conditions not affected by mining

activities. Data on the nature and level of contamination of sites will assist in progressive rehabilitation to meet

performance and closure criteria set out in CMPL’s Rehabilitation Monitoring Methodology and Determination

of Completion Criteria for Rehabilitation Ecosystems report (Appendix K).

3.6 Threatened Flora

The CSA mine is situated within the Cobar Peneplain Bioregion which extends from just south of Bourke to

north of Griffith. It has a total area of 7,334,664 ha and occupies 9.2% of the state.

The Cobar bioregion is characterised by an undulating to hilly landscape with shallow, red earth soils where the

vegetation is mainly open woodlands dominated by bimble box (Eucalyptus populnea), red box (Eucalyptus

intertexta) and white cypress (Callitris glaucophylla). The woodlands of the Cobar Peneplain Bioregion are the

most extensive woodland communities to remain in western NSW.

No threatened flora species have been observed during flora surveys at the CSA Mine (Parsons Brinckerhoff

2006 or Roderick et al 1999); the habitats within the site may however, provide suitable habitat for the following

four threatened species:

Western Goodenia – Goodenia occidentalis;

Pine Dondey Orchid – Diuris tricolour;

CMPL 2011 AEMR

76

Large-leafed Monotaxis – Monotaxis macrophylla;

Greenhood Orchid – Pterostylis cobarensis.

Employees of the CSA Mine undertaking surface exploration activities are provided with information to allow

them to recognise relevant flora and fauna species. All proposed drill sites, roads and tracks are inspected prior

to any exploration activity taking place. The inspections include an assessment of potential risks to flora, fauna

and cultural heritage. CMPL employees and contractors are instructed to notify the Environment Team of the

presence of any species or sites of potential importance so that they may be further examined and appropriate

controls or actions put in place. Details of the inspection are documented including identified species, the

appropriate department is notified of management conditions required. If exploration personnel have any doubt

they are instructed not to proceed with the exploration activities until clearance is received.

No vegetative cover within the lease area is permitted to be cut, destroyed, ringbarked or removed except if such

vegetation directly obstructs or prevents the carrying on of operations (as per CML5 lease conditions). Any

clearing not authorized under the Mining Act 1992 must comply with the provisions of the Native Vegetation Act

2003 and shall occur only following advice and authorisation from the Environmental Department.

3.7 Threatened Fauna

Public database searches indicate that a total of 50 listed threatened animal species have been either previously

recorded or have potential habitat with the CML5 mining lease area. These include three species of reptile, 36

species of bird and 11 species of mammal. A total of 68 different animal species have been recorded within the

mining lease, only four of which are listed as threatened species. They are the Grey-crowned Babbler, Major

Mitchell’s Cockatoo, Yellow-bellied Sheathtail Bat and the Little Pied Bat.

Flora and fauna surveys conducted before CMPL began operations in 1999 concluded that the re-opening of the

mine and continuation of works would have negligible impact on the surrounding fauna and flora habitat on the

greater lease area. The immediate area up to 5 km in radius from the mine and beyond is covered by the original

Bimble Box woodland providing adequate refuge for ranging species.

The 2006 CSA Mine Biodiversity Study identified the key threatening processes applying to the management of

biodiversity at the CSA Mine as:

Clearing of native vegetation/land clearance;

Competition and grazing by feral rabbits and goats; and

Predation by feral cats and foxes.

CMPL’s environmental objectives aim to ensure the clearing of native vegetation is minimised where possible.

The mine understands the value of connectivity and is fortunate to be within the Cobar Peneplain Bioregion,

which is the most extensive woodland community to remain in western NSW.

Competition, grazing and predation by feral animals on the CML5 lease are addressed in the CSA Mine Pest

Animal Management Plan. This management plan was first implemented in 2007, and is updated annually. This

CMPL 2011 AEMR

77

management plan will continue in to be implemented in the future in order to keep identified feral animals under

control. No fox baiting took place during 2011, however fox baiting is anticipated in 2012 in conjunction with

the surrounding landholders.

During 2011, a total of 1,218 goats were removed from CMPL managed lands. All goats removed from site are

recorded through a Livestock Production Assurance National Vendor Declaration (NVD). A goat cannot be sold

without an NVD which is used to document numbers and locations of goats harvested, provide assurance

landholder access was granted and more importantly to declare information about the food safety status of the

livestock. This compulsory process is managed by Meat and Livestock Australia (MLA).

Feral goat management is expected to improve with the appointment of a new feral pest control contractor in

2012. Additional personnel and resources will be invested into the management of feral goats by the new

contractor.

CMPL maintains a register of reptile sightings and management at the CSA Mine. A total of 14 snakes were

recorded in 2011. Of those that were identified, all were reported as the common Eastern Brown Snake

(Pseudonaja textilis) ranging in length between 0.3 – 1.5 m (average 1.0 m). Sightings were reported from the

mill, the administration building, the surface washbay and the shaft and the maintenance offices. Snake capture

and relocation was only required on four occasions. All other sightings were just reports, with no further action

taken due to no harm being posed to the work area.

3.8 Weeds

A total of 82 flora species were recorded on site during the 2006 biodiversity surveys, of which 84% were native.

Of the remaining 16%, the diversity and density of exotic species was highest in disturbed areas such as along

tracks, around dams and in previously cleared areas. All 13 exotic species recorded were herbs, none of which

are listed noxious weeds under the Noxious Weeds Act 1993 for the CSC noxious weeds control area.

Noxious weeds known to be in the area include the Galvanised Burr (Sclerolaena birchii) and the Common

Prickly Pear (Opuntia stricta). The galvanised burr is a native of Australia and is one of only very few species

that thrive in the dry hot conditions of Cobar. There are no plans to manage this species on the CSA Mine site,

as they are viewed as a positive establishing species that assist in revegetation succession. A prickly pear

infestation was discovered in mid 2008 in the disturbed area associated with the old housing estate to the south

west of the administration building. The Common Thornapple (Datura stramonium) and Wild Tobacco

(Solanum mauritianum) are also known to occur in the area. These weeds are not listed as noxious; however

pose a threat to human and livestock health.

The CSC Weeds Officer conducted the annual Noxious Weeds Inspection of the CSA Mine site during

December 2011. The weeds officer inspected the site focusing on the most likely locations for weed

establishment including topsoil stockpiles and newly disturbed areas. The CSC Weeds Officer concluded that

the CMPL owned property Red Tank was compliant with Local, State and Federal statutory requirements in

regards to the control of listed noxious weeds. The old housing estate behind administration was also inspected

to observe the known Prickly Pear infestation. This infested area has been closely monitored by CMPL since it

CMPL 2011 AEMR

78

was originally discovered in mid 2008. Some cochineal infected segments were released in the infested area in

August 2008 as an attempt to biologically control this outbreak. Unfortunately the infested segments did not

take to the shrub and died off. CMPL environmental staff and the CSC Weeds Officer investigated other options

for biological control over 2009, before resorting to spraying the area with herbicide in November 2009. This

herbicide treatment proved effective in wilting the plant and preventing flowering during 2010. The plant was

given a follow up spray in November 2010 to prevent regrowth. It was determined by the weeds officer that the

prickly pear population had been sufficiently controlled by previous spraying and will be assessed again in 2012,

with the possibility of reintroducing cochineal infected segments.

There were small populations of Bathurst Burr sighted during the inspection on topsoil stockpiles and battered

STSF Walls. No controls (i.e. spraying) were deemed necessary at the time of inspection; populations will

continue to be monitored for new growth during 2012 and any necessary actions will be taken to ensure the

population is controlled.

Wild Tobacco plants were found during the inspection in the former EDMS yard colonising disturbed ground.

Control measures were not considered necessary given the small population and the low risk which the weed

posed. Wild Tobacco will be monitored during 2012 to prevent further infestations occurring. Should further

weed infestations be encountered in the future, CMPL will employ species specific management strategies as

outlined in the CSA Mine Weed Management Plan and Handbook.

3.9 Blasting

All blasting and air blasting is confined to the underground mine workings at a depth greater than 1 km. The

mining method adopted at CSA uses bulk emulsion and ANFO initiated by the use of electronic detonation, less

than 500 kg of explosives are consumed per delay. While this method remains in use, no surface monitoring for

vibration is required.

3.10 Operational Noise

Blasting and crushing are the two noisiest operations at the CSA mine site. Both occur more than 700 m

underground and are not audible at the surface. The grinding circuit, adjacent to the concentrator, is the loudest

operation on the mines surface. Various pieces of mobile plant equipment are occasionally used for surface

projects, such as for TSF construction works. Such surface activities are typical operations of a mine site, and

thus do not require noise monitoring. The distance of the CSA mine site from the township of Cobar (11 km)

and from residential properties on surrounding land (minimum 3 km) contributes to a lack of operational noise

complaints.

3.11 Visual, Stray Light

Stray light pollution does not impact on surrounding neighbours due to lighted area on surface being restricted

to a small operational area, and the location of the mine over 3 km from the nearest residence and 11 km from

the township of Cobar. CMPL has never received a complaint in regard to light, and as such has no impetus to

amend current practices.

CMPL 2011 AEMR

79

3.12 Aboriginal Heritage

CMPL mining leases are on Western Lands Lease land on which Native Title has been extinguished. The CSA

Mine is located on the traditional homelands of the Ngiyampaa people. This land is of cultural, economic and

spiritual importance to the Ngiyampaa people, and many Elders still hold a deep interest in cultural matters. Any

potential disturbance is therefore carefully considered and agreed upon by all relevant parties prior to works

commencing.

CMPL is committed to maintaining good relations with all external stakeholders. Any aboriginal archaeological

finds, artefacts or information concerning aboriginal sites that are passed on to the company are appropriately

handled and reported to OEH within reasonable time of being aware of the location or discovery. No aboriginal

place, object or relic is to be disturbed or damaged without the consent or authorisation of the OEH.

CMPL has adopted the NSW Mineral’s Council Due Diligence Code of Practice for the Protection of the

Aboriginal Objects in the assessment of new projects and in all exploration activities undertaken on CML5

during the 2011 reporting. The code outlines a ‘Due Diligence’ process to ensure there is no unintended harm to

Aboriginal artefacts. This process is illustrated in Figure 17.

Ongoing open communication and involvement will be maintained and advice sought from the local aboriginal

community and the regulatory authorities when necessary throughout all future the mining operations.

Figure 17 Due Diligence Process for the Protection of Aboriginal Heritage

CMPL 2011 AEMR

80

3.13 Natural and European Heritage

Heritage items within CML5 are managed according to the relevant legislation and guidelines, namely the three

pieces of legislation governing the conservation of environmental heritage in NSW: the National Parks and

Wildlife Act 1974, the Heritage Act 1977, and the Environmental Planning and Assessment Act 1979. Any

heritage assessments required will be conducted in line with the CSC Local Environmental Plan (LEP).

There are no identified species, habitats or ecosystems within CML5 that require particular attention or

management with regards to natural heritage. No significant geological and physiographical features have been

identified on sites that are not common throughout the district.

European heritage sites on CML5 include:

Mining Quarters

The site of a miner’s quarters which was erected in the 1960’s is located on CML5 approximately 400 m

south-west of the administration building. The site once contained five houses and one swimming pool;

these were removed after mine closure in 1998. The only remaining remnants are the bitumen road, some

cleared areas with stockpiles of topsoil, and some garden beds that continue to grow exotic garden species.

“Eloura”

The “Eloura” site is located 1.5 km from the CSA Mine site. This area shows remnants of old rock

gardens and buildings. It is understood that most of the older buildings were removed during mine

upgrades in the 1950s and 1960s.

CSA Power House

The CSA powerhouse contains five HSF8 Mirrlees diesel engines, manufactured in 1951 by Mirrlees,

Bickerton and Day in Stockport, England. These engines provided the main power supply for CSA Mine

from the early 1960’s, when they were relocated to Cobar from Kempsey, until Cobar was connected to the

State power grid in 1966. The five engines represent excellent examples of medium sized stationary

engines of the mid-20th century and combined with the brush alternators they are an increasingly rare

example of turbocharged technology fitted to diesel engines, a technology previously used to provide

power in rural Australia.

The powerhouse building and engines are not listed on any statutory heritage registers (NSW State Heritage

Register, CSC LEP or the Commonwealth Heritage List). However, recognising their heritage significance

CMPL engaged specialist consultants Godden Mackay Logan (GML) in February 2011 to complete an

archival recording of both the powerhouse and the engines consistent with OEH Guidelines6. The Mirrlees

diesel engines were subsequently placed on the National Trust of NSW Heritage Register in July 2011.

6 NSW Heritage Office, June 1998, How to Prepare Archival Records of Heritage Items, Department of Urban Affairs and Planning, Sydney.

CMPL 2011 AEMR

81

This register however is non-statutory with no legal implications for their conservation or restrictions on

development. The report is provided in Appendix G.

During 2011 CMPL investigated the option of relocating the engines to the Great Cobar Heritage Museum

for display, however, CSC were unable to commit to the ongoing liability of the display and maintenance

of the engine/s. CMPL plans to retain the Mirrlees Engines in situ within the Powerhouse at CSA Mine for

the foreseeable future. This decision will be reviewed with the progression of the major shaft extension

project which will extend the life of the mine and includes the installation of additional site infrastructure

and a significant increase in personnel on site.

3.14 Spontaneous Combustion

History has shown that there are no items which pose a high direct risk of spontaneous combustion at the CSA

Mine. Two minor incidents have been recorded since reopening the CSA in 1999. Both incidents occurred on

surface and involved smouldering Cu concentrate at the mill. Mineralogical assessment of the concentrate at the

time failed to identify any contributing factors for these incidents. Whilst some CSA Cu concentrate has shown

signs of spontaneous combustion, it is considered a minor risk, and is easily prevented by regular hosing down,

clean-up and stockpile management including stock rotation.

3.15 Bushfire

No fires have been recorded on site in the past and as a result of the prolonged drought and minimal

groundcover, the current threat is quite low. To reduce the risk of fire, firebreaks are regularly maintained

around the perimeter of the operational and infrastructure areas. No open fires are permitted on site for land

clearing or fire breaks, except in accordance with a bush fire hazard reduction certificate issued by local council.

All total fire bans are observed. Hot work permits are mandatory on site for all work performed outside

workshops (and other designated areas) that could generate a flame, fire, heat or sparks. This could include (but

not limited to) welding, soldering, thermal cutting/heating, grinding, use of electric power tools or lighting fires

All on-site staff are inducted and educated on the dangers of fire. They are trained in the location and correct use

of fire extinguishers and hydrants in their work areas. The Cobar Rural Fire Brigade is situated on the north side

of town and can be at the CSA mine site within 15 minutes to respond to any surface vegetation fire. The CMPL

Mine Rescue Team is equipped and trained to assist in the event of bushfires on/near the mining lease.

3.16 Mine Subsidence

The CSA Mine subsidence zone is located over 1 km from the current stoping and development activities.

Subsidence occurred prior to the CMPLs operation of the mine; hence the area is excised from the mining lease.

It is very unlikely that there will be another failure through to the surface due to the current mining operation

being significantly deeper in the mine and much more advanced in the mining technique and ground support

used today. The only open void of concern is located underground at 4 Level just off the main decline. This

underground stope has been open for approximately 20 years and is monitored periodically. There have been no

changes to the void recorded during the past 10 years.

CMPL 2011 AEMR

82

The current backfilling method is a combination of CHF and waste rock fill (WRF). The methodology is to fill

all voids created by stope extraction. Stope voids which are going to be exposed again by the stope extraction

activities adjacent to them are filled by placing a 10-15 m high 10% CHF ‘plug’ in the bottom of the void and

then filling the remaining void with 2-4% CHF depending on the geometry of the stope void. If only one side of

the stope void is to be exposed by the next stope then WRF can be placed in the non-exposed side of the void

creating what is termed co-disposal. Stope voids which are not going to be exposed are filled with a 10-15 m

high 10% CHF ‘plug’ followed by WRF. The top down mining method used at the CSA mine requires that a 10-

15 m 10% CHF plug be placed at the bottom of stope voids to allow development back through the bottom of the

stopes for the extraction of the stopes below. If there are no stopes planned below a stope void then the void is

completely WRF.

Given these backfilling methods, it is considered that the likelihood of any underground voids collapsing and

propagating to the surface is extremely unlikely.

3.17 Hydrocarbon Contamination

Hydrocarbon storage, handling and disposal are carried out in accordance with the CMPL Chemical and

Hydrocarbon Storage and Disposal Procedure (PRO-159) developed in compliance with all relevant Dangerous

Goods legislation, WorkCover Codes of Practice, and applicable Australian Standards.

Spill kits are available at various locations around the site and staff and contractors are trained in the use of such

kits during site inductions. Hydrocarbon contaminated soils are removed and disposed of in the TSF. This is a

rare occurrence on site as all fuel and oil tanks on site are bunded.

3.18 Methane Drainage / Ventilation

Deep exploration diamond drilling within the underground mine occasionally encounters a flammable gas

mixture comprising hydrogen (approximately 80%) and methane (approximately 20%). Such occurrences are

rare, short term and of a very small magnitude. Gas levels are generally undetectable or at trace levels when

measured in the exhaust airway. The very minimal amounts of gas that may occur in the mine are released with

all other underground air via the Main RAW on surface. These releases are highly unlikely to have any

reportable detrimental effect on the environment, if any at all, due to the minuscule levels encountered.

All localised and short term safety implications at the CSA Mine site are managed as per the CMPL

Underground Flammable Gas Management Plan (MHP-003).

Ventilation in the underground mine is managed through the Mine Ventilation System. This system circulates

fresh air through the underground workings in order to:

Supply breathable, oxygenated air to underground personnel;

Remove dust, fumes, toxic and flammable gases from the underground environment (through return air

ways) and cool working areas by removing heat emitted by the surrounding rock and diesel equipment.

CMPL 2011 AEMR

83

3.19 Public Safety

The CSA Mine site is clearly signposted on the main access road and is fenced to prevent accidental entry. The

main entry area is subject to high security gates and an electronic tag entry system. CMPL ensures all activities

permitted on the lease do not interfere with or damage fences and that all gates within the lease areas are closed

or left open in accordance with the requirements of the landholder. The boundary fences are signposted and

monitored regularly for damage or any sign of intrusion. A perimeter inspection of the site is carried out on a

monthly basis.

All persons entering the site must undergo a site induction. Employees and contractors complete (at a minimum)

a general surface induction, with additional inductions also completed for specific work areas (e.g.

underground). All visitors, delivery drivers or short term contractors are inducted through the CMPL visitor

induction program. They are required to conform to site PPE requirements and are accompanied on site at all

times by a fully inducted CMPL or contracted employee.

3.20 Other Issues and Risks

3.20.1 NSW Dam Safety Committee Surveillance Report

Tailings Dam Surveillance Inspection reports are completed annually by qualified Dam Engineers (Golder

Associates) for submission to the NSW Dam Safety Committee (DCS). In 2011 the Surveillance Inspection took

place on the 15 February 2011 and the Annual Inspection Report was finalised for submission to the DSC in

June 2011. A copy of the full report is attached as Appendix H. A letter of acceptance of the Surveillance

Report and the proposed remediation actions was issued by the DSC in June 2011. The next annual inspection is

scheduled for February 2012.

The 2011 Surveillance Report includes 17 recommendations, listed below along with an update on works

commissioned:

1. Establish trigger levels for the new piezometers installed along the crest of the STSF perimeter

embankment:

Piezometers P51 to P57 were installed in February 2011 to monitor any changes in the phreatic surface of

the newly constructed perimeter embankment. The final construction depths and details of these

piezometers were reviewed by the Golder dam engineers and the recommended trigger levels were

determined. These are now integrated into the existing monthly monitoring program as detailed in Section

3.4.1.

2. Erosion protection should be placed on the slope at the junction between the deposition causeway and the

new perimeter embankment:

Erosion protection, including geotextile material, was placed on the slope of the junction between the

deposition causeway and the new perimeter embankment in May 2011. Ongoing monitoring of erosion has

CMPL 2011 AEMR

84

revealed the protection has withstood the 279 mm of rainfall which fell on the dam from May to December

2011.

Erosion Protection at the Junction of the Deposition Causeway and the New Perimeter Embankment

3. Erosion protection should be placed over the gully that has formed on the slope near the crest of the

intermediate berm at the STSF east embankment:

Erosion protection was placed over this area on 30 April 2011. Monitoring results to date indicate these

works are withstanding further erosion damage.

4. Future causeway raises should be constructed by placing rock fill in layers of maximum 400 mm thickness.

This should limit seepage through the causeway, the development of cracks on the causeway crest and the

potential for slumping of the slopes. The cracks on the current causeway should be managed by placement

of a rock fill or tailings buttress against each slope. Cracks should be continually monitored during the

daily inspections, and vehicular access should continue to be prohibited onto the causeway until buttressing

works are complete:

Repair works to the causeway were completed 30 April 2011 with additional rock fill material placed with a

dozer and roller. Monitoring for erosion has shown the repair works were successful, although vehicle

access is still limited as a precautionary measure. Daily monitoring will continue in 2012 and all future

causeway raises will be undertaken in accordance with the recommended construction method.

Repair Works to Causeway

5. Hairline cracks on the STSF and STSFE spillways should be repaired by a suitably experienced contractor:

These works were completed in March 2011. No further issues have been observed since.

CMPL 2011 AEMR

85

6. Further separation movement of concrete panels on the STSF western spillway should be managed by

bolting steel straps across the separation cracks and joints. This should be undertaken by a suitably

experienced contractor:

A proposal and quotation for repair works was obtained 21 March 2011. Details of the proposed repairs

and approach were forwarded to the Golder Dam Engineers for comment on the suggested actions. CMPL

had a contractor arranged to complete these remediation works in July 2011. Unfortunately this work has

been delayed due to extended periods of excess water in the dam (preventing access to the base of the

spillway) and unavailability of contractors. This work will be re-quoted and completed in 2012 as soon as a

suitably qualified contractor is available.

7. The large tree at the rock fill buttress over the old penstock should be removed and the remnant hole

backfilled with compacted clay rich soil. This should be undertaken prior to proposed slope reshaping

works:

The tree was removed from the rock fill buttress at the old penstock and the hole was backfilled as

recommended on 30 April 2011.

8. Erosion protection should be placed over the gully that has formed at the south east corner of the rock fill

buttress over the old penstock:

This work was completed by an earthmoving contractor in August 2011. No further issues have been

detected during the weekly monitoring of this site.

9. Reinstatement of Operational Freeboard along the northern embankment of the STSFE. This should be

undertaken by initially spreading the tailings bund formed along the inside edge and then placing a thin

layer of rock fill over the embankment crest to provide the minimum 300 mm freeboard:

The tailings bund was pushed in with a scraper before a layer of clean rock fill was placed around the

perimeter to reinstate the operational freeboard. The works were completed 30 May 2011.

10. The tailings mound formed by excavation of the drain along the south west embankment of the STSFE

should be spread over the tailings surface or removed:

The recommended works were completed 30 May 2011 and a layer of rock armouring was also placed to

provide erosion protection and improve freeboard.

Works at the South West Embankment of the STSF

CMPL 2011 AEMR

86

11. Accumulated sediment on the floor of the stormwater pond should be monitored. Based on the current

accumulation and the risk of damaging the geo-membrane, clean out works are not currently considered

necessary:

Monitoring of the material in the base of this dam was undertaken throughout 2011 and will continue in

2012. Clean up options will be investigated in consultation with qualified Dam Engineers when deemed

necessary.

12. Tailings deposited on the floor of the lined compartment of the Decant Dam should also be monitored.

Clean out works are not currently considered necessary:

Options for removing the built up tailings material in the base of the lined decant pond were investigated in

April 2011 and deemed not viable (cost and practicalities of carrying out the task without creating greater

issues with torn geo-membrane). The tailings material in the base of this dam will continue to be monitored

in 2012 and alternative clean up options will be investigated when deemed necessary.

13. Holes in the geo-membrane of the lined compartment of the Decant Dam should be repaired. This should

be done during a dry period:

Repair works were completed 2nd

May 2011 by an experienced contractor. No further issues have been

reported since.

Repair of Geomembrane Holes at the Decant Dam

14. Erosion protection should be placed over the gully that has formed in the north west corner of the central

unlined compartment of the Decant Dam. This should be done during a dry period:

Clean rock fill material was placed in the north west corner of the central unlined decant dam to provide

erosion protection. This work was completed in April 2011 in conjunction with the construction of a new

spillway between this unlined compartment and the new additional decant dam adjacent.

15. Decommission Survey Beacon numbers 11 and 12. Establish new Survey Beacons along the crest of the new

STST perimeter embankment:

Upon installing new survey beacons around the newly constructed perimeter embankment (as per advice

from the dam engineers), survey beacons 11 and 12 were decommissioned and removed from the

monitoring program.

16. Improve bunding around tailings delivery pipes at north west corner of the STSFE:

CMPL 2011 AEMR

87

These bunding improvements were completed in July 2011 by an earthworks contractor.

17. Review survey of Booster Station area and design and implement drainage system to manage water in this

area:

This work is in progress following the survey of the Booster Station surrounding area in May 2011.

Drainage options are to be determined in discussion with the Golder Dam Engineers as part of the current

Life of Mine design for the site. This will ensure any drainage plans are consistent with future modifications

to the tailings storage perimeter embankments.

The next Annual STSF Surveillance Inspection is due on the 24 January 2012 by the Golders Dam Engineers.

3.20.2 Annual Return

The CMPL 2010-2011 Annual Return was submitted to the EPA in July 2011. For the sixth consecutive year the

CSA Mine had no EPL non-compliances. A copy of the Annual Return in provided in Appendix I.

3.20.3 Environmental Incidents

CMPL maintains a detailed internal incident database for the recording of all incidents reported on site. All

CMPL employees and contractors are trained in incident reporting as part of the site induction program. An

online event report must be submitted for any unplanned incident or event that occurs at the CSA Mine. This

includes environmental incidents, as well as any personal injury, property loss or damage, hazards and near

misses.

CMPL use the online database internal event management system InControl INX. This is an effective form of

communicating any issues or incidents on site. The degree of reporting is much greater than is statutorily

required, the general culture at the CSA to report everything is preferred over under reporting. The majority of

environmental incidents generally involve leaks and spills, which are reported regardless of whether they are

contained in a bund or not, and regardless of the material spilt (e.g. tailings, process water, backfill).

Major incidents that occur on site and therefore require notification to the Environmental Pollution Hotline

(EPA) are those involving the death or injury to fauna on or associated with the TSF, and/or incidents causing or

threatening material harm to the environment. In the event of such an incident, the EPA is notified verbally

within 24 hours, and by written report within 7 days, of the incident occurring. During 2011 four EPA

reportable incidents occurred, all related to kangaroo miring’s in the STSF.

Overall there was a rise in fauna deaths from 2010 (5) to 2011 (7). Two of these incidents resulted from bats

becoming entangled in a fence and a belt. One incident involved the drowning of a goat after it became stuck in

a sump whilst attempting to access water, and four were considered reportable incidents involving the death of a

kangaroo in the TSF. Verbal and written reports were provided as per CMPLs EPL requirements to the OEH

(EPA).

CMPL 2011 AEMR

88

There was a significant decrease in the number of incidents involving backfill spills in 2011 (1) from 2010 (7).

This was largely due to improvement works at the facility and the implementation of improved backfill

operational monitoring procedures in 2011. Further detail is provided in Section 2.10.

The number of incidents of tailings spills increased significantly from 2010 (3) to 2011 (9). Five of these

incidents occurred at the Tailings Booster Hopper at the TSF. As a result of reoccurring incidents the booster

hopper containment pond was upgraded in June 2011 to improve its containment capacity and improve access.

Furthermore procedures relating to the operation of the hopper were reviewed and an environmental training

package was rolled out to members of the Ore Processing Team in June 2011. The training emphasised the need

to implement procedures reducing and minimising the risk of spills of tailings and other contaminated

substances. The number of spills decreased towards the end of 2011. A significant improvement is therefore

expected in 2012.

Figure provides a comparison of incidents occurring in 2010 and 2011. Table 28 provides information on all

environmental incidents occurring at CSA in 2011.

Figure 22 CMPL Environmental Incidents by Type 2010 and 2011

89

Table 28 CSA Environmental Incidents 2011

Incident # Date Details Corrective Actions

502609

(Risk: Low) 9/01/2011

Hydrocarbon

spill

Fuel tank overflowed at the underground workshop8960 fuel bay whilst fuel was being sent

underground.

The system was immediately isolated and was later repaired. The correct procedure for the task was

communicated to be implemented.

502670

(Risk: Low) 21/01/2011 Tailings Spill

The booster hopper at the TSF overflowed following a loss of power. Tailings overflowed the bund and

entered the containment pond. Tailings were redirected while power was restored to the hopper.

The containment pond was cleaned out once the tailings material had sufficiently dried out.

502672

(Risk: Low) 23/01/2011

Hydrocarbon

Spill

The fuel valve at the 8960 fuel bay was stuck and 2.5 L of diesel was spilt into the containment bund. Diesel was pumped from the containment bund into appropriate waste receptacles. The fuel valve was

immediately isolated and later repaired.

502685

(Risk: Low) 24/01/2011 Fauna Death

A bat was found dead on the fence of the Stormwater Catchment Dam at the base of the STSFE. The

bat appears to have become tangled on the fence after landing to sleep/rest.

The incident is so far an isolated case and is monitored for any further related incidents.

502833

(Risk: Low) 24/02/2011 Tailings Spill

The tailings booster hopper at the TSF overflowed as a result of the pump dump flap coming loose.

Tailings escaped from the bund via a hole into the overflow pond. Tailings were pumped out of the

bund.

The hole in the bund was repaired and sealed. The bund overflow pond was cleaned out to maintain capacity for

any potential spills in the future. Systems and procedures at the tailings Booster Hooper to be investigated to

prevent further spills.

502857

(Risk: Low) 25/02/2011 Fauna Death

A dead goat was found in the overflow sump at the back of the explosives contractors’ yard. The goat

appears to have fallen into the concrete sump and drowned as it was full of water after recent rainfall.

The goat was removed from the sump and appropriately disposed of. The sump was covered with mesh to prevent

future access to fauna seeking water.

502939

(Risk: Low) 18/03/2011 Fauna Injury

Two birds were found trapped in the inlet of the residue pit clean up motors. The birds were freed and

taken from the mill and placed on the ground. Once on the ground the birds flew away unassisted

however it was noticed that the legs on both birds had been injured.

The feasibility of placing a cover over the inlet fan to limit bird access was investigated. It was determined not to

be necessary given the low probably of the incident occurring again.

503051

(Risk: Low) 15/04/2011 Fauna Death

A deceased kangaroo was found bogged in the STSF during a routine inspection. The kangaroo

appeared to have become stuck in the wet slurry as a result of recent tailings deposition.

The kangaroo was pulled from the wet slurry and on retrieval the animal was found to be deceased. The incident

was reported verbally to the EPA Pollution Hotline within 24 hours, however due to computer network difficulties

it was advised to call back within business hours. The incident was reported on the next working day (incident no.

128161) and followed up by a written report within 7 days on 20/04/2011.

503114

(Risk: Low) 1/05/2011

Hydrocarbon

Spill

A delivery driver was crossing the Railway line adjacent to the Ore Processing Plant when the fuel tank

of the truck struck the concrete ramp causing it to rupture and spill approximately 300 L of diesel.

The spill was contained using absorbent spill booms and pads. The spill was cleaned up using designated

absorbent material which was disposed of in accordance with waste management procedures.

503194

(Risk: Low) 25/05/2011 Tailings Spill

When the tailings line to the QTS north bore hole was broken to be flushed approximately 200 L of

tailings was spilled. The tailings material overflowed the containment bund and spilt into the

surrounding area outside the bund.

Once dried, the spilt tailings material was scraped up and appropriately disposed of.

503193

(Risk: Low) 26/05/2011 Tailings Spill

Tailings material spilled outside the tailings booster hopper at the TSF. On identification of the spill, tailings were redirected from the hopper. An investigation concluded that the tailings

line had become blocked and caused the spill. The tailings line was flushed to clear the blockage. Once dried the

tailings material was cleaned up and disposed appropriately in the TSF.

503236

(Risk: Low) 8/06/2011 Cement Spill

To remove a blockage (build-up of cement) within the cement silo, the remaining cement in the silo

was released onto the ground within the bunded area. During the release a thin layer of cement dust was

blown onto the roadway.

Immediate action was taken to clean up the cement spillage within the bund and roadway to prevent further

contamination. Depositional dust monitoring did not return results above EPA limits.

503308

(Risk: Low) 29/06/2011 Fauna Death

During a routine TSF inspection, a kangaroo was found drowned in the STSF by an operator. The

kangaroo appeared to have become stuck in the wet slurry as a result of recent tailings deposition. As

the kangaroo had already drowned it was left in the tailings dam.

The incident was reported verbally to the EPA Pollution Hotline within 24 hours (report # 129552). Written

notification was provided to the OEH within 7 days on 4/7/2011.

503314

(Risk: Low) 1/07/2011 Tailings Spill

A small volume of tailings was spilt during test work on newly installed air actuated valves to the

tailings recycle line. The spill was caused by a failing of the valve fitting.

The union of the valve fitting was adjusted and the leak stopped. The spill was cleaned up by shovelling up the

small amount of tails outside the pipe bunding back inside the bund.

503341

(Risk: Low) 9/07/2011 Fauna Injury

A goat was found on a ledge in the decline attempting to get out. The goat appeared to have an injured

leg.

The goat was removed from the ledge and collected by the CMPL Goat Contractor.

503355

(Risk: Low) 14/07/2011 Fauna Death

A routine inspection on the air pump at the QTS South Bore Hole identified a dead bat caught in the

belt of the pump.

The deceased bat was removed. Given the small inlet to the pump and the low probability of this event occurring,

no further action was deemed necessary.

CMPL 2011 AEMR

90

Incident # Date Details Corrective Actions

503359

(Risk: Low) 14/07/2011 Tailings Spill

While unbogging the QTS south backfill line between the primary and booster hoppers, tailings was

spilt outside the bunded area.

Contaminated material once dried was collected and disposed of at the TSF.

503392

(Risk: Low) 22/07/2011 Tailings Spill

Tailings booster hopper overflowed due to pour points blocking. The pour pointes were unblocked. Procedures and regular flushing of pour points have been reviewed and regular flushing is to take place to prevent

bogging of the tailings line. The booster hopper containment pond has been upgraded to better capture spills and

improve access.

503398

(Risk: Low) 24/07/2011 Backfill Spill

Approximately 50 L of backfill was spilled on the surface from the backfill line going underground.

The spill was and contained within bunds.

The backfill plant was shut down immediately. An investigation found the spill was caused by the deterioration of

plastic lining and steel casing of the pipes. Works have begun to drill a new bore hole.

503454

(Risk: Low) 7/08/2011

Hydrocarbon

Spill

1 L of oil split when two hoses blew on a cement agitator at the underground loading ramp at the

mobile plant lay down area.

The spill was immediately cleaned up with absorbent material and appropriately disposed of.

503709

(Risk: Low) 8/09/2011

Fauna

Miring

2 goats became bogged in the operation water storage dam. The goats were removed from the dam. On inspection the animals were found to have no injuries and were

released.

503730

(Risk

Moderate)

16/09/2011 Tailings Spill

Approximately 500 L of tailings was spilt at the booster hopper when a belt had burnt off the pump

causing the pump to fail. This material was contaminated within the upgraded spillway and containment

pond.

The belt was replaced immediately following incident. Contaminated material was scraped up and disposed of

appropriately.

503789

(Risk: Low) 3/08/2011 Fauna Death

2 kangaroos were found drowned in the STSF during a routine inspection. The kangaroos appeared to

have become stuck in the wet slurry as a result of recent tailings deposition.

The incident was reported verbally to the EPA pollution hotline (ref # 131589) within 24 and followed up with a

written report within 7 days on 05/10/2011.

503991

(Risk: Low) 20/11/2011 Tailings Spill

A spill of tailings occurred at the 150 thickener feed box. The spill breached the containment bund at

the feed box and spilt onto the road and into the borrow pit drain. The spill occurred after an operator

noticed the fines return hopper overflowing and swapped the valves to backfill to the 150 thickener.

The spill was contained and cleaned up. Pumps were checked and lines were corrected.

503971

(Risk: Low) 15/11/2011 Fauna Death

A kangaroo was found drowned in the STSF during a routine inspection. The kangaroo appeared to

have become stuck in the wet slurry as a result of recent tailings deposition.

The incident was reported verbally to the EPA pollution hotline 10:30am 17/11/2011 (ref # 132554) and followed

with a written report 21/11/2011 (i.e.: within 7 days of the incident).

91

4 COMMUNITY RELATIONS

The CSA Mine is an owner operated mine currently employing 349 permanent staff (including apprentices) and

on average 99 contractors. The mine is operated on a 24 hour basis, 365 days a year. The majority of

underground and mill employees do shift work on a four-on four-off roster system, whilst day staff

(management, administration, maintenance) work 5 days per week. The bulk of the CSA workforce lives within

the Cobar Township, contributing a considerable flow on economic benefit to the local community and local

economy.

The CSA Mine apprenticeship scheme continued into 2011 with 10 apprentices employed at the end of the

reporting period. Two apprentices successfully completed their apprenticeships at the end of 2011.

In addition to this program, a number of years ago CMPL provided a scholarship in Mining Engineering to two

local school students. In November 2010 the first of the two students graduated from the University of

Wollongong with a Bachelor Degree in Mining Engineering. He commenced full time employment with CMPL

as a Graduate Mining Engineer at the end of 2010. The second student completed his degree in November 2011

and has since commenced work as a full time Graduate Mining Engineer at CSA Mine. The CSA Mine also

hosts visitors from several universities for vocational work experience and major projects, during 2011 a total of

8 students were employed at the CSA Mine.

CMPL continued its partnership with the University of Tasmania during 2011. A project by a Geology PhD

student titled “Controls on mineralization, including sulphide mineralogy, at the CSA Mine, Cobar NSW”

commenced in 2010 and was continued throughout 2011. The PhD student and the CSA Geology team are

attempting to improve the success rate from drilling within and around the mine and regional exploration. The

main aim of the project is to deliver an enhanced and more predictive model of the CSA Mine via understanding

the controls on mineralization (including the development of an understanding of the spatial variability of

sulphide mineralogy and the dependence of sulphide mineralogy on mineralization controls). The project will

continue in 2012.

4.1 Environmental Complaints

In compliance with the CSA Mine’s EPL conditions, CMPL maintains a 24 hour telephone pollution complaints

line through the CMPL reception switchboard. The phone number is advertised to the local community via the

local newspapers and the White Pages. All environmental complaints are directed to the Health, Safety &

Environment Team, and are recorded as per the CMPL Environmental Complaints Procedure and Record Form.

No complaints were received from the public during 2011.

4.2 Community Liaison

Community support is essential in maintaining the CSA Mine’s future operations in Cobar. To secure ongoing

links with the community, CSA Mine regularly communicates its operational plans to the local community. This

is undertaken through:

Ongoing liaison with CSC;

CMPL 2011 AEMR

92

Providing open and honest feedback to the workforce and contracting companies;

Local newspaper media releases;

Involvement with key community groups and projects.

Examples of CMPL’s involvement in the community are detailed in the following sections.

4.2.1 Expanding Cobar’s Airline Service

CMPL participated as members of a working group with CSC, Peak Gold Mine and Endeavor Mine to establish

a regular air service to and from Cobar. The Cobar community lost its previous airline service in December

2008 after the service provider retired its Cobar to Dubbo route.

The local mines in partnership with CSC were successful in securing Brindabella Airlines to conduct an initial 4

month feasibility trial in September 2010. This resulted in Brindabella Airlines providing return Sydney to

Cobar flights 3 days per week since September 2010 through to September 2011. From October 2011 and

continuing in 2012 the air service flies twice per day Monday to Friday. This service is not only essential to the

local mining industry but it also provides the opportunity to have specialist health professionals service the

Cobar Community on a regular basis.

4.2.2 CSA Mine Rehabilitation Environment Management Plan (REMP) Community

Consultation Meeting

In July 2011 CMPL engaged an external consultant from AECOM to assist in the consultation process for the

development of the first CSA Mine Rehabilitation and Environmental Management Plan (REMP)

To underpin the REMP and consultation process CMPL developed land use objectives with the aim to:

Reach a point where the land can be relinquished in a timely fashion;

Minimise closure costs to CMPL;

Maximise potential return on the land;

Minimise environmental impact;

Minimise the risk to public safety to the satisfaction of relevant stakeholders; and

Meet current regulatory requirements (as a minimum).

Following the regulator consultation process, CMPL commissioned AECOM to assist with the engagement of

external stakeholders. The focus of the external stakeholder engagement program was to collect and collate

stakeholder ideas regarding final land use of operational and nonoperational lands owned or managed by CMPL.

To achieve this all stakeholders were informed in writing of CMPL’s intention to develop a REMP, and were

requested to provide comments and suggestions regarding the future of the mine. In addition, community

members were invited to a meeting held by CMPL in August 2011 to discuss the future of the mine. Invites were

distributed via an advertisement in the local paper and individual written and verbal invitations to specific

stakeholder groups such as local councillors, the Cobar Business Association, local high and primary schools,

environmental and social groups, local government departments (such as the Western Catchment Management

Authority), local aboriginal groups, other surrounding mines, and rural landholders and neighbours. Stakeholders

in attendance at the meeting included:

CMPL 2011 AEMR

93

Local graziers and residents;

Local Councillor;

President of the Cobar Business Association;

The Cobar media;

CMPL employees; and

Representatives from neighbouring mines (Tritton and Peak Gold Mine).

Key issues that arose from the stakeholder meeting included:

Creation of diversity in employment and training opportunities for youth whereby there are incentives

for them to remain to the Cobar area;

Mitigation of the issue of people travelling out of region to do their shopping by encouraging a variety

of shops and retail outlets;

Enhance tourism to make Cobar a “must see’ location linked to a local icon (e.g. Dubbo has the zoo);

Recognition that Cobar’s geographical isolation is an innate advantage that should be realised and

promoted to relevant industry.

All feedback and suggestions resulting from the consultation described above have been considered in the

preparation for the REMP. The alternative land usage options suggested and discussed by stakeholders are

displayed in Table 29.

Table 29 Land Use Options

Infrastructure Area Lands Impacted by

Mining

Non Operational

Lands

Tailings Storage

Facilities Alter

na

te La

nd

use

Op

tion

s

Training centre

- mining

- other

Gaol Trial plot for

agriculture on

rangelands

Waste disposal

linked to

encapsulation

Defence training facility /

military exercise

Waste disposal facility-

issues to consider

- railway access

- groundwater

consideration

- proximity to

underground mine

Defence training

facility / military

exercise

Research – plant

bioaccumulation

Ammunition production Tourism linked to mining

Abattoir for goats / piggery /

kangaroos / tannery

Car testing ground –

linked to temperatures

and dirt roads Ethical slaughter of stock

Commercial forestry - milling

Power station – solar /

geothermal / link to availability

of flat land, power, train line,

sealed road

4.2.3 Working with the Cobar High School

In 2011 CMPL recruited eight apprentices to start a four year apprenticeship in the field of Mechanical Trades,

Electrical Trades and Metal Fabrication & Welding in 2012. This represents an increase of 5 apprentices from

CMPL 2011 AEMR

94

the intake of 2011. CMPL received 100 applications for the 8 apprenticeships, the majority of which were local

school leavers.

CSA Mine in conjunction with Cobar High School conducted a careers day in 2011 which involved students

from years 10,11 and 12 visiting the Mine site and participating in interactive presentations on the many

different careers they can pursue with the CSA Mine.

CMPL staff from the Environmental, Mining Engineering and Metallurgy Departments also volunteered their

time as supervisors for the Outback Science and Engineering Challenge in May 2011.

CMPL continue to host an annual visit for the Year 9 Geography excursion to the mine, which took place in June

2011. Students learnt how to measure distance and height changes, length and vertical exaggeration on a GPS

by collecting data and drawing a cross sectional diagram of the TSF. The students and teachers were given a site

tour and enjoyed learning about the CSA Mine.

Cobar High School Students Visiting the CSA Mine

4.2.4 Clean Up Australia Day

CMPL participated in the Business Clean Up Australia Day for the sixth consecutive year on 1 March 2011 by

hosting a site wide clean up at the CSA Mine. All employees were encouraged to participate and do their part

for the local environment. Participation was good with 30 volunteers taking 1 ½ hours to clean up target areas

around the mine site, car parks, gardens and surrounding bushland. A BBQ lunch was held following the clean

up to thank all volunteers.

Approximately 60 large garbage bags were filled (including 23 bags of recycling) and 6 ute loads of larger items

such as scrap steel, old pipes, pallets and old drums were collected. All materials were recycled where possible.

General observations included a significant decrease in rubbish in all areas on site and in the bushland

surrounding the car parks and entrance road since the 2010 clean up.

CSA Staff Volunteers Taking Part in Clean Up Australia Day 2011

CMPL 2011 AEMR

95

4.2.5 Central West Mining and Extractive Environment Team (MEET) 2011

CMPL in association with Peak Gold Mine and the Endeavour Mine for the first time hosted the annual MEET

conference in 2011. The two day conference was attended by 35 representatives from mines in the region and

provided the opportunity for employees from mines outside the Cobar region to take a tour of all three Cobar

mines to gain a better understanding of the sites and their issues. The conference presented participants an

excellent opportunity to network and to share ideas, projects and challenges. Presentations were given under the

2011 MEET theme of ‘Sustainable Mining Challenges – Environmental and Community Issues for current

mining in historic areas’.

Participants at the 2011 MEET in Cobar

4.2.6 National Tree Day

The CSA Mine took part in National Tree Day activities on 5 August 2011. Fifteen volunteers representing all

Departments took the opportunity to make a positive contribution to their environment by donning gardening

gloves and taking up shovels. Around 100 native trees and shrubs were planted on a recently prepared

rehabilitation area behind the ore processing plant at the CSA Mine. The day was a great success and all

volunteers enjoyed making a lasting and positive contribution to their work environment as well as the added

health benefits. Volunteers were provided with a healthy lunch as a reward for their efforts. It is hoped this will

become an annual event at the CSA Mine.

CSA Employees taking part in National Tree Day at CSA Mine

4.2.7 National Recycling Week

As part of National Recycle Week (7 – 13 November 2011) the local mines (CSA, Peak and Endeavour) teamed

up with local business ACCESS recycling to set up an electronic waste (e-waste) collection point for local

businesses and residents. It is anticipated that this collection will be arranged annually.

CMPL 2011 AEMR

96

The National Recycle Week campaign also included CMPL attending each local primary and high school to

educate students on the growing e-waste problem, how e-waste could be recycled and the environmental benefits

of doing so. Students assisted in the campaign by creating posters to encourage residents and businesses to

recycle their e-waste. These were displayed in businesses around town.

The campaign collected a total of 8 1,000L pods full of e-waste which was collected by the RED group for

dismantling and recycling in Melbourne.

.

Representatives from ACCESS Recycling, Peak, Endeavour and CSA Mines

Educating Students about the Benefits of Recycling e-waste at Cobar Primary School

4.2.8 Ride to Work Day

A group of 7 CSA Mine employees opted for two wheels instead of four on their journey to work on 12 October

2011 as part of CSA Mine’s participation in the National Ride to Work Day.

Ride to Work participants met up on the edge of town on the Wednesday morning to complete the 15 km

journey. A volunteer support crew travelled with the riders who all successfully arrived at the CSA Mine in

times varying between 25 to 40 minutes. Some employees who were initially daunted by the thought of 15 km

journey were pleasantly surprised with the comparative ease of the ride and aim to do it more often for the

health, cost and environmental benefits.

CMPL 2011 AEMR

97

Ride to Work day is an annual event at the CSA Mine, which aims to encourage more people to park up the car

and take up riding on a more regular basis. CSA employees were part of more than 36,000 people across the

country who took part in the national event.

CSA Employees Taking Part in the 2011 Ride to Work Day

4.2.9 Community Contributions

CMPL contributed $83,000 to the local economy over the 2011 period through awarding employees with Cobar

Quids to be spent in Cobar as part of our Rewards and Recognition program.

CMPL also contributed $36,852 in donations during 2011, the recipients of which are listed in Table 30.

CMPL 2011 AEMR

98

Table 30 CMPL Donation Recipients 2011

Local Community Groups Sporting Organisations

Cobar Show Society – Fireworks Display and

Entertainment

CSC – Donation towards Miner’s Ghost

Festival

Cobar Arts Council – Various donations for

multiple events.

Cobar Business Association – 2011 Cobar

Business Awards

Kubby House Day Care Centre

Cobar Scout and Cubs Group

Copper City Dog Trials

Cobar Community Radio Station

Cobar Rodeo

Cobar Girl Guides

Cobar Theatrical Society

Copper City Men’s Shed

Western Heritage Group

Cobar Mobile Children’s Services

Cobar Memorial Services Women’s Bowling

Club

Cobar Touch Football Association

Local Inter-Mine Challenge - Golf Day

Cobar Rifle Club

Cobar Clay Target Club

Cobar Miners Race Club.

CSA sponsored Basketball competition

Cobar Junior Soccer Club

Cobar Blues Football & Netball Club

Cobar Senior Men’s Swimming Club

Cobar Junior Swimming Club

Cobar Junior Basketball – travel funding

Cobar Junior & Senior Rugby League Club

Cobar Rugby Union Club

Cobar Amateur Pistol Club

Local Schools Charities

Cobar High School – Science & Engineering

Challenge, Annual Presentation Day

Cobar Public School – Spring Fair, Festival of

Instrumental Music & Annual Presentation Day

St Johns Primary School – Annual Bazaar and

Annual Presentation Night

Donation to Keep Australia Beautiful –

Education Program for primary school children

Variety Children’s Charity

Kidney Health Australia

Fundraiser for various local families in need

MS Society

CMPL 2011 AEMR

99

5 REHABILITATION

CMPL Mining Lease conditions state that land disturbed must be rehabilitated to a stable and permanent form

suitable for a subsequent land use that is compatible with the surrounding land and land use requirements.

CSA Mine is currently in the operational stage of mining with most surface disturbance already taken place and

the mine in steady production. All of the planned expansion and upgrade works that are due to take place over

2012 and 2013 at the CSA Mine are simply replacements which will not generate any significant additional

disturbance. The sections below detail what CMPL is doing to ensure the Mining Lease rehabilitation

requirements are met.

5.1 Buildings

Significant clean up works were carried out over 2011 with the removal of a number of redundant buildings and

infrastructure from the surface working areas. An experienced demolition and scrap steel contractor was

commissioned over a 2 month period and removed the following items from site:

Ore Processing Area:

Concentrate thickener;

Old storage tank;

No 4 mill plinth;

Two 7 ft float columns;

Nine empty concentrate containers.

No. 1 Shaft and Winder area:

Old electrical control room – including concrete slabs;

Ventilation fans and motors, ducting and mounting plinth foundations;

Old storage tank;

No 4 mill plinth;

Two 7 ft float columns;

Nine empty concentrate containers;

Two 3.3 kV transformers;

Three winders and ropes.

Powerhouse area:

Six alternator transformers and associated platforms.

5.2 Rehabilitation of Disturbed Land

The total area of the CML5 mining lease is 2,474 ha. Approximately 243 ha of the Mining Lease is currently

subject to disturbance associated with the CSA Mine, 190 ha of which is covered by disturbance associated with

the TSF. The excised areas total approximately 118 ha, thus leaving 125 ha of land requiring rehabilitation by

CMPL 2011 AEMR

100

CMPL prior to mine closure. During 2011 progressive rehabilitation works were carried out on approximately

4.5 ha of land through earthworks, seeding, planting tube stock and the placement of green waste.

5.2.1 Little Mount Brown and Subsidence Area

Rehabilitation works were undertaken at the Little Mount Brown and Subsidence Areas in 2009 to manage the

overland flow of storm water and improve surface stability. The works were designed to ensure the long term

stability of the site hence satisfying performance criteria of landform establishment outlined in CMPL’s

Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report (Appendix K). While this work created a stable landform, past contamination and the limited

growth media present has limited ecosystem development.

Previous attempts at seeding with native grass seeds have not been successful at establishing vegetative cover.

The soil profile at the CSA Mine is typical of ridge areas in the Cobar Peneplain Bioregion with very shallow

soils; bedrock is visibly present on the surface in some areas. Observations of the rocks at this rehabilitation site

reveal discolouring indicating a high metal content. This contamination is likely due to residues from a smelter

which once existed in close proximity to the site and was removed many years ago.

To assist with ecosystem establishment the principles of Land Form Function Analysis (LFA) are utilised to

create a series of patches and inter patches for monitoring. Monitoring of the rehabilitation at Little Mount

Brown and the Old Subsidence Area was undertaken by specialist consultants in September 2011 as part of

CMPL’s annual Rehabilitation Monitoring program. Results are briefly discussed below and in more detail in

Section 5.4.3. The Rehabilitation Monitoring Program Report is available as Appendix J.

Monitoring results revealed both sites reached key performance indicator (KPI) targets set out in the

Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report (Appendix K) for infiltration, stability and nutrient recycling by surface ripping creating

surface roughness. However, the sites fell below target ranges for organic matter, ground cover, as well as

mature and juvenile trees and shrubs. To address these short comings, topsoil and straw was spread across the

site in patches.

Results have been positive with Punty Bush (Senna artemisiodes) shrubs establishing on the site. The

performance of rehabilitation progress will be assessed against KPIs including infiltration, stability, nutrient

recycling, organic matter and ground cover through the rehabilitation monitoring program in 2012.

Little Mount Brown Rehabilitation Area Following Topsoiling and Spreading of Barley Straw

CMPL 2011 AEMR

101

5.2.2 Mill Rehabilitation Area

The area to the south of the mill has a history of contamination due to years of spills and runoff from the mill

draining over the site on its journey to the Borrow Pit Dam. Years of leaching has mobilised the oxidised

materials and redeposited them into the underlying soil surfaces. The site has varied levels of contamination

with precipitates and crusting evident on soil surfaces.

The northern section of this area was rehabilitated in 2008. Works to continue the rehabilitation south toward

the Borrow Pit Dam was undertaken in 2011. Contaminated drainage was first diverted around the site, the area

was then flattened and ripped cross contour to prevent erosion and assist in vegetation establishment.

Performance criteria set out in CMPL’s Rehabilitation Monitoring Methodology and Determination of

Completion Criteria for Rehabilitation Ecosystems report (Appendix K) were used in rehabilitation design.

Native tube stock was planted in July 2011 with limited success. Subsequently soil testing on the site was

conducted to determine the major limitation for vegetation establishment. Results of testing indicated the

following limiting factors:

Low pH (4.1);

Low capacity to potentially form acid;

Concentrations of metals Cu, Pb, As and Zinc and major cations (Ca, Mg, Na) elevated above

background levels;

Organic matter, inorganic nitrogen and reactive phosphorus.

Area Behind Mill Before 2011 Rehabilitation

Area Behind Mill After 2011 Rehabilitation

Further works to establish vegetation at the site will be competed in 2012 including topsoiling. Green waste will

be spread across the site to provide patches for nutrient build up and soil moisture retention with the aim of

forming a suitable growing medium for vegetation establishment. The performance of rehabilitation progress

CMPL 2011 AEMR

102

will be assessed against KPI’s including infiltration, stability, nutrient recycling, organic matter and ground

cover through CMPL’s rehabilitation monitoring program.

5.2.3 STSF Embankment Walls Rehabilitation

Performance criteria as set out in the Rehabilitation Monitoring Methodology and Determination of Completion

Criteria for Rehabilitation Ecosystems report and the STSF Rehabilitation and Closure Plan includes the

establishment of stable slopes less than 17 degrees. Due to the STSF wall lift and excavation of the new Decent

Dam, resources were made available in 2011 for the battering of existing embankments on the STSF which had

slopes greater than 17 degrees.

Once battered, green waste from a local landholder and CSC was placed on the slopes to prevent erosion and

establish a growing medium. The placement of green waste aims to create surface roughness, increasing soil

infiltration and also add organic matter. The embankments were seeded with oats, a fast growing annual cover

crop, to facilitate conditions for further ground cover establishment and shrub growth. The success of the

rehabilitation will be assessed against performance criteria established in the Rehabilitation Monitoring

Methodology and Determination of Completion Criteria for Rehabilitation Ecosystems report and STSF Closure

and Rehabilitation Plan during 2012 rehabilitation monitoring.

Delivery of Green Waste from Local Landholder

STSF Embankment Before and After 2011 Rehabilitation

CMPL 2011 AEMR

103

5.3 Other Infrastructure

5.3.1 Excised Areas

Discussions between the Derelict Mines Coordinator and CMPL continued throughout 2012 with further

progress continuing on the potential NTSF rehabilitation project.

CMPL developed a NTSF Decommissioning Strategy proposal in conjunction with Dam Engineers and

Rehabilitation specialists from Golder Associates during early 2011. This was developed with the intention of

getting the proposed strategy clearly laid out and shows a clear path moving forward with this project. This

proposal was submitted to the Derelict Mines Program (DMP) for consideration on the 13 May 2011.

A response was received from the Divison of Resreouces and Energry (DRE) on 8 September 2011 stating that

the Deparmtent generally concurs with the proposed process for planining the rehabilitation works. It was

considered by DRE that there is potentially significant environmental and financial risks associated with the

project and therefore requires:

A detailed environmental assessment outlining the current status of the facility, and a review of the

available rehabilitation options, including the ‘do nothing’ option;

All proposed partial rehabilitation by CMPL must be planned on the basis that there will be no

government funded assistance for the project;

Inclusion in the decommissioning strategy a provision for mitigation measures, such as the management

of dust generation, erosion, off-site movement of sediment, and seepage;

Develop rehabilitation closure criteria and final land use; and,

Define roles and responsibilities of CMPL and the DMP for monitoring and maintenance.

CMPL and Golders are progressing with these requests and will submit an initial desktop environmental

assessment to DRE in March 2012. The next step will then be a risk workshop with relevant stakeholders, which

will be undertaken to determine if there are any significant issues that need to be addressed and to further

develop the sequence of works required to plan the proposed rehabilitation work.

CMPL will also work with DTIRIS NSW Derelict Mines during 2012 to start planning the rehabilitation of the

excised Big Mount Brown area and the surrounding CSA Mine disturbed land. There is great potential for a

combined rehabilitation project to take place in this area once the old decline spoils and contaminated ore

stockpiles are removed and the area is no longer required for use. It would be ideal for a rehabilitation project to

take place in partnership between CMPL and DTIRIS to ensure desirable and cost effective rehabilitation

outcomes are achieved for both parties. This is a potential project to be considered and discussed in greater

detail during 2012 when all decline stockpiled materials have been removed from the area.

CMPL 2011 AEMR

104

5.4 Rehabilitation Trials and Research

CMPL actively works towards progressive rehabilitation over the operational life of the mine. The rehabilitation

of sections of the mine site as they become available will assist in reducing the long-term closure liability.

Obvious benefits of progressively rehabilitating non-operational areas of the mine include:

Reduction of the overall un-rehabilitated ‘footprint’ of the mine;

Ability to trial various options and demonstrate rehabilitation outcomes well before mine closure;

Reduction of closure costs, and

Reduction of the ‘security bond’ posted with regulatory authorities.

CMPL continues to research, trial and monitor the availability of rehabilitation options. All research

programmes and field trials are planned to extend over several years in order to establish, monitor and modify

them before acceptable outcomes are achieved. It is critical that research and trials are established and

continually monitored so results can be documented and knowledge gained can be incorporated into final mine

closure plans.

5.4.1 Soil Remediation Trials

A soil remediation trial involving two sample sites (east of the old CSA spoils and north of the subsidence area)

commenced in 2005. Within each sample site, three trial plots were prepared, one plot was treated with lime, the

second with “Terra B” (an environmental remediation reagent produced by Virotec) and the third acting as the

control with no additional treatment. After treatment, a lysimeter was placed in the centre of each plot. Water

samples are taken from the lysimeter after periods of heavy rainfall and sent to Virotec for analysis. The aim of

the trial is to determine which treatment, if any, is most successful in the neutralisation of soil pH, and the

binding of metals to reduce bioavailability.

Sampling of trial plots can only occur after significant rainfall events (> 25 mm). Rainfall conditions in 2011 led

to one sample being collected in the 2011 period. The single sample was collected from the Old Smelter site

with “Terra B” treatment. .

Results from previous years suggested that the “Terra B” treatment is meeting expectations to bind bioavailable

metals and maintain a pH suitable for vegetation establishment. The sample of the leachate collected during the

2011 reporting period saw further reductions in metal concentrations and arsenic, cadmium, chromium, Cu,

nickel, lead and mercury concentrations were below ANZECC guidelines.

Monitoring of the trials will continue in 2012 in order to formulate an appropriate soil remediation methodology

that will support a successful revegetation program. The results of these ongoing trials will continue to be

documented in forthcoming AEMR’s and will be analysed in full for detailed consideration as the current MOP

period expiry date approaches.

5.4.2 Tailings Dam Rehabilitation Trials

CMPL commissioned a vegetation trial on the STSF during the 2011 reporting period. The trial is located in the

north west corner of the STSF and is aimed at trialling different methods to successfully establish vegetation on

CMPL 2011 AEMR

105

the Tailings Surface. The results of the trial will provide ongoing feedback into CMPL’s completion criteria for

rehabilitation ecosystems by providing potential methods to achieve identified performance and closure criteria.

Following review of CMPL’s TSF cover designs a store and release cover system was selected largely based on

climatic factors and resources available for rehabilitation. Store and release cover systems are designed to cover

sulphide bearing waste rock which stores moisture during wet periods and releases moisture during dry periods

and are well suited to semi-arid conditions. The function of this design is to limit rainfall infiltration and oxygen

ingress into underlying waste material.

Four cover treatments were selected for the trials on four separate plots. The treatments were selected on their

ability to provide a potential growing medium and their availability on site as a resource for large scale

rehabilitation. These included:

Control (no cover treatment);

Clean topsoil placed on the tailings surface;

Compacted waste rock placed on the tailings surface;

Virotec Terra B Reagent placed on the tailings surface.

Virotec Terra B is a commercially available product used to treat mine wastes including sulphidic mine tailings.

The product is design to permanently neutralise acid and trap trace metals by creating strong ionic bonds

immobilising metals into insoluble non-reactive sediment.

Vegetation species for the trials were selected based on their ability to achieve closure criteria as set out in

CMPL’s Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report and STSF Rehabilitation and Closure Plan whilst maintaining integrity with surrounding

vegetation. On each plot the following species were trialled:

Native tube stock including Bimble Box (Eucalyptus populnea), Punty Bush (Senna artemisiodes)t

Bush (Atriplex hummularia);

Silk Sourgham (Sourgham X. alum Parodi) . This vigorous summer annual was selected to act a cover

crop and provide favourable conditions for the establishment of perennial species;

Native Pasture Seed Mix including Corkscrew Grass (Stipa setacea) and Windmill Grass (Chloris

truncarta).

Initial results have been promising with vigorous growth of the Silk Sorghum on the topsoil covered plots.

Limited growth of Silk Sorghum occurred on the Virotec and waste rock plots. Expectantly, mortality of tree

and shrub species has been high in the control plots with none of the planted tube stock establishing. Tree and

shrubs have successfully established in the topsoil plots, whilst there has been limited establishment in the waste

rock and Virotec Plots.

Rehabilitation on the trial plots will continue to be monitored (including Land Function Analysis (LFA)) in 2012

to assess the performance of cover treatments against STSF Rehabilitation and Closure Criteria and completion

criteria outlined in the CMPL Rehabilitation Monitoring Methodology and Determination of Completion Criteria

for Rehabilitation Ecosystems report (Appendix K). These criteria are used to assess the effectiveness of the

cover treatments.

CMPL 2011 AEMR

106

Growth of Silk Sorghum in Topsoil Cover in October 2011 and December 2011

5.4.3 Analogue Long Term Monitoring Sites

CMPL has two long term analogue monitoring programs conducted on land undisturbed by mining activities on

and surrounding CML5. These two programs were continued in 2011 and are based on widely acknowledged

and accepted methods of analogue sampling in the Western NSW Region: Rangeland Assessment Program

(RAP) and Land Function Analysis (LFA).

The aim of long term analogue monitoring is to provide suitable rehabilitation goals and closure criteria to feed

in to the CSA Rehabilitation Monitoring Methodology and Determination of Completion Criteria for

Rehabilitation Ecosystems report (Appendix K). Analogue monitoring fulfils CMPL’s regulatory requirement to

provide achievable and measureable closure criteria based on local environmental conditions.

Rangeland Assessment Program

CMPL established two Rangeland Assessment Program (RAP) monitoring sites in 2010 in partnership with

the Western Catchment Management Authority (CMA). Monitoring of these sites continued in 2011 by

Catchment Officers from the Western CMA.

The aim of the RAP is to provide objective and quantitative data on the status of the rangelands of NSW

and record changes over time to improve the way rangelands are managed. There are 25 RAP sites in the

Cobar district. Using the RAP model, CMPL can draw on 20 years of data collected in the region and

compare sites of the same range type within the same region and climatic location to the condition of

CMPL rehabilitation monitoring sites.

There are two RAP sites located on undisturbed land in the vicinity of CSA Mine, each representing a final

end land use and broad land systems in the western district of NSW. Land systems in the western district

are largely dependent on their gradient and if they are a run-off (ridge) or run-on area (drainage flat). Ridge

sites are less productive and have shallower topsoil while drainage flats have accumulated nutrients and

tend to have higher productivity. In 2010 under the guidance of Western CMA Officers, two sites were

selected by CSA to best reflect local environmental conditions and account for natural variations to

landscape. CSA 1 is located on a ridge on CMPL owned property ‘Red Tank’ and is characterised by a

CMPL 2011 AEMR

107

sparse ground cover and shrub layer. CSA 2 is located on drainage flat within the Council Regeneration

Zone, a greenbelt surrounding Cobar.

Monitoring of the RAP sites was undertaken by representatives from the Western CMA in December 2011.

A detailed analysis of site conditions including pasture diversity, proportion of perennial and annuals and

ground cover indicated a reduction in ecosystem function corresponding to the drier seasonal conditions.

CSA 2 proved more resilient than CSA 1 in maintaining perennial pasture species despite the drier seasonal

conditions. Understanding seasonal variation is an important component of setting realistic and achievable

closure criteria accounting for the high natural variation experienced in Cobar land systems.

RAP Monitoring at CSA in 2011

Land Function Analysis

DnA Environmental consultants were engaged in 2011 to establish an annual rehabilitation monitoring

program based on the principles of LFA. The annual rehabilitation monitoring program is designed to

provide quantified data from representative reference sites. The data will be used as a benchmark when

assessing rehabilitation outcomes and will therefore assist in measuring compliance with the CMPL

Rehabilitation Monitoring Methodology and Determination of Completion Criteria for Rehabilitation

Ecosystems report (Appendix K).

CMPL aims to create stable rehabilitated landforms that integrate with surrounding landscapes in areas

disturbed by mining. The current planned long term land use is rangeland grazing. Therefore local grazing

areas on lower slopes containing sparse to moderate endemic tree and shrub cover were used as a point of

reference for rehabilitation targets. Three grazed rangeland communities and two ridge reference sites were

established as primary ecological targets.

Three areas of rehabilitation were monitored in 2011 as a part of the annual rehabilitation monitoring

program. These included:

Little Mount Brown (CSA LMB);

CSA Mill;

Old Subsidence Area (CSA OS);

CMPL 2011 AEMR

108

Results of the 2011 LFA Rehabilitation Monitoring are displayed in Table 31. The Rehabilitation

Monitoring Report is provided in Appendix J and can be referred to for further detail on the rehabilitation

monitoring methodology used and the determination of completion criteria for rehabilitated ecosystems.

LFA Monitoring of the CSA Mill, CSA OS and CSA LMB Rehabilitation Sites

109

Table 31 LFA Rehabilitation Monitoring Results 2011

KPI

Rehabilitation Site

Comment CSA

LMB

CSA

OS

CSA

MILL

Stability and Nutrient

Cycling CSA LMB’s stability is derived from cross ripping creating moderate to high surface roughness and increased levels of deposition in comparison to other

sites. Some weak soil crusts developing. CSA MILL had the lowest stability index due to the extent of the inter-patch area combined with increased levels

of erosion and highly unstable soils.

Infiltration

CSA OS had large piles of felled trees and woody debris providing high surface relief in areas. The older age of this site meant soil crusts were more

developed, cryptogams had started to colonise small areas and the soils were generally very hard with low levels of erosion beneath the log piles.

Mature Trees

CSA LMB and CSA OS are relatively immature sites hence no mature trees were recorded. CSA MILL recorded 7 mature trees recorded. These were

retained during rehabilitation works after removal of contaminated soil.

Shrubs and Juvenile Trees

CSA LMB had no shrubs or trees recorded. CSA OS had shrubs which germinated from the topsoil which was sourced from the TSF extension.

CSA MILL had shrubs which regenerated from the surrounding remnant vegetation.

Ground Cover CSA LMB and CSA Mill had low total ground cover values with most cover provided by straw mulch or scattered stones. CSA OS’s majority of cover

attributable to extensive logs piles. Some also provided by dead leaf litter and small occurrences of perennial and annual vegetation and cryptogams.

Native Species Diversity

(per m2)

Note: levels were low in 2 of the 3 grazed reference sites and there were no exotic species in the reference sites. CSA LMB recorded one native shrub and

no exotic species. CSA OS had a large number of herbs and a diversity of tree, shrubs, sub-shrubs and grasses similar to the range of the reference sites.

The only rehabilitation site to contain exotic species. CSA Mill, despite relatively low diversity overall contained similar proportions of species found in the range of reference sites and no exotic species.

Rilling CSA LMB was the only site where riling was recorded with one of the two rills exceeding the minimum value of concern and requiring amelioration.

Soil pH All sites fell well below target levels and were very strongly acidic and require lime remediation

Electrical Conductivity All sites significantly exceeded targets and were highly to extremely saline. This is likely to have implications for plant growth and establishment.

Organic Matter and

Phosphorous All sites has low levels, however this was also reflected in the reference sites.

Nitrates Nitrates were low in the grazed reference site. CSA OS and CSA MILL had particularly high nitrate levels far exceeding the desirable range.

Cation Exchange Capacity

(CEC)

All sites had very high levels exceeding the desirable range. These results may indicate they are likely to have good retention ability and potentially high

soil fertility however due to excessive EC (and nitrates) these are more likely to be related to earlier mining related activities rather than natural

hydrological and agricultural influences.

ESP CSA LMB and CSA OS well below the desirable levels. Results indicate soils at CSA MILL are likely to be sodic.

Metals

All sites had excessively high levels of Sulfur, Zinc, Manganese and Lead. CSA LMB and CSA MILL had excessively high levels of Cu, Silicon, Selenium, Lead and Arsenic. All sites had unusually high levels of Ca, Mg and K likely to be reflected in the high EC and CEC levels recorded at the site.

While some elements slightly elevated in the reference sites (e.g. Iron, Silicon, Lead and Arsenic) those recorded within the rehabilitation areas far

exceeded these and are likely to provide further implications for plant establishment and growth.

Notes:

Indicates characteristic meet key performance indicator targets Indicates characteristic did not meet key performance indicator targets

110

5.5 Further Development of the Final Rehabilitation Plan

In 2011 CMPL engaged consultants AECOM to develop a Rehabilitation and Environmental Management Plan

(REMP) to address commitments made in the 2010 AEMR and support the renewal of the CSA MOP which is

due for renewal at the end of 2012. The purpose of the REMP is to create a framework for mine closure which

has measurable performance and closure criteria to achieve sustainable ecosystem development. The REMP is

due to be finalised in early 2012.

The performance measures and indicators in the REMP are designed to form the basis of the Closure Criteria.

They provide the ability to track progress towards final land use and development of sustainable ecosystems

through a series of conceptual stages shown in Figure 2 and described as:

Stage 1 Decommissioning: Removal, where relevant, of hard stand areas, buildings, contaminated

materials, hazardous materials;

Stage 2 Landform Establishment: Incorporates gradient, slope, aspect, drainage, substrate material

characterisation and morphology;

Stage 3 Growing Media Development: Incorporates physical, chemical and biological components of

the growing media and ameliorants that are used to optimise the potential of the media in terms of the

preferred vegetative cover;

Stage 4 Ecosystem and Land use Establishment: Incorporates operational and non-operational lands,

revegetated lands and habitat augmentation; management and establishment of flora, retained

infrastructure and adjoining predicted land use;

Stage 5 Ecosystem and Land use Sustainability: Incorporates components of floristic structure, nutrient

cycling recruitment and recovery, community structure and function which are the key elements of a

sustainable landscape, together with economic and social impact or benefit.

CMPL 2011 AEMR

111

Figure 23 Conceptual Stages of Sustainable Ecosystem Development

To evaluate the progress of rehabilitation fulfilling long term land use objectives and closure criteria, CMPL

implemented an annual rehabilitation monitoring program as described in Section 5.4.3. Rehabilitation

procedures and completion criteria are updated when required to continually improve rehabilitation standards, as

more data on reference sites or the targeted vegetation community becomes available.

Table 32 and Table 33 summarise rehabilitation occurring in 2011 and proposed for 2012 and an update on the

maintenance activities of rehabilitated land.

CMPL 2011 AEMR

112

Table 32 Summary of Proposed Rehabilitation

A: MINE LEASE AREA

Area Affected/Rehabilitated (hectares)

2010 2011 2012

(estimated)

A1 Mine lease area 2474.1 ha 2474.1 ha 2474.1 ha

B: DISTRTURBED AREA

B1 Infrastructure Area (other disturbed areas to be

rehabilitated at closure including facilities, roads) 9.8 ha 9.8 ha 9.8 ha

B2 Active Mining Area (excluding items B3-B5 below) 115.7 ha 115.7 ha 115.7 ha

B3 Waste Emplacements (active/unshaped/in or out of pit) 0.5 ha 0.5 ha 0.5 ha

B4 Tailings Emplacement (active/unshaped/uncapped) 86.5 ha 86.5 ha 86.5 ha

B5 Shaped Waste Emplacement (awaits for maintenance) 0 ha 0 ha 0 ha

TOTAL ALL DISTURBED AREAS 212.5 ha 212.5 ha 212.5 ha

C REHABILITATION

C1 Total Rehabilitated Area (except for maintenance) 7 ha 4.5 ha 1.6 ha

D REHABILITATION

D1 10 to 18 degrees 0 ha 2.2 ha 0.6 ha

D2 Greater than 18 degrees 0 ha 0 ha 0 ha

E SURFACE OF REHABILITATED LAND

E1 Pasture and grasses 7 ha 4.5 ha 1.6 ha

E2 Native forest/ecosystems 0 ha 0 ha 0 ha

E3 Plantations and crops 0 ha 0 ha 0 ha

E4 Other (include non-vegetative outcomes) 0 ha 0 ha 0 ha

Note:

1. These figures do not include excised areas as they are not the responsibility of CMPL

Table 32 shows nil further disturbance areas were created during 2011 and no further plans to disturb areas in

2012. A total area of 4.5ha was rehabilitated during the reporting period (as detailed in section 5.2) with a further

1.6ha planned for 2012 (mill rehabilitation area). The 0.6 ha increase in 10 to 18 degrees rehabilitation attributes

to the STSF wall embankment (refer to 5.2.3).

CMPL 2011 AEMR

113

Table 33 Maintenance Activities on Rehabilitated Land 2011

Nature of Treatment

Area Treated

(ha) Comment/control strategies/treatment detail

2011 2012

Additional erosion

control works

(drainage and water diversion)

1 0

Drainage improvement earthworks (Section 2.8.3)

completed. De-silting of the Operational Water Dams

was completed in January 2011 with 3,500 m3 removed

to maintain capacity.

Re-covering

(Topsoil and waste rock

stockpiling on surface)

0 0

No further stockpiles are planned for 2012.

Soil treatment

(Continuing trials -lime, virotec

& control plots)

1.5 1.5

Soil remediation trials continue to be monitored. No

further maintenance work was required in 2011 or

anticipated in 2012.

Treatment/Management

(grazing, cropping, slashing etc) 0 0

Nil.

Re-seeding/Replanting 4.5 1.6

Green waste was spread on the STSF embankment walls.

Replanting occurred on the Mill Rehabilitation Area and

the TSF Rehabilitation Trials. Seeding of rehabilitation

areas around the Old Subsidence Area, Little Mount

Brown, STSF embankment and the TSF rehabilitation

trial plots was carried out in 2011.

Further seeding is scheduled for 2012 at the site of the

slag pile once the mines rescue equipment has been

relocated and rehabilitation works completed. Seeding is

also expected at Big Mount Brown Once Rehabilitation

works have been completed (potentially 2012 or 2013).

Adversely Affected by

Weeds 0.1 0.1

Prickly pear infestation at old housing estate was

monitored in 2011 with no spraying deemed necessary.

Minor weeds removed from site.

Feral animal control

(via additional fencing, trapping,

baiting, etc)

2474 2474

Feral Goat removal continued in 2011 over the CML5

mining lease.

CMPL 2011 AEMR

114

6 ACTIVITIES PROPOSED FOR 2012

Key activities CMPL intends to progress in 2012 are listed in Table 34.

Table 34 Proposed activities for 2012

Proposed Activity Priority

Ranking

Scheduled

Completion

Date

Conduct annual TSF Surveillance Inspection by qualified Dam Engineer H 30/01/12

Finalise draft SWMP and submit to DTIRIS and OEH H 30/03/12

Complete a site wide audit of the current piping requirements, remove

redundant pipes and ensure adequate bund capacity is available for all

necessary pipes

H 30/03/12

Address design adequacies in concrete settling bund at the mill including

enlargement of the sump H 30/03/12

Complete remediation works to manage the further separation movement of

concrete panels at the STSF western spillway as recommended in the 2011

TSF Surveillance Inspection Report.

H 30/04/12

Develop and submit a MOP for the 2013 – 2017 period to DTIRIS for

approval. The plan will be developed in accordance with REMP guidelines H 30/06/12

Assess energy usage to determine commitments under EEO. If EEO is

triggered in the 2011-2012 financial year CMPL will fulfil its commitments

by registering by March 2013 and submitting an assessment plan by

December 2013.

H 30/09/12

Investigate alternative backfilling methodologies to optimise the use of waste

rock fill underground and minimise any requirement to hoist waste in the

future

H 31/10/12

Investigate additional dust mitigation measures from the TSF including:

increasing the size, thickness and extent of waste rock emplacement; and

potential chemical treatments

H 31/10/12

Replace tailings thickener H 30/12/12

Complete scoping study to determine the options for introducing a surface

ore stockpile as part of the works associated with the Mill Grinding Circuit

upgrade

H 30/12/12

Complete feasibility study on the use of paste fill in underground operations

and submit MOP amendment if required H 31/12/12

Implementation of new goat control contractor to improve the management

of feral goats M 31/01/12

Consult with OEH to finalise commitments under ESAP including the

submission of a final report M 30/3/12

Progress rehabilitation works at the Mill, Big Mount Brown and old Slag Pile

rehabilitation sites including the spreading of topsoil and seeding M 30/3/12

CMPL 2011 AEMR

115

Proposed Activity Priority

Ranking

Scheduled

Completion

Date

Prioritise and assess the feasibility of energy efficiency projects identified

through the energy assessment and develop an action plan for implementation M 30/04/12

Investigate requirements to manage the Eloura site and determine if it is

within the Mining Lease or CMPL owned property M 31/08/12

Investigate the remaining 4 areas on site suspected of contamination. Data on

the nature and level of contamination of sites will assist in progressive

rehabilitation to meet performance and closure criteria

M 30/09/12

Monitor prickly pear population and assess implement control measures

where required including the possible reintroduction of cochineal infected

segments

M 30/09/12

Address key actions identified in the energy assessment gap analysis to

further develop sustainable energy and carbon management practices M 30/10/12

Continue removing remaining pile of crushed Big Mount Brown

contaminated waste material M 31/12/12

Develop an underground settling and pumping system to allow effective

reuse of recycled water underground M 31/12/12

Liaise with DTIRIS Derelict Mines to further progress the potential for a

NTSF rehabilitation project M 31/12/12

Work with DTIRIS Derelict Mines to plan for the rehabilitation of the

excised Big Mount Brown area and surrounding CSA Mine disturbed land M 31/12/12

Conduct educational campaigns to achieve a recycling rate

consistently greater than 30% M 31/12/12

Progress works to upgrade the grinding circuit in the mill in conjunction with

the ongoing shaft extension project M 31/12/12

Implement fox baiting program in conjunction with surrounding landholders L 31/07/12

CMPL 2011 AEMR

116

7 REFERENCES

Australian and New Zealand Environment and Conservation Council (ANZECC) and

Agriculture and Resource Management Council of Australia and New Zealand (2002)

Australian and New Zealand Guidelines for Fresh and Marine Water Quality, National Water

Quality Management Strategy.

Bureau of Meteorology (2011) Website www.BOM.gov.au. Data accessed 15/01/2012.

Cobar Management Pty Ltd (CMPL) (2007) Mining Operations Plan 2008-2012, December

2007.

Coffey Geosciences Pty Ltd (2005A) CSA Copper Mine Soil Sampling Report. A report

prepared for Cobar Management Pty Ltd, November 2005.

Doos, Stephanie (Oct 2011) A Geophysical and Hydrogeological Approach to Delineating

the Great Chesney Fault, Cobar, NSW. The Australian National University.

DTIRIS (2006) Guidelines to the Mining, Rehabilitation and Environmental Management

Process. EDG03 version 3

DnA (2011) Rehabilitation Monitoring Methodology and Determination of Completion

Criteria for Rehabilitation Ecosystems report.

Department of Primary Industries – Mineral Resources (2006) Environmental

Management Guidelines for Industry: Guidelines to the Mining, Rehabilitation and

Environmental Management Process Version 3.

National Environment Protection Council (1999) National Environmental Protection

Measure for Site Investigations (NEPM) guidelines.

NSW Heritage Office (1998) How to Prepare Archival Records of Heritage Items,

Department of Urban Affairs and Planning, Sydney.

Parsons Brinkerhoff (2006b) Biodiversity Survey and Assessment – CSA Mine Cobar.

December 2006.

Roderick et al (1999) Flora and Fauna Survey, CSA Mine, Cobar.

CMPL 2011 AEMR

117

7.1 Plans

1 Mine Context

2 Land Preparation and Mining Activities

3 Rehabilitation

4 Mining Plan - Vertical Section

5 Site Layout

7.2 Appendices

A Environmental Protection License 1864

B 2010 AEMR Review Meeting Minutes

C Stormwater Drainage Improvement Works Report

D CMPL Environment and Community Policy

E CSA Air and Water Quality Monitoring Data 2011

F Contaminated Sites Sampling Report 2011

G Industrial Heritage Site Listing Report

H STSF Surveillance Report 2010

I 2011 Annual Return EPL 1864

J 2011CSA Rehabilitation Monitoring Report

K Rehabilitation Monitoring Methodology and Determination of Completion Criteria for

Rehabilitation Ecosystems report