Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Purpose
Use this procedure to analyze material costs by cost elements.
Trigger
Perform this transaction when you need to analyze material costs by cost elements.
Menu Path
Use the following SAP Easy Access menu path(s) to begin this transaction:
Transaction code via Command edit field.
Transaction Code
CK84_99_COST_ELEMENT
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
1/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Screen Flow
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
2/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Procedure
1. In SAP, start the transaction using the menu path or transaction code.
SAP Easy Access
2. As required, complete/review the following fields:
Field R/O/C Description
Command R Sequence of characters entered from the keyboard.. The key code enables you to select menu options using the keyboard. To do this, you use characters derived from the menu options. Example: CK84_99_COST_ELEMENT
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
3/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
3. Click the Enter button .
Analyze Itemization: Cost Elements (Grouped)
4. As required, complete/review the following fields:
Field R/O/C Description
Material R The goods that are the subject of business activity. The material can be traded, used in manufacture, consumed, or produced. Example: 66810949
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
4/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Field R/O/C Description
Plant R A plant is an organizational unit for dividing an enterprise according to production, procurement, maintenance, and materials planning. It is a place where materials are produced, or goods and services are provided. Example: 7U11
Costing variant
R Contains all control parameters for costing, including parameters that control how cost estimates are executed and which material prices or activity prices are used to valuate the costing items. Example: PPC1
Costing version
R Method of distinguishing two or more cost estimates for the same material. Example: 1
Costing Date
R Date from which a costing run is valid. Example: 23.01.2009
5. Click the Cost Comp. View drop-down list .
6. Click the Cost of Goods Manufactured list item .
7. Click the Execute button .
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
5/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Cost Elements (Grouped)
8. Click the Exit button .
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
6/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Analyze Itemization: Cost Elements (Grouped)
9. Click the Exit button .
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
7/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Result
You have successfully analyzed material costs by cost elements.
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co
st Element Itemization.udc
8/9
Work Instruction CK84_99_COST_ELEMENT - JPN - Cost Element Itemization
Scenario
Instructions In this simulation you are required to:
Analyze Material Costs by Cost Elements in SAP ECC 6.0.
Required Data
This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.
Field Value
Material 66810949
Plant 7U11
Costing variant PPC1
Costing version 1
Costing Date 23.01.2009
Wednesday, July 15, 2009 CO_CK84_99_COST_ELEMENT_JPN_Co