Change Management Procedure
Global Information Technology
-
8/12/2019 CM Procedures
2/36
Information TechnologyChange Management Process
CHANGE MANAGEMENT............................................................................................ 3
INTRODUCTION ................................................................................................................ 3
OVERVIEW ....................................................................................................................... 3
CHANGE MANAGEMENT OBJECTIVES .............................................................................. 3SCOPE .............................................................................................................................. 4
CHANGE MANAGEMENT PROCESS ........................................................................ 6
GENERAL INFORMATION.................................................................................................. 6
ROLES AND RESPONSIBILITIES ......................................................................................... 7
CHANGE DEFINITION ....................................................................................................... 8CHANGE TYPES................................................................................................................ 9
CHANGE WINDOWS........................................................................................................ 12
RISK ASSESSMENT ......................................................................................................... 12
CR SUBMISSION........................................................................................................... 15
SUBMITTING A CHANGE REQUEST ................................................................................. 15
Requirement .............................................................................................................. 15KEY PROCESS STEPS ...................................................................................................... 16
ACCESSING THE CRTEMPLATE IN MAGIC ..................................................................... 17PROCESS STEPS FOR DOCUMENTING AND SUBMITTING A CHANGE REQUEST ................ 18
SECTION 1...................................................................................................................... 19
Request Number.................................................................................................... 19CR Type ................................................................................................................ 19
Opened .................................................................................................................. 19
Status ID................................................................................................................ 19Group Name.......................................................................................................... 19
SECTION 2...................................................................................................................... 19
Requestor ID ......................................................................................................... 19Sponsor Name....................................................................................................... 19
Phone number ....................................................................................................... 19Requestor Manager ............................................................................................... 19
SECTION 3...................................................................................................................... 20
Start and end time ................................................................................................. 20
Actual.................................................................................................................... 20System................................................................................................................... 20
Platform................................................................................................................. 20
Y/E (Year End) ..................................................................................................... 20Equip /System Affected ........................................................................................ 20
EDI........................................................................................................................ 20Subject ID ............................................................................................................. 20
SECTION 4...................................................................................................................... 21
Business Unit Affected ......................................................................................... 21
Could change affect anything else? ...................................................................... 21Describe the activity ............................................................................................. 21
Backout Plan ......................................................................................................... 21
Dependencies ........................................................................................................ 21
Revised 09/13/04 1
-
8/12/2019 CM Procedures
3/36
Information TechnologyChange Management Process
Impact of not making the change.......................................................................... 21
Validation.............................................................................................................. 21Who will validate, onsite person and phone number............................................ 21
Completion Status................................................................................................. 21
Risk Assessment ................................................................................................... 22
Approver Email Address....................................................................................... 22Who can approve a CR ......................................................................................... 22
Delegation of approval authority .......................................................................... 23
SECTION 5...................................................................................................................... 23Save the CR to Create a Ticket and Route to a Manager for Approval................ 23
Manager and Direct Report of CIO Approval Process......................................... 23
CR Date/Time Change and CR Time Extension .................................................. 23Change the date and/or time of the activity before the CR has been presented at
the meeting............................................................................................................ 23
Change the date and/or time after receiving approval at the meeting, before the
activity has been performed, and the date/time change is before the next weekly
meeting.................................................................................................................. 24Extend the CR while performing the activity ....................................................... 24
SECTION 6...................................................................................................................... 25Contingency Plan in the event Magic is not available.......................................... 25
CR APPROVAL PROCESS .......................................................................................... 26
REQUESTOR MANAGER NOT AVAILABLE TO APPROVE A CR ................... 26
Submitting a CR to a Designated Manager........................................................... 26
RESUBMIT A CHANGE REQUEST TO A MANAGER FOR APPROVAL ......... 26
UNPLANNED AND EMERGENCY CR APPROVAL PROCESS........................... 26
ACCEPTED CHANGES................................................................................................ 27
CHANGE MANAGEMENT MEETING AGENDA.................................................................. 27Change Management Meeting .................................................................................. 27Change Management Meeting Minutes .................................................................... 27CR Implementation and Ticket Closure.................................................................... 27
EXAMPLE COMPLETED CHANGE REQUEST TEMPLATE................................................... 28
APPENDIX B .................................................................................................................. 29
EXAMPLE CHANGE REQUEST HELP DESK TICKET ......................................................... 29
APPENDIX C.................................................................................................................. 30
EXAMPLE EMAILNOTIFICATION SENT TO APPROVING MANAGER................................. 30MANAGER AND DIRECT REPORT OF CIOAPPROVAL PROCESS ...................................... 31
APPENDIX D.................................................................................................................. 33
EXAMPLE EMAILNOTIFICATION SENT TO THE REQUESTOR........................................... 33
APPENDIX E .................................................................................................................. 35
VISIO DIAGRAM OF MAGIC PROCESS ............................................................................. 35
Revised 09/13/04 2
-
8/12/2019 CM Procedures
4/36
Information TechnologyChange Management Process
CHANGE MANAGEMENT
Introduction
This document describes the processes used to plan, coordinate, and implement changesto any production, test or development environment at Mattel, Fisher Price, andAmerican Girl. It includes the roles and responsibilities IT staff members adhere to
ensure that any modification to an environment does not interrupt user production and
environment performance.
All GIT locations operate by this process and adhere to the process guidelines. The
Requestor and Approving Manager assume full responsibility for the scope of the
change.
OverviewChange Management is designed to implement change into the IT environment with
minimal disruption of service.. This includes changes in technology, tools, systems, andhardware. Change Management defines the documentation, processes, roles and
responsibilities necessary to plan for and implement change.
One of the key elements of Change Management is to ensure that IT staff, users and
business units are aware of the change and understand the effect a change will have on
any environment. Since many systems are dependent on others communication of
pending changes is an essential step to identify and eliminate any risk associated to otherenvironments.
The documentation and approvals process required are not intended to discourage change
but to encourage planning and consideration of the impact of the changes.
Change Management Objectives
The objectives of Change Management include:
Control, manage, and monitor the change process.
Communicate the activity.
Plan the implementation. Communicate a backout process.
Ensure proper authorization has been received for each change
Focus on impact, assessment, and feasibility of implementing changes
Establish each participants role and area of responsibility
Manage and coordinate all changes with potential to impact the productionenvironment and minimize disruptions to customers and production systems.
Revised 09/13/04 3
-
8/12/2019 CM Procedures
5/36
Information TechnologyChange Management Process
Fast Track the approval process for low impact and development and testenvironment changes and changes that will not result in system downtime, loss in
user productivity, limited user access to an application, or have significant impactto a projects timeline.
Eliminate the number of change back-outs caused by ineffective change planning
or implementation Provide proper notification of change activities.
Ensure that proper authorization has been received prior to implementation ofproduction Change Requests
Ensure that any possible interruption to the production environment is minimized
Ensure (and enforce) that everyone adheres to the Change Management process
Hold weekly Change Management meetings to ensure that GIT and managementare aware of and in agreement with all Change Requests.
Discuss unsuccessful CRs during the weekly Change Management meeting toreview cause of failure and production impact.
Provide an audit trail of all changes
Consolidation of changes where possible.
Scope
The following is a guideline to help determine the types of changes, which areconsidered a change to the production environment. This is not an all-inclusive list.
Technical
System software installations related to new versions, releases, or modification
levels System software maintenance which provides new functionality or resolution of
known or potential problems
Parameters which control the operation of any software product
Database software installations related to new versions, releases, or upgrades
Major security / access changes
Database re-organizations
IPLs/reboots
Desktop Management Services
LAN file servers and storage devices Network operating systems
LAN database, FAX, and mail servers
Global changes to PC operating system software
Communication servers
Application software residing on each file server
Revised 09/13/04 4
-
8/12/2019 CM Procedures
6/36
Information TechnologyChange Management Process
Telecommunications
Network software changes, maintenance fixes, or new software releases
Network hardware moves, additions, or changes
Network reconfigurations
Network hardware upgrades Router reloads or restarts
Voice software fixes, enhancements or installation of new products
Voice hardware or software upgrades
Connectivity devices such as intelligent hubs, switches, routers and multiplexors
Global changes and changes that affect critical resources to wiring facilities whichprovide for data transport
Facilities Changes
Cabling
UPS modifications maintenance Building modifications
Remote control changes
Building Power and anything that could affect service
Application Services
Changes to add, remove, or change functionality of any production applicationsystem or package. This encompasses changes to jobs, procedures, programs,
recovery instructions, and production schedules
Any data conversion, data load or implementation process(es) that may impactany aspect of the production environment or users
Database Stored procedures
Revised 09/13/04 5
-
8/12/2019 CM Procedures
7/36
Information TechnologyChange Management Process
Change Management Process
General Information
1 Changes that result in database modifications, system downtime, loss in userproductivity, limited user access to an application, have significant impact to a
project timeline require a 5 working days lead time prior to the date of the
activity. All Change Requests and associated documentation must have theopportunity to be discussed at the weekly Change Management meeting.
2 Change Requests must be received in the Magic Change Request queue withappropriate approval prior to the close of business Monday to be included on the
Wednesday meeting agenda.
3 Change Requests received after 17:00 (5PM PST) and scheduled before thefollowing weeks meeting would be considered Unplanned and would need aCIOs direct report approval.
4 If Monday is a holiday then Change Requests submitted by 13:00 (1:00 PM PST)Tuesday to be included on the Wednesday meeting agenda.
5 The Change Management Meeting Agenda will be distributed on Mondayevening. If Monday is a holiday the agenda will be published Tuesday evening.
6 Change Management meetings are held each Wednesday at 8:00 AM PST (11:00AM EST).
7 The Change Management Coordinator is the on-duty PTC supervisor. The HelpDesk Manager is the process administrator.
8 In the event of an Emergency Change Request, or an Unplanned Change Request,authorization from any of the CIOs direct reports is required.
9 Emergency Change Requests are submitted for approval as the result of a SEV 1event. A change can be declared an emergency when immediate repair servicesare required to a production environment and a Severity1 trouble ticket is opened
in MHD.
10 Unplanned and Emeregency Change Requests must be approved by a direct reportof the CIO.
Revised 09/13/04 6
-
8/12/2019 CM Procedures
8/36
Information TechnologyChange Management Process
Roles and Responsibil itiesRole and Responsibility Tasks
TheSponsor is the customer who
requested the change. Communicates requirements to Change Requester.
Verifies the change was implemented per their request
The Change Requesteris responsible
for preparing the change for
implementation and is responsible for
the success of the change. A customer,
vendor or supplier can initiate a change,
but GIT personnel must submit all
change requests.
Ensures the changes are fully documented before submitting the request
for review
Ensures the impact of the change is fully understood by support groups
and by the Change Coordinator
Attends the weekly Change Management meeting to answer any inquiries
about the changes as required
Coordinates any client testing as required
Ensures the Change Coordinator is involved in any change planning
process
Drafts customer notification to ensure customers are notified of approved
changes and/or outages
All CRs are required to include detailed back-out/contingency informationwhich is available for customer review
Upon completion, notifies the Sponsor that the change was completed
Verifies with the Sponsor that the change was implemented to their
satisfaction
Documents the results and closes the ticket
Does not implement any change without following proper procedures
The Change Coordinator ensures the
change management process functions
smoothly and efficiently.
Facilitates the weekly Change Management meeting
Takes responsibility for ensuring timely approval of all changes from
support groups
The Change Implementeris the
person or group (Production Control
Group) that executes the change.
Receives, reviews, and understands the change request to be implemented
Adheres to the dates and activities of the implementation schedule
Executes back-out and fall-back procedures for responsible components,when required
Documents any events that happen during change implementation
Works with the Help Desk to create any problem tickets related to the
change and notes them in the Change Request entry
Notifies the Change Requester after the change has been implemented
Revised 09/13/04 7
-
8/12/2019 CM Procedures
9/36
Information TechnologyChange Management Process
Change Defini tion
Change - Any modification or addition to the production environment that is not a
routine task. Most changes will go through the process with the Change Coordinator as
the decision-maker on borderline cases.
Examples of typical Changes that are not considered production environmentchanges:
Addition of a new electronic mail user
Routine security updates
Password resets
Report Distribution changes
Desktop Changes (except for major installations, i.e. a new release of theoperating system)
Changes to test or development systems
Web application changes that do not modify the database
Web application changes that affect presentation only and involve HTML or ASPchanges that result in a content change, they do not go through the CR process.
Revised 09/13/04 8
-
8/12/2019 CM Procedures
10/36
Information TechnologyChange Management Process
Change Types
Type Description
Planned Reviewed and approved through the Change ManagementProcess. This set of activities can be abbreviated or very comprehensive
to deal with the significance of the Change. The stakeholders determine
the scope of the review that the Change requires. Requires a Managers
approval. Must have the opportunity to be discussed at a Change
Management Meeting.
Unplanned An Unplanned Change is a change required to software,
hardware, etc. that was not anticipated in the current change
window. These changes must be implemented according tothe business needs sooner than the scheduled weekly
Change Management meeting and/or within 5 business days.
A business requirement dictates it must be implemented as
soon as possible with a quick approval process. Requires theapproval of the CIO or any one of the CIO Direct Reports.
All Unplanned Change Requests are, however, included in
the weekly Change Management agenda and discussed(after-the-fact) at the next meeting.
Emergency A change can be declared an emergency when immediate
repair services are required to a production environment anda Severity1trouble ticket is opened in MHD. The CIO or
any one of the CIO Direct Reports may approve the change.
In some instances, the approval will be after the fact if the
required change is business impacting.Fast Track Fast Track changes do not require a 5 day lead time. They
are low risk, have no impact on production systems anddatabases, and do not result in server or system downtime to
production environments and the users production access
will not be interrupted.
Revised 09/13/04 9
-
8/12/2019 CM Procedures
11/36
Information TechnologyChange Management Process
ENVIRONMENT AND
CONDITION
RISK
LEVEL PLANNED UNPLANNED EMERGENCY
Production
No system downtime.
Change will notmodify database(s)
No impact to userproductivity or access
to the environment.
Access to theenvironment will be
not be interrupted or
limited.
Within the four wallsof the requestors
company or entire
location.
LOW Fast Track
Production
System will be down.
Change will modify database(s)
User productivity will be
interrupted.
Access to the environment will
be interrupted or limited.
Within or outside the fourwalls of the requestors
company
LOW
MODERATE
HIGH
5 Day Lead
Required
CIO Direct
Report
Approval
Required
SEV 1 Trouble
Ticket
CIO Direct
Report
Approval
Development/Test
Change inDevelopment/Test will
not impact a
production instance,
result in system
downtime or limit a
users access to the
environment.
LOW Fast Track
Development/Test
Change inDevelopment/Test will
result in system
downtime or limited
accessibility and will
have an impact on the
projects timeline.
LOW
MODERATE
HIGH
5 Day LeadRequired
CIO DirectReport
Approval
Required
SEV 1 TroubleTicket
CIO Direct
Report
Approval
Revised 09/13/04 10
-
8/12/2019 CM Procedures
12/36
Information TechnologyChange Management Process
ENVIRONMENT AND
CONDITION
RISK
LEVEL PLANNED UNPLANNED EMERGENCY
Web Application
Change does not
modify database.
Changes affectspresentation only and
involve HTML or ASP
changes that result in a
content change, they
do not go through the
CR process.
LOW NO CR
REQUIRED
NO CR
REQUIRED
NO CR
REQUIRED
Web Application
Change will modify
database(s)
LOW
MODERATE
HIGH
5 Day Lead
Required
CIO Direct
Report
ApprovalRequired
SEV 1 Trouble
Ticket
CIO DirectReport
Approval
Software
Installation or upgradeof software
LOW
MODERATE
HIGH
5 Day Lead
Required
CIO Direct
Report
Approval
Required
SEV 1 Trouble
Ticket
CIO Direct
Report
Approval
Hardware
Installation or upgradeof hardware
LOW
MODERATE
HIGH
5 Day Lead
Required
CIO Direct
Report
Approval
Required
SEV 1 Trouble
Ticket
CIO Direct
Report
Approval
Revised 09/13/04 11
-
8/12/2019 CM Procedures
13/36
Information TechnologyChange Management Process
Change Windows
Changes are implemented as requested with the following exceptions:
All planned database changes will be performed during the weekend change
window or unless the requestors Manager has approved the change during aweekday non-working hours and non-critical processing periods.
Communication i.e..telecom and email changes will be performed during non-working hours and non-critical processing periods.
Changes that require a system outage or major upgrades will be scheduled duringthe weekend change window.
There will be no changes allowed during the last week of each month or duringthe last two weeks of each quarter unless approved by a director report of theCIO.
Unplanned and Emergency changes will be completed as needed to supportcritical business needs outside of normal change windows.
Risk Assessment
Every change has an associated risk. The person requesting the change should assess the risk level of the
change. Modeling the change in a lab environment or with a modeling tool can also help assess the risk of a
change. We recommend assigning one of the following risk categories to each change request:
High-riskThese changes have the highest impact on user groups or particular
environments, and may even affect an entire site. Backing out of the change is time
consuming or difficult. You should research high-risk changes using the toolsavailable, and implement the change in conjunction with necessary support personnel.
Make sure management is aware of the change and its implications, and notify allusers.
Moderate-riskThese changes can critically impact user environments or affect anentire site, butbacking out of the change is a reasonably attainable scenario. You
should research moderate-risk changes using tools available, and possibly review the
change with support personnel. We recommend notifying all users of a moderate-risk
change.
Low-risk These changes have minor impact on user environments and backing out of
the change is easy. Low-risk changes rarely require more than minimal
documentation. User notification is often unnecessary.
Revised 09/13/04 12
-
8/12/2019 CM Procedures
14/36
Information TechnologyChange Management Process
Change Request Submission and Approval FlowChart
Business
communicates
requirements to
Change Requestor
Magic Buisness
Rule
Records Approval
Approving
Manager
responds to
MAGICTSD with
Approval
MHD sends email
to Approving
Manager advising
CR needs
approval
Change
Requestor
submits CR via
Magic
Change
Coordinator adds
request to weeklyagenda
CM MeetingApproval obtained
at CM Meeting
Requestor
notifies Ops of
CR start.
REQUESTOR
IMPLEMENTS
Requestor
notifies Ops of
CR end.
Ops updates and
closes CR
Return email to
Change
Requestor
correction
Requestor corrects and
closes CR or resubmits
for approval
Approving
Manager declines
approval and
emails Requestor
Except forUnplanned CRs
Revised 09/13/04 13
-
8/12/2019 CM Procedures
15/36
Information TechnologyChange Management Process
This page left intentionally blank
Revised 09/13/04 14
-
8/12/2019 CM Procedures
16/36
Information TechnologyChange Management Process
CR Submission
Submitt ing a Change Request
Requirement
The Requestor must have a Magic user id, have access to Change Request link on their
Magic navigation bar, and have a Mattel, Fisher Price or American Girl email address.
Requestors who do not have a Magic user id will follow the former CR submission
process defined in the Contingency Plan section of this document.
The Change Requester fills out a Change Request form which details the necessary
changes along with back-out procedures, who and what will be affected by the change,
and contact information during the implementation process.
The Change Request form is the most important piece of the Change Request process.
The form contains a series of questions to assist the Change Requester in communicatingthe scope of the request, identifying the required participants, and noting the impact to the
business unit(s). For Application changes it is important to document whether or not the
change could affect any other system. The Change Requester is responsible for
completing the Change Request form. The form may be returned to the ChangeRequester if the form is incomplete or lacking required detail.
Revised 09/13/04 15
-
8/12/2019 CM Procedures
17/36
Information TechnologyChange Management Process
Key Process Steps
There are key steps in the process that ensure Magics business automation rules perform
as programmed:
Generate email notifications to the Requestor and Approving Manager Correctly classify the activity as a Change Request
Receive a response to an approval and assign the CR to the Change Coordinator
Unplanned CR Approval Process
If they are not followed the automation rules will not generate notification of creation and
request for approval.
These key steps are highlighted with a traffic signal
Revised 09/13/04 16
-
8/12/2019 CM Procedures
18/36
Information TechnologyChange Management Process
Accessing the CR Template in Magic
Click on the Change Request link
on your Magic navigation bar.The Change Request template will display.
Revised 09/13/04 17
-
8/12/2019 CM Procedures
19/36
Information TechnologyChange Management Process
Process Steps for Documenting and Submitting a ChangeRequest
he following process steps describe the sections to be completed in the CR
pleted.
ll fields are required to be filled in to obtain approval.
5
T
template. The steps correspond to the five template sections that must be com
to obtain approvals. The data entered for any request will be published in the
change management agendas and discussed in the weekly meeting.
A
Revised 09/13/04 18
-
8/12/2019 CM Procedures
20/36
Information TechnologyChange Management Process
Section 1
Request Number
No entry required. This is a read only field. It will auto fill when you save the CR.
CR Type
The contents of this field will be determined by what the Requester has selected on theChange Request form. The recurring ticket defaults to PLANNED in this field, but if
another Change Type is selected on the Change Request form, the field will have to be
edited to reflect the correct type.
From the drop down menu select Fast Track, Planned, Unplanned or Emergency.
Opened
No entry required. This is a read only field. It will auto fill when you save the CR.
Status ID
Do not change. The status id must be OPEN.
Group Name
No entry or group assignment is required. It will auto fill when you save the CR. The CR
will be assigned to the requestors Magic group.
Section 2
Requestor ID
The Requesters department and extension are required. MAGIC profiles may include thisinformation, but if the appropriate areas do not fill, the information will need to be added.
Click on the pop up list button to select your name.
Sponsor Name
No entry required.
Phone number
Requestor work phone number is required.
Requestor ManagerClick on the pop up list button. Select the Requestors Manager name.
Revised 09/13/04 19
-
8/12/2019 CM Procedures
21/36
Information TechnologyChange Management Process
Section 3
Start and end time
Enter dates in US format (MM/DD/YY).
Enter times in 24hour/military clock format.
All start and end times must be entered as Pacific Standard Time (Los Angeles).
Actual
Leave this field blank. The Requestor will enter the actual time spent performing the CRafter the activity is complete but before the help desk ticket is closed.
System
Enter the name of the system(s) and applications the CR activity is planned for.
PlatformClick on the pop up list button to select the platform type.
Y/E (Year End)
The default is NO so you can normally leave this field blank unless it is a year-endactivity.
Equip /System Affected
Click on the pop up list button to select the equipment or system type affected by the CR
activity.
EDIFor EDI activities click on the pop up list button to select the appropriate value.
Subject ID
Click on the pop up list button. The support subject list will be presented. Placeyour pointer on subject id CR, left click once on the field to highlight in blue, click OK
and the subject type will auto fill with CR. You may also type CR in the Subject ID
field instead of using the pop-up list. If CR type is not used the business rule that
generates the email request to the Approving Manager will not kick off.
If a subject type id is not CR the business automation rules associated with this
process will not perform as programmed. The Approving Manager will not receive
the approval request. The Change Request will remain assigned to Requestor.
Revised 09/13/04 20
-
8/12/2019 CM Procedures
22/36
Information TechnologyChange Management Process
Section 4
Business Unit Affected
Identify the business units and users directly and/or indirectly affected by the activity.
Identify the number of users affected.
Could change affect anything else?
Identify the systems, hardware, and processes directly or indirectly affected by the
activity.
Describe the activity
The Approving Manager, Change Coordinator, and IT peers will rely on the
description is this field to approve a Change Request. To expedite approval a
concise description is required. It should include the description of work to be
performed including, but not limited to:
1. Actions and tasks you will take.
2. Reason why the activity will be performed.3. Locations affected business units, divisions, and their geographical locations4. Number of users affected.5. Domain names and ip addresses.6. Application name(s).
Backout Plan
Describe the process and procedure that you will follow in the event you have to back out
of the CR. Include the point of time within the planned activities stop and start time inwhich you will stop all CR activities and return to a pre CR status.
DependenciesDescribe the people, processes and resources the CR depends on to be successful.
Impact of not making the change
Describe the consequences of not performing the planned activity.
Validation
Describe the tasks that will be performed to validate that the change is successful. Includewhen these tasks will be performed.
Who will validate, onsite person and phone number
Identify who will validate the success of the change and provide contact numbers.
Completion Status
Leave this field blank. The Requestor will select Successful, Unsuccessful, CausedProblem or Not Complete after the activity is complete but before the help desk ticket isclosed.
Revised 09/13/04 21
-
8/12/2019 CM Procedures
23/36
Information TechnologyChange Management Process
Risk Assessment
Every change has an associated risk. The person requesting the change should assess the
risk level of the change. Modeling the change in a lab environment or with a modeling
tool can also help assess the risk of a change. We recommend assigning one of the
following risk categories to each change request:
High-Risk
These changes have the highest impact on user groups or particular environments, andmay even affect an entire site. Backing out of the change is time consuming or difficult.
You should research high-risk changes using the tools available, and implement the
change in conjunction with necessary support personnel. Make sure management is awareof the change and its implications, and notify all users.
Moderate-Risk
These changes can critically impact user environments or affect an entire site, but
backing out of the change is a reasonably attainable scenario. You should researchmoderate-risk changes using tools available, and possibly review the change with support
personnel. Make sure management is aware of the change and its implications, and notifyall users.
Low-Risk
These changes have minor impact on user environments and backing out of the change is
easy. Low-risk changes rarely require more than minimal documentation. Make suremanagement is aware of the change and its implications, and notify all users.
Approver Email Address
Enter the email address of the Manager who will approve the CR. The email
address must be entered in the following format for the Approving Manager to receive a
request to approve email fromMagicTSD. Example format:
If the Approving Managers email address is not entered or accurate the business
rules associated with this process will not perform as programmed. The Approving
Manager will not receive the approval request. The Change Request will remain
assigned to Requestor.
Who can approve a CRThe approval hierarchy requirement for CRs is:
Revised 09/13/04 22
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected] -
8/12/2019 CM Procedures
24/36
Information TechnologyChange Management Process
Fastrack and Planned CR Requestors ManagerUnplanned and Emergency CR - Requestors Manager, Director, VP, Direct Report of the
CIO
Delegation of approval authorityIf a Manager, Director, VP, or CIO direct report with CR approval authority will be out
of the office he/she can delegate approval authority to a peer or direct report. An email
must be sent to the Change Coordinator identifying the start and end dates of thedelegation period and the designees name.
Section 5
Save the CR to Create a Ticket and Route to a Manager for Approval
Once all fields are complete click on the save icon. This will generate a ticket numberand send the email notification fromMagicTSDto the Requestor and Approving Manager.
Example emails are displayed in Appendix C and D.
Manager and Direct Report of CIO Approval Process
To approve a request reply to the email without changing the Subject line. The request
will be updated in the Magic system with your name and approval and route the ticket to
Magic group CHANGE REQUEST for processing. See Appendix C for email example.
CR Date/Time Change and CR Time Extension
Change the date and/or time of the activity before the CR has beenpresented at the meeting.
If the CR must be performed prior to the weekly meeting the Requestor willchange the CR type to Unplanned and obtain the approval of their Manager,
Director, and a direct report of the CIO. (All Unplanned CRs require the approvalof a direct report of the CIO)
If the CR will be presented at the next weekly meeting the Requestor will changethe date and time on the CR. The Requestor/Representative will receive the CR
agenda and is required to attend the next CM meeting.
If the agenda has been published and the change is not shown on the agenda theRequestor/Representative will inform the Change Coordinator of the change at the
meeting.
Revised 09/13/04 23
-
8/12/2019 CM Procedures
25/36
Information TechnologyChange Management Process
Change the date and/or time after receiving approval at the meeting,before the activity has been performed, and the date/time change isbefore the next weekly meeting.
Requestor will send an email to the Change Coordinator.
Change Coordinator will modify the CR
Requestor will notify the business unit and all affected users.
Change Coordinator will discuss CR with date/time change at next meeting.
Extend the CR while performing the activity
Requestor is extending the CR end time by no more than 2 hours
Requestor will email or call Phoenix Operations.
Requestor will notify the business unit and all affected users
Operations will document the request in the CR action notes.
Requestor is extending the CR end time by more than 2 hours but less than 4 hours.
Approving Manager will notify Phoenix Operations they approve of theextension.
Requestor will notify the business unit and all affected users
Operations will document the request in the CR action notes.
Requestor is extending the CR end time by more than 4 hours
Requestor will inform their Director of the extension request.
Director will notify Phoenix Operations approving the extension.
Requestor will notify the business unit and all affected users
Revised 09/13/04 24
-
8/12/2019 CM Procedures
26/36
Information TechnologyChange Management Process
Operations will document the request in the CR action notes.
The Requestors VP should be notified if the CR is considered high impact.
CRs may not be extended beyond the next weekly change meeting, after which a
new CR is required.
Section 6
Contingency Plan in the event Magic is not available
In the event Magic is not available use the following process to submit a CR for approval:
Obtain a Change Request Form from:
http://is-r-us/IS-R-US/BusinessCenter/PhoenixDataCenter/CMhome.htm. The formfields are a replication of the Magic template only in MS Word format.
Fill in all fields.
Submit the form to the Approving Manager and required UsersInstruct the Approving Manager to submit their approval via email to email address 7411
(the Phoenix Help Desk).
When Magic is available the Help Desk will open a Change Request in Magic.
Revised 09/13/04 25
http://is-r-us/IS-R-US/BusinessCenter/PhoenixDataCenter/CMhome.htmhttp://is-r-us/IS-R-US/BusinessCenter/PhoenixDataCenter/CMhome.htm -
8/12/2019 CM Procedures
27/36
Information TechnologyChange Management Process
CR Approval Process
Email Received From MagicTSD - Reply to MagicTSD.
If you receive an email from MagicTSD follow the approval instructions described in the
email and reply to MagicTSD . Do not change the subject line when replying. When you
reply the request will be updated in Magic with your name and approval status.
Email Received From a Direct Report - Forward to MagicTSD
If you receive an email from a direct report follow the approval instructions described in the email and
forward your approval to MagicTSD. Do not change the subject line. When you forward the requestwill be updated in Magic with your name and approval status.
Requestors who do not have a Magic user idRequestors who do not have a Magic user id will follow the former CR submission process and submit
their request via a MS Word document. Submit your approvals to Customer Service -Phoenix.
Requestor Manager Not Available to Approve a CR
Submitting a CR to a Designated Manager
If a Requestors Manager is not available to approve a CR the Requestor should
forward the email notification they received (Example in Appendix D) to the designated
Approving Manager. When doing so ensure the following instruction is sent to the
designate and do not change the subject line:
To approve this request forward this email to email address MAGIC TSD.
Please do not change the Subject line. This will ensure your approval
will be processed by the Magic system.
Resubmit a Change Request to a Manager for Approval
In the event a Manager decides to approve a request after originally declining it
and the Manager does not have the original email requesting approval follow the stepsdefined in the section above. When doing so do not change the subject line.
Unplanned and Emergency CR Approval Process
Requestors should submit Unplanned and Emergency CRs to their Manager.
The Manager will forward the MagicTSD email (do not change the subject line) to a
direct report of the CIO for approval.
The direct report of the CIO will forward the email (do not change the subject line) toMagicTSD with their approval.
Revised 09/13/04 26
-
8/12/2019 CM Procedures
28/36
Information TechnologyChange Management Process
Accepted ChangesOnce the proper approvals have been received all Planned Change Requests will be
accepted and reviewed at the next Change Management meeting.
Change Management Meeting Agenda
The Change Management meeting agenda is a listing of all 'Accepted' change requests in
the MAGIC system. The report will list the requests in order of the planned installation
date and time. The Change Coordinator will generate an agenda on Monday to allrequestors and all members of distribution list Change Management - Global IT.
ALL Planned Change Request are due by close of business *Monday 1700hrs PST
to make the next meetings agenda.
*If Monday is a holiday CRs are due by 1300hrs PST on Tuesday.
Change Management Meeting
On Wednesday at 0800 PST/PDT of every week, the Change Management meeting will
be held to discuss all of the Change Requests that appear on the agenda. The Requester
must be present to answer any questions regarding their request.
If the request is rejected for any reason in the Change Management meeting, the Change
Coordinator will update the MAGIC ticket with the reason, change the status of the ticketaccordingly ( REJECTED,).
Only requests for the current 1-week cycle will be approved.
If the request is approved in the weekly meeting, the MAGIC ticket will be updated to
'APPROVED' status.
Change Management Meeting Minutes
After the meeting the Change Coordinator will generate the minutes of the meeting
listing all approved Planned requests to all the requestors and members of distribution listChange Management - Global IT.
CR Implementation and Ticket Closure
The Requester must call or email Phoenix Operations (701-3041) to advise the CR theyare beginning the CR implementation. Another call or email must be made no later than
the planned end time of the implementation to provide a closure status. If the request hasbeen completed, the MAGIC ticket will then be assigned to the appropriate workgroup as
indicated by the RequestersManager on the MAGIC Ticket for final update on the
success of the implementation. The Requesters Manager or Requester will then close the
MHD ticket.
Revised 09/13/04 27
-
8/12/2019 CM Procedures
29/36
Information TechnologyChange Management Process
Appendix A
Example Completed Change Request Template
Approval
Received
Accepted by
Change
Coordinator
Approval
Requested
Revised 09/13/04 28
-
8/12/2019 CM Procedures
30/36
Information TechnologyChange Management Process
Appendix B
Example Change RequestHelp Desk Ticket
Email sent by
Requestor to
Manager
Manager
Approved
Requestor creates
CR
Change Coordinator
receives in Magic
queue to process.
Revised 09/13/04 29
-
8/12/2019 CM Procedures
31/36
Information TechnologyChange Management Process
Appendix C
Example Email Notification Sent to Approving Manager-----Original Message-----
From: [email protected] [mailto:[email protected]]Sent: Wednesday, November 12, 2003 10:57 AMTo: [email protected]
Subject: Management Approval needed for: CR #(138473)
CR# 138473 has been submitted by James BeckPhone: (623)476-3042 EXT:Open Date: 11/12/2003 9:55:38 AM
Your approval is necessary for this request to be processed by the
ChangeCoordinator.
To appr ove t hi s r equest r epl y t o t hi s emai l wi t hout changi ng t heSubj ect l i ne. The r equest wi l l be updated i n t he Magi c system wi t h yourname and appr oval .
I f you do not appr ove t hi s r equest , pl ease cont act t he request or shownabove, and do not r epl y t o t hi s emai l . A r epl y i s consi der ed anappr ovalby t he Magi c appl i cat i on.***********************************************************
Ri sk Assessment : Moderate
Request Type: PLANNED Change Request s
Pl anned St ar t ( PST) : 11/ 22/ 03 12: 00
Pl anned End( PST) : 11/ 22/ 03 15: 00
Syst em: Magi cTSD
Pl at f orm: NT
Equi p/ Syst em Af f ect ed: Appl i cat i ons
Busi ness Uni t s Af f ected: Ever ybody usi ng t he Magi cTSD syst em
Coul d change af f ect anyt hi ng el se: No
Descr i pt i on of Act i vi t y: Run a backup on t he magi c dat abase onnapdcm70a.Shut down Magi cTSD t o run t he DBAdmi n ut i l i t y.Modi f y t he Hel pDesk vi ew t o add Cl i ent i nf ormat i on.Modi f y f orms f or Hel p Desk t o di spl ay new cl i ent i nf ormat i on.
Revised 09/13/04 30
-
8/12/2019 CM Procedures
32/36
Information TechnologyChange Management Process
Ref ormat t he Change Request For m t o el i mi nate unnecessar y f i el ds.Reboot NAPDCM70A t o r ecycl e al l servi ces.St art and test Magi cTSD t o make sur e changes ar e worki ng cor r ect l y.
Backout Pl an: Rest ore database
Dependanci es: Shut down magi cTSD. No access t o appl i cat i on duri ng t hi sCR.
I mpact of not maki ng change: Needed cl i ent i nf ormat i on wi l l not beavai l abl e i n t he Hel p Desk t i cket wi ndow.
Val i dat i on Method: St art magi c appl i cat i on and make sure t hewi ndows/ dat adi spl ay cor r ectl y
Who wi l l val i dat e: J i m Beck
Onsi t e per son: J i m Beck
Onsi t e phone number : 6234763042
Onsi t e Cel l / Pager :
Manager and Direct Report of CIO Approval Process
To approve a request reply to the email without changing the Subject line. The request
will be updated in the Magic system with your name and approval.
-----Original Message-----From: Tavilla, RichardSent: Wednesday, November 12, 2003 11:04 AM
To: MagicTSDCc: Beck, James E; Hartman, Lynn L; Brown, Alex; Calderon, Eddie;
McCune, John M; Perez, Joe; Tavilla, Richard; Zeilinger, JerrySubject: RE: Management Approval needed for: CR #(138473)
appr oved
- - - - - Or i gi nal Message- - - - -Fr om: Magi cTSD@Mat t el . com [ mai l t o: Magi cTSD@Mat t el . com]Sent : Wednesday, November 12, 2003 10: 57 AM
To: Ri char d. Tavi l l a@mat t el . comSubj ect : Management Appr oval needed f or : CR #( 138473)
CR# 138473 has been submi t t ed by J ames BeckPhone: (623)476- 3042 EXT:Open Dat e: 11/ 12/ 2003 9: 55: 38 AM
Your appr oval i s necessary f or t hi s r equest t o be processed by t heChangeCoor di nat or .
Revised 09/13/04 31
-
8/12/2019 CM Procedures
33/36
Information TechnologyChange Management Process
To appr ove t hi s r equest r epl y t o t hi s emai l wi t hout changi ng t heSubj ectl i ne. The request wi l l be updat ed i n t he Magi c syst emwi t h your nameandappr oval .
I f you do not appr ove t hi s r equest , pl ease cont act t he request or shownabove, and do not r epl y t o t hi s emai l . A r epl y i s consi der ed anappr ovalby t he Magi c appl i cat i on.***********************************************************
Ri sk Assessment : Moderate
Request Type: PLANNED Change Request s
Pl anned St ar t ( PST) : 11/ 22/ 03 12: 00
Pl anned End( PST) : 11/ 22/ 03 15: 00
Syst em: Magi cTSD
Pl at f orm: NT
Equi p/ Syst em Af f ect ed: Appl i cat i ons
Busi ness Uni t s Af f ected: Ever ybody usi ng t he Magi cTSD syst emCoul d change af f ect anyt hi ng el se: No
Descr i pt i on of Act i vi t y: Run a backup on t he magi c dat abase onnapdcm70a.Shut down Magi cTSD t o run t he DBAdmi n ut i l i t y.Modi f y t he Hel pDesk vi ew t o add Cl i ent i nf ormat i on.Modi f y f orms f or Hel p Desk t o di spl ay new cl i ent i nf ormat i on.Ref ormat t he Change Request For m t o el i mi nate unneccessar y f i el ds.Reboot NAPDCM70A t o r ecycl e al l servi ces.St art and test Magi cTSD t o make sur e changes ar e worki ng cor r ect l y.
Backout Pl an: Rest ore database
Dependanci es: Shut down magi cTSD. No access t o appl i cat i on duri ng t hi sCR.
I mpact of not maki ng change: Needed cl i ent i nf ormat i on wi l l not beavai l abl e i n t he Hel p Desk t i cket wi ndow.
Val i dat i on Method: St art magi c appl i cat i on and make sure t hewi ndows/ dat adi spl ay cor r ectl y
Who wi l l val i dat e: J i m Beck
Onsi t e per son: J i m Beck
Onsi t e phone number : 6234763042Onsi t e Cel l / Pager :
Revised 09/13/04 32
-
8/12/2019 CM Procedures
34/36
Information TechnologyChange Management Process
Appendix D
Example Email Notification Sent to the Requestor
-----Original Message-----
From: [email protected] [mailto:[email protected]]Sent: Wednesday, November 12, 2003 10:57 AMTo: [email protected]
Subject: Management Approval needed for: CR #(138473)
APPROVAL REQUEST HAS BEEN SENT TO: [email protected]***********************************************************
CR# 138473 has been submi t t ed by J ames Beck
Phone: (623)476- 3042 EXT:Open Dat e: 11/ 12/ 2003 9: 55: 38 AM
Your appr oval i s necessary f or t hi s r equest t o be processed by t heChangeCoor di nat or .
To appr ove t hi s r equest r epl y t o t hi s emai l wi t hout changi ng t heSubj ectl i ne. The request wi l l be updat ed i n t he Magi c syst emwi t h your nameandappr oval .
I f you do not appr ove t hi s r equest , pl ease cont act t he request or shownabove, and do not r epl y t o t hi s emai l . A r epl y i s consi der ed anappr ovalby t he Magi c appl i cat i on.***********************************************************
Ri sk Assessment : Moderate
Request Type: PLANNED Change Request s
Pl anned St ar t ( PST) : 11/ 22/ 03 12: 00
Pl anned End( PST) : 11/ 22/ 03 15: 00
Syst em: Magi cTSD
Pl at f orm: NT
Equi p/ Syst em Af f ect ed: Appl i cat i ons
Busi ness Uni t s Af f ected: Ever ybody usi ng t he Magi cTSD syst emCoul d change af f ect anyt hi ng el se: No
Revised 09/13/04 33
-
8/12/2019 CM Procedures
35/36
Information TechnologyChange Management Process
Descr i pt i on of Act i vi t y: Run a backup on t he magi c dat abase onnapdcm70a.Shut down Magi cTSD t o run t he DBAdmi n ut i l i t y.Modi f y t he Hel pDesk vi ew t o add Cl i ent i nf ormat i on.Modi f y f orms f or Hel p Desk t o di spl ay new cl i ent i nf ormat i on.Ref ormat t he Change Request For m t o el i mi nate unneccessar y f i el ds.Reboot NAPDCM70A t o r ecycl e al l servi ces.St art and test Magi cTSD t o make sur e changes ar e worki ng cor r ect l y.
Backout Pl an: Rest ore database
Dependanci es: Shut down magi cTSD. No access t o appl i cat i on duri ng t hi sCR.
I mpact of not maki ng change: Needed cl i ent i nf ormat i on wi l l not beavai l abl e i n t he Hel p Desk t i cket wi ndow.
Val i dat i on Method: St art magi c appl i cat i on and make sure t hewi ndows/ dat adi spl ay cor r ectl y
Who wi l l val i dat e: J i m Beck
Onsi t e per son: J i m Beck
Onsi t e phone number : 6234763042
Onsi t e Cel l / Pager :
Revised 09/13/04 34
-
8/12/2019 CM Procedures
36/36
Information TechnologyChange Management Process
Appendix E
Visio Diagram of Magic Process
CHANGE REQUEST
SUBMISSION USING
MAGIC HELP DESK
Requestor logs
into magic and
Fills out the
Change Request
Approver replies to
email with written
approval
Business Rule 1
fires. Sends
request for
approval to
specified address
Change
Request is
Saved in
Magic
Approver
reviews
Change
Request
APPROVED
Approver works
with Requestor to
get approval
REJECTED
Magic updates
Change Request
with approval
information,
Assigns to Change
Control group.
Change
Coordinator
reviews CR for
proper approval