Introduction

is one of the construction organizations

founded in the Philippines with its primary objective, to design and

build all types of structures at a reasonable cost.

offers a wide range of services: Pre-Design

Feasibility, Architectural Interiors, Comprehensive Design,

Engineering & Construction.

Page 3: C&M Partners Co. Profile as of JAN 2011

The Firm

The beginning of could be easily traced since it all started 2007 when Mr. Ediver Correa together with Ms. Andreanne

Molano (now husband and wife), who worked in separate design and construction firms, decided to put up contracting firm using their

resources – financial & technological skills.

During its first year, operated as a designer –practicing architect for mostly commercial and residential spaces as its specialized fields. Given sufficient time and proactive skilled individuals,

numerous clients came their way, a chance to expand its operation.

Though relatively a short period of existence, manifested a growing & consistently learning through different handled

projects.

Today, has more than 100 workers that includes: foreman, carpenters, painters, laborers, and other skilled men needed

for construction.

Page 4: C&M Partners Co. Profile as of JAN 2011

Visio

n, M

issio

n &

Co

re

V

alu

e

Vision

Mission

Core Values

To be an organization with a reputation for excellence, reliability,

integrity and quality.

A design and construction firm that will provide high standard

services and quality products that are well accepted to the

satisfaction of customers .

COMMITMENT

Committed to deliver services that surpass customer expectations

in value and ethnical practices.

PROFESSIONALISM

INTEGRITY

Implement the utmost standards of principled manners and promote a

work milieu that persuades mutual cost, solidarity and open

communication that emphasizes awareness, initiative and liability.

EXCELLENCE

Strive for distinction with its highest quality services an innovativeness.

REPUTATION

Respected for contributing and partaking the life and well-being

of the society.

Principled Work Attitude.

Page 5: C&M Partners Co. Profile as of JAN 2011

Co

mp

an

y

In

fo

rm

atio

n

Registered Company NameC. & M. Partners – Construction Services Co. Ltd.

S.E.C. Registration No.PL200815987

Tax Identification No.

298-884-857-000

Business Permit No.0223 Series of 2011

Sanitary Permit No.

NF-11-0163 Series of 2011

Brgy. Business Permit No.050-11 w/ O.R. 5973292 Series of 2011

Business Address

# 21 Venus St. Phase 2 Brgy. Pantoc, L.V.D.S.N. MeycauayanCity, Bulacan

Contact No.

Sun – 0922 870 2991 to 92Smart – 0929 767 7593Globe – 0916 686 1882

Website

www.cmpartnersco.com

Page 6: C&M Partners Co. Profile as of JAN 2011

Ce

rtific

atio

n

Page 7: C&M Partners Co. Profile as of JAN 2011

Services

Pre-Design Services

Feasibility StudiesThis service provides clients with information regarding multiple issues for a

possible project.

Design Services

Architectural DesignThis service involves the design and creation of the architectural project, and

is consists of multi-step process to create final set of documents to further

allow a project to be constructed.

Conceptual Design PhaseThis begins with the review of existing conditions and ideas

about the project. The general scope and goals are also

being established.

Preliminary Design Phase

During this phase, the chosen conceptual design solution is

refined and addresses more complex construction issues. The

goals of the project are maintained as the design solution

becomes more complex and progresses toward completion.

Final Design Phase

This is the process of creating the final documents that will

be used to construct the project. The goal of this phase is to

document the design solution in detail and produce a set of

documents.

Interior ServicesThe company’s services for interior projects include:

* Space Planning for existing shell buildings

* Complete interior renovations of existing spaces

* Re-Design of existing interior spaces

* Selection of materials and finishes

* Selection of color schemes and color coordination

* Selection and specification of equipment

Page 8: C&M Partners Co. Profile as of JAN 2011

Services

Construction Phase Service

Basic Services

The company’s services continue until the project if

completed. Regardless of the method of project delivery,

C&M Partners can provide construction contract

administration.

Services provided during this phase include:

* Job site progress meetings and reviews* Review and monitoring of construction

schedule

* Field observations of work completed

* Ensure construction meets projects specifications

* Review of shop drawings and contractor

submittals

* Verification of contractor requests for

payment* Response to owner and contractor questions

* Clarifications and modifications due to field

conditions

Consulting Services

The company can readily provide consulting services.

These may be as third party, client representative or various

other reasons.

Page 9: C&M Partners Co. Profile as of JAN 2011

Projects

Pictures after the construction. Creative

Concept walls consist of three colors:

green, orange and yellow. Each color has

its own significance for the different rooms

that is part of the office space.

Project Title:

Creative Concepts Inc. – Office Renovation

Location:5/f eurovilla 2, V.A. Rufino st., Legaspi

Vill. Makati City

Client:

Realform Furniture

Cost of project:

Php 625,000.00

Date / Year of Construction:

March to April 2008

Page 10: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:Cognitive IT Solutions Inc. – Office

Renovation (part I)

ITArea

-before

ITArea

-after

Man

ager

’s r

oom

-before

Man

ager

’s r

oom

-after

Location:10/f Athenauem bldg. L.P. Leviste St.,

Salcedo Village, Makati City

Client:

Realform Furniture

Cost of project:

Php 490,000.00

Date / Year of Construction:

May to June 2008

Page 11: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Cognitive IT Solutions Inc. – Office

Renovation (part II)

Location:10/f Athenauem bldg. L.P. Leviste St.,

Salcedo Village, Makati City

Client:

Realform Furniture

Cost of project:

Php 93,400

Date / Year of Construction:

April to may 2009

Pictures after the construction. Cognitive Office was first renovated in 2008, but some part of the

area was left and only until 2009 that the said

part was to be continued.

Page 12: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

5-Storey Choa Residence

Location:

524 E.T. Yuchengco St., Binondo, Manila

Client:

Mr. & Mrs. Erwin Choa

Cost of project:

Php 4,300,000.00

Date / Year of Construction:

Sept. 2008 to Feb. 2009

Pictures before the construction (clockwise from

left):

L-shaped kitchen cabinet details; old comfort

room showing toilet and sink; master bedroom

Pictures after construction (clockwise from top left):

“painted red” kitchen cabinet details; new and

treated comfort room; the pink cabinet that

separates 2 bed; the wooden

staircase treated back wall.

Page 13: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Argosy Advisers Inc.

Location:

Pacific Star Bldg. Makati City

Client:

Realform Furniture

Cost of project:

Php 405,235.70

Date / Year of Construction:

June to July 2009

before

During construction

Page 14: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

KGJS Fleet Management manila, Inc.

Location:5/F ; 6/f; 7/F VAR Bldg., Ayala Ave. cor.

Rufino St., makati City

Client:

Realform Furniture

Cost of project:Php 223,500.00 ; PHP 115,000.00;

Php 194,734.12

Date / Year of Construction:Dec. 2008; June to July

2009 ; feb. to mar. 2010

Pictures after the construction. The first

renovation of the KGJS Inc. was held December 2008. It includes the main office of the CEO,

Accounting Area, Secretary Area, plus other

minor spaces.

7th

Flo

or:

Pictures after the construction. This area houses BPO of the KGJS company.

6th

Flo

or:

Page 15: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Microgaming technology Corp. – Office renovation

Location:18/F Unit 1804 taipan Place, Emerald Ave.

Ortigas Ctr., Pasig City

Client:

Realform Furniture

Cost of project:Php 420,000.00; Php 127,207.60;

Php 201,566.04; Php 34,,904.10

Date / Year of Construction:

June 2009; Sept 2009; march

2010; june to aug 2010

Office before

(walls were painted mint green )

Office after(Tables are now installed and walls plus the cabinets were changed to

black and white)

Page 16: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

WNS Global Services – Office Renovation

Location:G/F Superstore Bldg., Times Square St.

Araneta ctr., Cubao, Quezon City

Client:

Group Perspective Inc.

Cost of project:

Php 750,000.00

Date / Year of Construction:

June to July 2009

Taken During the actual

construction period

Off

ice

aft

er

Page 17: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Felo II- Street Drainage & Road Construction

Location:

Felo II st. Brgy. Pasolo, Valenzuela City

Client:

Congressman rex gatchalian

Cost of project:

Php 1,520,768.00

Date / Year of Construction:

March to May 2010

be

fore

aft

er

Page 18: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Medical Plaza Condo. – Interior Revovation

Location:Unit 2701 Medical Plaza Condo., Ortigas

Ctr., Pasig City

Client:

Atty. Jay Jerota

Cost of project:

Php 524,998.09

Date / Year of Construction:

March to June 2010

be

fore

aft

er

Page 19: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:3-Storey mercado Residence

Location:

Tangos, baliwag, Bulacan

Client:

Mrs. Evelyn Mercado

Cost of project:

Php 1,500,000.00

Date / Year of Construction:

March to June 2010

before

after

Page 20: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

2-Storey tycangco residence

Location:

San Juan, Metro Manila

Client:

Mrs. Cora Tycangco

Cost of project:

Php 5,321.078.00

Date / Year of Construction:

Dec. 2009 –mar. 2009; June to

Oct. 2010

beforeafter

Page 21: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Fence of Sto. NiÑo Parish Church

Location:

El Camino Road, LVDSN, Meyc. Bul

Client:

Mr. & Mrs. Jun Molano

Cost of project:

Php 150,000.00

Date / Year of Construction:

Mar. to April 2010

After shots

Page 22: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Spliethoff Office – Fit Out

Location:39/F Rufino Tower Bldg. Ayala Avenue,

Makati City

Client:

Archidecs– Archt. Mike Luga

Cost of project:

Php 16,522,954.64 ++

Date / Year of Construction:

Aug. - Oct. 30, 2010

During Demolitionand actual construction

Aft

er

Page 23: C&M Partners Co. Profile as of JAN 2011

Projects

Project Title:

Tri-Ohms Engineering Office–Fit Out

Location:Quirino H-way Sacred Heart Village,

Novaliches, Fairview Quezon City

Client:

Ms.Jeannet Perey - Owner

Cost of project:

Php 890,193.13

Date / Year of Construction:

Dec. 1 to Dec 30, 2010

During Demolition

and actual

construction

Page 24: C&M Partners Co. Profile as of JAN 2011

Presents:

Design Conceptualization Projects

(clockwise from top left): Avida Condo I Dining; Avida Condo II Dining; Avida Condo I-

Living; Noel Dumaop Apt.; Avida Condo III Living; Medical Plaza Condo I Entry Area.

Projects

Page 25: C&M Partners Co. Profile as of JAN 2011

Presents:

Design Conceptualization Projects

(clockwise from top left): Noel Dumaop Façade; Riverfront Condo I Living; CDO

LVDSN Branch; Noel Dumaop Apartment.

Projects

Page 26: C&M Partners Co. Profile as of JAN 2011

Presents:

Design Conceptualization Projects

(clockwise from top left): Vision X office w/ Red Painted Wall; Baby’s rm. w/ blue closet

from Ng Residence; RCBC Savings Bank – Ortigas Branch; RCBC Savings Bank –

Laguna Branch.

Projects

Page 27: C&M Partners Co. Profile as of JAN 2011

Presents:

Design Conceptualization Projects

(clockwise from top left): MVU Office; Executive Suite @ Parañaque Doctors; Sagrada

Familia showing the altar; KGJS Office showing the accounting area; Kim Store

Projects

Page 28: C&M Partners Co. Profile as of JAN 2011

Presents:

Design Conceptualization Projects

Design Proposals (clockwise from top left): Luntiang Kabukiran Ecofarm Hotel; 2-Storey

Apartment of Mr. Amparo; Mr. Henry James Aralan 2-Storey House; Thesis Project of an

Architecture UST student Batch 2009; Bungalow House of Ms. Bernadette Amparo.

Projects

Page 29: C&M Partners Co. Profile as of JAN 2011

Presents:

Design And Build Projects

Name of Project: AMG SKILLED HANDS & TRAINING SCHOOL

BLDG.

Location: CAGAYAN VALLEY

ROAD, MAKAPILAPIL, SAN

ILDEFONSO, BULACANDate / Year: 2007

Name of Project: INFORESTA

PHILS. INC.

Location: 4/F UNIT A-6 MARVIN

PLAZA, CHINO ROCES, MAKATI

CITYDate / Year: 2007

Name of Project: VISION X INC.

Location: G/F SM CYBERZONE II,

JUPITER COR. ZODIAC STS. BRGY.

BEL-AIR, MAKATI CITY

Date / Year: 2007

Name of Project: LUNTIANG

KABUKIRAN ECOFARM & NATURE

PARK

Location: HALAY-HALAY, PILILIA,

RIZAL

Date / Year: 2008

Name of Project: SAGRADA

FAMILIA CHURCH

Location: BRGY. MAASIM, SAN

ILDEFONSO, BULACAN

Date / Year: 2008

Name of Project: MVU – TRADE-

COM CTR.

Location: 585-B CORDILLERA COR.

ARAYAT STS., MANDALUYONG

CITY

Date / Year: 2008

Name of Project: RCBC SAVINGS

BANK

Location: BIÑAN, LAGUNA

BRANCH

Date / Year: 2009

Name of Project: WAREHOUSE &

PARKING AREA OF ASM TRAINING

SERVICES

Location: LOT 4, LEVERIZA ST.,

MALATE, MANILA

Date / Year: 2009

Projects

***Contact References available only

upon request.

Page 30: C&M Partners Co. Profile as of JAN 2011

Presents:

Design And Build Projects

Name of Project: RCBC SAVINGS

BANK

Location: PACIFIC PLAZA CONDO.

ORTIGAS CTR., PASIG CITY

Date / Year: 2009

Name of Project: MRS. CATALIG

RESIDENCE

Location: SAN JUAN, HAGONOY,

BULACAN

Date / Year: 2009

Name of Project: “KIM” BOUTIQUE

Location: SM MALL OF ASIA,

PASAY

Date / Year: 2009-on going

Name of Project: GOTOKING –

CATERKING FOOD INC.

Location: 2/F FOODCOURT, THE

MEDICAL CITY, ORTIGAS AVE.,

PASIG CITY

Date / Year: 2009

Name of Project: GOTOKING –

CATERKING FOOD INC.

Location: FOODCOURT, SM

MEGAMALL

Date / Year: 2009

Name of Project: ENGR. REY

ALCONSEL’S RESIDENCE

Location: FAIRVIEW, QUEZON CITY

Date / Year: 2009 to JAN 2010

Name of Project: DENNIS &

SHERYL REYES RESIDENCE

Location: BLK. 1 LOT 19 & 20 P2

SAUDIA VILLAGE, PAG-ASA IMUS,

CAVITE

Date / Year: 2009

Name of Project: JON BERNARDO

OFFICE LAYOUT

Location: UNIT 1119 11/F

BURGUNDY BLDG., MAKATI CITY

Date / Year: 2009

Projects

***Contact References available only

upon request.

Page 31: C&M Partners Co. Profile as of JAN 2011

Presents:

Design And Build Projects

Name of Project: ASM OFFICE

Location: CRI 665 QUIRINO AVE.

COR LEVERIZA STS., MALATE

MANILA

Date / Year: 2009

Name of Project: MR. & MRS.

DELFIN TABORA’S 2-STOREY

RESIDENCE

Location: 12 BULACAN ST.,

BONIFACIO VILLAGE, PASONG

TAMO, TANDANG SORA

Date / Year: 2009

Name of Project: MR. & MRS.

LIONELL ALLAS’ RESIDENCE

Location: QUEZON CITY

Date / Year: 2009

Name of Project: MR. ROLAND

LORILLA’ RESIDENCE

Location: QUEZON CITY

Date / Year: 2009

Name of Project: MR. PABILONIA

RESIDENCE

Location: QUEZON CITY

Date / Year: 2009

Name of Project: NHA PABAHAY

HOUSING PROJECT

Location: MONTALBAN, RIZAL

Date / Year: NOV 2009 to JAN

2010

Name of Project: MRS. CATHY

FRANCISCO

Location: GEMINI COR.

CAPRICORN STS. P3 LVDSN

MEYCAUAYAN CITY

Date / Year: 2009

Name of Project: 8-DOOR, 2-

STOREY APARMENT- MR. BAUSA’S

Date / Year: 2009- 2010

Projects

***Contact References available only

upon request.

Page 32: C&M Partners Co. Profile as of JAN 2011

Presents:

Design And Build Projects

Name of Project: BCP AREA-IP

CONVERGE

Location: 34/F RCBC BLDG. ,

AYALA AVE., MAKATI CITY

Date / Year: 2010

Name of Project: MR. NOEL

DUMAOP’S 6-DOOR, 2-STOREY

APARTMENT

Location: FAIRVIEW, QUEZON CITY

Date / Year: 2010

Name of Project: GPI Warehouse & Office

Location: PASIG CITY

Date / Year: 2010

Name of Project: PETER NGO’S

RESIDENCE

Location: BINONDO, MANILA

Date / Year: 2009-2010

***Contact References available only

upon request.

Name of Project: CDO – LVDSN

BRANCHLocation: EL CAMINO RD. LVDSN

MEYCAUAYAN CITY

Date / Year: 2010

Name of Project: CONFESSION

BOX OF SN PARISH CHURCH

Location: LVDSN MEYCAUAYAN

CITY

Date / Year: 2010

Name of Project: ASM PERIMETER

FENCE

Location: 2248 M. ASUNCION ST. MALATE, MANILA

Date / Year: 2010

Name of Project: MR. JEROTA’S

SALON

Location: ETON BLDG., TAFT AVE., MANILA

Date / Year: 2010

Projects

Page 33: C&M Partners Co. Profile as of JAN 2011