Clinton Combined Sewer Overflow (CSO) Storage Facility...

30
Onondaga County Executive Joanne M. Mahoney Clinton Combined Sewer Overflow (CSO) Storage Facility Project Onondaga County Executive Joanne M. Mahoney Bruce G. Munn, Nicholas Capozza, Ryan C. Fisher, A.J. McGinn June 4, 2013

Transcript of Clinton Combined Sewer Overflow (CSO) Storage Facility...

Onondaga County Executive Joanne M. Mahoney

Clinton Combined Sewer Overflow (CSO) Storage Facility Project

Onondaga County Executive Joanne M. Mahoney

Bruce G. Munn, Nicholas Capozza, Ryan C. Fisher, A.J. McGinnJune 4, 2013

Onondaga County Executive Joanne M. Mahoney

Project Team Acknowledgement • Environmental Engineering Associates, LLP

• GHD• O’Brien & Gere• ARCADIS

Onondaga County Department of Water Environment Protection

• Matthew J. Millea, Deputy County Executive• Tom Rhoads PE, Commissioner• Nicholas Capozza, Project Manager

Onondaga County Executive Joanne M. Mahoney

Project Team Acknowledgement Brierley Associates – Geotechnical Engineering

Bryant Associates – Structural Inspection ServicesFisher Associates – Site/Civil Inspection ServicesB&L Engineering – Site/Traffic DesignGroup One Design – Architectural DesignLandscape & Prospect – Landscape Architecture PB Americas – Noise Mitigation

CDM/C+S Joint Venture – Construction ManagementJett Industries/Kiewit Construction – General Contractor

Onondaga County Executive Joanne M. Mahoney

Project Background

• Judgment on Consent signed in 1989• Amended Consent Judgment (ACJ) signed 1998

Capture >85% of average annual CSOsRemoval of floatables Achieve water quality standards for bacteria in Onondaga Lake

• County negotiated 4th Stipulation ACJ November 2009

3.7 MG Clinton CSO storage operational by December 31, 2013

Incorporation of Green Infrastructure for CSO reduction

95% CSO Capture by December 31, 2018

Onondaga County Executive Joanne M. Mahoney

Project LocationOnondaga Lake

Metro WWTP

Destiny USA

Clinton CSOStorage Facility

Armory Square

S.U. Sheraton

Onondaga County Executive Joanne M. Mahoney

Project Location

• Insert CSO map from Ed

Onondaga County Executive Joanne M. Mahoney

Key Project Goals/Challenges

• Meet ACJ milestones and requirements– Complete Design November 2010– Commence Construction July 2011– Commence Operation December 31, 2013

• Keep all CSO storage below grade– Allow reuse of parking lot above CSO Storage– High saline content of groundwater up to 80,000 mg/l– Comply with BMP’s for groundwater dewatering

Onondaga County Executive Joanne M. Mahoney

Key Project Goals/Challenges

• Other County Goals– Maximize CSO Storage– Requirement to accommodate 1 year

2 hour storm flow – Be consistent with “Save the Rain Program”

• Local Construction Concerns– Mitigation of construction noise– Parking/Traffic mitigation– Archeological/Environmental concerns

Onondaga County Executive Joanne M. Mahoney

CSO Storage Facility Alternatives

1. Conventional Dewatering/Construction2. Tunneling Construction 3. Four Vertical Slurry Wall Tanks/Cut and Cover

Conveyance 4. Three Vertical Slurry Wall Tanks/Single Tunnel

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Alternative Cost Analysis1

Cut-and-Cover (single tank)

2

Three Tunnels

3

Slurry Wall Three Tank/Tunnel

4

Slurry Wall four tank and cut-and-

cover

Construction Cost $55,800,000 $36,700,000 $41,200,000 $48,800,000

Overflow Pumping Addition $3,300,000 $3,300,000 $3,300,000 $3,300,000

Contingency (20%) $11,800,000 $8,000,000 $8,900,000 $10,400,000

Subtotal Construction Cost $70,900,000 $48,000,000 $53,400,000 $62,500,000

Escalation to Construction Mid

Point in 2012 (6%)$4,300,000 $2,900,000 $3,200,000 $3,800,000

Total Estimated Construction Cost $75,200,000 $50,900,000 $56,600,000 $66,300,000

Onondaga County Executive Joanne M. Mahoney

Unique Design Aspects• Innovative Geotechnical

ApproachSlurry diaphragm wall constructionJet grout plug and sheeting groundwater containmentOpen face + closed face TBM options

• Specialized Construction Prequalification

Jet grouting Tunneling

• Project Labor Agreement Provisions

Union work forceExemption from Wicks LawOne construction contract

Onondaga County Executive Joanne M. Mahoney

Use of Green Technologies

• Recovery and reuse of storm drainage flows for CSOStorage Cleaning

• Bioswales and storm flow treatment• Green roof on West Chamber• Use of LED site lighting and parking lot lighting• “Flow through by gravity” design

Onondaga County Executive Joanne M. Mahoney

Construction Approach

• Project Bid July 2011 - $70,640,000– General Contractor - Jeff Industries/

Kiewit Construction • Contract Awarded August 2011• Revised Construction Approach

Reinforced concrete box tunnels vs. circular tunnels

Onondaga County Executive Joanne M. Mahoney

Facility layout

Onondaga County Executive Joanne M. Mahoney

West Chamber

Onondaga County Executive Joanne M. Mahoney

West Structure

Onondaga County Executive Joanne M. Mahoney

East Chamber

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Onondaga County Executive Joanne M. Mahoney

Project Status

• Project is 70% complete• Scheduled for operational December 31, 2013• 12 month start up and performance period,

December 31, 2014• Project updates to follow

Onondaga County Executive Joanne M. Mahoney

QUESTIONS?

Onondaga County Executive Joanne M. Mahoney

Bruce [email protected]

(315) 679 5800

Onondaga County Executive Joanne M. Mahoney