Climate Action Plan and Alternative Energy Overview UNC Energy Task Force March 17, 2010.
-
date post
19-Dec-2015 -
Category
Documents
-
view
215 -
download
0
Transcript of Climate Action Plan and Alternative Energy Overview UNC Energy Task Force March 17, 2010.
Climate Action Plan and Alternative Energy Overview
UNC Energy Task ForceMarch 17, 2010
Agenda• Introduction
• Overview of Climate Action Plan (CAP) and Alternative Energy Study
• Modeling Results
• Question and Answer
Climate Action Plan• UNC became an early signatory to the American Colleges and
Universities Presidents Climate Commitment (ACUPCC) in 2007 and began development of its Climate Action Plan
• Overall goal = zero net greenhouse gas emissions by 2050
• The plan addressed all sources of greenhouse gas (GHG) emissions in UNC’s inventory:– On-site fossil fuel combustion (Scope 1 emissions)
– Purchased electricity (Scope 2 emissions)
– Transportation and other indirect sources (Scope 3 emissions)
• The plan includes measures affecting both energy demand and energy supply
Alternative Energy Study• In 2008, in support of the Climate Action Plan, UNC initiated a
study of several alternative energy technologies for potential implementation at UNC
• Involved a diverse team of experts, including UNC Energy Services staff, contractors, and technology suppliers
• Publicly-available and proprietary studies were reviewed, suppliers were interviewed, and plant trips were made to examine operational examples of the alternative energy technologies under consideration
Alternative Energy Study• The alternative energy technologies included:
– Biomass Gasification– Co-firing Biomass– Landfill Gas– Poultry Litter– Solar PV– Solar Thermal– Anaerobic Digestion of Animal Waste– Wind Power– Geothermal– Ocean/Tidal Energy– Algae– Carbon Sequestration– Modular Nuclear– Municipal Solid Waste (MSW) Plasma Gasification– Fuel Cells
Alternative Energy Study• Alternatives that impact the central utility plant:
– Switch to Natural Gas– Large-scale Biomass Plant– Co-firing Biomass– MSW Plasma Gasification– Modular Nuclear
• Through significant research and discussion, the team evaluated the merits of each technology, the potential for implementation at UNC, and made recommendations for further, more detailed evaluation
Near-term Alternatives – Carbon Reduction
50% Natural Gas50% Coal Substitute
100% Coal Substitute
Large Scale BiomassPlasma Gasification
Near-Term Portfolio Long-Term Common
Long-Term Alternative
LFG Banked Offsets
Additional Projects
This is How We Looked at Alternatives
Process & Key Assumptions • Process overview
– Decision quality– “Sustainable” decision criteria
• Well defined baseline– Building blocks– Highlights
• Energy price forecasting – Natural gas– Coal– Biomass
• Financial risk exposure to climate change– Legislative policy scenarios– Cost of carbon– Results by scenario
Analysis & Insights • Sample alternative (use model)
• Abatement Curve
• Portfolio Development
• Impact on Energy Consumption
• Conclusions
1. Process overview - Decision quality
Process Elements• Decision quality• Investment analysis• Stakeholder questions• Insights versus answers• Fit the objective• “Sustainable” decision
criteria
Commitment to Action
0
1
2
3
4
5
6Commitment to Action
Correct Frame & Constraints
Well Articulated Objectives
Well Articulated Decision Criteria
Well Defined Baseline
Process Inclusive of Stakeholders
Creative & Doable OptionsReliable & Meaningful
Information
Logical Reasoning
Tradeoffs Clear
Risks Understood & Mitigated
On-going Basis for Performance Measurement
Decision Support Accessible to Key Audiences
Decision Quality AttributesProceed Recycle
Sustainable decision criteria
1) Traditional economic financial metrics 2) Monetize non-traditional risks
• Reliability• Climate change
3) Explicit consideration of non-monetized values:• Environmental• Social• Economic
Worksheet Campus Description
MainCarolina North
MainCarolina North
MainCarolina North
Energy Use Intensity Factors developed with input from the Utilities staff.Main
Carolina NorthMain
Carolina NorthMain
Carolina NorthCommodity prices used in the calculation of the primary energy expenses.Graphics illustrating forecasted utility demand and primary energy consumption by campus.
MainCarolina North
Emission factors used to calculate the GHG emissions.This sheet illustrates the potential direct and indirect financial exposure to possible GHG regulation.
Action Valuation SummaryThis sheet provides a summary overview of the valuation metrics for all the actions considered for inclusion in the CAP.
Action Valuation Sheets This sheet describes the assumptions for each action.
Abatement CurveThis sheet shows the abatement curve that illustrates the value and potential impact of each alternative relative to the other alternatives.
Portfolio Wedges and Valuation This graphic illustrates each portfolio action as a wedge and the impact on GHG emissions.
Other Factors Describes other factors used in the calculations in the CAP model.
Describes the business-as-usual GHG emissions.
GHG Regulatory Financial Exposure
Energy Use Intensity Factors
GHG Emissions
Commodity Price Assumptions
GHG Emission Factors
Describes the primary energy used to meet demand and associated costs.
Base Case/Business-as-Usual Components
Valuation of GHG Mitigation Actions
Portfolio Development
Miscellaneous
Population Forecast
Campus Area (GSF) Forecast
Energy Use Intensity Forecast
Demand Forecast
Utility Supply
Primary Energy
Demand and Primary Energy Graphs
This information was developed with information provided by the Office of Institutional Research and Assessment and guidance from Facilities Planning staff. See comments in assumption fields.The forecast was compiled with information from the Capital Plan, Carolina North buildout assessment, and guidance from the Facilities Planning staff.This information characterizes the historical energy use intensity of the campus and describes the assumptions for future energy use intensity.
Campus-wide utility demand calculated based on the assumptions above.
Describes the components of supply used to meet the demand.
Well defined baseline – the “Base Case”Building blocks
Well defined baseline – the “Base Case”Highlights
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
2007 2012 2017 2022 2027 2032 2037 2042 2047
MM
Btu
Main Campus Primary Energy Consumption
Natural Gas
Coal
Purchased Electricity
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
2007 2012 2017 2022 2027 2032 2037 2042 2047
MM
Btu
Main Campus Demand
Chilled Water
Steam
Electricity
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
2012 2017 2022 2027 2032 2037 2042 2047
MM
Btu
Carolina North Demand
Chilled Water
Steam
Electricity
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
2012 2017 2022 2027 2032 2037 2042 2047
MM
Btu
Carolina North Primary Energy Consumption
Natural Gas
Purchased Electricity
20102012
20142016
20182020
20222024
20262028
20302032
20342036
20382040
20422044
20462048
2050 $-
$5.00
$10.00
$15.00
$20.00
$25.00
$-
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
$160.00
$/M
MBt
u
$/M
Wh
NG
Purchased Electricity
Coal
Coal Sub
Raw Biomass
Energy Price Forecasting – Full Cost
Financial risk assessmentClimate change
Most risk exposures of colleges and universities fall within the following six categories:– Strategic risk– Operating risk– Compliance & regulatory risk– Financial risk– Reputational risk– Technology risk
Financial exposure
Proposed legislation informed the development of Energy Strategies’ Policy Scenarios
Federal Cap and Trade Policy Scenarios
Policy Scenario Scope of Coverage Cap
(% below 2000 Levels)Sectors Covered
UNC Chapel Hill Emissions Covered
Allocation(% Purchased)
Use of Offsets andOther Cost Controls
Energy Strategies
"Stringent"
5% by 2015
15% by 2020
40% by 2030
80% by 2050
Economy-wide
Scope 1: direct at source
Scopes 2,3: indirect through suppliers
Overall: 20% auction increasing to 60%
Covered entity: 60% increasing to 100%
No safety valve
U.S. offsets limited to 5% of compliance
No Banking
Energy Strategies
"Moderate"
1% by 2015
10% by 2020
30% by 2030
70% by 2050
Economy-wide
Scope 1: direct at source
Scopes 2,3: indirect through suppliers
Overall: 15% auction increasing to 40%
Covered entity: 30% increasing to 65%
No safety valve
U.S. and international offsets limited to 10%
of compliance
Banking for 5 years
Energy Strategies
"Soft"
1% by 2015
8% by 2020
20% by 2030
50% by 2050
Electric Power (Excluding Cogen), Transportation, &
Manufacturing
Scope 1: excludedScopes 2,3: indirect through suppliers
Overall: 10% auction
Covered entity: 0% increasing to 30%
Safety valve in place
U.S. and international offsets limited to 25%
of compliance
Unlimited banking
6 GHGs—CO2, CH4, N2O, HFCs, PFCs, and
SF6
Upstream for transport fuels & LDC
natural gas; downstream for large coal users and large
point sources
20052007
20092011
20132015
20172019
20212023
20252027
20292031
20332035
20372039
20412043
20452047
20490
2,000
4,000
6,000
8,000
10,000
12,000Cap Levels of Various Legislative Scenarios
Business as UsualBingaman-Specter, S.1766McCain-Lieberman, S.280Olver-Gilchrest, HR.620Boxer-Lieberman-Warner, S.3036Doggett, HR.6316Sanders-Boxer, S.309Waxman-Markey, HR.2454Kerry-Boxer, S.1733Energy Strategies Stringent CaseEnergy Strategies Moderate CaseEnergy Strategies Weak Case
Tota
l Allo
wan
ces
Ava
ilabl
e (M
illio
ns o
f Met
ric
Tons
CO
2e)
0
50
100
150
200
250
300
350
400
2015 2020 2025 2030 2035 2040 2045 2050
2009
$/m
etri
c ton
CO
2
GHG Emission Allowance Price Projections (2009$)
3rd Party Forecasts (2008 Legislation)
Energy Strategies - High Trend (P90)
Energy Strategies - Mid Trend (unweighted or P50)
Energy Strategies - Low Trend (P10)
Energy Strategies - Mid Trend (weighted or EV)
Energy Strategies developed a set of carbon allowance price forecasts…
Financial risk exposure to climate change
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
2010 2015 2020 2025 2030 2035 2040 2045 2050
Annu
al Fi
nanc
ial E
xpos
ure
2009
$ M
M
GH
G Em
issi
ons (
MTC
O2e
)
Main Campus
Subject to Compliance Cost GHG Emissions Not Subject to Compliance Cost
Total GHG Emissions Annual Financial Exposure (2009$MM) - Right Axis
PV of Financial Exposure in 2009$ - $551MM
$0
$2
$4
$6
$8
$10
$12
$14
$16
$18
$20
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
2010 2015 2020 2025 2030 2035 2040 2045 2050
Annu
al Fi
nanc
ial E
xpos
ure
2009
$ M
M
GH
G Em
issi
ons (
MTC
O2e
)
Carolina North
Subject to Compliance Cost GHG Emissions Not Subject to Compliance Cost
Total GHG Emissions Annual Financial Exposure (2009$MM) - Right Axis
PV of Financial Exposure in 2009$ - $42MM
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$200
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
2010 2015 2020 2025 2030 2035 2040 2045 2050
Annu
al Fi
nanc
ial E
xpos
ure
2009
$ M
M
GH
G Em
issi
ons (
MTC
O2e
)
Combined
Subject to Compliance Cost GHG Emissions Not Subject to Compliance CostTotal GHG Emissions Annual Financial Exposure (2009$MM) - Right Axis
PV of Financial Exposure in 2009$ - $593MM
Weak Moderate Stringent
Brea
kthr
ough
Ad
vanc
es
Low Trend (P10) P30Mid Trend
(unweighted or P50)
Mod
erat
e Ad
vanc
es
P30Mid Trend
(weighted or EV)P70
Min
imal
Ad
vanc
es Mid Trend (unweighted or P50)
P70 High Trend (P90)
Tech
nolo
gy S
cena
rio
Legislative Scenario
Sample Alternative
Actionable Alternative: Co-fire 20 Percent Coal Substitute
NPV through 2050
Cumulative Carbon
Abatement (2010 - 2050)
Contribution toward
Neutralilty in
Link to Input Assumptions/Notes Incremental Utility Savings (Costs) ($13,439,739) 1,987,193 2050 Terminal Value?Incremental GHG Compliance Savings (Costs) $28,239,818 Average -8.21% Yes
Reference Case: Avoided Capital Cost $0 55,200 Project LifeYear Implemented: 2015 New Capital Cost ($1,557,343) 30
Implementation Time Frame: Short-term Avoided Operating Costs $0New Operating Costs ($506,850)
Net Cash Flow $12,735,885DPI: 9.2 $53,722,586 Value if 100% credit for avoided MTCDEIRR: 40%
Total Incremental Savings (Cost) w/o Compliance Savings ($15,503,933)Levelized Cost (Savings) per MTCDE Avoided: $22 DACI
Levelized Avoided Compliance Cost per MTCDE Avoided: $40 1.45B C D
A+B+C+D
Electricity SteamChilled Water
Purchased Electricity
NG - Central Coal Coke BiomassCoal
SubstituteSyngas
Transportation Fuels
Primary EnergyOther Short-
Term VariableLong-Term
Variable Total Scope 1 Scope 2 Scope 3
Incremental GHG Compliance Savings
(Costs)
Avoided Capital Cost
Incremental Capital Cost
Avoided Operating Costs
Incremental Operating Costs
Total OPEX/CAPEX
Net Cash Flow
FYE MWh klb thr MWh MMBtu MMBtu tons MMBtu MMBtu MMBtu Gallons 2009$ 2009$ 2009$ 2009$ MTCDE MTCDE MTCDE 2009$ 2009$ 2009$ 2009$ 2009$ 2009$ 2009$ 2009$2010 0 0 0 0 0 0 0 0 0 0 $0 $0 0 0 0 $0 $0 $0 $0 $0 $0 $0 $02011 0 0 0 0 0 0 0 0 0 0 $0 $0 0 0 0 $0 $0 $0 $0 $0 $0 $0 $02012 0 0 0 0 0 0 0 0 0 0 $0 $0 0 0 0 $0 $0 $0 $0 $0 $0 $0 $02013 0 0 0 0 0 0 0 0 0 0 $0 $0 0 0 0 $0 $0 $0 $0 $0 $0 $0 $02014 0 0 0 0 0 0 0 0 0 0 $0 $0 0 0 0 $0 $0 ($2,000,000) $0 $0 ($2,000,000) $0 ($2,000,000)2015 0 0 0 0 0 -489,162 0 0 489,162 0 $286,998 $286,998 -58,485 0 0 $587,316 $0 $0 $0 ($40,000) ($40,000) $0 $834,3132016 0 0 0 0 0 -439,516 0 0 439,516 0 $114,760 $114,760 -52,549 0 0 $609,135 $0 $0 $0 ($40,000) ($40,000) $0 $683,8962017 0 0 0 0 0 -463,259 0 0 463,259 0 $83,977 $83,977 -55,388 0 0 $731,870 $0 $0 $0 ($40,000) ($40,000) $0 $775,8472018 0 0 0 0 0 -463,656 0 0 463,656 0 $9,997 $9,997 -55,436 0 0 $826,286 $0 $0 $0 ($40,000) ($40,000) $0 $796,2822019 0 0 0 0 0 -463,010 0 0 463,010 0 ($72,093) ($72,093) -55,358 0 0 $922,545 $0 $0 $0 ($40,000) ($40,000) $0 $810,4522020 0 0 0 0 0 -485,828 0 0 485,828 0 ($164,470) ($164,470) -58,086 0 0 $1,074,033 $0 $0 $0 ($40,000) ($40,000) $0 $869,5642021 0 0 0 0 0 -486,677 0 0 486,677 0 ($255,243) ($255,243) -58,188 0 0 $1,198,445 $0 $0 $0 ($40,000) ($40,000) $0 $903,2022022 0 0 0 0 0 -480,643 0 0 480,643 0 ($351,753) ($351,753) -57,467 0 0 $1,309,275 $0 $0 $0 ($40,000) ($40,000) $0 $917,5222023 0 0 0 0 0 -478,359 0 0 478,359 0 ($457,715) ($457,715) -57,193 0 0 $1,432,604 $0 $0 $0 ($40,000) ($40,000) $0 $934,8882024 0 0 0 0 0 -476,075 0 0 476,075 0 ($567,502) ($567,502) -56,920 0 0 $1,558,949 $0 $0 $0 ($40,000) ($40,000) $0 $951,4472025 0 0 0 0 0 -473,791 0 0 473,791 0 ($681,513) ($681,513) -56,647 0 0 $1,688,068 $0 $0 $0 ($40,000) ($40,000) $0 $966,5542026 0 0 0 0 0 -471,507 0 0 471,507 0 ($794,989) ($794,989) -56,374 0 0 $1,833,598 $0 $0 $0 ($40,000) ($40,000) $0 $998,6102027 0 0 0 0 0 -469,223 0 0 469,223 0 ($905,546) ($905,546) -56,101 0 0 $1,982,388 $0 $0 $0 ($40,000) ($40,000) $0 $1,036,8422028 0 0 0 0 0 -466,939 0 0 466,939 0 ($1,017,786) ($1,017,786) -55,828 0 0 $2,134,138 $0 $0 $0 ($40,000) ($40,000) $0 $1,076,3522029 0 0 0 0 0 -464,655 0 0 464,655 0 ($1,135,545) ($1,135,545) -55,555 0 0 $2,288,555 $0 $0 $0 ($40,000) ($40,000) $0 $1,113,0102030 0 0 0 0 0 -462,371 0 0 462,371 0 ($1,254,868) ($1,254,868) -55,282 0 0 $2,445,352 $0 $0 $0 ($40,000) ($40,000) $0 $1,150,4842031 0 0 0 0 0 -460,086 0 0 460,086 0 ($1,380,736) ($1,380,736) -55,009 0 0 $2,624,751 $0 $0 $0 ($40,000) ($40,000) $0 $1,204,0152032 0 0 0 0 0 -457,802 0 0 457,802 0 ($1,517,420) ($1,517,420) -54,736 0 0 $2,806,913 $0 $0 $0 ($40,000) ($40,000) $0 $1,249,4932033 0 0 0 0 0 -455,518 0 0 455,518 0 ($1,646,826) ($1,646,826) -54,463 0 0 $2,967,014 $0 $0 $0 ($40,000) ($40,000) $0 $1,280,1882034 0 0 0 0 0 -453,234 0 0 453,234 0 ($1,759,389) ($1,759,389) -54,189 0 0 $3,104,374 $0 $0 $0 ($40,000) ($40,000) $0 $1,304,9852035 0 0 0 0 0 -450,950 0 0 450,950 0 ($1,864,020) ($1,864,020) -53,916 0 0 $3,243,310 $0 $0 $0 ($40,000) ($40,000) $0 $1,339,2902036 0 0 0 0 0 -448,666 0 0 448,666 0 ($1,978,509) ($1,978,509) -53,643 0 0 $3,406,821 $0 $0 $0 ($40,000) ($40,000) $0 $1,388,3122037 0 0 0 0 0 -449,413 0 0 449,413 0 ($2,115,499) ($2,115,499) -53,733 0 0 $3,591,943 $0 $0 $0 ($40,000) ($40,000) $0 $1,436,4442038 0 0 0 0 0 -450,159 0 0 450,159 0 ($2,252,150) ($2,252,150) -53,822 0 0 $3,776,401 $0 $0 $0 ($40,000) ($40,000) $0 $1,484,2512039 0 0 0 0 0 -450,906 0 0 450,906 0 ($2,388,130) ($2,388,130) -53,911 0 0 $3,959,798 $0 $0 $0 ($40,000) ($40,000) $0 $1,531,6682040 0 0 0 0 0 -451,652 0 0 451,652 0 ($2,527,173) ($2,527,173) -54,000 0 0 $4,152,434 $0 $0 $0 ($40,000) ($40,000) $0 $1,585,2612041 0 0 0 0 0 -452,399 0 0 452,399 0 ($2,667,720) ($2,667,720) -54,090 0 0 $4,339,861 $0 $0 $0 ($40,000) ($40,000) $0 $1,632,1412042 0 0 0 0 0 -453,145 0 0 453,145 0 ($2,803,849) ($2,803,849) -54,179 0 0 $4,520,836 $0 $0 $0 ($40,000) ($40,000) $0 $1,676,9872043 0 0 0 0 0 -453,892 0 0 453,892 0 ($2,945,926) ($2,945,926) -54,268 0 0 $4,724,104 $0 $0 $0 ($40,000) ($40,000) $0 $1,738,1792044 0 0 0 0 0 -454,638 0 0 454,638 0 ($3,106,513) ($3,106,513) -54,357 0 0 $4,954,206 $0 $0 $0 ($40,000) ($40,000) $0 $1,807,6932045 0 0 0 0 0 -455,384 0 0 455,384 0 ($3,289,773) ($3,289,773) -54,447 0 0 $5,217,632 $0 $0 $0 ($40,000) ($40,000) $0 $1,887,8592046 0 0 0 0 0 -456,131 0 0 456,131 0 ($3,492,381) ($3,492,381) -54,536 0 0 $5,499,065 $0 $0 $0 ($40,000) ($40,000) $0 $1,966,6842047 0 0 0 0 0 -456,877 0 0 456,877 0 ($3,709,398) ($3,709,398) -54,625 0 0 $5,800,741 $0 $0 $0 ($40,000) ($40,000) $0 $2,051,3432048 0 0 0 0 0 -457,624 0 0 457,624 0 ($3,942,584) ($3,942,584) -54,714 0 0 $6,125,093 $0 $0 $0 ($40,000) ($40,000) $0 $2,142,5092049 0 0 0 0 0 -458,370 0 0 458,370 0 ($4,193,841) ($4,193,841) -54,804 0 0 $6,474,730 $0 $0 $0 ($40,000) ($40,000) $0 $2,240,8892050 0 0 0 0 0 -459,117 0 0 459,117 0 ($4,465,198) ($4,465,198) -54,893 0 0 $6,852,422 $0 $0 $0 ($40,000) ($40,000) $0 $2,347,223
Terminal Value: $0 0 0 0 $0 $0 $0 $0 $0 $0 $0 $0A 36 0 0 B C D A+B+C+D
Rock Wool Sales
Incremental Non-Utility OPEX/Capital Savings (Cost)
HR_Chiller_IRB_2
AIncremental Utility Demand (MMBtu) Incremental Primary Energy Input Incremental Utility Savings (Costs) Incremental GHG Savings (Cost)
HOME
Co-fire 20 Percent Coal Substitute
Actionable Alternative: Co-fire 20 Percent Coal Substitute
NPV through 2050
Cumulative Carbon
Abatement (2010 - 2050)
Contribution toward
Neutralilty in
Link to Input Assumptions/Notes Incremental Utility Savings (Costs) ($13,439,739) 1,987,193 2050Incremental GHG Compliance Savings (Costs) $28,239,818 Average -8.21%
Reference Case: Avoided Capital Cost $0 55,200Year Implemented: 2015 New Capital Cost ($1,557,343)
Implementation Time Frame: Short-term Avoided Operating Costs $0New Operating Costs ($506,850)
Net Cash Flow $12,735,885DPI: 9.2IRR: 40%
Total Incremental Savings (Cost) w/o Compliance Savings ($15,503,933)Levelized Cost (Savings) per MTCDE Avoided: $22 DACI
Levelized Avoided Compliance Cost per MTCDE Avoided: $40 1.45
HR_Chiller_IRB_2
HOME
Co-fire 20 Percent Coal Substitute
ECM
(Min
imal
Fin
anci
al In
vest
men
t)
SB 6
68 M
ain
Co-fi
re 2
0 Pe
rcen
t Coa
l Sub
stitu
te
100%
Coa
l Sub
stitu
te
50%
Coa
l Sub
stitu
te
Plas
ma
Arc
Gas
ifica
tion
of M
SW -
Syng
as
50%
NG
, 50%
Coa
l Sub
stitu
te
Plas
ma
Arc
Gas
ifica
tion
of M
SW -
Syng
as p
lus
NG
(Re
plac
e A
ll Co
al) 50
Per
cent
Nat
ural
Gas
Larg
e Sc
ale
Biom
ass
Plan
t
Busi
ness
-as-
Usu
al E
mis
sion
s (2
050)
: 669
,000
MTC
DE*
*
($200)
($150)
($100)
($50)
$0
$50
$100
$150
Leve
lized
Cos
t (S
avin
gs)
per M
TCO
2e
Average Contribution Toward Neutrality in 2050 (1,000's MTCDE)
Thin clients where appropriate
Business Travel
Behavioral_Initiative
Computer Standby Mode (Purchasing/Recycling)Chiller Plant Efficiency (incl. phase I, phase II, and Tomkins)ECM (Minimal Financial Investment)
Commuter Emissions
Commercial Mail Management
SB 668 Main
ECM (Aggressive Financial Investment)
Campus Fleet
Heat Recovery Chillers and Solar Thermal (CN)
Compost
SB 668 CN
Heat Recovery Chiller at IRB (Phase II)
Consolidated Delivery
Heat Recovery Chiller at IRB (600 ton)
Landfill Gas (CN)
Co-fire 20 Percent Coal Substitute
Biomass Gasification at Carolina North (Phase I)
100% Coal Substitute
50% Coal Substitute
Plasma Arc Gasification of MSW - Syngas
Shops and Informal Contract Recycling
ECM (Moderate Financial Investment)
50% NG, 50% Coal Substitute
Plasma Arc Gasification of MSW - Syngas plus NG (Replace All Coal)50 Percent Natural Gas
Biomass Gasification w/ Biochar Production at CNLarge Scale Biomass Plant
Biomass Gasification at Carolina North (Phase II)Solar Thermal (CN)
Solar Thermal to Electricity (Troughs) (CN)
Solar Thermal to Electric (Dish Sterling) (CN)
Demo Scale Concentrating Solar PV (CN)
Adjusted Levelized Cost (Savings)
>
<**Net of Utility Footprint change
CAP Portfolio – Near-term Alternatives
– Thin Clients– Business Travel– Duplex Printing– Behavioral Initiatives– Computer Standby– Chiller Plant Efficiency
Projects– Low-cost ECMs– Commuter Travel
– Commercial Mail Management
– Green Building (SB 668)– Campus Fleet– Composting– Heat Recovery Chillers at
IRB (Phase 1 and 2)– Consolidated Delivery
The following are near-term alternatives (implemented 2010 through 2015) that are cost effective regardless of the value of greenhouse gas emissions abated:
CAP Portfolio – Near-term Alternatives
Additionally, the following near-term alternatives are included because they are either already in progress or they would be cost effective in a carbon-constrained world:
– Landfill Gas– Co-Fire 20% Coal Substitute
ECM
(Min
imal
Fin
anci
al In
vest
men
t)
SB 6
68 M
ain
Co-fi
re 2
0 Pe
rcen
t Coa
l Sub
stitu
te
Busi
ness
-as-
Usu
al E
mis
sion
s (2
050)
: 669
,000
MTC
DE*
*
($200)
($150)
($100)
($50)
$0
$50
$100
$150
Leve
lized
Cos
t (S
avin
gs)
per M
TCO
2e
Average Contribution Toward Neutrality (1,000's MTCDE)
Thin clients where appropriate
Business Travel
Behavioral_Initiative
Computer Standby Mode (Purchasing/Recycling)Chiller Plant Efficiency (incl. phase I, phase II, and Tomkins)ECM (Minimal Financial Investment)Commuter Emissions
Commercial Mail Management
SB 668 Main
Campus Fleet
Compost
SB 668 CN
Heat Recovery Chiller at IRB (Phase II)Consolidated Delivery
Heat Recovery Chiller at IRB (600 ton)Landfill Gas (CN)
Co-fire 20 Percent Coal SubstituteAdjusted Levelized Cost (Savings)
>
<
Near-term Alternatives Abatement
($40.0)
($20.0)
$0.0
$20.0
$40.0
$60.0
$80.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
2009
$ M
M
Incremental Operating Savings (Cost) GHG Compliance SavingsIncremental P & I Combined Incremental Savings (Cost) w/o GHG SavingsCombined Incremental Savings (Cost) w/ GHG Savings
NPV w/o GHG Compliance Savings ($MM): $152.7
PV of Incremental Capital ($MM): $60.0NPV w/ GHG Compliance Savings ($MM): $289.4
Path: Near-term Alternatives – Cash Flow
Near-term Alternatives - Impact on Energy Demand and Coal Use
0
100,000
200,000
300,000
400,000
500,000
600,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
MW
h
Electricity Demand
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
2,000,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
klb
Steam Demand
0
50,000,000
100,000,000
150,000,000
200,000,000
250,000,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
ton-
hour
CW Demand
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
Tons
Coal
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
MW
h
Electricity Demand
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
klb
Steam Demand
0
50,000,000
100,000,000
150,000,000
200,000,000
250,000,000
300,000,000
2010
2015
2020
2025
2030
2035
2040
2045
2050
ton-
hour
CW Demand
Long-term Portfolio PathsCommon Alternatives
The following alternatives will be implemented in the mid- or long-term and will be common to all long-term Portfolio Paths:
– Solar Thermal/Heat Recovery Chillers (Carolina North)– Biomass Gasification Plant Phases 1 and 2 (Carolina North)– Moderate ECM Implementation (Main Campus)
Long-term Portfolio Paths
After the near-term alternatives are implemented, there are 4 mutually exclusive paths UNC may follow to carbon neutrality. These paths are characterized by a major change to the central heating plant:– 50% Coal Substitute, 50% Natural Gas– 100% Coal Substitute– MSW Plasma Gasification – Syngas w/ NG (Replace all
Coal)– Large Scale Biomass Plant
($40.0)
($20.0)
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
2009
$ M
M
Incremental Operating Savings (Cost) GHG Compliance SavingsIncremental P & I Combined Incremental Savings (Cost) w/o GHG SavingsCombined Incremental Savings (Cost) w/ GHG Savings
NPV w/o GHG Compliance Savings ($MM): $61.8
PV of Incremental Capital ($MM): $105.3NPV w/ GHG Compliance Savings ($MM): $287.1
Path: 50% NG, 50% Coal Substitute
Portfolio Comparison – Cash Flow
($40.0)
($20.0)
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
2009
$ M
M
Incremental Operating Savings (Cost) GHG Compliance SavingsIncremental P & I Combined Incremental Savings (Cost) w/o GHG SavingsCombined Incremental Savings (Cost) w/ GHG Savings
NPV w/o GHG Compliance Savings ($MM): $83.7
PV of Incremental Capital ($MM): $124.5NPV w/ GHG Compliance Savings ($MM): $297.2
Path: Plasma Arc Gasification of MSW - Syngas plus NG (Replace All Coal)
($40.0)
($20.0)
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
2009
$ M
M
Incremental Operating Savings (Cost) GHG Compliance SavingsIncremental P & I Combined Incremental Savings (Cost) w/o GHG SavingsCombined Incremental Savings (Cost) w/ GHG Savings
NPV w/o GHG Compliance Savings ($MM): $79.2
PV of Incremental Capital ($MM): $105.3NPV w/ GHG Compliance Savings ($MM): $334.3
Path: 100% Coal Substitute
($40.0)
($20.0)
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
2010 2015 2020 2025 2030 2035 2040 2045 2050
2009
$ M
M
Incremental Operating Savings (Cost) GHG Compliance SavingsIncremental P & I Combined Incremental Savings (Cost) w/o GHG SavingsCombined Incremental Savings (Cost) w/ GHG Savings
NPV w/o GHG Compliance Savings ($MM): $86.0
PV of Incremental Capital ($MM): $133.7NPV w/ GHG Compliance Savings ($MM): $279.3
Path: Large Scale Biomass Plant
Conclusions1. Almost 50% reduction from business-as-usual
GHG emissions and coal use achieved by 2020.2. Several viable long-term paths to GHG mitigation
and the elimination of coal are being pursued.3. CFB boilers offer valuable “optionality” for use of
alternative solid fuels.4. GHG mitigation greatly accelerated in a cost
effective manner if a price is legislated for GHG emissions.