Click to edit Master subtitle style 5/24/12Parliamentary Hearings on the ISMO Bill Public Hearings...
-
Upload
myles-hood -
Category
Documents
-
view
219 -
download
0
Transcript of Click to edit Master subtitle style 5/24/12Parliamentary Hearings on the ISMO Bill Public Hearings...
Click to edit Master subtitle style
5/24/12 Parliamentary Hearings on the ISMO Bill
Public Hearings on the ISMO Bill [B9 – 2012]
Parliamentary Portfolio Committee on Energy
Presented by Mark PickeringMeridian Economics15 May, 2012
5/24/12 Parliamentary Hearings on the ISMO Bill
Why is the ISMO Important?
5/24/12 Parliamentary Hearings on the ISMO Bill
22
Cape Times of May 1882: "The House of Assembly
continues to be lighted by the electric light and the
result has so far been highly satisfactory. The light is full, clear, pervasive and steady,
and greatly improves the appearance of the chamber."
Electricity Supply Commission
(ESCOM) established by the
government of South Africa in
terms of the Electricity Act
(1922).
All assets of the Victoria Falls Power
Company expropriated and taken over by
Escom in accordance with the Power Act of
1910 and the Electricity Act of 1922.
The Electricity Supply Commission (Escom) replaced by
an Electricity Council and a Management Board. Escom
renamed as Eskom
Government targets 30% Independent
Power Producers
1882 1923 1987 20121948
100% 100%
~20% ~5%
Gvt 30% IPP
policy
• Since 1923 legislation and government action has actively encouraged state-owned power production, and actively discouraged private power production.
• The ISMO potentially represents the most fundamental shift in power sector legislation since 1922.• But will the ISMO achieve government’s policy goal to facilitate investment by IPPs?
Private power production over time (% of total)
2001
<5%
ISMO to be established
Source: http://heritage.eskom.co.za
5/24/12 Parliamentary Hearings on the ISMO Bill
Why is the ISMO Important?
• We have had favourable Government policy on private investment in power generation since the 1998 White Paper on Energy – but very little has been achieved.
• By 2012 private investment decisions account for less than 2% of new generation capacity.• Even if the entire REIPPPP (3,725MW) is included, private investment is still under 20%. 5/24/12 Parliamentary Hearings on
the ISMO Bill33
2001 2004 2010 20122006
New generation investment decisions since 2001
Government targets 30%
Independent Power
Producers
Government approves Eskom investments:Camden RTS (1,520MW) Grootvlei RTS (1,200MW) Komati RTS (1,000MW)Medupi (4,800MW)Kusile (4,800 MW)Ingula (1,300 MW)
Cabinet decision. DOE to procure 1,000MW of OCGT peaker from IPPs. Eskom to build 1,000 MW
2003
Government approves additional
1,000MW of Eskom OCGT peaker plant
Eskom signs Power Purchase
Agreements (PPAs) with IPPs
under the MTPPP for
273MW
DOE announces Preferred
Bidders for 1,415 MW of
renewable IPPs
Eskom ~16,000 MW
273 MW1,000 MW
14,620 MW
1,000 MW
IPPs 273 MW
5/24/12 Parliamentary Hearings on the ISMO Bill
The Standard Model of Institutional Reform
• Government is not following the standard reform model.
• Instead we are pursuing a Hybrid Model. 5/24/12 Parliamentary Hearings on
the ISMO Bill44
Generation
Transmission
Distribution
Plan
ning
Vertical and horizontal
disaggregation
G G
Wholesale Market
G
Transmission
Retail Market
C
G
Distrib Distrib Distrib
C C C
Vertically Integrated
State-Owned Utility
Competitive markets with regulated monopolies
Competition
Competition
Monopoly
Monopoly
5/24/12 Parliamentary Hearings on the ISMO Bill
The Hybrid Model
• What functions need to be isolated from Eskom to make the Hybrid Model function effectively?
5/24/12 Parliamentary Hearings on the ISMO Bill
55
Generation
Transmission
Distribution
Plan
ning
Legal and organisational
reforms
Vertically Integrated
State-Owned UtilityEskom
Key functionsremoved
Eskom
5/24/12 Parliamentary Hearings on the ISMO Bill
The Hybrid ModelSix key functions must be performed
Parliamentary Hearings on the ISMO Bill
66
Who should be responsible for generation expansion planning & security of supply?
Will plans be indicative or mandatory? Exclusive or flexible?
How will new-build opportunities be allocated between the incumbent SOE (Eskom) and IPPs?
How should we deal with unsolicited bids?
Who should manage the procurement of IPPs? Who should be responsible for contract negotiations? Who should approve long term PPAs?
How do we avoid potential conflicts of interest when a SOE is the Single-Buyer?
How do we ensure fair dispatch between SOE generators and IPPs?
How do we ensure equitable grid access?
5/24/12
Allocation
Procurement
Buyer
System Operator
Transmission
Planning
5/24/12 Parliamentary Hearings on the ISMO Bill
ISMO
Effect of Draft Legislation ISMO Bill and ERA 2nd Amendment Bill
77
Eskom Holdings
C C C
D (Regions 1-6)
KIC
C
Mun
KSACS
Mun
Planning
Allocation
Procurement
Buyer
System Operator
TransmissionEffect of the draft legislation• ISMO reports to MOE• ISMO performs just three of the
six functions• MOE takes the key decisions on
Planning and Allocation• Transmission remains with
Eskom.
Will this be effective?
5/24/12 Parliamentary Hearings on the ISMO Bill
Scenarios
Determinations
Eskom Gx Imp Exp
IPPs
Minister of Energy
5/24/12 Parliamentary Hearings on the ISMO Bill
Draft LegislationComment
• We welcome the decision to restructure the electricity industry by creating the ISMO.
• We agree that the Hybrid Model is a practical way forward.
• This model may be more difficult to implement than it may first appear.
• Better integration of the six key functions will lead to better results.
• We recommend that all six functions should be housed within one institution – the ISMO
– more commonly known as a Transmission System Operator or TSO.
5/24/12 Parliamentary Hearings on the ISMO Bill
88
Planning
Allocation
Procurement
Buyer
System Operator
Transmission
ISMO
5/24/12 Parliamentary Hearings on the ISMO Bill
Planning and Allocation FunctionsWho will implement IRP2010?
New build options
Coal (PF, FBC,
imports, own build)
Nuclear Import hydro Gas – CCGT Peak – OCGT Wind CSP Solar PV
MW MW MW MW MW MW MW MW
2010 0 0 0 0 0 0 0 02011 0 0 0 0 0 0 0 02012 0 0 0 0 0 0 0 3002013 0 0 0 0 0 0 0 3002014 5001 0 0 0 0 400 0 3002015 5001 0 0 0 0 400 0 3002016 0 0 0 0 0 400 100 3002017 0 0 0 0 0 400 100 3002018 0 0 0 0 0 4004 1004 3004 2019 250 0 0 2373 0 4004 1004 3004 2020 250 0 0 2373 0 400 100 3002021 250 0 0 2373 0 400 100 3002022 250 0 1 1432 0 805 400 100 3002023 250 1 600 1 1832 0 805 400 100 3002024 250 1 600 2832 0 0 800 100 3002025 250 1 600 0 0 805 1 600 100 1 0002026 1 000 1 600 0 0 0 400 0 5002027 250 0 0 0 0 1 600 0 5002028 1 000 1 600 0 474 690 0 0 5002029 250 1 600 0 237 805 0 0 1 0002030 1 000 0 0 948 0 0 0 1 000Total 6 250 9 600 2 609 2 370 3 910 8 400 1 000 8 400
Firm commitment
necessary now
Final commitment
in IRP 2012
1. Built, owned & operated by IPPs 2. Commitment necessary due to required high-voltage infrastructure, which has long lead time 3. Commitment necessary due to required gas infrastructure, which has long lead time 4. Possibly required grid upgrade has long lead time and thus makes commitment to power capacity
necessary
(DOE, March 2011)
The IRP will clearly require significant investment by IPPs.
These investments have very long lead times.
5/24/12 99 Parliamentary Hearings on the ISMO Bill
5/24/12 Parliamentary Hearings on the ISMO Bill
7
Planning and Allocation Functions
Who will implement IRP2010?
• The Minister has had responsibility for Planning and Allocation functions under the ERA since 2006
• The Minister has still to determine which portions of the plan should be done by Eskom and which should be done by IPPs
– The Minister has indicated that she will issue a determination that 3,725 MW of renewables should be done by IPPs, but has still to gazette this.
• NERSA cannot license investments outside of the IRP
• Without a positive determination it is very risky for an IPP to invest in project development.
5/24/12 Parliamentary Hearings on the ISMO Bill
1010
Total additional new capacity (without committed) until 2030 in GW
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
5/24/1
2
5/24/1
2
5/24/12
5/24/12
5/24/12
5/24/12
5/24/12
Policy-Adjusted IRP
Import
15%
23%
6%
6%
9%
42%
Share of total new GW
(DOE, March 2011)
5/24/12 Parliamentary Hearings on the ISMO Bill
Investment OutcomesGreenfield IPPs in Africa
Source: based on WB PPI database as well as author’s compilation. Notes: (X) designates projects were cancelled; * designates projects are under construction; emergency power units not depicted.
Morocco (3): Tetouan, Jorf Lasfar, Tahaddart Tunisia (2): El Biban, Rades II
Algeria (2): Kahraba, Kahrama
Egypt (3): Sidi Krir, Port Said, Suez
Ethiopia (1): Gojeb*
Kenya (4): Westmont, Iberafrica, OrPower4, Tsavo
Tanzania (4):Tanwat, IPTL, Songas, Mtwara
Mauritius (4): Belle Vue, Deep River, FUEL, St Aubin Angola
(1):Chicapa*
Senegal (2): GTI Dakar, Kounoune I IPP*
Congo (1): Sonda (X)
Nigeria (3): AES Nigeria Barge, Okpai, Afam*
Ghana (1): Takoradi II
Cote D’Ivoire (2): Vridi Ciprel, Azito
Burkina Faso (1): Hydro Afrique
(Eberhard, 2010. UCT GSB)
5/24/12 1111 Parliamentary Hearings on the ISMO Bill
Hybrid Markets:• 40 IPPs• 15 Countries• 10,000MW• US$8 billion
investedIt can be done!
5/24/12 Parliamentary Hearings on the ISMO Bill
Planning and Allocation Functions
• We recommend that the ISMO rather than the Minister should be responsible for the Planning and Allocation functions
– Capacity and expertise will reside within the ISMO– The ISMO will hold demand and supply side data– Accountability for results should be clearly allocated– Planning needs to be closely linked to procurement
5/24/12 Parliamentary Hearings on the ISMO Bill
1212
Planning
Allocation
Procurement
Buyer
System Operator
Transmission
ISMO
5/24/12 Parliamentary Hearings on the ISMO Bill
Planning and Allocation Functions
• We recommend that the Minister should NOT be responsible for the Planning and Allocation functions
– The Ministry lacks capacity to perform the highly technical and complex planning function
– The Minister already has sufficient powers to determine policy and influence planning and allocation
• e.g. government’s 30% IPP policy– The Minister should avoid conflicts of interest
• Minister should not develop projects– Sound governance processes require checks and
balances• NERSA and Minister should have powers of review
• We therefore recommend that the legislation should be amended to transfer Planning and Allocation functions to the ISMO, with provision for Ministerial guidance via explicit regulations and NERSA review.
5/24/12 Parliamentary Hearings on the ISMO Bill
1313
Planning
Allocation
Procurement
Buyer
System Operator
Transmission
ISMO
5/24/12 Parliamentary Hearings on the ISMO Bill
Transmission Function
• Access to the grid is essential for generation projects
• We recommend that the Transmission function should be transferred to the ISMO in order to:
– Overcome Eskom’s conflict of interest as the dominant generator and grid owner/operator
– Strengthen the ISMO’s balance sheet– Promote a balanced approach between Supply-side
and Demand-side solutions• Vertical disaggregation is a common industry
reform which lenders and investors should be familiar with. 5/24/12 Parliamentary Hearings on
the ISMO Bill1414
Planning
Allocation
Procurement
Buyer
System Operator
Transmission
ISMO
5/24/12 Parliamentary Hearings on the ISMO Bill
Conclusion• South Africa requires massive investment in new
generation capacity. • Eskom and government cannot afford to do this alone. • IPPs bring innovation and capital, as the REIPPPP is
demonstrating.• The introduction of IPPs needs to be speeded up by
establishing a dedicated, competent, state-owned entity that is independent of Eskom.
• Hybrid markets require effective integration of the six functions. This is best done within one institutions – the ISMO.
Parliamentary Hearings on the ISMO Bill
1515
Planning
Allocation
Procurement
Buyer
System Operator
Transmission
ISMO
5/24/12
Click to edit Master subtitle style
5/24/12 Parliamentary Hearings on the ISMO Bill
Thank You