CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report - March 2014
CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report #2 - March 2014
description
Transcript of CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report #2 - March 2014
1[19-Mar-2014] «BE/RF»
CLIC TBM Prototype T0@CLEX
Integration. Inventory. Planning
Report #2 - March 2014
Dmitry Gudkov
1
2[19-Mar-2014] [CMWG Meeting] «BE/RF» 2
CONTENTS
2D layout
Inputs
Supporting elements for CLEX components in the working area• Integration• Inventory
Integration of TBM and modification of CLEX components. Drive beam
Integration of TBM and modification of CLEX components. Probe beam
Inventory of the CLEX components (working area, preliminary)
Status of components production for TBM
Planning for the TBM installation in CLEX
Documentation
3[19-Mar-2014] [CMWG Meeting] «BE/RF» 3
TBM Prototype T0@CLEX. Integration. Phase 1.
Igor Syratchev
4[19-Mar-2014] [CMWG Meeting] «BE/RF» 4
TBM Prototype T0@CLEX. Integration. Phase 1.
Igor Syratchev
5[19-Mar-2014] [CMWG Meeting] «BE/RF» 5
TBM Prototype T0@CLEX. Integration. Phase 1.
Igor Syratchev
6[19-Mar-2014] [CMWG Meeting] «BE/RF» 6
TBM Prototype T0@CLEX. Integration. Phase 3.1.
Mod
ule
bord
er Module border
• 1 PETS and 1 SAS will be powered;• VGVs are installed on each extremity to
detach the test stand;
2D layout is based on one phase 3.1 (see above)Phase 3.3 requires another modification of the primary RF network (2..3 new waveguides, splitter, directional coupler).
7[19-Mar-2014] [CMWG Meeting] «BE/RF» 7
INPUTS. Integration of TBM. Probe beam
3D model is based on the document prepared by Wilfrid Farabolini: EDMS 1366387
Are implemented in the drawing CLIATCIN0005 (under way):
8[19-Mar-2014] [CMWG Meeting] «BE/RF» 8
INPUTS. Integration of TBM. Drive beam
Positions of the quadrupoles, input from Jacob Esberg: EDMS 136638821.33596587 '"QUADRUPOLE"' '"TL2.QDD10"' 0.575 UNCHANGED23.29201587 '"QUADRUPOLE"' '"CM.QFD0310"' 1.95605 UNCHANGED23.79201587 '"QUADRUPOLE"' '"CM.QDD0315"' 0.5 UNCHANGED24.29201587 '"QUADRUPOLE"' '"CM.QFD0320"' 0.5 UNCHANGED25.90225587 '"RFCAVITY"' '"P1"' 1.61024 UNCHANGED27.98793587 '"QUADRUPOLE"' '"CM.QFD0565A"' 2.08568 Has been increased28.39727587 '"QUADRUPOLE"' '"CM.QFD0565B"' 0.40934 Has been decreased
29.961016 '"RFCAVITY"' '"P2"' 1.56374 has been increased30.428016 '"QUADRUPOLE"' '"QTB1"' 0.467 0.467 As specified30.965016 '"RFCAVITY"' '"P3"' 0.537 0.537 As specified31.432016 '"QUADRUPOLE"' '"QTB2"' 0.467 0.467 As specified
33.19201587 '"QUADRUPOLE"' '"CM.QFD0560"' 1.76 1.76 As specified34.19201587 '"QUADRUPOLE"' '"CM.QFD0570"' 1 UNCHANGED37.19399775 '"RBEND"' '"CM.BHB0600"' 3.001982 UNCHANGED
Are implemented in the drawing CLIATCIN0005 (under way):
9[19-Mar-2014] [CMWG Meeting] «BE/RF» 9
TBM implantation in CLEXTask Duration Date
0 Remove the safety barriers 0.5 days 1.061 Preparation of the storage tables inside CLEX 0.5 days 1.06
2 Radioprotection Survey Visit 1 day 2.06
3 Dismantling of the shielding blocks (to get the direct access for new equipment)
1 day 2.06
4 Organizing of free access to CLEX building 1day 3.06
storage
10[19-Mar-2014] [CMWG Meeting] «BE/RF» 10
TBM implantation in CLEXTask Duration Date
5 Initial measurements in CLEX 2 days 04.0605.06
6 Dismantling of TBTS PB and DB tanks- disconnection of electrical cables and water pipes
- disconnection and dismantling of RF network
7 days 03.0611.06
11[19-Mar-2014] [CMWG Meeting] «BE/RF» 11
TBM implantation in CLEXTask Duration Date
7 - dismantling and transport of the TBTS PB Tank to the buffer zone 1 day 10.06
12[19-Mar-2014] [CMWG Meeting] «BE/RF» 12
TBM implantation in CLEXTask Duration Date
8 - dismantling and transport of the TBTS DB Tank and transport to the storage
1 day 11.06
13[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
9 - Disconnection of all cables (+ labelling) and pipes in the working area
5.5 days 12.0619.06
~14 meters
14[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
10 - Removal of the equipment in the working area 4.5 days 16.0620.06Component Pic Quantity Component Pic Quantity
Quadrupoles 12 Supports 10
Correctors 10Sector
vacuum valves 4
BPMs and diagnostics chambers
8
Pumping ports
(including valves and
pumps)
5
Flashbox 1 Drift Tubes and bellows 20 + 22
15[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
11 - Dismantling of the yellow girders and feet 3 days 23.0625.06
12 - Removal of the cooling distribution (central line) 3 days 26.0630.06
13 - Precise Floor marking before drilling of the holes for installation of the TBM supporting system: 32 holes in total
For dimensions: DRAWING CLIATCIN0004
1 days 01.07
14 Drilling of the floor for all the supporting equipment 1.5 days 02.0703.07
Task Quantity
Feet to be removed from area 6
Feet to be replaced 2
Girders to be removed from area 6
Girders to be replaced 6
New girders to be manufactured(see on next slides)
3
16[19-Mar-2014] [CMWG Meeting] «BE/RF»
Supporting Elements for TBM and CLEX Components
2 Feet to be reused in different place (8 holes to be drilled)
New girders (x3)
TBM supporting benches (24 holes to be drilled for installation)
• All green feet will not be moved• Green girders will be moved by several cm.
17[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
15 - Installation of the supporting elements of the TBM and CLEX components
Installation of the new yellow supporting girders (1 day) Transport and Installation of the TBM extremity benches (1 day) Geometrical control of the extremity benches (1 day)
3 days 07.0709.07
16 - TBM installation and assemblySee next slides
22 days 10.0708.08
18[19-Mar-2014] [CMWG Meeting] «BE/RF»
Installation of the TBM supporting systemTask Duration Date
17 Installation of the TBM supporting system 5 days 10.07-16.0718 Geometrical control of the TBM supporting system 1 day 17.0719 Alignment of the girders (with respect to the existing beam) 1 day 18.0720 Installation of alignment’s device (wire, cable, sensors, data acquisition, …) 2 days 21.07-22.0721 Absolute measurement (cWPS sensors vs AT401 tracker) 1 day 23.0722 Test of actuators displacement on 1 mm range (girder unloaded) - OPTIONALLY 1 day 24.0723 Test of the Articulation Point (girder unloaded) - OPTIONALLY 1 day 25.07
19[19-Mar-2014] [CMWG Meeting] «BE/RF»
1. (DBQ+BPM) x 2; SAS x 2; PETS x 2; + fixating clamps2. Vacuum equipment (minipumps; valves; gauges)
Installation of the components of the TBM + alignment control
Task Duration Date24 Installation of the components of the TBM + alignment control + cooling test 5.5 days 28.07-04.0825 Cables for TBM routing and connection to the equipment in the external shelter 2.5 days 04.08-08.08
3. Supporting frame + RF load
4. Supporting frame + RF network
5. Cooling tubes (fittings are pre-installed)
The TBM assembly is performed by subassemblies:
Transport of the girders with installed components requires the design (+safety validation) of the transport tooling. Subassemblies will reduce the overall installation time.
To compensate the weight of SAS #2 and #4 the load will be installed on the MB girder.
20[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
26 Primary RF Network installation• Installation of the RF components on the TBTS tank (2 days)• Installation of the waveguides between TBTS tank and TBM Including supports, pumping port etc. (1 day)
3.5 days 04.0807.08
Waveguide support based on standard components will be delivered soon.
21[19-Mar-2014] [CMWG Meeting] «BE/RF»
TBM implantation in CLEXTask Duration Date
27 Installation of CLEX components according to new configuration (not all the components are listed below, +5..10 components, final inventory under way)
12.5 days 08.0724.07
Component Pic Quantity Component Pic Quantity
Quadrupoles 12 Supports 18
Correctors 8Sector
vacuum valves 4
BPMs and diagnostics chambers
9
Pumping ports
(including valves and
pumps)
5
Flashbox 1 Drift Tubes and bellows 24 + 26
22[19-Mar-2014] [CMWG Meeting] «BE/RF»
CLEX working area after installation of components
23[19-Mar-2014] [CMWG Meeting] «BE/RF»
Final tests and cables reconnection
Task Duration Date28 Leak tightness test 2 days 08.08-11.0829 Final alignment tests 4 days 12.08-15.0830 Reconstruction of cable trays and cables pulling 5 days 18.08-22.08
31 Reconnection of all cables (according to labelling) and pipes in the working area 2.5 days 25.08-27.08
32 Cooling system test 2 days 27.08-28.0833 Cleaning the area 3 days 29.08 - 02.0934 Closing the shielding 1 day 03.0935 Safety chain test 1 day 04.0936 Commissioning 5 days 05.09- 12.09
24[19-Mar-2014] [CMWG Meeting] «BE/RF»
Resources
Cooling system: final integration is under way by Vadim Soldatov and Alexios Lorens Vamvakas
Installation: FSU108, Andrey Olyunin, Wilfrid Farabolini (CLEX equipment coordination)
Vacuum for CLEX: Esa Antero Paju
Fiducialization, alignment: ABP-SU
Special tasks: external companies or other groups of CERN are involved
The planning must take into account the summer holidays of people involved in the installation. The holidays periods can be integrated in the personal calendar of each person (MS Project). Holidays to be supplied to Dmitry for the integration
25[19-Mar-2014] [CMWG Meeting] «BE/RF»
Status of components. TBM
Component Design Production Status Exp.
3D % 2D % Parts % Assembly
SAS 100 100 100 Brazing Mar’14
PETS 100 100 100 100 done
RF Network waveguides 100 100 100 brazing Apr’14
DB BPM 100 100 100 50 Apr’14
Vacuum minitanks and equipment 100 100 100 100 done
Vacuum drift tubes 100 100 0 0 Apr’14
RF Loads 100 100 Production, Ext. Comp. done
Directional Couplers 100 100 Production, Ext. Comp. done
Cooling tubes/fittings 100 90 0 - done
Supporting system 100 100 Test is under way done
U-clamps 100 100 50 0 Apr’14
Standard Supporting Frames 100 100 100 80 Apr’13
TBM ASSEMBLY May’13
26[19-Mar-2014] [CMWG Meeting] «BE/RF»
Status of components. TBM. Primary RF Network
Component Design Production Status Expected
3D % 2D % Parts % Assembly
RF Network waveguides 100 100 100 50 Apr’14
Vacuum fittings 100 100 0 0 done
Supporting system elements 100 100 0 0 done
Standard Supporting Frames 100 100 0 0 done
27[19-Mar-2014] [CMWG Meeting] «BE/RF»
Status of components. CLEX working area
Component Design Production Status Expected
3D % 2D % Parts % Assembly
Vacuum fittings and bellows (drift tubes)
100 - 0 0 Apr’14
Supporting girders 100 0 0 0 Apr’14
Implantation drawings (under way) 100 95 0 0 Mar’13
Cooling pipe
28[19-Mar-2014] [CMWG Meeting] «BE/RF»
Documentation
• EDMS 1366387 – INPUT. Integration of TBM in CLEX. Probe beam
• EDMS 1366388 – INPUT. Integration of TBM in CLEX. Drive beam
• CLIATCIN0004 (under way) – Integration of TBM in CLEX. Supporting system
• CLIATCIN0005 (under way) - Integration of TBM in CLEX. RF components
• EDMS 1366389 – TBM installation in CLEX. Detailed planning (preliminary)