CLF&P Transmission Project Status Update
The projects currently planned for the CLF&P transmission system are included on the following pages as shown in the WestConnect 2014 Annual Ten Year Transmission Plan. For updates on project status between Annual Ten Year Transmission Plans, refer to the quarterly stakeholder meeting presentations in the Transmission Planning -> TCPC folder on the CLPT OASIS site.
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants: WAPA‐RMR
Project Description: New 115 kV substation about 1.5 miles from the Warren substation
on the Warren‐Corlett 115 kV line
Voltage Class: 115 kV
Facility Rating:
Point of Origin/Location: North Range 115 kV (North Range Business Park, Cheyenne, WY)
Point of Termination:
Intermediate Points:
Length of Line (in Miles): 0.0
Type of Project: Substation
Development Status: In‐Service
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increased load serving capability and improved reliability.
Estimated Cost (in 2013 Dollars): $400,000
Schedule:
Construction Date: 2011
Planned In‐Service Date: 2013
Regulatory Info: Approved ‐ Wyoming PSC
Regulatory Date: 2012
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
North Range 115 kV Substation
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
�
�
LegendHappy Jack 115 kV to North Range 115 kV (Proposed)
� SUBSTATION
115 kV
WAPA
0 0.50.25
Miles
�
North Range
CLFP North Range 115 kV to Happy Jack 115 kV.
Happy Jack
Map Printed12/09/11.Line Route shown is for informational purposes only.
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants: Black Hills Power
Project Description: New 115kV lines connecting Cheyenne Prairie Generating Station to
existing lines between East Business Park and Archer 115kV
Voltage Class: 115 kV
Facility Rating: 222 MVA
Point of Origin/Location: Cheyenne Prairie Generating Station 115kV
Point of Termination: East Business Park ‐ Archer 115 kV Tap
Intermediate Points:
Length of Line (in Miles): 1.3
Type of Project: Transmission Line
Development Status: Planned
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increase load serving capability and improved reliability
Estimated Cost (in 2013 Dollars): $6,500,000
Schedule:
Construction Date: 2012
Planned In‐Service Date: 2014
Regulatory Info: Approved ‐ Wyoming PSC
Regulatory Date: 2012
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
Cheyenne Prairie Generating Station 115 kV Lines
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
_
Cheyenne Praire Generating StationSubstation
Source: Esri, i-cubed, USDA, USGS, AEX, GeoEye, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community, Copyright:©2012 Esri, DeLorme, NAVTEQ, TomTom
Map Printed 12/12/12
_ SubstationWAPA Transmission CLFP Transmission Route
0 2,0001,000Feet
¹
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants:
Project Description: New 115 kV line between Corlett and the new South Cheyenne 115
kV substations.
Voltage Class: 115 kV
Facility Rating: 219 MVA
Point of Origin/Location: Corlett 115 kV substation
Point of Termination: South Cheyenne 115 kV substation
Intermediate Points:
Length of Line (in Miles): 9.0
Type of Project: Transmission Line
Development Status: Under Construction
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increased load serving capability and improved reliability.
Estimated Cost (in 2013 Dollars): $4,300,000
Schedule:
Construction Date: 2011
Planned In‐Service Date: 2014
Regulatory Info: Approved ‐ Wyoming PSC
Regulatory Date: 2012
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
Corlett‐South Cheyenne 115 kV Line
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants: WAPA‐RMR
Project Description: New 115 kV line between the new North Range and Swan Ranch and
Cheyenne South 115 kV substations.
Voltage Class: 115 kV
Facility Rating: 189 MVA
Point of Origin/Location: North Range 115 kV substation
Point of Termination: Cheyenne South 115 kV substation
Intermediate Points: Swan Ranch 115kV substation
Length of Line (in Miles): 13.0
Type of Project: Transmission Line
Development Status: Under Construction
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increased load serving capability and improved reliability.
Estimated Cost (in 2013 Dollars): $3,300,000
Schedule:
Construction Date: 2011
Planned In‐Service Date: 2014
Regulatory Info: Approved ‐ Wyoming PSC
Regulatory Date: 2013
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
North Range‐Swan Ranch‐Cheyenne South 115 kV Line
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants: WAPA‐RMR
Project Description: New 115 kV line between Happy Jack and the new North Range 115
kV substations.
Voltage Class: 115 kV
Facility Rating: 222 MVA
Point of Origin/Location: Happy Jack 115 kV
Point of Termination: North Range 115 kV
Intermediate Points:
Length of Line (in Miles): 1.0
Type of Project: Transmission Line
Development Status: Under Construction
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increased reliability.
Estimated Cost (in 2013 Dollars): $900,000
Schedule:
Construction Date: 2012
Planned In‐Service Date: 2014
Regulatory Info: Approved ‐ Wyoming PSC
Regulatory Date: 2012
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
Happy Jack‐North Range 115 kV Line
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants:
Project Description: New 115 kV substation in Swan Ranch Business Park in Cheyenne,
Wyoming.
Voltage Class: 115 kV
Facility Rating:
Point of Origin/Location: Swan Ranch 115 kV (Swan Ranch Business Park, Cheyenne, WY)
Point of Termination:
Intermediate Points:
Length of Line (in Miles): 0.0
Type of Project: Substation
Development Status: Planned
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increased load serving capability and improved reliability.
Estimated Cost (in 2013 Dollars): $2,500,000
Schedule:
Construction Date: 2014
Planned In‐Service Date: 2014
Regulatory Info:
Regulatory Date:
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 605‐721‐2268
Website Information
Swan Ranch 115 kV Substation
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants:
Project Description: Two new radial 115kV transmission lines from North Range to the
new Microsoft Data Center substation
Voltage Class: 115 kV
Facility Rating:
Point of Origin/Location: Microsoft Substation (near Cheyenne, WY)
Point of Termination:
Intermediate Points:
Length of Line (in Miles):
Type of Project: Transmission Line and Substation
Development Status: Planned
Routing:
Subregional Planning Group: CCPG
Purpose of Project: To serve the Microsoft Data Center load
Estimated Cost (in 2013 Dollars): $9,500,000
Schedule:
Construction Date: 2014
Planned In‐Service Date: 2015
Regulatory Info: Submitted ‐ Wyoming PSC
Regulatory Date: 2013
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 1‐605‐721‐2268
Website Information
Microsoft Substation and Transmission
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
Project Sponsor: Cheyenne Light Fuel and Power
Additional Project Participants:
Project Description: Add a second 230/115kV Transformer at South Cheyenne
Voltage Class: 230 kV
Facility Rating: 200 MVA
Point of Origin/Location: South Cheyenne Substation (near Cheyenne, WY)
Point of Termination:
Intermediate Points:
Length of Line (in Miles):
Type of Project: Transformer
Development Status: Planned
Routing:
Subregional Planning Group: CCPG
Purpose of Project: Increase load serving capability and reliability
Estimated Cost (in 2013 Dollars): $4,200,000
Schedule:
Construction Date: 2014
Planned In‐Service Date: 2015
Regulatory Info: Submitted ‐ Wyoming PSC
Regulatory Date: 2013
Permitting Info:
Permitting Date:
Contact Information: Wes Wingen
Email [email protected]
Phone 1‐605‐721‐2268
Website Information
Second South Cheyenne 230/115kV Transformer
Cheyenne Light Fuel and Power2014‐2023 Transmission Plan
^
^̂
^
^
^
Copyright:© 2012 Esri, DeLorme, NAVTEQ, TomTom, Source: Esri,DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid,IGN, IGP, and the GIS User Community
^ SubstationsProposed North Range to Cheyenne South 115kVProposed Corlett to Cheyenne South 115 kV Existing 115kVWAPA
0 21Miles
¹North Range-South Cheyenne 115 kV Project.
Corlett
Swan Ranch (Proposed)
Map Printed 11/18/2013.Line Route shown is for informational purposes only.
North Range
Cheyenne South
Happy JackMicrosoft Data
Center (Proposed)