Transcript of Clemson University Bioscience - Stainless Railings
This document contains SC Railing Company proprietary information. Disclosure is prohibited without the prior written permission of SC Railing Company.
7008 Northland Drive, Suite 150 Minneapolis, Minnesota 55428 p: 1-877-215-RAIL(7245) w: sc-railing.com
Glenlake is a low-maintenance choice for outdoor applications
All lateral tubing was bent to create a radius on the stair landing
Stainless steel tube infill creates a clean, linear design
Free-standing sections were placed in wall openings along walkways
Optional post-mounted handrails were utilized on the stair application
Breaks in infill tubing were accommodated by doubling all mounting hardware on posts
Project: Clemson University Bioscience
Location: Clemson, SC
Architect: Perkins + Will
GC: DPR Construction
Completion: December 2012
Scope: This project, with a six-month duration, called for more than 200
linear feet of our Glenlake stainless steel tube infill railing, as well as
350 feet of our Tivoli glass-supported railing. Grade 316 stainless
steel was utilized for all exterior locations, which hold up to
environmental exposure to heat, moisture, and airborne pollutants.
Project Information
University Scientific Research Building
Case Study: Clemson Bioscience