Clearing Wreckage To Inject U4 SFP Cooling Water

download Clearing Wreckage To Inject U4 SFP Cooling Water

of 60

Transcript of Clearing Wreckage To Inject U4 SFP Cooling Water

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    1/60

    Clearing Wreckage To Inject U4 SFP

    Cooling Water

    1

    Debris Was Blocking

    Pumper Access to SFPDebris Cleared For Pumper

    By Manual Tank-BulldozerL. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    2/60

    Established Pool Recirculation Cooling

    L. Barrett Consulting LLC 2

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    3/60

    Release Periods Based On Site Gamma

    Levels

    L. Barrett Consulting LLC 3

    U2 Internal Explosion?

    U3 Gray Smoke?

    U3 Explosion?

    U3 White Smoke?

    uSv/h@Gate@1

    Km

    U1 Explosion?

    U4 Building Explosion?

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    4/60

    Establishing Core Recirculation Cooling

    In Early July

    Turbine

    Building

    Need Water RecirculationSystem To Stop Feed & Bleed

    Venting & Radioactive Water

    Creation~30M gallons High Rad Water

    4

    Cable/Pipe Tunnels Leakage

    L. Barrett Consulting LLC

    New Chemical/Radiological

    Purification SystemWater

    Purificatio

    n

    Reactor

    Vessel Leak

    Primary

    ContainmentLeak

    Intake Strctrs

    Heat

    Sea

    Damaged Reactor Building

    Flooded Basement

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    5/60

    Recirc Core Cooling

    L. Barrett Consulting LLC 5

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    6/60

    L. Barrett Consulting LLC 6

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    7/60

    Current Primary Containment Integrity

    Oxygen-Hydrogen Risk

    7

    Hydrogen & Steam Atmosphere

    Currently In Primary Containments

    As System Cools May Draw Air with

    Oxygen Back Into the Containment

    and Could Become Explosive

    Currently Injecting Inert nitrogen to

    Prevent Oxygen In-leakage, however

    Unit 3 has significant containment

    leakage

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    8/60

    Current Primary Containment Integrity

    Seismic Risk

    8

    Primary Containments are Partially

    Flooded with Core Feed Water Outflow

    Well Beyond Design Basis Levels

    Earthquake Aftershocks Add

    Increased Dynamic Stress to Higher

    than Design Static Stress

    Reactor Building Structure Has Likely

    Been Degraded by Explosions and

    initial Earthquake To an Unknown

    Degree

    Containment Integrity Margins being

    Evaluated

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    9/60

    Current Unit 4 Reactor Building

    Structural Integrity Seismic Risk

    9

    Explosions Have Weaken RB Structure

    A Large Earthquake Aftershock May

    Cause Building Failure

    Keeping Pool Water Level at a

    Minimum to reduce Loads

    Adding

    Steel &

    Concreteunder PoolHigh

    Gamma

    Field

    Causing

    DelaysL. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    10/60

    Gather Data Inside Reactor Buildings

    10

    Adapted Military Drones With

    Thermal & Radiation Capabilities L. Barrett Consulting LLC

    Inside Reactor Buildings

    ~1-100R/Hr & U2 High Vapor

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    11/60

    Working Conditions are ChallengingRestoring Power In High Radiation & Contaminated Areas

    11L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    12/60

    Control Room Power Restoration

    12

    Before Power Restored After Power Restored

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    13/60

    Working In Contaminated Buildings

    13

    Entering Waste

    Processing Building

    Worker Showing TB Basement

    Floor Water Level

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    14/60

    Reactor Building Air FiltrationAccess to Calibrate Reactor Water Level Instrumentation

    L. Barrett Consulting LLC 14

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    15/60

    U2 Reactor Building Conditions

    L. Barrett Consulting LLC 15Water 4M deep in Basement

    Ground RB Floor

    Robots First

    Personnel Second

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    16/60

    U3 Reactor Building Conditions

    L. Barrett Consulting LLC 16

    Reducing 5-18R/hr Gamma Fields

    For N2 Containment Injection

    Robotic Vacuum Cleaner

    50-20mm Steel Plate Floor Shielding

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    17/60

    Airborne Mitigation

    17L. Barrett Consulting LLC

    Dust Suppression Resin Application

    Unit 1 Fabric Enclosure55M High & 47M X 42M

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    18/60

    Unit 1 Canopy Design/Construction Process

    L. Barrett Consulting LLC 18

    Laser Measure Existing Building Laser Image New Enclosure

    Construction Sequence PlaningMockup Const Training

    New Fast Const Concepts

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    19/60

    Minimizing Building Rain In Leakage

    Unit 1 Turbine Building RoofPatchTo Reduce Radioactive Water Overflow

    Current Rainy Season: Typhoon Ma On with 4 last week

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    20/60

    Contaminated Water Accumulating

    Feed & Bleed Core Cooling Flushed Large

    Amounts of Highly Radioactive Water into

    Building Basements

    Approximately 30 Million Gallons Now

    Approximately 25 Million Curies

    Increasing at ~100,000 gallons per day

    Rainy Season Adding More

    L. Barrett Consulting LLC 20

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    21/60

    Effluent Release Flow PathsReactor Building-Turbine Building-Intake -Sea

    21L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    22/60

    Contaminated Water ContainmentOverflow from U2 Reactor Bldg to Turbine Bldg to

    Intake Structure Wall Crack to Sea~ 27,000 Ci Cs-137 Released this Path 4/1-6

    -Reference Chernobyl was 2MCi Cs-137 released

    22

    Leak Reduced 11-04-04

    Leak Sealed 11-04-06

    Sodium Silicate Injection

    Non-Safety Grade

    intake Structure

    Radioactive Water

    Leak 11-04-02

    L. Barrett Consulting LLC

    C i d W C i

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    23/60

    Contaminated Water ContainmentHow the Intake Wall Crack Leak was Stopped

    23

    Leak Sealed 11-04-06

    Sodium Silicate InjectionCable Chase Path

    Other Similar Leakage Paths To SealL. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    24/60

    Sealing Other Leakage Paths to Sea

    L. Barrett Consulting LLC 24

    Concreting One of ~37 Cable & Pipe Chase Paths

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    25/60

    Mitigate Basement Leakage Into

    Groundwater Paths To Sea

    L. Barrett Consulting LLC 25

    Planning Underground Barrier Walls to Bed Rock

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    26/60

    Water Retention Tank FarmsUnderground Tanks Under Construction

    L. Barrett Consulting LLC 26

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    27/60

    Accident Water Management

    27

    Silt Fence

    20-50 Million Gallons Of Highly Radioactive Water To Be Transferred To Onsite Tankage

    Relative

    Low Activity

    Released

    Sluice Gates

    &

    Zeolite Bags

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    28/60

    Water Release MitigationContain/Retard Intake Structure Cs/Sr

    Contamination

    28

    Zeolite Bags To Adsorb Cs/SrSluice Gate to Minimize Outflow

    To OceanL. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    29/60

    Water Release MitigationSilt Fence to Retard Cs/Sr Release to Sea

    29L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    30/60

    Process Intake Canal Water Through

    Zeolite Beds to Remove Released Cesium

    L. Barrett Consulting LLC 30

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    31/60

    US Fresh Water Barge On Site-April

    31

    Japanese Tow Operators

    Japanese ship hauling US Navy water barge

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    32/60

    New Water Barge On Site-June

    32

    2.5 Million Gallon Capacity BargeL. Barrett Consulting LLC

    A id W T Pl

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    33/60

    Accident Water Treatment Plans

    ~30 Million Gallons in Basements

    L. Barrett Consulting LLC 33

    1200T/day (330Kgal/day or 200gpm) Rate Goal with 1E3 DF Startup Late June

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    34/60

    Water Recirculation Processing Plan

    L. Barrett Consulting LLC 34

    Four Stage System

    1. Oil Removal: Toshiba

    2. Cesium Removal: Kurion3. Fission Products Removal: AREVA

    4. Salt Removal: Hitachi

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    35/60

    Oil Removal

    L. Barrett Consulting LLC 35

    Separator InternalsSeparator Unit

    Cesium Removal Stage

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    36/60

    Cesium Removal Stage

    L. Barrett Consulting LLC 36

    Individual Zeolite Beds

    Shielded Skids

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    37/60

    Fission Product Precipitation Stage

    L. Barrett Consulting LLC 37

    Installed Co-Precipitation UnitChemical Injection Tanks

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    38/60

    Process System Locations

    L. Barrett Consulting LLC 38

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    39/60

    Water Tank & Systems Locations

    L. Barrett Consulting LLC 39

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    40/60

    Water Processing Difficulties

    With First Kurion/AREVA System

    Many Systems Leaks & Issues

    ~60% Capacity

    High Rad Sludge Management Challenges Will Emerge

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    41/60

    New Water Processing System

    Simplified Active Water Retrieve and Recovery System (SARRY)

    Toshiba Lead

    2 Lines of 8 Larger (24Ton) Zeolite/Silicate Filter Beds to

    replace/augment Initial Kurion/AREVA System

    Planned August Operation

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    42/60

    Site Needs Extensive Decon

    L. Barrett Consulting LLC 42

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    43/60

    Debris Hotspots100R/hr

    L. Barrett Consulting LLC 43

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    44/60

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    45/60

    Decontamination Cleanup Solids

    45

    Remote Debris Removal

    -90R/Hr Concrete Piece

    Remote Debris Transporter

    With Solid Waste Container

    L. Barrett Consulting LLC

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    46/60

    Onsite Solid Storage Area

    L. Barrett Consulting LLC 46

    ~300+ 4M3 Containers to June

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    47/60

    Solid Waste Handling Equipment

    L. Barrett Consulting LLC 47

    Shielded Fork Lift Remote Controlled Equipment

    i l ili i

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    48/60

    On Site Personnel Facilities

    L. Barrett Consulting LLC 48

    Change House

    Shielded Work Areas

    Rest Areas

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    49/60

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    50/60

    Personnel Exposures

    ~4,000 Onsite Personnel

    Most are < 100 mSv (10R)

    ~100 are >100mSv (10R) < 250mSv (25R)

    ~6 are ~ 500-600mSv (50 to 60R)

    Over Exposures

    Internal Ingestions Issue

    More Likely

    L. Barrett Consulting LLC 50

    Off i i

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    51/60

    Offsite impacts

    L. Barrett Consulting LLC 51

    Offsite Cs/Sr Contamination

    School Playground Dose

    Remediation

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    52/60

    H F li & R ti

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    53/60

    Human Feelings & Reactions

    53L. Barrett Consulting LLC

    TEPCO ROADMAP SEQUENCE 06-17

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    54/60

    54L. Barrett Consulting LLC

    C t & E i I

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    55/60

    Current & Emerging Issues Maintain Sustainable Closed Cooling

    After Shock Structural Integrity Containment Degradation

    High Rad Water Containment~30+ Million Gallons

    Highly Rad Water Processing Sludge ~1,000R/hr range

    20-100 Mega Curie Amounts (TMI~1MCi)

    Impact Site Recovery

    Building Containment/Filtration

    Offsite Remediation Management Restructure

    Regulatory Restructure

    Finance?

    L. Barrett Consulting LLC 55

    I t l A id t R Ph

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    56/60

    Internal Accident Recovery Phases

    1. Energy Heat Rejection Control

    1. Much Improved with Closed Residual Heat Removal

    Gas Release Control/Mitigation1. Containments

    2. Filtration1. Liquid Release Control/Mitigation

    1. Control Highly Radioactive Water in Basements

    2. Initially Contain in Tanks

    3. Create Effective Purification Systems

    2. Solids/Contamination Control Materials Management1. Contain/package

    2. Store/transport

    3. Dispose56L. Barrett Consulting LLC

    E t l Ph Of A id t

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    57/60

    External Phases Of Accident

    Plant Accident Recovery Period Impossible Information Demands

    Stabilize/Remediate/Recover/Protect

    Hours-Days-Weeks-Months-Years-Decades

    Environmental Impact Period Public Perception/Impacts/Remediation (Offsite) Weeks-Months-Years

    Societal/Institutional Reactions Period Cultural Political

    Policy

    Financial

    Management57L. Barrett Consulting LLC

    Personal Fukushima Observations

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    58/60

    Personal Fukushima Observations

    Not a Public Health Catastrophe Radiological Impacts Inconsequential Compared to Earthquake/Tsunami Impacts

    Is An Industrial Plant Catastrophe Caused By A Natural Disaster The Tsunami was the Main Safety Issue

    Three Melted Cores & Severely Damaged & Contaminated Buildings

    Units 1-4 Complete Loss, Units 5 &6 Technically Recoverable

    Cleanup Long & Expensive, but Technically Achievable (Much Larger than TMI)

    Energy Dissipation is Getting Better, but Safety Challenges Aftershock Safety

    System & Containment Degradation

    Building Access Difficult

    Environmental Release Mitigation is a Growing Challenge Water & Airborne Radioactive Effluents

    Onsite & Offsite Environmental Impact Mitigation

    Multiple Management, Social, Political & Economic Issues Ahead E.G. Waste & Spent Fuel Disposition Pathways

    Lessons Learned Ahead58L. Barrett Consulting LLC

    Personal U.S. Nuclear Safety Observations

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    59/60

    e so a U S uc ea Sa ety Obse at o s Current Reactors Have Adequate Safety Margins

    U.S. Tsunami Risks are Limited To Only A Few U.S. Sites

    Past Risk Informed Severe Accident Improvements HaveAlready Addressed Many Fukushima Issues

    Station Blackout & 911 Improvements

    Systematic, Methodical, & Risk Informed Fukushima

    Lessons Learned Evaluations Are Appropriate Industry

    NRC

    Resist Quick Fix Emotional Reactions

    Continuous Improvement Culture Will Further Strengthen U.S. Capabilities

    Lessons Learned From TMI Lessons Learned TMI Lessons Learned Greatly Improved US Nuclear Safety and Productivity

    Most Painful Lessons are the Most Teachable

    Fukushima Lessons Should Improve Safety and Advance Global & U.S. NuclearEnergy As Three Mile Island Lessons Learned Did Thirty Years Ago.

    59L. Barrett Consulting LLC

    L k H B tt

  • 8/13/2019 Clearing Wreckage To Inject U4 SFP Cooling Water

    60/60

    Lake H. [email protected]

    Lake Barrett is a part time independent consultant in the energy field. He hasworked in the nuclear energy and nuclear materials management areas for over 4decades, most recently as the former head of the US Department of Energys Officeof Civilian Nuclear Waste Management which is responsible for implementing theUnited Sates programs for spent nuclear fuel and high-level radioactive waste, asmandated by the Nuclear Waste Policy Act. In that capacity, he led the complexscientific Yucca Mountain Geologic Repository program through the statutory siteselection process culminating with the Presidential site designation and followingsuccessful House and Senate votes.

    He also served at U. S. Nuclear Regulatory Commission, where he was directlyinvolved with the early response to the Three Mile Island reactor accident andbecame the Site Director, responsible for regulatory programs during thestabilization, recovery, and cleanup of the damaged reactor. He also has hadextensive managerial and engineering experiences in DOEs Defence Programs andprivate industry at both Bechtel Power Corporation, with commercial nuclear powerplants, and Electric Boat Division of General Dynamics with nuclear reactor andsubmarine systems design, operation, and decommissioning.