Conference on CCT and CCS 2-3rd December,2013
Overview of BHEL corporation
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
BHEL – Activity Locations in India
Conference on CCT&CCS
Dec 13
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
BHEL’s GLOBAL FOOTPRINT
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Pulverised Fuel Boilers
Sub critical
•60 MW
•110 MW
•200 MW
•210 MW
•250 MW
•500 MW
•600 MW
Super Critical
•660 MW
•700 MW
•800 MW
•1000 MW
BHEL’s Boiler Range
Fluidised Bed Combustion Boilers
Bubbling Fluidized Bed
•20 MW
•45 MW
•60 MW
•80 MW
•120 MW
Circulating Fluidized Bed
•60 MW
•75 MW
•125 MW
•135 MW
•250 MW
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
BHEL Corporate – Turn over
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
BHEL Initiatives towards CCT and CCS
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Our Goals on CCT and CCS
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Coal Gasification
Coal Characterization Collaborative Research
ScTF CFBC
SFBTF
Bharat Heavy Electricals Limited
Research facilities in BHEL Trichy Complex
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Coal Research Centre
Conference on CCT and CCS 2-3rd December,2013
CRC Equipments
Total = 22 Equipment
Project Outlay Rs 1743 Lakhs
Bharat Heavy Electricals Limited
X-Ray Fluorescence Spectrometer
Inductively Coupled Plasma Mass Spectrometer
Microwave Digestor
Mercury Analyser
Portable Flue Gas Analyser
Gas Chromatography
FUEL CHARACTERISATION
THERMAL CHARACTERISATION
MINERAL CHARACTERISATION
PARTICLE CHARACTERISATION
ENVIRONMENTAL LAB
Proximate Analyser
Ultimate Analyser
Bomb Calorimeter
Sulphur Determinator
FTIR Spectrometer
Thermo Gravimetric Analyser
Differential Scanning Calorimeter
High Temperature X-Ray Diffraction Spectrometer
Computer Controlled Scanning Electron Microscope
Low Temperature Asher
Particle Size Analyser
Surface Area And Pore Analyser
Zeta Meter
Gas Pyconometer
PM 10 & PM 2.5 Particle Analyser
Drop Tube
Furnace System
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Drop Tube Furnace Test Facility
Conference on CCT and CCS 2-3rd December,2013
Key research areas on CCT and CCS
• Increasing efficiency of PF Boilers -Development of AUSC boiler
• Development of CFBC and IGCC of higher capacity
• Biomass Co-firing and Oxy fuel combustion technology
• Technology development for Carbon dioxide capture from flue gas
• Reduction measures for non GHG like NOx through -Over Fire Air compartment
-Bypass Over Fire Air Firing
-SCR development
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Plant type with power
rating
Steam Pressure (kg/cm2)
Steam Temperature
(C)
Efficiency (%)
CO2 Emissions (g/kW-hr)
Coal saving for one 800 MW unit
( t/year ) **
Sub Critical
170 540 38-39 900 Base
Super Critical* 247 565 40 830 1,01,000
Ultra Super Critical
250 600 42 784 2,88,000
Advanced Ultra Super Critical
300 700 45 740 5,38,000
* The improvements are with respect to the best units under construction in India ** For the coal HHV of 3500 Kcal/kg • Extension of coal reserves by 11% • Competitive in electricity cost on deployment
Bharat Heavy Electricals Limited
Reduction of CO2 emission with increase of
steam parameters
Conference on CCT and CCS 2-3rd December,2013
Indian Govt. National Mission for Technology - AUSC
Driven by the government’s National Mission for Technology, the Advanced Ultra Super Critical (AUSC) project ( 300Bar, 710/720°C) is under Development by a joint venture of BHEL, NTPC and the Indira Gandhi Centre for Atomic Research (IGCAR).
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
• To conduct experiments at Supercritical (SC)/ Ultra Supercritical (USC) conditions of steam
• Know why generation for establishing SC & USC boiler technology
Objective
• Rs. 12 cr. Investment
• Pressure - 400 bar
• Temperature - 700 Deg.C
• Heat flux - 1000 kW/m2
Capabilities
• Commissioned in Dec. 2008
• Experiments under progress Status
World Class
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
NTPC/ BARH II STPP – 2 x 660 MW
Coal Fuel
568 / 596 oC Temperature
255/54.65 kg/cm2 (g) Pressure
2120/1708.2 t/h. Steam Flow
31.03.2008 Zero Date
U6/1700 & U6/1701 Contract No.
Not in SG Package Dust Collector
2 Nos. SAF 42.5/26.6-1, Axial
Reaction-TLT ID Fan
2 Nos. PAF 19/10.6 – 2, Axial
Reaction-TLT PA Fan
2 Nos. FAF 25/11.2 – 1, Axial
Reaction-TLT FD Fan
PAH - 2 Nos. 28.5 VI 58 (70)MR,2NOS
31.5 VI 70 (82)MR ALSTOM Supply Airheater
9 Nos. Bowl Mill, HP 1103 Mill
Major Auxiliaries
Parameters at SHO / RHO
BARH II – 2 x 660 MW Project
National Thermal Power Corporation Customer
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
APPDCL / Sri Damodaram Sanjeevaiah
TPS 2 x 800 MW
Blended Coal ( 70 % Indian Washed Coal, 30
% Imported Coal) Fuel
568 / 596 oC Temperature
255/57.9 kg/cm2 (g) Pressure
2600 / 2052 t/h. Steam Flow
25.07.2008
Zero Date
1800, 1801 Contract No.
4 Nos. FAA-8x45M-2x112150-2 Dust Collector
2 Nos. SAF – 40/ 21-1, Axial Reaction ID Fan
2 Nos. PAF 20/12.5-2, Axial Reaction PA Fan
2 Nos. SAF 27.3/12.2-1, Axial Reaction FD Fan
2 Nos. TRI-SECTOR, 34.5 VI 94, Airheater
6 Nos. Bowl Mill, HP 1203 Mill
Major Auxiliaries
Parameters at SHO / RHO
Sri Damodaram Sanjeevaiah T P S –2 x
800 MW Project
APPDCL Customer
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Integrated Gasification Combined Cycle
Heat Flow Diagram
Efficiency – 42%
74%
35%
18%
10
%
HRS
G
GT Exh
100%
Loss-2%
Loss-2%
Stack Loss Condenser
Loss
Misc Loss-
3%
Steam
Coal 25
%
47%
17%
33%
Loss - 8%
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Coal Gasification – CCDP 6.2 MWe
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Corp. R&D,
Hyderabad
18
TPD
(PEDU)
6.2 MW
CCDP
182 MW
IGCC
Tiruchy
Scale up:
Geometrical - 1:1.14
Capacity - 1: 1.21
Pressure - 1:0.9
Scale up:
Geometrical - 1: 3.3
Capacity - 1: 9.33
Pressure - 1:1.2
1.2
TPD
(APFBG)
Corp R&D
Hyderabad
Dia 0.2 m
Press 2.0 ata
Scale up:
Geometrical - 1: 2.25
Capacity - 1: 15
Pressure - 1:5
125 MW
IGCC
Concept Design
Scale up:
Geometrical - 1: 2.91
Capacity - 1: 11.1
Pressure - 1:3
APGENCO
Vijaywada
450- 650 MW
IGCC
Future Commercial Scale IGCC Plant
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Milestones in BHEL’s IGCC Development
Role of CFBC in CCT
• High fuel flexibility
• Can burn coal of high moisture content (Lignite)
• Low SOx emission due to absorption of SOx in lime bed
• Because of lower bed temperature, it generates less amount of NOx.
• Efficiency is comparable with PCC of same capacity.
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
CFB Boiler Development
Test Facility installed
Collaboration with
First CFB boiler (175 t/hr ) installed at BILT , Bhigwan
First Utility reheat boiler (2x125 MW) installed at
SLPP, Mangrol
Collaboration with LLB ends 125 MW, RVUNL, Giral
75 MW order received from GEB, Kutch
2 x 135 t/hr M/s Gujarat Ambuja cement
2 x 250 MW order received from Neyveli Lignite
Corporation
2 x 125 MW NLC – Barsingsar
2 x 125 MW repeat order received from SLPP
1 x 135 t/h repeat Order received from GACL
1x120 t/h First Export order received from PT BR, Indonesia
2x135MW order received from KNS,NewCaledonia2x30 MW PT MSW, Indonesia
3 x 275 t/h Petcoke fired units from BORL
125 MW repeat order received from RVUNL, Giral
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900
Y
e
a
r
Boiler Capacity in t/hr
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
27
CFB Product Range
Combustor Wing Wall Non Integral FBHE Integral FBHE Pant Leg
< 30 MW 60-100 MW 60-135 MW 125 MW 250 MW
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Project Fuel %S
BILT ,Sinarmas IC 0.35
SLPP, Mangrol L 2.00
GLPP, Giral L 6.00
GACL, Kodinar IC 0.43
KLTP Ext, Kutch L 4.90
BTPP, Barsingsar L 1.70
SLPP Extn, Mangrol L 2.00
BORL, Bina IC P 5.63
PT IBR, Indonesia IC 0.96
KNS, Koniambo AC 0.80
PT MSW, Indonesia IC 0.28
BECL Bhavnagar L 4.00
BHEL CFB – Fuel Summary
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
CFB Boilers – Capacity & Range
Range Upto 850 t/h (250 MWe ), 545ºC & 172 kg/cm2(g)
Fuels Range Lignite, Petcoke, Coal, Middlings, Washery Rejects
HHV >1800 kcal/kg Ash < 70%wt Total Moisture < 55%wt Sulphur < 6%wt
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
CFBC capacity status-worldwide
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Lignite Potential In India
Lignite Reserves – 39 bill. Tons (Proven in Mill tons) Tamil Nadu 31327 (2831) Rajasthan 4485 ( 561) Gujarat 2663 ( 785) Puduchery 417 ( 0) J&K 28 ( 0) Kerala 10 ( 0) West Bengal 1 ( 0) Total 38931 (4177)
Potential 70 Nos: 250 MW (Approx. 50 mill tons one 250 MW plant)
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
BHEL 125 MWe CFBC Boilers – SLPP Units
1&2 Units Commissioned in 1999
3&4 Units Commissioned in 2010
One of the best performing lignite power plants
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Location : Giral, Barmer Dt , Rajasthan Fuel : Lignite ( 40 % M & 6 %S) Highest in world Design fuel, kcal/kg : HHV – 3000 Start-up : 2007 Availability : 60-90%
RVUNL (Giral) – 2 x 125 MWe CFB Boiler
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Location : Barsingsar, Bikaner Dt , Rajasthan
Fuel : Lignite ( 40 % M & 0.8 %S) Unique Palana Lignite
HHV : 1900 - 3300kcal/kg
Start-up : 2010
Availability : 80-90%
NLC BARSINGSAR CFB 2 x 125 MWe
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
250MW – What’s New • Combustor – Single to Pant Leg
• Cyclones – Two to Four
• Pressure rating – 170 ata vs 130 ata
• FBHE – Integral to Separate
• Airheater – Tubular to Quadsector RAPH
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
HIGHER CAPACITY CFBC BOILERS ESTABLISHED
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Successfully established CFB technology for difficult Lignite Variety available in
Rajasthan
- High Sulphur Content
- with shrinking ash characterisitics
Plants firing lignite from Gujarat & Rajasthan are operating successfull today
The Largest CFB boiler of 250 MW has demonstrated full load capacity firing
Lignite from Neyveli, Tamil Nadu
BHEL has extensive R&D facilities to characterize various fuels and
successfully fired washery rejects of 70% ash content, various coals etc.
BHEL has solution for firing various fuels of coal & lignite in CFB boilers
BHEL-TRECSTEP EU Project on Demonstration and deployment of
CCT and CCS project
BHEL has initiated the following projects
Pilot scale testing of Oxy fuel combustion
Cofiring of Biomass
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Biomass is a Carbon Neutral Fuel
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Demonstration of Wood Pellets (20% by wt) Co-firing with Coal in SFBTF to European Union Team
Dr. Rodrigo Ubierna (ROM) Visit
on 12th June 2013 to BHEL
Mr. ARNO SCHAEFER (Head of
Operation, EU Delegation to India) &
Ms. SMITHA SINGH (Project
Manager) VISIT to BHEL on
14.06.2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Firing with 100% coal
Firing with coal and 20% of Wood pellets
Flame
Photograph from
rear side of the
combustion
chamber
• Studies with wood pellets has been showed good results and temperature profiles, heat
flux values near wall are closely matching with 100% coal test results.
• Better flame stability observed as biomass co-firing proportion increases
• With limited proportion of firing biomass with coal up to 20% by mass
• No slagging, fouling or heavy deposition observed
• Flowability issues observed when biomass proportion is more than 20% by wt
Biomass Co-firing with Coal – Project
Completed
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Oxy- combustion Technology in PC Boilers
Conference on CCT and CCS 2-3rd December,2013
400 KW Pilot scale – Oxy fuel Combustion Test Facility
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
• CO2 separation from flue gas and fuel gas by wet scrubbing
with ammonia solvents.
• Ammonia method offers lower solvent cost, lower energy for
regeneration, applicable for retrofits and new plants.
• BHEL has developed the ammonia process for CO2 capture in
bench scale.
CO2 capture and regeneration by Ammonia
absorption process
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Pilot scale CO2
capture testing
facility
Conference on CCT and CCS 2-3rd December,2013
13.5 13.2 13.6
1.20.6 0.3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
3.1% NH3 soln 6.25% NH3 soln
12.5% NH3 soln
% CO2 before absorption % CO2 minimum in absorption
Bharat Heavy Electricals Limited
CO2 absorption trend using Ammonia Solution
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bypass Over Fire Air (BOFA)System
Bypass Over Fire Air (BOFA) system
• Cost effective technology among the technologies
available for NOx reduction in pulverised coal fired
thermal power plants.
• Employs deep air staging technique to abate NOx
emission.
• The BOFA system was retrofitted into a 250 MW boiler
supplied by BHEL (Suratgarh).
• The NOx reduction capability around 50%.
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Selective Catalytic Reduction
• BHEL has developed Selective Catalytic Reduction
system for NOx reduction in PC fired boilers by injecting
ammonia in to the flue gas in the presence of a catalyst.
• SCR pilot plant has been established at Fuel Evaluation
Test Facility at BHEL Trichy.
• NOx reduction capability of the SCR system was
demonstrated to be in the order of 90-95%.
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Selective Catalytic Reduction(SCR) System
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Summary BHEL has implemented Supercritical parameters for PF boilers and moving towards USC and AUSC towards Higher Efficiency and Lower Emissions.
Process development for IGCC of higher capacity is completed and is ready for commercialization
CFBC of 250MWe capacity established to handle wide variety of fuels including Lignite
Developed technology for biomass co-firing and oxyfuel combustion technology
Know how on CO2 capture from flue gas is developed and demonstrated on pilot scale
Reduction of non GHG emissions like NOx is commercialized based on need
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013
Bharat Heavy Electricals Limited
Conference on CCT and CCS 2-3rd December,2013