Clay Farm Community Centre
Presentation to the Southern Fringe Community Forum
28 June 2011
Alan Carter
Head of Strategic Housing
Clay Farm Community Centre
A Partnership Project
Partners Facilities
City and South Cambs Community Centre – multi- use hall, community café, youth wing
Trumpington Street Medical Practice/PCT
Health Centre
County Council Library, social services ‘touch down’
Police ‘Touch down’
Cambridgeshire Partnerships Limited
Apartments
Clay Farm Community Centre
A Partnership Project
In the context of the Cambridgeshire Quality Charter for Growth
“……support creation of a sense of community and to meet the changing needs of the residents of the area. We see this through co-location of public services into a vibrant and sustainable hub that draws the whole community together.”
Clay Farm Community Centre
Facilities Floor Area (sq m)
Community Rooms 466
Community Cafe 128
Youth Wing 182
Library 337
Health Centre 953
Pharmacy 125
Police/Social Services Touchdown
135
Shared 549
Residential 900
Clay Farm Community Centre
Cost (£)
Build – including fit out 7,250,000
Design and other consultants 800,000
Fees – planning, public art 60,000
Other eg project management 90,000
8,200,000
Working Budget
Clay Farm Community Centre
Funding (Working Budget - £8,200,000)
Capital Funding (£)
Developer contributions – City 2,278,000
Developer contributions – County 1,251,000
County Library – top-up 261,000
Cambridgeshire Partnerships Limited 1,200,000
Total 4,990,000
Plus – Revenue Contributions in respect of the Health Centre :
£1,010,770 in 8 equal annual instalments
Clay Farm Community Centre
Date House Completions Dev. Contributions
Mid 2012 68 44,000
End 2012 314 378,000
Mid 2012 550 1,110,000
End 2014 880 1,730,200
1241 2,593,800
1588 3,184,150
1953 3,427,000
Time-lines
Clay Farm Community Centre
A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Trigger for delivery of site for building. 450 units.
OJEU tender process for design team 1Outline design, costings and approvals
Planning approval 2Detail design, costings and approvals
Tender process for constructors 3Tender and negotiation processess
Mobilisation
Site Start
Project build
Project completion
2013 20142011 2012
Procurement Timetable
Clay Farm Community Centre
Selection of Design Partner
Tender Process Timescale
Prep tender documents End August 11
OEJU Notice Sept 11
Shortlist Oct 11
Invitation to Tender Oct – Dec 11
Evaluation Jan – Feb 12
Award Feb 12