Class Seven-Time Mgt

download Class Seven-Time Mgt

of 97

Transcript of Class Seven-Time Mgt

  • 8/8/2019 Class Seven-Time Mgt

    1/97

    Continuous ImprovementContinuous Improvement

    Project TimeManagement

    ZAFAR KAMAL

  • 8/8/2019 Class Seven-Time Mgt

    2/97

    Project and Project Management

    Project temporary endeavor undertaken to create aunique product or service

    Has a definite beginning and end and interrelatedactivities

    Programs adopt new set of objectives and continue towork; projects cease when declared objectives havebeen attained

  • 8/8/2019 Class Seven-Time Mgt

    3/97

    Projects are unique characteristics are progressivelyelaborated

    Progressively: proceeding in steps

    Elaborated: worked with care and detail

    Scope of project should remain constant even ascharacteristics are progressively elaborated

    Project and Project Management

  • 8/8/2019 Class Seven-Time Mgt

    4/97

    Project Management: the application of knowledge, skills,tools and techniques to project activities in order to meet orexceed stakeholder needs and expectations from a definedproject balancing the following:

    Scope, time, cost, and quality

    Stakeholders expectations Requirements (needs) vs. unidentified requirements

    (expectations)

    Project and Project Management

  • 8/8/2019 Class Seven-Time Mgt

    5/97

    Programs are groups of projects managed in acoordinated way to obtain benefits not available frommanaging the projects individually

    Most programs have elements of ongoing operations

    Series of repetitive or cyclical undertakings Projects are often divided into subprojects for more

    manageability Often contracted out to external organizations

    Project and Project Management

  • 8/8/2019 Class Seven-Time Mgt

    6/97

    Project Time Management

    General Comments:

    Projects can have more than 1 critical path (increases risk) and caninvolve dummy tasks

    Negative float indicates that you are behind Resource Leveling involves possibly letting schedule and cost slip Heuristics just means rule of thumb e.g. 80/20 rule Schedules are calendar based makes this different than a time

    estimate

    Bar Chart a.k.a. Gantt chart (track progress, report to entireteam including stakeholders, control tool)

    Network Diagram (to show task inter-dependencies, showproject organization, basis for project control) Milestone chart (report to Senior management, shows major

    events)

  • 8/8/2019 Class Seven-Time Mgt

    7/97

    Project Time Management

    General Comments: To shorten project schedule examine the critical path

    Crashing add more resources to the criticalpath tasks Usually results in increased cost

    Fast Tracking performing tasks in parallel Can result in re-work and increased risk

    Best to select method that has least impact on theproject (is the importance on cost, risk or schedule?)

  • 8/8/2019 Class Seven-Time Mgt

    8/97

    Project Time Management

    General Comments: Bar (Gantt) Charts

    Weak Planning Tool, effective progress and reporting tool Does not show interdependencies of tasks Does not help organize the project more effectively

    Network Diagrams (PERT, CPM, PDM)

    Shows task interdependencies Aids in effectively planning and organizing work Provides a basis for project control

    Milestone Charts Only shows major events Good for reporting to management and customer

    Flow Charts

    Depicts workflow and not commonly used for project management

  • 8/8/2019 Class Seven-Time Mgt

    9/97

    Project Time Management

    General Comments: Free Slack (Float) amount of time a task can be delayed

    without delaying the early start date of its successor Total Slack (Float) amount of time a task can be delayed

    without delaying the project completion date

    Lag inserted waiting time between tasks Resource Leveling level peaks of resource usage; stable

    number of resources allows schedule and cost slip in favor ofleveling resources

  • 8/8/2019 Class Seven-Time Mgt

    10/97

    www.pmstudy.com 10

    What is Project Time

    Management? Processes required to ensure timely completion of

    the project. Major time management processes include:

    Activity definition.

    Activity sequencing. Activity resource estimating Activity duration estimating. Schedule development.

    Schedule control..

  • 8/8/2019 Class Seven-Time Mgt

    11/97

  • 8/8/2019 Class Seven-Time Mgt

    12/97

    www.pmstudy.com 12

    Types of Dependencies Mandatory dependencies:

    Inherent in the nature of the work. Usually involve physical limitations. e.g. You cannot build the ceiling until walls of a

    house are completed.

    Discretionary dependencies: Defined by the project management team. Should be used with care and well documented

    since they may limit later scheduling options. e.g. Best practices.

    External dependencies: Involve a relationship between project activities

    and non-project activities (i.e. Activities out ofscope for the project).

    e.g. Dependency on the economy, environmentalfactors etc.

  • 8/8/2019 Class Seven-Time Mgt

    13/97

    www.pmstudy.com 13

    Precedence Diagramming

    Methods (PDM)

    Uses nodes to represent the activities and connectsthem with arrows that show dependencies.

    Includes four types of dependencies namely: Finish to start (most commonly used).

    Finish to finish. Start to start. Start to finish.

    Dummy activities not used. Does not allow loops or conditional branches.

  • 8/8/2019 Class Seven-Time Mgt

    14/97

    www.pmstudy.com 14

    Arrow Diagramming Methods (ADM)

    Method of constructing a project networkdiagram that uses arrows to represent theactivities and connects them at nodes to

    show their dependencies. Uses only finish-to-start dependencies.

    Dummy activities may be used.

    Does not allow loops or conditionalbranches.

  • 8/8/2019 Class Seven-Time Mgt

    15/97

    www.pmstudy.com 15

    Network Templates

    Standardized networks used to expeditepreparation of project network diagrams.

    Portions of a network are called subnets

    or fragnets:Useful when project includes several

    identical or close to identical features.

  • 8/8/2019 Class Seven-Time Mgt

    16/97

    www.pmstudy.com 16

    Activity Duration Estimating

    Process of taking information on projectscope and resources and then developingdurations for input to schedules.

    Progressively elaborated. Requires consideration of elapsed time.

  • 8/8/2019 Class Seven-Time Mgt

    17/97

    www.pmstudy.com 17

    Historical Information

    Available from:Project files : records of previous

    project results that are detailed enough

    to aid in duration estimatesCommercial duration estimating

    databases : this is available for

    standard tasksProject team knowledge : individual

    members of the project team may

    remember previous actual or estimates

  • 8/8/2019 Class Seven-Time Mgt

    18/97

    www.pmstudy.com 18

    Analogous Estimating (top-down

    Estimating)

    Uses the actual duration of a previous,similar activity as the basis for estimatingthe duration of a future activity.

    Is a form of expert judgment. Most reliable when:

    Previous activities are similar in fact

    and not just in appearance. Individuals preparing the estimateshave the needed experience.

  • 8/8/2019 Class Seven-Time Mgt

    19/97

    www.pmstudy.com 19

    Quantitatively based durations

    Quantities to be performed for eachspecific work category is taken

    It is then determined how many times the

    work category is going to be performed inthe given activity

    Time duration for the activity = number of

    occurrences X duration of one activity

  • 8/8/2019 Class Seven-Time Mgt

    20/97

    www.pmstudy.com 20

    Constraints Factors that will limit a management teams options. Two types of constraints are:

    Imposed dates: Used to restrict the start or finish dates for the tasks. Most commonly used constraints are start no

    earlier than and finish no later than. e.g. Market window on a technology project,

    weather restrictions on outdoor activities,government mandated compliance etc.

    Key events or major milestones: Completion of certain deliverables by specified

    dates as requested by project sponsor, customer orother stakeholders.

    Once scheduled, the milestones may be difficult tomove.

  • 8/8/2019 Class Seven-Time Mgt

    21/97

    www.pmstudy.com 21

    Mathematical Analysis

    Involves calculating theoretical early andlate start and finish dates.

    Popular techniques: Critical path method (CPM):

    Calculates a single deterministic early and late startand finish date for each activity based on specifiedsequential network logic and activity durationestimates.

    Project evaluation and review technique(PERT): Uses a weighted average duration estimate to

    calculate activity durations.

  • 8/8/2019 Class Seven-Time Mgt

    22/97

    www.pmstudy.com 22

    Duration Compression

    Special case of mathematical analysis Looks for ways to shorten the project

    schedule without changing project scope

    Techniques used: Crashing: in which cost and scheduletradeoffs are analyzed to determine how, if atall, to obtain the greatest amount of

    compression for the least incremental cost Fast tracking: doing activities in parallel thatwould normally be done in sequence. Oftenresults in rework and increases risk

  • 8/8/2019 Class Seven-Time Mgt

    23/97

    www.pmstudy.com 23

    Simulation

    Involves calculating multiple projectdurations with different sets of activityassumptions

    Common techniques:Monte Carlo analysis

    What-if analysis (using logic network to

    simulate different scenarios)

  • 8/8/2019 Class Seven-Time Mgt

    24/97

    www.pmstudy.com 24

    Resource Leveling Heuristics

    Done because mathematical analysis produces apreliminary early-start schedule that requires moreresources during certain time periods than are available.

    e.g. Rule of thumb allocate scarce resources to criticalpath activities first.

    Often results in a project duration that is longer than thepreliminary schedule. (Also called resource basedmethod).

    Resource reallocation: used to bring the schedule backor as close as possible to the originally intendedduration.

    Reverse resource allocation: if projects have a finite andcritical project resource, requiring that the resource bescheduled in reverse from the project ending date.

    Critical chain: A technique that modifies the projectschedule to account for limited resources.

  • 8/8/2019 Class Seven-Time Mgt

    25/97

    www.pmstudy.com 25

    Project Schedule

    Includes at least planned start andexpected finish dates for each activity.Presented graphically using:

    Project network diagramsBar charts and GANTT charts

    Milestone charts

  • 8/8/2019 Class Seven-Time Mgt

    26/97

    www.pmstudy.com 26

    Schedule Updates Any modification to the schedule information used to

    manage a project. Schedule baseline: this is the approved project schedule

    and is a component of the project plan. Provides the basisfor measuring and reporting schedule performance.

    Revisions: special categories of schedule updates

    because of scope/estimate changes. The schedulebaseline remains same, but start and end dates for someactivities may change.

    Re-baselining: done if schedule delays are very severe used to provide realistic data to measure performance.(Done in only extreme cases, because all historical datawill be lost for the project schedule).

    New target schedules: if there are small changes to theproject schedule, then the schedule baseline is keptconstant but new target schedules may be used.

  • 8/8/2019 Class Seven-Time Mgt

    27/97

    Project Time Management Planning

    Project time management involves the processes required toensure timely completion of a project. The main planning tasksperformed as part of project time management are activitydefinition, activity sequencing, activity resource estimating, activityduration estimation, and schedule development.

    Activity Definition: The project manager starts with the project charter and then

    develops a project scope statement, WBS, WBS dictionary, projectmanagement plan and other related documents.

    Creating the Activity List and Attributes:

    The activity list is a tabulation of activities to be included on aproject schedule. The list should include the activity name, anactivity identifier or number, and a brief description of the activity.

  • 8/8/2019 Class Seven-Time Mgt

    28/97

    Project Time Management Planning

    The activity attributes provide schedule related information abouteach activity, such as predecessors, successors, logicalrelationships, resource requirements, constraints, imposed dates,and assumptions related to the activity.

    The activity list and activity attributes should be in agreement with

    WBS and WBS dictionary The goal of activity list is to ensure that project team members are

    in complete understanding of all activities necessary to completethe project

    The WBS is often expanded during the activity definition process

    as the project team members further define the activities requiredfor performing the work.

  • 8/8/2019 Class Seven-Time Mgt

    29/97

    Project Time Management Planning

    The project team should review the activity list and attributes withkey stakeholders to avoid any mishap or unrealistic schedule whichmay delay overall project.

    Creating a milestone list:

    A milestone is a significant event on a project. It often take several

    activities and a lot of work to complete a milestone, but milestone itself is like a marker to help in identifying necessary activities

    Milestones are also useful tools for setting schedule goals andmonitoring progress, and project sponsors and senior managersoften focus on major milestones when reviewing projects.

  • 8/8/2019 Class Seven-Time Mgt

    30/97

    Project Time Management Planning

    Activity Sequencing: Activity sequencing involves reviewing the activity list and

    attributes, project scope statement, and milestone list to determinethe relationships or dependencies between activities.

    It also involves evaluating the reasons for dependencies and the

    different types of dependencies.A dependency or relationship relates to the sequencing of projectactivities or tasks. For example, does a certain activity have to befinished before another one can start? Can the project team doseveral activities in parallel?

  • 8/8/2019 Class Seven-Time Mgt

    31/97

    Project Time Management Planning

    Three basic types of dependencies:1. Mandatory dependencies are inherent in the nature of the work

    being performed on a project. They are sometime referred to asHard Logic because their relationships are unavoidable

    2. Discretionary dependencies are defined by the project team.

    For example, a project team might follow good practice and notstart detailed design work until key stakeholders sign off on all ofthe analysis work. Also known as soft logic

    3. External dependencies involve relationships between projectand non project activities. The installation of new software might

    depend on delivery of new hardware from an external supplier.

  • 8/8/2019 Class Seven-Time Mgt

    32/97

    Project Time Management Planning

    NETWORK DIAGRAMS: Network diagrams are the preferred technique to show activity

    sequencing.

    A network diagram is a schematic display of the logicalrelationships among, or sequencing of, project activities

    The format of network diagram uses the activity-on-arrow (AOA)approach, or the arrow diagramming method (ADM)

    AOA network diagrams are generally easy to understand andcreate a different method is more commonly used: the precedencediagramming method. The precedence diagramming method

    (PDM) is a network diagramming technique in which boxesrepresent activities.

  • 8/8/2019 Class Seven-Time Mgt

    33/97

    Project Time Management Planning

    Four types of dependencies:In a project network, a dependency is a link amongst a project'sterminal elements.

    1. Finish-to-start: a relationship in which the from activity must finishbefore the to activity can start. For example you cannot provide

    training until after the training materials are available. Finish-to-start isthe most common type of relationship, or dependency, and AOAnetwork diagrams use only finish-to-start dependencies.

    Task B cannot start until task A finishes, also known as (FS)

    (Foundations dug) FS(Concrete poured)

    A

    B

  • 8/8/2019 Class Seven-Time Mgt

    34/97

    Finish Start - Relationship

    I have two activities to complete in my project, which isto construct a wedding cake.

    The activities are to make the cake and put on thefrosting. The finish start relationship says that I cannot

    start putting the frosting on the cake until I have bakedthe cake layers.

    Notice that I could, logically, put the frosting on any timeafter that. The relationship constricts the start of theactivity of frosting the cake to be no sooner than thefinish of baking the cake.

  • 8/8/2019 Class Seven-Time Mgt

    35/97

    Project Time Management

    2 Start-to -start: A relationship in which the from activity cannotstart until the to activity is started. For example, as soon as youstart a project review meeting, you can start documentingattendees, serving refreshments, taking minutes, and so on.

    Task B cannot start until task A starts, also known as SS(Project work started) SS(Project management activities

    started)

    A

    B

  • 8/8/2019 Class Seven-Time Mgt

    36/97

    Start Start Relationship

    For example, using the above example of constructing awedding cake, I do not want to apply the frosting to the cake untilthe master chef is on scene. The two activities then are:

    1. apply frosting to cake

    2. Master chef supervises cake construction

    The start-start relationship says that I cannot start putting thefrosting on the cake until I have the master chef present. Noticethat I could, logically, put the frosting on any time after that. Therelationship constricts the start of the activity of frosting the caketo be no sooner than the beginning of the master chef

    supervising the cake construction.

  • 8/8/2019 Class Seven-Time Mgt

    37/97

    Project Time Management

    3 Finish-to finish: a relationship in which the from activity must befinished before the to activity can be finished. One task cannotbe finished until another finishes. For example, quality controlefforts cannot finish before production finishes, although bothactivities can be performed at the same time.

    Task B cannot finish until task A finishes, also known as FF

    (Last chapter written) FF(Entire book

    written)

    A

    B

  • 8/8/2019 Class Seven-Time Mgt

    38/97

    Finish-Finish Relationship

    For example, using the example of applying the frosting to thewedding cake, I must have the master chef there until thefrosting is complete so that he or she can approve it. The masterchef is then restricted from finishing the supervising activity untilthe frosting activity is finished. The two activities are:

    1. Apply frosting to cake2. Master chef supervises cake construction

    The finish finish relationship says that the master chef cannotfinish supervising the cake construction until the frosting iscompleted. Notice that I could, logically, have the master chef

    continue supervising after that. The relationship constricts thefinish of the master chef supervising activity to be no soonerthan the finish of the frosting activity

  • 8/8/2019 Class Seven-Time Mgt

    39/97

    Project Time Management

    4 Start-to-finish: a relationship in which the from activity must startbefore the to activity can be finished. This type of activity is rarelyused, but it is appropriate in some cases. For example, anorganization might strive to stock raw material just in time for themanufacturing process to begin. A delay in the start of themanufacturing should delay completion of stocking the raw

    material

    Task B cannot finish until task A starts, also known as SF

    (New shift started) SF (Previous shift finished)

    A

    B

  • 8/8/2019 Class Seven-Time Mgt

    40/97

    Start Finish Relationship

    For an example, using the wedding cake example again, te

    project is still to construct a wedding cake, and the activity is toapply the frosting to the cake. We do not want to finish applyingthe frosting to the cake until the master chef is on the scene. Thetwo activities then are:

    1. Applying frosting to the cake

    2. Master chef supervises cake constructionRemember that the start-start relationship says that I cannotstart putting the frosting on the cake until I have the master chefpresent. The start finish relationship says that I cannot startputting on the frosting on the cake until I have the master chef

    present. The start finish relationship says that I can start puttingon the of the cake before the master chef is present, but I am notallowed to finish putting on the frosting until the master chef hasstarted supervising. The relationship constricts the finish of theactivity of frosting the cake to be no sooner than the beginning ofthe master chef supervising the cake construction.

  • 8/8/2019 Class Seven-Time Mgt

    41/97

    Activity Resource Estimating

    The estimate of duration for each activity needs good idea ofquantity and type of resources (people, equipment and material)that will be assigned to each activity.

    Important questions to answer in activity resource estimatingincludes:

    1. How difficult will it be to do specific activities on the project?2. Is there any unique in the projects scope statement that will

    affect resources?

    3. Does the organization have appropriate people, equipment, andmaterials available for performing the work?

    4. Does the organization need to acquire more resources for thisproject? Would it make sense to outsource some of the work?

  • 8/8/2019 Class Seven-Time Mgt

    42/97

    Activity Resource Estimating

    Sample for ARE: Project name: Just-in-time Training Project

    WBS item number: 3.1.2

    WBS Name: Administer Survey

    Description: Internal members of ourIT department will performthis task. The individual must be knowledgeable in using onlinesurvey software so that they can enter the actual survey into thissoftware. They must also know how to run a query to find the e-mail addresses of employees in purchasing, accounting,engineering, IT, sales, marketing, manufacturing, and HR

    departments.

  • 8/8/2019 Class Seven-Time Mgt

    43/97

    Activity Duration Estimating

    After working with key stakeholders to define activities, determinetheir dependencies, and estimate their resources, the next processin project time management is to estimate the duration of theactivities.

    It is important to note that duration includes the actual amount of

    time spent working on an activity plus elapsed time. The output of activity duration estimating include updates to the

    activity attributes, if needed, and duration estimates for eachactivity. Duration estimates are provided as a discrete numbers,such four weeks, as a range, such as three to five weeks; or asthree point estimate.

    Three point estimate is an estimate that includes an optimistic,most likely and pessimistic estimate.

  • 8/8/2019 Class Seven-Time Mgt

    44/97

    Schedule Development

    Schedule development uses the results of all the preceding projecttime management processes to determine the start and end datesof project activities and of the entire project.

    The ultimate goal of the schedule development is to create a

    realistic project schedule that provides a basis for monitoringproject progress for the time dimension of the project.

    Project manager must lead their teams in creating realisticschedules and then following them during project execution.

  • 8/8/2019 Class Seven-Time Mgt

    45/97

    www.pmstudy.com45

    PERT Estimations

    Term Formula Used

    PERT Value(Expected duration)

    (Pessimistic+ 4*(Most Likely) + Optimistic)6

    Standard Deviation(Sigma)

    Pessimistic Optimistic

    6

    Variance (Standard Deviation)2

    For more than one Tasks (e.g. for a project where all tasks lie on the critical path)

    Term Formula UsedPERT Value Sum of PERT Values of individual

    tasks

    Standard Deviation Sum of Variances of all the tasks

    Variance Sum of variances of all the tasks

  • 8/8/2019 Class Seven-Time Mgt

    46/97

    Continuous ImprovementContinuous Improvement

  • 8/8/2019 Class Seven-Time Mgt

    47/97

    Correct Choice: 2

    Justification: Activity Attributes: Attributes of the activities -including responsibility (i.e. who will perform the work), geographic area orbuilding (where the work has to be performed) and activity type (i.esummary or detailed) - are very important for further selection and sorting ofthe planned activities in a convenient way for the users. WBS classificationis also an important attribute that allows useful activity ordering and sorting.

    PMBOK 2000 Page 74

  • 8/8/2019 Class Seven-Time Mgt

    48/97

    Continuous ImprovementContinuous Improvement

  • 8/8/2019 Class Seven-Time Mgt

    49/97

    Continuous ImprovementContinuous Improvement

  • 8/8/2019 Class Seven-Time Mgt

    50/97

    Continuous ImprovementContinuous Improvement

  • 8/8/2019 Class Seven-Time Mgt

    51/97

    Continuous ImprovementContinuous Improvement

  • 8/8/2019 Class Seven-Time Mgt

    52/97

  • 8/8/2019 Class Seven-Time Mgt

    53/97

  • 8/8/2019 Class Seven-Time Mgt

    54/97

  • 8/8/2019 Class Seven-Time Mgt

    55/97

  • 8/8/2019 Class Seven-Time Mgt

    56/97

  • 8/8/2019 Class Seven-Time Mgt

    57/97

  • 8/8/2019 Class Seven-Time Mgt

    58/97

  • 8/8/2019 Class Seven-Time Mgt

    59/97

  • 8/8/2019 Class Seven-Time Mgt

    60/97

    Continuous ImprovementContinuous Improvement

    Project Management

    PERT and CPMPERT: The program evaluation and review technique

    along with CPM: Critical Path Method are two popular

    quantitative analysis techniques that help managers

    plan, schedule, monitor, and control large and complexprojects.

    CPM also called critical path analysis is a network

    diagramming technique used to predict total project

    duration.

  • 8/8/2019 Class Seven-Time Mgt

    61/97

    Six Steps of PERT and CPM

    1. Define the project and all of its significant activities or tasks2. Develop the relationships among the activities. Decide which

    activities must precede others

    3. Draw the network connecting all of the activities

    4. Assign time and/or cost estimates to each activity

    5. Compute the longest time path through the network; this iscalled the critical path

    6. Use the network to help plan, schedule, monitor, and control theproject

  • 8/8/2019 Class Seven-Time Mgt

    62/97

    PERT Understanding

    Almost any large project can be subdivided into a series ofsmaller activities or tasks that can be analyzed with PERT.When you recognize that projects can have thousands ofspecific activities, you see why it is important to be able toanswer such questions as the following:

    1. When will the entire project be completed?

    2. What are the critical activities or tasks in the project,that is, the ones that will delay the entire project ifthey are late?

    3. Which are the non critical activities, that is, the onesthat can run late without delaying the entire projectscompletion?

    4. What is the probability that the project will becompleted by a specific date?

  • 8/8/2019 Class Seven-Time Mgt

    63/97

    PERT

    5. At any particular date, is the project on schedule,behind schedule , or ahead of project schedule?

    6. On any particular date, is the money spent equal to,less than, or greater than the budgeted amount?

    7. Are there enough resources available to finish theproject on time?

    8. If the project is to be finished in a shorter amount oftime, what is the best way to accomplish this at theleast cost?

  • 8/8/2019 Class Seven-Time Mgt

    64/97

    General foundry example of PERT

    General foundry, a metal works plant in Milwaukee,has been trying to avoid the expense of installing airpollution control equipment. The local environmentalprotection group has recently given the foundry 16weeks to install a complex air filter system on its mainsmokestack.

    All the activities seem rather confusing and complexuntil they are placed in a network.

    Activities and Immediate predecessors for General

    foundry listed down for further action Total eight number of activities were found

  • 8/8/2019 Class Seven-Time Mgt

    65/97

    ACTIVITY/PREDECESSORS Table

    Activity Description ImmediatePredecessors

    A Build Internal Components -

    B Modify Roof and Floor -C Construct Collection Stack A

    D Pour concrete and install frame B

    E Build high temperature burner C

    F Install control system C

    G Install air pollution device D, E

    H Inspect and Test F, G

  • 8/8/2019 Class Seven-Time Mgt

    66/97

    Drawing the PERT Network

    Once the activities have all been specified andmanagement has decided which activities mustprecede others, the network can be drawn.

    There are two common techniques for drawing PERT

    networks. The first is called activity-on-node (AON) andthe second one is called activity-on-arc (AOA).

    In constructing an AON network, there should be onenode representing start of the project and one noderepresenting the finish of the project.

  • 8/8/2019 Class Seven-Time Mgt

    67/97

    Network for General foundry,Inc.

  • 8/8/2019 Class Seven-Time Mgt

    68/97

    Activity Times

    The next step in the PERT procedure is to assign estimates of thetime required to complete each activity. This is usually given in units of weeks. Activity time estimates is not always an easy task, therefore it

    needs historical data. Experts opinion etc. Due to uncertainty in activity times, the developers of PERT

    employed a probability distribution based on three time timesestimates for each activity

    PERT often assumes that time estimates follow the beta probabilitydistribution. It has been found to be appropriate for determining anexpected value and variance for activity completion times.

  • 8/8/2019 Class Seven-Time Mgt

    69/97

    Activity Times

    Optimistic time (a) = time an activity will take if everything goes aswell as possible. There should be only a small probability (say,1/100) of this occurring.

    Pessimistic time (b) = time an activity would take assuming veryunfavorable condition. There should also be only a smallprobability that the activity will really take this long.

    Most likely time (m) = most realistic time estimate to complete theactivity

    t = a + 4m + b/6

  • 8/8/2019 Class Seven-Time Mgt

    70/97

    Time Estimates

    Activity Optimistic

    (a)

    Most probabl

    (m)

    Pessimistic

    (b)

    Expected tim

    (t)

    Variance

    (b-a)/6^2

    A 1 2 3 2 4/36

    B 2 3 4 3 4/36

    C 1 2 3 2 4/36

    D 2 4 6 4 16/36

    E 1 4 7 4 36/36

    F 1 2 9 3 64/36

    G 3 4 11 5 64/36

    H 1 2 3 2 4/36

  • 8/8/2019 Class Seven-Time Mgt

    71/97

    How to find the Critical Path

    The critical path is the longest time path route through thenetwork.

    Any delay of an activity on the critical path will delay completionof the entire project

    1. Earliest start time (ES); an activity can begin without violation of

    immediate predecessor requirement2. Earliest finish time (EF); an activity can end

    3. Latest start time (LS); an activity can begin without delaying theentire project

    4. Latest finish time (LF); an activity can end without delaying the

    entire project

  • 8/8/2019 Class Seven-Time Mgt

    72/97

    Box understanding

    This box comprises of activity, duration (t) and timesalready explained

    Activity t

    ES EF

    LS LF

  • 8/8/2019 Class Seven-Time Mgt

    73/97

    Calculation

    Earliest Time: EF = ES + t Earliest start = largest of earliest finish times of

    immediate predecessors

    Start

    A t=2ES=0 EF=0+2=2

    B t=3ES=0 EF=0+3=3

  • 8/8/2019 Class Seven-Time Mgt

    74/97

    General Foundrys Network with expected Activity Times

  • 8/8/2019 Class Seven-Time Mgt

    75/97

    General Foundrys Earliest Start (ES) and Earliest Finish (EF) Times

  • 8/8/2019 Class Seven-Time Mgt

    76/97

    Latest Times

    The next step in finding the critical path is to computethe latest start time (LS) and the latest finish time (LF)for each activity. This calculation is called as backwardpass.

    Latest start time= latest finish time-activity time

    LS = LF t

    Latest finish time= smallest of latest start times foractivities

  • 8/8/2019 Class Seven-Time Mgt

    77/97

    Slack in Critical Path

    When ES, LS, EF, and LF have been determined, it is a

    simple matter to find the amount of slack time, or free time,that each activity has. Slack is the length of time an activitycan be delayed without delaying the whole project.

    Slack = LS ES or slack = LF EF Critical activities have no slack time

    In project management, float orslack is the amount oftime that a task in a project network can be delayed withoutcausing a delay to subsequent tasks (free float)

    project completion date (total float)

    An activity that has a total float equal to zero is said to be a'critical activity', which means that a delay in the finish timeof this activity will cause the entire project to be delayed bythe same amount of time. A critical activity typically hasfree float equal to zero, but an activity that has zero freefloat may not be on the critical path.

  • 8/8/2019 Class Seven-Time Mgt

    78/97

    Slack or Floats

    Consider the process of replacing a broken pane of glass in the window of your home. There are variouscomponent activities involved in the project as a whole;obtaining the glass and putty, installing the new glass,choosing the paint, obtaining a tin of paint, painting thenew putty once it has set, wiping the new glass free of

    finger smears etc. Some of these activities can run concurrently e.g.

    obtaining the glass, obtaining the putty, choosing thepaint etc., while others are consecutive e.g. the paintcannot be bought until it has been chosen, the new puttycannot be painted until the window is installed and thenew putty has set. Delaying the acquisition of the glassis likely to delay the entire project - this activity will be onthe critical path and have no float, of any sort, attachedto it and hence it is a 'critical activity'.

  • 8/8/2019 Class Seven-Time Mgt

    79/97

    A relatively short delay in the purchase of the paint maynot automatically hold up the entire project as there isstill some waiting time for the new putty to dry before itcan be painted anyway - there will be some 'free float'

    attached to the activity of purchasing the paint andhence it is not a critical activity. However a delay in choosing the paint in turn inevitably

    delays buying the paint which, although it may notsubsequently mean any delay to the entire project,

    does mean that choosing the paint has no 'free float'attached to it - despite having no free float of its ownthe choosing of the paint is involved with a path throughthe network which does have 'total float'.

    Slack or Floats

  • 8/8/2019 Class Seven-Time Mgt

    80/97

    General foundrys Latest Start (LS) and Latest Finish (LF) Times

  • 8/8/2019 Class Seven-Time Mgt

    81/97

    Schedule and Slack times

    activity ES EF LS LF Slack On Critical

    Path

    A 0 2 0 2 0 Yes

    B 0 3 1 4 1 No

    C 2 4 2 4 0 Yes

    D 3 7 4 8 1 No

    E 4 8 4 8 0 Yes

    F 4 7 10 13 6 No

    G 8 13 8 13 0 Yes

    H 13 15 13 15 0 Yes

  • 8/8/2019 Class Seven-Time Mgt

    82/97

    General Foundrys Critical Path (A-C-E-G-H)

  • 8/8/2019 Class Seven-Time Mgt

    83/97

    Probability of Project Completion

    The critical path analysis helped us determine thatfoundrys expected project completion time is 15 weeks.If the project is not completed in 16 weeks, Generalfoundry will be forced to close by environmentcontrollers (legal requirement). On the basis of thisrequirement any variation in critical path may affect the

    completion of project on time. PERT uses the variance of critical path activities to help

    determine the variance of the overall project. If theactivity times are statistically independent, the projectvariance is computed by summing the variances of thecritical activities

  • 8/8/2019 Class Seven-Time Mgt

    84/97

    Project Completion Probability

    Project variance = variances of activities on criticalpath

    Project variance= 4/36+4/36+36/36+64/36+4/36=3.111

    Project standard deviation = = project variance

    Project standard deviation = 3.111 = 1.76 weeks How can this information be used to help answer

    questions regarding the probability of finishing theproject on time?

    Assume that the total project completion time follows anormal probability distribution.

  • 8/8/2019 Class Seven-Time Mgt

    85/97

    Standard Deviation=1.76 Weeks

    15 Weeks

    (Expected Completion Time)

  • 8/8/2019 Class Seven-Time Mgt

    86/97

    Project Completion Probability

    To find the probability that this project will be finished on or before the 16week deadline, we need to determine the appropriate area under thenormal curve.

    Z = due date expected date of completion/ Z = 16 weeks 15weeks/1.76 weeks Z = 0.57

    Where Z is the number of standard deviations the due date or target datelies from the mean or expected date. From normal table we can find the value of Z Value of Z is 0.71566, there is a 71.6% chance that the pollution control

    equipment can be put in place in 16 weeks or less.

  • 8/8/2019 Class Seven-Time Mgt

    87/97

    Probability of Meeting 16-Weeks Deadline

    15

    Weeks

    Expected Time is 15 Weeks .57 Standard Deviation

    Probability(T 16 Weeks)is 71.6%

    16

    Weeks

  • 8/8/2019 Class Seven-Time Mgt

    88/97

    What PERT was able to Provide

    1. The projects expected completion date is 15 weeks2. There is a 71.6% chance that the equipment will be in placewithin 16-week deadline.

    3. Five activities (A, C, E, G, H) are on the critical path. Any delayon this path will delay entire project

    4. Three activities (B, D, F) are not critical but have some slacktime built in. this means that resources can be borrowed withoutdisturbing entire project completion time.

    5. A detailed schedule of activity starting and ending dates hasbeen made available.

  • 8/8/2019 Class Seven-Time Mgt

    89/97

    Continuous ImprovementContinuous Improvement

    PERT/COST

    PERT is an excellent method of monitoring and controllingproject length, it does not consider another very important

    factor, project cost. PERT/COST is a modification of PERT

    that allows a manager to plan, schedule, monitor, and

    control cost as well as time.

    Budgeting process of a project

    Four steps of the budgeting process:

    1. Identify all costs associated with each of the activities.

    Then add these costs together to get one estimated cost or

    budget for each activity

    2. If you are dealing with large project, several activities can

    be combined into larger work packages. A work package issimply a logical collection of activities

    C

  • 8/8/2019 Class Seven-Time Mgt

    90/97

    Project Cost Monitoring

    3 Covert the budgeted cost per activity into a cost per time period. To do this, weassume that the cost of completing any activity is spent at a uniform rate overtime. Thus, if the budgeted cost for a given activity is $48,000 and the activitysexpected time is four weeks, the budgeted cost per week is $12,000 (=$48000/4weeks)

    4 Using the earliest and latest start times, find out how much money should bespent during each week or month to finish the project by the date desired.

    B d t f G l F d

  • 8/8/2019 Class Seven-Time Mgt

    91/97

    Budget for General Foundry

    Gantt Chart for General Foundry

    1 2 3 4 5 6 7 8 9 10 11 12 13 14

    A

    B

    CD

    E

    F

    G

    H

    Budget for General Foundry

  • 8/8/2019 Class Seven-Time Mgt

    92/97

    Budget for General Foundry

    Activity Earliest StartTime ES

    Latest startTime LS

    Expected Time, t Total Budgeted cost Budgeted cost perweek ($)

    A 0 0 2 22000 11000

    B 0 1 3 30000 10000

    C 2 2 2 26000 13000

    D 3 4 4 48000 12000

    E 4 4 4 56000 14000

    F 4 10 3 30000 10000

    G 8 8 5 80000 16000

    H 13 13 2 16000 8000

    Budget for General Foundry

  • 8/8/2019 Class Seven-Time Mgt

    93/97

    Budget for General Foundry

    The weekly budget for the project is developed from the previous data. The earlieststart time for activity A, for example is 0. Because A takes 2 weeks to complete, isweekly budget of $11,000 should be spent in weeks 1 and 2. Similar calculation isvalid for all activities as per Gantt chart and earliest start time.

    The weekly budgeted cost as per activities duration is very simple to perform.

    B d t d C t

  • 8/8/2019 Class Seven-Time Mgt

    94/97

    Budgeted Cost

    Budgeted Cost ES

    activity

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total

    A 11 11 22

    B 10 10 10 30

    C 13 13 26D 12 12 12 12 48

    E 14 14 14 14 56

    F 10 10 10 30

    G 16 16 16 16 16 80

    H 8 8 16

    total 308

    total/wk

    21 21 23 25 36 36 36 14 16 16 16 16 16 8 8

    total 21 42 65 90 126 162 198 212 228 244 260 276 292 300 308

    B d t d C t

  • 8/8/2019 Class Seven-Time Mgt

    95/97

    Budgeted Cost

    Budgeted Cost LS

    activity

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Total

    A 11 11 22

    B 10 10 10 30

    C 13 13 26D 12 12 12 12 48

    E 14 14 14 14 56

    F 10 10 10 30

    G 16 16 16 16 16 80

    H 8 8 16

    total 308

    total/wk

    11 21 23 23 26 26 26 26 16 16 26 26 26 8 8

    total 11 32 55 78 104 130 156 182 198 214 240 266 292 300 308

    Monitoring and Controlling Project Costs

  • 8/8/2019 Class Seven-Time Mgt

    96/97

    Monitoring and Controlling Project Costs

    The purpose of monitoring and controlling projects costs is to ensure that theproject is progressing on schedule and that cost overruns are kept to a minimum.The status of entire project should be checked periodically.

    Having same project with additional information after starting the project andstanding in sixth week of the 15-week project. Activities A, B, and C have beenfinished. These activities incurred costs of $20,000, $36,000 and $26,000respectively. Activity D is only 10% completed and so far the cost expended has

    been $6000. Activity E is 20% completed with an incurred cost of $20,000, andactivity F is 20% completed with an incurred cost of $4,000. activities G and H havenot been started. Check for Overrun?

    Monitoring and Controlling Project Costs

  • 8/8/2019 Class Seven-Time Mgt

    97/97

    Monitoring and Controlling Project Costs

    Monitoring and controlling project costs:

    Activity Total budgeted cost($)

    Percent of completion Value of workcompleted ($)

    Ac tual Cost ($) Activity Di fference ($)

    A 22,000 100 22,000 20,000 -2,000

    B 30,000 100 30,000 36,000 6,000

    C 26,000 100 26,000 26,000 0

    D 48,000 10 4,800 6,000 1200

    E 56,000 20 11,200 20,000 8800

    F 30,000 20 6,000 4,000 -2,000

    G 80,000 0 0 0 0

    H 16,000 0 0 0 0

    Total 100,000 112,000 12,000 overrun