McCORMICK PLACEHEADQUARTERS HOTEL & EVENT CENTER
Metropolitan Pier and Exposition Authority
McCormick Experience
Why Design Build ?
(MBE)
(MBE)
(MBE)
(MBE/WBE)
(MBE)
(Hotel) (Event Center)
DESIGN-BUILD LEAD
DIVERSITY/ COMMUNITY
OUTREACH MANAGER
CONSTRUCTION MANAGEMENT
PARTNERS
DESIGN LEADS
Past Success at McCormick Place
2. Hotel Overview
Key Facts• 1206-room, 40-floor, Marriott Marquis
Hotel• (2) 25,000sf Ballrooms• 90,000sf Meeting Space• Renovation of Historic ABC Building• Central Plant Upgrades• Anticipated Completion – Q3 2017
Aerial View Southeast East Elevation
Street Level – Podium Street Level – Pedestrian Walkways
Hotel Base Design Hotel Alternate Design
Hotel Base Design
Hotel Alternate Design
Design Refinement Results• Reduced Elevators• Reduced Enclosure• Removed Building Maintenance Unit• Refined Structure• Mechanical Floor Removed
Schedule Highlights• 32-month Design-Build Contract• Schematic & Design Development• Early Demolition & Enabling Work• 25-month Construction Schedule• Potential Early Occupancy
3. Event Center Overview
Key Facts• MPEA/DePaul University Partnership• 10,000-seat, 300,000sf Basketball
Arena & Multi-Purpose Venue• Anticipated Completion – Q3 2017• Pelli Clarke Pelli – Design Architect • Moody Nolan – Architect-of-Record
Design Refinement ResultsMaintained the Spirit of the Pelli Clarke Pelli Design Concept• Raised Event Floor To Grade (was -22.5’)• Building Area Reduced By (approximately) 30,000
GSF• Simplified Roof Expression/Structure• Simplified Façade Materials & Detailing• Simplified HVAC Distribution
Event Center Options
Original
Modified
Aerial View - Original Aerial View - Modified
Event Center– Entry at Cermak Road
Event Level - Original Event Level - Modified
Building Section – Viewing North
Entry Lobby
Event Space /Arena
Schedule Highlights• 30-month Design-Build Contract• Initial Design “Reset” Phase• Schematic & Design Development• Early Demolition & Enabling Work• 23-month Construction Schedule
McCORMICK PLACEHEADQUARTERS HOTEL & EVENT CENTER