Claremore Medical Office Building
From Landfill to Medical Office Building
A Brownfield Success Story
THE GREEN SIDEOF BROWNFIELD REMEDIATION
![Page 2: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/2.jpg)
In 2002, Claremore Hospital initiated plans to develop a medical office building (MOB) adjacent to the hospital on a
vacant lot owned by the City of Claremore.
![Page 3: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/3.jpg)
Site located in a mixed commercial and residential area in Claremore
Claremore Regional Hospital adjacent site to the south.
![Page 4: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/4.jpg)
ESA Site Reconnaissance:Approximate 5.5 acre vacant, grass-covered lot with baseball fields.
![Page 5: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/5.jpg)
Previous report of “Subsurface Evaluation of the City of Claremore Abandoned Landfill” dated October 27, 1992 indicated the landfill was located on subject site and property currently occupied by public library. Report indicated the landfill began operations between 1941 and 1958, and was closed between 1958 and 1964.
A local resident stated that, as a child, he lived near the subject site and recalled a landfill on the site. He believed the landfill was approximately 30-40 feet deep.
![Page 6: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/6.jpg)
Site Investigation / Methane Evaluation
Borings and temporary monitor wells installed in February and June 2003– Arsenic, chromium, lead and mercury, and 1,4-
dichlorobenzene concentrations exceed MCLs in groundwater samples
July 2003, Claremore Regional Hospital:– Contracted with the ODEQ under the Oklahoma
Brownfields Voluntary Redevelopment Act (Memorandum of Agreement and Consent Order [MACO])
![Page 7: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/7.jpg)
Brownfield Process
Site Characterization completed in 2003– Data, Historical Summaries– Pathway/Receptor Assessment– Risk Assessment– Remedial Options
Preliminary landfill methane analysis in November 2003 and methane recovery system design in August 2004
![Page 8: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/8.jpg)
Cross Section
TRASH AND DEBRIS
![Page 9: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/9.jpg)
Brownfield Process
Public Notice of Draft Site Cleanup Plan (Dec. 14, 2004)
Final Site Cleanup Plan (Feb. 8, 2005)
![Page 10: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/10.jpg)
Elements of Site Cleanup Plan
Primary receptors:– Commercial workers exposed to methane and VOCs
via inhalation of vapors– Construction workers exposed to via dermal contact
and ingestion of impacted soil and GW
Remedial measures– Slab-on-pier building design– Segregation and disposal of contaminated soil
and GW– Methane monitoring/evacuation system
![Page 11: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/11.jpg)
Cleanup Plan Implementation
Risk Management Before Construction Operations– Pre-construction meeting (December 2004)
Risk Management During Construction Operations– Communications to workers about contaminant
exposure– Construction worker PPE– Management of wastes– Equipment decontamination– Limited access to construction site– Methane monitoring and ventilation system
![Page 12: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/12.jpg)
PPE for construction workers while drilling piers
Setting rebar for concrete piers
Construction Worker Exposure
![Page 13: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/13.jpg)
Solid Waste (Drill cuttings for piers)
Groundwater Waste (Pumped from piers)
Management of Wastes
![Page 14: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/14.jpg)
Finished Piers for Foundation
![Page 15: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/15.jpg)
Manifolded Gathering System
Perforated PVC Pipe
Methane and VOC Gathering System
![Page 16: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/16.jpg)
20-mil HDPE Geomembrane and Boots Around Piers, Elevator, Utilities and Other Penetrations
![Page 17: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/17.jpg)
Medical Office Building
PVCVentilationPipe Riser
Rooftop Vent Fan
![Page 18: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/18.jpg)
Sump for drainage from methane gathering system
Interior-Mounted Ultima X Gas
Methane Monitor & Alarm
![Page 19: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/19.jpg)
Cleanup Plan Implementation
Post-Construction Risk Management– Methane monitoring of building interior
Future Monitoring and Maintenance Requirements– Cover soil to prevent erosion– Construction worker protection during future
construction– Groundwater monitoring (Limited time)– Methane monitoring and ventilation system
maintenance
![Page 20: Claremore Medical Office Building From Landfill to Medical Office Building A Brownfield Success Story THE GREEN SIDE OF BROWNFIELD REMEDIATION.](https://reader035.fdocuments.in/reader035/viewer/2022062519/56649c925503460f9494df0e/html5/thumbnails/20.jpg)
Land Use Restrictions
No residential use of property No use of groundwater and no drilling of wells
other than for investigation or remediation No excavation below 2 feet without ODEQ
approval