CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box 678 Croydon Vic 3136 Telephone: 9723 0744 Facsimile: 9723 0799 18453: NB268 August 2018 30 th August 2018 Our Reference: 18453:NB268 Winslow Constructors Pty Ltd 50 Barry Road CAMPBELLFIELD VIC 3061 Dear Sirs/Madams, RE: LEVEL 1 EARTHWORKS INSPECTION AND TESTING SEVENTH BEND STAGE 4 (MELTON SOUTH) Please find attached our Report No’s 18453/R001 18453/R005 which relate to the field density testing that was conducted within the filled allotments at the above subdivision. The level 1 inspections and associated field density testing was performed in August 2018. The inspections and testing of the earthworks was undertaken in general accordance with the Level 1 requirements of AS 3798 - Guidelines on Earthworks for Commercial and Residential Developments. The site inspection and testing was performed by experienced geotechnicians from this office. Any areas that were deemed unsatisfactory were reworked and retested under their supervision. The testing was performed to the relevant Australian Standards and the accompanying test reports carry NATA endorsement. The attached compaction results, which were located randomly throughout the fill profile, are considered to be representative of the bulk fill materials that were placed across the reported allotments by Winslow Constructors during the aforementioned period. The approximate locations of the field density tests can be seen on the attached plan (Figure 1). We are of the view that the bulk fill materials that have been placed across the reported allotments by Winslow Constructors during the aforementioned period can be considered as having been placed in a controlled manner to a minimum density ratio of 95% (standard compactive effort). Please contact the undersigned if you require any additional information. Civil Geotechnical Services Nick Brock

Transcript of CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL...

Page 1: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

CIVIL GEOTECHNICAL SERVICES

ABN 26 474 013 724

PO Box 678 Croydon Vic 3136

Telephone: 9723 0744 Facsimile: 9723 0799

18453: NB268 August 2018

30th August 2018

Our Reference: 18453:NB268

Winslow Constructors Pty Ltd

50 Barry Road

CAMPBELLFIELD VIC 3061

Dear Sirs/Madams,

RE: LEVEL 1 EARTHWORKS INSPECTION AND TESTING

SEVENTH BEND – STAGE 4 (MELTON SOUTH)

Please find attached our Report No’s 18453/R001 – 18453/R005 which relate to the field

density testing that was conducted within the filled allotments at the above subdivision. The

level 1 inspections and associated field density testing was performed in August 2018.

The inspections and testing of the earthworks was undertaken in general accordance with the

Level 1 requirements of AS 3798 - Guidelines on Earthworks for Commercial and Residential

Developments.

The site inspection and testing was performed by experienced geotechnicians from this office.

Any areas that were deemed unsatisfactory were reworked and retested under their

supervision. The testing was performed to the relevant Australian Standards and the

accompanying test reports carry NATA endorsement. The attached compaction results, which

were located randomly throughout the fill profile, are considered to be representative of the

bulk fill materials that were placed across the reported allotments by Winslow Constructors

during the aforementioned period. The approximate locations of the field density tests can be

seen on the attached plan (Figure 1).

We are of the view that the bulk fill materials that have been placed across the reported

allotments by Winslow Constructors during the aforementioned period can be considered as

having been placed in a controlled manner to a minimum density ratio of 95% (standard

compactive effort).

Please contact the undersigned if you require any additional information.

Civil Geotechnical Services

Nick Brock

Page 2: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

��������������� ������ ���������������������� ������������������ ���� � �!"#$%&'&() *$'+*,-*.-$ */0123/4*5��3.�67�510/487/�9/4 '7//6:)���;<=>?@�AB�C.DDE* *�6/ '��F/:G:.�D513�1H�F IJKLMNJOPQRSTUVTJWRXJYRZ.[):\]:�̂�:\]�:�\_-7/0/:4/01230:�34:45��1320:�5/67/:��H̀51276:�C:'a$8:.�065�F1�D6̀:b64�-7/:45��132:07�FF:3�6:c/5/H5�4��/4:�5:��H1/4d:13:�7�F/:�5H�56d:�167��6:67/:�5166/3:H/5�1001�3�C:'a$8:.�065�F1�:D6̀:b64�-7/:��36/360:�C:6710:45��132:�5//F/�65�31��FF̀:2/3/5�6/4d:�5/��3C14/361�F:�34:��̀:�3F̀:c/:�0/4C�5:67/:H�5H�0/:C�5:�71�7:67/̀:�5/136/34/4�.FF:0/66132:��6:07��F4:c/:��551/4:��613:����54�3�/:�167:e..+8��3�1FE006�34�54:45��1320:�5:�0:3��13�6/4�3:7�54:��H̀:HF�30:H5�f14/4:c̀'a$8�:.3̀:41216�F:13C�5��61�30�HHF1/4:c̀:6710:�CC1�/:10:C�513C�5��61�3:�3F̀�:.3̀:410�5/H�3�1/007��F4:c/:410��00/4:�167:67/0�H/5136/34/36� ��������gh�ib/f/F:��d:]�:j�//30:#��4d:a/Fc��53/:%&8:k��\l:m̂�:k:_��\:����::n::o:m̂�:k:_��\:��� :n::����0�/����� ,�5:8�3065��61�3Fpq��59q/32q ��/:r:/sC�54:5��4d:�/F6�3q ��/r�\q4�20:H4Cq ��/r�\r� a/Fc��53/:%&8:k��\b/f/F:�d:\̂t:'6:u1F4�:#��4.D*:D5�v/�60:D6̀:b64 w�3��5̀: ��])�x�FF��b�%1/̀5�'�'�67�01f��b�-�̀F�5 �p��� �_ �yyz�{�|{�yb�̀��6:DF�3:#��4��590:�34:*5�13�2/:a/F6�3:816̀:8��3�1F'6�2/:\}oA;~�A<~�h!��A?�FIGURE 1

# Approximate field density test location

1

2

3

4

5

6

789

10

11

12

13

1415

16

1718

1920

2122

Page 3: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

COMPACTION ASSESSMENT

Job No 18453

CIVIL GEOTECHNICAL SERVICES Report No 18453/R001

6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018

Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB

Project SEVENTH BEND - STAGE 4 Date tested 06/08/18

Location MELTON SOUTH Checked by JHF

Feature EARTHWORKS 200 mm Time: 13:45

Test procedure AS 1289.2.1.1 & 5.8.1

Test No 1 2 3 - - -

Location

REFER REFER REFER

TO TO TO

FIGURE 1 FIGURE 1 FIGURE 1

Approximate depth below FSL

Measurement depth mm 175 175 175 - - -

Field wet density t/m³ 1.97 1.97 1.99 - - -

Field moisture content % 19.7 18.2 16.7 - - -

Test procedure AS 1289.5.7.1

Test No 1 2 3 - - -

Compactive effort

Oversize rock retained on sieve mm 19.0 19.0 19.0 - - -

Percent of oversize material wet 0 0 0 - - -

Peak Converted Wet Density t/m³ 1.97 1.98 2.02 - - -

Adjusted Peak Converted Wet Density t/m³ - - - - - -

Optimum Moisture Content % 17.5 17.0 15.0 - - -

Moisture Variation From 2.5% 2.0% 2.0% - - -

Optimum Moisture Content wet wet wet

Density Ratio ( R HD ) % 100.0 99.5 98.5 - - -

Material description

No 1 - 3 Clay Fill

Layer thickness

Standard

AVRLOT HILF V1.10 MAR 13

Page 4: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

COMPACTION ASSESSMENT

Job No 18453

CIVIL GEOTECHNICAL SERVICES Report No 18453/R002

6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018

Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB

Project SEVENTH BEND - STAGE 4 Date tested 07/08/18

Location MELTON SOUTH Checked by JHF

Feature EARTHWORKS 200 mm Time: 08:30

Test procedure AS 1289.2.1.1 & 5.8.1

Test No 4 5 6 - - -

Location

REFER REFER REFER

TO TO TO

FIGURE 1 FIGURE 1 FIGURE 1

Approximate depth below FSL

Measurement depth mm 175 175 175 - - -

Field wet density t/m³ 1.76 1.75 1.94 - - -

Field moisture content % 22.3 23.2 23.5 - - -

Test procedure AS 1289.5.7.1

Test No 4 5 6 - - -

Compactive effort

Oversize rock retained on sieve mm 19.0 19.0 19.0 - - -

Percent of oversize material wet 0 0 0 - - -

Peak Converted Wet Density t/m³ 1.78 1.77 1.92 - - -

Adjusted Peak Converted Wet Density t/m³ - - - - - -

Optimum Moisture Content % 21.5 21.0 21.5 - - -

Moisture Variation From 1.0% 2.5% 2.0% - - -

Optimum Moisture Content wet wet wet

Density Ratio ( R HD ) % 99.0 99.0 101.0 - - -

Material description

No 4 - 6 Clay Fill

Layer thickness

Standard

AVRLOT HILF V1.10 MAR 13

Page 5: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

COMPACTION ASSESSMENT

Job No 18453

CIVIL GEOTECHNICAL SERVICES Report No 18453/R003

6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018

Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB

Project SEVENTH BEND - STAGE 4 Date tested 08/08/18

Location MELTON SOUTH Checked by JHF

Feature EARTHWORKS 200 mm Time: 10:00

Test procedure AS 1289.2.1.1 & 5.8.1

Test No 7 8 9 10 11 12

Location

REFER REFER REFER REFER REFER REFER

TO TO TO TO TO TO

FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1

Approximate depth below FSL

Measurement depth mm 175 175 175 175 175 175

Field wet density t/m³ 1.84 1.88 1.84 2.02 1.96 1.98

Field moisture content % 20.3 17.8 20.2 19.2 21.0 16.9

Test procedure AS 1289.5.7.1

Test No 7 8 9 10 11 12

Compactive effort

Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 19.0 19.0

Percent of oversize material wet 0 0 0 0 0 0

Peak Converted Wet Density t/m³ 1.86 1.91 1.86 2.01 1.98 1.99

Adjusted Peak Converted Wet Density t/m³ - - - - - -

Optimum Moisture Content % 18.5 16.5 19.0 21.5 23.0 17.0

Moisture Variation From 2.0% 2.5% 2.0% 2.0% 2.0% 0.0%

Optimum Moisture Content wet wet wet dry dry

Density Ratio ( R HD ) % 99.0 98.5 99.0 101.0 99.0 99.0

Material description

No 7 - 12 Clay Fill

Layer thickness

Standard

AVRLOT HILF V1.10 MAR 13

Page 6: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

COMPACTION ASSESSMENT

Job No 18453

CIVIL GEOTECHNICAL SERVICES Report No 18453/R004

6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by BGG

Project SEVENTH BEND - STAGE 4 Date tested 09/08/18

Location MELTON SOUTH Checked by JHF

Feature EARTHWORKS 200 mm Time: 16:06

Test procedure AS 1289.2.1.1 & 5.8.1

Test No 13 14 15 16 17 18

Location

REFER REFER REFER REFER REFER REFER

TO TO TO TO TO TO

FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1

Approximate depth below FSL

Measurement depth mm 175 175 175 175 175 175

Field wet density t/m³ 1.93 1.80 1.81 1.79 1.94 1.92

Field moisture content % 23.0 20.8 21.5 23.4 24.6 20.5

Test procedure AS 1289.5.7.1

Test No 13 14 15 16 17 18

Compactive effort

Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 19.0 19.0

Percent of oversize material wet 0 0 0 0 0 0

Peak Converted Wet Density t/m³ 2.00 1.81 1.81 1.81 2.01 2.00

Adjusted Peak Converted Wet Density t/m³ - - - - - -

Optimum Moisture Content % 21.0 18.5 19.5 21.5 22.5 18.0

Moisture Variation From 2.0% 2.5% 2.0% 2.5% 2.0% 2.5%

Optimum Moisture Content wet wet wet wet wet wet

Density Ratio ( R HD ) % 96.5 100.0 100.0 99.0 96.5 96.0

Material description

No 13 - 18 Clay Fill

Layer thickness

Standard

AVRLOT HILF V1.10 MAR 13

Page 7: CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL SERVICES Report No 18453/R004 6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018

COMPACTION ASSESSMENT

Job No 18453

CIVIL GEOTECHNICAL SERVICES Report No 18453/R005

6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018

Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB

Project SEVENTH BEND - STAGE 4 Date tested 14/08/18

Location MELTON SOUTH Checked by JHF

Feature EARTHWORKS 200 mm Time: 09:00

Test procedure AS 1289.2.1.1 & 5.8.1

Test No 19 20 21 22 - -

Location

REFER REFER REFER REFER

TO TO TO TO

FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1

Approximate depth below FSL

Measurement depth mm 175 175 175 175 - -

Field wet density t/m³ 1.78 1.76 1.83 1.84 - -

Field moisture content % 29.5 27.6 29.0 26.4 - -

Test procedure AS 1289.5.7.1

Test No 19 20 21 22 - -

Compactive effort

Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 - -

Percent of oversize material wet 0 0 0 4 - -

Peak Converted Wet Density t/m³ 1.86 1.86 1.88 1.92 - -

Adjusted Peak Converted Wet Density t/m³ 1.87 - - 1.94 - -

Optimum Moisture Content % 30.0 28.5 29.5 26.5 - -

Moisture Variation From 0.5% 1.0% 0.5% 0.0% - -

Optimum Moisture Content dry dry dry

Density Ratio ( R HD ) % 95.5 95.0 97.5 95.0 - -

Material description

No 19 - 22 Clay Fill

Layer thickness

Standard

AVRLOT HILF V1.10 MAR 13