CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL...
Transcript of CIVIL GEOTECHNICAL SERVICES ABN 26 474 013 724 PO Box … · 2019-08-06 · CIVIL GEOTECHNICAL...
CIVIL GEOTECHNICAL SERVICES
ABN 26 474 013 724
PO Box 678 Croydon Vic 3136
Telephone: 9723 0744 Facsimile: 9723 0799
18453: NB268 August 2018
30th August 2018
Our Reference: 18453:NB268
Winslow Constructors Pty Ltd
50 Barry Road
CAMPBELLFIELD VIC 3061
Dear Sirs/Madams,
RE: LEVEL 1 EARTHWORKS INSPECTION AND TESTING
SEVENTH BEND – STAGE 4 (MELTON SOUTH)
Please find attached our Report No’s 18453/R001 – 18453/R005 which relate to the field
density testing that was conducted within the filled allotments at the above subdivision. The
level 1 inspections and associated field density testing was performed in August 2018.
The inspections and testing of the earthworks was undertaken in general accordance with the
Level 1 requirements of AS 3798 - Guidelines on Earthworks for Commercial and Residential
Developments.
The site inspection and testing was performed by experienced geotechnicians from this office.
Any areas that were deemed unsatisfactory were reworked and retested under their
supervision. The testing was performed to the relevant Australian Standards and the
accompanying test reports carry NATA endorsement. The attached compaction results, which
were located randomly throughout the fill profile, are considered to be representative of the
bulk fill materials that were placed across the reported allotments by Winslow Constructors
during the aforementioned period. The approximate locations of the field density tests can be
seen on the attached plan (Figure 1).
We are of the view that the bulk fill materials that have been placed across the reported
allotments by Winslow Constructors during the aforementioned period can be considered as
having been placed in a controlled manner to a minimum density ratio of 95% (standard
compactive effort).
Please contact the undersigned if you require any additional information.
Civil Geotechnical Services
Nick Brock
��������������� ������ ���������������������� ������������������ ���� � �!"#$%&'&() *$'+*,-*.-$ */0123/4*5��3.�67�510/487/�9/4 '7//6:)���;<=>?@�AB�C.DDE* *�6/ '��F/:G:.�D513�1H�F IJKLMNJOPQRSTUVTJWRXJYRZ.[):\]:�̂�:\]�:�\_-7/0/:4/01230:�34:45��1320:�5/67/:��H̀51276:�C:'a$8:.�065�F1�D6̀:b64�-7/:45��132:07�FF:3�6:c/5/H5�4��/4:�5:��H1/4d:13:�7�F/:�5H�56d:�167��6:67/:�5166/3:H/5�1001�3�C:'a$8:.�065�F1�:D6̀:b64�-7/:��36/360:�C:6710:45��132:�5//F/�65�31��FF̀:2/3/5�6/4d:�5/��3C14/361�F:�34:��̀:�3F̀:c/:�0/4C�5:67/:H�5H�0/:C�5:�71�7:67/̀:�5/136/34/4�.FF:0/66132:��6:07��F4:c/:��551/4:��613:����54�3�/:�167:e..+8��3�1FE006�34�54:45��1320:�5:�0:3��13�6/4�3:7�54:��H̀:HF�30:H5�f14/4:c̀'a$8�:.3̀:41216�F:13C�5��61�30�HHF1/4:c̀:6710:�CC1�/:10:C�513C�5��61�3:�3F̀�:.3̀:410�5/H�3�1/007��F4:c/:410��00/4:�167:67/0�H/5136/34/36� ��������gh�ib/f/F:��d:]�:j�//30:#��4d:a/Fc��53/:%&8:k��\l:m̂�:k:_��\:����::n::o:m̂�:k:_��\:��� :n::����0�/����� ,�5:8�3065��61�3Fpq��59q/32q ��/:r:/sC�54:5��4d:�/F6�3q ��/r�\q4�20:H4Cq ��/r�\r� a/Fc��53/:%&8:k��\b/f/F:�d:\̂t:'6:u1F4�:#��4.D*:D5�v/�60:D6̀:b64 w�3��5̀: ��])�x�FF��b�%1/̀5�'�'�67�01f��b�-�̀F�5 �p��� �_ �yyz�{�|{�yb�̀��6:DF�3:#��4��590:�34:*5�13�2/:a/F6�3:816̀:8��3�1F'6�2/:\}oA;~�A<~�h!��A?�FIGURE 1
# Approximate field density test location
1
2
3
4
5
6
789
10
11
12
13
1415
16
1718
1920
2122
COMPACTION ASSESSMENT
Job No 18453
CIVIL GEOTECHNICAL SERVICES Report No 18453/R001
6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018
Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB
Project SEVENTH BEND - STAGE 4 Date tested 06/08/18
Location MELTON SOUTH Checked by JHF
Feature EARTHWORKS 200 mm Time: 13:45
Test procedure AS 1289.2.1.1 & 5.8.1
Test No 1 2 3 - - -
Location
REFER REFER REFER
TO TO TO
FIGURE 1 FIGURE 1 FIGURE 1
Approximate depth below FSL
Measurement depth mm 175 175 175 - - -
Field wet density t/m³ 1.97 1.97 1.99 - - -
Field moisture content % 19.7 18.2 16.7 - - -
Test procedure AS 1289.5.7.1
Test No 1 2 3 - - -
Compactive effort
Oversize rock retained on sieve mm 19.0 19.0 19.0 - - -
Percent of oversize material wet 0 0 0 - - -
Peak Converted Wet Density t/m³ 1.97 1.98 2.02 - - -
Adjusted Peak Converted Wet Density t/m³ - - - - - -
Optimum Moisture Content % 17.5 17.0 15.0 - - -
Moisture Variation From 2.5% 2.0% 2.0% - - -
Optimum Moisture Content wet wet wet
Density Ratio ( R HD ) % 100.0 99.5 98.5 - - -
Material description
No 1 - 3 Clay Fill
Layer thickness
Standard
AVRLOT HILF V1.10 MAR 13
COMPACTION ASSESSMENT
Job No 18453
CIVIL GEOTECHNICAL SERVICES Report No 18453/R002
6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018
Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB
Project SEVENTH BEND - STAGE 4 Date tested 07/08/18
Location MELTON SOUTH Checked by JHF
Feature EARTHWORKS 200 mm Time: 08:30
Test procedure AS 1289.2.1.1 & 5.8.1
Test No 4 5 6 - - -
Location
REFER REFER REFER
TO TO TO
FIGURE 1 FIGURE 1 FIGURE 1
Approximate depth below FSL
Measurement depth mm 175 175 175 - - -
Field wet density t/m³ 1.76 1.75 1.94 - - -
Field moisture content % 22.3 23.2 23.5 - - -
Test procedure AS 1289.5.7.1
Test No 4 5 6 - - -
Compactive effort
Oversize rock retained on sieve mm 19.0 19.0 19.0 - - -
Percent of oversize material wet 0 0 0 - - -
Peak Converted Wet Density t/m³ 1.78 1.77 1.92 - - -
Adjusted Peak Converted Wet Density t/m³ - - - - - -
Optimum Moisture Content % 21.5 21.0 21.5 - - -
Moisture Variation From 1.0% 2.5% 2.0% - - -
Optimum Moisture Content wet wet wet
Density Ratio ( R HD ) % 99.0 99.0 101.0 - - -
Material description
No 4 - 6 Clay Fill
Layer thickness
Standard
AVRLOT HILF V1.10 MAR 13
COMPACTION ASSESSMENT
Job No 18453
CIVIL GEOTECHNICAL SERVICES Report No 18453/R003
6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018
Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB
Project SEVENTH BEND - STAGE 4 Date tested 08/08/18
Location MELTON SOUTH Checked by JHF
Feature EARTHWORKS 200 mm Time: 10:00
Test procedure AS 1289.2.1.1 & 5.8.1
Test No 7 8 9 10 11 12
Location
REFER REFER REFER REFER REFER REFER
TO TO TO TO TO TO
FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1
Approximate depth below FSL
Measurement depth mm 175 175 175 175 175 175
Field wet density t/m³ 1.84 1.88 1.84 2.02 1.96 1.98
Field moisture content % 20.3 17.8 20.2 19.2 21.0 16.9
Test procedure AS 1289.5.7.1
Test No 7 8 9 10 11 12
Compactive effort
Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 19.0 19.0
Percent of oversize material wet 0 0 0 0 0 0
Peak Converted Wet Density t/m³ 1.86 1.91 1.86 2.01 1.98 1.99
Adjusted Peak Converted Wet Density t/m³ - - - - - -
Optimum Moisture Content % 18.5 16.5 19.0 21.5 23.0 17.0
Moisture Variation From 2.0% 2.5% 2.0% 2.0% 2.0% 0.0%
Optimum Moisture Content wet wet wet dry dry
Density Ratio ( R HD ) % 99.0 98.5 99.0 101.0 99.0 99.0
Material description
No 7 - 12 Clay Fill
Layer thickness
Standard
AVRLOT HILF V1.10 MAR 13
COMPACTION ASSESSMENT
Job No 18453
CIVIL GEOTECHNICAL SERVICES Report No 18453/R004
6 - 8 Rose Avenue, Croydon 3136 Date Issued 17/08/2018
Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by BGG
Project SEVENTH BEND - STAGE 4 Date tested 09/08/18
Location MELTON SOUTH Checked by JHF
Feature EARTHWORKS 200 mm Time: 16:06
Test procedure AS 1289.2.1.1 & 5.8.1
Test No 13 14 15 16 17 18
Location
REFER REFER REFER REFER REFER REFER
TO TO TO TO TO TO
FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1
Approximate depth below FSL
Measurement depth mm 175 175 175 175 175 175
Field wet density t/m³ 1.93 1.80 1.81 1.79 1.94 1.92
Field moisture content % 23.0 20.8 21.5 23.4 24.6 20.5
Test procedure AS 1289.5.7.1
Test No 13 14 15 16 17 18
Compactive effort
Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 19.0 19.0
Percent of oversize material wet 0 0 0 0 0 0
Peak Converted Wet Density t/m³ 2.00 1.81 1.81 1.81 2.01 2.00
Adjusted Peak Converted Wet Density t/m³ - - - - - -
Optimum Moisture Content % 21.0 18.5 19.5 21.5 22.5 18.0
Moisture Variation From 2.0% 2.5% 2.0% 2.5% 2.0% 2.5%
Optimum Moisture Content wet wet wet wet wet wet
Density Ratio ( R HD ) % 96.5 100.0 100.0 99.0 96.5 96.0
Material description
No 13 - 18 Clay Fill
Layer thickness
Standard
AVRLOT HILF V1.10 MAR 13
COMPACTION ASSESSMENT
Job No 18453
CIVIL GEOTECHNICAL SERVICES Report No 18453/R005
6 - 8 Rose Avenue, Croydon 3136 Date Issued 28/08/2018
Client WINSLOW CONSTRUCTORS PTY LTD (CAMPBELLFIELD) Tested by SB
Project SEVENTH BEND - STAGE 4 Date tested 14/08/18
Location MELTON SOUTH Checked by JHF
Feature EARTHWORKS 200 mm Time: 09:00
Test procedure AS 1289.2.1.1 & 5.8.1
Test No 19 20 21 22 - -
Location
REFER REFER REFER REFER
TO TO TO TO
FIGURE 1 FIGURE 1 FIGURE 1 FIGURE 1
Approximate depth below FSL
Measurement depth mm 175 175 175 175 - -
Field wet density t/m³ 1.78 1.76 1.83 1.84 - -
Field moisture content % 29.5 27.6 29.0 26.4 - -
Test procedure AS 1289.5.7.1
Test No 19 20 21 22 - -
Compactive effort
Oversize rock retained on sieve mm 19.0 19.0 19.0 19.0 - -
Percent of oversize material wet 0 0 0 4 - -
Peak Converted Wet Density t/m³ 1.86 1.86 1.88 1.92 - -
Adjusted Peak Converted Wet Density t/m³ 1.87 - - 1.94 - -
Optimum Moisture Content % 30.0 28.5 29.5 26.5 - -
Moisture Variation From 0.5% 1.0% 0.5% 0.0% - -
Optimum Moisture Content dry dry dry
Density Ratio ( R HD ) % 95.5 95.0 97.5 95.0 - -
Material description
No 19 - 22 Clay Fill
Layer thickness
Standard
AVRLOT HILF V1.10 MAR 13