Professional Work Orders (Work Package):
HIMS Mandatory Form
Rachel Broome
HIMS Frontpage
Project Mangers Workbook
• CMS >>
• HIMS >>
• Project Manager’s HIMS Workbook Import >>
• Select Region >>
• Enter Agresso code >>
• Save!
Project Managers Workbook
• Access from CMS
• Automatically populates fields
• Keeps all management plan documents together
Forms List
• PWO link
Example PWO
Tasks and Budget
Verification Requirements
PWO Issue & Acceptence
• A PWO is a contract between PM who wants something and WPM who agrees to deliver in accordance with budget, timing and deliverables identified on PWO
• Signing confirms agreement
Summary
• A PWO is a contract between PM and WPM
• It needs to be accepted
– Signed and Dated
– Hardcopy in 71 file
• Access via PM’s workbook
• In case of scope change we should get a new PWO
– For better change control / VO mgmt with clients
• PWO’s need monitoring by WPM