CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box...
Transcript of CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box...
![Page 1: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/1.jpg)
CityLink Tulla Widening
– Bulla Road to Power Street
Dr. Kabir Patoary | Principal Engineer – Bridges | GHD
![Page 2: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/2.jpg)
Presentation Title
Introduction | Presentation outline
• Project Background
• New bridges:– Bulla Road southbound entry ramp over the Collector Distributor
– Pascoe Vale Road over Western Link
– Mt Alexander Road over Moonee Ponds Creek
• Widening or modification of existing bridges:– Bulla Road Bridge North Abutment Modification (Separate Paper)
– Western Link over Pascoe Vale Road
– Moonee Ponds Creek Bridges 1,2,4 and 6 (Separate Paper)
– Citylink southbound ramp to power street and Burnley tunnel (Ramp Z)
– West Gate Freeway eastbound elevated structure
• Conclusions
![Page 3: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/3.jpg)
Presentation Title
Introduction | Project BackgroundAirport
Burnley/Domain
Tunnels
Bell
Street
Bulla Rd to Power
St (CTW Section)
Pascoe
Vale
Road
New
Bell
Street
Bridge
• 2 packages of work
– Melbourne Airport to Bulla Road
• Funded by Federal and State Government
• Delivered by VicRoads
• Approx. length of 8 kM
– Bulla Road to Power Street (CTW - this project)
• Funded and delivered by Transurban
• Approx. length of 16 kM
• One extra lane in each direction
• Contract Awarded May 2015
• Expected Completion by end 2017
• Total capital cost ~$1.28 billion for both packages
![Page 4: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/4.jpg)
Presentation Title
Introduction | Project Background
• Client Transurban
• Contractor CPB – Design &Construct Partner
• Main Consultants Aurecon-GHD Joint Venture (AGJV)
• Other Consultants Doulgas Partners (geotechnical)
SLR (Noise Modelling)
KBR (Proof Engineering)
PowerPlant (Lighting Design)
Hassel (Urban and Architectural)
Visionstream (ITS)
Davis Langdon & AECOM (IR)
![Page 5: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/5.jpg)
Presentation Title
Introduction | Project Background
Total 36 Design Packages, over 4000 Structural Drawings
• 3 New Bridges (total 400 m length)
• 10 Existing Bridge Widening (total 1800 m length)
• 7 Gantry Packages (70 New, 30 Existing)
• 3 Noise Wall Packages (40 Noise Walls)
• 5 Retaining Wall Packages (10 Retaining Walls)
• 7 Pier protection Packages (17 Pier Protection)
• 1 Existing Bridge Strengthening package
![Page 6: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/6.jpg)
Presentation Title
Introduction | Project Background
➢ Large Number of Design Packages
➢ True Brown Field Site
➢ Coordination/Integration between three design offices
and four verification offices
➢ Semi-Alliance Environment for D&C
➢ Very tight delivery timeline & Penalty
➢ Stakeholders & IR Approval
Major Design Challenges
![Page 7: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/7.jpg)
Presentation Title
New Bridges | Bulla Road southbound entry ramp
![Page 8: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/8.jpg)
Presentation Title
New Bridges | Bulla Road southbound entry ramp
![Page 9: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/9.jpg)
Presentation Title
➢ Existing ground profile require one abutment to be top down with Soil
Nail and another bottom up construction with RE Wall
➢ High bridge skew requiring an in-situ diaphragm at abutment
➢ Construction staging including limited access for crane positioning.
➢ Heavy beams due to high skew and long span resulting in onerous
crane requirements.
Major Design Constraints
New Bridges | Bulla Road southbound entry ramp
![Page 10: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/10.jpg)
Presentation Title
New Bridges | Bulla Road southbound entry ramp
![Page 11: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/11.jpg)
Presentation Title
Design Details-Girder End
New Bridges | Bulla Road southbound entry ramp
![Page 12: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/12.jpg)
Presentation Title
Design Details-Approach Slab
New Bridges | Bulla Road southbound entry ramp
![Page 13: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/13.jpg)
Presentation Title
New Bridges | Pascoe vale Rd Bridge over Western Link
• Also Called Bell Street Interchange
• Existing Bridge → 1 lane for Tullamarine Fwy on Ramp and 1 for
Pascoe Vale Rd bound traffic
• New bridge → Connecting Bell St to Pascoe Vale Rd traffic
– Free up an additional lane on existing bridge
– Eliminate dangerous left hand merging
![Page 14: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/14.jpg)
Presentation Title
New Bridges | Pascoe vale Rd Bridge over Western Link
• Complex site requiring the bridge to span over:
– Entire CityLink carriageway (11 lanes)
– Existing Pascoe Vale Rd exit ramp bridge
– Moonee Ponds Creek channel
– Craigieburn Railway line ( 2 tracks)
– Close proximity to Strathmore Secondary College
![Page 15: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/15.jpg)
Presentation Title
• 269m long structure with maximum span of 62m
– Spans 1 to 4 → Continuous steel box girders
– Spans 5 to 6 → Simply supported Super-T girders
– Piers skewed up to 29 degrees to suit site geometry
– Curve radius of up to 165m
Span Arrangement
SPAN 1
(45m)SPAN 2
(62m)
SPAN 3
(61.5m)
SPAN 4
(45m)
SPAN 5
(23.9m)SPAN 6
(32m)
EJ EJEJ
Abut. B
Abut. A
New Bridges | Pascoe vale Rd Bridge over Western Link
![Page 16: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/16.jpg)
Presentation Title
Superstructure
New Bridges | Pascoe vale Rd Bridge over Western Link
![Page 17: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/17.jpg)
Presentation Title
Substructure
Abutment B
Abutment A
Transition Pier
Steel Box Pier
New Bridges | Pascoe vale Rd Bridge over Western Link
![Page 18: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/18.jpg)
Presentation Title
• 3D “spine” grillage deck model using Spacegass
• Steel box modelled as single beam elements
• Rigid outriggers pinned to webs
• Response spectrum analysis for earthquake design due to complex
geometry
3D Spacegass Grillage Model
New Bridges | Pascoe vale Rd Bridge over Western Link
Analysis and Design
![Page 19: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/19.jpg)
Presentation Title
• Local steel Finite Element Models in MIDAS Civil
• Skew diaphragms beyond “hand calculation” in AS5100.6
Local MIDAS Civil FE Plate Model for Diaphragms
New Bridges | Pascoe vale Rd Bridge over Western Link
Analysis and Design
![Page 20: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/20.jpg)
Presentation Title
Construction Challenges
• Complex site required close co-ordination between
design and construction teams:
– Construction sequence
– Crane positioning in constrained site critical
• Steel splice locations
• Maximum lifting weights
– Temporary towers
– All major girder lifts to be completed under night
road and rail closures
Credit: VicRoads
New Bridges | Pascoe vale Rd Bridge over Western Link
![Page 21: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/21.jpg)
Presentation Title
New Bridges | Mt Alexander Road over Moonee Ponds Creek
Major Constraints
• Close proximity to the existing bridge
• Requires partial removal of the
existing north east approach
embankment
• New bridge piers/columns are to line
up with existing
• Soffit level to be no lower than
existing
• Pedestrian Path under below 1 in 10
ARI
NEW BRIDGE LOCATION
![Page 22: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/22.jpg)
Presentation Title
New Bridges | Mt Alexander Road over Moonee Ponds Creek
![Page 23: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/23.jpg)
Presentation Title
New Bridges | Mt Alexander Road over Moonee Ponds Creek
![Page 24: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/24.jpg)
Presentation Title
Existing Bridges Widening| Western Link Bridge over Pascoe Vale Road
![Page 25: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/25.jpg)
Presentation Title
Existing Bridges Widening| Western Link Bridge over Pascoe Vale Road
•Live running traffic on CityLink north and southbound lanes
•The existing noise wall is also to be retained during construction
•Depth of structure to achieve existing clearance to Pascoe Vale Rd.
•Pier strengthening works require
•Existing underground utilities in close proximity to or running below new substructure
•Driven piles will require pre boring to minimise vibration effects on gas main
![Page 26: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/26.jpg)
Presentation Title
Existing Bridges Widening| Western Link Bridge over Pascoe Vale Road
![Page 27: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/27.jpg)
Presentation Title
Existing Bridges Widening| Western Link Bridge over Pascoe Vale Road
• Deck Cast in 2 stage
• Partial Road Closure
• Limit of Deflection and Vibration during deck casting
• High strength Low shrink low slump concrete for stitch
![Page 28: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/28.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Ramp Z
![Page 29: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/29.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
N
Abutment
Pier 9
Pier 10
Span 1
Span 2
Pier1B
Image: Google Earth
• Existing ramp constructed in 2009/2010
• 420 m of elevated structure in 14 spans
• Existing Pier 9 Crosshead spans over West Gate Freeway
![Page 30: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/30.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
N
Abutment
Pier 9
Pier 10
Span 1
Span 2
Pier1B
Image: Google Earth
• Existing Span 1 and 2 are 42m long 2.3m deep composite steel I-Girders,
connected to existing CityLink segmental concrete box girders
• Existing Span 3 to 14 Super-T beams are 26-32m long
![Page 31: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/31.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Challenges - Span 1 Widening
• Risk of additional load transferred to Ramp L due to
Span 1 widening
• No reserved capacity for Ramp L
• Avoid deck strengthening due to location of first pier
Existing Welded
Connection
Existing
Deck
![Page 32: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/32.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Solution - Span 1 Widening
Span 1 Plan Span 1 Elevation
• Pier location selected to maintain an optimized stiffness of girder
• Flexible enough to allow deflection of deck at start of widening and hence no
need for deck strengthening
• Stiff enough to eliminate additional load transfer to Ramp L
• Girder extended under the existing deck, made non-composite for 25% of its
length
• Pier1B located under existing deck at 1/3 span
![Page 33: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/33.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Challenges - Span 2 Widening
• Two steel I-girders connected to the existing
• Kinked in plan to suit the curved geometry
• Excessive twist of girders under girder and deck SW
• Unbalanced reactions of girders
Span 2 FE Model - Twisted Girders
(SAP2000)
![Page 34: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/34.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Solution - Span 2 Widening
• Both girders are required to be assemble together on site
• Torsional restraint provided by pair of cross bracings at the ‘kinked’ points
• Supported on a temporary tower at mid-span till composite action achieved
• Minimized the amount of permanent twist
Span 2 Plan
![Page 35: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/35.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Challenges – Pier 9 Crosshead
• Existing crosshead is a precast post-tensioned beam
• Existing Super-T beams are supported on a concrete corbel
• Crosshead was not designed for future widening
• Assessment showed that crosshead suspension reinforcement is not
adequate for the new beam loads
• Anchoring into crosshead was also impossible due to presence of
post-tensioning
• Extending existing concrete corbel was not a solution
Existing Post-
Tensioning ProfileExisting concrete
corbel
![Page 36: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/36.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Design Solution – Pier 9 Crosshead
• Steel fabricated saddle with 100mm thick top plates
• Transfer loads from bearings to top of crosshead
• All components checked for fatigue
• Simple structural form and ease of installation achieved
Side View
Pier 9 Saddle
![Page 37: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/37.jpg)
Presentation Title
Existing Bridges Widening| Ramp Z-Southbound Ramp Bolte to Power St.
Pier 10 Crosshead
Design Challenges Design Solution
• Limited structural depth available
• Casting crosshead over live traffic
• Possible West Gate Freeway traffic
disruption
Existing
Pier 10
Independent
new column
• Independent new concrete column
• Two fabricated steel I-girders cantilever
over the West Gate Freeway
• Crosshead held to the top of the new
column by cast-in stress bars
• Shallow structural depth achieved
• Easy installation
![Page 38: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/38.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• Total length of widening 1010 m
• Total 24 span. Span length varies from 31 m to 56 m
• Existing structure is constructed in the mid 1980’s
• Existing structure is continuous up to 300 m
• Segmental Box Girder balanced cantilever construction.
• Widening width varies from 0 to 3.5 m
![Page 39: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/39.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• The widening work is to be constructed adjacent to live traffic
• The widening work crosses a number of existing access roads and tram routes
• Existing 3.8 m x 3.8 m Melbourne Water storm water drain close to pier.
• Low piling headroom under existing Deck
• Piling adjacent and close proximity to existing Westgate Elevated Structure
substructures
Design Constraints
![Page 40: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/40.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• For Widening up to 0.8 m
Design Solutions - Superstructure
![Page 41: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/41.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• For Widening up from 0.8 m to 2.4 m
Design Solutions - Superstructure
![Page 42: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/42.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• For Widening up from 2.4 m to 3.2 m
Design Solutions - Superstructure
![Page 43: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/43.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
• Transition from I Girder to Box Girder
Design Solutions - Superstructure
![Page 44: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/44.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
Design Solutions - Substructure
![Page 45: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/45.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
Design Solutions - Substructure
![Page 46: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/46.jpg)
Presentation Title
Existing Bridges Widening| Westgate Freeway Eastbound Elevated Structure
Design Solutions - Articulation
![Page 47: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/47.jpg)
Presentation Title
Conclusions
• An excellent example of fitting new works within a busy existing
road corridor
• Design decisions were heavily influenced by the need to
accommodate the existing traffic and associated highway works,
and to suit construction staging under operating live traffic
• Major bridgeworks successfully completed and Road open for
traffic months ahead
• Close co-ordination with design and construction teams was
critical for successful completion
![Page 48: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/48.jpg)
Presentation Title
Acknowledgments and Questions
• Acknowledgments
− CPB Contractors
− Transurban
− VicRoads
− Douglas Partners
− Hassell
• Thank you for listening
![Page 49: CityLink Tulla Widening Bulla Road to Power Street · –Spans 1 to 4 → Continuous steel box girders ... • 3D “spine” grillage deck model using Spacegass • Steel box modelled](https://reader030.fdocuments.in/reader030/viewer/2022040919/5e9588f943646f7e7a084812/html5/thumbnails/49.jpg)
Presentation Title
www.ghd.com
citylinktullawidening.vic.gov.au