City Region Development Project · The City Region Development Project (CRDP) is under...
Transcript of City Region Development Project · The City Region Development Project (CRDP) is under...
Involuntary Resettlement Due Diligence Report June 2014
BAN: City Region Development Project (CRDP) -
Road & Drainage Subproject, Mongla Port
Pourashava
Prepared by Local Government Engineering Department (LGED) for the People’s Republic of
Bangladesh and the Asian Development Bank.
CURRENCY EQUIVALENTS (as of 15 June 2014)
Currency unit – taka (Tk)
Tk1.00 = $0.0129 $1.00 = Tk77.7695
NOTES
(i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2014 ends on June 2014.
(ii) In this report, "$" refers to US dollars. This Involuntary Resettlement Due Diligence Report monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 1
Government of the People’s Republic of Bangladesh Ministry of Local Government, Rural Development and Co-operatives
Local Government Division Local Government Engineering Department (LGED)
City Region Development Project (CRDP) ADB Loan No. 2695-BAN
INVOLUNTARY RESETTLEMENT
DUE DILIGENCE REPORT
For
Road & Drainage Subproject, Mongla Port
Pourashava
Package No: CRDP/LGED/MONGLA/NCB/2013/W-01
& CRDP/LGED/MONGLA/NCB/2014/W-02
PIU: MONGLA PORT POURASHAVA
June 2014
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 2
Table of Contents
I. INTRODUCTION II. PROJECT BACKGROUND AND DESCRIPTION III. STUDY METHODOLOGY IV. SUBPROJECT DESCRIPTION V. IMPACT AND OUTCOME OF THE SUBPROJECT VI. SUBPROJECT BENEFITS VII. SOCIAL IMPACT ASSESSMENT FOR THE SUBPROJECT
General
Land Acquisition & Resettlement
VIII. MITIGATION OF SOCIAL CONCERNS IX. COMMUNITY CONSULTATION X. GRIEVANCE REDRESS MECHANISM XI. CONCLUSION
Tables:
Table-1: Road & Drainage Improvement Components Table-2: List of Consultations/Meetings at different locations of the subproject under
Mongla Port Pourashva
Figure 1: Mongla Port Pourashva Road and Drainage Layout
Annexure:
Annexure-1: Involuntary Resettlement (IR) Impacts Checklist by Schemes of the Road and Drainage subproject under Mongla Port Pourashva.
Annexure-2: List of Participants in Consultations Meetings
Annexure-3: Draft Project Information leaflet on Social Safeguard Issues.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 3
Abbreviations:
ADB : Asian Development Bank AP : Affected Person BWDB : Bangladesh Water Development Board CRDP : City Region Development Project DDR : Due Diligence Report DP : Displaced Person DPD : Deputy Project Director GOB : Government of Bangladesh GRC : Grievance Redress Committee GRM : Grievance Redress Mechanism IA : Implementing Agency IR : Involuntary Resettlement KfW : Kreditanstalt für Wiederaufbau LA : Land Acquisition LA&R : Land Acquisition and Resettlement LGED : Local Government Engineering Department LGRD & C : Local Government Rural Development & Cooperatives MCD : Municipal Capacity Development (MCD) Consultants MDS : Management Design & Supervision MPR : Monthly Progress Report M&E : Monitoring & Evaluation PD : Project Director PMCU : Project Management and Coordination Unit PIU : Project Implementation Unit PPTA : Project Preparatory Technical Assistance QPR : Quarterly Progress Report RAJUK : Rajdhani Unnyan Katripakha (Capital Development Authority) RCC : Reinforcement Cement Concrete R&R : Resettlement and Rehabilitation RF : Resettlement Framework RP : Resettlement Plan SES : Socio-economic Survey SPS : Safeguard Policy Statements TOR : Terms of Reference XEN : Executive Engineer
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 4
I. INTRODUCTION 1. The Mongla Port Pourashava Subproject comprises roads, drains, regulators/sluice gates
and re-excavation of canals selected under the CRDP is the outcome of the feasibility study
conducted during implementation by the MDSC & PMCU. Under feasibility study, a preliminary
Social Safeguard Impact Assessment (SSIA) was conducted comprising a long list of proposed
schemes. At this stage of project implementation, PMCU Social safeguard Team conducted
resettlement & social impact assessments in detail on the 15 design completed & under
implementation schemes comprising construction/improvement of main roads with number of
link roads, drains, culverts & regulators, re-excavation of canals etc. This impact assessment for
the design completed schemes under the subproject was done conducting a thorough
investigation of different social safeguard issues visiting each of the schemes following the
final detail engineering design prepared by MDS Consultant to fulfill the requirements of ADB’s
Involuntary Resettlement and Safeguard Policy Statement (SPS, 2009). The major objective of
the above study / investigations was to assess and identify all the possible socioeconomic
and resettlement impacts with necessary mitigation measures of different concerns. This report
has been prepared only for the design completed schemes based on the aforesaid study
findings, which will be updated subsequently incorporating the remaining schemes after
completion of final detail design by the MDSC. The subproject covers
construction/improvement/re-excavation of numbers of roads, canals including regulators
selected within the Mongla Port Pourashava to facilitate proper communication/transportation
& improve drainage facilities for the people of subproject area. Implementation of these
schemes under the subproject also are expecting to provide required drainage facilitates & flood
management to residents of the Pourashava. Moreover, construction and re-excavation of
regulators and canals also will restrict intrusion of saline water during high tide and resolve
frequent water stagnation problem within the Pourashava areas. However, during investigations,
it was revealed that the schemes selected and already completed detail design for
implementation will be constructed /improved respectively on the existing road & canal alignments
& drains along the road shoulders without affecting any structures. Moreover, due to
construction/improvement of the aforesaid schemes under the subproject are not expecting to
have neither any physical nor any economic displacement of any people. As a result, there is no
possibility of new land acquisition and no structure affected & none found to require relocation,
consequently no resettlement impacts are anticipating. Under the circumstances, this report may
be treated as a due diligence report (DDR) with respect to social safeguard issues for the
concerned subproject.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 5
II. PROJECT BACKGROUND AND DESCRIPTON
2. The City Region Development Project (CRDP) is under implementation by the
Government of Bangladesh financed by ADB include KfW and SIDA as co-financiers. The
project has been initiated for development of different infrastructure facilities under the project
area for the city dwellers to improve the existing condition. Under the current program, the
CRDP is operating its activities covering Dhaka and Khulna cities and suburbs. The Project
aims at enhancing growth potential and improving environmental sustainability of the targeted
city regions through effective regional urban planning. The Project is supporting development of
key urban infrastructure, focusing on urban environment and local economic development
through strengthening municipal management and capacity for effective and sustainable urban
development.
3. This CRDP project has been formulated as a sector loan and is currently under
implementation since 2011 covering a period of 6-years. The sub-projects under the CRDP is
being selected & implementing are expected to enhance economic activities in the regional
context and to provide opportunities for investment, including: (i) comprehensive urban
renewal and economic revitalization; (ii) transport infrastructure upgrading, public transport,
traffic management; (iii) water supply and sanitation; (iv) solid waste management; (v) energy
conservation and efficiency for governance and the private-sector; and (vi) strengthening
local governance and municipal funding. The project comprises of three components. These
are:
I. Development of Urban Infrastructures; II. Improvement of Urban Planning; and III. Strengthening of Municipal Management and Capacity
4. Asian Development Bank (ADB) approved the Loan 2695-BAN for City Region
Development Project (CRDP, the Project) on 10 November 2010. The Government of
Bangladesh (the Government) approved the Development Project Proposal (DPP) for the
Project on 2nd. August 2011. The Loan Agreement of CRDP was signed on 10th. August 2011
and became effective on 23rd. September 2011. The CRDP is co-financed by German Financial
Cooperation through KfW with a grant of EUR 10.5 million (about $14.855 million) allocated for
climate change adapted urban development in Khulna. The CRDP is also co-financed by the
Swedish International Development Authority (SIDA )with a grant of SEK 90.0 million (about
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 6
$13.0 million) administered by ADB for urban center infrastructure and governance
improvements. Local Government Engineering Department (LGED) is the lead executing
agency of the Project. Different identified subprojects and new subprojects selected under the
project are implementing/will be implemented by a number of Implementing Agencies (IAs),
such as: Dhaka City Corporation (DCC), Khulna City Corporation (KCC), RAJUK, LGED, DPHE
and respective Pourashavas under the project.
III. STUDY METHODOLOGY
5. The social Safeguard Consultants team visited selected & design completed scheme sites
under the Subproject at Mongla Port Pourashava in April 2014. The main purpose of the field trip
was to conduct a detail assessment/ study for the selected subproject covering different
resettlement and social safeguard issues likely to occur due to the construction & improvement of
the selected schemes. In course of study, consultants had discussions and sharing of ideas with
Mayor, councilors & Executive Engineer of Mongla Port Pourashava at their office along with other
concerned engineers and staff. During discussions, the consultants briefed them about the
objectives and the purpose of the visit and informed them about the planned site visit and different
activities to be carried out along the alignments of the selected subproject/scheme sites. The
consultants also had a number of consultations with the local people and beneficiaries at different
locations of the subproject. During site visit, Assistant Engineer, councilors along with other
concerned engineers and staff of Mongla Port Pourashava accompanied the consultant’s team to
assist them and also to identify the locations and alignments of different schemes. In accordance
with the objective of the field visit, the consultants visited all along the road & drain alignments
and investigated about the resettlement and social safeguard issues if any, likely to occur for the
selected schemes under the sub-project using an IR impact assessment checklist.
IV. SUBPROJECT DESCRIPTION
6. Mongla Port Pourashava is one of the Local Government Administrative units located in
southwestern part of Bangladesh about 45 km south of Khulna City. The Pourashava area is
divided by the river Pashur into two parts. Most of the Pourashava area comprising 8 Wards
located on the south bank of river Pasur and only one ( Ward no.-4) out of nine Wards of the
pourashava situated on the north bank of the river Pasur covering the Mongla port area. The
Mongla Port is renowned as the second important sea port of Bangladesh. There are many large
and medium industries also are located in and around centering port and Mongla Port Pourashava
includes export processing zone (EPZ) with number of different industries. Day by day importance
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 7
of Mongla Port is increasing considering its contribution to national economy and also due to
development of different economic activities consequences to increase in population significantly.
To cope with the demand of increasing population within the pourashava, rapid development of
different civic facilities includes roads, drainages etc. for the city dwellers now becomes inevitable.
Under the circumstances, this subproject has been proposed comprising different infrastructure
development under different components. The subproject components aim is to upgrade and
expand the urban services, including (i) main road of the town with number of connecting internal
service roads including side drain located in different wards of the pourashava; (ii) one Poshur
River front road on the existing embankment; (iii) one Truck terminal at port area; (iv) three
regulators/ sluice gate and (v) three canals re-excavation for drainage and flood management
schemes. The proposals are concerned with activities which address the most acute needs for
better urban services and facilities to inhabitants of the town/pourashava. The details of the design
completed schemes under the sub-project are shown in Table-1 & a subproject location map in
figure-1 below.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 8
Table-1: List of design completed road, drain, regulator and canal re-excavation schemes for improvement
Package No.
Lot Name of Schemes Length
(km) Proposed development activities Remarks
CR
DP
/LG
ED
/MO
NG
LA
/NC
B/2
01
3/W
-01
CR
DP
/LG
ED
/MO
NG
LA
/NC
B/
20
13
/W-0
1/R
D-1
Improvement of Sheik Abdul Hai road & Abdul Majid road with six link roads from Alamgir store to Zia Sarak.
2.435 Road improvement & construction on the
available Existing road alignment
Design completed
2 Vent Box Culvert on Sheik Abdul Hai road & Abdul Majid road
2X4mX3.6mX5.4m
Culvert construction on the available
Existing road alignment
Design completed
Improvement/construction of of side drain and footpath along Sheik Abdul Hai road & Abdul Majid road with six link roads from Alamgir store to Zia Sarak.
3.314
Improvement/construction of drain along the existing road shoulder
Design completed
CR
DP
/LG
ED
/MO
NG
LA
/NC
B/2
01
3/W
-01
/RD
-2
Improvement of GC Road for new main road, Sromick Sangha road, Giashuddin road, Abdul Hai road (part), Kabostan roadwith one link road
1.416
Road improvement & construction on the available Existing road alignment
Design completed
Construction/Improvement of side drain and footpath along GC Road for new main road, Sromick Sangha road, Giashuddin road, Abdul Hai road (part), Kabostan road with one link road
1.638
Improvement/construction of drain along the existing road shoulder
Design completed
Improvement of GC road for Madrasha road from Sk. Abdul Hai road to Kamarkhali bridge
1.353 Road improvement & construction on the
available Existing road alignment
Design completed
Construction/Improvement of side drain and footpath along Sk. Abdul Hai road to Kamarkhali bridge
2.388 Improvement/construction of drain along
the existing road shoulder
Design completed
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 9
Package No.
Lot Name of Schemes Length
(km) Proposed development activities Remarks
Improvement of GC road for Hazi Baharuddin road from Madrasha road to Bhasani road with one box culvert at link road-2
1.060
Road improvement & construction on the available Existing road alignment
Design completed
2 Vent Box Culvert on CC road for Hazi Baharuddin road from Madrasha road to Vashani road
2X4mX3.6mX4m
Culvert construction on the available
Existing road alignment
Design completed
CR
DP
/LG
ED
/MO
NG
LA
/NC
B/2
01
4/W
-02
Regulator-1 Construction of Regulator at starting point of Kumarkhali Khal
2 Vent Construction of regulator on the existing canal
Design completed
Regulator-2 Construction of Regulator at starting point of Thakrun Bari Khal
2 Vent Construction of regulator on the existing canal
Design completed
Regulator-3 Construction of Regulator at Kainmari Khal
3 Vent Construction of regulator on the existing canal
Design completed
Canal-1 Re-excavation of Kumarkhali Khal
0.850 Re-excavation on the existing canal Design completed
Canal-2 Re-excavation of Thakrun Bari Khal
1.250 Re-excavation on the existing canal Design completed
Canal-3 Re-excavation of Kewratola Khal
1.000 Re-excavation on the existing canal Design completed
Road-2 Improvement of CC road for Madrasha road from Shik Abdul Hai road to Kumarkhali Bridge
0.100 Road improvement & construction on the available Existing road alignment
Design completed
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 10
Figure 1: Mongla Port Pourashava Road and Drainage Layout
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 11
V. IMPACT AND OUTCOME OF THE SUBPROJECT
7. The subproject covers improvement and construction of roads, drain, regulator and canal
re-excavation to extend facilities for the urban dwellers in the subproject location and will bring
direct benefit to the inhabitants of the Pourashava area. The schemes undertaken for
construction/improvement under the program will improve transport facilities & increase the
capacity of receding waste water from industries, households, commercial premises etc. with
restriction of saline water intrusion in the pourashava area during high tide The subproject is
expected to increase area coverage of drainage and will guarantee health condition & will
reduce transport cost of goods and services including travelling cost of the residents of town.
The outcome of the subproject is improved transport & drainage system within the Pourashava
area and also will prevent water logging problem & unexpected flood during high tide &
monsoon. Construction/improvement of the drain will ensure efficient drainage system within
the subproject area. The present subproject is therefore, designed for an expansion of
transport facilities and improvement of the drainage system to meet the present and calculated
future demands for the citizens of Pourashava. The subproject expected to improve the service
standards with respect to proper transport and drainage facilities.
VI. SUBPROJECT BENEFITS
8. Through construction and improvement of roads, drain, regulator and canal re-
excavation under the subproject is anticipated to bring various quantifiable benefits. Availability
of good drainage facilities will add to improve both the quality of life, and living condition of
residents, easy transportation with low cost, which will bring new avenues for investments
and consequently will boost up economic development. Extended benefits will include
employment opportunity of local people in construction works and thus to receive short-term
socio-economic benefits. To ensure benefits to local people, the Contractor will be required
to employ labor force from local communities, particularly within the vicinity of construction sites
as much as possible. The main beneficiaries of the improved road & drainage system will be the
citizens of pourashava area provided with better transport & drainage facilities to a
considerable number of populations of the town. This will improve the quality of life of residents
of the city as well as raising standards of both individual and public health. Moreover, the
subproject will bring economic gains to local people in the form of increased employment and
while spending less on healthcare & transport, will save money leading to improve in livelihood
standards significantly.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 12
VII. SOCIAL IMPACT ASSESSMENT FOR THE SUBPROJECT 9. General: The Social safeguard Team conducted the study visiting subproject sites in
April, 2014. The main purpose of the study was to assess and quantify resettlement and social
safeguard issues. During site investigations, consultants had discussions and sharing of ideas
with the Mayor and councilors & concerned Engineers/off icials , of the Pourashava , at
Mongla Port Pourashava office and also conducted meetings with the local people, local
government representatives in the subproject area. However, during field visit program,
Consultant physically visited all the design completed schemes selected for construction and
improvement under the subproject and investigated the likely impacts on the people with respect
to land acquisition & resettlement and other social safeguard issues (An IR impact checklist with
required verification of the sites in April, 2014 attached with this report as annexture-1). During
site visit, Assistant Engineer, one sub-assistant Engineer, and a surveyor of the Pourashava
accompanied the consultants to assist to identify the locations & alignments of the proposed
schemes and organized consultations/meetings with the local representatives and people of the
at different locations of the subproject area. The major findings of the social impact assessment
study have been summarized below:
10. It was revealed from the study that the road, drain, regulator & canal re-excavation
schemes under the subproject selected for construction under the CRDP is expected to
facilitate improved transport & drainage facilities for the residents of the Pourashava area.
During discussions, it was reported by the Pouarsha representatives & officials, particularly the
local residents & local representatives that onrush of population in the city in every year are
causing severe problems to city dwellers due to insufficient civic facilities particularly in
consideration of the existing roads or coverage of drainage facilities, flood problems etc. They
were expecting that implementation of this subproject within the Pourashava area could
solve the current problem of the residents at a greater extent. The proposed roads, drain,
regulator & canal re-excavation schemes selected under the subproject were a long demand of
the people of the Pourashava.
11. During site visit, consultants investigated about the existing condition of the road,
drainage & canal alignments emphasized on land acquisition, resettlement & rehabilitation
issues. Important findings of the study in connection to IR and social safeguard issues is
that the improvement/constructions of the roads, drains drainage & canal re-excavation was
found to be carried out on the available existing roads and the drains along the edge of the
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 13
existing roads, construction of new drains also along the edge of the existing roads and re-
excavation of canals on existing ROW.. These improvement/construction and re-excavation
works of the schemes under the subproject will neither require nor involve any land acquisition.
In fact, there are no structures, houses, shops or any other establishments found to be affected
on the proposed road, canal & drain alignments, being construction activities will carried out on
the existing roads and canals ROW and the drains at the edge of the existing road alignment. As
a result, no dislocation, displacement or demolition of houses or structures will be required due
to the development. Moreover, on the way to different sites, consultant also had
meetings/discussions with some local people about the necessity of these roads and drains
construction and their improvements. All of them unanimously, welcomed the project and
narrated the current situation and sufferings of city dwellers due to poor condition of roads and
existing drainage system and the paucity of drainages. So, the people discussed/consulted
have been found interested and urged for immediate construction/development of sufficient
number of roads & drains within the pourashava area. Most of the participants during
discussions showed positive attitudes to the proposed subproject improvements. None
opposed the subproject. The public views and suggestions to minimize the likely adverse
impacts and to enhance positive impacts due to the subproject implementation have been noted
and incorporated in the report. In this connection, they assured the consultant to extend all
sorts of cooperation and participation during construction/development of this sub project.
12. Land Acquisition & Resettlement: The infrastructure improvements under CRDP could
have resettlement impacts. However, the schemes selected under the subproject of the Mongla
port Pourashava include number of roads, drains, canals, regulators etc. In this connection, an in-
depth social impact assessment was conducted on the design completed schemes only to
examine these issues, particularly with respect to the requirements of the ADB Policy on
Involuntary Resettlement (1995), Social Safeguard Policy Statement (SPS) 2009 and national
legislation of the Government of Bangladesh. The social safeguard study for the design
completed schemes under Mongla Port Pourashava suggests that there are no possibility of new
land requirements, being improvement of the road will be done on the existing ROW and land is
available belong to Pourashava. The drain construction/improvement will be done on the road
shoulder available land and canal re-excavation will be done on the existing canals. The RoW
allocated for the road, canal and drain schemes also were confined through design prepared by
MDS Consultant using existing road’s ROW and drain construction/improvement at the edge of
existing road shoulders. It was revealed through physical investigation that the subproject impact
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 14
does not extend over any privately owned or any other new land for undertaking civil works. As
such no land acquisition and resettlement will be required. Besides, the proposed ROW for the
design completed road, canals & drains under the subproject, there is no possibility of affecting
any structure and none found to be required relocation. Moreover, there is no possibility to loss
of livelihood, neither permanent nor temporary due to loss of land/assets occupied or squatting by
anybody is expected for the proposed development. Therefore, the potential impact of the
subproject on privately owned land/assets was fully eliminated, and correspondingly, no issues
relating to involuntary Resettlement will occur during implementation of the subproject. Although,
concerned road, canal and drainage schemes unlikely to have any IR or resettlement impact.
However, the construction/improvement of the subproject may cause only minor temporary
disturbances limited to dust and noise, movement of people etc., which will be limited to the
construction period only, and could easily be mitigated as described in this report. Summary of
land acquisition and resettlement impacts which has been assessed using a standard IR
checklist undertaking a complete transect walk for the subproject annexed with this report as
annexure-1.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 15
Pictures-1: showing existing condition in some locations of the Roads, drain & canals selected for construction/ Improvements and re-excavation
Picture-1: Views of Sheik Abdul Hai road showing no
IR impact
Picture-2 of Madrasa Road to Kumerkhali Bridge showing no IR impact
Picture-3: Views link road 2 alignment showing structures at the edge of the road bring no IR impact.
Picture-4: Views link road 2 alignment showing structure at the edge of the road bring no IR impact
Picture-5: Views of Kumarkhali canal selected for Re-excavation will not
bring any IR impact.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 16
VIII. MIT IGATION OF SOCIAL CONCERNS
13. Although the construction/improvement of road, and drainage and canal re-excavation
schemes under the subproject is not expecting any land acquisition and involuntary
resettlement, either physical or economic displacement, or temporary restrictions to land use.
However, some assumptions were made that during civil works for different schemes,
pedestrians, residents and shop keepers/different business operators carrying out different
economic activities particularly beside the road; customers might face temporary
disturbances in connection to movement and operate their business. In order to avoid even
minor temporary disturbances during the construction activities, the following measures are
suggested to eliminate such impacts:
Informing all residents local households and traders about the nature and duration of works in advance, so that they can make necessary preparations to face the situation..
providing wooden walkways/planks across trenches for pedestrians and metal sheets
where vehicle access is required.
Increasing the workforce and using appropriate equipment to complete the work in a minimum timeframe.
Suggest people to wear musk to prevent from dust problem during construction.
Other social concern, if any will be properly solved by Grievance Redress Committee (GRC) under the Grievance Redress Mechanism (GRM) of the project already formed by the PIU/PMCU.
Any other preventive measures to be adopted as required considering the situation during construction.
14. Therefore, the above mitigation measures during civil works would not impede local
resident, pedestrians’ customers and clients from shopping locally or using the usual services
from local businesses.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 17
IX. COMMUNITY CONSULTATION
15. Consultation and meetings started holding with the local community, Pourashava officials,
public representatives, local community people and different stakeholders since subproject
preparation to date at different stages of the project activities to identify different issues,
problems/constraints and prospects and feedback from the participants in connection to different
development activities under the subproject. Consultation is a continuous process which requires
holding from the very beginning of the project preparation to implementation of the project. The
consultations conducted so far were mainly covering information dissemination about the project
/subproject activities & its scope, possible positive and negative impacts includes necessity of land
acquisition, procedures of compensation valuation for the affected land & properties, payment of
compensation, APs/local people’s opinions /feedback on different social issues & concerns e.g.
fair compensation, grievances, local demand, involvement of APs & local people in different
project activities & employment in project works etc.
16. However, such consultations/meetings were conducted at Pourashava office and also at
different sites of the subproject with participation of the Pourashva officials, local representatives,
and local community people to assess the IR impacts. The consultations covered mainly to inform
project stakeholders include project affected & beneficiary people about the project concept, its
objectives and different social safeguard issues, land acquisition requirements etc. as per
technical design of the subprojects. They were also consulted to know about their perceptions on
risks and consequences of the subproject development concerns, views on alternative options and
beneficiary participation in Project cycle. The potential affected persons along with local
residents/community leaders and other stakeholders were consulted through group meetings and
personal contact. The inputs from the stakeholders meetings have been used to develop
appropriate mitigation measures. This interactive approach will continue during the implementation
of the subproject. The findings of the above consultations revealed lots of positive impacts in spite
of a few temporary impacts/concerns limited to construction period only, which have the scope of
mitigation. Table 2 provided with the list of consultations/meetings conducted in different locations
of the subproject area followed by some pictures of consultations below.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 18
Table-2: List of Consultations/Meetings at different locations of the subproject under Mongla Port Pourashva
Sl.
No
Date of
Consultation
Place of
consultation
Number of
Participants
Issues
Discussed
Major findings
01 21-04-2014 Mongla Port
Pourashavan
Office
14 ( Mayor,
Executive
Engineer,
Senior
officials, and
Support Staff
Purpose of the
visit to road &
drainage
sachems, Social
Safeguard & IR
issues,
Grievance
Redress
Mechanism, etc.
The Mayor facilitated to holding the
meeting at Pourashava Office and
provided all necessary support and
cooperation. In the meeting main
discussion was held on the road,
drainage and canal alignment & it’s
possible impacts. Participants reported
that the road will be improved on the
existing ROW & the drain constructed at
the at the edge of the existing road
shoulder The site selected for
construction/improvement of road,
drain& re-excavation of canals are free
from any structures, tress, etc.
In addition detail discussion on Social
Safeguard and Grievance Redress
Mechanism. The participants were
briefed & understood the social
safeguard issues and Grievance
Redress Mechanism. Adopted for this
project & assured to comply with ADB
policy during subproject implementation
& currently GRM is functioning.
02 21-04-2014 At
Kumerkhali
under Sk.
Abdul Hai
Road to
Kumerkhali
Bridge
17 (Local
Elite, project
beneficiaries,
Businessmen
, Physician, .
Services,
House wife)
- Purpose of the visit, --
information dissemination about the subproject & its scope - possible positive and negative impacts - necessity of land acquisition, - compensation issues - APs/local people’s opinions /feedback on
Many of the participants heard about the
proposed development program and
welcomed the project, because they are
facing problem due to lack of sufficient
number of roads & drains for
transportation of goods/agricultural
products & usual day to works e.g going
to school, market, offices, business.
During rainy season they experience
untold sufferings due to huge water
logging in the area in absence of
drainage facilities. So, participants urged
immediate implementation of the
subproject area to get rid of drainage
problem. Participants seemed, there are
hardly any possibilities of IR impacts
considering land acquisition & physical
or economic displacement of people,
being construction/development of roads
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 19
Sl.
No
Date of
Consultation
Place of
consultation
Number of
Participants
Issues
Discussed
Major findings
different social issues & concerns - grievances redress machanisn - local demand, -participation of local people in different project activities - employment in project works etc
on the existing alignments& drains will
be done on the road shoulder. They
assured to cooperate as required
including land donation, if require any.
The participants understood GRM
procedure
They welcome the project
implementation policy & would be happy
to get employment during subproject
implementation, if possible.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 20
Picture-2: Views of Consultation with Mongla Port Officials and local people in the
subproject area.
Meeting at Mongla Port Pourabhava with Mayor &
concerned Engineers and officials Meeting with Local People at Kumerkhali under Sk.
Abdul Hai Road
Consultations with road side people at Madrasha
during site visit
Consultations with women during site visit
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 21
X. GRIEVANCE REDRESS MECHANISM (GRM)
17. In order to receive and facilitate the resolution of affected people’s concerns, complaints,
and grievances concerning the subproject’s safeguards performance, a GRM to be established
at PIU level. This GRM will work to address any complaints that arise during the implementation
of the subproject. In addition, the GRM will include a proactive measure before commencement
of construction of subproject (prior to mobilization), the community will be formally advised of
project implementation details, so that all necessary project information is communicated
effectively to the community and their immediate concerns can be addressed. This proactive
approach with communities will be pursued throughout the implementation of the subproject.
18. The GRM will address affected people's concerns and complaints proactively and
promptly, using an understandable, communicated, and transparent process that is gender
responsive, culturally appropriate, and readily accessible to all segments of the affected people
at no costs and without retribution. The mechanism will not impede access to the Country’s
judicial or administrative remedies. The Local Government Division (LGD) under the Ministry of
LGRD&C issued the office order via memo no. 46.063.014.01.00.015.2011-234; dated: 23 Feb
2014 for the formation of GRC under the GRM for the PIUs under City Region Development
Project. Accordingly, the focal person of PIUs started briefing among the concerned project
stakeholders about the GRM procedures of CRDP and also focusing the mitigation process of
grievance/complaint received from the community, if any. It needs to be mentioned that the
Consultants discussed /briefed about the formation of GRM, its functions & responsibilities
among the project beneficiary/affected persons in the subproject area different times during site
visit.
IR Diligence Report: Drainage Subproject-Mongla Port Pourashava
Page # 22
XI. CONCLUSION
19. A due diligence process was conducted for the subproject to examine the IR issues
particularly with respect to the requirements of the ADB’s SPS (2009) and Land Acquisition
Policy of GOB. However, the road, drainage, regulator and canal construction/improvement
under the subproject at Mongla Port Pourashava will be a straightforward
construction/improvement along the existing road and canal on Pourashava/Government lands.
As a result, the subproject’s roads drain & canal improvement/construction & re-excavation will
neither cross nor affect any land or any structures. Further, any disturbance will be limited to
construction period only. The likely impacts are short- term, localized and could either be easily
avoided or mitigated. The present report describes the findings of the study focused on the
subproject likely impacts in terms of social safeguard and Involuntary Resettlement. The results
of the study suggest that the impact of schemes under this subproject does not incur any land
acquisition, resettlement or economic displacement. The reasons for this outcome are:
i) improvement of the proposed road will be done on the existing road ROW are
encumbrance free;
ii) construction of new drains will be done alongside existing roads are a l so encumbrance free;
iii) Re-excavation of canals will be done on the existing canals are encumbrance free; and iv) the population of the town along the proposed subproject alignments will
hardly impede their business or any other economic activities due to construction of drains, so there should be no resulting losses in income or assets;.
20. The design completed schemes under the subproject studied are unlikely to have any
involuntary resettlement impacts, thus can be classified as a Category C considering the IR
impacts. As a result, it will not require any resettlement survey and preparation of Resettlement
Plan (RP). But it will require extensive consultations/ discussions, with the people and
beneficiaries and to ensure their participation during implementation of the subproject to solve
negative impacts if any, to expedite project works. However, safeguard compliance monitoring
will still be conducted during the project implementation and civil works activities.
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 23
Annexure-1: Involuntary Resettlement (IR) Impacts Checklist by Schemes of the Roads, Drainage, Canals Re-excavation, Regulators under the Subproject of Mongla Port Pourashava.
A. Road Component:
Package No.
Name of Road / Drain / Culvert / Regulator Selected for
Construction / improvement
Chainage Type of assets/structure along the roads and drains
alignment
Possible IR
Impacts
Remarks/Note
W-01 Improvement of Sheik Abdul Hai road & Abdul Majid road from Alamgir store to Zia Sarak.
Ch 0+000 to Ch 1+800 Shops, Houses, Boundary wall, Offices, Ditches, Schools, Electric Poles, etc. etc.
Not expected
All structures on the edge of the road alignment
Link Road 01 Ch.0+000 to Ch. 0+051m Shops, Houses, Boundary wall, etc.
Not expected
All structures on the edge of the road alignment
Link Road 02 Ch.0+000 to Ch. 0+084m Shops, Houses, Boundary wall, etc.
Not expected
All structures on the edge of the road alignment
Link Road 03 Ch.0+000 to Ch. 0+100m Shops, Houses, Boundary wall, etc.
Not expected
All structures on the edge of the road alignment
Link Road 04 Ch.0+000 to Ch. 0+100m Shops, Houses, Boundary wall, etc.
Not expected
All structures on the edge of the road alignment
Link Road 05 Ch.0+000 to Ch. 0+195m Shops, Houses, Boundary wall, etc.
Not expected
All structures on the edge of the road alignment
Link Road 06 Ch.0+000 to Ch. 0+105m Shops, Houses, Ponds, Boundary Wall, etc.
Not expected
All structures on the edge of the road alignment
Drain improvement/construction along Sheik Abdul Hai road & Abdul Majid road with six link road from Alamgir store to Zia Sarak.
Drain - 1 Ch 0+100 to Ch 0+682 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Drain - 2 Ch 0+000 to Ch 0+450 Shops, Houses, Boundary Not All structures on the
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 24
A. Road Component:
Package No.
Name of Road / Drain / Culvert / Regulator Selected for
Construction / improvement
Chainage Type of assets/structure along the roads and drains
alignment
Possible IR
Impacts
Remarks/Note
Walls, etc. expected edge of the drain alignment
Drain - 3 Ch 0+000 to Ch 0+200 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Drain - 4 Ch 0+050 to Ch 0+050 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Link Drain-1 Ch 0+000 to Ch 0+060 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Link Drain -2 Ch 0+000 to Ch 0+084 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Link Drain -3 Ch 0+000 to Ch 0+100 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Link Drain -4 Ch 0+000 to Ch 0+100 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Link Drain -5 Ch 0+000 to Ch 0+195 Shops, Houses, Boundary Walls, etc.
Not expected
All structures on the edge of the drain alignment
Improvement of CC Road for Hazi Baharuddin Road from Madrasa Road to Vashani Road
Ch. 0+000 to Ch. 0+825m Houses, Shops, Electric Poles, Boundary Wall, Ponds, etc
Not expected
All structures on the edge of the road alignment
Link Road - 01 Ch. 0+000 to Ch. 0+120m Houses, Shops, etc. Not expected
All structures on the edge of the road alignment
Link Road - 02 Ch. 0+000 to Ch. 0+089m Houses, Shops, etc. Not expected
All structures on the edge of the road alignment
Improvement of CC road for New Main Road, Sromik Shongha Road, Giasuddin road, Sk. Abdul
Ch. 0+000 to Ch. 1+085m Houses, Shops, Boundary Walls, Mosques, Electric Poles, etc.
Not expected
All structures on the edge of the road alignment
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 25
A. Road Component:
Package No.
Name of Road / Drain / Culvert / Regulator Selected for
Construction / improvement
Chainage Type of assets/structure along the roads and drains
alignment
Possible IR
Impacts
Remarks/Note
Hai Road (Part) Koborstan Road with one Link Road
Construction of Drain for New Main Road, Sromik Shongha Road, Giasuddin, Abdul Hai Road (Part) Koborstan Road and Link Road-01
Ch. 0+000 to Ch. 1+085m Houses, Shops, etc. Not expected
All structures on the edge of the drain alignment
Construction of Drain of Madrasa Road from Sk. Abdul Hai Road to Kumerkhali Bridge
Ch. 0+000 to 1+593m Houses, Shops, etc. Not expected
All structures on the edge of the drain alignment
W-02 Regulator-1: Construction of Regulator at starting point of Kumarkhali Khal
Not expected
No structure
Regulator - 2: Construction of Regulator at starting point of Thakrun Bari Khal
Not expected
No structure
Regulator - 3: Construction of Regulator at Kainmari Khal
Not expected
No structure
Canal-1: Re-excavation of Kumarkhali Khal
Ch. 0+000 to 0+850m Houses, Shops, etc. Not expected
All structures on the edge of the canal alignment
Canal-2: Re-excavation of Thakrun Bari Khal
Ch. 0+000 to 1+250m Houses, Shops, etc. Not expected
All structures on the edge of the canal alignment
Canal-3: Re-excavation of Kewratola Khal
Ch. 0+000 to 1+000m Houses, Shops, etc. Not expected
All structures on the edge of the canal alignment
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 26
Annexure-2: List of Participants in Consultations Meetings in different Location of Mongla Port Pourashava
Sl. No.
Name Occupation Sex (M/F)
Age (year)
1. Location of the meeting : Pourabhavan, Mongla Port
01. Md. Zulfikar Ali Mayor, Mongla Port Pourashava
M 48
Md. Mizanur Rahman International Resettlement Specia;ist
M 59
02. Md. Rafiqul Islam Executive Engineer, Mongla Port
M 50
03. Md. Shofiqul Islam Assistant Engineer M 45
04. Md. Abdur Rahman Service M 40
05. Shymol Kumer Hawlader Service M 42
06. Ratan Kamur Mondal Service M 39
07. Md. Nizamuddin Service M 44
08. Md. shahidul Islam Service M 36
09. Md. Hasan Service M 40
10. Khondoker Khairul Islam Service M 32
11. Sultan Ahmed Service M 29
12. Tushar Kanti Gosh Service M 37
13. Bimol Das Service M 55
14. Mahbubur Rahman Local Elite M 60
2. Location of the meeting : Kumerkhali, Mongla Port
01. Md. Auyub Hawlader Service M 59
02. Md. Rafiqul Islam Labour leader M 50
03. Abdul Malik Local Elite M 50
04. Md. Abul Kasem Bhuiyan Local Elite M 46
05. Md. Monzurul Hoque Business M 32
06. Md. Showkat Hossain Business M 36
07. Md. Kamrul Islam Business M 32
08. Md. Emdadul Islam Business M 28
09. Md. Jahidul Islam Business M 45
10. Md. Ores Ali Business M 38
11. Md. Alam Hawlader Service M 40
12. Md. Mozibur Rahman Local Elite M 33
13. Md. Sohag Khan Local Elite M 43
14. Dr. Mozibul Islam Local Elite M 52
15. Md. Monir Bizaly Service M 30
16. Md. Mostafa Local Elite M 35
17. Md. Emam Farazy Business M 28
18. Dr. Md. Abdul Latif Physician M 48
19. Md. Halim Khan Business M 40
20. Latifa Begum House wife F 35
21. Rousanara Begum House wife F 40
22. Lovely Akhter Service F 29
23. Fuloru Begum Service F 33
24. Saleha Begum House Wife F 36
25. Abdul Khaleque Business M 55
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 27
Annexure-3: Draft Project Information Leaflet on Social safeguards Issues
Government of the People’s Republic of Bangladesh
Ministry of Local Government, Rural Development and Cooperatives Local Government Division
Local Government Engineering Department
Project Information Leaflet (Draft)
For
City Region Development Project (CRDP)
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 28
1. Introduction to the Project (CRDP) - The City Region Development Project (CRDP) is under implementation by the Government for development of different infrastructure facilities covering Dhaka and Khulna regions. The Project will support development of key urban infrastructure, focusing on urban environment and economic development through strengthening municipal management and capacity for effective and sustainable development. The project is implementing number of subprojects jointly funded by ADB, KfW, SIDA and GoB. The project has been formulated as a sector loan to be implemented over a period of 6-years starting from 2011 to 2016. The subprojects under CRDP eligible for funding assistance include transport, water supply & sanitation, solid waste management, drainage, energy efficiency, bus terminal etc. 2. Implementation Arrangement: Local Government Engineering Department (LGED) is the lead executing agency of the Project. Different subprojects to be undertaken will be implemented by a number of Implementing Agencies (IAs), such as: City Corporations, RAJUK, LGED, DPHE, Pourashavas & Upazillas under the project area. 3. Subproject Selection Procedure: The implementation of the Project includes identified sample sub-projects during PPTA along with selection & approval of additional new sub-projects during implementation. The process for selection and approval of new sub-projects are: PMCU invited proposals from municipalities and urban centers covered under the Project. Upon approval of the Steering Committee and no objection from ADB/KfW/SIDA, a feasibility study was carried out by the Consultants following the procedure of PPTA and finally is implementing those subprojects found feasible. 4. Land Acquisition & Resettlement of the project affected people: The project is unlikely to have significant land acquisition & resettlement impacts. The basic principles of CRDP are to: (i) avoid involuntary resettlement whenever feasible; (ii) minimize resettlement where population displacement is unavoidable; and (iii) ensure that displaced persons receive assistance so that they are at least as well-off as they would have been in the absence of the project. 5. The persons eligible for compensation: The APs with or without title to land & properties will be entitled for compensation, resettlement benefits & assistance following the RF and the ADB policy. The APs “with” title to the lands will receive cash compensation for their affected lands, including the structures, fences they have constructed, and crops and trees planted on the lands. Those “without” title to the lands will be compensated for their structures constructed thereon, and crops and trees they have grown in the affected lands. APs eligible for compensation to be identified through a census & detail measurement survey of the affected prosperities. 6. Time for conducting census and inventory of losses in the subproject area: After finalization of detail design for a subproject, concerned PIU office will mark the subproject alignments. After that consultants with support from the PIUs will conduct the census of all APs and will record the inventory of their affected properties in survey questionnaire. The properties recorded in the survey questionnaire will be the bases in calculating the compensation. The completion date of the census survey will be considered “cut-off-date” for receiving entitlements by the APs. After the cut-off-date, no new persons, buildings/ structures or cause, any kind of land use change, will be considered eligible for compensation or resettlement assistance. 7. Category of Vulnerable Affected Persons (APs): i) Households below the poverty line, ii) Households headed by the elderly persons iii) Households headed by physically handicapped, iv). Households headed by women & v) Households headed by Indigenous Persons
IR Due Diligence Report : Mongla Port Pourashava : Annexure
Page # 29
8. Bases for calculating the compensation: All unit prices for calculating the compensation for lands, structure and other affected assets will be based on replacement cost at prevailing market rates in the subproject area.
9. Provision of other benefits to the APs: There are various benefits e.g. income restoration, relocation/shifting, vulnerability allowances that the APs will get from the project. In addition, APs or any member of their family will be provided with skill development trainings and also in employment during construction of the subprojects. In the long-term, the subprojects will be of great help to the people.
10. Responsibility of compensation Payment: Depending on the types of loss, the Deputy Commissioner, PIU/PMCU will pay compensation to APs
11. Procedure for resolving the grievances/issues related to compensation or other Social Safeguard Issues: A Grievance Redress Mechanism (GRM) framed for the
project with the objective to receive & facilitate resolution of APs, complains &
grievances to ensure project safeguard performance. The GRM should be scaled to the risks and adverse impacts of the project. It should address displaced persons concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all segments of the affected people at no costs. The GRM shall not impede access to the existing judicial or administrative remedies. The APs will be appropriately informed about the mechanism. The APs would have every access to file any complaint with the local Grievance Redress Committee (GRC) that established at each PIU. A focal person at each PIU level is responsible (Resettlement safeguards officer or Project Manager) to record complains from APs with convening GRC meetings, recording decisions, issuing minutes of the meetings and taking follow up action etc. The duties of the GRC are: (i) provide necessary support to APs on safeguard related issues; (ii) record grievances of APs and prioritize those that need immediate resolutions; (iii) inform the PMCU of serious disputes that need to be resolved within the appropriate period; and (iv) update the APs on status of their complaints.
12. Public disclosure of Social safeguard Documents/Resettlement Plans: The resettlement plan or other safeguard documents of the project/subproject will be disclosed among the APs and beneficiaries in a local language. These documents will also be uploaded on CRDP/LGED and the ADB website to facilitate dialogue with other individuals and organizations. The PMCU & ADB will ensure the safeguard documents for the subprojects to receive the feedback from stakeholders’ during implementation and to disseminate the necessary information about the major changes of a scheme under the subproject (if any).