City of Windsor Post Construction Audit Report Square East Building · 2015. 7. 20. · 400 CHS...
Transcript of City of Windsor Post Construction Audit Report Square East Building · 2015. 7. 20. · 400 CHS...
-
I of II
Office of the
Auditor General
City of Windsor
A Review of the Project Approval Process,
The Award of the Contracts and,
The Information Reported to City Council for
Decision Making Purposes
Post Construction Audit Report
On the 400 City Hall
Square East Building
Report II-A:
The Design / Build RFP
December 2009
Auditor General’s Office
MARKED COPY: TRACEABLE
To: The Audit Committee and City Council of the Corporation of the City of Windsor
Date: December 2009
I am pleased to present to you our report II-A of the 400 CHS Audit entitled, “A Review of the
Project Approval Process, The Award of the Contracts and The Information Reported to Council for
Decision Making Purposes.”
This audit report is presented to you in keeping with the mandate of the Auditor General’s Office,
“To support City Council and Municipal Administration in meeting their legislated responsibilities,
in improving the performance of the corporation in the programs and services it delivers and in
ensuring the accountability of local government to the taxpayers. The Auditor General’s Office will
bring an independent, objective, professional and value-added approach in evaluating the economy,
efficiency, effectiveness and equity of the results of the corporation’s programs and in evaluating the
appropriateness and adequacy of risk management procedures and management controls.”
Respectfully,
Angela Berry
Lead Auditor, Auditor General’s Office
City of Windsor
QUESTIONS?
The following staff of the Auditor General’s Office may be contacted by email to answer public questions on the
information within this audit report:
To contact the Auditor General’s Office, email us at: [email protected]
Auditor General’s Office Staff:
Angela Berry, Lead Auditor
Florence Lee-St. Amour, Auditor – RFP Approval and Procurement Process
Hayley McCoy, Auditor – The 400 CHS Furniture Tender
TABLE OF CONTENTS
1.0 EXECUTIVE SUMMARY .........................................................................................................................1
2.0 INTRODUCTION TO THE 400 CHS AUDIT REPORT ........................................................................27
2.1 About Good Governance ................................................................................................................27
2.2 An Audit Report about Good Municipal Governance, Not the 400 CHS Project ..........................29
2.3 Scope Limitations & the Conclusion of the 400 CHS Review .......................................................30
2.4 Scope Limitation Issues: The Original Report Split into Two Parts ..............................................31
2.5 Conclusion ......................................................................................................................................31
3.0 OBJECTIVES, SCOPE AND METHODOLOGY ...................................................................................33
3.1 Objectives, Scope and Methodology ..............................................................................................33
3.2 Change to A Best Practice Reporting Format .................................................................................35
3.3 Role of Administration in the Completion of the Review ..............................................................35
3.4 Engaging KPMG to Assist the Audit Function...............................................................................36
4.0 THE PROJECT BUSINESS CASE ..........................................................................................................37
4.1 Expanding on the Report I Recommendation, for the Implementation of a Project Management
Methodology ...................................................................................................................................37
4.2 Project Approval Requirement Issues – The Essential Business Case ...........................................38
4.3 Council’s Good Governance Actions Helped to Mitigate Project Risk ..........................................39
4.4 Conclusion: .....................................................................................................................................41
5.0 THE APPROVAL & PROCUREMENT PROCESS FOR THE 400 CHS, MAIN CONSTRUCTION
CONTRACT ...............................................................................................................................................42
5.1 Report Objective .............................................................................................................................42
5.2 Summary of the Timeline for the Award of the Design / Build Contract .......................................43
5.3 Phase 1 – 3 Discussion & Report Findings .....................................................................................45
5.3.1 Legal Conclusions of the Project Approval and Procurement Process for the Award of the Main
Construction Contract .....................................................................................................................46
Appendix A-I: Legal Review of the RFP & Contracting Practices .........................................................48
5.4 Phase 4 – “Price” Financial Analysis Discussion and Report Findings .........................................82
5.4.1 The Working Environment of the RFP Evaluation Committee ......................................................82
5.4.2 The “Price” Financial Analysis and the Information Reported to Council for Decision Making
Purposes ..........................................................................................................................................95
Discussion: The “Price” Financial Analysis ..................................................................................99
5.5 The Adequacy and Fairness of the “Price” Financial Analysis ....................................................112
5.6 Building Size as the Sole Analysis Criterion & the Impact on the “Risk” Criterion Used for the
Recommendation to Award the RFP ............................................................................................113
6.0 LEGACY COST REPORTING ..............................................................................................................121
Appendix B: Summary of Recommendations and Management Comments ........................................................122
Appendix C:Glossary of Terms ..............................................................................................................................142
1.0 EXECUTIVE SUMMARY
1.1 Background of the 400 CHS Report
About the City’s 400
CHS Project.
In 2001, the Corporation of the City of Windsor (the City) began a process to design
and construct the 400 CHS building (400 City Hall Square). The purpose of the
building was to consolidate the income security programs of the City of Windsor, the
Province of Ontario and the Federal Government into one location. The building was
substantially completed by 2005 at which time the tenants began moving into the
building.
Background of the
400 CHS Audit
Report.
What was the scope of
the review?
The 400 CHS audit is
now concluded – in
three separate
reports.
In 2006, the Auditor General’s Office (under a former structure entitled City Auditor’s
Office) undertook a post-construction audit of the processes approving the project and
managing the construction of the building. In April of 2007, the City Auditor’s Office
prepared a draft document, entitled, “Draft: Post-Construction Audit Report on the 400
City Hall Square East Building”. Since that time, the (former) City Auditor’s Office
has transitioned into the Auditor General’s Office (July 2008).
The audit objectives included a review of the extent to which the project approval and
procurement processes were conducted in compliance with the City’s Purchasing By-
Law, the Municipal Act, 2001 and the Common Law governing procurement by public
authorities in awarding the contracts for the building design and construction and for
the building fit-ups. Additionally, the objectives included a review of the quality of the
information reported to Council for decision-making purposes for project approval and
procurement processes.
- Part I: In February of 2009, the Auditor General's Office released Part I of the
400 CHS audit entitled, “Post Construction Audit Report on the 400 City Hall
Square East Building - Management of the 400 CHS Construction Contract”.
- This Phase II Report is 2 parts: Phase II-A and Phase II-B, which brings the
audit to conclusion. Each report phase has two parts – the audit report and
legal report, as listed below.
Part II-A The RFP process for the Design Build Contract. Appendix A-
I, Legal review of the RFP process.
Part II-B The project’s main Furniture Tender 02-04 for the building fit-
ups. Appendix A-II, Legal review of the Furniture tender.
City of Windsor AGO 1
Report II, Parts A (Design / Build RFP) and B (Furniture Tender) are reviews of
different types of procurement activities, however the findings of each review, were
remarkably similar. Therefore the recommendations of the review have been recorded
in Part A only. Part B, while dealing with a different topic, provides additional support
for consideration of the Part A report recommendations.
Why did we conduct
this review?
The 400 City Hall Square project was a project funded through municipal tax dollars.
As such, there is a high standard required for public transparency and accountability.
This audit report is the end-product of the post-construction audit. It serves as an
effective governance tool, to facilitate transparency and accountability for past
Municipal activities and for improvement in future Municipal activities.
How did we conduct
this review?
The audit involved extensive discussions with various members of current and former
City Staff, Management and City Councillors who worked on the project as well as the
gathering and close examination of numerous City documents (from reports to Council
to Committee meeting minutes to e-mails and memos).
Our fieldwork for this report commenced on April 15, 2008 and concluded June 30,
2009. The work started where the draft dated April 2007 left off. It included review
and analysis of new information received from Administration and gathered through
interviews conducted in 2008 and 2009.
The audit was a collaboration of Audit staff completing the fieldwork, analysis, review
and reporting, Miller Thomson providing legal interpretation of evidence and legal
advice, and KPMG Forensic (engaged by Miller Thomson) providing fact-gathering
and review to support the legal opinions as well as oversight of some of the audit work
of the staff of the City’s Auditor General’s Office.
1.2 A New Plateau in Transparency & Accountability
This report examines, openly, highly sensitive issues. Its publication represents a new
plateau in the level of transparency and accountability reached by the City. The audit’s
findings and recommendations hold nothing back in criticism, where justified, of past
conduct. This should assist Council in holding itself and its administrators more
accountable. Moving on from what took place in the past, the recommendations of the
report address existing risk exposure by providing governance level recommendations
for future improvements, in order to achieve best practices.
City of Windsor AGO 2
The report findings do
not point to issues
with any of the
Proponents or
Consultants that
worked with the City
or with the 400 CHS
Building built by
Vindella – for that
part of the project
was deemed a
success.
We would like to emphasize that any criticisms in this report are exclusively directed
at the decisions and activities of the City of Windsor. The story told in this report is
about the City doing things that subjected the City, its RFP proponents and Consultants
to unnecessary risks. The audit results in no way reflect on the quality of the building
obtained or the services delivered by any of the Proponents or Consultants that
participated in this project, for the building design and construction was described in
our Report I of the 400 CHS review as a success.
1.3 The Audit about Governance Reform – Not the 400 CHS Project
Although the project
construction phase
was a success, there
were serious
problems on the
project caused by
weakness in the City’s
governance structure.
As the audit review progressed, it became clear that if the report were to describe only
the events of the procurement processes of the 400 CHS project, without digging
deeper to examine the basic, underlying causes, the real story would have been missed.
While the audit findings of the project events are concerning, the root cause of what
took place is that the City’s governance structure at that time was not as robust as it
should have been. It was significantly fragmented, creating an environment ripe for
exposing the City to unnecessary risk and cost. The criticisms in this report reveal that
risk. The report recommendations should assist the City to improve its performance on
similar large and / or complex procurement projects and to improve on the quality and
usefulness of information reported to Council for decision making purposes.
What is good
governance & why is
it important?
Governance has two elements: a set of laws/rules and policies, and the processes of
interpreting and applying them. A good municipal governance structure is achieved
through a strong framework of laws and policies (Municipal Act and other applicable
Ontario statutes, City By-Laws, policies and procedures) as developed and
implemented by a core structure of authority (Council and Administration).
The governance structure grants and limits authority, defines public expectations, and
creates mechanisms to ensure accountability and verify performance for the ratepayers
of the City. Good municipal governance also enables the City to be accountable for
the way in which Council and Administration carries out their legal and ethical duties
when dealing with the various interests of the public and the City’s employees, while
managing the City so as to achieve its operational goals efficiently.
City of Windsor AGO 3
Using the examples of
the past as support,
the audit report
recommendations
assist to address risk
that exists today.
By reviewing what happened on the 400 CHS Project, we were able to identify
significant risk and control weaknesses in the City’s governance structure, to present
an inventory of what the City has done since 2002 to improve the weakened control
condition, and to develop recommendations towards improvement on serious risk
weaknesses that exist today.
The recommendations of the report speak to a call for reform to the City’s governance
structure and its support systems. The main audit report demonstrates the need for
such change, through findings and detailed discussions of the decisions and actions of
the City during the project Design / Build RFP and Main Furniture Tender processes.
Why is there a need for change? Certain practices used by the City – both staff and
Council members – during the RFP process through to the award of the contract to the
selected proponent, were unfair and were in contravention of the laws that govern the
City of Windsor. The audit assists in providing recommendations to address the risk of
the City making the same mistakes in the future.
It is important to recognize that there has been significant progress at the City since the
project began (2002). The current governance structure is not what it was in 2002
however, it is still not – and never will be – perfect. Therefore, by using the examples
of the past from which to learn important lessons, the audit can help to prevent the
recurrence of structural weaknesses in the City’s governance system. With this goal in
mind, this audit report recommends various ways to improve future municipal
operations and to strengthen the City’s current governance structure.
1.4 Four Main Causes of the 400 CHS Project Issues
There were issues in
the City’s governance
structure that created
pressure and
opportunity for things
to go wrong.
The audit report considers issues of the 400 CHS project around weaknesses in three
core elements of good governance in the municipal context: (i) The appropriate
allocation of powers between Council and Administration, (ii) The maintenance of
continuous vigilance over the City’s accountability systems and, (iii) Appropriate
corrective action taken when the system controls have been avoided without proper
authorization, or where the City becomes exposed to significant risk.
Council made the
error of breaking the
first element of good
governance, by
stepping into the role
of Administration.
In 2002, Council was concerned about three significant issues that affected the 400
CHS project: (1) the history of other projects going over budget and the lack of
communications from Administration to Council on those projects, (2) the fact that the
City was in the shadow of the multi-hundred-million dollar MFP crisis, and (3) the fact
that the City was carrying a significant municipal debt load, which by the year 2003,
was 54% higher than the municipal average (and headed higher given a number of
planned projects requiring debt issuances).
City of Windsor AGO 4
This heightened the
risk of problems
occurring, but was by
no means the sole
cause of project
problems.
These serious problems faced by the City prompted the decision of Council to step into
the role of Administration in undertaking a review of the RFP responses and
developing a short list of the RFP proponents for the 400 CHS project. This action
took place in the midst of Administration managing the RFP process and created an
environment of conflicting processes, unfair practices, frustration and intimidation.
Council did not maintain the segregation of powers required for governance to operate
effectively, and many serious problems ensued. The action heightened the risk that
problems would arise, and for those problems that did arise, the impact was amplified.
While this action did have a significant impact on this project, it was secondary to the
weaknesses in the City’s governance structure – which created the risk of what then
took place.
Poor project planning
and failure to
adequately set the
project stage for
success was a 2nd
cause.
Another main cause of the 400 CHS problems started long before Council stepped into
the role of Administration. Council was initially approached by Administration with a
request to approve an “idea”, and from that point, the project evolved into a “reality”.
Between the “idea” and the “reality” phases, the critical steps taken by Administration
towards project planning and implementation were weak.
Administration did not provide Council with a strong business case, with a defined,
critical review of the prospective financial and environmental impacts, risks of, or
alternatives to the project. A strong business case is a good tool for Council to use in
deciding whether to proceed with a project. The case should show strong support for
the recommendation that the project is worth pursuing, by demonstrating that the
project is more likely than not to achieve its identified goals.
Going into the project, Council had major concerns about known risk to the City – with
the ongoing project issues, MFP and the City’s high debt level. Council also had
concerns about unknown risk because the project was loosely defined and poorly
planned. Administration did not have an adequate plan in place to serve as a solid base
to prove to Council that Administration had done its homework for the project.
Without the availability of such data, Council did not have the information to assess
prudently, whether the project was likely to be successful.
The weakness in project planning included the absence of adequately defined and
established standards of quality and performance for Administrative planning and
reporting to Council. The City also lacked an appropriate project management
methodology that would help to ensure that the project was well planned and managed
in accordance with the City’s Purchasing By-Law, when the temptation to deviate from
the process required by the By-Law and the Common Law materialized.
City of Windsor AGO 5
The 3rd
cause:
Weakness in reporting
to Council for
decision making
purposes.
Anyone preparing information for Council, which is intended to be acted upon, has a
duty of care to take all reasonable steps to ensure that what is prepared for Council is
done so with great clarity, is unbiased and includes all relevant information that is
material to the decision. The reporting to Council in this case was unclear, weak in
disclosure of relevant material information and in some areas was inconsistent.
In a reporting process, the duty of care generally falls to the entire team involved.
Primarily to the author and secondarily to the reviewers required to scan the reports for
glaring errors. The City’s reporting process for the project worked against
transparency of accountability as it muddied the line between the duty of the author
and reviewer. For example, the author had no authority over the report final content.
There were multiple report reviewers who did not have full knowledge (and some did
not have any knowledge) of the ongoing project problems. However, the reviewers did
have authority over the final report content.
The AGO has made specific recommendations to address the weaknesses in the City’s
reporting process, which while improved since 2002, needs improvement to effectively
support good governance and good Council communication.
The 4th cause:
Council and
Administration
demonstrated a low
level of awareness
and understanding of
the laws governing
the City.
Additional causes for the problems include, that the situation resulted in considerable
confusion and inconsistency regarding the respective roles of individual members of
Council and the Administration on the committee appointed to oversee the RFP
process. And, that throughout the 400 CHS procurement processes, Council members
and some senior staff members came to demonstrate a low level of awareness and
understanding of some of the most basic principles of the laws governing the City.
The combined effects of the four causes form the basis of the findings and extensive
report discussions of audit report II-A (the RFP) and II-B (the Furniture Tender).
1.5 The Overriding Concern of the 400 CHS Review
Why are we
concerned today?
The overriding concern of the findings presented in this audit report is that weaknesses
in the City’s governance structure and support systems, compounded by a low level of
awareness and understanding of the principles of some of the laws governing the City,
have led to an ongoing problem for the City of Windsor. While a great deal of
progress has been made since 2002, there is still a significant level of risk that remains
today.
The central conclusion of the review was that certain practices used by the City, both
staff and Council members, during the RFP process through to the award of the
contract to the selected proponent, were unfair and were in contravention of the laws
City of Windsor AGO 6
that govern the City of Windsor. While we did not find evidence to support that the
issues of the 400 CHS project were a result of deliberate actions to deceive or to cause
malice or harm, we caution that there is concern that the environment and culture of
the City during the 400 CHS project fostered pressure, opportunity and the
rationalization to bend or go around the rules.
The adverse impact of this type of risk environment is the strongest in times where it
matters the most, when the City is in the process of making important, time sensitive
and expensive decisions. Given the ongoing high volume of work and activities, there
is a concern that this is a regular risk scenario for Council and Administration at the
City of Windsor and it is our strong recommendation that this negative culture and
governance environment be immediately addressed.
The following examples from the 400 CHS project highlight the reality of the
weakened governance system and the perverse outcomes it produced for the City of
Windsor:
- Some in a position of power (both Council and Administration) achieved what was
perceived to be a desirable result, but the result was unfair and caused the risk of
costly law suits against the City, members of Council and members of senior
Administration.
- Through the actions taken and decisions made, the City risked damage to its
goodwill reputation, to future business relationships (including the ability to attract
quality proponents), and to relationships between Council and City staff. Of
additional concern were the costs that were incurred to achieve this outcome.
- Because of the problems in the governance structure, Council and some members
of Administration were without access to critical information that would have
presented them the opportunity to help the City make alternative, or better,
decisions. Seemingly, Council, the Councillors on the RFP Evaluation Committee
and some of the Administration did not have the knowledge of the serious ongoing
problems, or even that serious problems existed.
In summary… Through this audit, we have raised the awareness that in today’s environment of
municipal transparency and accountability, both Council and senior Administration are
at risk of making decisions without access to the best information available to the point
where serious errors may be made and serious risk may be invited. Both Council and
senior Administration are at risk of being held legally and professionally responsible
for errors that take place in the name of the City of Windsor.
City of Windsor AGO 7
We do not want to leave the impression that the problem is or was the personalities of
the people in place, or were merely the problems that took place on an almost decade
old project. The problem was, and remains, the weaknesses of the City’s governance
structure. Focussing on the structural problem, rather than on personalities, the audit
recommendations call for reform to the City’s governance system. The report also
provides advice to assist Council and Administration in taking the first steps to correct
this situation.
A light at the end of
the tunnel…
The City’s current government, Council, the CAO and senior Administration, faces
two challenges. The first is immediate: answering to the public for what transpired on
the 400 CHS project. The second is more long-term: effect the changes needed to
prevent the City from making the same mistakes in the future.
For a good chance of success, Council should be requested to commit to the following:
(1) A long term advancement strategy to deal with the recommendations of the
review, provided to assist Council and Administration in addressing
weaknesses in the City’s governance system that expose the City to significant
risk.
(2) Long term support that empowers Administration to develop, implement and
maintain the strategy. Such support will potentially require additional costs
and dedicated resources to achieve improvement.
The staff of the AGO have studied the activities of the City’s current municipal
government over the past few years – both Council and Administration. Based on our
observations, we are optimistic that the current Council, CAO and senior
Administration will successfully meet these challenges.
City of Windsor AGO 8
1.6 What Were the Findings of the Review?
Findings of the RFP
Evaluation
There are 12 findings of the audit evaluation of the City’s RFP procurement process
for the design / build contract, comprised of 4 legal conclusions and 8 audit findings,
as listed below:
Legal Conclusion 1: Although we found no evidence of intentional wrongdoing, Council members and
some senior staff members demonstrated a lack of awareness and understanding of
some of the most basic principles of the laws governing the City, including that:
(a) individual Council members do not have the powers of Council itself unless
specifically and validly delegated to them by a Council resolution or By-Law;
(b) neither one, nor more than one Council member appointed to an ad hoc
procurement committee has the authority to over-ride City staff members of
the same committee, or to treat them as merely advisory, unless Council by
resolution or By-Law has given them that power (which was not done with the
400 Building);
(c) once a power has been delegated by By-Law (e.g. a purchasing By-Law
delegating all purchasing power to specific staff manager positions) Council
cannot simply ignore its own By-Law and do whatever it pleases, but must
comply with its By-Law, unless and until it validly amends the By-Law or
creates an exemption from it in another By-Law;
(d) when an RFP is structured as it was for the 400 Building, the submission of
compliant proposals by proponents creates what the Supreme Court of Canada
has defined as the “bidding contract” (“Contract A”) between the City and
each compliant proponent, giving the City legally binding contractual
obligations to each compliant proponent, including obligations (i) to treat each
compliant proponent fairly and evenly and (ii) not to award the ultimate
contract (the project) to a proponent whose proposal was non-compliant;
(e) the City breached this “bidding contract” where, after the closing deadline, it
allowed Vindella, a proponent which had submitted a non-compliant proposal
that should have caused it to be eliminated from further participation, to amend
that proposal, when there was no language in the RFP which gave the City
such a right; and
(f) the City breached the “bidding contract” for the 400 Building by allowing
(actually, inviting) Vindella to amend its non-compliant proposal, thereby
exposing the City to a claim for the reasonable overhead and profit that
City of Windsor AGO 9
EllisDon would have earned from carrying out the project.
Legal Conclusion 2 The City Solicitor was impeded from carrying out the legal duties of his senior legal
position, as required by the Rules of Professional Conduct of the Law Society of Upper
Canada, by:
(a) the literal wording of the City’s Procedural By-Law;
(b) the structural insulation of the Mayor and Council from timely and unfiltered
(by the City Solicitor’s superiors) legal advice; and
(c) the attitude that “we will seek your legal advice when we want it” rather than
“be proactive and exercise your best judgment to help us to avoid going offside
legally”.
These legal, structural and attitudinal impediments have placed Windsor’s City
Solicitor in an untenable conflict situation, and, more importantly, prevented the City,
during the 400 Building RFP process and the building’s construction, from receiving
the benefit of the timely and independent legal advice that all corporations need. This
is risky conduct rendering the City liable to costly law suits. Large public companies
would find such a situation unacceptable. We can see no reason why municipal
corporations should structure themselves to receive a lower standard of legal protection
than their private sector counterparts.
Legal Conclusion 3 The Vindella proposal was non-compliant and should have been rejected immediately,
rather than selected for negotiations at the same time as EllisDon, whose proposal was
compliant. Nor was it fair for the City to allow (and even to assist) Vindella to amend
its proposal after the deadline for submitting a compliant proposal had passed.
Legal Conclusion 4 Correspondence between the City and EllisDon demonstrates that EllisDon was aware
of its legal rights. The City is fortunate not to have been sued by EllisDon when it was
passed over in favour of Vindella. Such legal proceedings would have imposed
significant costs on the City in terms of legal expenses and potential damage claims,
not to mention the political and reputational cost to the City. Had EllisDon sued the
City (before the limitations period had expired), it is possible that the three Council
members on the RFP working committee, who acted without written Council authority
in over-riding the staff and assisting Vindella over their objections, may have been
City of Windsor AGO 10
named as individual defendants. That is why Council members should be aware that
they may be taking personal risks when they engage in legally unauthorized conduct
causing damage to RFP proponents or tender bidders. The naming of Council members
as individual defendants may have placed the City in a position of continuous, ongoing
legal conflict of interest with the three Council members, in that the City (or its
insurers) would have had to raise a defence to an EllisDon lawsuit that would have
been antagonistic to the defences of the 3 Council members.
Audit Conclusion 1 A best practice of project management1 is that a successful project starts with a solid
business case, one that justifies informed, high level support that later, everyone else
can also see reason to support. We did not find evidence of a comprehensive business
case, or its equivalent under another heading, being presented to Council for informed
decision-making purposes for this project. The decision to proceed does not appear to
have been based on a defined, critical review of the prospective financial and
environmental impacts, risks of, or alternatives to the project.
Audit Conclusion 2 The vague Council motion that approved the creation of the ad-hoc procurement
committee and the absence of an adequate, approved business case resulted in a
division between the Councillors and the Administration responsible for
recommending the preferred proponent for the award of the Design / Build Contract.
The division was not contained within that group, but extended to other Administration
involved on the project and reporting to Council. 2
a) The division was evident in the project reports to Council in July, August and
September of 2002. Due to significant concerns over the MFP procurement
scandal and the City’s 2002 debt load, the Council members on the committee,
supported by some Administration external of the committee were running the
selection process on “lowest price” and members of Administration on the
committee were committed to the RFP matrix (Purchasing By-Law).
b) Between January 2002 and September 2002, members of junior
Administration brought concerns to the attention of some senior
Administration and the message reached the then-CAO regarding the City’s
1 Sources: Eight Key Factors to Ensuring Project Success; and Avoiding the Project Management Obstacle Course. Author
Duncan Haughey, a certified PMP and PRINCE2 Practitioner, is the editor of Project Smart, the project management
resource that helps managers at all levels to improve their performance: http://www.projectsmart.co.uk/whitepapers.html
2 Direct evidence which would reveal the identity of individuals will be held confidential by the Auditor General’s Office.
City of Windsor AGO 11
own departures from the announced RFP process as represented to the
prospective proponents.
c) Ultimately, the project environment became adverse. There are multiple
project documents and interview comments that strongly support our finding
that the working environment for certain members of Administration became
one of frustration and intimidation. Commendably, under the pressures of this
environment, some junior members of Administration showed significant
strength and resolve through repeated attempts to have the City return to
fidelity to the RFP process and the Purchasing By-Law.
d) Serious communication issues ensued. Project documentation and
correspondence among all levels of Administration through to February of
2004 shows that the division continued even after the award of the RFP. This
documentation shows that some members of senior Administration, including
the then-CAO were aware of the problems and the expressed legal concerns
with deviating from the RFP process.
e) The concerns about going offside legally reached the level of the then-CAO.
However, through the lack of documentation or comment support, it remains
unclear whether the then-CAO ever apprised the Councillors on the ad-hoc
procurement committee, or apprised Council as a whole, of the dangers of
selecting the final proponent without compliance with the applicable
procurement rules.
Audit Conclusion 3 It was not transparent in the reports to Council that Council was being asked to deviate
from the RFP process or to circumvent the Purchasing By-Law when the
Administration recommended that Council provide “direction” to the RFP Evaluation
Committee to negotiate with the highest ranking proponents in both the technical and
financial reviews of the RFP evaluation. Council was being asked to direct the
Committee to go down a path it legally could not go, without disclosing this.
a) This raises questions of unacceptable “Bid Shopping”, which “occurs when a
municipality opens the bids and then uses them to “negotiate” by approaching
bidders with the information and trying to get them to lower their bids. This
violates Contract A and the duty of good faith.” 3
3 Source: Fall 2008 Municipal Leader magazine, “Love Me, Tenderer: Municipalities, Tendering and the Law” by John D.
Stefaniuk, Partner , Thompson Dorfman Sweatman LLP.
City of Windsor AGO 12
b) It is unclear whether Council was ever advised that providing direction to
negotiate with proponents at this stage in the process would amount to Council
approval to circumvent the Purchasing By-Law. However, as Council could
have amended this By-Law to exempt the 400 Building from it with relative
ease, it is doubtful that this would have been presented, but left undone. The
Stage 2 RFP and related correspondence to the Proponents was clear – that the
Award of the RFP would be decided based on the RFP Assessment Matrix.
What remains unclear, and unlikely, is that Council was advised of this
requirement or reminded of this requirement when deciding on the RFP
Award.
c) The RFP itself created no such division between “technical” and “financial”.
Rather, points were awarded only on a matrix that included a weighting for
financial as well as other criteria. It was not accurate to characterize this
comprehensive and publicly-announced matrix as merely “technical”, and the
narrow, short-run analysis of purchase price alone as “financial”. It was also
without legal foundation to declare two “winners” and to pit one against the
other.
Audit Conclusion 4 The reports to Council failed to disclose the Vindella proposal was non-compliant to
the RFP, and therefore, had to be rejected, rather than declared a winner in the non-
existent “financial” category. The Vindella proposal was presented to Council as a
compliant and seemingly viable proposal, giving the false appearance that it was the
lowest compliant bid4 in the running for the award of the contract.
Audit Conclusion 5 After the Stage 2 evaluation and ranking of the RFP proponents concluded, the City
turned away from the RFP Assessment Matrix process to a “Price” Financial Analysis
to decide the award of the RFP contract.
Whether referred to by Administration as “Annual Operating Budgetary Impact”,
“Cost Neutral”, “Budget Neutral” or “Building Ownership Risk”, etc, the goal of the
“Price” Financial Analysis was to determine the lowest price of ownership (not lowest
cost of ownership) for the 400 CHS building.
The financial information brought forward to Council to determine this lowest price
factor was designed by Administration. There is a concern that Council was not told
4 Means the Bid that would provide the City of Windsor with the desired goods and/or services at the lowest per unit or
overall cost, meets all the Specifications and contains no major irregularity or qualifications.
City of Windsor AGO 13
by Administration that the Purchasing By-Law RFP Matrix which took into account
both long-term “Cost” & short-run “Price” (Value for Money) applied the maximum
weight to the Life Cycle Costing proposal requirement, which was clearly an
appropriate and meaningful evaluation tool to determine the lowest cost of ownership
of a fixed asset over its useful life.
To expand on this statement, the use of cheaper but less durable building designs and
materials, which require earlier replacement and more costly annual maintenance, only
serve to drive down the initial price by an amount which may be smaller than the total
cost of the building over its useful life. This may result in a transfer of costs from this
generation to our children, raising an issue of intergenerational equity.
Audit Conclusion 6 Based on the audit work performed, it is the opinion of the AGO that the “Price”
Financial Analysis used to evaluate the proponents’ proposals was flawed to the point
that it was unfair to Council and to taxpayers. There was incomplete disclosure of
material facts, which likely created the situation that Council did not have the
information to make an informed decision as to the award of the RFP Contract.
a) Council was advised, “…the variance between best and worst case scenario is
the amount of risk the Municipality must consider as the cost of owning this
facility on an annual basis.”
b) The presentation of the “Price” Financial Analysis “Risk” calculation along
with discussion of the RFP requirements in the same report, likely gave
Council the impression that the RFP requirements had relevance to the results
of the analysis. It is unclear whether Council was ever advised that the RFP
Matrix information included in the reports to Council became “for Council
information” only.
c) The “Price” Financial Analysis did not include an adequate evaluation of real
project risks. The risk analysis was a simple calculation that only equalled the
current amount of speculative space rent. The same outcome was achievable
through a simple arithmetic calculation: current un-rented space x the
estimated lease rate per square foot.
d) There was a material omission in the September 2002 report to Council to
recommend the Award of the RFP Contract. No final risk calculation,
Variance (Risk), on a basis consistent with previous reporting, was shown in
the September report. If the final risk calculation had been shown, in carrying
through Administration’s risk analysis methodology consistently, EllisDon
City of Windsor AGO 14
would now have been shown to be less risky. There was also no commentary
to indicate that contrary to prior reports, EllisDon was now the “winner” for
this risk criterion. Although we pursued the question with vigour, no one
connected with the project was able to provide us with any explanation for this
material omission.
Audit Conclusion 7 Based on the audit work performed, the AGO has determined that the “Price” Financial
Analysis used to evaluate the proponents’ proposals was flawed to the point that it was
unfair to the Proponents. Any proposal which met the stated City requirements or
requests of the RFP (any proponent that gave the City what the City asked for), was
placed at an immediate and uncontrollable disadvantage in comparison to a proponent
that did not meet the City’s requirements or requests. Conversely, the less compliant
the proposal, the better chance the proponent had to be declared the winner of the RFP
process.
Audit Conclusion 8 The financial analysis in the reports to Council dated July 18, 2002 (in-camera),
August 21, 2002 (in-camera) and September 4, 2002 (open session # 8652),
consistently used, but did not clearly state the total office space requirement as 111,500
sq. ft., a material decrease of 31,100 sq. ft. from the City’s RFP Stage 2 requested
estimate of 142,600 sq. ft. Any office space greater than 111,500 sq. ft. was now
treated by Administration to be “speculative” space, and thus, as a risk.
It was not appropriate to use the 111,500 sq. ft. value in the financial analysis without
disclosing the nature and consequences of that newly-adopted number. The
presentation of the information regarding the 111,500 sq. ft. in the reports to Council
was incomplete and unclear. Based on the audit work performed, the AGO determined
that:
a) The number represented a material change from the stated requirements of the
RFP as presented to the proponents, and the change had a distorting, punitive
effect on the evaluation of the proposals that came closest to meeting the
building size requirement presented by the City’s RFP.
b) The number was changed by Administration as a result of the loss of the
Provincial tenant, to reflect the then-current risk to the City. The information
should have been used to highlight the risks to Council, to assist Council in its
decision whether to approve the project to proceed. Instead, the information
was used in a manner that punished the RFP proponents that met the stated
City of Windsor AGO 15
requirements of the RFP and rewarded one that did not.
c) By material error or omission, what the reports to Council did not provide was
a discussion of the risk impact to the City that would result from this opaque
change. As stated in the legal memorandum (Appendix A), this change is one
part of the process leading to the breach of the City’s “bidding contract”
obligations to EllisDon. If not for the passage of time, the City would be
facing the risk of compensating EllisDon for the overhead and profit it would
have earned.
d) More broadly defined, the City risked damage to its goodwill, damage to future
business relationships including the ability to attract quality proponents and
quality investment, damage to relationships between Council and City staff,
and caused the risk of legal action against the City, members of Council and
members of senior Administration.
1.7 The Recommendations of the Audit
The Audit
recommendations
To support City Council and Municipal Administration in meeting their legislated
responsibilities, in improving the performance of the corporation in the programs and
services it delivers and in ensuring the accountability of local government to the
taxpayers, we provide the following 13 recommendations:
Recommendation 1 Develop a Strategic Plan to Address Audit Recommendations
To maximize the opportunity to enhance effectiveness and to achieve efficiencies in
the implementation of the 400 CHS recommendations, we recommend the CAO
consider the merits of addressing the recommendations of this review as a package,
through the development of a comprehensive strategic plan that may include a review
of risk, the City’s current strategic plan & corporate initiatives, resource requirements,
etc, and to respond to this audit recommendation with a date that Administration may
report back to the Audit Committee with an action plan and timeframes of the
packaged plan.
For a good chance of success, Council should be requested to commit to the following:
(1) A long term advancement strategy to deal with the recommendations of the
review provided to assist Council and Administration in addressing
weaknesses in the City’s governance system that expose the City to significant
City of Windsor AGO 16
risk.
(2) Long term support that empowers Administration to develop, implement and
maintain the strategy. Such support will potentially require additional costs
and dedicated resources to achieve improvement.
Recommendation 2 To Correct the Structural Insulation of Council’s Access to Timely, Independent
Legal Advice through an Amended Procedural By-law Number 420-2001 or a
Separate By-Law
We recommend that the CAO review the merits of the legal recommendation of Miller
Thomson LLP, and develop a policy for Council review and approval to correct the
issue of the structural insulation of the Mayor and Council, by way of By-Law or By-
Law amendment. This correction is recommended to provide the Mayor and Council
access to timely, independent legal advice from the City Solicitor. And further, to
remove the reporting independence conflict of the City Solicitor, which currently
serves as a barrier to the City Solicitor’s obligation to act in accordance with his or her
legal duties and other duties, such as those required as an Ontario Lawyer under the
Rules of Professional Conduct of the Law Society.
Recommendation of Andrew Roman of Miller Thomson LLP: “We would recommend
that the independence of the City Solicitor be enshrined either in an amended
Procedural By-law Number 420-2001 or within a separate By-law (to be made
consistent with an amended 420-2001) called “Terms of Reference for the City
Solicitor of the City of Windsor”. This By-law would be available to all Councillors
and staff of the City and available to the public on the City’s website, like other
municipal by-laws. This expanded role for the City Solicitor would be set out in much
the same way that the Terms of Reference for the Chair, President and certain key
officers of many Canadian public companies are, and are made available to the public
as a function of good corporate governance.”
Recommendation 3 The Removal of Structural Impediments to an Effective Corporate
Communication System through the Development of Policy and Amendment to
Procedural By-Law 420-2001
That Administration develop a protocol for Council review and approval to correct the
structural issues (relating to or resulting from the organization or functioning of a
political or economic system) that threatens the health of the City’s communication
City of Windsor AGO 17
system; the purpose of which is to preserve the flow of timely, appropriate, relevant
and critical information from the Administration to the Mayor, Council and CAO.
We recommend the policy include the following development of policy and
amendments to By-Law number 420-2001:
i) A City policy that defines the duty of the CAO, General Managers and each
Department Head to report information up a defined chain of command, where
he or she becomes aware of a level of risk being taken that is unacceptably
high to the City of Windsor. (Related City policy includes the “Fraud Policy
and Protocol”, CS.A2.05 under the control of Corporate Services and “Hotline
Protocols”, CAE-01-08 under the control of the Auditor General’s Office.)
ii) The guarantee of no career repercussions imposed on any staff carrying out
these duties should be enshrined by way of an amendment to Procedural By-
Law number 420-2001.
iii) Procedural By-Law number 420-2001 Section 24.1 “Each Department Head
shall act in accordance with any statutory duties”, should be revised to define
the requirement for the CAO, General Managers and each Department Head to
act in accordance with his or her legal duties and other duties, such as those
required as Officers and Employees of the Municipality and those under the
Rules of Professional Conduct of the various disciplines to which he or she
may belong. (I.e. Accountants, Engineers, etc.)
iv) That Procedural By-Law number 420-2001, be amended to revise the phrase
“and control” of Section 24.2, in order to remove implied structural barriers to
the required level of independence for the General Managers and each
Department Head to act in accordance with his or her legal duties and other
duties.
v) That Administration finalize the Corporate Code of Ethics policy for City
Staff, and bring forward the policy to Council for review and approval. The
City has implemented a code of ethics policy for members of Council;
however the code of ethics policy for Administration and staff remains in
draft.
City of Windsor AGO 18
Recommendation 4 Establish a “Top Down” Training Initiative, with Mandatory Components, to
Address the Risk of Legal Errors, Damage to the City’s Goodwill Reputation and
the Ability to Attract Quality Proponents and Future Investment.
To address the identified control weaknesses which lead to the risk of unintentional
errors that may invite legal action against the City, Council, members of Council and
senior Administration, and / or damage to the City’s goodwill reputation and ability to
attract quality proponents in the City’s projects and investment endeavours, we
recommend the following:
That the CAO consider the merits of developing a Corporate training initiative for the
review and approval of Council. The training initiative should provide for mandatory
and non-mandatory opportunities for Council, Administration and City Staff to be
exposed to ongoing education about the roles and responsibilities of the basic
principles of the laws governing the City as well as continued professional
development and education on emerging issues and high risk areas of purchasing and
procurement or other identified subject areas.
We recommended a course of mandatory training to include the exposure to seminars
and materials on the basic principles of the laws that govern the City which:
i) For Council: Acquaints Council with the Municipal Act and legal
requirements for,
a) The Role of Council vs. the Role of Administration,
b) Council and Corporate Governance, and
c) Potential Risk and Liability for Errors Made by Council, and
Individual Members.
ii) For senior Administration: Enhance the ongoing and valuable training
program that acquaints Administration with the Municipal Act and legal
requirements for,
a) The Role of Council vs. the Role of Administration,
b) Senior Administration, Council and Corporate Governance, and
c) Potential Risk and Liability to Administration and Council for Errors
Made by the Council, Individual Members of Council and the
Administration.
City of Windsor AGO 19
iii) City Council, Administration and Staff (Purchasing and Legal staff):
a) Acquaint Council, Administration and City Staff with the implications
of a process that creates the “bidding contract” and the duties and
obligations that flow, even from a process that does not create a
“bidding contract”.
b) Enhance the ongoing and valuable training program with other training
opportunities to expose Staff to current and emerging issues in
purchasing, procurement or others as defined by Administration.
Recommendation 5 To Establish an Accountability Standard of Due Diligence and Due Professional
Care for the Improvement of Information Reported to Council and the CAO for
Decision Making Purposes.
We recommend that the Administration establish a Corporate wide control policy for
Council review and approval that requires the preparation of communications or
reports to Council and the CAO in accordance with due diligence and due professional
care. This type of control should lead to better decisions by improving on the quality
and usefulness of information reported to City Council and senior Administration for
decision making purposes, facilitate transparency through full disclosure, communicate
pertinent risk considerations and establish accountability for the information reported.
In the 400 CHS project, transparency of project accountability was not clear due to
several factors. Improvement of this condition can be achieved through enhancements
to the City’s current reporting protocols as recommended through the development of a
Council approved policy which would:
i) Establish the standard for information to be assigned and prepared to a defined
standard of due diligence and due professional care as per the following
definitions:
a) Due Diligence is the degree of care that a prudent person would exercise.
This would involve the requirement to assign the work to be conducted to
a person with the requisite knowledge, skill and experience to complete the
required task.
b) Due Professional Care calls for the application of the care and skill
expected of a reasonably prudent and competent professional in the same
or similar circumstances. Due professional care is exercised when the
City of Windsor AGO 20
analysis and information reported are performed in accordance with the
Professional Standards under which the author or signatories are bound.
(I.e., Accountant, Engineer, Lawyer, etc.)
ii) The City should create a policy for the development of Council reports which
helps Council and Administration to more fully assess the potential risks of
making decisions with full or partial information, and give Council the
opportunity and understanding to accept or reject those risks. The policy
should:
a) Enshrine the understanding that it is incumbent upon Administration to
review and report special circumstances to Council.
b) Include the requirement for a standardized report heading for
“Important Risk Disclosures”.
c) Make mandatory, that Council reports include a risk discussion with
the requirement to clearly set out within the report body any significant
information that is not disclosed, why, the potential impact including
the risk of not having that information, and any compensating
information.
d) Where appropriate, include Life Cycle Costing information to facilitate
value for money decision making.
iii) Such a policy should retain the standards and requirements established in the
existing Corporate Services control tool: The finance checklist for council
reports and delegation of authority reports (r. April 16, 2009).
Recommendation 6 Formalize & Enhance the City’s Life Cycle Costing (LCC) Strategy to Provide for
Increased Effectiveness, Efficiencies and Value for Money for the City Of
Windsor.
We recommend the CAO consider the merits of developing an LCC strategy, which
has significant value added potential to provide the City opportunities to achieve better
value for money in all its (1) procurement activities, (2) the delivery of products and
services and (3) in municipal performance measurement.
This audit reviewed the importance of LCC as it relates to an RFP evaluation and
selection process on the basic principle of LCC, which is to determine the cost of a
City of Windsor AGO 21
particular product or service through the consideration of environmental, social and
economic costs and benefits that occur throughout the life of a product or service,
rather than on price alone. This is but one aspect of the benefit of LCC, which has far
reaching applications:
i) LCC can assist in making more effective decisions and better informed
procurement choices such as, whether or not to purchase or lease a specific
product or service or which to select from a range of options.
ii) LCC provides the opportunity to maximize on effectiveness and efficiencies
within in every service, program, project, etc. that the City delivers.
iii) In this aspect of LCC, there is existing opportunity to maximize on the
effectiveness and efficiencies of ongoing strategic initiatives. Performance
Measurement, Asset Management, the Service Delivery Review, City Projects
and City procurement, are all founded on the principles of LCC.
iv) As the LCC strategy progresses through maintenance, experience and
sophistication, the City should expect to continue to achieve measurable
improvements in value for money.
Recommendation 7 Transparency and Accountability Amendment to the Purchasing By-Law 400-
2004 for any Exceptions to or Exemptions from the By-Law
Given the significant risk to the City of Windsor involved, it is not recommended that
Council provide approval for the circumvention of the Purchasing By-Law controls.
However, we recognize that under extraordinary circumstances, such activity may
become necessary. We recommend that the City’s Purchasing By-Law 400-2004 be
amended to establish accountability and transparency where exceptions / exemptions
from the By-Law are required. We recommend such amendments to the By-Law
include:
i) A statement of the legal authority under which Council is authorized to
approve exceptions / exemptions of the Purchasing By-Law.
ii) Recognition of the Purchasing By-Law as the best practice standard to achieve
value for money in the City’s purchasing and procurement activities. It should
be noted that a circumvention of the By-Law should be the extraordinary
exception rather than the rule.
iii) The requirement for a written report recommendation to be brought forward to
City of Windsor AGO 22
Council by Administration, which clearly discloses that Council is being asked
to approve the circumvention of the Purchasing By-Law. (A consistent
problem observed by Audit in this, and past audit reviews)
iv) The requirement for the Council report to include a statement of legal risk and
/ or recommendation, prepared by the City Solicitor (or designate) and that the
City Solicitor (or designate) be in attendance to advise Council during the
discussion.
v) The requirement for the Council report to include a statement of purchasing
risk and / or recommendation, prepared by the City’s Purchasing Manager (or
designate) and that the Purchasing Manager (or designate) be present to advise
Council during the discussion.
vi) That the decision of Council to approve the circumvention of the By-Law be
clearly and comprehensively representative of the decision and direction in the
resolution of the Committee of the Whole.
Recommendation 8 Legal Review, Amendments to Purchasing By-Law 400-2004 & the Requirement
for Appropriate Oversight Over the City’s Purchasing and Procurement
Activities
We recommend the CAO consider the merits of the following recommendations to
improve on Purchasing By-Law 400-2004 and to address the risk of recurrence of
purchasing and procurement issues that were reported in the 400 CHS audit review:
i) That Administration establish within Purchasing By-Law 400-2004, a level of
required oversight by the City’s Purchasing or Legal department on purchasing
and procurement processes of a specified dollar amount and complexity.
Administration should conduct a review of the current Purchasing By-Law to
determine whether the coverage of defined Purchasing & Legal department
oversight on purchasing and procurement activities is commensurate with the
purchasing activity and level of risk exposure to the City of Windsor.
ii) As part of the oversight framework, that the Purchasing By-Law be amended
to include the requirement for a Legal and Purchasing review and sign off, on
specific purchasing and procurement activities in excess of a specified dollar
amount or complexity involving a Tender, RFP, or other procurement tool that
results in a formed Contract or Agreement. I.e. Purchasing and Legal sign-off
on RFP or Tender documents to be issued by the City.
City of Windsor AGO 23
iii) That Administration commission the City’s Legal Services department to
conduct a legal review of the Purchasing By-Law in comparison to the legal
memorandum appendix A to this report created by Andrew Roman of Miller
Thomson. The legal review should compare the By-Law and the legal
memorandum to look for additional opportunities for improvement and / or
legally required changes to Purchasing By-Law 400-2004.
iv) We recommend that Administration address the specific legal concern
identified in Appendix A, that Purchasing By-Law 400-2004, “contains a
number of provisions which could be interpreted as attempting to give the City
the right to treat proponents unfairly.”
Recommendation 9 Amend Procedural By-law Number 420-2001 to Ensure The Requirements of the
By-Law for the Establishment of Committees Approved by Resolution of Council
Are Carried Out
By-law Number 420-2001, Part 19 and Appendix B, b), ii sets out specific actions that
are required to take place, upon approved motion by the Committee of the Whole to
form a Special Committee of Council/Advisory Committee or Task Force. However,
there is no control mechanism in place to ensure the required actions are carried out.
We recommend that Procedural By-Law 420-2001 be amended to include language
which defines the responsibility of person(s) or position(s) required to report back to
the Clerk in order to fulfil requirements of Appendix B, b), ii of the City’s Procedural
By-Law. And that the By-Law be revised to include a control mechanism to ensure
that the requirements of the By-Law are carried out to the satisfaction of the Clerk, or
other defined accountable Head.
Recommendation 10 Governance / Project Management / Oversight Improvement
There should be a requirement for projects requiring City funding in excess of a
specified amount, that the City Solicitor (or designate) be assigned to the upper tiers of
project Committees (such as those with a three-tier project management structure
recommended in the Brodel Report) with a defined role to be present to provide pro-
active legal advice and recommendations to Council and Administration in order to
keep projects from steering off-side legally.
City of Windsor AGO 24
Recommendation 11 Attach Project Management Improvement Recommendations to Report I
The recommendations towards improvement to the City’s project management process
within this report should be incorporated into the Project Management Methodology
currently being developed by Administration as per the audit recommendation adopted
in the audit report issued in February 2009 entitled, “Post Construction Audit Report
on the 400 City Hall Square East Building”.
That the City of Windsor establish an adequate and effective project management
methodology that provides standard methods and guidelines to ensure that projects are
conducted in a disciplined, well-managed and consistent manner and; to promote the
delivery of a quality project that will be completed on time, within budget and in
accordance with the project specifications.
Recommendation 12 Project Management Improvements
There should be a requirement, for all future discretionary City projects requiring City
funding in excess of a specified amount, that Administration must prepare and submit
a comprehensive business case analysis for the purpose of making supportable and
prudent investment recommendations to Council.
Council decisions regarding the approval of major projects such as the 400 City Hall
Square building should be based on a standard of information established by
Administration to include the identification and documentation of key decision factors
such as clear objectives, analysis of alternatives, expected outcomes, critical success
factors, an environmental risk assessment and risk mitigating measures, cost/benefit
analysis, financing plans, scope and impact of the project.
Recommendation 13 Project Management, RFP and Tender Control Improvements
We recommend, as identified in the legal memorandums Appendix A, Part I RFP and
Part II Furniture Tender to this report, that Administration should establish model
documents for its bid processes and for its true request for proposal so that the process
elements are constructed with the needs and obligations of the City in mind, while risk
is controlled.
The City, in the design of this control should include:
i) The RFP or Tender should specifically incorporate the Purchasing By-Law to
have the effect of providing By-Law guidance as to what is and is not a
City of Windsor AGO 25
compliant proposal.
ii) The development of standardized procurement documents for Tenders and
Proposals with the assistance of purchasing / procurement specialists. An
advantage of such a control is that it promotes effectiveness & efficiency,
mitigates risk and helps to preserve the continuity of operations where
experience leaves the corporation.
iii) The requirement for periodic reviews of the standardized procurement
documents to assess compliance to changes to law and to fine tune for past
experience in using the tool.
iv) The initial model documents to be approved by the City Solicitor (Legal).
v) The development of a mandatory use checklist that includes triggers such as,
the required rejection of any bid or proposal or the required interaction /
approval of Purchasing and / or Legal.
City of Windsor AGO 26
2.0 INTRODUCTION TO THE 400 CHS AUDIT REPORT
2.1 About Good Governance
What is municipal
governance?
How does
governance work?
Role of Council &
Administration in
good governance.
Governance has two elements: a set of laws/rules and policies, and the processes of
interpreting and applying them. As with all such endeavours, there is a need to strive for
constant improvement.
A good municipal governance structure is achieved through a strong framework of laws
and policies (Municipal Act and other applicable Ontario statutes, City, By-Laws,
Policies and procedures) as developed and implemented by a core structure of authority
(Council and Administration). This governance structure grants and limits authority,
defines public expectations, and creates mechanisms to ensure accountability and verify
performance for the residents of the City.
The Municipal Act, 2001 provides the City with the core of a governance framework.
The core power structure outlined in the Act defines the role of Council as making
policy (By-Laws, Policy, direction to Administration, etc.) and the role of
Administration as implementing that policy (through development, monitoring,
implementation and enforcement of procedures).
An efficient and effective governance structure is dependent upon the development and
implementation of strong accountability systems. These systems, which include internal
auditing through the statutory Office of the Auditor General, are designed to monitor and
record the City’s activities, to confirm compliance with the applicable laws, and to
ensure enforcement policies that provide for corrective action whenever laws, processes
and policies have not been followed.
Generally, an internal audit report considers issues around three core elements of good
governance in the municipal context:
(1) That the City maintains the appropriate allocation of powers between Council
and Administration,
(2) That Administration maintains continuous vigilance over the City’s
accountability systems and,
(3) That Council and Administration take appropriate corrective action when the
system controls have been avoided without proper authorization, or where the
City becomes exposed to significant risk because the controls in place are
City of Windsor AGO 27
Why is good
governance
important?
inadequate.
Good municipal governance enables the City to be accountable for the way in which
Council and Administration carries out their legal and ethical duties when dealing with
the various interests of the Public and the City’s employees, while managing the City so
as to achieve its operational goals efficiently.
The Auditor General’s
role in good
governance, as
established by Council
In July 2008, Council made an important contribution to its governance process by
approving the conversion of the former Office of the City Auditor to the Office of the
Auditor General. Additionally, Council strengthened the independence of Windsor’s
internal audit function through a change to its reporting structure. By reporting to
Council through the Audit Committee, the Auditor General is functionally and
administratively independent of the City's Administration. Such internal auditor
independence is crucial to the effectiveness of the Office.
What is Internal
Auditing in the
Municipal Context?
Internal auditing through the Office of the Auditor General, a function created by the
Municipal Act, is very different from the external auditors who audit the City’s financial
statements. Internal auditing helps an organization accomplish its objectives by bringing
a systematic, disciplined approach to evaluate and improve the effectiveness of risk
management, control, and governance processes.
Section 223.19 of the Municipal Act explains the municipal role of internal
auditing as, “… assisting the council in holding itself and its administrators
accountable for the quality of stewardship over public funds and for
achievement of value for money in municipal operations.”
Thus, our work is more about quality and value than quantity.
The principal purpose of an internal audit report in a municipal context is to
communicate the results of an objective evaluation of the municipality’s activities in the
form of findings and recommendations for future improvement, to achieve best
practices. The real benefit of the internal audit process is not the criticism of past
decisions and activities, as these are in the past, but to assist Council and the
Administration to learn from them, and thus, to improve municipal governance. This
will provide greater value for money in future City operations.
City of Windsor AGO 28
2.2 An Audit Report about Good Municipal Governance, Not the 400 CHS Project
This public audit
report is a product of
Council’s dedication
to increased
transparency and
accountability in
Municipal Operations.
This report examines, openly, highly sensitive issues. Its publication represents a new
plateau in the level of transparency and accountability reached by the City. The audit’s
findings and recommendations hold nothing back in criticism, where justified, of past
conduct. This should assist Council in holding itself and its administrators more
accountable. Moving on from what took place in the past, the recommendations of the
report address existing risk exposure by providing governance level recommendations
for future improvements, in order to achieve best practices.
The passage of time
and entangled,
complex events make
accountability for
what took place non-
transparent and
difficult to enforce.
It is not the role of the audit function to hold anyone accountable as such. Rather, we are
here to provide the facts and analysis to Council and Administration for review, to assist
them in holding themselves accountable, and to provide them with recommendations for
future improvement.
Completion of this audit task was difficult. Due to the passage of time, the exodus of
most of the staff that worked on the project, the complexity of the issues and many
environmental factors, there is a reduction in the practical accountability for what took
place during the period of the project. (Appendix C, Glossary of Terms, can assist in
providing greater clarity to the audit discussions of this report.)
For example, the majority of the Administrative team involved in the project that would
have participated in preparing a response to this audit report in draft form are no longer
working at the City of Windsor. Thus, the current senior level of Administration have
inherited the difficult task of responding to the complexities of the audit report with a
reliance on what has been reported, but with a limited oral history of the events that took
place.
The findings of this
review do not reflect
on the quality of this
project, which in audit
report I – was deemed
a success.
In the presentation of the report findings it was necessary to discuss by name, for
purposes of distinction of the parties, the Proponents involved in the RFP and Tender
processes as well as external Consultants and Participants in the project.
We would like to emphasize that any criticisms in this report are exclusively directed at
the decisions and activities of the City of Windsor. The story told in this report is about
the City doing things that subjected the City, its RFP Proponents and Consultants to take
unnecessary risks. The audit results in no way reflect on the quality of building obtained
or the services delivered by any of the Proponents or Consultants that participated in this
project. The building design and construction was described in our Report I of the 400
CHS review as a success.
The 400 CHS audit evaluated the two main procurement processes of the project: (1)
The Main Building Construction RFP and (2) The Main Furniture tender. Under review
City of Windsor AGO 29
were the decisions, events and actions of the City that took place between 2002 and 2005
under a different City leadership, both Council and senior Administration, than is in
place today.
The review findings of
the past are most
useful as examples of
the real story – what
can go wrong when
the City’s governance
structure is in trouble.
As the audit review progressed, it became clear that if we were to describe only the
events of the procurement processes of the 400 CHS project, without digging deeper to
examine the basic, underlying causes, we would miss the real story. While the audit
findings are, in themselves concerning, the root cause is that the City’s governance
structure at that time was not as robust as it should have been. It was significantly
fragmented, creating an environment ripe for exposing the City to needless risk and cost.
The criticisms in this report reveal that risk. Our findings and recommendations should
assist the City to improve its performance in similar large and complex procurement
projects in the future.
Using the examples of
the past, our
recommendations also
take into
consideration the
progress of the City in
strengthening its
Governance structure.
It is important to recognize that there has been significant progress at the City since
2002. The current governance structure is not what it was in 2002. However, it is still
not – and never will be – perfect. Therefore, by using the examples of the past from
which to learn important lessons, the audit can help to prevent the recurrence of
structural weaknesses in the City’s governance system. With this goal in mind, this
audit report recommends ways to improve future municipal operations and to strengthen
the City’s current governance structure.
2.3 Scope Limitations & the Conclusion of the 400 CHS Review
This is the Phase II
report on the 400
CHS Building.
What is a scope
limitation?
This audit review
has been impacted
by a number of
This document is the second report on the audit work and analysis commenced with the
draft audit prepared by the (former) City Auditor’s Office in April of 2007 entitled,
“Draft: Post-Construction Audit Report on the 400 City Hall Square East Building”.
Our review had the benefit of the substantial volume of new information (both
documents and interviews) provided by Administration to the Auditor between April of
2008 and June of 2009.
A scope limitation is anything that gets in the way of an audit being completed
effectively (i.e. timely, useful reporting) and efficiently (i.e. appropriate use of internal
audit staff time and financial resources to complete the audit.)
Of key importance to this file were the significant to severe scope limitations under
which the audit was begun. Those limitations had a severe impact on the potential
usefulness of the April 2007 draft tabled in-camera at the November 2007 meeting of the
City of Windsor AGO 30
significant scope
limitations.
Audit Committee. Overcoming those limitations also, necessarily, had a large impact on
the volume of work, and the time required, to bring the April 2007 draft to completion.
2.4 Scope Limitation Issues: The Original Report Split into Two Parts
In 2008, Audit
reviewed the
challenges of the
scope limitations
and split the report
into two parts.
The (former) City Auditor’s Office prepared a draft 400 CHS audit in April 2007, noting
the scope limitations that impacted the draft document. The result was a draft document
(April 2007), prepared under a significant scope limitation, with three main sections:
A) City of Windsor’s Process for Awarding the Contract for the Building.
B) City’s Tendering of Building Fit-Ups.
C) Project Management Methodology. (Project team performance, on time, on
budget)
Because of the need for us to release what could be completed as soon as possible, the
AGO did the necessary work, and released it, in two parts. Report I, released in
February, 2009, completed section C) of the April 2007 draft. This Report II will
complete the much expanded sections A) and B) of the April 2007 draft.
- In February of 2009, the Auditor General’s Office released Report I entitled,
“Management of the 400 CHS Construction Contract.” Pages 34 – 39 of that report
provided a discussion of the scope limitation impacts on the “C) Project
Management Methodology” part of the audit.
- The scope limitations described in this report are specific to the impact on the audit
objectives for “A) City of Windsor’s Process for Awarding the Contract for the
Building” and “B) City’s Tendering of Building Fit-Ups”.
2.5 Conclusion
There are a number of legal and public policy reasons why the April 2007 draft (a working
paper of the Auditor General’s Office) cannot and should not be released. We understand
that this is frustrating to some members of the public who may be curious about its content.
While the Auditor General’s Office is prohibited by law from releasing the April 2007 draft,
City of Windsor AGO 31
Refer to the KPMG
report, which will
provide a more
comprehensive
explanation of what
happened on this
file.
and, like the Ontario Auditor General, would not release incomplete drafts for sound policy
reasons in any event, we can assure the reader that the Auditor has taken steps to make
certain that all of the issues and concerns considered in the April 2007 draft have been
investigated in detail and with great care, and addressed within this audit report. This
report holds back nothing, censors nothing, and pulls no punches.
The earlier scope limitations on this file have been rectified through obtaining a large
volume of documents and numerous lengthy and detailed interviews. This mass of new data
required a substantial increase in audit work to verify, cross-check and analyze. Once the
audit is completed and our work with the consultants has concluded, the Auditor will be in
the position to present a full accounting to the Audit Committee of the external and internal
costs of completing this file.
- We received, literally, thousands of documents from Administration in 2008 / 2009,
which we were required to organize, review and analyze.
- Even with this large volume of data, there were a number of serious issues reported in
the April 2007 draft that could not be explained by the project documentation alone.
- To fill the important information gaps, the Auditor conducted approximately 40 hours
of information gathering and fact validating interviews, with a diverse range of
interviewees.
The City’s Audit Committee, committed to accountability, transparency and improvement
to future operations, has requested that KPMG issue a report on the audit process of the 400
CHS review. The KPMG report will expand on the topic of scope limitations, provide
additional details, and provide value added recommendations to the City towards the
improvement of the effectiveness and efficiency of future audits.
City of Windsor AGO 32
3.0 OBJECTIVES, SCOPE AND METHODOLOGY
3.1 Objectives, Scope and Methodology
Why did we
complete this
review?
The mandate of the Auditor General’s Office is to support City Council and Municipal
Administration in meeting their legislated responsibilities. This is to be done through
improving the performance of the corporation in the programs and services it delivers,
and in that way, ensuring the qualitative accountability of local government to the
taxpayers. Pursuant to this mandate, the Auditor conducted a post construction review,
to help the City to meet the high standard required for large public project procurement.
The 400 City Hall Square project was a large municipal design and construction project,
and it was funded through municipal tax dollars.
This audit report is the end-product of the post-construction audit of the 400 CHS
Project. It is intended to serve as a value-added tool that not only facilitates short term
transparency and public accountability for the project, but also, serves as a valuable long
term source of information and analysis to everyone with an interest in the project – a
group that includes City Council, the Audit Committee, City Administration and Staff,
the Public, other Municipal organizations, etc.
A post-construction audit is not intended to be a Public Inquiry under the Public
Inquiries Act; nor is it intended to be an exercise in turning up the corner of every rug, to
see if anyone has swept any dirt under it. Used as intended, a post-construction audit is
an effective tool of Corporate Governance that provides a history of what has taken
place, recognizes processes that were performed well and recognizes areas where
improvements need to be recommended.
What were the
objectives of the
review?
The audit objectives included a review of the extent to which the project approval and
procurement processes were conducted in compliance with the City’s Purchasing By-
Law, the Municipal Act, 2001 and the Common Law governing procurement by public
authorities in awarding the contracts for the building construction and fit-ups.
Additionally, the objectives included a review of the quality of the information reported
to Council for decision-making purposes for project approval and procurement
processes.
This is the final
report, bringing the
400 CHS audit to
completion.
This Phase II Report is 2 parts: Phase II-A and Phase II-B.
Phase II-A, the RFP process for the Design Build Contract.
Phase II-B, the project’s main Furniture Tender 02-04 for the building fit-ups.
City of Windsor AGO 33
How did we do the
review?
The audit involved extensive discussions with various members of current and former
City Staff, Management and City Councillors who worked on the project as well as the
gathering and close examination of numerous City documents (from reports to Council
to Committee meeting minutes to e-mails and memos).
Collaborative effort
with Auditor
General’s Office
staff, KPMG
(Forensic) and
Miller Thomson
(Legal).
Principal steps in
the audit
Our fieldwork for this report commenced on April 15, 2008 and concluded June 30,
2009. The work started where the draft dated April 2007 left off and included review
and analysis of new information received from Administration and gathered through
interviews conducted in 2008 and 2009.
The audit was a collaboration of Audit staff completing the fieldwork, analysis, review
and reporting, Miller Thomson providing legal interpretation of evidence and legal
advice, and KPMG Forensic (engaged by Miller Thomson) providing fact-gathering and
review to support the legal opinions as well as oversight of some of the audit work of the
staff of the City’s Auditor General’s Office.
This file dealt with a number of sensitive issues and as such, required the senior level
oversight of a Chief Audit Executive (CAE), a position which has been vacant since
January of 2008. Paul Ross, Senior Vice President of KPMG Forensic (Waterloo)
fulfilled the required oversight role of the CAE in order to complete the audit with an
appropriate standard of proficiency and professional care.
Due to the legal aspects of some of the 400 CHS issues, it was necessary to engage the
specialized legal skill to interpret the audit evidence of the contracting process and to
provide the Auditor with timely legal advice. The City’s internal legal department
would have been in a position of conflict of interest in reviewing its own activities and
opinions as the department was very involved in the 400 CHS project. The Auditor
filled the required legal role by engaging, Andrew Roman, a Partner in the legal firm
Miller Thomson LLP.
The principal steps undertaken in performing the audit were to review and analyze a
substantial volume of new information received from Administration. The Auditor’s
staff reviewed thousands of physical documents along with approximately 100 electronic
project files covering a time span that ranged from 2001 to 2009, including the following
data:
- 400 CHS in-camera and open session reports to Council and minutes of its
meetings.
- 400 CHS Project files, physical and electronic, that were maintained by
Corporate Projects.
- 400 CHS Project Steering Committee meeting minutes and reports.
- Relevant emails, faxes, notes, etc. from administrative staff.
City of Windsor AGO 34
The Audit staff attempted to meet with all persons with a central level of knowledge
about, or involvement on the project. We interviewed approximately 20 such
individuals (some more than once).
- Early information gathering interviews were held to collect general project
knowledge, to identify persons involved in the project and to identify additional
sources of project documentation. These interviews were conducted by the staff
of the Auditor General’s Office before KPMG was retained.
- KPMG conducted most of the remaining interviews. With the exception of a
perceived conflict of interest or an out of town interview, a staff member of the
City’s Auditor General’s Office was present during these interviews to follow
up with secondary questions and as an observer to retain general continuity for
the City.
- Other interviews requiring legal skill and legal knowledge were conducted by
Miller Thomson, with staff of the Auditor General’s Office present to follow up
with secondary questions and as an observer to retain general continuity for the
City.
- Not counting preparation time, over 40 hours of interviews were conducted,
over a period of several months.
3.2 Change to A Best Practice Reporting Format
The City of Toronto Auditor General’s Office is considered to be an Internal Auditing
leader, whose works exemplify best practices. Our Audit reporting has changed and is
now based on the best practice reporting format of the City of Toronto Auditor General’s
Office.
3.3 Role of Administration in the Completion of the Review
Acknowledgment of
the level of
cooperation,
participation and
support of
The Auditor would like to acknowledge the high level of cooperation, participation and
support received during the fieldwork and analysis stage of this review from the past and
present members of Administration, City Council and external consultants who worked
on the project.
City of Windsor AGO 35
Administration that
facilitated the
conclusion of this
audit.
The Auditor would also like to acknowledge the high level of support received from the
senior administrative team who worked with us during the reporting stage, and who
responded to the audit report through Management Comments. The senior
administrative team was led by John Skorobohacz, then-Chief Administrative Officer
and Helga Reidel, then-General Manager of Corporate Services and current Chief
Administrative Officer.
- The review was brought to completion by providing Administration the opportunity
to review the report in draft form in its entirety, with a request to communicate any
identified issues of fact or error.
- Additionally, senior Administration was requested to respond to the audit report
recommendations. The responses of Administration have been attached as
submitted in the Executive Summary of Recommendations & Management
Comments, as were submitted by Administration. This response by Administration
is an essential precondition to the completion of any municipal internal audit
process.
3.4 Engaging KPMG to Assist the Audit Function
Given the timing,
risk and privacy
issues associated
with this review, we
view the decision to
engage KPMG was
both responsible
and appropriate.
KPMG Forensic (based in Waterloo), a branch of the City’s external auditor KPMG
(based in Windsor), was engaged to serve in an assurance and oversight capacity on this
audit file.
Audit standards require that if the external service provider is also the organization’s
external auditor and the nature of the engagement is extended audit services, then the
Auditor General’s Office needs to ascertain that work performed does not impair the
external auditor’s independence5.
The justification for the decision to permit Miller Thomson to retain KPMG for the
internal audit work was based on the legal necessity to protect the privacy of the file and
to reduce the cost and time required to complete the remaining work on the file. KPMG
had been in regular attendance at the City’s Audit Committee meetings and as such, was
familiar with the preliminary issues of the file and the ongoing scope challenges of the
audit function.
We did not identify any issues of impairment to KPMG’s independence and, given the
timing, risk and privacy issues associated with this review, our decision to permit Miller
Thomson to retain KPMG was both responsible (cost-effective) and appropriate.
5 International Professional Practices Framework (IPPF) Practice Advisory 1210.A1-1
City of Windsor AGO 36
4.0 THE PROJECT BUSINESS CASE
4.1 Expanding on the Report I Recommendation, for the Implementation of a
Project Management Methodology
Report I, entitled “Post Construction Audit Report on the 400 City Hall Square East
Building” 6, concluded with a central recommendation regarding project management:
“That the City of Windsor establish an adequate and effective project
management methodology that provides standard methods and guidelines to
ensure that projects are conducted in a disciplined, well-managed and
consistent manner and; to promote the delivery of a quality project that will be
completed on time, within budget and in accordance with the project
specifications.”
In Report, Part I, the Auditor General’s Office addressed the impact of this control
weakness on the Project Management Team’s performance for the project and the lack
of specific and measurable project objectives, which imposed limitations on our ability
to measure that performance.
In this report the Auditor General’s Office will address another important aspect of an
adequate project methodology that was missing in this project, and which led to many
problems in the procurement activities for the 400 CHS project: The absence of a
comprehensive business case (or its equivalent under another heading) with a defined,
critical review of the prospective financial and environmental impacts, risks of, or
alternatives to the project.
6 Released February 2009, “Post Construction Audit Report on the 400 City Hall Square East Building”. To obtain a copy,
call 311 or follow this web link: http://www.Citywindsor.ca/DisplayAttach.asp?AttachID=13246
City of Windsor AGO 37
4.2 Project Approval Requirement Issues – The Essential Business Case
The project was
approved before the
project was planned,
and a business case
was never
presented.
Finding 1.
A best practice of project management7 is that a successful project starts with a solid
business case, one that justifies informed, high level support that later, everyone else can
also see reason to support. We did not find evidence of a comprehensive business case,
or its equivalent under another heading, being presented to Council for informed
decision-making purposes for this project. The decision to proceed does not appear to
have been based on a defined, critical review of the prospective financial and
environmental impacts, risks of, or alternatives to the project.
What is a business
case?
Why is a business
case important?
Why and How did
this happen?
A business case is a comprehensive analysis (in this case to be assembled by
Administration) that tests the feasibility of a project’s success. A business case usually
includes factors such as a mission statement, project summary, critical success factors,
impacts, alternatives, expected outcomes, basic market analysis, risk analysis and a
preliminary analysis of costs and revenues.
A well-developed business case is a useful tool for Council in deciding whether to
proceed with a large and costly project. There should be strong support for a
recommendation that the project is worthy of the expenditure. The business case should
contain sufficient financial and management analysis to satisfy Council that the project
is more likely than not to meet the identified goals.
Once Council approves the project to proceed, the business case becomes a tool for
continued project management. By Clearly defining Council’s expectations, the
business case becomes a means of communicating the project goals and objectives to
everyone involved in its implementation. In that way it becomes a project effectiveness
and efficiency measure that can be used for assessing project performance from start to
finish.
The cart was put before the horse when the project was approved before the project was
planned. As is to be expected, initially, Council was approached with a request to
approve an “idea”, and from that point, the project evolved into a “reality”. Between the
“idea” and the “reality” phases, the critical steps taken towards project planning and
implementation were weak, perhaps because a strong business case was never created.
7 Sources: Eight Key Factors to Ensuring Project Success; and Avoiding the Project Management Obstacle Course. Author
Duncan Haughey, a certified PMP and PRINCE2 Practitioner, is the editor of Project Smart, the project management
resource that helps managers at all levels to improve their performance: http://www.projectsmart.co.uk/whitepapers.html
City of Windsor AGO 38
Why should the City
be concerned?
Conducting the business of large project management without a good methodology --
and good controls in place to ensure the methodology is working -- puts City projects at
risk of being managed ad-hoc. Managing large procurement projects in this type of
unplanned, reactive environment, is almost certain to lead to problems that may be
avoided with a detailed business plan.
The 400 CHS project is not short of examples as to what can go wrong:
- The 400 CHS project environment was one of evolving Council expectations
and widespread confusion as to what the project deliverables were.
- Throughout the project, Administration is noted as asking itself the question,
“What are we supposed to deliver?”
- The expected outcomes of the project were so poorly defined that today, after
Audit has studied the entire body of project documentation, the project goals,
objectives and deliverables are still somewhat vague.
- Project performance measurement is, therefore, indeterminate. The final project
outcome cannot be specifically measured because the project specifications and
expectations were never clearly defined.
- The legal concerns that occurred during the 400 CHS project, as outlined in the
legal memorandum attached to this report, could have been avoided. (See
Appendix A for the legal memorandum)
4.3 Council’s Good Governance Actions Helped to Mitigate Project Risk
Council’s good
governance actions
mitigated some of
the risk on the
project.
After the project was approved on the merits of the “idea”, Council practiced good
governance by setting the stage for future reporting requirements. As a result, Council
can be credited for mitigating some of the initial risk associated with proceeding with the
project without a business case.
- Council, in considering the merits of the 400 CHS project at an in-camera meeting
held on or about June 25, 2001, approved the project in principle and directed
Administration to submit a comprehensive report with a business plan for the
project, outlining any capital funding requirements, decreases in existing annual
operating expenses, sources of revenue and projected annual expenses related to the
proposal. (M103-2001)
City of Windsor AGO 39
Council continued this good governance practice by keeping the focus on reporting
requirements as the project progressed:
- IQ8 41-2001 November 5, 2001 Council meeting - “Requests that a future report
dealing with the proposed building for the consolidation of Income Support Services
Program… include an analysis of ownership versus lease options along with a
detailed analysis of all expenses and revenues including identified savings
associated with the consolidation of the municipal Social Services function.”
- CQ 75-2002 (C) March 4, 2002 Council meeting – “Asks for a cost benefit analysis
regarding the consolidation of the Social Services Department based on the square
footage of the proposed development adjacent to City Hall compared to the square
footage of existing Social Services facilities, with the evaluation to include existing
operating costs as well as projected leasing costs in the new headquarters.”
We did not find
evidence that the
questions of Council
were ever
adequately
addressed by
Administration.
In keeping with best practices and good governance, the initial direction provided by
Council was for Administration to submit a comprehensive report with a business plan
for the project – a project business case. After that direction, Council, on two further
occasions, asked Administration to report on various financial components of what
would be included as part of an adequate business case.
As the project progressed from Council approval to the process for the formation of the
main design-build construction contract, some important elements of a business case
were recorded within a number of project reports to Council, and peripherally in the RFP
documents. However, even considered collectively, these diverse sources of information
do not form what would be considered a solid and clear business case for the project.9
As a result, the direction and questions of Council were never adequately addressed by
Administration.
8 IQ or CQ means an in-camera or open-session Council question.
9 For a detailed analysis of the impact of this issue and specifics of the adequacy of project planning, refer to section 5 of this
report: “The RFP Process and the Award of the Main Construction Contract.”
City of Windsor AGO 40
4.4 Conclusion:
Projects are a daily fact of life for the City of Windsor; So much so that the business
practice is ongoing rather than intermittent. The City has many municipal projects
underway at any given time, and even while these projects are ongoing, the City is
continuously planning for more.
In our audit discussions, Administration confirmed our observation that Administration
takes project management and the successful delivery of projects very seriously. The
overriding concern is not a question of the dedication, commitment or skill of
Administration, but that, for most staff, large and/or complex Project Management is not
the principal role of Administration.
As noted in the Part I report, Phase I of a best practice project management methodology
requires a solid business plan to serve as the foundation for the project. The City does
not currently have a project management methodology in place that makes this a
requirement. Further, as occurred on the 400 CHS project, while working large scale
City projects, Administration may be required to maintain both the high level of Project
Management performance and their regular assigned duties. This situation sets a
difficult standard for any project lead to maintain.
Project Management is a profession.10
Without this type of professional expertise
assigned to work on large or complex projects, and without the appropriate policies,
procedures and other resources in place, the role of Administration in managing large
and/or complex projects would be challenging and the project environment one of high
risk. In today’s project environment, until such time as the City establishes an adequate
project management methodology, at least for major projects, the City’s project
management process will remain one of “high risk”, and beset by preventable problems.
Within Report I and Report II of the 400 CHS audit we have made a number of
recommendations for the improvement of the City’s project management policies and
practices. We suggest that Administration consider using a Project Management
Professional (whether internal or external) experienced in large and complex projects, to
assist in developing an improved project management methodology.
10
A Project Management Professional is defined as a person or firm certified in the requisite knowledge, skills and other
competencies of project management. This definition is in recognition of Project Management as a profession, which has
various designations founded upon specialized educational training in the discipline of planning, organizing, and managing
resources to bring about the successful completion of specific project goals. There are a number of project management
certifications: PMP, CAPM, PgMP, MPM, PMI-RMP, PMI-SP, GSC, PRINCE2, AIPM, etc. Many Universities offer
masters certificates in project management, graduate degrees, etc.
City of Windsor AGO 41
5.0 THE APPROVAL & PROCUREMENT PROCESS FOR
THE 400 CHS, MAIN CONSTRUCTION CONTRACT
5.1 Report Objective
The City’s
Purchasing By-Law
makes it clear: the
City has the legal
responsibility to
conduct
procurement
processes fairly,
honestly, ethically
and with integrity.
The report objective.
The City’s Purchasing By-Law sets an appropriately high ethical tone by including the
requirement to conduct procurement processes lawfully and fairly with a high degree of
honesty, ethics and integrity.
Section 9 of Purchasing By-Law 400-2004 requires:11
(1) “Open and Honest Dealings With Everyone Who is Involved in the
Purchasing Process.”
(2) “Fair and Impartial Award Recommendations for All Contracts and
Tenders,” without extending “preferential treatment to any vendor, including
local companies.”
(3) “An Irreproachable Standard of Personal Integrity on the Part of All Those
Designated as Purchasing Agents...”
The objectives of this section of the audit report were (i) to review whether the project
approval and procurement processes were conducted in compliance with the City’s
Purchasing By-Law, the Municipal Act, 2001 and the Common Law governing
procurement by public authorities; and (ii) to review the information reported to Council
for its decision-making purposes for project approval and procurement processes for the
contracts for the building design and construction.
To minimize overlap and duplication of effort;
- The legal memorandum (appendix A) addresses the degree of legal compliance in
the RFP approval and procurement process.
- The audit review addresses the quality of the information presented to Council for its
decision making purposes for the award of the 400 CHS design/build contract.
11
During the time period under discussion in this section, Purchasing By-Law 9-2000 was in effect. This requirement was
not specifically stated in By-Law 9-2000, however the By-Law did embody the spirit of honesty, fairness, and a high ethical
standard of integrity that is more clearly defined in the amended Purchasing By-Law, Section 9 of By-Law 400-2004.
City of Windsor AGO 42
5.2 Summary of the Timeline for the Award of the Design / Build Contract
Selection for the
design-build
contract was a 4-
phase process.
There was ongoing
confusion and
continuous
misapplication of
the City’s By-Laws
and policies
throughout the RFP
evaluation and
selection process.
Background:
The timeline to select a company to design and build the 400 City Hall Square East
building was made up of 4 phases,
(1) August 2001- Expression of Interest (EOI),
(2) December 2001 – Design-build RFP Stage 1, and
(3) March 2002 – Design-build RFP Stage 2 Assessment Matrix
(4) July – September 2002 – Selection occurs based on “Price”
While the timeline may appear to reflect a standard RFP procurement process, what took
place during that time was not standard. Starting with the establishment of the RFP
Evaluation Committee and throughout the remainder of the process, there was ongoing
confusion and continual misapplication of the City’s By-Laws and policies.
Following the timeline, these examples help to explain the areas of confusion and
misapplication:
The RFP Evaluation Committee was not clearly defined within the documented
resolution of Council that created the committee. It was unclear whether the
Committee established by Council was a formal “Council Committee”
(governed under Procedural By-Law 420-2001) or other ad-hoc “Committee”.
Through the continuous misapplication of By-Laws and policy, the City (at
times Council, at times Administration, at times both) demonstrated a limited
understanding of,
o The purpose of the Purchasing By-Law and its required application to
the RFP,
o The difference between an RFP and a Tender,
o The principles of a “Design / Build” process, and
o Financial principles such as “Price”, “Cost”, “Value for Money”, the
appropriateness of its financial and risk analysis, etc.
Our discussion to follow addresses what resulted from this confusion: a complex system
of continuous errors that exposed the City to a high degree of risk.
What is an EOI or an RFP?
Phase 1:
The Expression of
Interest (EOI)
A call for Expressions of Interest was issued by the City on or about August 2, 2001
requesting responses for a building with a minimum of 141,500 square feet. Expressions
of Interest were received from 15 potentially interested suppliers.
City of Windsor AGO 43
What is an EOI?
An “Expression of Interest” is a response to an invitation by the City to potentially
interested suppliers of goods or services to express interest in being considered as a
potential supplier in a future RFP or other, more detailed process to procure certain
goods or services as required by the City.
Phases 2 & 3:
The RFP
What is an RFP?
What is a Compliant
Proposal?
Stage 1 RFP
The City followed its Request for Expression of Interest with a two (2) stage Request for
Proposal (RFP).
A “Request for Proposal” is used rather than a Tender where a need is identified, but the
method by which it will be achieved is unknown or flexible at the outset. This process
allows vendors to propose solutions or methods to arrive at the desired result. It is the
solicitation of written, competitive proposals, to be used as a basis for entering into a
contract when detailed specifications and price will not necessarily be the predominant
criterion.
“Compliant Proposal” means a competitive offer, binding on the proponent and
submitted in response to and substantially compliant with the City’s Request for
Proposal. The proponent of a non-compliant proposal should not be considered for
further steps in the RFP process. The City evaluates and compares all compliant
proposals to determine which proponent should be awarded the contract. Proposal
evaluation uses criteria such as, but not limited to: proponent qualifications and
experience, product or service features and characteristics, service quality and efficiency
and cost (both the price at time of purchase and the post-purchase) operation and
maintenance costs. Price is normally one of the City’s criteria but will not necessarily be
the predominant one because the quality and suitability of the ideas proposed will also
be critically important. Unlike tenders, Proposals will not have public openings.
In December 2001, the City issued the Stage 1 Design / Build RFP to the prospective
vendors that responded to the EOI. On or about January 14, 2002, Council adopted an
in-camera resolution to appoint three Councillors to a working committee with members
of Administration (from this point on referred to as the RFP Evaluation Committee) to
review the proposals received and to develop a short list of the proponents.
In their responses to the Stage 1 RFP, the proponents were required to provide the details
of their qualifications related to this project. The RFP Stage 1 submissions detailing the
proponents’ qualifications were reviewed by the RFP Evaluation Committee. Only six
proponents were invited to participate further.
City of Windsor AGO 44
Stage 2 RFP and
Assessment Matrix
What is an
“Assessment
Matrix”?
City turned away
from the Purchasing
By-Law process.
Of the six proponents invited to participate in Stage 2, only four submitted proposals.
These Stage 2 submissions were subjected to an evaluation process whereby the RFP
Evaluation Committee reviewed the Proposals against pre-established criteria and
reached consensus on the final rating. The results of this evaluation process were
recorded in an “Assessment Matrix”.
The Assessment Matrix provided 10 different categories for measuring the proposals and
assigned points to each category (with 5 points being the most appropriate to the City’s
requirements) and gave each category a weighting factor (with a factor of 3 being the
most critical to the project).
This is normally where the RFP process ends as the assessment matrix results are
determinate of the outcome of the Award of the Contract. What happened instead was
that the City turned away from the RFP Evaluation Matrix results process of the
Purchasing By-Law, in favour of something else – Price.
Phase 4
Price
Upon completion of the Stage 2 Evaluation Matrix, the RFP evaluation results were
presented to Council on or around May 17, 2002 (preliminary results) and again on or
around July 18, 2002 in an in-camera report. The in-camera report, prepared by
Administration, set out the results of the RFP Assessment Matrix and provided a
financial analysis of the proposals based on price.
The in-camera report dated July 18, 2002 contained a request of the RFP Evaluation
Committee for Council’s approval to “negotiate” with the highest ranking proponents in
both the incorrectly named “technical review” (RFP Evaluation Matrix, which already
included price as one factor) and the newly created “financial review” (Price Financial
Analysis), which had not until then been part of the RFP process. This negotiation with
two parties instead of the one winner of the RFP process was presented as being to
obtain a “best deal” for the City.
5.3 Phase 1 – 3 Discussion & Report Findings
Detailed report
discussion.
The legal issues arising from this change in the procurement process for the RFP Award,
including the questions of “Bid Shopping” and the use of new and previously
undisclosed criteria to determine the Award, are summarized in the following discussion
and in detail in Appendix A.
The legal memorandum addressed the first part of the audit objective for this section,
which was to include a review of whether the project approval and procurement
processes were conducted in compliance with the City’s Purchasing By-Law, the
Municipal Act, 2001 and the common law governing procurement by public authorities.
City of Windsor AGO 45
5.3.1 Legal Conclusions of the Project Approval and Procurement Process
for the Award of the Main Construction Contract
Appendix A is an
external legal
review of the RFP
procurement
process.
There were
numerous legal
issues and legal
errors made during
the procurement and
approval process for
the Award of the
main construction
contract.
So as to preserve the
integrity of the legal
information of
Appendix A, the
written text of the
legal memorandum
copied into this
report was
unaltered.
The Auditor General’s Office asked Andrew Roman, a Partner at the Miller Thomson
LLP law firm, to review the practices used by the City – both staff and Council members
– beginning with the issuance of the first RFP through to the selection of the proponent
to design and construct the 400 Building. The legal review resulted in a legal
memorandum, attached, unedited, as Appendix A to this report.
The Central Conclusion of the Legal Review
The central conclusion of the legal review was that certain practices used by the City –
both staff and Council members – beginning with the issuance of the EOI through to the
award of the contract to the selected proponent were unfair and were in contravention of
the laws that govern the City of Windsor.
Of importance to note is that there were many issues that led to this conclusion. The
three related, but different sets of issues that are considered in detail in the legal
memorandum are:
I. The Relationship Between Council Members And The City Staff In The RFP
Proponent Evaluation Process
II. The Legal Requirement For The Fair Treatment Of Proponents In An RFP Or
Bidding Process
III. The Requirements Of The City’s Purchasing By-Laws
Additionally, the legal memorandum provides a number of recommendations to support
City Council and Municipal Administration in meeting their legislated responsibilities.
These recommendations are intended to improve the performance of the corporation in
future procurement processes; the overall governance structure of the City in obtaining
unobstructed legal advice; and in ensuring the transparency and accountability of local
government to the taxpayers.
Rather than to duplicate effort to say the same thing, and more importantly, to avoid
running the risk of altering the intent of the legal advice provided, Mr. Roman’s legal
memorandum has been attached to this report in its entirety. The following index will
assist in following the legal findings through the Appendix A discussion.
City of Windsor AGO 46
12
The CAO has already taken steps to address this legal finding, as reflected in the City’s new organization structure.
Legal Conclusion 1:
Awareness &
Understanding of
the Law
Appendix A, p. 3
Index Summary of the Legal Findings of the RFP Review
Heading Pages
The Relationship Between Individual Council Members And The City Staff
In The RFP Proponent Evaluation Process.
5-6
Council, not Individual Council Members, Are “The Boss” 6-8
Should Individual Council Members Be Excluded from All Procurement? 8-9
Obtaining Timely, Independent Legal Advice for Procurement Processes 9-14
Legal Conclusion 2:
Access to timely,
independent legal
advice was impeded 12
Appendix A, pp. 3-4
The Legal Requirement For The Fair Treatment Of Proponents In An RFP
Or Bidding Process.
14-15
Does The City Have Legal Obligations as a Result of Issuing the RFP and
Receiving Proposals?
15-17
Did the City’s RFP Process Create Contract A, the “Bidding Contract”? 17-18
Were the Proposals of Either EllisDon or Vindella Compliant so as to
Create the “Bidding Contract” Between the City and One or Both of These
Proponents?
18-21
Given the Nature of the RFP, What Are the Obligations of the City? 21-23
Assuming Vindella’s Proposal Was Compliant, Was EllisDon Treated
Fairly in the Evaluation?
23-26
What is the Exposure of a Party Like the City Upon Breach of its
Obligations Under the “Bidding Contract”?
26-28
How Might the City Minimize its Exposure on Future RFP’s? 28-30
Legal Conclusion 3
& 4:
Non-compliance to
the Purchasing By-
Law & the Legal
exposure that
resulted.
Appendix A pp. 4-5
The Requirements Of The Purchasing By-Laws 30
By-Law 9-2000 30-31
By-Law 400-2004 31-34
STOP The legal memorandum is required reading before continuing with this report. For full
comprehension of the legal issues of the review and to gain background for the report sections to
follow, please read Appendix A.
City of Windsor AGO 47
Toronto
To: Angela Berry
From: Andrew J. Roman
416-595-8604
Date: November 3, 2009
Subject: Legal Review of RFP and Contracting Practices Used by the City of Windsor in
Designing and Constructing the 400 Building
OVERVIEW:
The City of Windsor has asked Miller Thomson LLP to review the practices used by the City –
both staff and Council members – beginning with the issuance of the first RFP through to the
selection of the proponent contracted to design and construct the 400 Building. In preparing this
memorandum, we have had the opportunity to review various City staff correspondence, reports,
notes, file excerpts and other documentation extracted mainly from over 1300 pages of
documents, including:
City of Windsor By-Law Number 9-2000, A By-Law to Establish Purchasing and Materials
Management Policies and Procedures (passed and effective January 4, 2000)
City of Windsor Purchasing By-Law Number 400-2004 (passed and effective December 13,
2004)
City of Windsor By-Law Number 420-2001, A By-Law to Provide Rules Governing the
Proceedings of the Council of the City of Windsor and the Conduct of its Members (passed
November 19, 2001 and effective January 1, 2002) and subsequent amendments
December 2001 Design-Build Request for Proposal Stage 1 New Office Building and Parking
March 2002 Design-Build Request for Proposal Stage 2 New Office Building and Parking
RFP Stage 1 proponent submissions
RFP Stage 2 proponent submissions
Questions to proponents
Answers from proponents
Specific in-camera and public council reports, resolutions and motions
City of Windsor AGO 48
MILLER THOMSON LLP - 2 -
Although we have had one short meeting with the City Solicitor and an interview with the City
Solicitor and the City Clerk1, we have not interviewed any other City staff or the City Council
members who were involved in working on the project at one time or another. Rather, for the
sake of cost efficiency and the avoidance of duplication, we have relied upon the interviews
conducted mainly by the assigned KPMG consultants2.
During the course of our review, while examining the narrow and specific issues related to the
RFP and the proponent selection process, it became clear to us that there were certain related,
very basic legal issues that were either poorly understood by everyone or misunderstood entirely.
Such misunderstanding is common among municipalities in Canada. As well, because this arises
in a specialized and evolving area of law, many lawyers may be unaware of these issues.
Accordingly, to assist in a proper understanding of the specific issues it became necessary for us
to outline the more basic legal background so that our observations on the narrower issues
become more readily comprehensible.
Our earlier drafts of this Memorandum were considerably longer due to the use of numerous,
detailed footnotes setting out the support for various statements and opinions. Most of these
have been removed from this final version to reduce its length and make it easier to read.
However, there is extensive documentary and interview support for all of the statements of fact
or the reported opinions and statements of others, in a separate table (confidential working paper)
from the Office of the Auditor-General. We are grateful to Florence Lee-St. Amour of the
Auditor-General’s Office for having prepared this table.
The three related, but different sets of issues that are considered in detail in this memorandum
are:
I. The Relationship Between Council Members And The City Staff In The RFP
Proponent Evaluation Process
II. The Legal Requirement For The Fair Treatment Of Proponents In An RFP Or
Bidding Process
III. The Requirements Of The City’s Purchasing By-Laws
1 The City Solicitor (formerly the Director of the Legal Division- 2002) and the City Clerk were interviewed by
Andrew Roman and Angela Berry on September 12, 2008. 2 Some of the interviews were conducted by City staff before KPMG was retained. KPMG conducted most of
the interviews after they were retained, and a member of the City’s Auditor General staff was present during
most of the KPMG interviews mainly as an observer, to obtain some general continuity for the City, through
memory and notes of the interviews.
City of Windsor AGO 49
MILLER THOMSON LLP - 3 -
CONCLUSIONS:
1. Although we found no evidence of intentional wrongdoing, Council members and
some senior staff members demonstrated a lack of awareness and understanding of some of the
most basic principles of the laws governing the City, including that:
(a) individual Council members do not have the powers of Council itself unless
specifically and validly delegated to them by a Council resolution or By-Law;
(b) neither one, nor more than one Council member appointed to an ad hoc
procurement committee has the authority to over-ride City staff members of the
same committee, or to treat them as merely advisory, unless Council by resolution
or By-Law has given them that power (which was not done with the 400
Building);
(c) once a power has been delegated by By-Law (e.g. a purchasing By-Law
delegating all purchasing power to specific staff manager positions) Council
cannot simply ignore its own By-Law and do whatever it pleases, but must
comply with its By-Law, unless and until it validly amends the By-Law or creates
an exemption from it in another By-Law;
(d) when an RFP is structured as it was for the 400 Building, the submission of
compliant proposals by proponents creates what the Supreme Court of Canada has
defined as the “bidding contract” (“Contract A”) between the City and each
compliant proponent, giving the City legally binding contractual obligations to
each compliant proponent, including obligations (i) to treat each compliant
proponent fairly and evenly and (ii) not to award the ultimate contract (the
project) to a proponent whose proposal was non-compliant;
(e) the City breached this “bidding contract” where, after the closing deadline, it
allowed Vindella, a proponent which had submitted a non-compliant proposal that
should have caused it to be eliminated from further participation, to amend that
proposal, when there was no language in the RFP which gave the City such a
right; and
(f) the City breached the “bidding contract” for the 400 Building by allowing
(actually, inviting) Vindella to amend its non-compliant proposal, thereby
exposing the City to a claim for the reasonable overhead and profit that EllisDon
would have earned from carrying out the project.
2. The City Solicitor was impeded from carrying out the legal duties of his senior
legal position, as required by the Rules of Professional Conduct of the Law Society of Upper
City of Windsor AGO 50
MILLER THOMSON LLP - 4 -
Canada3, by:
(a) the literal wording of the City’s Procedural By-Law4;
(b) the structural insulation of the Mayor and Council from timely and unfiltered (by
the City Solicitor’s superiors) legal advice; and
(c) the attitude that “we will seek your legal advice when we want it” rather than “be
proactive and exercise your best judgment to help us to avoid going offside
legally”.
These legal, structural and attitudinal impediments have placed Windsor’s City Solicitor in an
untenable conflict situation5, and, more importantly, prevented the City, during the 400 Building
RFP process and the building’s construction, from receiving the benefit of the timely and
independent legal advice that all corporations need. This is risky conduct rendering the City
liable to costly law suits. Large public companies would find such a situation unacceptable. We
can see no reason why municipal corporations should structure themselves to receive a lower
standard of legal protection than their private sector counterparts.
3. The Vindella proposal was non-compliant and should have been rejected
immediately, rather than selected for negotiations at the same time as EllisDon, whose proposal
was compliant. Nor was it fair for the City to allow (and even to assist) Vindella to amend its
proposal after the deadline for submitting a compliant proposal had passed.
4. Correspondence between the City and EllisDon demonstrates that EllisDon was
aware of its legal rights. The City is fortunate not to have been sued by EllisDon when it was
passed over in favour of Vindella. Such legal proceedings would have imposed significant costs
on the City in terms of legal expenses and potential damage claims, not to mention the political
and reputational cost to the City. Had EllisDon sued the City (before the limitations period had
expired), it is possible that the three Council members on the RFP working committee, who
acted without written Council authority in over-riding the staff and assisting Vindella over their
objections, may have been named as individual defendants. That is why Council members
should be aware that they may be taking personal risks when they engage in legally unauthorized
conduct causing damage to RFP proponents or tender bidders. The naming of Council members
as individual defendants may have placed the City in a position of continuous, ongoing legal
conflict of interest with the three Council members, in that the City (or its insurers) would have
had to raise a defence to an EllisDon lawsuit that would have been antagonistic to the defences6
3 The Law Society of Upper Canada is the body that licenses all of the lawyers practising law in Ontario, and
regulates them through its Rules of Professional Conduct. The Law Society is as much a creature of Provincial
Statute as is the City of Windsor. The Rules of the Law Society have as much the force of law as do the By-
Laws of the City. 4 Sections 23.2, 24.1 and 24.2 of By-Law Number 420-2001.
5 Such a conflict is present when obedience to one law may require disobedience to the other.
6 If sued personally, the three Council members’ defences would have been that (a) they were at all times acting
City of Windsor AGO 51
MILLER THOMSON LLP - 5 -
of the three Council members.
ANALYSIS:
I. THE RELATIONSHIP BETWEEN INDIVIDUAL COUNCIL MEMBERS AND
THE CITY STAFF IN THE RFP PROPONENT EVALUATION PROCESS:
Broadly speaking, under the Municipal Act, 2001 (hereafter sometimes referred to as the “Act”),
it is the role of Council to make policy and the role of the Administration to implement that
policy. That is no less true in procurement than in other areas of municipal activity.
There was considerable confusion and inconsistency on the part of both Council members and
City staff, from the very beginning of the 400 Building project, about the respective roles of the
Council members and the administration members on the committee appointed to oversee the
RFP process. There was similar confusion and inconsistency about the very nature of this
committee: was it a subcommittee of Council assisted by administrative staff under the Act, or
was it an administration committee under the City’s Purchasing By-Law, supplemented by the
appointment of three Council members7?
The documentation shows that the Mayor’s Office issued an information release to the public
(released on March 7, 2002) stating:
“City Council oversees this project through a subcommittee of three City Councillors (Coun.
Carlesimo, Coun. Hotham, and Coun. Valentinis) assisted by staff from City administration.”
Despite this information release, these documents are sketchy at best, and there is no record we
have seen of any subcommittee of Council actually having been created by a Council resolution.
Nor is it clear why the staff are shown as merely assisting a subcommittee of Council rather than
being at least equal members of an RFP evaluation committee created under the then-applicable
Purchasing By-Law.
Going the other way, and contradicting the information release from the Mayor’s Office, an In-
Camera Council Report states,
“A review committee composed of three members of Council and members of administration was
struck to evaluate the proposals.”
in their capacities as members of Council, and therefore, (b) that no civil action lay against them personally,
only against the City, and that (c) the City would be liable for their actions. The City (or its insurers) would
have responded that (a) there was nothing in any By-Law or Resolution that allowed these persons to give local
suppliers preference, to over-ride City staff in their procurement functions, or to treat EllisDon unfairly, and
indeed, (b) such actions were expressly prohibited in the applicable purchasing By-Law, so that (c) the City did
not authorize and is not liable for the unlawful conduct of these Council members, but rather, (d) they
themselves were liable. This conflict may have required the resignations of the three Council members until the
legal conflict was resolved by the trial or settlement of the law suit. 7 Former Councillor Peter Carlesimo, former Councillor Charlie Hotham and Councillor Fulvio Valentinis.
City of Windsor AGO 52
MILLER THOMSON LLP - 6 -
This is internally inconsistent with another part of the very same report, which states, on the very
next page
“Members of Council on the review committee directed administration…”.
The documents we have seen show no legal basis for ordinary, individual Council members to be
directing administration on a procurement matter.
To continue the confusion, two months later, a September 4, 2002 Council report for the
September 11, 2002 Council meeting stated:
“This working committee of Councillors was supported by administration serving in the role of
advisors…
and it went on to say:
“At the request of the City Councillors on the working committee six proponents were short listed
to proceed to stage two of the R.F.P.”
and to say:
“The administrative staff supporting the working committee evaluated the proposals based upon
an “assessment matrix”…
The working committee of councillors upon reviewing other evaluation considerations decided to
recommend continuation of all 4 proposals.”
The “other evaluation considerations” are not specified. This use of other considerations is
inconsistent with the principle of transparency and prevents auditing of what new and previously
unannounced considerations went into the evaluation and ranking of the responses to the RFP.
For the reasons discussed in detail below, considerations outside of the publicly announced
evaluation matrix should not have been used once the City had represented to the prospective
proponents that their proposals, if submitted, would be reviewed in accordance with the matrix.
Or, if the City found the matrix to have been seriously defective in some way, it should either
have allowed all proponents the same full and fair opportunity to revise their proposals for a new
matrix, or started the entire RFP process again.
It was reported by the majority of the City staff responding to interviews, and is also evident in
the written documents quoted above, that some of the Council members on the committee which
oversaw the procurement process for the 400 Building (hereafter referred to for simplicity as the
“Committee”) saw themselves as the decision-makers and the staff members as merely advisory
to them. We have been unable to determine any legal basis for this view, and consider it to have
been a misconception. This is an important misconception, as it may well have affected the
selection of the proponent given the contract to design and build the 400 Building.
Council, not Individual Council Members, Are “The Boss”
There is no doubt that in law, Council has the exclusive legislative role in the City. Only
Council can enact municipal By-Laws, subject to the limits imposed by the applicable municipal
City of Windsor AGO 53
MILLER THOMSON LLP - 7 -
legislation. However, individual members of Council do not have all the powers of Council
itself. Outside of their positions as Council members, individual members of Council have only
the power to represent the members of their respective wards in the affairs of the City, and in
particular, at meetings of Council and of Committees of Council. Thus, although Council is at
the apex of the municipal hierarchy, ordinary Council members are not. Indeed, they have no
special powers unless those powers are delegated – and validly delegated– to them by Council.
Section 23.1 (1) of the Municipal Act, 2001 authorizes a municipality to “delegate its powers and
duties .. to a person or body …”. Subsection (2) of that section sets out the rules for such
delegation. Rule 6 states that where a power is delegated, the power is deemed to be delegated,
subject to any limits delegated, e.g., as to conditions, approvals and appeals. One effect of this
subsection is that the same power cannot be delegated twice to different persons, unless the first
delegation is revoked, the power brought back into Council, and then delegated to someone else.
This becomes important when we review, below, the powers delegated by the two purchasing
By-Laws which delegate no powers to Councillors, either individually or as a committee.
The ordinary work of procurement for the City is carried out by City staff, not by Council, or by
Council members. It is doubtful that this kind of activity could ever, practically, be taken over
by Council, either in general or for a specific project. In large and complex procurement projects
conducted via an RFP such as this one, it might have been useful to have appointed a lawyer to
the Committee early on.
The Council resolution appointing the particular Council members to the Committee did not
purport to delegate to them any special powers of Council itself8. The language of the resolution
does not indicate that this is an appointment of a subcommittee of Council, but rather, of an
ordinary committee comprised of the three Councillors and certain unspecified members of the
administration. Council did not authorize any hierarchy within this working committee, nor did
it give any authority for the Committee to do anything outside of the regular RFP processes of
the Purchasing By-Law.
The two purchasing By-Laws (discussed below) placed the authority for the procurement
function squarely within the City staff. These By-Laws were not amended or waived by
resolution for the 400 Building. Therefore, in law, the members of the Committee who were
Councillors were merely ordinary members of an ad hoc Committee (which was probably not
even formally a committee of Council), and were not delegated any special legal powers or given
hierarchical elevation above the other Committee members who were members of the City staff.
Although this was the legal reality, it may not have been the practical reality.
The Council members of the Committee acted as if they had the exclusive power to make all of
the decisions while the other members of the Committee were merely there to advise them,
8 P. 182, January 14, 2002 In-Camera Council Motion M2-2002 item 5:
“That Councillors Hotham, Carlesimo and Valentinis BE APPOINTED to a working committee with members
of the administration for the purpose of undertaking a review and developing a short list of the RFP proponents
for the New Office Building at the former Police Headquarters.”
City of Windsor AGO 54
MILLER THOMSON LLP - 8 -
which advice could be accepted or rejected. In effect, these Council members took over for
themselves the procurement process normally conducted by staff, without any evident legal
basis. Council had already legally delegated the procurement function, in considerable detail, to
various staff managers, in the purchasing By-Law. The By-Law was not amended to create an
exception for the 400 Building, although that would have been the proper way to treat it if
Council had wanted to make this project an exception. Again, as a practical matter, individual
staff members reported in interviews that they had been intimidated by the presence of these
Council members, who behaved as, and were incorrectly seen as, “the bosses”. We are not
suggesting that these individual Council members said or did anything intentionally to intimidate
the City staff. Rather, the assumption that Council members were a higher authority was a
common misconception, shared by several members of the Committee, including two of the
Councillors. To put this into perspective, it is a common misconception among municipalities,
and by no means confined to Windsor, that because Council is at the apex of the municipal
pyramid, individual Council members have the same authority.
There is evidence that some individual members of the City staff did not share in this
misconception of the hierarchical superiority of the individual Councillors, and, quite properly,
complained to the City Solicitor about being overruled or pushed aside by the Council members.
There is also evidence that the City Solicitor brought a number of these legal concerns to the
attention of his superior, to whom he then reported (in his temporary role as Acting
Commissioner of Legal and Human Resources). However, there is no indication that his
superior raised the issue with these Council members to bring them back in line, or did anything
whatsoever to deal with these complaints. This inaction may have been because his superior also
felt powerless in dealing with the individual Council members who were overstepping their legal
authority. It may have been seen as a career-limiting move to complain about this.
Assuming these to be the most likely reasons for the lack of decisive action by either the City
Solicitor or his superior, we would point to two important structural problems that existed at the
time, within the organization of the City. Again, these are by no means unique to Windsor but
are probably shared by many municipalities in Ontario. However, that is no reason not to take
any necessary corrective action.
Should Individual Council Members Be Excluded from All Procurement?
The first structural problem was the tendency of individual Council members to see themselves
as having the authority of Council behind them, and the pragmatic, self-protective acceptance of
that misconception by City staff. Commissioner Denise Bellamy wrote in her Report9 for the
City of Toronto that Council members should be excluded entirely from the procurement
process. Her recommendation provides a simple, clear and unambiguous solution to the practical
problem of individual Council members, perhaps inevitably, exercising authority over City staff
9 Madam Justice Denise Bellamy was sitting in her capacity as a Commissioner of a Public Inquiry into two
related subjects, not as a judge. Her Report was released September 12, 2005, and has two titles on its cover:
Toronto Computer Leasing Inquiry and Toronto External Contracts Inquiry.
City of Windsor AGO 55
MILLER THOMSON LLP - 9 -
that they do not properly have. However, it may be possible to find a less extreme solution for
exceptional procurements such as this one.
Commissioner Bellamy’s proposed solution made perfect sense in the factual context in which it
was presented, namely, the procurement of computer hardware and software, which is not (or at
least should not have been) a high political-content decision. Therefore, the involvement of
elected representatives risked politicizing the procurement process needlessly. The fact situation
of a new municipal building, to which the public is ordinarily admitted, may be somewhat
different. The design of such a building (although not its actual construction) may to some
degree be seen as political. To choose an extreme example to illustrate the point, if the architect
had designed the front doors of the building to be gold plated in order to appear majestic, it
might well have been the legitimate role of Council members to express their concern that this
degree of opulence in the proposed design would be politically unacceptable. Similarly, whether
the added cost of making the ceilings 10 feet high instead of 8 feet high is worth the added
benefit is a trade off which could legitimately benefit from the advice (although not the dictation)
of individual elected representatives. How this political advice should be integrated with the
procurement function (e.g. through a joint Councillor-staff committee or through the oversight of
the entire Council or in other ways) is a management issue rather than a legal issue, hence
beyond the scope of our expertise.
Commissioner Bellamy should not be interpreted as having recommended that no procurement
process, regardless of what is being purchased, should ever have the involvement of any
members of Council. Nevertheless, her recommendation that there be no such participation may
prove to be the only workable solution if Council members are unable to participate in
procurement processes without taking them over entirely, or completely dominating them. Such
participation, to be effective, would have to include the right of City staff to disagree – with a
guarantee of no career repercussions for the staff members – from any recommendation to
Council favoured by individual Council members.
Obtaining Timely, Independent Legal Advice for Procurement Processes
The second structural problem was lack of timely, independent legal advice reaching Council on
the emerging problems with the individual Council members taking over the proponent selection
process without any legal authority. This structural problem was the direct result of the lack of
independence of the position of the City Solicitor (regardless of who may be the incumbent in
that office). Documents and interviews indicate that the City Solicitor expressed his concerns to
his superior, both as a lawyer and as the head of the Legal Department of the City, but we saw no
evidence that his superior either passed on these concerns to anyone, or took any action himself.
Indeed, if the City Solicitor had not, by coincidence, had members of the 400 CHS selection
committee administrative advisory group reporting to him (because the City Solicitor was also
the Head of their department), even the City Solicitor would not have known about it.
On the basis of our review, we are satisfied that the City Solicitor expressed the correct legal
concerns, and did so within his normal “chain of command” to the superior to whom he reported,
in his temporary role as Acting Commissioner of Legal and Human Resources. But that
reporting structure, created by the City’s Procedural By-Law, did not produce the necessary
degree of independent legal advice reaching Council at the right time.
City of Windsor AGO 56
MILLER THOMSON LLP - 10 -
The nature of the problem can be seen in the internal conflict and inconsistency between By-Law
Number 420-2001 (as amended), the City’s Procedural By-Law (passed in intended compliance
with section 55 of the Act). Part 23 of this By-Law sets out the role of the CAO, while Part 24
sets out the role of the department heads.
Section 23.2 states that:
23.2 All reports and recommendations of department heads shall be co-ordinated through the
Chief Administrative Officer.
Since the CAO is at the apex of the administrative structure, even if the City Solicitor is given
the title of Department Head, which is not necessarily the case, any report or recommendation
from the City Solicitor must go through the CAO. In practice – and as was seen in this case –
this means that the CAO can interrupt the flow of communication from the City Solicitor to
Council or the Mayor simply by not forwarding the report or recommendation higher up the
ladder. Or, as the price of forwarding it, the CAO can demand that the City Solicitor amend or
“censor” the report to comply with the CAO’s views. This power of the CAO to veto any report
or recommendation that the CAO does not like worked as a barrier to Council obtaining advice
that was timely and independent.
Sections 24.1 and 24.2 state:
24.1 Each Department Head shall act in accordance with any statutory duties.
24.2 Each Department Head shall be responsible to and subject to direction and control by the
Chief Administrative Officer.
These last two sections created serious problems, and therefore, need to be amended10
.
The expression “statutory duties” in section 24.1 is incomplete and under-inclusive, in that legal
duties are much broader than merely statutory. Many statutes are skeletal in structure and
content, and are fleshed out only in detailed regulations or rules. Each Department Head should
be required to act in accordance with all of his or her legal duties, not merely statutory duties. A
good example of this under-inclusiveness is found in the Rules of Professional Conduct made by
the Law Society of Upper Canada (the governing regulatory body for all lawyers in Ontario) (the
“Law Society”).
Ontario municipalities normally require all of their City Solicitors to be Ontario lawyers,
licensed to practice law in Ontario. As Ontario lawyers, all City Solicitors must comply with the
Law Society’s Rules. Any serious instance of non-compliance can result in the lawyer being
disciplined, and potentially even disbarred (which would make the lawyer unemployable as a
10 Section 24.1 might be amended to read: The Chief Administrative Officer and each Department Head shall act
in compliance with any applicable legal duties imposed by any Federal, Provincial or Municipal statute,
regulation, By-Law, rule or guideline. The City Solicitor and all City lawyers shall at all times comply with all
applicable Rules and Regulations of the Law Society of Upper Canada.
City of Windsor AGO 57
MILLER THOMSON LLP - 11 -
City Solicitor, or in any other kind of lawyer’s position, anywhere in Ontario).
All Ontario lawyers, whether in private practice in a law firm or employed by municipalities,
must adhere to the same rules. Of particular relevance, when a lawyer is employed by an
organization, and the lawyer knows that the organization either intends to act, has acted or is
acting illegally with respect to that matter, the lawyer shall advise the persons “up the ladder”.
This advice should be elevated, if necessary, one step at a time, including, ultimately, to the
Board of Directors of a corporation11
(or its municipal equivalent, the Mayor, and/or Council). If
the organization, despite the lawyer’s advice, continues with the wrongful conduct, the lawyer
must withdraw from acting in that matter12
. (Some legal commentators have gone so far as to
suggest that the lawyer should resign his position entirely, while others say only that the lawyer
should cease working on that particular matter or file.) Thus, the duty of any lawyer in these
circumstances is, first, to be the “whistleblower” up the hierarchical ladder as far as necessary
and, second, if that effort fails, to cease any activity which could be seen as knowingly assisting
in or encouraging any illegal conduct13
.
By-Law section 24.2 states that each Department Head shall be responsible to and subject to
direction and control by the CAO. If the City Solicitor is a Department Head, then that title
alone makes the occupant of that position responsible only to, and subject only to direction and
control by the CAO. If the City Solicitor is below the level of a Department Head, the lawyer’s
position is even less independent. There is a clear conflict between the absolute language of the
hierarchical structure in By-Law section 24.2 and the legal duties of a lawyer who happens to be
a City Solicitor under RPC Rule 2.02 (1.1), which states:
(1.1) Notwithstanding that the instructions may be received from an officer, employee, agent
or representative, when a lawyer is employed or retained by an organization, including a
corporation, in exercising his or her duties and in providing professional services, the lawyer shall
act for the organization.
As the Commentary under this rule explains, it is the organization, as such, that is the client. A
corporate client (which the City is) has a legal personality distinct from its shareholders, officers,
directors and employees. Thus, the client of the City Solicitor is not the Department Head, not
the CAO, not the Mayor and not Council, but the City itself. While a municipality will act and
give instructions to its lawyer through its officers, employees, elected representatives or
whomever, the lawyer’s duty is to ensure that it is the interests of the City that are to be served
and protected.
A coherent, internally consistent By-Law should not create a conflict of interest or a conflict of
duties on the part of the City Solicitor. The City Solicitor’s duty of adherence to the By-Law
should be consistent, at all times, with adherence to the RPC. The absence of any recognition in
11 Law Society of Upper Canada, Rules of Professional Conduct, Rule 2.02 (5.1) and (5.2) (hereafter cited as
“RPC”). 12
RPC Rule 2.09 (7) (d.1). 13
RPC Rule 2.02 (5).
City of Windsor AGO 58
MILLER THOMSON LLP - 12 -
the By-Law of circumstances under which it would not be insubordination but a legal duty for
the City Solicitor to refuse to accept direction and control by the CAO must be corrected by an
amendment to the By-Law14
.
On the other hand, it is also an important aspect of municipal governance that the City’s staff
accountability structure has the office of the CAO at the apex of the pyramid. It would not work
well to defeat or bypass that accountability structure on a regular basis, even for the City
Solicitor. The revised By-Laws should achieve both goals: preserving the accountability
structure in ordinary circumstances, while allowing the City Solicitor to fulfil the legal duty of
being a “whistleblower” in an emergency or if faced by a refusal of the CAO to permit an
important legal warning to go up the ladder to the appropriate elected representatives.
Moving on from our analysis of the conflict between the By-Law and the RPC, which can
relatively easily be resolved, we turn to the question of how best to ensure that timely and
independent legal advice reaches the Mayor and Council without putting the City Solicitor into a
“whistleblower” situation.
There are two possible administrative resolutions to this problem: either to obtain an outside
legal review (as is now being done in this very memorandum, albeit after the fact); or, to create a
higher level of structural independence for the City Solicitor; or to do both.
It would be impractical and prohibitively costly to obtain outside legal opinions on virtually
every matter of any controversy. The City Solicitor should remain the principal legal adviser to
the City, with the formal power and the accepted role of providing timely legal advice and
opinions to Council (or to designated representative of Council, discussed below) directly,
without going through the bureaucratic filters of the Commissioner of Legal and Human
Resources (now called the General Manager of Corporate Services) and the CAO. However, all
City Solicitors have their practical limitations, in that their main area of expertise lies within
municipal law in general and the Municipal Act, 2001 and similar statutes in particular. It is
unreasonable and unfair to expect City Solicitors to be experts in every area of law. Like
corporate in-house counsel everywhere, they should be expected to retain outside counsel when
specific expertise requires it. In this case, however, the legal issues under the various City By-
Laws and the contracting issues under the RFP would have been squarely within the knowledge
of a City Solicitor. Therefore, it would have been preferable if the appropriate role had been
structured for the City Solicitor. It would then have been less likely that Council members
would have mistakenly acted as if they had the authority to take over the decision-making
capacity of City staff in the procurement process.
We have considered a number of different ways in which the role of the City Solicitor could be
restructured. Organizational restructuring is not a legal question but a managerial one, in which
we as lawyers have no specialized expertise. Nevertheless, we can discuss what legal options are
available.
14 Section 24.2 might be amended to delete the words “and control”.
City of Windsor AGO 59
MILLER THOMSON LLP - 13 -
First, the City Solicitor could be instructed, if it is necessary to bypass the CAO in a special or
emergency situation, to go directly to the Mayor. As the Mayor is the CEO of the municipality,
this would not be a legally illogical choice. However, that would immediately politicize the
decision. It would put the Mayor on the spot in having either to take the decision all alone or to
call a meeting of Council and politicize the matter even further.
Second, the City Solicitor could be instructed, in these special circumstances, to go to the entire
Council. The obvious disadvantage would be the time and effort it would take to convoke a
Council meeting, and the question of who on the City staff would convoke this meeting if the
CAO were opposed to Council receiving the City Solicitor’s report.
A third possibility would be for Council, through a By-Law amendment, to appoint a small
committee of Council (e.g., a Legal Committee) with delegated powers to perform this task.
This approach is probably unnecessarily formal because several years might go by, or perhaps
even decades, without the City Solicitor ever having to exercise his “whistleblower”
responsibility. This means that this small committee would exist on paper, but would rarely have
anything to do.
A fourth possibility is to use the existing “whistleblower” structure that the City has in place,
operating through the Office of the Auditor General. Although the structure was established to
receive complaints from the public at large, it also can receive complaints from City staff at all
levels. The Auditor General already has sufficient structural independence from the CAO to
permit the Auditor General to report directly to the Mayor, to the entire Council, or to the
appropriate committee of Council any legal warnings of unlawful conduct presented by the City
Solicitor that the CAO was either failing to act upon or failing to report to the Mayor and
Council. This possibility has the advantage of keeping what would be an obvious disagreement
between the CAO and the City Solicitor within the municipal staff structure for internal
resolution for one final step, providing another opportunity for resolution without going to
Council. It is only if the Auditor General was unable to persuade the CAO to deal with the City
Solicitor’s warnings in a timely and appropriate manner that the City Solicitor would then have
to move his warning a further rung up the ladder, to the political level. In effect, using the
current “whistleblower” mechanism through the Auditor General adds a new rung to the City
Solicitor’s ladder, but hopefully, an effective one which would make it unnecessary in most
cases to go up to the next rung.
This formal, structural change in the independence of the City Solicitor, to be effective, would
also have required a change in attitude from one of “when we want your legal opinion we will
ask for it” to one of “it is your duty to give us your advice on your own initiative whenever you
think it necessary to warn us that we may be going off-side legally”.
We would recommend that the changed role of the City Solicitor be formally recognized, either
in an amendment to Procedural By-Law Number 420-2001 or within a separate By-Law. This
legal change would be available to all Councillors and staff of the City and available to the
public on the City’s website, like any other municipal By-Laws. This recognition of the legal
need to change the role of the City Solicitor would be made available to the public as a function
of good corporate governance. Documenting the independent “watchdog” aspect of the
functions of the City Solicitor is also consistent with relatively recent requirements for U.S. and
City of Windsor AGO 60
MILLER THOMSON LLP - 14 -
Canadian public companies to establish complaint procedures that provide for the receipt,
retention and treatment of complaints and permit confidential, anonymous submissions by
employees with respect to concerns that they may have regarding compliance matters (these have
become known as “whistleblower policies”; the City’s Hotline is one form of this).
While mandatory for public companies, many quasi-public and private organizations have
voluntarily implemented similar procedures. Since the implementation of these complaint
procedure requirements, the U.S. Securities and Exchange Commission and the Ontario
Securities Commission have increasingly sought to hold in-house legal counsel responsible for
compliance-related matters. Legal counsel, as an organization’s gatekeepers on the front lines of
compliance, can be held liable, not only for their own mistakes, but for failing to prevent or
address the corporate wrongdoings of others. A workable whistleblower policy that structurally
and formally includes the City Solicitor is a means of ensuring that an organization’s values and
ethical behaviours (as enunciated in its code of conduct and ethics or similar document) are
enforced.
II. THE LEGAL REQUIREMENT FOR THE FAIR TREATMENT OF
PROPONENTS IN AN RFP OR BIDDING PROCESS
Background
Under the basic law of contracts, the parties must intend to enter binding legal obligations. The
contract comes into being – where that intention exists – when one party makes an offer, the
other party accepts it while the offer is still open, and “consideration” (value) passes between the
parties.
The Stage 1 RFP gives the City a considerable leeway in dealing with proposals that it receives
in both Stage 1 and Stage 2. An example of that language is the following15
:
“The City reserves the right to accept proposals in whole or in part; to discuss different or
additional terms to those expressed in this RFP in the proposal; or, to amend or modify any term
of this RFP. The City reserves the right to reject all proposals.”
There appears to be a widely held view among Council members and even some City staff that
language such as this enables the City to do whatever it wants with the proposals it receives. As
will be seen later in this memorandum, this is a misconception.
The courts have made it clear – in cases that will be cited later in this memorandum – that
owners who engage in procurements similar to this one have duties to the proponents who
respond. Courts have shown an unwillingness to allow owners to treat proponents “unfairly”,
unless the owner expressly states – in the procurement documents – that it reserves the right to
treat proponents unfairly. A clause that announces that an owner may well be unfair is likely to
15 Section A, paragraph ix of the Stage 1 RFP
City of Windsor AGO 61
MILLER THOMSON LLP - 15 -
deter many prospective proponents, who will not want to make a considerable investment of time
and money to prepare a detailed proposal and then have it rejected unfairly.
What constitutes fair treatment has been defined by the courts with some particularity, although
fairness requirements will necessarily vary with the facts of the case. What is important to
understand is that the legal notion of “fairness” in procurement has a specific legal meaning that
is not to be confused with the commonly held concept of fair play or the notion of a level playing
field. Rather, in the procurement process, the duty of fairness is determined by the terms of the
procurement documents – in this case, the RFP. Where those documents are silent on a
particular issue or question, the courts will “imply”, or read in, such terms as they consider
reasonable to reflect the true intentions of the parties. The courts have also ruled that self-
protective language – such as that quoted above – does not entitle the owner to do whatever it
pleases with the proposals it receives.
Does The City Have Legal Obligations as a Result of Issuing the RFP and Receiving
Proposals?
The short answer is “yes”.
In 1981, the Supreme Court of Canada decided a case called Ron Engineering16
, which
fundamentally changed the bid process in the common law provinces of Canada. As a result of
Ron Engineering, when an owner institutes a procurement process with certain elements, that
owner is, in law, not only soliciting offers, but also, is making offers. The owner’s offer – to
each proponent – is to enter into a “bidding contract”, which the Court called Contract A. The
object of the procurement – in that case a building project – the Court called Contract B. The
intentions of the parties are a key factor in determining whether a contract will be entered into.
Where a procurement process does not state – one way or the other – that Contract A is intended,
the courts will usually determine that it was the intention of the parties to create the “bidding
contract”, upon the submission by proponents of responses that are compliant with the terms of
the procurement process, if that process includes the following elements:
specified closing time;
sealed submission;
identified form or contract;
bid bond to secure monetary offer made;
agreement to provide bonding, if successful;
financial offer, usually irrevocable.
A compliant response is one that is delivered on time and responds, in all material ways, to the
proposal requested by the owner. So, if the City’s RFP includes all, or most of the characteristics
of the “bidding contract” listed above, a court reviewing that process is likely to find that the
“bidding contract” came into existence between the owner and each compliant proponent.
16 The Queen (Ont.) v. Ron Engineering, [1981] 1 S.C.R. 111
City of Windsor AGO 62
MILLER THOMSON LLP - 16 -
Later in this memorandum we will address whether the City’s RFP had the necessary elements to
create the “bidding contract” between the City and proponents who submitted compliant
responses. It is important to understand, however, that if the RFP was capable of creating the
“bidding contract”, once that contract was formed by compliant responses, that contract is a real,
legally binding contract. Thus, both the City and compliant proponents would have legally
binding obligations under it.
Stated broadly, the owner’s obligations include treating all compliant proponents fairly by
following the terms of its own bid process. The proponents’ basic obligations include keeping
their proposals open for the required period, and entering into Contract B when it is awarded by
the owner; or, in the case of this RFP, entering into good faith negotiations for Contract B.
Since Ron Engineering, there has been a significant volume of new case law defining the duties
and obligations of both parties to the “bidding contract” (Contract A). In particular, there are two
additional Supreme Court of Canada decisions which bear upon most procurement processes –
including this one – once it is found that the “bidding contract” exists.
M.J.B Enterprises v. Defence Construction17
involved the interpretation and application of a
clause similar to the one quoted above in this memorandum. The clause read, more or less,
“…the lowest or any bid not necessarily accepted…”. After finding that the “bidding contract”
had arisen between the owner and each compliant bidder, the Court went on to decide that it was
an implied term of the “bidding contract” that, where there was at least one compliant bidder, the
owner had a contractual obligation to the compliant bidders not to award the contract to a non-
compliant bidder. The Court also held that because of this clause (known as a “privilege
clause”), the low compliant bidder did not have an absolute right to an award of Contract B. The
Court agreed that the owner may bypass the low compliant bidder – and rely on the privilege
clause in doing so – provided that the owner has a valid commercial reason for doing so (for
example, all compliant proposals are for prices above the owner’s budget).
The second Supreme Court of Canada decision which is useful to this analysis is Martel Building
v. The Queen 18
. In this decision the Court held that the “bidding contract” included an implied
duty on the part of the owner to treat all compliant proponents fairly and evenly.
In the Martel case, the owner breached this duty when it added a new evaluation criterion to the
procurement process after the proposals had closed. Not only did the owner add a new criterion,
it applied that criterion to Martel only. The Court held that the owner had breached its implied
duty of fairness under the “bidding contract” when it imported a new evaluation criterion (this
was unfair) and then applied it to Martel only (this was uneven). The Court went on to say that
this duty of fairness will be an implied term of every “bidding contract” unless there is a term in
the procurement documents which expressly excludes it (i.e. “the City does not intend to be
fair”). While Martel does not go quite so far as to say that in no circumstances can an owner
17 M.J.B. Enterprises Ltd. v. Defence Construction (1951) Ltd. [1999] 1 S.C.R. 619
18 Martel Building Ltd. v. R., [2000] 2 S.C.R. 860.
City of Windsor AGO 63
MILLER THOMSON LLP - 17 -
ever reserve to itself the right to be unfair, it makes it a requirement to reserve that right so
explicitly that anyone who accepts the owner’s offer to enter the “bidding contract” (by
submitting a compliant proposal) cannot complain that the owner breached the “bidding
contract” if it later treats that proponent unfairly.
There is a common public policy theme in all three cases, Ron Engineering, M.J.B. and Martel:
to protect the “integrity of the bidding system”. Over a span of two decades, different judges of
the Court have held that it is important to taxpayers of all levels of government, as well as to
private sector businesses, that the issuance of a call for tenders or of an RFP receive a positive
response from the largest possible number of motivated proponents. Prospective proponents will
be reluctant or unwilling to invest the time and money to prepare a response to an RFP unless
they have some confidence that the owner initiating the RFP will follow its own procurement
process.
Did the City’s RFP Process Create Contract A, the “Bidding Contract”?
The RFP required two separate submissions.
Stage 1
In Stage 1, proponents were required to provide information on project organization, safety,
building commissioning, schedule, quality control and related items. There was no requirement
to submit a financial offer for the 400 Building, nor any design proposal, nor any information on
how the prospective proponent might address the two options the City had in mind for the 400
Building.
Stage 1 was only to hear about the qualifications of all proponents who had responded to an
earlier request for expressions of interest. This request for qualifying responses is colloquially
referred to as a “beauty contest”. The Stage 1 portion of the RFP contained the representations
to prospective proponents that (i) all proponents’ responses would be reviewed against the
evaluation criteria in the matrix in Appendix B to the RFP, and that (ii) no more than five
proponents would be selected to proceed to Stage 2.
Our review of the submission requirements for Stage 1 shows that very few of the criteria giving
rise to the “bidding contract” were present. There is no language in Stage 1 which expresses an
intention to create the “bidding contract” upon the submission of a compliant proposal.
Accordingly, in our view, at the conclusion of Stage 1, the “bidding contract” did not arise
between the City and any of the proponents who submitted materials in response to Stage 1.
Stage 2
Stage 1 provided that only five proponents would be given the opportunity to submit the more
detailed proposal represented by Stage 2. Nonetheless, the City extended an invitation to six
City of Windsor AGO 64
MILLER THOMSON LLP - 18 -
proponents, the sixth being Vindella, even though Vindella had finished out of the top five in the
Stage 1 review19
.
Of the six proponents invited to submit proposals in Stage 2, two dropped out, and only four
submitted proposals. This suggests that there may already have been a concern on the part of the
two proponents that dropped out that submitting a detailed proposal to the City was not worth the
effort. Of the four that did respond, we have reviewed only the submissions of the two finalists,
Vindella and EllisDon. These two were the proponents whose submissions received the most
attention, with Vindella ultimately being contracted to design and build the 400 Building.
The submission requirements for Stage 2 are partly described in Stage 1 and partly described in
Stage 2. Taken together, the Stage 1 and Stage 2 submission requirements include the following
indicators of an intention to create the “bidding contract”:
identified form or contract
stipulated submission time;
price for the design and construction of the building (not irrevocable);
a bid bond;
an agreement to bond.
The form of contract is not defined in Stage 2, but the Stage 1 RFP had attached to it CCA-CSC-
RAIC Document 14-2000, an industry standard form.
As stated in Stage 1, Stage 2 provides for negotiations to occur between the City and the
preferred proponent. While this reduces the certainty that the “bidding contract” was intended, in
our view, a court would probably still conclude that the Stage 2 process was intended to create
the “bidding contract” with proponents who submitted a compliant proposal.
Were the Proposals of Either EllisDon or Vindella Compliant so as to Create the “Bidding
Contract” Between the City and One or Both of These Proponents?
The manner in which the “bidding contract” came into being in this case is not intuitively
obvious, but is the result of the legal creation of the Supreme Court of Canada in Ron
Engineering. When the City invited proponents to respond to Stage 2, it was deemed in law to
be extending an offer to the invited proponents, even though Stage 2 did not specifically say that.
The proponents would then have been deemed to accept the City’s offer to enter the “bidding
contract” by submitting a proposal that responded in all material respects to the proposal
solicited in the procurement documents. This deemed offer and acceptance was all that was
necessary to create Contract A.
19 As identified in the interview commentary. The Stage 1 RFP evaluation conducted by the Administration staff
resulted in the recommendation to go forward in the process to Stage 2 with only the top 4 proponents.
City of Windsor AGO 65
MILLER THOMSON LLP - 19 -
(i) EllisDon Proposal
There is no suggestion that the EllisDon proposal was received late. Had the proposal been
received late, the offer to enter the “bidding contract” with the “City” would have expired and
the proposal would have been non-compliant.
From a review of the materials provided by the City, it appears that EllisDon responded with
details on both option 1 and option 3 (as described in the Stage 1 RFP). As well, the proposal
included the required agreement to bond and bid bond.
The bid bond submitted by EllisDon has a term of thirty days running from the date of proposal
submission. As there was nothing in the Stage 2 RFP which required a particular term for the
bid bond, no particular term is required in order to be compliant. Similarly, the agreement to
bond submitted by EllisDon has a thirty day term. Again, there was no requirement in the RFP as
to the term of the agreement to bond.
As stated in Stage 1, the Stage 2 process provided for negotiations between the preferred
proponent and the City. Given the two options being investigated, given the size of the project
and given the complexity of the design, it is highly unlikely that EllisDon (or any other
proponent) and the City would be in a position to sign a contract within thirty days of proposal
delivery (meaning that the bid bond will probably expire prematurely). As this is a structural
shortcoming in the RFP, we do not believe that it renders the EllisDon proposal non-compliant.
So far as the City’s assessment of the technical merits of the EllisDon proposal is concerned, the
materials we have reviewed, including the “RFP Assessment Matrix”, indicate that the EllisDon
proposal was very highly rated and, at least initially, deemed significantly superior to that of
Vindella (EllisDon rating 87; Vindella rating 25).
Based on the information at our disposal, we believe the EllisDon proposal was compliant and
that it had the “bidding contract” with the City.
(i) Vindella Proposal
There is no suggestion that the Vindella proposal was late and we will assume that it, like the
other proposals, was submitted on time.
In considering the compliance of the Vindella proposal, it is important to identify the corporation
that was invited by the City to respond as a Proponent to Stage 2. In a letter dated March 15th
,
2002, that invitation was extended to “Vindella Enterprise Inc.”.
The Vindella proposal begins with an undated cover letter which reads, in part, as follows:
“The Proponent, Vindella Enterprise Inc., and its participants, Oscar Construction Company
Limited, Sterling Ridge Investments Inc., J.P. Thomson & Associates Ltd. And Martini Barile
Marusic LLP., are pleased to present for your consideration their Proposal…” [emphasis added]
Later in the same letter, Vindella acknowledges its invitation to participate in Stage 2 by making
the following statement:
City of Windsor AGO 66
MILLER THOMSON LLP - 20 -
“Needless to say, Vindella Enterprise Inc. is honoured in having been selected to submit this
Proposal…”
There is an important distinction made in the RFP between two words which sound similar –
“Proponent” and “Participant” – but have different meanings which should not be confused. In
Appendix A to the Stage 1 RFP, Section A., the prospective Proponent is required to provide a
significant amount of information about itself, its corporate history, business and experience.
Included in the information that it is to provide to the City is the following:
iv. Provide and summarize the legal agreements which describe the relationship between the
Proponent and any Participants.
In its Stage 1 Proposal at Tab A, Vindella responded to the required information about itself, as
Proponent. It then included, at Tab A, section iv., a list of Participants who would be part of its
team. Four Participants were listed, including Oscar Construction Company Limited. Of its
team, Vindella included the following statement:
“Vindella Enterprise Inc. has worked in the past as a team player with the other Participants noted
herein (as is noted in the examples of similar developments listed below) to ensure the
requirements and objectives of the occupants of the development are always achieved. The
combination of Vindella Enterprise Inc. as the project developer/manager and Oscar Construction
Company Limited as the general contractor has been a recipe of success within the County of
Essex for years.”
Vindella goes on to give a more complete profile of each of the four Participants.
It is clear that both the City and Vindella intended a distinction between the Proponent and a
Participant. The Proponent is the contracting party. The Participants are those who will support
the Proponent in carrying out the Project.
In the financial portion of its proposal, Vindella submits a bid bond which is in the amount
required by Stage 2 – 10% of its price. However, the bid bond has two deficiencies, one minor,
the other major.
First, as stated in Stage 1, the Stage 2 RFP requires that the bid bond be in the form of a standard
document, “CCDC220”. The bid bond is not in the form CCDC220. While the bid bond is not on
standard form CCDC220, its terms are substantially similar, and therefore this deficiency is one
of form, not substance. For that reason it is excusable. (The term of the bond is sixty days and
hence it would also have expired before any contract was signed – as was the case with
EllisDon).
Second, the bid bond, rather than supporting the Proponent, Vindella, alone, supports both
Vindella and Oscar Construction Company Limited, a Participant. In the bid bond, these two
companies are defined, jointly, as “Principal”. The issue of who is the “Principal” is more
fundamental, and goes beyond mere form. If the Proposal from Vindella is in fact a proposal
from a joint venture including Oscar, then the proposal is non-compliant because Oscar did not
participate in Stage 1 as a Proponent and the City’s invitation to participate in Stage 2 as a
Proponent was extended to Vindella only. On the other hand, if only Vindella had made the
proposal, then the bid bond would be supporting a proposal by a joint venture between Vindella
and Oscar – a proposal that was not submitted. The agreement to bond has the same problem as
City of Windsor AGO 67
MILLER THOMSON LLP - 21 -
the bid bond – it represents the agreement of the surety company to issue bonding jointly to
Vindella and Oscar. In our view, neither the bid bond nor the agreement to bond are compliant
with the Stage 2 RFP.
It is difficult for us, as lawyers, to form any independent opinion on whether the proposal
received from Vindella/Oscar was also non-compliant in its failure to meet the technical
requirements of the Stage 2 RFP. We do know that the proposal was extensively criticized by
City staff in numerous memoranda and emails saying that it had failed to address certain key
issues set out in the RFP as requirements, or had addressed them so superficially as to be
unsatisfactory. The City Solicitor also criticized it, at one point in time, as being ambiguous in
the sense that the written text of the proposal and the drawings were inconsistent, making it
impossible to determine which was the “real” proposal. We understand that his concern was
subsequently resolved, however that may have been because the Vindella proposal was
significantly changed. Four sets of very specific questions were sent to Vindella seeking to fill
these gaps, and Vindella submitted a significant amount of additional data to augment its initial
proposal. So, the Vindella submission may also have been non-compliant because it was
seriously deficient in failing to provide the design, construction and pricing proposal required by
the Stage 2 RFP. If that was the case, then the specific questions addressed to Vindella were
more than merely questions seeking clarification of what was already in the proposal. They were
really questions, the answers to which could be considered “nursing” Vindella into appearing to
be compliant by inviting Vindella to complete and improve its proposal, long after the deadline
for submitting complete and compliant proposals had passed.
Given the Nature of the RFP, What Are the Obligations of the City?
(i) Stage 1
As indicated above, Stage 1 of the RFP did not have the ingredients to create the “bidding
contract” between the City and proponents who submitted compliant proposals. While this
means that the City had no contractual obligations to any of the proponents at that stage, it still
does not mean it was free to do whatever it pleased.
In Mellco Developments Ltd. v. Portage la Prairie (City)20
, the Manitoba Court of Appeal dealt
with a request for proposal process run by that City respecting the sale and development of
certain municipal land. An unsuccessful proponent sued the City on the basis that the request for
proposal created a “bidding contract” between the proponent and the City upon submission of the
proponent’s proposal. The plaintiff contended that the City had breached the “bidding contract”,
entitling the disappointed proponent to damages.
The Court held that the request for proposal was never intended to create the “bidding contract”
(and actually expressed the intention not to enter a contract) and dismissed that aspect of the
case. The Court went on to comment on the obligations of an owner that has created a request
for proposal process that does not create the “bidding contract”. The Court concluded that the
20 [2001] 11 W.W.R. 282, Aff’d 222 D.L.R. (4
th) 67 (Man. C.A.)
City of Windsor AGO 68
MILLER THOMSON LLP - 22 -
City had an obligation to conduct itself fairly and in good faith when running its procurement
process. Otherwise, proponents would incur significant expenses, become disillusioned over
futile proposals and cease to participate in future procurements.
Our sense is that this obligation of fairness described in the Mellco Developments case is not
limited to Manitoba, but would, in Ontario as well, be held to be an obligation of the City – in
this process – to follow its own process when carrying out Stage 1.
(ii) Stage 2
By the time the proponents submit their Stage 2 proposals, they have been through a request for
expressions of interest and a Stage 1 evaluation/pre-qualification. What these earlier processes
mean to Stage 2 is that the City is satisfied that any of the six proponents invited to submit a
Stage 2 proposal would be satisfactory to the City if they met the evaluation criteria set out in
Stage 2. The Stage 2 evaluation criteria include an assessment of the design and financial
solutions proposed for the two options described by the City. In effect, the two processes that
preceded Stage 2 narrow the City’s scope for evaluation. In some respects, this means that the
outcome of the evaluation process – using the “R.F.P. Assessment Matrix” should have been
determinative of the outcome unless some extraordinary and unanticipated circumstances
occurred.
As indicated earlier, Stage 2 includes the ingredients to create the “bidding contract” with
proponents who submitted a compliant proposal. The “bidding contract” requires the City to
treat all compliant proponents fairly and either to select a preferred proponent or to cancel the
entire process, all in keeping with the terms of the RFP. This means that the City cannot import
new evaluation criteria into the evaluation process. Neither can it decide – after proposals have
been submitted – not to comply, or not to require proponents to comply with the terms of the
“bidding contract” (for example, to accept a proposal from a proponent not invited to participate
in Stage 2).
In the M.J.B. case discussed earlier, the Court held that the “bidding contract” includes an
implied term that an owner will not award the ultimate contract (Contract B) to a non-compliant
proponent where it has the “bidding contract” with at least one proponent. In this RFP, the duty
of the City to a compliant proponent is to refrain from selecting a non-compliant proponent as
the preferred proponent.
Earlier in this memorandum we mentioned the Martel case which established – at the Supreme
Court of Canada level – that the “bidding contract” includes an implied duty on the part of the
owner to treat all compliant bidders fairly (unless there is a specific term in the procurement
documents negating that obligation). There is no such specific term in the Stage 2 RFP. So, in
this case, the City would treat a compliant proponent unfairly were it to change the evaluation
criteria set out in the RFP after the deadline for the submission of proposals.
(iii) Summary of RFP Obligations
The City had duties to the proponents in Stage 1. It was open to any of the five highest ranking
proponents to complain to the City that a sixth proponent was added to the process. The City
City of Windsor AGO 69
MILLER THOMSON LLP - 23 -
could have avoided the risk of such a complaint by issuing an addendum and amending the Stage
1 RFP as to the number of invitations that would be extended.
With respect to Stage 2, we believe that the proposal from EllisDon was compliant, creating the
“bidding contract” between it and the City. The City had developed an “RFP Assessment
Matrix” for use in the evaluation process. This matrix was not in the original Stage 2 RFP, but
was issued to the proponents by letter on April 19th
, 2002. It is reasonable to treat this letter as
effectively amending Stage 2 by adding the matrix as the evaluation methodology. The
implication of the matrix becoming part of the RFP was that the highest ranked proponent on the
matrix would become the preferred proponent, and would be given the first opportunity to
negotiate a contract with the City.
It appears that the City – perhaps inadvertently – breached its “bidding contract” obligations by
(i) accepting a bid bond and an agreement to bond from a party other than just Vindella, (ii)
permitting it to amend its possibly non-compliant proposal (through four sets of questions and
answers), (iii) by ignoring the scores on the matrix and by considering the selection of the
preferred proponent using a single criterion – initial cost – not disclosed in the Stage 2 RFP.
This new criterion is evidenced by a City In Camera report of August 21st, 2002 which concludes
with the following:
“Based on the documentation provided by the proponents, the EllisDon proposal is the preferred
option if the building’s attributes and long-term operating costs are the predominant criteria for
judging whether to risk investing in this building as a municipal asset, while the Vindella proposal
is the preferred option if building price is predominant judgment criterion.”
The Councillors on the selection committee acted as if they believed that they could,
individually, do whatever they wanted in selecting the successful proponent, including ignoring
the result of applying the matrix table, and applying different criteria. This apparent belief was
based on the theory that there were enough “weasel words” in the RFP to provide them with
such unlimited discretion. This belief was incorrect. Therefore, any action taken upon it was
without legal foundation. It amounts to changing the rules of the game in the middle of the
game, which amounts to attempting to amend a contract without first obtaining the agreement of
the other party to the contract.
Assuming Vindella’s Proposal Was Compliant, Was EllisDon Treated Fairly in the
Evaluation?
Earlier in this memorandum we concluded that the Vindella proposal was non-compliant because
of the bid bond issue. In this section, we give Vindella the benefit of the doubt and examine the
way in which the City did its comparative evaluation of the Vindella proposal and the EllisDon
proposal.
The way the RFP process was handled makes it difficult to determine when the City closed the
competition and declared a winner. The actual sequence of events can be summarized in the
following steps:
City of Windsor AGO 70
MILLER THOMSON LLP - 24 -
1. After the matrix had been applied at Stage 221
, around May 17, 2002, EllisDon
was the clear leader, as shown in the table below.
Proponent Total Weighted Score
EllisDon 87
Mady 60
MKT 55 (arithmetic corrected)
Vindella 25
2. The Vindella proposal appeared to have the lowest immediate capital cost,
although no analysis was done to determine whether this initial appearance would be sustained
through the lifecycle of the building by taking into account the differences in maintenance and
operating cost resulting from the various different buildings proposed. Nevertheless, and despite
the opposition of the City staff, the Councillors, believing that they had the sole authority to
make decisions about the RFP process at this stage, decided to put the Vindella proposal into
competition with the EllisDon proposal. As well, City staff found that the Vindella proposal was
vague on a number of important specifics, so that the apparently low price could not be
definitively tied to design details indicating what was to be provided at that price. While such an
inconsistency would normally result in a finding that the proposal was noncompliant, and
therefore ineligible to proceed further, Vindella was given the opportunity to amend/rectify its
proposal22
.
The first round of proponent interviews and written questions were held with the 4 proponents on
June 20, 2002. Once narrowed to 2 proponents, interviews were conducted and questions were
asked on August 2, 2002. Thereafter, the first subsequent round of written questions was dated
August 8, 2002.
The first four written questions to Vindella were seeking information to fill in the gaps (material
deficiencies) in its proposal, thereby inviting Vindella to revise its proposal, and showing
Vindella how to revise it:
1. Please resubmit your elevations on page 21 & 22 of your submission and detail all
exterior material finishes.
21 The matrix result was never publicly disclosed. It was attached to the May 17, 2002 and July 18, 2002 in-
camera Council reports. EllisDon obtained a copy, likely through filing a formal request under the Municipal
Freedom of Information and Protection of Privacy Act. 22
The September 4, 2002 Report to Council on September 11, 2002 stated:
“During the [RFP] interview process Vindella presented the City of Windsor an additional option consolidating the
office and parking structure all on the single site to the east of City Hall. The option presented by Vindella resulted
in a revised price of $22,532,791. Members of Council on the working committee directed administration to
conduct a comprehensive financial review of all proposals and report back to Council with the findings of the
review.”
City of Windsor AGO 71
MILLER THOMSON LLP - 25 -
2. Please resubmit plans on pages 14 to 19 inclusive indicating square footages for each
individually labelled space. Please include a plan for the provision of a second
underground floor of parking and provide your revised quoted total price.
3. Please provide an outline specification of exterior finishes identified in the requested
resubmitted elevation drawings referred to above.
4. Please provide an outline specification identifying the buildings structural systems.”
Also, Vindella was provided with the opportunity to give the City an additional option, as
described in footnote 22, above. This occurred some time between the May 17, 2002 and July
18, 2002 in-camera Council reports, and likely happened on June 20, 2002, when the four
proponents were interviewed.
On August 1, 2002, EllisDon was asked, “What cost savings might be available for the City to
consider which do not impact the value and sustainability of the design?”. That is quite a
different question. It asks EllisDon to suggest building substantially the same building as it had
designed, but for less money. It is really just a request to offer a discount from the proposed
price. It does not request a change in design to meet a target price.
3. However, Stage 2 does not contemplate amendments to proposals after closing.
Giving either Vindella or EllisDon the chance to amend would represent amending the rules on
the fly, after closing, which is a breach of the implied duty of the owner to treat all compliant
proponents fairly and evenly.
4. Only Vindella was encouraged/permitted to amend its design, and to re-price its
proposal based on a different design. It is not clear that Council knew that Vindella – contrary to
the RFP – had been given this opportunity. Council may also have been unaware that
negotiations that were proceeding at the same time with both EllisDon and Vindella were
inconsistent with the RFP Stage 1 stated intention to negotiate with one proponent.
5. The Committee’s recommendation to Council placed a great deal of weight on the
factor of the “risk” inherent in each proposal. Risk analysis can be a useful contribution to RFP
analysis, and therefore, is to be encouraged. However, it must be a complete analysis. Council
would have been left with the impression that EllisDon was riskier than Vindella. And which
municipal Council would not want to reduce risk, or avoid it entirely? Yet the recommendation
does not use the ordinary meaning of the word “risk”, but rather, “risk” was narrowly and
specially defined as meaning only the risk that the annual impact of the proposal on the City’s
operating budget would be greater than zero. This risk analysis was potentially misleading to
Council in that (i) other, potentially much greater material risks were not taken into account at
the same time and in the same analysis; and (ii) the number provided actually represented only
one thing, speculative space rent, the amount of which was hypothetical and speculative in both
cases. As well, the relatively minor dollar value of the difference in budget increase risk
between the two proposals was not compared with the overall magnitude of the project – a
comparison that would have shown that any difference in such narrowly defined, speculative risk
estimate was trivial and unlikely to be meaningful, given the far greater risk that either proponent
would come in over budget, or that the project would require spending on “extras” that would
swamp any minor difference in forecasting at the pre-construction stage.
City of Windsor AGO 72
MILLER THOMSON LLP - 26 -
6. In the earlier reports to Council, the Vindella proposal was shown as having a
lower risk than the EllisDon proposal, thereby suggesting that prudence and safety lay with
accepting the Vindella proposal. In the final report to Council, the September 4, 2002 Council
Report for the September 11, 2002 Council meeting, which led to the decision of Council as to
which proponent to choose, the final risk calculation was entirely omitted. Had it been included,
and calculated in the same manner as before, it would have shown that the EllisDon proposal
actually had the lower risk of increasing the annual operating budget. According to the City’s
Auditor General Staff, if this calculation had been done at this time, in a manner consistent with
the July 18, 2002 and August 21, 2002 in-camera Council reports, the final numbers would be
Vindella = $642,060 and EllisDon = $595,500. The lower number had in previous reports been
treated as identifying the less risky proposal, and therefore, EllisDon would have been presented
as less risky than Vindella. We have been unable to obtain any explanation as to why this
calculation was presented in two earlier reports but not in this report, and therefore, cannot
determine whether the omission was inadvertent or intentional. In any event, Council was not
informed, prior to its decision on the selection of the winning proposal, of even the limited risk
analysis conducted, showing EllisDon as having the less risky proposal.
There is also the matter of the City’s existing purchasing By-Law, By-Law 9-2000. In some
procurement processes the purchasing policy or By-Law is incorporated by reference into the
procurement and becomes part of the “bidding contract”. We have not been able to find any
language which clearly imports the purchasing By-Law into the RFP. That is not to say that the
By-Law would not have a bearing on the outcome of litigation, were litigation to occur. The
court is likely to take the By-Law into consideration when determining how the duty of fairness
might be articulated where the City is involved. The By-Law might also have the effect of
negating some of the discretion described in Stage 1 (and carried over into Stage 2). For
example, if the By-Law said that the City always awards contracts to the low compliant bidder,
then that aspect of the policy might make it easy for the low compliant bidder to prove that, but
for the breaches of the “bidding contract” by the City, it was entitled to receive the contract. A
detailed analysis of the City’s two purchasing By-Laws is provided below.
What is the Exposure of a Party Like the City Upon Breach of its Obligations Under the
“Bidding Contract”?
The “bidding contract” is a real contract. The fact that the contract is implied by a court rather
than written by the parties themselves does not make it any less binding a contract. A party that
breaches its contract is exposed to an award against it of contract level damages. A concise
statement of damages for breach of contract is found in the Supreme Court of Canada decision in
BG Checo International Limited v. B.C. Hydro and Power Authority23
: a successful plaintiff in a
claim for breach of contract is to be put in the position it would have occupied had the contract
been performed as agreed.
23 [1993] 1 S.C.R. 12.
City of Windsor AGO 73
MILLER THOMSON LLP - 27 -
A breach of the “bidding contract” by an owner can result in an award to the contractor ranging
from zero damages to the profit it was likely to have enjoyed had it been awarded the project for
which it was competing.
Were EllisDon to sue the City for breach of the “bidding contract”, it would be entitled to
recover the overhead and profit it would have earned had it been awarded the 400 Building
contract, provided that it can establish the following:
that, but for the breach of the “bidding contract” by the City, it would have been
awarded the contract;
that the amounts estimated for the recovery of overhead and profit were
reasonable;
that there was nothing in the conduct of the project to suggest that the amount
carried by EllisDon for overhead and profit should be discounted.
Faced with this kind of case, a court must first determine whether EllisDon would have been
successful in obtaining the contract at all. The RFP Stage 2 process called for negotiation and it
is quite possible that the negotiation could have proven unfruitful. So, the first hurdle which
EllisDon would have to clear has some difficulty, as it requires the court to speculate as to the
outcome of a negotiation process. However, EllisDon might be able to persuade the court, with
the assistance of expert evidence, that the outcome in most RFP processes is that the first ranked
proponent is given the contract, and therefore, on a balance of probabilities, that would have
been the likely outcome. Nevertheless, EllisDon may have to explain away the possibility that
the City could invoke the broad discretion clause described in Stage 1 to cancel the process or,
for good reason, could award the contract to someone other than EllisDon.
If EllisDon clears the first hurdle and proves that, but for the breach of the “bidding contract”, it
would have been the victor, it will still have to convince a court that its estimate of overhead and
profit was reasonable and that there were no factors that would have made the job more difficult
or expensive to complete. For example, if Vindella – in the course of carrying out the 400
Building – had encountered problems with buried telecommunications facilities that had to be
moved, or found adverse soil conditions that would also have affected EllisDon and that cost
Vindella money, that circumstance may cause the court to discount any award it was
contemplating to make to EllisDon.
Speaking generally, however, on a project with a construction value of approximately
$25,000,000, the hypothetical EllisDon recovery could easily be in the low millions.
The events giving rise to these issues happened in mid 2002. By October 30th
, 2002, EllisDon
was on record as complaining to the then-Mayor that it had been treated unfairly and that if it so
chose, it could successfully prosecute an action against the City for breach of the “bidding
contract”.
On January 1st, 2004, Ontario’s new Limitations Act, 2002 came into effect. This new Act
stipulated that a party who became aware of an act or omission giving rise to a claim must start
litigation within the two years following the date it knew or should have known of its claim. This
applies to claims discovered after January 1st, 2004. The predecessor to the Limitations Act, 2002
City of Windsor AGO 74
MILLER THOMSON LLP - 28 -
allowed a six year period after discovery of a claim within which a party had to begin litigation.
In this case, the former Act would apply and EllisDon is subject to a six year limitation period.
Unless there is something we do not know, any claim by EllisDon for a breach of the “bidding
contract” expired six years after its recognition that it had a claim. At some point prior to
October 30th
, 2002 – when EllisDon wrote to the then-Mayor – it recognized it had a claim. We
believe any claim which EllisDon might be able to make on this RFP is now, in all likelihood,
statute barred as being beyond the limitation period.
How Might the City Minimize its Exposure on Future RFP’s?
Implementation of the following steps will improve the City’s procurement process and, at the
same time, help avoid exposure to litigation:
(i) Understand Procurement Law
It is now 2009 and many lessons may have been learned from the RFP of 2002. Nonetheless, we
recommend that procurement staff be exposed to seminars and materials which will acquaint
them with the implications of a process that creates the “bidding contract” and the duties and
obligations that flow, even from a process that does not create a “bidding contract”.
(ii) Process Selection
The City – like any other owner – is able, under the law, of convening a competitive
procurement process without employing the “bidding contract” to do so.
When a procurement process for a significant expenditure is being planned, it would be prudent
for the City to ask itself whether this process should be one which includes the ingredients that
will create the “bidding contract” (and say so) or not. If the City elects a process that does not
create the “bidding contract”, it still has a broad obligation – one which the courts have
expressed as an obligation of fairness – to follow the process which its own documents describe.
(iii) Preparing the Procurement Documents
The procurement documents – whether they create the “bidding contract” or not – should state
the intention of the City clearly, ideally at the beginning of the document. For example, a
paragraph expressing the intention of the City might read:
“The City does not intend to create any contractual obligations (sometimes referred to as a bidding
contract or Contract A) with any proponent by virtue of issuing this RFP and/or by receiving
and/or by evaluating the proposal received from any vendor. In no event shall the City be
responsible for any costs incurred by any vendor and/or its affiliates in the preparation and
submission of a proposal or further participation in the RFP process.”
Although the vast majority of any procurement document should be directed toward the object of
the procurement, it is important that the elements of the procurement document which describe
the process be carefully prepared so that the legal implications – “bidding contract” or not – are
properly set out. For example, words like “may” and “shall” need to be used carefully as they
City of Windsor AGO 75
MILLER THOMSON LLP - 29 -
can fundamentally alter the nature of the process and restrict or enlarge the discretion of the City
– discretion being an important tool.
It would be helpful to the City if it established model documents for its bid processes and for its
true request for proposal so that the process elements are constructed with the needs and
obligations of the City in mind, while risk is controlled.
(iv) Special Clauses
If the “bidding contract” is to be utilized in a procurement, there are clauses that can be added
which reduce the risk to the City and to the proponents in the event of a breach of the “bidding
contract”. For example, courts in Canada have approved the use of limitation of liability clauses
which, if properly employed, reduce the incentive to a wronged party to commence litigation.
Another useful clause is an alternative dispute resolution provision which gives the right to the
City only to convene an arbitration with a disgruntled proponent and thereby head off litigation
over the terms of the “bidding contract”.
These are but two examples of clauses that can lower the risk of litigation arising out of
procurement processes. There are other clauses now being used in procurement processes which
provide considerable flexibility to the owner while still observing and respecting the implied
duty of fairness.
(v) Resisting Temptation
In many procurement processes the most carefully prepared procurement documents cannot
anticipate everything. Often an owner will find itself in the position where the best result to it is
not the result that the procurement documents – properly applied – will produce.
If recommendation (iii) is followed, the City will have a good deal of flexibility in dealing with
the evaluation. But, if it is necessary for the City to change the evaluation criteria after the
submission of proposals, claims are a likely result.
As trite as it sounds, the City staff and any Councillors involved in procurement have to learn to
resist the temptation to force a particular outcome of a procurement process when the process, if
properly followed, would produce a different outcome.
(vi) Local Preference
It appears from our review of the materials that the 400 Building evaluation and selection
process were influenced by the lack of a local proponent among those to be invited to make the
Stage 2 proposal. Purely on merit, it appears that Vindella would not have been invited to
participate in Stage 2.
Although there are some restraints on the degree to which local preferences can be included in
procurement documents (the Agreement On Internal Trade being one restraint) there is some
room for preferring local content. However, experience has suggested to us that local preferences
do not achieve better procurement outcomes for taxpayers.
City of Windsor AGO 76
MILLER THOMSON LLP - 30 -
Many owners who have used local preferences have discovered that, once local vendors learn
that there is a local preference policy, whether written or unwritten, their incentive to be
competitive is reduced. At the same time, outside vendors learning of a local preference are less
likely to submit proposals, as they do not believe the playing field is level. So, while it may not
be politically attractive in the short run, our advice is to resist the temptation to employ local
preferences in the City’s procurement processes. Of course, using a local preference in the
evaluation process when none has been written into the procurement documents is a breach of
the “bidding contract” because it is – among other things – unfair.
III. THE REQUIREMENTS OF THE PURCHASING BY-LAWS
There are two successive purchasing By-Laws that were in force during the relevant time period
for the project. Both of them had as a common feature the delegation of all procurement
responsibility to various management levels of the City staff, with no role contemplated for
individual Councillors.
There were, in both By-Laws, dollar thresholds above which staff could not enter into an
agreement to purchase without Council approval. There was nothing in either By-Law that would
even suggest that the process of obtaining such above-threshold approval could involve Council
members. In other words, the general rule was and still is that the entire procurement process is
to be administrative and apolitical. This apolitical principle also covers the process of obtaining
approval for above-threshold procurements, in the sense that the staff would make an apolitical,
administrative recommendation for approval of the expenditure. What Council did with that
recommendation was another matter. That was the Council process, which would be expected to
be political.
By-Law 9-200024
The very first numbered paragraph of this By-Law states that:
1. The civic administration is authorized to deal with all contracts for purchases of goods,
services and equipment at a price not exceeding the preauthorized expenditure limit referred to in
Section 2 herein and in conformity with the procedures set out in Schedule “A”…
The dollar threshold for requiring Council approval was $100,000.
This is a clear delegation of power to the civic administration over all procurement contracts, and
this delegation is reinforced by other parts of this By-Law and its Schedule “A”, which forms
part of it.
For example, section 2.4 (1) (c) of Schedule “A” states:
24 Passed and effective January 4, 2000, this By-Law was in force until By-Law 400-2004 was passed and
effective on December 13, 2004.
City of Windsor AGO 77
MILLER THOMSON LLP - 31 -
All goods, equipment or services shall be purchased only by the Purchasing Manager or designate
upon authority of a resolution of Council and/or a written and properly authorized requisition
within the limits and conditions set out.
Paragraph 3 of the By-Law specifically authorizes the CAO to make policies respecting
procedures for the opening, evaluation and recommendation of tenders and proposals.
With respect to construction projects in particular, section 8.6 (1) (f) states that the Purchasing
Manager must reject any bid which contains a major irregularity. “Major irregularity” is a
defined term:
… a deviation from the bid request which affects the price, quality, quantity or delivery and is
material to the award.
“Minor irregularity” is also a defined term, meaning a deviation from the bid request which
affects form rather than substance. Thus, a deviation from the bid request can be permitted if
and only if it is both immaterial to the award and one of form rather than substance.
The subsection specifically acknowledges that if a deviation that is material and of substance
were to be permitted, the bidder could gain an unfair advantage over competitors. The
Purchasing Manager is required by the By-Law to reject such a deviating bid or proposal, to
prevent such unfair advantage. As that is the duty of the Purchasing Manager, if three
Councillors assume his duties in procurement for a project (whether validly or invalidly), the
duty of fairness to all proponents imposed upon them is the same.
The RFP does not specifically incorporate the purchasing By-Law. In law, therefore, the By-Law
has not been made a term of Contract A. However, the Courts may still examine the By-Law to
determine how the City might have behaved under certain circumstances. For example, if the By-
Law provides that the City always awards contracts to the low compliant proponent, then, had
EllisDon sued, it may have used this By-Law provision to help it prove that, but for the breach of
Contract A, it would have been the proponent involved in negotiations for the project. Since the
By-Law is not specifically adopted in the RFP, it will not have the effect of providing By-Law
guidance as to what is and is not a compliant proposal.
By-Law 400-2004
This new purchasing By-Law is much lengthier and more detailed than the one it replaced. It
was not in force at the time the decisions were made regarding the 400 Building, but remains in
force now, and thus, is important for future procurements.
It also contains a number of provisions which could be interpreted as attempting to give the City
the right to treat proponents unfairly. If these very broad provisions were to be tested in a court
of law, in the absence of the appropriate language in an RFP to give the City such rights, the
court would probably treat them as merely unenforceable verbiage.
If there is a pre-defined evaluation plan, made public as part of the RFP process (as there was in
this case) then that is part of the offer made by the City to proponents, and becomes part of the
“bidding contract” when the offer is accepted through the submission of a compliant proposal.
City of Windsor AGO 78
MILLER THOMSON LLP - 32 -
The Purchasing Principles defined in Part III of the new By-Law state, in subsection 5 (1), that
General Managers and Department Heads have the responsibility for the oversight of all
purchasing activities within their department(s) and are accountable for achieving Best Value
while following the purchasing principles of this By-Law. Obviously, they cannot be held
accountable for achieving Best Value if they are, in future, prevented by individual Councillors
from selecting the proposal that, in their opinion, represents that Best Value. Subsection 5 (2) (a)
delegates authority to the Manager of Purchasing and Risk Management to act as the legal
purchasing agent for the City, under the direction and supervision of the City Solicitor. Nowhere
does the purchasing By-Law say that the person occupying this position may be placed under the
direction and supervision of three members of Council appointed to an ad hoc committee.
Section 16 deals specifically with requests for proposals. Subsection (6) requires the Purchasing
and Risk Management Division to maintain a list of suggested Evaluation Criteria for assistance
in formulating an evaluation process when there is an RFP. Subsection 8 then states that an
“Evaluation Committee” composed of a minimum of two representatives from the department...
shall review all proposals against the established criteria and reach consensus on the final rating
results. Unfortunately, the By-Law does not say explicitly what is to be done with those final
rating results. Presumably, however, the intention is that the Evaluation Committee, having used
the Evaluation Criteria and arrived at a consensus as to Best Value, would ensure that the
proponent offering the Best Value was chosen as the successful one. Otherwise, all of this
careful process of evaluation would be a meaningless exercise in keeping up public appearances,
which would be inconsistent with the ethical considerations set out in section 9 of the By-Law.
Section 9 requires:
(i) open and honest dealings with everyone who is involved in the purchasing process;
(ii) fair and impartial award recommendations for all contracts and tenders, without extending
preferential treatment to any vendor including local companies25
; and
(iii) an irreproachable standard of personal integrity on the part of all of those designated as
purchasing agents...”.
It is important to note that neither the old purchasing By-Law nor the new one contemplates any
role in the procurement process for individual Councillors. The appointment of Councillors to
an Evaluation Committee is neither specifically permitted nor specifically prohibited by the By-
Law. This gives rise to two related questions: is it permissible to appoint Councillors to such a
committee; and, if so, what role or function can such Councillors lawfully play on such a
committee, consistent with the other requirements of the By-Law. In answering these questions,
it is safe to assume that the role of Councillors cannot be broader than the role of Council itself.
Council cannot delegate to individual Councillors power it does not have itself because it has
already delegated such powers to City managers.
25 Section 55 also explicitly prohibits granting preference to local suppliers. Vindella was a local supplier and was
granted preference.
City of Windsor AGO 79
MILLER THOMSON LLP - 33 -
The role of Council itself in the procurement process is limited to approving purchases with a
price in excess of $150,000 (in the new By-Law) and $100,000 (in the old By-Law).
Presumably, this approval process was not limited to being a mere rubber stamp, but would
include the right to determine, subject to the legal constraints of fairness and of consistency with
the RFP, whether the successful proponent chosen by the Evaluation Committee should or
should not be awarded Contract B.
The right to review and approve purchases in excess of a certain price does not mean, however,
that Council, having delegated the entire evaluation process to the staff in a By-Law, could
simply redo the entire evaluation process and select another proponent as the winner, using
criteria other than those which were publicly offered to proponents at the RFP stage, or using the
same criteria but with different weights. Similarly, it does not mean that Council could delegate
to three Councillors the task of redoing the entire evaluation process and selecting another
proponent as the winner. Such a re-selection would be inconsistent with the inclusion of the
requirements for “Openness and Transparency” and “Accountability” in subsection 10 (1) of the
new purchasing By-Law.
Do three Councillors appointed to an Evaluation Committee (that is not a committee of Council)
have the authority to overrule a By-Law, or to waive its normal operation, or to dictate a decision
to the Purchasing Manager that may be inconsistent with his duty under the By-Law? The
question must be given careful consideration.
The Canadian legal system, like that in all democracies, is marked by the constitutional
requirement that everyone in government must act in accordance with the “rule of law”. This
means that the law applies equally to everyone, and that everyone is equally obligated to comply
with the law. The courts will not accept the argument that the English monarchs used to make
centuries ago: “the laws do not apply to me because I make the laws”. Yet there may be a
belief, even today, that the civic administration may be bound by the purchasing By-Law, but
Council is not, and by extension, individual Council members are not. A moment’s reflection
demonstrates that this is a serious misconception.
Although the Provincial Legislature enacted the Highway Traffic Act, the Premier, all the
members of the Cabinet, all the members of the judiciary and all the members of the public
service of the Province have to comply with the speed limits on provincial highways. The law
applies equally to everyone. Whenever any legislative body – whether Parliament, the
Provincial Legislature or a municipal council – makes a law or By-Law, this law is binding on
everyone. If the intention is not to make it binding on someone, either generally or for a specific
set of circumstances, then that intention must be expressed clearly in the law itself. If that is not
done, the presumption is that the law was intended to apply to everyone.
Had Council so intended, it could have amended the purchasing By-Law specifically for the 400
Building. Legally, this could have been done through a special exception to the purchasing By-
Law. The exception would have had to be created through a By-Law amendment specifically for
the particular project. This amendment would, among other things, have defined the roles of the
staff and Council members of the Committee created for the project. When the building was
completed (or earlier, when the design was completed, if the need for the Councillors to be
involved in the procurement process had passed) the amendment could be revoked, again, by
City of Windsor AGO 80
MILLER THOMSON LLP - 34 -
Council enacting a further amendment to the purchasing By-Law. However, Council did not do
this in this particular case, and therefore, the power and authority it had delegated in the By-Law
to staff remained in force.
4009480.1
City of Windsor AGO 81
5.4 Phase 4 – “Price” Financial Analysis Discussion and Report Findings
Phase 4 – Detailed
discussion and
analysis.
Phase 4 – “Price” represents a change in direction from the Purchasing By-Law approved
process, an abandonment of The RFP Assessment matrix represented to proponents as being
the criteria for final selection to a new and previously undisclosed criterion, Price. Price,
which ultimately became the deciding factor, came from a brief and inadequate financial
analysis. It then led to the creation of simultaneous negotiations with the highest ranking
proponent in the RFP Assessment Matrix with another proponent who led the new “lowest
price” criterion:
In other words, The City switched to the use of considerations outside of the publicly
announced evaluation matrix to decide the award of the RFP Contract and outside of the
Purchasing By-Law. As a result of this change in decision criterion, many errors followed.
The issues of Phase 4, “Price” include discussion around two main topics,
5.4.1 The Working Environment of the RFP Evaluation Committee
5.4.2 The “Price” Financial Analysis and Information Reported to
Council for Decision Making Purposes
5.4.1 The Working Environment of the RFP Evaluation Committee
Pages 5 – 14 of the
legal memorandum
(Appendix A)
contain a detailed
legal analysis
regarding the
overall governance
structure of the City,
including the impact
it had on the project,
the City, City Staff
and Council as a
whole.
Finding 2.
The vague Council motion that approved the creation of the ad-hoc procurement committee
and the absence of an adequate, approved business case resulted in a division between the
Councillors and the Administration responsible for recommending the preferred proponent
for the award of the Design / Build Contract. The division was not contained within that
group, but extended to other Administration involved on the project and reporting to
Council. 13
a) The division was evident in the project reports to Council in July, August and
September of 2002. Due to significant concerns over the MFP procurement scandal
and the City’s 2002 debt load, the Council members on the committee, supported by
some Administration external of the committee were running the selection process
on “lowest price” and members of Administration on the committee were
committed to the RFP matrix (Purchasing By-Law).
13
Direct evidence which would reveal the identity of individuals will be held confidential by the Auditor General’s Office.
City of Windsor AGO 82
b) Between January 2002 and September 2002, members of junior Administration
brought concerns to the attention of some senior Administration and the message
reached the then-CAO regarding the City’s own departures from the announced
RFP process as represented to the prospective proponents.
c) Ultimately, the project environment became adverse. There are multiple project
documents and interview comments that strongly support our finding that the
working environment for certain members of Administration became one of
frustration and intimidation. Commendably, under the pressures of this
environment, some junior members of Administration showed significant strength
and resolve through repeated attempts to have the City return to fidelity to the RFP
process and the Purchasing By-Law.
d) Serious communication issues ensued. Project documentation and correspondence
among all levels of Administration through to February of 2004 shows that the
division continued even after the award of the RFP. This documentation shows that
some members of senior Administration, including the then-CAO were aware of the
problems and the expressed legal concerns with deviating from the RFP process.
e) The concerns about going offside legally reached the level of the then-CAO.
However, through the lack of documentation or comment support, it remains
unclear whether the then-CAO ever apprised the Councillors on the ad-hoc
procurement committee, or apprised Council as a whole, of the dangers of selecting
the final proponent without compliance with the applicable procurement rules.
About the Divide in the RFP Evaluation Committee
The issues of the
divide, as outlined
in the finding, are
discussed in detail
in Appendix A.
Here, we focus on
the how and why the
divide happened.
5.4.1 a) About The Division
The legal memorandum (Appendix A) goes into detail regarding the structural and
communications problems within the project organization structure. In addition to providing
supplemental support for the legal memorandum discussion, this section provides an
opportunity to emphasize how a solid business case, based on a good project management
methodology, would have assisted in avoiding some of the legal and other issues that occurred
on this project.
City of Windsor AGO 83
How was the divide
formed?
What was the
divide?
5.4.1 b) Junior Administration Managed the Project Until the Stage 1 Proposals Were
Received
Members of junior Administration managed the 400 CHS procurement process from June 25,
2001, up to and including issuing the EOI and Stage 1 of the RFP. The results of the audit
analysis verified that up to this point junior Administration, principally through the actions of
the Senior Property Negotiator, ran the RFP process in accordance with the Purchasing By-
law without any noted exceptions.
On January 14, 2002, Council established an RFP review and selection committee structure to
include both members of Council and Administration. The vague Council motion resulted in
a procurement process split into two divergent paths. Communication between the two
groups, operating on two separate paths, was not effective and eventually became adversarial.
1. The Councillors, out of real concern for the City’s then-current debt load,14
tried
to change the procurement process into one based on short-run purchase price,
not the RFP Assessment Matrix, and not even the lowest cost over the expected
lifetime of the asset, including maintenance and operating costs. 15
2. Administration, in recognition of its role of responsibility under the Municipal
Act, tried to run the procurement process based on the results of the RFP Matrix,
as required by the Purchasing By-Law.
3. Eventually, a division grew between Administration on the RFP Evaluation
Committee and those involved in reporting to Council on the project. There was
evident disparity between the RFP matrix requirements and the newly-created
“technical” versus “financial” winners information presented by Administration
in the July, August and September project reports to Council.
Communication between the two groups, operating on the two separate paths, was not
harmonious. As explained in the legal memorandum (Appendix A), junior Administration on
the committee, quite properly, complained to the City Solicitor about being overruled or
pushed aside by the Councillors.
The project documentation shows the message was carried to the then-CAO and that there was
14
We have been advised by Administration, that in 2002 the City was carrying a very large debt load. In light of this and the fact
that the City had just gone through MFP, Council was very concerned.
15
Many terms were used throughout the project to define the same thing: Price. This is explained later in the report. Budget
neutrality was interpreted at this time, as meaning that the impact on the City’s annual operating budget would be $0. However, the
analysis presented to Council did not take into account differences in operating and maintenance costs between two building
designs, one of which was more costly to construct initially, but may have been more budget neutral through savings in operating
and maintenance costs.
City of Windsor AGO 84
Another reason the
divide was
perpetuated - the
City did not use best
practice: a Business
Case, a Project
a level of comprehensive awareness of the ongoing problems among the various levels of
some Administration staff. However, there is no indication that the then-CAO raised the issue
with these Council members or dealt with these complaints. We have not found evidence that
the three City Councillors on the ad-hoc committee, or City Council itself, were made aware
of either the fact that the project had been taken outside of the legal framework of the
Purchasing By-Law and the common law applicable to such procurement contracts, or the
serious consequences that could flow from such conduct.
Some senior members of City Administration did not work directly with the Councillors, but
were involved in the review and approval of the Committee reports brought forward to
Council for information and decision making purposes. The reporting process for the 400
CHS project assisted to greatly muddy the responsibility and accountability for what took
place on this project.
The signatories to the reports to Council did not necessarily indicate participation in, or a
detailed level of involvement in preparing the project reports for Council. At times, a
signature was representative of an involved individual on the project, at times of an individual
involved only in reviewing the report to Council information (with limited knowledge of the
project history and detail) and at other times, the signature was representative of an individual
required as a formality to approve the report under the City’s protocol based on Procedural
By-Law 420-2001, which provides authority for the report to be released to Council.
In our meetings and interviews of this audit, we were advised of a concerning issue regarding
the project reports to Council. Report signatories were not necessarily aware of the serious
ongoing issues of the project RFP evaluation (the same is true of the Furniture Tender). We
were advised that some individuals participated in a review of the reports, provided
authorizing signatures, and even spoke to the reports at Council, absent knowledge that would
have afforded them the opportunity to step in and make attempts to rectify the situation. This
issue highlights a serious control issue in the City’s reporting to Council procedures, which
the AGO has addressed in a recommendation to this audit report.
5.4.1 c) No Approved Business Case & The City Did Not Follow Procedural By-Law 420-
2001 for this Project
The legal analysis starting at Page 5 of the legal memorandum (Appendix A) begins by
highlighting the following:
1) There was considerable confusion and inconsistency on the part of both Council
members and City staff, from the very beginning of the 400 Build project, about the
respective roles of the Council members and the Administration members on the
committee appointed to oversee the RFP process.
2) There was similar confusion and inconsistency about the very nature of the
City of Windsor AGO 85
Charter or the
Procedural By-Law
420-2001.
committee.
The legal risks identified in Appendix A may have been avoidable with a Council approved
project charter or project plan that clearly defined roles, authorities and decision rights in
accordance with the requirements of the Purchasing By-Law, the Municipal Act, the common
law governing procurement contracts and Council’s direction.
The inconsistencies and confusion made it difficult to determine the exact nature of the RFP
Evaluation Committee. We did not find documentation to support that the City carried out the
steps of Procedural By-Law 420-2001, required to take place when Council appoints a
Committee. 16
Therefore, it is unclear as to whether Council wished this committee to be a
committee of Council. Regardless of the confusion, it is important to highlight that a best
practice of project management for a defined project structure is already well-represented in
Procedural By-Law 420-2001, which requires the following to take place when Council
appoints a Committee.
Appendix B to Procedural By-Law 420-2001 states;
a) “That all requests for the formation of a Special Committee of Council/Advisory
Committee or Task Force be presented to Committee of the Whole for consideration.
b) That all requests, upon approved motion by the Committee of the Whole, be referred
to the Clerk for a report back on the following:
i. inventory of previous and existing activities related to the issue
ii. reporting structure, membership composition, mandate, objectives, legislative
requirements, work plan and timelines for the Special Committee of
Council/Advisory Committee or Task Force
iii. responsibilities of Committee members
iv. membership expertise requirements for the Special Committee of
Council/Advisory Committee or Task Force
v. proposed budget allocation requirement and source of funding
vi. staffing requirements
vii. other necessary resources, and
viii. term limits”
There is however, a weakness in this section of the By-Law which we have addressed in a
16
“Committee” per the Procedural By-Law 420-2001 means a Committee of Council which has been duly appointed to deal with
specific administrative matters and provides advice and/or recommendations to Council.
City of Windsor AGO 86
Control Issue:
Unclear
Responsibility and
Accountability for
implementing and
enforcing the By-
Law requirements.
How did Council
become involved in
the project?
recommendation to this report. It does not seem logical to expect the Clerk to complete such
tasks given the author of such a report would require specific knowledge of the purpose for the
committee and the task at hand. The By-Law is unclear as to who is required to fulfill these
requirements, or to report back to the Clerk. Further, the By-Law does not appear to include a
control mechanism to ensure that these requirements are carried out to the satisfaction of the
Clerk, or to another defined accountable Head.
5.4.1 d) How Council Became Involved in the Project
On June 25, 2001, Council approved the project in principle by resolution CR780/2001. Up to
the time the RFP Evaluation Committee was formed, the project was being managed by junior
Administration.
City Council became involved in the project because of the history of other projects going
over budget and the lack of communications to Council on those projects. On January 14,
2002, Council approved the recommendation, “That Councillors Hotham, Carlesimo and
Valentinis BE APPOINTED to a working committee with members of the Administration for
the purpose of undertaking a review and developing a short list of the RFP proponents for the
New Office Building at the former Police Headquarters.”
Chart A below, depicts the structure of the RFP Evaluation Committee that resulted from the
resolution of Council that approved the formation of the group and the assignment, by Senior
Administration, of members of Administration to be advisors to the Councillors on the
Committee.
City of Windsor AGO 87
What did the
structure of the RFP
Evaluation
Committee look
like?
Chart A: Project Structure During The RFP Procurement & Award Process17
This real concern
and the reason
Council got
involved, may have
added tension into
the working
environment of
Council and
Administration.
5.4.1 e) Why Council Became Involved on the Project
As explained in draft notes from a February 25, 2005 Steering Committee meeting:
“…in 2001 – 2002 the City was in the shadow of MFP and a significant debt load.”
“The mandate of the committee at that time [the RFP Evaluation Committee was
formed] was if this project cost the City any extra money, it would not go forward.”
“…If Administration could show the cost of the new building would reflect the
monthly payment of rent, then the project could be viable. The project was given the
go ahead on that basis.”
As was the case for the 400 CHS project, Council departed from its proper policy-making
governance role and ventured into the policy implementation role of Administration on more
than one project, perhaps as a result of strong concerns over the City’s debt load and MFP. In
our discussions with Administration, the AGO was advised that the Current Administration
believes that these reasons were known as the significant concern of Council during that time.
17
This Chart represents the Administrative Advisory group that worked on the RFP Evaluation Committee. Some of the members
listed were more involved than others, some worked intermittently, as needed, to provide advice, expertise and assistance to the
project.
Councillor 1 Councillor 2 Councillor 3
Assigned by Council resolution Jan. 14, 2002 (in-camera Council meeting)
Formed for the purpose of undertaking review & developing short list of R.F.P. with Administration.
Fund Accounting Manager
Director of Administration
Social Services Senior Property
Negotiator Director of
Facility Management
Legal Public Works
Project Engineer Director of Traffic City Centre
Revitalization Manager
Administrative Advisors assigned to assist the Working Committee.
City of Windsor AGO 88
According to current Administration, Council was also involved in the administration of a
large project concurrent with the 400 CHS project; the Western Super Anchor project. While
that project did not receive Council approval to go forward, Council and Administration
worked together through a number of tasks and there were significant challenges in the
Council / Administration work environment of the Super Anchor project. The reason Council
got involved on these projects may have added tension to the 2002 project environments.
Administration advised the AGO of an indicator of positive progress and performance of the
City’s debt load since 2002, as recorded in the 2008 / 2009 Municipal Financial Indicators
report of BMA Management Consultant Inc.
Debt Charges as % Total Expenditures (2002 figures were not Available)
Data 2003 2004 2005 2006 2007 2008
Windsor 6.3% 5.3% 3.8% 3.1% 2.4% 2.2%
Average 4.1% 3.8% 3.9% 4.4% 4.1% 4.2%
Council and
Administration have
worked hard over
the years. The
City’s debt load has
significantly
improved – Windsor
is now 48 % below
the municipal
average.
In 2003, Debt Charges as a % of Total Expenditures for the City of Windsor were reported at
6.3%, or 54% higher than the municipal average. Administration has advised that, “this high
debt level was headed even higher given the then planned debt issuances for major projects
such as the 400 CHS Project, the redevelopment of Huron Lodge, and the funding of a new
arena.” Owing to Council's focus and Administration’s diligence in reducing long term debt
over the last several years, by 2008, this dropped to 2.2%, or 48% below the municipal
average.
According to BMA, debt service costs as a percentage of the total expenditures reveals the
level of expenditures required to service past obligations, which is, therefore, not available for
other services currently required. The state of the City's high debt level of 2002, along with
the then-notorious MFP crisis may have been major contributing factors towards the primary
focus on the initial price of the 400 CHS Project, at the expense of the longer term value for
money RFP requirements. With these factors in mind, it may have been viewed by the then-
Administration that, while long term operating costs of the proposals were also important, the
initial price of the project would have been more highly weighed as it would reduce the
ongoing debt charges.
While this discussion presents a potential explanation for why the reports of Administration to
Council focused so heavily on the initial price of the project, the deviation from the stated and
legally correct RFP process cannot be condoned. The direction to deviate from the RFP
Assessment Matrix to become predominantly based on price – or for any reason at all – was
not in accordance with the law of procurement, with the City’s purchasing By-Law and with
the Municipal Act. This exposed the City to the risk of significant financial loss through
successful legal action against the City and higher costs for future procurements if the public
lost faith in the City’s fair treatment of RFP proponents and there were fewer respondents to
City of Windsor AGO 89
RFPs.
Communication
issue: From day
one, Council
communicated a
consistent message
– Budget Neutral or
no go for the
project.
As we move on in
the report, we will
identify that the
actual principal
concern was
“Price”.
“Price” and
“Budget – Neutral”
are financial
accounting terms
and there is a very
important difference
between the two.
5.4.1 f) The Councillors on the Evaluation Committee Were Concerned With Price
Many of the project problems were caused by unrealistic thinking about budget neutrality. As
discussed above, the Administrative side of the process wished to remain faithful to the RFP
evaluation process. Yet, from Day 1 through to the Award of the RFP Contract, Council’s
message was consistent – Budget Neutral18
or No-Go for the Project.
However, one cannot make the City’s desire for budget neutrality a criterion in an RFP
process. Preparing a response to this type of RFP is a very costly process for proponents.
Potential proponents would have no idea of the City’s budget, or what rental rate the City
expects or wishes to charge per square foot per year over the life of the asset. There would be
no responses to such a vague RFP. No one would be able to submit a proposal for a building
with determinative but unknown or undisclosed financial prerequisites. This is where the
business case becomes crucial.
If the City had developed a business case with stated assumptions that were debated and
agreed to, it could then have decided either not to construct and own the building (hence no
RFP) or to issue an RFP with detailed requirements for both City-occupied and rental space in
a building of specified square footage and maximum price.
On the Capital budget side, during the City’s 2002 budget deliberations, Council approved
budget resolution B42-200219
with respect to the Debt Management Strategy with the
following provision:
- “That no other major projects BE APPROVED in the 2002-2007 period other than the
Justice Facility, Richmond Landing, Training Facility, Multi-Use Recreation Facility,
Lou Romano Project and Huron Lodge. Debt identified in this report should be
considered in the context of this resolution and the other projects currently contemplated
or already approved by City Council...”
18
Budget – neutral means where the impact on the City’s annual operating budget would be $0. An appropriate process to
measure this goal on the operating side would require a complex financial analysis used to compare the proposals to determine the
lowest cost to the City.
19
This resolution carries a connected message from Council. There would be no capital projects approved outside what was
identified in
B42-2002. Any project going forward would need to fit into the existing debt strategy, and have a $0 impact on the
City’s debt load.
City of Windsor AGO 90
On the Operating budget side, the importance of the internal goal of Budget-Neutrality was
clear in project documentation such as Reports to Council, Steering Committee minutes, staff
emails and reports in the media quoting City staff and members of Council. A good example
of this message is reflected in the draft Committee notes discussed above.
And finally, the importance of Council’s message was carried forward to the conclusion of the
September 2002 Report to Council written by Administration, which recommended the Award
of the RFP to a proponent as the,
- “…proposal allows the City the potential to achieve a cost neutral position for the
project.”20
In the “Price” Financial Analysis of the September report, the concept of “any extra money”
was narrowly considered as equal to purchase price and the possibility not all extra space
would be rented, not cost over the lifetime of the building. Thus, potentially higher long-run
operating and maintenance costs were treated as irrelevant.
Good
communication
controls required
for the system of
governance to
effectively operate.
Given the global
environment under
which this project
5.4.1 g) Effective Communication Required for Good Governance
Conditions such as those discussed in this report which existed during the RFP evaluation and
selection process for this project have a negative impact on effective communication between
Council and Administration, which is integral to effective Corporate Governance.
It is incumbent upon Administration to preserve the flow of timely, accurate, appropriate,
relevant and critical (risk) information to the City’s decision makers. However, there are
structural weaknesses that exist which, under the right circumstances, will make this important
task of Administration difficult.
We have made recommendations for Administration to consider the development of policy
and By-Law amendments to address identified structural weaknesses and to remove structural
impediments21
to an effective corporate communication system.
5.4.1 h) City Wide Risk Events Had an Affect on the Project
The municipality of 2002 was much less structured than it is today and there were a number of
20
Cost – neutral, used in this context means the same thing as Budget – neutral. That the impact on the City’s annual operating
budget would be $0.
21
Related to or resulting from the organization or functioning of a political or economic system.
City of Windsor AGO 91
took place –
transparency and
accountability for
the issues is weak.
Risk events outside
of the project also
had an impact on
the project
environment &
effective
communication.
external risk events of the project that had an impact on the project. Because of the conditions
of the project environment and the conditions of the total environment (City wide) – the lines
of transparency and accountability for the issues on this project are not clear.
Concurrent Risk Events Created a Crisis for the City and Trouble for the Project:
- Some senior and experienced Administration who had witnessed the MFP crisis had
recently left the employ of the City. The remaining Administration was stigmatized by
MFP.22
- At that time, the City was low in senior staff with sophisticated risk management and
project management experience.
- The team of Administration that remained after these departures inherited a large problem;
rebuilding the trust, relationships and reputation of Administration, a condition they have
been steadily working at improving ever since.
Corporate Governance in 2002 was Not as Strong as it Is Today:
- Organizational instability was prevalent among the top levels of Administration, and this
was exacerbated by the intrusion of individual Council members into the procurement
function.
- There was a lack of a corporate risk framework, including a lack of strong risk analysis,
and risk communication policies.23
- There was a lack of supporting governance policies to provide an alternate forum for
concerned persons to come forward. For example, today Council has in place an Integrity
Commissioner, Auditor General’s Office, Hotline, Fraud Policy, Council Code of Ethics,
etc. Further, Administration is working on finalizing a City Staff & Administration Code
of Ethics to bring to Council for approval.24
22
The MFP crisis was discovered by the City in 2001. In July 2005, the County, City and EWSWA (the "Plaintiffs”) settled a
legal action commenced in the Ontario Superior Court of Justice against MFP Financial Services, Leasing-Infrastructure Financing
Trust 1 ("LIFT") and others in which the Plaintiffs had alleged that certain of the defendants had fraudulently and negligently
misrepresented the rate of interest payable by the Plaintiffs in respect of a head lease and sublease intended to be a loan to finance
certain costs incurred by the Authority to develop the Regional Landfill and pay the costs of future landfill expansions.
23
The City does not have a risk management or enterprise risk management (ERM) framework in place today. This is outside of the
scope of this audit but still important, as ERM would require effective communication policies to be in place to ensure timely
critical information reaches the City’s decision makers. Administration’s current OCI initiative should help improve this control
area.
24
The City has implemented a code of ethics policy for members of Council; however the code of ethics policy for Administration
and staff remains in draft.
City of Windsor AGO 92
Council has
completed a number
of initiatives
towards
improvement to
accountability,
transparency and
good governance for
the City of Windsor.
5.4.1 i) Council & Administrative Initiatives Since 2002, Have Significantly Improved
the Governance Structure, Corporate Culture, and Risk Environment of the
City
The City of Windsor website contains the following information which highlights recent
achievements of Council to improve municipal governance, transparency and accountability25
:
“In 2006, the Municipal Act was amended to include new provisions respecting the
accountability and transparency of municipal government and its operations. Since
that time, City Council has taken a number of important steps to meet the new
requirements of the Municipal Act to enhance transparency and accountability and to
improve on the corporate governance structure of the City of Windsor.”
The following list of initiatives and actions of Council, supported by the City’s
Administration, demonstrate the City’s deliberate path to increasing transparency and
accountability of the municipality:
1. Appointment of Accountability & Transparency Officers
- Integrity Commissioner (Approved October, 2007)
- Auditor General’s Office (Created July 2008)
- Audit Committee website 2008, where the public can access Auditor Committee
and Auditor General’s Office information through 311, Council Services or the
Audit Committee website at http://www.Citywindsor.ca/002781.asp
- Voluntary Lobbyist Registry26
2. Implemented Council Code of Conduct
- On October 22, 2008, Windsor City Council passed a new Code of Conduct for
Council.
- The code of conduct can be viewed on the web at:
http://www.Citywindsor.ca/DisplayAttach.asp?AttachID=12807
25
For more information, refer to the City’s Municipal Accountability and Transparency website located on the web at:
http://www.Citywindsor.ca/002634.asp
26
Council has approved the creation of a voluntary Lobbyist Registry, but has chosen not to appoint an Ombudsman at this time.
City of Windsor AGO 93
3. Appointed a Public Meeting Investigator
- The Act mandates that citizens have the right to request that an investigation be
conducted into the appropriateness of closed meetings of Council.
- The City of Windsor has appointed the firm of Amberley Gavel Ltd. as its
Meetings Investigator.
4. Corporate Culture Initiatives (IRIDE)
- IRIDE is a City initiative aimed at positive and effective change to the City’s
overall culture through a Council supported VISION and MISSION and principles
of IRIDE.
- IRIDE stands for Integrity, Respect, Innovation, Diversity and Empowerment.
- While upholding the principles of IRIDE, the Current Administration is in the
process of making improvements to this culture initiative.
5. Mandatory Policy Development
Municipalities have been mandated to have, and regularly review certain policies.
Administration has developed a number of policies for Council approval. For
example,
- In 2003, the City commissioned PriceWaterhouseCoopers to conduct a Controls
and Procedures Audit on Corporate Services. This report has led to a number of
initiatives and changes to the City’s core financial department which greatly
improved on municipal accountability and responsibility.
- New purchasing By-Law, 2004 (Currently in revision).
- Corporate Template for financial implications of reports dealing with capital
projects.27
- Office of Continuous Improvement (OCI) – For the improvement of internal
control and risk management. (Structure pending)
- Service Delivery Review.
- Draft code of ethics policy for employees.
27
This policy should address some of the control issues identified within this report regarding “information presented to Council
for decision making purposes.”
City of Windsor AGO 94
5.4.2 The “Price” Financial Analysis and the Information Reported to
Council for Decision Making Purposes
Additional audit
findings of the RFP
procurement
process review.
The information presented by the Administration to Council was inadequate for decision
making purposes in a number of ways. The presentation of whether and how the
proponents complied with the RFP’s requirements and among the compliant proponents,
and how they ranked in the RFP evaluation process was inadequate and incomplete. There
was also a lack of disclosure that the recommended process was a significant deviation
from the legally binding RFP procurement process by way of circumvention of that process
and of the Purchasing By-Law.
Finding 3.
It was not transparent in the reports to Council that Council was being asked to deviate
from the RFP process or to circumvent the Purchasing By-Law when the Administration
recommended that Council provide “direction” to the RFP Evaluation Committee to
negotiate with the highest ranking proponents in both the technical and financial reviews of
the RFP evaluation. Council was being asked to direct the Committee to go down a path it
legally could not go, without disclosing this.
a) This raises questions of unacceptable “Bid Shopping”, which “occurs when a
municipality opens the bids and then uses them to “negotiate” by approaching
bidders with the information and trying to get them to lower their bids. This
violates Contract A and the duty of good faith.” 28
b) It is unclear whether Council was ever advised that providing direction to negotiate
with proponents at this stage in the process would amount to Council approval to
circumvent the Purchasing By-Law. However, as Council could have amended this
By-Law to exempt the 400 Building from it with relative ease, it is doubtful that
this would have been presented, but left undone. The Stage 2 RFP and related
correspondence to the Proponents was clear – that the Award of the RFP would be
decided based on the RFP Assessment Matrix. What remains unclear, and unlikely,
is that Council was advised of this requirement or reminded of this requirement
when deciding on the RFP Award.
c) The RFP itself created no such division between “technical” and “financial”.
Rather, points were awarded only on a matrix that included a weighting for
financial as well as other criteria. It was not accurate to characterize this
comprehensive and publicly-announced matrix as merely “technical”, and the
28
Source: Fall 2008 Municipal Leader magazine, “Love Me, Tenderer: Municipalities, Tendering and the Law” by John D.
Stefaniuk, Partner , Thompson Dorfman Sweatman LLP.
City of Windsor AGO 95
narrow, short-run analysis of purchase price alone as “financial”. It was also
without legal foundation to declare two “winners” and to pit one against the other.
Finding 4.
The reports to Council failed to disclose the Vindella proposal was non-compliant to the
RFP, and therefore, had to be rejected, rather than declared a winner in the non-existent
“financial” category. The Vindella proposal was presented to Council as a compliant and
seemingly viable proposal, giving the false appearance that it was the lowest compliant
bid29
in the running for the award of the contract.
Finding 5.
After the Stage 2 evaluation and ranking of the RFP proponents concluded, the City turned
away from the RFP Assessment Matrix process to a “Price” Financial Analysis to decide
the award of the RFP contract.
Whether referred to by Administration as “Annual Operating Budgetary Impact”, “Cost
Neutral”, “Budget Neutral” or “Building Ownership Risk”, etc, the goal of the “Price”
Financial Analysis was to determine the lowest price of ownership (not lowest cost of
ownership) for the 400 CHS building.
The financial information brought forward to Council to determine this lowest price factor
was designed by Administration. There is a concern that Council was not told by
Administration that the Purchasing By-Law RFP Matrix which took into account both long-
term “Cost” & short-run “Price” (Value for Money) applied the maximum weight to the
Life Cycle Costing proposal requirement, which was clearly an appropriate and meaningful
evaluation tool to determine the lowest cost of ownership of a fixed asset over its useful
life.
To expand on this statement, the use of cheaper but less durable building designs and
materials, which require earlier replacement and more costly annual maintenance, only
serve to drive down the initial price by an amount which may be smaller than the total cost
of the building over its useful life. This may result in a transfer of costs from this
generation to our children, raising an issue of intergenerational equity.
29
Means the Bid that would provide the City of Windsor with the desired goods and/or services at the lowest per unit or overall
cost, meets all the Specifications and contains no major irregularity or qualifications.
City of Windsor AGO 96
Finding 6.
Based on the audit work performed, it is the opinion of the AGO that the “Price” Financial
Analysis used to evaluate the proponents’ proposals was flawed to the point that it was
unfair to Council and to taxpayers. There was incomplete disclosure of material facts,
which likely created the situation that Council did not have the information to make an
informed decision as to the award of the RFP Contract.
a) Council was advised, “…the variance between best and worst case scenario is the
amount of risk the Municipality must consider as the cost of owning this facility on
an annual basis.”
b) The presentation of the “Price” Financial Analysis “Risk” calculation along with
discussion of the RFP requirements in the same report, likely gave Council the
impression that the RFP requirements had relevance to the results of the analysis.
It is unclear whether Council was ever advised that the RFP Matrix information
included in the reports to Council became “for Council information” only.
c) The “Price” Financial Analysis did not include an adequate evaluation of real
project risks. The risk analysis was a simple calculation that only equalled the
current amount of speculative space rent. The same outcome was achievable
through a simple arithmetic calculation: current un-rented space x the estimated
lease rate per square foot.
d) There was a material omission in the September 2002 report to Council to
recommend the Award of the RFP Contract. No final risk calculation, Variance
(Risk), on a basis consistent with the previous report, was shown in the September
report. If the final risk calculation had been shown, in carrying through
Administration’s risk analysis methodology consistently, EllisDon would now have
been shown to be less risky. There was also no commentary to indicate that
contrary to prior reports, EllisDon was now the “winner” for this risk criterion.
Although we pursued the question with vigour, no one connected with the project
was able to provide us with any explanation for this material omission.
City of Windsor AGO 97
Finding 7.
Based on the audit work performed, the AGO has determined that the “Price” Financial
Analysis used to evaluate the proponents’ proposals was flawed to the point that it was
unfair to the Proponents. Any proposal which met the stated City requirements or requests
of the RFP (any proponent that gave the City what the City asked for), was placed at an
immediate and uncontrollable disadvantage in comparison to a proponent that did not meet
the City’s requirements or requests. Conversely, the less compliant the proposal, the better
chance the proponent had to be declared the winner of the RFP process.
Finding 8.
The financial analysis in the reports to Council dated July 18, 2002 (in-camera), August 21,
2002 (in-camera) and September 4, 2002 (open session # 8652), consistently used, but did
not clearly state the total office space requirement as 111,500 sq. ft., a material decrease of
31,100 sq. ft. from the City’s RFP Stage 2 requested estimate of 142,600 sq. ft. Any office
space greater than 111,500 sq. ft. was now treated by Administration to be “speculative”
space, and thus, as a risk.
It was not appropriate to use the 111,500 sq. ft. value in the financial analysis without
disclosing the nature and consequences of that newly-adopted number. The presentation of
the information regarding the 111,500 sq. ft. in the reports to Council was incomplete and
unclear. Based on the audit work performed, the AGO determined that:
a) The number represented a material change from the stated requirements of the RFP
as presented to the proponents, and the change had a distorting, punitive effect on
the evaluation of the proposals that came closest to meeting the building size
requirement presented by the City’s RFP.
b) The number was changed by Administration as a result of the loss of the Provincial
tenant, to reflect the then-current risk to the City. The information should have
been used to highlight the risks to Council, to assist Council in its decision whether
to approve the project to proceed. Instead, the information was used in a manner
that punished the RFP proponents that met the stated requirements of the RFP and
rewarded one that did not.
c) By material error or omission, what the reports to Council did not provide was a
discussion of the risk impact to the City that would result from this opaque change.
As stated in the legal memorandum (Appendix A), this change is one part of the
process leading to the breach of the City’s “bidding contract” obligations to
EllisDon. If not for the passage of time, the City would be facing the risk of
compensating EllisDon for the overhead and profit it would have earned.
City of Windsor AGO 98
d) More broadly defined, the City risked damage to its goodwill, damage to future
business relationships including the ability to attract quality proponents and quality
investment, damage to relationships between Council and City staff, and caused the
risk of legal action against the City, members of Council and members of senior
Administration.
Discussion: The “Price” Financial Analysis
What was the
“Price” Financial
Analysis?
May 2002 was the last time the RFP Matrix results reported to Council held any weight on
the outcome of the RFP Award. By the July 2002 report to Council, the outcome of the
RFP Award was driven by the results of the seriously flawed “Price” Financial Analysis.
The “Price” Financial Analysis introduced by Administration had two components: (1)
Price and (2) Risk, which presented itself as calculating the annual operating budget impact
as (i) a best case scenario, (ii) a worst case scenario, and (iii) the “variance between best &
worst case = RISK”.
Therefore, as defined by Administration:
Difference in Annual Operational Budgetary Impact =
Variance (worst case scenario minus best case scenario) = Risk
Council was not advised that the “risk” calculated only equalled the estimated price of
speculative space rent. 30
In actuality, the calculation for the “Price” Financial Analysis
meant:
Difference in Annual Operational Budgetary Impact =
Estimated Speculative Space Rent
That is by no means a comprehensive analysis of the relevant risks of a major project like
this. The calculations in the “Price” Financial Analysis were described by several different
terms in the project reports to Council. Whether the results of the calculation were referred
to as “Annual Operating Budgetary Impact”, “Cost Neutral”, “Budget Neutral” or
“Building Ownership Risk”, etc, the goal of the “Price” Financial Analysis was to
determine the lowest short-run price of ownership (not lowest actual, long-run cost of
ownership) for the 400 CHS building.
30
Speculative space is un-rented space.
City of Windsor AGO 99
The discussion of the audit findings is presented in the following sequence:
A. “Price” vs. “Cost” – What’s the Difference?
B. May 2002: Concerns with the Information Presented to Council for Decision
Making Purposes.
C. July 2002: The Deviation From the RFP Process & Issues of Fairness to the
Proponents.
D. August 2002: Issues of Transparency in Reporting to Council & Fairness to the
Proponents.
E. September 2002: Continued Issues through to the Award of the RFP.
The decision of the
City to move away
from the “RFP
Assessment Matrix”
to “Price” shows
the limited
understanding of the
nature and purpose
of the purchasing
By-Law, which is to
achieve the lowest
overall cost to the
City.
A. “Price” vs. “Cost” – What’s the Difference?
A central conclusion of the legal memorandum (appendix A) was that “Council members
and some senior staff members demonstrated a low level of awareness and understanding
of some of the most basic principles of the laws governing the City…” The findings and
discussion to follow help to demonstrate the effects of this conclusion around financial
terms: “Price”, “Cost” and “Value for Money”.
1. The difference between “Price” and “Cost.” To clarify the commonly
misunderstood difference between price and cost in the 400 CHS building31
project:
- “Price” is the lowest immediate capital cost, the one-time value of money paid for
the building to be completed. In this case, the total project price paid for the
construction of the 400 CHS building was $ 23,367,173.
- “Cost”, includes the price paid for the building and the money it will take to
maintain the building during its lifetime. The cost of the 400 CHS building will
continue to be paid by taxpayers for years after the price was paid.
2. The difference between “Price”, “Cost” and “Value for Money”
- Simply put, “Value for Money” means the best available combination of “Price”
and “Cost”. 32
- The decision to steer away from the RFP Matrix shows there was a limited
31
This discussion refers to the construction price of the building known as 400 CHS. The discussion does not include
consideration of the other project expenditures, i.e., furniture fit-ups, district energy, sale of social services assets, etc.
32
To achieve Value for Money means the City has obtained the maximum benefit from the goods and services it both acquires
and provides, within the resources available to it, in accordance with the laws, principles, guidelines and standards of the
municipality.
City of Windsor AGO 100
understanding of Council and some Senior members of Administration that “Value
for Money” was the better financial measurement tool for minimizing the total bill
for taxpayers.
- The RFP assessment matrix is thus, for good reason, the approved Purchasing By-
Law method used by the City to ensure decisions on RFP Awards result in “Value
for Money” for the taxpayers of the City of Windsor.
Council was first
introduced to the
RFP ranking results
in a May 17, 2002
In-Camera report.
Proponents’
“Price” rankings
were not
consistently
reported.
B. May 2002: Concerns with the Information Presented to Council for Decision
Making Purposes:
Administration first reported RFP evaluation results in an in-camera report dated May 17,
2002. The evaluation results were presented as preliminary and Administration requested
and received approval to continue to evaluate the RFP’s including necessary interviews
with the intent to bring a further report to Council.
“While six proponents for our R.F.P. were shortlisted following the Stage 1 review, only
four submitted responses to the Stage 2 request for detailed information. The Stage 2
respondents were:
1) Vindella Enterprise Inc.;
2) Mady Development Corporation;
3) M.K.T. Development Group;
4) Ellis Don”
May 17, 2002 RFP “Price” Rankings Reported:
Chart B: RFP Design / Build Price
Mady Ellis Don MKT Vindella
29,850,000
27,300,000
30,476,588
26,742,000
Correction: Vindella price excluding GST
24,992,114
- In terms of clarity of presentation, the financial values were not consistently presented
for each proponent.
- The Vindella proposal was reported inclusive of GST and the other proposals were
reported net of GST. (The actual price net of GST included in Vindella’s proposal was
$24,992,114).
- The presentation was Apples to Oranges. It was not adequately explained that these
City of Windsor AGO 101
were different prices for substantially different buildings, not different prices for the
same type of building.
- As noted earlier, these numbers were for purchase price only. They were not a full
costing to show the different impacts on the City’s budget in future years of differences
in operating costs and maintenance costs resulting from differences in basic design and
in the construction materials used.
May 17, 2002 Final RFP “Technical = Non-Price” Ratings Reported33
:
The “Non-Price” ratings (referred to as “Technical” by Administration) of the RFP
Evaluation Committee rankings were presented as follows: “The administrative technical
committee has evaluated the proposals based upon the attached “assessment matrix”. The
weighted scores for the proposals, excluding the “Price Proposal” section are shown on
the matrix.”
Chart C: Stage 2 RFP – Assessment Matrix (May 17, 2002 In-Camera Report to Council)
RFP Assessment Matrix Weight Factor Mady Ellis Don MKT Vindella
Matrix Requirements Points Weight Points Weight Points Weight Points Weight
Product
Drawings 1 5 5 5 5 5 5 3 3
Building Design / Function 3 2 6 4 12 2 6 3 9
Parking Requirements 3 4 12 5 15 1 3 2 6
Additional Amenities 1 5 5 5 5 0 0 1 1
Compliance Civic Sq. Urban Design 2 2 4 4 8 2 4 2 4
Sustainable Design (LEEDS) 2 3 6 5 10 3 6 1 2
Outline Specifications/ Standards 1 4 4 5 5 4 4 0 0
Cost Price Proposal 3
Life Cycle Costing 3 4 12 5 15 4 12 0 0
Schedule Project Schedule 3 2 6 4 12 5 15 34 0 0
Total 60 87 55 25
Converted to a % out of 95 points 63% 92% 58% 26%
Weight Factor: Marked the importance of the RFP requirement, 3 being of the greatest importance.
Product, Cost & Schedule: The main categories of the RFP requirements to be met by the proponents.
33
Although reported as preliminary, these values did not change and therefore represent the final RFP technical rating scores.
34 Arithmetic corrected: May 2002 report showed MKT scored a 13 in this category. Weighting corrected 5 X 3 = 15.
City of Windsor AGO 102
The results of the
Matrix evaluation
show the Vindella
proposal is deficient
in some areas
The legal memorandum (Attachment A) discusses the non-compliance of the Vindella
proposal on the basis of a Bid-Bond requirement that is widely unknown outside of
procurement specialists. Additionally, the results of the RFP Evaluation Matrix show the
Vindella may have been non-compliant on common evaluation factors. Before
consideration of the “Price Proposal” requirement, the Ellis Don proposal was compliant
and the Vindella proposal may have been non-compliant due to major irregularities.35
That
is why Vindella received a score of 0 (zero) in two of the five most important categories –
Life Cycle Costing and Project Schedule.
A review of the Vindella Stage 2 proposal confirmed that both the Life Cycle Costing and
Project Schedule requirements were not adequately addressed by Vindella. There was very
little submitted with Vindella’s proposal response for these two requirements that would
provide meaningful data for the RFP Evaluation Committee to consider in its review.
Barring the previous
opportunities, it
would have been
prudent for the City
to stop at this point,
and declare
EllisDon the winner
of the RFP.
There was a
material difference
in technical quality
– a 62 point
difference between
the compliant
EllisDon and the
non-compliant
Vindella.
Despite the fact that the Vindella proposal was non-compliant, in July 2002, Vindella was
kept in the RFP process to be placed in direct competition with EllisDon. It does not seem
to have been a prudent business decision to accept the legal risk of forgoing the RFP
process to bypass a superior proposal, and put it into a bidding competition with a non-
compliant proposal.
- Taking into consideration clarifying questions, before material changes to the
Vindella proposal (which occurred between May and July 2002), the price of the
Vindella proposal was $24,992,11436
and the price of the EllisDon proposal was
$26,288,555.37
- Refer to Chart C above: In consideration of the total weighted score of the RFP
proponents, the Vindella proposal, even if it had been given full marks for Price
Proposal = 15 points, and everyone else was given 0 for price, would achieve a
total of 40 points in the matrix. This value would not reach the next lowest ranking
competitor, (if given 0 for price consideration) which was ranked a score of 55
points.
- Looked at more globally, to come ahead of EllisDon’s 87 points, Vindella would
have needed not only a compliant proposal, but also, a total of 88 points, which was
35
Purchasing By-Law 400-2004 definition of “Major Irregularity”: A deviation from the Bid request which affects the price,
quality, quantity or delivery and is material to the Award. If the deviation is permitted, the bidder could gain an unfair advantage
over competitors. The Manager of Purchasing and Risk Management must reject any Bid which contains a major irregularity.
36
Vindella’s original proposal price.
37
EllisDon’s original proposal price of $27,300,000 – ($1,011,445) for the optional restaurant & fitness area, electrical vault
adjustment and the underground parking development levy not required.
City of Windsor AGO 103
63 points more than it received. Somehow, at least implicitly, Vindella was given
the equivalent of these 63 points. This was possible only by departure from the
RFP process that the City represented to the prospective proponents would be
followed.
This special in-
camera meeting of
Council marks the
“official” point in
time the City turned
away from the RFP
Evaluation Matrix
(Purchasing By-
Law) to – “Price”
Financial
Evaluation.
C. July 2002: The Deviation From the RFP Process & Issues of Fairness to the
Proponents
Administration reported to Council, at a special in-camera meeting of Council, on July 24,
2002 (Report date July 18, 2002), the results of the RFP Evaluation Matrix and
recommended that:
“If Council wishes to proceed with this project, it is recommended that direction be
given to the review committee to negotiate with the highest ranking proponents in both
the technical and financial reviews (Vindella for financial and EllisDon for technical),
to obtain a “best deal” for the City under the ownership and leasing scenarios.
Discussions with both proponents should promote competitiveness.”
A different course of action was adopted through the following resolution of Council:
“That the Administration BE DIRECTED to negotiate with the highest ranking
proponents in both the technical and financial reviews to obtain a “best deal” for the
City under the ownership scenario for the Income Security Building Project, as detailed
in the Confidential report dated July 18, 2002 from the Commissioner of Corporate
Services et al, with the expectation of a future report to City Council on the outcome of
those negotiations.”
There was no mention of the fact that the normal and expected outcome of an RFP process
such as this one was that there would be only one highest ranking proponent, who would be
given the exclusive first right to negotiate the contract. The usual (although not invariable)
result is that the highest ranking proponent is also awarded the contract. Pitting the highest
ranking proponent against a non-compliant proponent, or against a proponent with a
ranking for “financial” that was not part of the RFP ranking process announced to
proponents, and was developed only after the proposal deadline had passed, is highly
irregular.
The July RFP Matrix Discussion
The RFP matrix received limited representation in the report comments. This undervalued
the legal importance of the matrix evaluation of each of the proponent’s proposals in
compliance with the RFP criteria.
City of Windsor AGO 104
The RFP matrix was
not given adequate
attention or
consideration in the
report analysis.
The report is silent
on the subject of
RFP compliance.
This implies
compliance was not
treated as a
threshold issue.
- The report’s discussion of the RFP assessment Matrix was limited to a note that the
matrix was attached as an appendix. Only the RFP criteria for the Windsor Civic
Square Urban Design Study, Parking and Price requirements are evaluated in the report.
- The report indicated the matrix evaluation was based on information forwarded by the
proponents to meet the criteria established by the committee.
- The Vindella proposal was non-compliant due to major irregularities however; this fact
was not reported. The report is silent on the subject of RFP compliance, which wrongly
implied that compliance was not an issue.
- The inclusion of a non-compliant proposal at this stage is inconsistent with the
reasoning in several decisions of the Supreme Court of Canada dealing with fairness in
the RFP/bidding processes.
The July Financial Analysis – The Introduction of the “Price” Financial Analysis
The focus of the July 2002 report was to present the financial evaluation of the decision to
purchase or lease – to compare the “operational impact” that ownership and leasing would
each have.
The report was prepared by Administration to address CQ 75-2002 (C), asked at a March 4,
2002 Council meeting:
CQ 75-2002 (C) - “Asks for a cost benefit analysis regarding the consolidation of
the Social Services Department based on the square footage of the proposed
development adjacent to City Hall compared to the square footage of existing
Social Services facilities, with the evaluation to include existing operating costs as
well as projected leasing costs in the new headquarters.
City of Windsor AGO 105
Numerous issues
followed:
Numerous Significant Issues Would Follow
a) There were inconsistencies between the financial costs presented in July 18, 2002 and
the May 17, 2002 report.
Chart D: Talks Result in Changes in 1 out of 4 Proposals
Mady Ellis Don MKT Vindella
May-17
29,850,000
27,300,000
30,476,588
24,992,114
Jul-18
29,850,000
26,975,880
30,476,588
22,532,79138
Change -
(324,120)39 -
(2,459,323)
b) The Vindella proposal was materially changed – before Council provided, by way of
influence through the information and recommendations of the Administrative reports
to Council, the direction and approval to negotiate with the highest ranking proponents
in both the official RFP ranking and the subsequent “financial” review.
- An obscure fact reported to Council in the September 2002 Report to Council (#8652)
was that the Vindella proposal which was allowed to proceed to be in competition with
EllisDon on the “Price” financial analysis, was not the same proposal that had been
submitted in response to the RFP, and had been evaluated in the RFP matrix. (This
topic is covered in the detailed legal analysis of Appendix A, pp. 23 – 26.) The legal
consequences of so doing were not reported.
- Excerpts from the Miller Thomson legal memorandum:
The first four written questions to Vindella were seeking information to fill in the gaps
(material deficiencies) and revise its proposal…
Also, Vindella was provided with the opportunity to give the City an additional
38
We have adjusted the value reported in the July 18, 2002 report to Council, to correct a transposition error. The financial
analysis for Vindella used the price $22,352,791. A difference of $180,000 less than the actual revised Vindella price. The
transposition error was corrected by Administration in the September 2002 report to Council.
39
$324,120 was to exclude amenity space provided as an option by EllisDon in their Stage 2 proposal. There was no change to
the EllisDon proposal.
City of Windsor AGO 106
So what changed?
option… This occurred sometime between the May 17, 2002 and July 18, 2002 in-
camera reports to Council, and likely happened on June 20, 2002 when the four
proponents were interviewed.
- Report to Council #8652, to Council on September 11, 2002 stated:
“During the [RFP] interview process Vindella presented the City of Windsor an
additional option consolidating the office and parking structure all on the single site to
the east of City Hall. The option presented by Vindella resulted in a revised price of
$22,532,791. Members of Council on the working committee directed Administration
to conduct a comprehensive financial review of all proposals and report back to
Council with the findings of the review.”
- What was Changed After the Deadline for Completed Proposals to be Filed?
The Vindella proposal price changed from $24,992,114 (as at May 17, 02) to
$22,532,791 (as at July 18, 02). The net reduction in price of $2,459,323, included the
following changes.
o A permanent parking structure to be built on the former police site valued at
$6,345,977 was eliminated from the Vindella proposal. The Vindella proposal,
pre-change, would have provided a total of 569 parking spaces.40
o The revised proposal reduced that number to 435 (a reduction of 134 parking
spaces).41
o $3,071,654 was added to provide 1 additional level of underground parking.
o $815,000 was added for work requested by the City to demolish the former
police building.
c) The revised Vindella proposal was never re-evaluated against the RFP matrix, the use
of which was by then abandoned. However, the City no longer had a then current RFP
assessment grade to measure Vindella against any other proponent. As learned in our
interviews and meetings for this audit, some Administration, outside of the RFP
Evaluation team, were unaware of this fact.
40
Speaking to the issues of a lack of risk based project planning and ERM; the City did not identify the link between the 400
CHS project and the Tunnel expansion project before the RFP documents were released. The former police site land was
earmarked for the Tunnel expansion and a permanent parking structure or building on the former police headquarters site would
not have fit into the City’s strategic objectives. The OCI, once in place, should minimize the risk of this type of issue recurring.
41
The value 435 represents the Vindella parking deliverables of the project identified by Administration in report to Council
#8652 dated September 4, 2002. Due to the unclear deliverables within the RFP documents and main construction contract, we
were unable to determine the contractual obligation for parking spaces that Vindella was required to meet.
City of Windsor AGO 107
d) It was never stated that Council was actually being asked to consider Vindella’s non-
compliant proposal, contrary to the law in both the Purchasing By-Law and the
common law of bidding and tendering as laid down by the courts. The mere
presentation of the Vindella proposal to Council would have given Council the
impression that Vindella was at least a compliant proponent, if not the lowest
compliant proponent. If Council had been told that it was being asked to approve a
non-compliant proposal, improperly amended at the request of, and with the assistance
of the then-Administration, all contrary to law, it is doubtful that it would even have
entertained the thought of doing so.
There was a
material omission of
financial
information – Mady
may have been a
lower price
proposal than
Vindella, however
this was not
reported.
Vindella went on to
be placed in
competition with
EllisDon.
e) There was material financial information that appears to have not been reported to
Council. Further, it is unclear who in Administration had knowledge of this
information. According to project documentation, given fair presentation of financial
facts, Mady was the lowest priced proposal at this time. We identified an undated
financial document within the Project Management files in which someone in
Administration had summarized the following results:42
- “On the RFP assessment matrix, Mady scored second to EllisDon while Mady’s
price was lower than all prices. Notwithstanding, Mady’s proposal was not short
listed.”
- “Vindella’s original price per sq. ft. was identified as $182.50. Mady’s was
$164.00.” After adjustments: “Vindella’s overall price is $154.00 per sq. ft.”
“Now Mady’s price is $157.00 per sq. ft.”
- “Keep in mind this is for a 10 storey building. If we adjust for the difference in
cost between a 4 storey [Vindella] and a 10 storey [Mady] building …makes
Mady’s final price $126.00 per sq. ft.
- Even if this adjustment were not made, Mady’s final price was $157.00 per sq. ft.
with a huge score advantage in the assessment matrix over the Vindella proposal
which was $154.00 per sq. ft.”
- If Mady had the opportunity to revise his proposal to a 4 storey building, it is
reasonable to assume that his price would have come in much less than the $154.00
per sq. ft. of Vindella. Mady was given no opportunity to submit an additional
proposal while Vindella was given that opportunity.”
42
The financial data prepared by Administration appears to be feasible. Audit completed an independent analysis to test the
reliability of the information contained in the undated / unsigned Administrative analysis. The audit analysis, using information
reported in Council documentation, and without consideration of the change from a 10 storey to 4 storey building, came within +
$5 / sq. ft. for the Mady proposal after “adjustments”.
City of Windsor AGO 108
f) As a result of the omission of material financial data, Vindella – not Mady – may have
been selected as the winner on price and the proponent to move on in the RFP process
to compete in negotiations with EllisDon.43
g) The “Price” Financial Analysis is introduced. Administration calculated the annual
operating budget impact as (i) a best case scenario, (ii) a worst case scenario, and (iii)
the “variance between best & worst case = RISK”. Council was not advised that the
“risk” calculated only equalled the price of estimated speculative space rent.
- The “Price” Financial Analysis had no foundation in either the Purchasing By-Law or
the ordinary law governing RFPs and tendering.
- By July 2002, Administration had gone through the motions of the RFP process – but
the importance of the process was only in appearance. Ignored in the “Price” Financial
Analysis were material cost factors of the RFP requirements, such as LEEDS, Life
Cycle Costing and the Civic Urban Design Study.
- The weaknesses of the “Price” Financial Analysis were significant and will be
presented in a detailed analysis later in the audit report.
D. August 2002: Issues of Transparency in Reporting to Council & Fairness to the
Proponents
The following comments represent examples of the division within Administration on
the evident disparity between the “technical” and “financial” aspects of the RFP
matrix requirements in the information presented by Administration in the various
reports to Council.
a) The RFP requirements continued to be discussed in the project reports to Council,
giving the appearance that they were being considered in the financial analysis, but
they were not.
b) The reporting discussion of the Vindella proposal provides clear examples of how the
proposal is deficient – without going as far as to acknowledge that it was non-
compliant, or to accept that it should not be permitted to proceed further because of
these deficiencies.
43
The purpose of this audit comment is to show examples of the errors in the process. The legal memorandum is clear, that
EllisDon should have been declared the winner in the RFP process, which won EllisDon the exclusive right to enter into
negotiations with the City. Because the City formed a “Contract A”, it was not lawful to put a non-compliant proponent with the
lowest ranking in the RFP matrix against one with the highest ranking in the RFP matrix into a bidding contest.
City of Windsor AGO 109
c) Certain members of junior Administration attempted to stand firm in support of the
RFP process by providing comments for inclusion within the reports to Council to
reflect the impact of the RFP evaluation. For example:
“The Windsor Civic Square Urban Design Study may be understood as having
established a quality benchmark for all development in the City Hall Precinct”…
“The Vindella submission explicitly rejects incorporating certain important
features…”
And, “EllisDon’s LEEDS rating is 30% higher than Vindella’s…this superior
rating offers the advantage of more favourable building operating costs…”
And, “The EllisDon proposal is the preferred option if the building’s attributes and
long-term operating costs are the predominant criteria for judging…” “While the
Vindella proposal is the preferred option if building price is predominant…”
The problem with this last quotation is that building price had already been given a certain
weighting in the RFP matrix that was not predominant, and that weighting had been
presented to the proponents as the basis for the competition, in effect, as the rules of the
game. This wording in the presentation to Council, “if building price is predominant”, gave
the impression that it was permissible – and fair to compliant proponents – to change the
rules in the middle of the game to make building purchase price predominant, without
redoing the entire RFP process.
Further, these quotations show that some members of the Administration were aware of the
important differences between “Price”, “Cost” and “Value for Money” and addressed these
financial considerations in the discussion of the report to Council. However the “Price”
Financial Analysis remained focussed on “Price” and "Speculative Space" and ignored
“Cost” and “Value for Money”.
The problem
information
repeated.
E. September 2002: Continued Issues through to the Award of the RFP:
a) This report to Council presented the non-compliant Vindella proposal as an eligible
proponent, maintaining the appearance that it was still the lowest compliant bid in the
running for the award of the contract.
b) The inclusion of Vindella at this stage of the process gave the appearance that (i)
although one proposal was “technically” superior to the others, that superiority was
merely “technical” (a somewhat negative description) that had not taken the very
important factor of cost into account at all; and (ii) all had passed the RFP evaluation,
thus leaving price as the final decision criterion for Council to consider.
City of Windsor AGO 110
At the time the
Award decision was
placed before
Council,
Administration
included specific
examples of
Vindella’s possible
non-compliance and
areas of the
proposal that
Administration was
unsure of.
c) As was done in August, only some of the RFP requirements are discussed which gave
the appearance that the matrix was given consideration in the financial analysis or
final decision, when it was not.
d) As was done in August, the report’s discussion of the Vindella proposal provides clear
examples of how the proposal is deficient in attempting to meet the RFP requirements;
without going as far as to include the word “non-compliant”, and recommending its
outright rejection. Examples include:
The Civic Square Urban Design Study. Compliance required per CR292/93.
- The report states “The following table summarizes how the documents provided by
each proponent address the most important aspects of the 8 design guideline
areas.”
- The following compliance concern comments are reported for the Vindella
proposal. It is reasonable to anticipate, that in order to address these concerns,
Vindella would be required to change the price of the proposal and / or design of
the building, which cannot lawfully be permitted once the deadline for submitting
complete proposals has passed.
o “Arcade of unspecified dimensions offered as $50,000 extra. If provided would
reduce office sq. ft’g on ground floor.” “Streetscape development approach not
documented”
o “..one important functional aspect of the building project which needs to be
confirmed is how loading docks and refuse collection would be accommodated
in the Vindella proposal while maintaining required ground floor spaces
specified in the RFP.”
o EllisDon is identified as “Strong” adherence to the Urban Design Study
guidelines, and Vindella is identified as “Moderate”.
The LEEDS Rating
- EllisDon is reported as achieving a “Silver” grade, which was 30% higher than
Vindella’s “Bronze” rating.
- LEEDS costs were not considered in the “Price” financial analysis. The report
states, “Higher LEEDS scoring translates into ongoing operating savings;
however, we are unable to quantify the potential impact at this time.”
City of Windsor AGO 111
Life Cycle Costing (LCC)
- The report to Council is silent on this material long term cost consideration.
- Life Cycle Costing was not considered in the financial analysis.
- LCC has a major impact on the ability of the City to achieve value for money. The
importance of LCC is so strong, that it has been addressed in a recommendation to
this audit report.
5.5 The Adequacy and Fairness of the “Price” Financial Analysis
The closer a
proposal came to
fully meeting the
RFP wish list, the
lower the
probability of being
chosen.
How and Why did
this happen?
The City asked for
the proponents to
meet requirements
and to suggest
amenities – but the
financial analysis
did not take many of
these factors into
consideration.
Result: The less
responsive the
proposal, the better
As noted above, it appears that the City’s final decision to select Vindella was based on its
“Price” analysis, which had two parts:
1. Comparison of total construction price, and
2. A narrow financial risk analysis
The calculation of building ownership risk (as defined by Administration: Difference in
Annual Operational Budgetary Impact) encompassed consideration of only one variable –
the current price of the current un-leased space in the 400 CHS building. Audit found it
unexpected and unreasonable for a project of this magnitude that building ownership risk
would be defined this narrowly.
The City’s RFP set out various essential requirements and further requests for additional
amenities. The financial risk calculation of the “Price” Financial Analysis was so flawed
that any proposal which fully met the stated City requirements or requests was placed at an
immediate and uncontrollable disadvantage in comparison to a proponent that did not meet
the City’s requirements or requests. Conversely, the less responsive the proposal, the
greater the probability the proponent had to be declared the winner of the RFP process.
This was obviously a perverse result.
The City required proposals to meet the RFP’s product, cost and schedule requirements of:
- Drawings
- Building Design / Function
- Parking Requirements
- Additional Amenities
- Price Proposal
- Life Cycle Costing
- Total building size
- Compliance to the Windsor Civic Square
Urban Design
- Sustainable Design (LEEDS, Leadership in
Energy and Environmental Design)
- Outline Specifications / Standards
- Project Schedule
City of Windsor AGO 112
the proposal looked
in the financial
evaluation.
The “Price” Financial Analysis ignored this balanced, comprehensive approach to quality
and cost. It consisted, in part of a narrow, risk based financial analysis that returned results
in what Administration defined as the annual impact of the proposal on the City’s operating
budget greater than zero dollars. (Budget Neutrality).
Ignored in this analysis were material cost factors of omitted RFP requirements, such as
LEEDS, Life Cycle Costing and the Civic Urban Design Study. The City had asked for all
of these things, presumably because it believed that each required item would have an
intrinsic value with an attached cost. Yet, ultimately, the City went with the lowest short-
term price proposal, which did not meet the RFP requirements and received the lowest score
on some of these City-requested items.
The best way to demonstrate the impact of the “Price” Financial Analysis is to quantify the
effect of the omitted RFP requirements. Given the lapse of time and the absence of
financial estimates and information, it would be extremely difficult and subjective to
attempt to quantify the impact of LEED’s, Life Cycle Costing and the Windsor Civic Urban
Design Study. However, we were able to analyze the “Price” financial risk analysis which
was defined as the annual impact of the proposals on the City’s operating budget greater
than zero dollars. (Budget Neutrality). Our analysis is based on the City’s Requested Total
Building Size.
5.6 Building Size as the Sole Risk Analysis Criterion & the Impact on the
“Risk” Criterion Used for the Recommendation to Award the RFP
A. The City’s Requested Total Building Size
It would appear logical from the RFP building size requirements that if a proponent
submitted a Stage 2 proposal with 142,600 sq. ft., the City would view this proposal
favourably for this criterion, as it would meet the City’s stated need. However, under the
risk analysis of the “Price” Financial Analysis of procurement, this was not the case.
The City’s “Total Building Size” requirement was consistent through stage 1 and stage 2:
- The City’s RFP Stage 1 stated: “The City of Windsor has a requirement for up to
13,250 usable square metres of office space…”
- The City’s RFP Stage 2 seemed to be consistent with Stage 1, which stated: “The
total building size is estimated to be 13,250 m2 (142,600 sq. ft.).”
City of Windsor AGO 113
The City asked for
an estimated
building size of
142,600 sq. ft.
The City’s estimated
building space
needs changed, but
only after the RFP
Stage 2 proposals
had been received
and the deadline
had passed.
B. Change in the City’s Building Size Needs
May 10, 2002 was the deadline set by the City for the Stage 2 RFP proponent submissions
to be received by the City. After this deadline had passed the City was informed that a
major expected tenant would not be leasing space. Therefore, approximately 30,000 sq. ft.
of the City’s requested total building size no longer had a designated tenant. The
alternatives then were to remove the space from the design requirements or to keep the
space and hope to find another tenant.
The July 2002 Administration in-camera report to Council states: “…during the interview
process (June 2002) the City of Windsor received notification that MCSS (province) would
no longer be part of the project…As a result there is now additional speculative space in the
building based upon the original terms of reference and the corresponding proposals.”
City Administration
redefined the total
office space need to
be 111,500 sq. ft.
C. City Administration’s Analysis of the RFP Stage 2 Proponents’ Proposals
There were three key Administration reports to Council providing information and analysis
of the proposals responding to the RFP. These reports were dated July 18, 2002 (in-
camera), August 21, 2002 (in-camera) and September 4, 2002 (open session # 8652).
Consistent throughout these three reports (but not clearly stated), Administration redefined
the total office space requirement as 111,500 sq. ft., a decrease of 31,100 sq. ft. from the
City’s RFP Stage 2 requested estimate of 142,600 sq. ft. Any office space greater than
111,500 sq. ft. was now treated by Administration as speculative space, and a risk. The
proponent who had offered to provide the most space for the City’s dollar thus
automatically became characterized as having the riskiest proposal.
City of Windsor AGO 114
The use of this new
value was
inadequate for
Council's purposes
and unfair to the
proponents.
Table 1: Various Table Extracts from the July 2002 Administration Report to Council
Vindella Mady MKT Ellis Don
(1) Net Rentable Office Space (sq. ft.)
136,980
181,242
142,596
142,800
(2) Speculative Square Footage
included above (including space that
held for provincial government)
25,480
69,742
31,096
31,300
(3) Rent for Speculative Space
($15.00 per sq. ft. excl. c.a.m.)
$382,200
$1,046,130
$466,440
$469,500
(4) Variance (RISK)
$382,200
$1,046,130
$466,440
$469,500
Table 1 Comments: Speculative Square Footage, on line (2) above:
The least amount of speculative space was considered the least risky. Based on the above,
Vindella, with the least speculative space, was considered favourably as the lowest risk.
The AGO considers the analysis to be flawed as:
a) Vindella’s proposal was considered favourably even though the building size was 5,620
sq. ft. less than the City’s RFP Stage 2 request for a building size estimated at 142,600
sq. ft. This non-compliance with the space requirement may well have contributed to
the lower price in the Vindella proposal.
b) As at May 10, 2002, the RFP Stage 2 deadline date, the province was still anticipated to
be a tenant, and its estimated space needs were included in the RFP Stage 2 building size
estimate of 142,600 sq. ft. Yet the City based the analysis on 111,500 sq. ft. as if the
province was not going to be a tenant, without allowing all of the proponents to reduce
their proposed building designs and the resultant costs to 111,500 sq. ft.
c) The “Price” Financial Analysis effectively penalized the highest ranked proponent for
the City’s loss of a planned tenant (a risk that was not within the control of the RFP
proponents). Administration’s definition of speculative space as space greater than
111,500 sq. ft. was inconsistent with the RFP Stage 2 request for an estimated 142,600
sq. ft. Illogically, this put any space-compliant proponents at an immediate
disadvantage, compared to a proponent that failed to comply by offering significantly
less than the RFP-required space.
City of Windsor AGO 115
If the province had
decided to become a
tenant, the Vindella
building would have
been too small to fit
them.
d) The City was still negotiating a potential lease with the Province up to June of 2002, a
month after the RFP closed. Vindella’s proposal was too small by 4,520 sq. ft, to
accommodate the provincial Government’s space needs.
e) Project documents include comments from Administration stating that the Province did
not elect to withdraw, but rather, the City responded with lease rates that were too high
to win the contract under the Province’s RFP process. The Vindella proposal’s space
shortfall now became a winning attribute.
f) MKT’s proposal fell short of the RFP request by an insignificant 4 sq. ft., but was shown
as having 31,096 sq. ft. of speculative space. Illogically, MKT was placed at an
immediate disadvantage when compared with Vindella who was 5,620 sq. ft. short of
the RFP space request, and therefore showed a lower, 25,480 sq. ft. of speculative space.
Analysis: Numbers
if the City’s RFP
Stage 2 building size
estimate of 142,600
sq. ft. was used.
Table 2: What Would Have Been the Result Using the City’s RFP Stage 2 Building Size
Estimate of 142,600 sq. ft.?
Vindella Mady MKT Ellis Don
(5) Net Rentable Office Space (sq. ft.)
136,980
181,242
142,596
142,800
(6) Speculative Square Footage
included above (excluding space that
was held for provincial government)
0
38,642
0
200
(7) Rent for Speculative Space
($15.00 per sq. ft. excl. c.a.m.)
0
$579,630
0
$3,000
(8) Variance (RISK)
0
$579,630
0
$3,000
Table 2 Comments:
g) Vindella’s proposed space was insufficient by 5,620 sq. ft. The analysis would not have
identified the risk that the building was too small (a situation that would not have existed
had the RFP been followed).
h) Reflected here, the EllisDon proposal shows a trivial risk variance. Even at this stage, in
consideration of price and the overall superiority of the proposal, EllisDon seems the
prudent choice for the award of the RFP.
City of Windsor AGO 116
D. July 2002 Report to Council: Administration’s Definition of Building Ownership
Risk
Administration’s July 2002 in-camera report defined building ownership risk as:
“The risk in this option is one of annual operational budgetary impact on the
Municipality with ownership.”
The expression “the risk” implies that there was only one risk. However, this “risk”
represented only one factor, which was Administration’s revised definition of speculative
space. Therefore, the other, more significant risks were ignored in reports to Council, and
in assessing the RFP proponents.
As a reminder, Administration calculated the annual operating budget impact of (i) a best
case scenario, (ii) a worst case scenario, and (iii) the “variance between best & worst
case=RISK”.
However, as can be seen above in Table 1, lines (3) and (4), the “risk” calculated only
equalled the estimated speculative space rent. After these calculations were shown,
variance/risk was set out as per Table 1 line (4) above. Administration then went on to say:
By way of the report
recommendation,
Administration
placed focus on the
project award solely
on the financial
analysis (which
disregarded most of
the requirements of
the RFP)
“The variance between best and worst case scenario is the amount of risk the
Municipality must consider as the cost of owning this facility on an annual basis.
The level of risk the Municipality is willing to accept should always be minimal.
Therefore, in evaluating risk of the above the proponent with the lowest risk under
ownership to the City is the Vindella proposal. This is because their proposal has
the least budgetary impact on the City. However, this proponent was ranked the
lowest in our RFP technical review. Ellis Don ranked the highest in the technical
reviews. It should be noted that the building and parking amenities of both
proponents are very similar. Both have two floors of underground parking and are
very similar in size.”
There were
significant cost
savings
opportunities that
were not in the
financial analysis.
E. Additional Cost Savings Were not Considered
The material RFP attributes of Life Cycle Costing and LEEDS energy savings were
captioned, but not included, in the financial analysis by Administration. The August and
September 2002 Administration reports’ best and worst case scenario calculations are
footnoted with, “this does not reflect potential operating savings of the development”.
Why not? That major omission was never explained.
City of Windsor AGO 117
At a minimum, the reports to Council should have stated why potential operating savings
were not shown. The exclusion of potential annual operating savings, in a project of this
magnitude, for the lifetime of the building, would seem sufficiently significant to require
disclosure and discussion within the body of the report, instead of being shown as an
incomplete table footnote.
To illustrate potential operating savings, we provide the following simplified examples:
- The EllisDon proposal purported to have qualified the City for a capital cost rebate
to a maximum amount of $250,000 under the Government of Canada Commercial
Building Incentive Program (CBIP).44
- The completed 400 CHS building under the Vindella proposal did not qualify for
this incentive.
- The EllisDon proposal purported a savings of 20% in annual lighting and electrical
power, by way of its building design and materials. The 400 CHS building hydro
costs averaged $232,000 per year for 2007 and 2008. A 20% annual savings of
these energy costs would amount to an estimated $46,400 every year, over the life
of the building. Over 20 years, the cost savings forgone is estimated to be
$928,000.45
In July and August
of 2002, Vindella
was in the lead in
the RFP, based on
the “Price”
criterion.
F. A Material Omission Causing a Critical Error
Table 3: Risk Results Reported in July and August of 2002
Variance
(RISK)
Vindella Ellis Don*
Jul 02 $382,200 $469,500
Aug 02 $382,200 $595,500
* August report to Council: EllisDon’s total office space, speculative space, best and worst case scenarios
and variance “risk” include 8,400 sq.ft. of optional amenity space from EllisDon’s Stage 2 proposal.
Inconsistently, in the same reports, EllisDon’s price was shown without the optional amenity space.
To note: there was no actual change to the EllisDon proposal, the change in value shown from July to
August is a result of the inconsistency of reporting optional amenity space.
44
CBIP offers a financial incentive for the incorporation of energy efficiency features in new commercial/institutional building
designs.
45
This is a simplified analysis that does not take inflation or present value of money into consideration.
City of Windsor AGO 118
In September, the
tables turned and
EllisDon was now in
the lead – now being
“less risky” than
Vindella.
Table 3 Comments:
Administration’s August 2002 report to Council was consistent with the July 2002 reported
risk presentation, although with less commentary. In both reports, Vindella was shown as
less risky.
Table 4: Risk Calculation for Variance (Risk) Not Shown in September of 2002
Variance (RISK) Vindella Ellis Don**
Best Case Scenario ($91,019) $263,738 ***
Worst Case Scenario $551,041 $859,238
Net Variance (Risk)* $642,060 $595,500 ****
* The September report included the values for the best case and worst case scenario, but the net calculation
for Variance (Risk) was not shown.
** September report to Council: EllisDon’s total office space, speculative space, best and worst case
scenarios and variance “risk” include 8,400 sq.ft. of optional amenity space from EllisDon’s Stage 2
proposal. Inconsistently, in the same reports, EllisDon’s price was shown without the optional amenity
space.
*** Calculation error corrected. Report to Council shows Best Case Scenario as $363,738
**** There was no change to the EllisDon proposal, the change in value shown from July to August,
carried through to September is a result of the inconsistency of reporting optional amenity space.
Table 4 Comments:
Administration’s September 2002 report to Council was generally consistent with the
August 2002 report’s risk presentation. However, the final risk calculation, Variance
(Risk), included in Table 4 above, was not shown in the September report.
If the final risk calculation had been displayed, in a manner consistent with the previous
reports, EllisDon would now have been shown to be less risky. There was no commentary
to inform Council that contrary to prior reports, EllisDon was now the “winner” under this
risk criterion. This was a critical omission, for which we were unable to obtain any
explanation.
City of Windsor AGO 119
What happened?
Why did the risk
results switch?
Why did the risk results switch?
- During post-closing negotiations with Vindella, it was allowed to increase its space in
order to become compliant with the RFP, including ground floor requirements, and also,
to meet the City’s requested building setbacks.
- Under the flawed “Price” Financial Analysis, Vindella’s building was now the larger of
the two, now had the most speculative space, and now was the more risky of the two
proposals.
What does all this
mean? What is the
risk involved?
The City should be
concerned. Based on
the results of the
audit, the AGO found
the unfair “Price”
analysis and reporting
to Council exposed the
City to significant risk.
The practices
highlighted in this
audit have the
potential to damage
the City’s goodwill
and have a negative
affect on future
investment and
business relationships.
G. The Conclusion of the Legal and Audit Review of the 400 CHS RFP Procurement
Process
The results of this audit demonstrate that if this procurement process had been faithful to the
principles of the City’s Purchasing By-Law, the process would have been consistent with
best practice.
a) By design, the By-Law stipulates a fair and even process that, if followed properly,
encourages numerous competitive proposals in future RFPs and protects the City
from making wrong choices that are likely to be unfair and result in costly law suits.
b) The RFP procedures that are governed by the Purchasing By-Law and consistent
with the common law of bidding and tendering provide a best practice approach for
the City of Windsor, to achieve “Value for Money” 46
in procurement activities.
c) When, as in this case, these laws are circumvented, the legal and value for money
protection is lost.
These actions of the City under this project had the following impact: The City risked
damage to future business relationships including the ability to attract quality proponents
and quality investment, damage to relationships between Council and City staff, and created
the risk of legal action against the City, members of Council and members of senior
Administration. Of lesser importance, but still important, were the costs, time and resources
expended to achieve this outcome.
We have made recommendations to address the conditions that caused the problems on the
400 CHS RFP evaluation. If implemented, these should effect positive change to the City’s
management culture and municipal governance. This will involve some changes to the
City’s By-Laws, procurement practices and internal controls.
46
Value for money is a term used to assess whether or not the City has obtained the maximum benefit from the goods and
services it both acquires and provides, within the resources available to it, in accordance with the laws, principles, guidelines and
standards of the municipality.
City of Windsor AGO 120
6.0 LEGACY COST REPORTING
We cannot report on the
legacy costs at this time.
We are requesting the
Audit Committee provide
direction to the AGO as
to how to proceed.
The Audit Committee, at the meeting of February 17, 2009, requested the staff of the
Auditor General’s Office work with Administration to report back on the “Legacy
Costs” of the 400 CHS building for the following topics of an Administrative
response to the 400 CHS review Report I.
"The audit report should also consider whether the City received good value for
the money such as:
– The building accommodation of 200 more City staff (and workstations)
than originally planned totalling an additional 29,690 square feet of fit
up.
– The replacement value of the building is substantially greater than actual
construction costs (reference: R.S. Means Building Construction Cost
Data)"
The goal of the “Value for Money” analysis was to report on the value of the cost
savings achieved by the City. We requested, but were not provided with the
information from Administration required to conduct the necessary audit steps in
order to complete the value for money analysis. We would like to advise Council
and the Committee that this information insufficiency arose in dealing with a past
member of senior Administration.
On November 9, 2009 the AGO brought this issue to the attention of the Current
CAO. She communicated that she is fully supportive of addressing the scope
limitation and was willing to provide any available information, should it be
available. On November 23, 2009, Administration provided the information to the
AGO.
The topic was added to the 400 CHS report II audit plan by the Audit Committee and
AGO staff is required to do the work as assigned unless otherwise directed by the
Committee. Based on the Lead Auditor’s preliminary assessment of the new
information, more time, data and cooperation from Administration would be required
to complete such a review. It is not recommended that Audit pursue completion of
this review, as the element of timeliness has passed, and the audit would delay work
progress on the annual audit plan.
City of Windsor AGO 121
Appendix B: Summary of Recommendations and Management Comments
Audit Recommendation
Agre
e
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 1.
Develop a Strategic Plan to Address Audit Recommendations
To maximize the opportunity to enhance effectiveness and to
achieve efficiencies in the implementation of the 400 CHS
recommendations, we recommend the CAO consider the merits of
addressing the recommendations of this review as a package,
through the development of a comprehensive strategic plan that
may include a review of risk, the City‟s current strategic plan &
corporate initiatives, resource requirements, etc, and to respond to
this audit recommendation with a date that Administration may
report back to the Audit Committee with an action plan and
timeframes of the packaged plan.
For a good chance of success, Council should be requested to
commit to the following:
(1) A long term advancement strategy to deal with the
recommendations of the review provided to assist Council
and Administration in addressing weaknesses in the City‟s
governance system that expose the City to significant risk.
(2) Long term support that empowers Administration to
develop, implement and maintain the strategy. Such
support will potentially require additional costs and
dedicated resources to achieve improvement.
To implement all of the
recommendations contained herein
through the use of a “task force” on a
concentrated effort basis would
require full time dedication of a
knowledgeable individual and part-
time effort of specialized resources
such as the Purchasing Manager and
City Clerk for an extended period of
time. This is estimated to be
approximately six (6) to nine (9)
months. Funding for these temporary
resources may be able to be directed
from the approved funding for the
Office of Continuous Improvement.
It is important to acknowledge,
however, that dedication of these
resources, largely to policy research
and writing, while a worthy task,
would detract from other worthy City
objectives that are underway or
planned for the near future. Another
approach worth considering is the
continuation of the steady, continuous
improvement that has taken place
over the past seven years as
evidenced in the management
Early in the new year, Administration
will bring a comprehensive report to
council in order for Council to be
able to make a fully informed
decision as to the best course of
action related to this matter.
The report will outline the
considerable progress already made
over the last several years with
regards to many of these
recommendations. Additionally, the
report will also provide options for a
deadline driven, “task force”
approach to dealing with any
remaining issues, and a more
incremental approach consistent with
the steady, continuous improvement
that has characterized our approach
over the past several years.
While both approaches have merit,
the deadline driven “task force”
method would require much more
human and financial resources and,
therefore, its benefits will need to be
weighed against the benefits that will
City of Windsor AGO 122
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
comments contained in this
document.
not be achieved though other
initiatives that will by necessity need
to be postponed or eliminated.
These comments on the action
plan/timelines are applicable to each
of the recommendations in this
document.
Recommendation 2.
To Correct the Structural Insulation of Council‟s Access to Timely,
Independent Legal Advice through an Amended Procedural By-law
Number 420-2001 or a Separate By-Law
We recommend that the CAO review the merits of the legal
recommendation of Miller Thomson LLP, and develop a policy for
Council review and approval to correct the issue of the structural
insulation of the Mayor and Council, by way of By-Law or By-Law
amendment. This correction is recommended to provide the Mayor
and Council access to timely, independent legal advice from the
City Solicitor. And further, to remove the reporting independence
conflict of the City Solicitor, which currently serves as a barrier to
the City Solicitor‟s obligation to act in accordance with his or her
legal duties and other duties, such as those required as an Ontario
Lawyer under the Rules of Professional Conduct of the Law
Society.
Recommendation of Andrew Roman of Miller Thomson LLP:
“We would recommend that the independence of the City Solicitor
be enshrined either in an amended Procedural By-law Number 420-
2001 or within a separate By-law (to be made consistent with an
amended 420-2001) called “Terms of Reference for the City
Solicitor of the City of Windsor”. This By-law would be available
X
As a result of a senior management
reorganization approved by City
Council on 10/27/09, the City
Solicitor now reports directly to the
CAO. This aspect of the structural
concern expressed in Mr. Roman‟s
legal memorandum dated 10/27/09
was brought to the attention of City
Council as part of the verbal
presentation by the CAO on this date.
City of Windsor AGO 123
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
to all Councillors and staff of the City and available to the public
on the City‟s website, like other municipal by-laws. This expanded
role for the City Solicitor would be set out in much the same way
that the Terms of Reference for the Chair, President and certain key
officers of many Canadian public companies are, and are made
available to the public as a function of good corporate governance.”
Recommendation 3.
The Removal of Structural Impediments to an Effective
Corporate Communication System through the Development of
Policy and Amendment to Procedural By-Law 420-2001
That Administration develop a protocol for Council review and
approval to correct the structural issues (relating to or resulting
from the organization or functioning of a political or economic
system) that threatens the health of the City‟s communication
system; the purpose of which is to preserve the flow of timely,
appropriate, relevant and critical information from the
Administration to the Mayor, Council and CAO.
We recommend the policy include the following development of
policy and amendments to By-Law number 420-2001:
i) A City policy that defines the duty of the CAO, General
Managers and each Department Head to report information
up a defined chain of command, where he or she becomes
aware of a level of risk being taken that is unacceptably
high to the City of Windsor. (Related City policy includes
the “Fraud Policy and Protocol”, CS.A2.05 under the
control of Corporate Services and “Hotline Protocols”, and
CAE-01-08 under the control of the Auditor General‟s
X
A policy with respect to duty to
communicate will also include a duty
to communicate risk information by
all members of Administration who
become aware of risks.
While there is no disagreement with
the spirit of this recommendation, any
such policy should also include
consequences for frivolous or
vexatious conduct or actions carried
out under these provisions.
It is further noted that this
recommendations appears to suggest
a policy/ protocol to govern the
development of policy. While in
theory this may be agreeable, the
value of such a document, when
written, may be difficult to discern.
Regarding 3 (v), while the value of
the Ethics policy is not questioned,
agreement with this recommendation
does not imply management‟s
City of Windsor AGO 124
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Office.)
ii) The guarantee of no career repercussions imposed on any
staff carrying out these duties should be enshrined by way
of an amendment to Procedural By-Law number 420-2001.
iii) Procedural By-Law number 420-2001 Section 24.1 “Each
Department Head shall act in accordance with any
statutory duties”, should be revised to define the
requirement for the CAO, General Managers and each
Department Head to act in accordance with his or her legal
duties and other duties, such as those required as Officers
and Employees of the Municipality and those under the
Rules of Professional Conduct of the various disciplines to
which he or she may belong. (I.e. Accountants, Engineers,
etc.)
iv) That Procedural By-Law number 420-2001, be amended to
revise the phrase “and control” of Section 24.2, in order to
remove implied structural barriers to the required level of
independence for the General Managers and each
Department Head to act in accordance with his or her legal
duties and other duties.
v) That Administration finalize the Corporate Code of Ethics
policy for City Staff, and bring forward the policy to
Council for review and approval. The City has
implemented a code of ethics policy for members of
Council; however the code of ethics policy for
Administration and staff remains in draft.
concurrence to any inference that
appropriate ethics principles were
contravened by any member of
administration involved in this
project.
City of Windsor AGO 125
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 4.
Establish a “Top Down” Training Initiative, with Mandatory
Components, to Address the Risk of Legal Errors, Damage to
the City’s Goodwill Reputation and the Ability to Attract
Quality Proponents and Future Investment.
To address the identified control weaknesses which lead to the risk
of unintentional errors that may invite legal action against the City,
Council, members of Council and senior Administration, and / or
damage to the City‟s goodwill reputation and ability to attract
quality proponents in the City‟s projects and investment
endeavours, we recommend the following:
That the CAO consider the merits of developing a Corporate
training initiative for the review and approval of Council. The
training initiative should provide for mandatory and non-mandatory
opportunities for Council, Administration and City Staff to be
exposed to ongoing education about the roles and responsibilities of
the basic principles of the laws governing the City as well as
continued professional development and education on emerging
issues and high risk areas of purchasing and procurement or other
identified subject areas.
We recommended a course of mandatory training to include the
exposure to seminars and materials on the basic principles of the
laws that govern the City which:
i) For Council: Acquaints Council with the Municipal Act
and legal requirements for,
a) The Role of Council vs. the Role of
Administration,
X
The Corporation has an active corporate training initiative under the auspices
of the corporate staff development committee.
Additionally, under the direction of the Office of the CAO, staff development
introduced professional development opportunities to orient staff by way of:
o Corporate Coaching
o Employee Mentoring
o Leadership Windsor Essex participation
o Departmental Team Building activities
o Management Windsor Certificate Program
o Master‟s Certificate in Municipal Management
The culmination of these programs have resulted in two nationally recognized
awards for which the Corporation has recently been the recipient for
„recognizing commitment to workplace learning.
Some of the more relevant training courses afforded to management staff
since 2002 include: Project Management, An Introduction to Concepts and
Tools; Policy Development and Analysis; Project Management in Practice;
Technical Report Writing; Procurement Training: Understanding the Cycle;
A Guide to the Purchasing By-law; Procurement Training: Managing,
Designing and Drafting RFP‟s; Accounting and Corporate Budgeting:
Orientation to Risk Management; Report Writing for Council; Municipal Act
Training.
Recommendation 4(i)
The opportunity for training is provided to Councillors at the beginning
of every new Council term – currently this is on a four (4) year cycle.
The orientation includes material pertaining to the regulatory
framework which govern the municipality, the Mayor, Councillors and
Administration and covers such topics as:
City of Windsor AGO 126
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
b) Council and Corporate Governance, and
c) Potential Risk and Liability for Errors Made by
Council, and Individual Members.
ii) For senior Administration: Enhance the ongoing and
valuable training program that acquaints Administration
with the Municipal Act and legal requirements for,
a) The Role of Council vs. the Role of
Administration,
b) Senior Administration, Council and Corporate
Governance, and
c) Potential Risk and Liability to Administration and
Council for Errors Made by the Council, Individual
Members of Council and the Administration.
iii) City Council, Administration and Staff (Purchasing and
Legal staff):
a) Acquaint Council, Administration and City Staff
with the implications of a process that creates the
“bidding contract” and the duties and obligations
that flow, even from a process that does not create
a “bidding contract”.
b) Enhance the ongoing and valuable training
program with other training opportunities to expose
Staff to current and emerging issues in purchasing,
procurement or others as defined by
Administration.
1. Legislative authorities;
2. The role of Council and Administration;
3. the Procedure By-law;
4. Current Corporate Policies and Plans; and
5. The City of Windsor Purchasing By-law.
This training is currently optional to all Councillors, however, in order
to fulfill this recommendation the City Clerk will ensure that the
training is amended to include all topics listed in the recommendation
and will recommend to Council that the training be made mandatory for
all Councillors on an annual basis with a control mechanism put in
place to ensure that the training has been received.
Recommendation 4(ii)
Training for all City Staff regarding the Municipal Act, its meaning and
applicability to the Corporation, has been available since 2008 and has
been provided to many staff members. The training covers material
such as:
1. The governance structure of the City;
2. Role of Council and Administration;
3. Introduction to Municipal Freedom of Information &
Protection of Privacy Act;
4. The process and structure for writing a Council Report, and
the required authorities;
5. The Delegation of Authority By-law;
6. The Procedure By-law;
City of Windsor AGO 127
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
7. The role and governance structures for Agencies, Boards,
Commissions and Committees of Council.
As is the case for all training courses, we are constantly striving to
improve and enhance the content of this training and we will review the
course content with this recommendation in mind.
Recommendation 4(iii)
(a) Since the inception of the current Purchasing By-law in
2004, the following training has been made available to City
Staff:
- Purchasing By-law 101 – A Guide to the Purchasing By-
law
- Procurement Training: Managing, Designing and
Drafting RFPs and
- Procurement Training – A Guided Tour the Tendering &
RFP Process
While the Purchasing By-law training deals with issues specific
to that document, the training regarding the tendering and RFP
process deals with the topics mentioned in this recommendation.
We agree that this training should continue to be made available
to City staff and that Councillors should also be provided this
training.
In addition, in the former Manager of Purchasing & Risk
Management (2004-2007) was afforded the opportunity to
City of Windsor AGO 128
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
attend a two day training session given by Paul Emannuelli, an
expert in the field of Procurement Law, which training was
sponsored by the Osgoode Law School Centre for Continuing
Education, which training focused on many of the procurement
issues raised in this report. Further, the incumbent in this
position who will be resuming her role in February, 2010 after a
return from parental leave, also recently attended this training in
November, 2009.
Finally, we would note that, since 2002, many issues have arisen
in the Municipal arena that have heightened the profile of
procurement issues and procurement law, particularly as related
to public procurement. Many of these issues, such as the
Bellamy Inquiry, have caused the City to review and re-write
the Purchasing By-law and to ensure that City staff be provided
with the training that is so critical and important in this area.
In addition, during the 2003 re-organization, the Purchasing
Division was re-aligned to report to the City Solicitor that is in
keeping with the heightened awareness of the legal issues
involved in every procurement process.
Notwithstanding all of the above, we note that the issues relating
to procurement within this audit report, were discerned with the
assistance of two pre-eminent experts in procurement law who
both indicted that these laws are not commonly understood by
lawyers who do not specialize in this field. Accordingly the
standard of due diligence recommended in this audit, may not be
practically achievable without significant additional funding
dedication on projects of sufficient magnitude to warrant this.
City of Windsor AGO 129
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 5.
To Establish an Accountability Standard of Due Diligence and
Due Professional Care for the Improvement of Information
Reported to Council and the CAO for Decision Making
Purposes.
We recommend that the Administration establish a Corporate wide
control policy for Council review and approval that requires the
preparation of communications or reports to Council and the CAO
in accordance with due diligence and due professional care. This
type of control should lead to better decisions by improving on the
quality and usefulness of information reported to City Council and
senior Administration for decision making purposes, facilitate
transparency through full disclosure, communicate pertinent risk
considerations and establish accountability for the information
reported.
In the 400 CHS project, transparency of project accountability was
not clear due to several factors. Improvement of this condition can
be achieved through enhancements to the City‟s current reporting
protocols as recommended through the development of a Council
approved policy which would:
i) Establish the standard for information to be assigned and
prepared to a defined standard of due diligence and due
professional care as per the following definitions:
a) Due Diligence is the degree of care that a prudent
person would exercise. This would involve the
requirement to assign the work to be conducted to a
person with the requisite knowledge, skill and
experience to complete the required task.
X
As indicated in a previous response,
report writing is one of the courses
that are part of the corporate training
initiative. Additionally,
administration has provided the AGO
with the template currently in use to
guide in the preparation and review of
council reports which is meant to
ensure that reports are
comprehensive, factual, disclose risks
involved, etc. Administration believes
that current procedures and policies
address this recommendation.
However, ongoing improvements will
be implemented stemming from
future training, future developments,
and auditors recommendations.
City of Windsor AGO 130
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
b) Due Professional Care calls for the application of the
care and skill expected of a reasonably prudent and
competent professional in the same or similar
circumstances. Due professional care is exercised when
the analysis and information reported are performed in
accordance with the Professional Standards under
which the author or signatories are bound. (I.e.,
Accountant, Engineer, Lawyer, etc.)
ii) The City should create a policy for the development of
Council reports which helps Council and Administration to
more fully assess the potential risks of making decisions
with full or partial information, and give Council the
opportunity and understanding to accept or reject those
risks. The policy should:
a) Enshrine the understanding that it is incumbent
upon Administration to review and report special
circumstances to Council.
b) Include the requirement for a standardized report
heading for “Important Risk Disclosures”.
c) Make mandatory, that Council reports include a
risk discussion with the requirement to clearly set
out within the report body any significant
information that is not disclosed, why, the potential
impact including the risk of not having that
information, and any compensating information.
d) Where appropriate, include Life Cycle Costing
information to facilitate value for money decision
making.
City of Windsor AGO 131
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
iii) Such a policy should retain the standards and requirements
established in the existing Corporate Services control tool:
The finance checklist for council reports and delegation of
authority reports (r. April 16, 2009).
Recommendation 6.
Formalize & Enhance the City’s Life Cycle Costing (LCC)
Strategy to Provide for Increased Effectiveness, Efficiencies
and Value for Money for the City Of Windsor.
We recommend the CAO consider the merits of developing an LCC
strategy, which has significant value added potential to provide the
City opportunities to achieve better value for money in all its (1)
procurement activities, (2) the delivery of products and services and
(3) in municipal performance measurement.
This audit reviewed the importance of LCC as it relates to an RFP
evaluation and selection process on the basic principle of LCC,
which is to determine the cost of a particular product or service
through the consideration of environmental, social and economic
costs and benefits that occur throughout the life of a product or
service, rather than on price alone. This is but one aspect of the
benefit of LCC, which has far reaching applications:
LCC can assist in making more effective decisions and
better informed procurement choices such as, whether or
not to purchase or lease a specific product or service or
which to select from a range of options.
LCC provides the opportunity to maximize on
effectiveness and efficiencies within in every service,
program, project, etc. that the City delivers.
In this aspect of LCC, there is existing opportunity to
X
The City currently undertakes
significant work relating to Life
Cycle Costing (LCC). This is
especially well developed in the roads
and sewers area. A number of
initiatives are currently underway
aimed at strengthening this aspect of
asset management; initiative related
to the tangible capital assets
requirements being implemented for
municipalities, two projects under the
SDR initiative, as well as the formal
structuring of an asset
management/asset planning function
within the Office of the Chief
Financial Officer (anticipated to be
commenced within part of phase II of
the recent corporate reorganization).
City of Windsor AGO 132
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
maximize on the effectiveness and efficiencies of ongoing
strategic initiatives. Performance Measurement, Asset
Management, the Service Delivery Review, City Projects
and City procurement, are all founded on the principles of
LCC.
As the LCC strategy progresses through maintenance,
experience and sophistication, the City should expect to
continue to achieve measurable improvements in value for
money.
Recommendation 7.
Transparency and Accountability Amendment to the
Purchasing By-Law 400-2004 for any Exceptions to or
Exemptions from the By-Law
Given the significant risk to the City of Windsor involved, it is not
recommended that Council provide approval for the circumvention
of the Purchasing By-Law controls. However, we recognize that
under extraordinary circumstances, such activity may become
necessary. We recommend that the City‟s Purchasing By-Law 400-
2004 be amended to establish accountability and transparency
where exceptions / exemptions from the By-Law are required. We
recommend such amendments to the By-Law include:
i) A statement of the legal authority under which Council is
authorized to approve exceptions / exemptions of the
Purchasing By-Law.
ii) Recognition of the Purchasing By-Law as the best practice
standard to achieve value for money in the City‟s
X
The By-law is currently being
amended. These suggestions will be
accommodated.
City of Windsor AGO 133
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
purchasing and procurement activities. It should be noted
that a circumvention of the By-Law should be the
extraordinary exception rather than the rule.
iii) The requirement for a written report recommendation to be
brought forward to Council by Administration, which
clearly discloses that Council is being asked to approve the
circumvention of the Purchasing By-Law. (A consistent
problem observed by Audit in this, and past audit reviews)
iv) The requirement for the Council report to include a
statement of legal risk and / or recommendation, prepared
by the City Solicitor (or designate) and that the City
Solicitor (or designate) be in attendance to advise Council
during the discussion.
v) The requirement for the Council report to include a
statement of purchasing risk and / or recommendation,
prepared by the City‟s Purchasing Manager (or designate)
and that the Purchasing Manager (or designate) be present
to advise Council during the discussion.
vi) That the decision of Council to approve the circumvention
of the By-Law be clearly and comprehensively
representative of the decision and direction in the resolution
of the Committee of the Whole.
City of Windsor AGO 134
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 8.
Legal Review, Amendments to Purchasing By-Law 400-2004 &
the Requirement for Appropriate Oversight Over the City’s
Purchasing and Procurement Activities
We recommend the CAO consider the merits of the following
recommendations to improve on Purchasing By-Law 400-2004 and
to address the risk of recurrence of purchasing and procurement
issues that were reported in the 400 CHS audit review:
i) That Administration establish within Purchasing By-Law
400-2004, a level of required oversight by the City‟s
Purchasing or Legal department on purchasing and
procurement processes of a specified dollar amount and
complexity. Administration should conduct a review of the
current Purchasing By-Law to determine whether the
coverage of defined Purchasing & Legal department
oversight on purchasing and procurement activities is
commensurate with the purchasing activity and level of risk
exposure to the City of Windsor.
ii) As part of the oversight framework, that the Purchasing By-
Law be amended to include the requirement for a Legal and
Purchasing review and sign off, on specific purchasing and
procurement activities in excess of a specified dollar
amount or complexity involving a Tender, RFP, or other
procurement tool that results in a formed Contract or
Agreement. I.e. Purchasing and Legal sign-off on RFP or
Tender documents to be issued by the City.
X
Recommendation 8(i)
There already exists within the by-
law a level of required oversight
by the Purchasing and Legal
Departments on purchasing
processes of a specified dollar
amount. Every procurement with a
value greater than $10,000.00
must be conducted by the
Purchasing Division
(procurements under this amount
can be done directly by City
departments with assistance from
the Purchasing Division). In
addition, all purchases with an
anticipated value in excess of
$50,000.00 must be made via a
tendering or RFP process that is
conducted by the Purchasing
Division and under the ultimate
supervision of the Manager of
Purchasing & Risk Management
and the City Solicitor. Finally, all
procurements of a value of
$150,000.00 or greater must be
approved by City Council and a
Council Report is written in
support of such procurements
which must be executed by the
City Solicitor and the City
Treasurer.
The current Purchasing By-law is
under review and all levels of
City of Windsor AGO 135
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
iii) That Administration commission the City‟s Legal Services
department to conduct a legal review of the Purchasing By-
Law in comparison to the legal memorandum appendix A
to this report created by Andrew Roman of Miller
Thomson. The legal review should compare the By-Law
and the legal memorandum to look for additional
opportunities for improvement and / or legally required
changes to Purchasing By-Law 400-2004.
iv) We recommend that Administration address the specific
legal concern identified in Appendix A, that Purchasing
By-Law 400-2004, “contains a number of provisions which
could be interpreted as attempting to give the City the right
to treat proponents unfairly.”
oversight and authority will be
reviewed in this exercise.
Recommendation 8(ii)
Please see item 8(i) above.
Recommendations 8(iii) and (iv)
This will be undertaken as part of
the current review of the
Purchasing By-law.
City of Windsor AGO 136
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 9.
Amend Procedural By-law Number 420-2001 to Ensure The
Requirements of the By-Law for the Establishment of
Committees Approved by Resolution of Council Are Carried
Out
By-law Number 420-2001, Part 19 and Appendix B, b), ii sets out
specific actions that are required to take place, upon approved
motion by the Committee of the Whole to form a Special
Committee of Council/Advisory Committee or Task Force.
However, there is no control mechanism in place to ensure the
required actions are carried out.
We recommend that Procedural By-Law 420-2001 be amended to
include language which defines the responsibility of person(s) or
position(s) required to report back to the Clerk in order to fulfil
requirements of Appendix B, b), ii of the City‟s Procedural By-
Law. And that the By-Law be revised to include a control
mechanism to ensure that the requirements of the By-Law are
carried out to the satisfaction of the Clerk, or other defined
accountable Head.
X
Recommendation 9
As part of the Corporate re-
organization of 2003, the position
of Manager of Council &
Committee Services/Deputy Clerk
was created. It is the role of this
position to ensure that the
Committees of Council are struck
in accordance with the Procedure
By-law and that all have clearly
defined roles and mandates. As a
result, since this position was
filled in 2004, all Council
Committees have prepared
mandates which are reviewed
annually and which are revised as
required after this review. This
position is also responsible for the
supervision of the
Council/Committee Coordinator
and the Committee Coordinator,
both of which positions provide
ongoing support to Council
Committees. The Manager
engages in continuous
improvement with the
Coordinators to ensure that the
Committees stay within and fulfill
their mandates. In these ways,
Administration is of the view that
the Corporation has progressed
substantially since 2002.
Further, as part of the Service
City of Windsor AGO 137
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Delivery Review, one of the
foundational projects is the
governance review of all
Agencies, Boards, Commissions
and Committees of Council. As
part of this review, all aspects of
the governance and operation of
Council Committees will be
reviewed and streamlined keeping
in mind the requirements of the
Municipal Act and the best
practices of other municipalities.
As part of this review,
Administration is committed to
ensuring that this recommendation
is addressed and that any
necessary amendments are made
to the Procedure By-law.
Recommendation 10.
Governance / Project Management / Oversight Improvement
There should be a requirement for projects requiring City funding
in excess of a specified amount, that the City Solicitor (or
designate) be assigned to the upper tiers of project Committees
(such as those with a three-tier project management structure
recommended in the Brodele Report) with a defined role to be
present to provide pro-active legal advice and recommendations to
Council and Administration in order to keep projects from steering
off-side legally.
X
Dollar amount will be defined within
the purchasing by-law and the new
City Solicitor by-law.
City of Windsor AGO 138
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Recommendation 11.
Attach Project Management Improvement Recommendations
to Report I
The recommendations towards improvement to the City‟s
project management process within this report should be
incorporated into the Project Management Methodology
currently being developed by Administration as per the audit
recommendation adopted in the audit report issued in February
2009 entitled, “Post Construction Audit Report on the 400 City
Hall Square East Building”.
That the City of Windsor establish an adequate and effective
project management methodology that provides standard methods
and guidelines to ensure that projects are conducted in a
disciplined, well-managed and consistent manner and; to promote
the delivery of a quality project that will be completed on time,
within budget and in accordance with the project specifications.
X
As of the date of these comments,
City Council has not yet adopted the
Part 1 recommendations of the AG
Office as they have not been formally
presented.
Implementation will commence upon
adoption by City Council.
Recommendation 12.
Project Management Improvements
There should be a requirement, for all future discretionary City
projects requiring City funding in excess of a specified amount,
that Administration must prepare and submit a comprehensive
business case analysis for the purpose of making supportable and
prudent investment recommendations to Council.
Council decisions regarding the approval of major projects such as
the 400 City Hall Square building should be based on a standard of
X
Many of these suggestions have been
implemented. It should also be noted
that the project management
methodology recommended in the
Brodel report has already been used
on two large projects. A formal
threshold needs to be defined in order
to clearly identify those projects to
which this increased level of due
diligence (which can be very costly
and time consuming) will be applied.
City of Windsor AGO 139
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
information established by Administration to include the
identification and documentation of key decision factors such as
clear objectives, analysis of alternatives, expected outcomes,
critical success factors, an environmental risk assessment and risk
mitigating measures, cost/benefit analysis, financing plans, scope
and impact of the project.
Recommendation 13.
Project Management, RFP and Tender Control Improvements
We recommend, as identified in the legal memorandums Appendix
A, Part I RFP and Part II Furniture Tender to this report, that
Administration should establish model documents for its bid
processes and for its true request for proposal so that the process
elements are constructed with the needs and obligations of the City
in mind, while risk is controlled.
The City, in the design of this control should include:
i) The RFP or Tender should specifically incorporate the
Purchasing By-Law to have the effect of providing By-Law
guidance as to what is and is not a compliant proposal.
ii) The development of standardized procurement documents
for Tenders and Proposals with the assistance of purchasing
/ procurement specialists. An advantage of such a control
is that it promotes effectiveness & efficiency, mitigates risk
and helps to preserve the continuity of operations where
experience leaves the corporation.
iii) The requirement for periodic reviews of the standardized
procurement documents to assess compliance to changes to
law and to fine tune for past experience in using the tool.
iv) The initial model documents to be approved by the City
X
Recommendation 13(i)
The City‟s current specifications already contain a provision that the
tenders will be reviewed for compliance in accordance with the
Purchasing By-law however, Administration will certainly review this
recommendation and enhance the current language as appropriate as
part of the current review of the Purchasing By-law.
Recommendation 13(ii)-(iv)
The City does currently have a “standardized” specification that has
been developed in accordance with the Purchasing By-law and industry
best practices, In addition, the City does have templates for Request for
Proposal Documents that have also been developed in accordance with
industry best practices. In the spirit of continuous improvement,
Administration would be happy to review this template as
recommended.
Recommendation 13(v)
Such a checklist does currently exist with respect to bid irregularities
and the action to be taken, and is found in the Purchasing By-law
(Schedule C). In light of this recommendation, this schedule will be
reviewed as part of the current review of the Purchasing By-law.
City of Windsor AGO 140
Audit Recommendation
Ag
ree
(X)
Dis
agre
e
(X)
Management Comments
(Required only for recommendations
where there is a disagreement)
Action Plan /
Time Frame
Solicitor (Legal).
v) The development of a mandatory use checklist that includes
triggers such as, the required rejection of any bid or
proposal or the required interaction / approval of
Purchasing and / or Legal.
City of Windsor AGO 141
Appendix C: Glossary of Terms
Term Explanation
Summary of Terms to Define Staff, Persons and Council
City or The City Refers to events, actions and / or decisions made at the level of, or with the knowledge of the top
tier of the City’s governance structure, which includes Council, or members of Council and senior
levels of Administration.
Also meaning, the City of Windsor
Council or
City Council
The group of elected officials of the City of Windsor, with responsibilities defined under the
Municipal Act, 2001 and other, related laws, as including:
(a) to represent the public and to consider the well-being and interests of the
municipality;
(b) to develop and evaluate the policies and programs of the municipality;
(c) to determine which services the municipality provides;
(d) to ensure that administrative policies, practices and procedures and controllership
policies, practices and procedures are in place to implement the decisions of council;
(d.1) to ensure the accountability and transparency of the operations of the
municipality, including the activities of the senior management of the municipality;
(e) to maintain the financial integrity of the municipality;
Councillor The title assigned to a Member elected to represent electors of a specific Ward.
Administration Represents a collective of City Staff. Refers to events, actions and / or decisions made at the level
of, with the knowledge of, but by a combination of involvement of City staff in junior positions,
management, senior management and / or the then-CAO. The key factor being that senior
management and / or the then-CAO were involved in the process.
While there is a varying degree of accountability for different tiers of employee, it is the
responsibility of all officers and employees of the City of Windsor, per the Municipal Act, s. 227:
(a) to implement council’s decisions and establish administrative practices and
procedures to carry out council’s decisions;
(b) to undertake research and provide advice to council on the policies and programs of
the municipality; and
(c) to carry out other duties required under this or any Act and other duties assigned by
the municipality. 2001, c. 25, s. 227.
CAO
Then-CAO
Chief Administrative Officer, head of all Administration (except those exempt by Law).
Per the Municipal Act, s. 229 (a), defined responsibilities include exercising general control and
management of the affairs of the municipality for the purpose of ensuring the efficient and
effective operation of the municipality.
Due to unusual circumstances leading to several rapid changes in who was the actual and/or the
acting CAO, we cannot say definitively which of one or more persons was the CAO, or the acting
CAO at specific decision points of the RFP evaluation and approval process.
City of Windsor AGO 142
Term Explanation
Senior
Administration
Refers to events, actions and / or decisions made at the level of, or with the knowledge of City
staff in the positions of senior management, which would likely include the then-CAO. Under
former City structures, this includes the CAO, General Manager or Commissioner and City
Directors, etc.
Junior
Administration
City staff employed in a middle or junior management role below the level of senior
Administration.
Staff City staff employed in a non-management role.
City of Windsor AGO 143