![Page 1: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/1.jpg)
City of Seattle Partnering Agreement
December 2017
![Page 2: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/2.jpg)
Agenda
• System Expansion Plan
• West Seattle and Ballard Link Extensions
• Partnering Agreement
![Page 3: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/3.jpg)
System expansion
More information on each project:
www.soundtransit.org/system
Sound Transit’s system expansion means
every few years new light rail, bus rapid
transit and commuter rail stations open
throughout the region, providing fast, reliable
alternatives to congested roads
![Page 4: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/4.jpg)
Regional Link light rail expansion
116+ miles 80+ stations 16 cities connectedBy 2041:
![Page 5: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/5.jpg)
Project Highlights:
• Opening 2030
• Length: 4.7 miles
• 4 elevated stations at SODO, Delridge,
Avalon and Alaska Junction; one at-
grade station at Stadium
• New rail-only fixed span crossing of the
Duwamish River
West Seattle Link Extension
![Page 6: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/6.jpg)
Project Highlights:
• Opening 2035
• Length: 7.1 miles
• Three elevated stations: Ballard,
Interbay, Smith Cove
• Six tunnel stations: Seattle Center, South
Lake Union, Denny, Westlake, Midtown,
International District/Chinatown
• New rail-only movable bridge over
Salmon Bay
Ballard Link Extension
![Page 7: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/7.jpg)
Draft EIS
Final EIS
Board selects project
to be built
Federal agency issues
Record of Decision
(ROD)
West Seattle Link Extension schedule
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2022-2025
Construction
& Testing
2025-2030
Start of
Service
Public involvement Safety education
Alternatives
development
Board identifies
preferred
alternative
![Page 8: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/8.jpg)
Draft EIS
Final EIS
Board selects project
to be built
Federal agency issues
Record of Decision
(ROD)
Ballard Link Extension schedule
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2026
Construction
& Testing
2027-2035
Start of
Service
Public involvement Safety education
Alternatives
development
Board identifies
preferred
alternative
![Page 9: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/9.jpg)
New approach to project development
Apply innovative ideas and lessons
learned to streamline project delivery
![Page 10: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/10.jpg)
![Page 11: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/11.jpg)
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Identify project
delivery method
early
Real estate
acquisition plan
Identify preferred
alternative early
Access
TOD
New approach to project development
*Schedule for West Seattle to Downtown segment only
![Page 12: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/12.jpg)
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Identify project
delivery method
early
Real estate
acquisition plan
Identify preferred
alternative early
Access
TOD
New approach to project development
*Schedule for West Seattle to Downtown segment only
![Page 13: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/13.jpg)
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Identify project
delivery method
early
Real estate
acquisition plan
Identify preferred
alternative early
Access
TOD
New approach to project development
*Schedule for West Seattle to Downtown segment only
![Page 14: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/14.jpg)
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Identify project
delivery method
early
Real estate
acquisition plan
Identify preferred
alternative early
Access
TOD
New approach to project development
*Schedule for West Seattle to Downtown segment only
![Page 15: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/15.jpg)
Alternatives Development process
Preferred
Alternative
Early 2019
DEIS
Alternatives Development
(Late 2018)
Level 2
Alternatives Development
(Mid 2018)
Level 1
Alternatives Development
(Early 2018)
ST3 representative
alignment
Stakeholder input
Early feasibility
studies
Level 1 alternatives
Stakeholder input
Early feasibility
studies
Station planning
Level 2 alternatives
Stakeholder input
Additional technical
analysis
Public involvement
![Page 16: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/16.jpg)
Communications and public involvement
• Community engagement and
Communications Plan
• Public Information Officer
• Community meetings, Open Houses
![Page 17: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/17.jpg)
Stakeholder engagement
Priority in Sound Transit System Expansion Implementation Plan:
“Enhance Sound Transit’s commitment to partnership, community
engagement, collaboration, transparency and accountability.”
Elected
Leadership
Group
Stakeholder
Group
Interagency
Group
![Page 18: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/18.jpg)
Permitting action
Land use
approvals
Construction
permits
Permitting plan(2021)
Agreements
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Construction
inspection
Certificate of
occupancy
Partnering agreement
(Late 2017)
Preferred alternative
concurrence (Early 2019)
*Schedule for West Seattle to Downtown segment only
![Page 19: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/19.jpg)
Permitting action
Land use
approvals
Construction
permits
Permitting plan(2021)
Agreements
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Construction
inspection
Certificate of
occupancy
Partnering agreement
(Late 2017)
Preferred alternative
concurrence(Early 2019)
*Schedule for West Seattle to Downtown segment only
![Page 20: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/20.jpg)
Permitting action
Land use
approvals
Construction
permits
Agreements
Alternatives
Development
Late 2017-2019
Environmental
Review
2019-2022
Final
Design
2023-2025*
Construction
& Testing
2025-2030*
Start of
Service
Public involvement Safety education
Construction
inspection
Certificate of
occupancy
Partnering agreement
(Late 2017)
Preferred alternative
concurrence (Early 2019)
*Schedule for West Seattle to Downtown segment only
Permitting plan(2021)
![Page 21: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/21.jpg)
Designated Representatives &
Project Development Team
Scope, Schedule, Budget
Project Definition
Community Engagement
Station Planning Activities
Partnering Agreement
Permit Streamlining
NEPA / SEPA
Coordination on Planned Projects
Staffing
![Page 22: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/22.jpg)
Designated Representative & Project Development Team
Partnering Agreement
Forum for early resolution of issues
![Page 23: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/23.jpg)
Scope, Schedule, Budget
Partnering Agreement
Complete project within ST3 schedule and budget
If requests to increase scope, identify scope reductions
elsewhere/local contributions
![Page 24: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/24.jpg)
Project Definition
Partnering Agreement
Start with ST3 representative project as basis to investigate other
reasonable alternatives to be studied
Collaborate early on evaluation of reasonable alternatives
![Page 25: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/25.jpg)
Community Engagement
Partnering Agreement
Collaborate on Community Engagement & Communications Plan
Convene Elected Leadership Group, Stakeholder Advisory Group and
Interagency Group
![Page 26: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/26.jpg)
Station Planning Activities
Partnering Agreement
Develop process to coordinate station planning activities
![Page 27: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/27.jpg)
Permit Streamlining
Partnering Agreement
Identify and implement actions to streamline permit review
Develop Preliminary Permitting Plan
![Page 28: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/28.jpg)
SEPA / NEPA
Partnering Agreement
Participate actively in environmental review process
Develop documents that both Parties can use for project approvals and
permitting decisions
![Page 29: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/29.jpg)
Coordination on Planned Projects
Partnering Agreement
Coordinate on planned projects within the project area
Resolve conflicts as early as possible
![Page 30: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/30.jpg)
Staffing
Partnering Agreement
Sound Transit may reimburse City costs for certain services
Develop funding agreement
![Page 31: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/31.jpg)
Next steps
• Initiate City working groups
• Initiate leadership groups
• Initiate formal community engagement
![Page 32: City of Seattle Partnering AgreementFinal Design 2023-2025* Construction & Testing 2025-2030* Start of Service Public involvement Safety education Construction inspection Certificate](https://reader034.fdocuments.in/reader034/viewer/2022042219/5ec5c39f5363f4327a4f222d/html5/thumbnails/32.jpg)