CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF...

64
1 CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY ADOPTED BY THE CITY COUNCIL JULY 17, 2012 UPDATED APRIL 22, 2014 AND MARCH 15, 2016) G.7.a Packet Pg. 95 Attachment: Road and Drainage Repairs Plan Updated 2-6-18 (1412 : CIOC Road and Drainage Plan approval)

Transcript of CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF...

Page 1: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

1  

         

 

CITY OF ORINDA   

 

Road and Drainage Repairs Plan 

 

(As Updated in 2017)                

February 6, 2018 

  

     

 

(ORIGINALLY ADOPTED BY THE CITY COUNCIL JULY 17,  2012 UPDATED APRIL 22, 2014 AND MARCH 15, 2016) 

G.7.a

Packet Pg. 95

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 2: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

i  

      

CITY OF ORINDA  

22 Orinda Way Orinda, California  94563 

 (925) 253‐4220 

[email protected]  

 

Acknowledgements 

STEVE SALOMON, City Manager 

LARRY THEIS, Director of Public Works and Engineering Services FARAH KHORASHADI, Paving Program Project Manager 

and 

CITIZENS’ INFRASTRUCTURE OVERSIGHT COMMISSION Terry Murphy, Chair 

Robert Hubner Vice‐Chair   Walter Bell 

Gordon Bizieff Jud  Hammon  

Bill Hurrell Richard Nelson

G.7.a

Packet Pg. 96

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 3: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

1  

CITY OF ORINDA ROAD AND DRAINAGE REPAIRS PLAN  

(As Updated in 2017)  Approved February 6, 2018 by the Orinda City Council   

 

 

EXECUTIVE SUMMARY 

The City of Orinda incorporated in 1985, and took over approximately 93 miles of paved 

publicly owned roads1 and roughly 19 miles of storm drain pipes and culverts from Contra 

Costa County at that time. The City’s General‐Fund operating budget, funded in great part 

by property taxes, sales taxes, and fees, was not sufficient to maintain all of the roads and 

drains in good condition. 

With available funds, primarily Gas Tax and Contra Costa County Sales Tax Return‐to‐

Source and grant funds, the City was able to repair and maintain the most heavily‐travelled 

roads (arterials, collectors, and school routes) in a generally good condition.  However, by 

2012, many of the less‐traveled "residential" roads were in poor condition.  At this point, a 

key issue was to fund repairs of these remaining roads, here called the Residential roads, 

and their associated storm drains. 

In July, 2012, a ten‐year, multi‐phase funding plan was approved by the City Council, to 

address this problem and to assist in managing the associated repair projects.  The total 

cost for repairs was estimated to be $58.4 Million.  The Plan was subsequently revised in 

2014 and 2016, and is further updated in this document.  In the 2016 revision, an 

additional funding phase was introduced to address key storm drain issues that had not yet 

been addressed and to complete repairs of the arterials, collectors, and school routes. 

The objectives of the March, 2016 plan, which remain the same in this revision, are to 

improve the citywide average Pavement Condition Index (PCI) to over 70 (Good to Very 

Good condition) by the end of the original ten‐year period (2021), to assure that no public 

road will have a Pavement Condition index of less than 50 at that time, to dramatically 

reduce the risk of new major storm‐drain failures, and to have sufficient annual revenues 

to maintain the public road and storm‐drain systems in that condition thereafter. 

                                                            1 There are also approximately 23 miles of privately‐owned roads within the city of Orinda, as well as important storm drains that are privately owned.  This document addresses only those roads and storm drains that are publicly owned.  

G.7.a

Packet Pg. 97

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 4: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

2  

Real progress on improving the residential roads began in 2013, with public support 

resulting in the approval by voters of a half‐cent sales tax in November, 2012.  The first 

revenues from this funding source, targeted for repair of Residential streets and drains, 

were available in April, 2013. 

In 2014, voters approved additional funds for repairs of residential roads and drains, a 

general‐obligation bond (Measure J) for $20 Million, followed by the subsequent passage 

of the 2016 Bond Measure L ($25 Million).  The availability of this level of funding has 

allowed the city to significantly accelerate repair of our Residential roads and associated 

drains.  This acceleration will shorten the duration of our disruptive road‐repair projects, 

with completion of repairs of residential roads now expected in 2019. The shortened 

duration of the repair project is expected to reduce costs, through the use of larger‐scale 

contracts, and the ability to take advantage of low oil prices, a main factor in the cost of 

the asphalt required to pave the roads. 

 

It is clear that dramatic progress has been made in repairing the city's roads and storm 

drains.  At the time this report is being written, the 2017 paving project is nearing 

completion.  Table 1 shows the lengths, in miles, of Residential and Arterial / Collector / 

School Route roads repaired from 2012 through 2019, including repairs projected for the 

2018 and 2019 repair projects.  Figure 1 shows the historical PCI data, from 2011 through 

G.7.a

Packet Pg. 98

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 5: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

3  

the end of 2016, and the projected improvement through 2019.  As can be seen in the 

chart, the average PCI of our public roads is projected to be nearly 70 by the end of the 

2017 paving project.  Based on the current projections, the City is anticipating 

rehabilitating all Residential roads by the end of 2019, after which, the system‐wide 

average PCI will be nearly 90. This will be considered one of the best overall ratings in the 

entire Bay Area. 

 

Year Residential 

Street/School Route Miles of Rehabilitation

Arterial/Collector/ School Route 

Miles of rehabilitation 

2012  0.66  1.77 

2013     

2014  0.94  3.86 

2015  6.85  2.24 

2016  8.50  0.73 

2017  10.46  0.36 

2018  13.74  1.34 

2019  25.41  1.48 

Miles repaired: Sub‐Totals 

66.6  11.8 

 

Total Miles Orinda Roads Repaired

78.3 

Table 1.  Lengths of Residential and Arterial/Collector/School Route roads repaired from 

2012, by year, including projected repairs, through 2019 

G.7.a

Packet Pg. 99

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 6: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

4  

 

Figure 1:  Pavement Condition Index; 2011 through 2016 and projected to 2019 

 

 

 

The map of Figure 4 also shows the progression ‐ and acceleration ‐ of the repair project, 

with yellow highlights showing those roads repaired from 2012 through 2016, red 

highlights showing those being repaired during the 2017 project, and blue highlights 

showing those scheduled to be repaired in 2018 and 2019.   

 

G.7.a

Packet Pg. 100

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 7: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

5  

 

G.7.a

Packet Pg. 101

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 8: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

7  

Completion of repairs of the residential roads, however, does not complete the overall 

project of repairing all of our public roads and associated storm drains.  Important repairs 

of Arterials, Collectors, and School Routes will remain, and the sinkhole on Miner Road 

clearly shows the necessity to emphasize storm drain rehabilitation work as quickly as 

possible. 

Additional funding will be required to rehabilitate these remaining Arterial, Collector, and 

School‐Route roads, and to accomplish key drainage repairs.    This update to the Roads 

and Drainage Repairs Plan retains the recommendation for Phase 4 funding of the March, 

2016 update, with the same estimated budget of $22 Million.  Preliminary descriptions of 

the road and drainage system repairs proposed within this budget are summarized in 

Attachments 7 and 8. 

Furthermore, our roads will not stay in good condition without maintenance. The plan 

describes the need for an on‐going funding stream (Phase 5 Funding), to be available after 

the completion of the present repairs projects, to provide this ongoing maintenance of our 

roads.  As shown in Table 2, the cost to maintain our public roads at an average PCI of 70 

or greater, with no road having a PCI falling below 50, and to provide routine maintenance 

for the associated storm drains, is estimated to be approximately $3.5 Million per year.  

Additional funding sources will be required to accomplish this goal. 

Maintaining the roads in good condition will significantly reduce Orinda's long‐term costs 

for roads in the future.  Extensive research shows that, for each dollar it would cost to 

treat a roadway with a PCI of 60 or higher, it would cost approximately $5 dollars to repair 

the roadway, once it has deteriorated to the point where major rehabilitation or 

reconstruction is necessary, as shown in Figure 5.  

 

G.7.a

Packet Pg. 102

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 9: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

8  

 

Figure 5:  Pavement Life Cycle (Source: Metropolitan Transportation Commission) 

 

Table 2 – Multi‐Phase Approach to Fund Orinda’s Roads and Drainage Repairs 

Phase 1 Approved 2012 

2012 ‐ 

2021 

Funded through 2022, with annual increments Half‐Cent Sales Tax (Measure L)with a 10‐Year Sunset  

Appropriated Annually by the City Council 

Phase 2 Approved 2014 

2014 Fully Funded 

$20 Million General Obligation Bond  (Measure J) for Residential Roads repairs 

Phase 3 Approved 2016 

2016 Fully Funded 

$25 Million General Obligation Bond (Bond Measure L) for Residential Roads repairs 

Phase 4  2020 Approximately $22 Million of new revenue for primarily for 

repairs of arterials, collectors, school routes and storm drains, to be  raised by a Bond, Parcel Tax, or other new  source 

Phase 5  2020 

Approximately $1 Million per year for maintenance of Arterials, Collectors and Bus Routes 

and  

Approximately $2.5 Million per year for maintenance of Residential Roads 

(Extension of the Half‐Cent Sales Tax plus approximately 1.5 Million per year from other Revenue Sources) 

 

G.7.a

Packet Pg. 103

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 10: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

9  

Summary 

To summarize, excellent progress has been made, significantly improving the pavement 

quality of Orinda's roads, and reducing the risk of failures of our storm drains.  However, 

there is a remaining need for funds to complete the repairs of our most‐frequently‐used 

roads and to repair some critical storm drains (Phase 4 funding, as shown in Table 2), and 

to support maintenance of our roads and storm drains in the long term (Phase 5 funding, 

as shown in Table 2).     

G.7.a

Packet Pg. 104

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 11: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

10  

BACKGROUND 

In 1985, the newly‐incorporated City of Orinda inherited approximately 93 miles of paved, 

publicly owned roads [26 miles of arterials and collectors, plus 67 miles of public 

residential roads and bus routes] from Contra Costa County.  The city also includes about 

100,000 linear feet (about 19 miles) of storm drain pipes and culverts. 

Unfortunately, Orinda's available funds going forward were not sufficient to address all of 

the maintenance and repair needs for the new city's roads and drains.  Within the existing 

budget, the city was able to spend an average of $2.3 million per year on street 

maintenance and repairs. Approximately $0.8 million annually was drawn from the City’s 

General Fund and the Garbage Franchise Fees and used for routine street maintenance 

(potholes, striping, sweeping, drainage, etc.). Approximately $1.5 million annually was 

made available for pavement rehabilitation and reconstruction, drawn from dedicated 

sources of funds ‐‐ Gas Tax, the countywide transportation sales tax Return‐to‐Source 

funds, and grant revenues from county and federal sources averaged over the 10‐year 

period. 

Development of Detailed Roads and Storm Drains Plans 

In October, 2004, the City Council created the Citizen's Infrastructure Committee, with a 

two‐year charter to assess the status of the city's roads and storm drains and quantify the 

funding requirements for repairs and maintenance. 

In July, 2006, this group submitted a report with a detailed analysis of the city's 

infrastructure.  The committee projected the 20‐year cost of repairing all publicly owned 

roads in Orinda to be approximately $ 72million, and estimated cost to repair all of the 

city's drains to be approximately13 Million.  They also analyzed a reduced‐scope effort, 

limiting repairs to the most frequently‐used roads (at least 500 average daily trips) and 

only the most critical drains.  They estimated that this more limited effort would still 

require approximately $60 Million. 

Based on this assessment, a series of funding measures was put on the ballot, beginning 

with a $69.1 Million bond measure in 2006.  This bond measure failed to receive the 

number of votes required for approval.  A subsequent $58.6 Million bond measure in 2007 

also did not receive sufficient support. 

G.7.a

Packet Pg. 105

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 12: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

11  

In 2007, the City Council formed a new advisory group, the Citizens Infrastructure 

Oversight Commission [CIOC].  The charter of the new commission was to provide 

oversight of spending on Orinda’s roads, to continue analysis of the nature and extent of 

the problem, including funding requirements, and to provide recommendations on how 

funds made available for road and drain repairs should best be allocated. 

Considering budget limitations, the City Council, on the recommendation of the CIOC, 

decided in 2009 to focus repairs on the most‐travelled roads; the arterials, collectors and 

bus routes.  The available funds (primarily gas tax, Return‐To‐Source funds from the 

County sales tax, and federal, state, and regional grants) were focused on repairs of the 

city's most heavily travelled roads.  As a result, the condition of these roads began to 

improve.  However, the condition of the city's residential roads continued to decline. 

In July 2012, the CIOC and city staff developed a 10 Year Plan that estimated the cost to 

repair the city's public roads and the associated storm drains to be approximately $58 

million. Implementation of the plan required a series of funding measures anticipated to 

be accomplished over four phases, projecting completion of the repairs in 2022.   

The first funding phase was funded through the passage in 2012 of Measure L, a one‐half 

cent sales tax increase that provides approximately $1 million each year. The second and 

third funding phases were funded through the passage in 2014 of Bond Measure J ($20 

Million) and the passage in 2016 of Bond Measure L ($25 Million).  These three measures, 

combined, allow the City to raise $10 Million (over 10 years) from the sales‐tax measure, 

plus $45 million through the two general‐obligation bond issues, with all these funds to be 

used for the repair Residential roads and the associated drains.  

At the same time, the city continued repairs and maintenance of the Arterials, Collectors, 

and School Routes through the County Return‐to‐Source sales tax and gas tax funds, 

supplemented by some federal, state, and regional grants.   

In the Nov. 17 and Dec. 15, 2015 City Council meetings, the Council reviewed recent 

reports from CIOC, and concluded that the goals for pavement quality should be made 

more stringent.  While increasing near‐term repair costs, long‐term maintenance costs are 

expected to be reduced by more than the increase in repair costs. 

In March, 2016, the city received the final report from Shaaf and Wheeler, an engineering 

firm hired to evaluate Orinda's storm drain system to make estimates of drain‐system 

G.7.a

Packet Pg. 106

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 13: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

12  

repairs that may be required, including prioritization and cost estimates for the repairs.  In 

the March, 2016, update of the Roads and Drainage Repairs Plan the CIOC and city staff 

recommended the introduction of another funding phase, to fund the modified pavement‐

quality goals and the increased storm‐drain‐repair requirements. 

Cost‐Saving Items 

With the passage of the two bond measures in 2014 and 2016, in advance of the schedule 

originally anticipated in the plan, the city now has the funds required to pursue a rapid and 

more efficient program for long‐needed repairs of our residential roads.  Additional 

benefits of this more‐rapid approach include securing favorable unit costs through larger‐

scale contracts and taking advantage of current low oil prices, a major factor in the cost of 

asphalt. 

To understand how to best use the available funds and other resources, the city requires 

quantitative measures of pavement condition.  A key element of this process is the 

Pavement Management Technical Assistance Program (P‐TAP), a program developed by 

the Bay Area Metropolitan Transportation Commission (MTC).  This program uses federal 

dollars to help Bay Area cities and counties stretch their budgets by: 

o Implementing, updating and maintaining pavement management databases 

o Providing accurate pavement condition data to city councils, county supervisors 

or other local decision makers 

o Providing engineering design assistance for pavement rehabilitation projects 

o Supporting  management of non‐pavement street and road assets such as signs, 

storm drains, curbs and gutters, traffic signals and street lights 

Through this program, Orinda pays only a small fraction (about 20%) of the cost for 

consultants to assess the condition of our roads.  Arterial and Collector streets are 

assessed every two years, and Residential streets are assessed every 4 years.  The results 

of these assessments are reported every two years.  As examples, below are the costs for 

the last three grant/reporting cycles: 

o PTAP 13 ‐ MTC grant $27,828; local match $5,565 

o PTAP 15 ‐ MTC grant $8,000; local match $2,000 (much lower since only 

Arterials/Collectors are field evaluated) 

o PTAP 17 ‐ MTC grant $27,810; local match $7,900 

G.7.a

Packet Pg. 107

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 14: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

13  

MTC also developed the StreetSaver software, which is used to estimate remaining 

pavement lifetime and the cost of repairs that would be required to bring pavement 

segments up to "very good" condition.  Analysis runs can be performed for various sets of 

goals, allowing staff to make informed decisions regarding the maintenance and repair of 

roads. 

To supplement the city's own funding sources, city staff researches applicable grant 

programs, and has had frequent success in applying for grants to support repair work. 

Through these efforts, about $9.2 million dollars in additional funds has been received 

since 2012.  A detailed list of these grants is included in Attachment 6. 

Significant cost savings were accomplished by the introduction of the Full‐Depth 

Reclamation (FDR) process, which dramatically reduces the amount of material that must 

be removed from the repair site and taken to a dump site, and virtually eliminates the 

requirement for crushed rock to be trucked in to the repair site.  Overall, this approach 

significantly reduces the cost of major road repairs, while still producing a high‐quality 

result.  See Attachment 9 for further details. 

In addition, the City has teamed with neighboring cities to share costs where possible.  

Examples include Ivy Drive repairs along the Orinda/Moraga border and Whitehall Court 

along the Orinda/Lafayette border.  In each case, the work was jointly funded by the two 

cities. 

Storm Drains ‐ Inspection and Repairs 

The city of Orinda has roughly 19 miles of storm drain pipes and culverts associated with 

our public roads.  Assessment of the storm‐drain system, performing repairs where 

needed, is a key aspect of the Roads and Drains program.  The storm drain system was 

investigated in detail as part of the CIC investigations, as reported in the July, 2006 CIC 

report.  An additional study was performed in 2015 and 2016 by the Schaaf and Wheeler 

engineering firm, as reported in the March, 2016 Storm Drain Plan. 

A large number of the smaller drains and culverts under our roads have already been 

addressed. As a routine part of the ongoing road‐repair projects, all associated storm 

drains, for which at least one end of the drain is accessible, are inspected, cleaned, and 

repaired or replaced as appropriate.  Examples are shown in the photographs below.  

Table 3 summarizes the inspection, cleaning, and repair of storm drains associated with 

G.7.a

Packet Pg. 108

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 15: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

14  

the road segments repaired in the 2017 Residential Roads Paving Program. 

 

 

G.7.a

Packet Pg. 109

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 16: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

15  

 

 

G.7.a

Packet Pg. 110

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 17: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

16  

Table 3:  Storm Drain Inspection, Cleaning, and Repair/Replacement (Linear Feet) for 

the 2017 Residential Roads Paving Program  

Linear Ft 

Cleaning of Storm Drain Pipe  12,088

CCTV Inspection of Storm Drain Pipe  12,088

Repair and Replace with 10"‐36" HDPE Pipe  800

Repair and Replace Shallow w/ 6"‐24" HDPE  1000

New 12"‐18" HDPE Pipe  200

Centrifugally ‐ Cast Conc. Pipe Liner 32"‐36"  510

  Linear Ft 

Curb and Gutter  3,007

AC Dike (Asphalt curb)  10,211

12" Deep V Ditch‐CD60  509

10” and 18” Valley Gutter  620

 

However, many of the city's larger culverts, which are generally deeper below the 

pavement, and often below our arterials, collectors, and school routes, have not been 

addressed.  A list of some of the storm drains and culverts particularly in need of attention 

is given in Attachment 7.  The list is based on the 2016 Storm Drain Plan, which identified 

storm drains that were under capacity for a 10 year storm event or were in poor 

condition.  We need to perform a detailed engineering study of the storm drains 

associated with our roads. The recommended Phase 4 funding of $15 Million is proposed 

to address this study, and includes a rough estimate of the funds required to perform the 

study and accomplish the most critical repairs.  Recent dramatic failures of storm drains at 

Miner Rd and Tarabrook Drive, as well as the large construction projects to upgrade the 

storm drains under North Lane and Glorietta Blvd clearly show that storm drain repairs can 

be very disruptive and very costly  

 

Key Events and Milestones 

A summary of key events and milestones is given in the table of Attachment 5.    

G.7.a

Packet Pg. 111

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 18: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

17  

NEXT STEPS 

This plan explicitly assumes that the City will continue to fund repair and maintenance of 

the Arterials, Collectors, and School Routes through the annual Pavement Management 

Program, using funds from Gas Tax and Return to Source. 

The focus for Residential roads remains on repairing the worst roads.  For these roads, 

repairs will generally require pavement reconstruction, such as Full Depth Reclamation. In 

the 2018 and 2019 paving projects, however, the program will move on to Residential 

roads that are less distressed, and the repairs will shift to less costly, simpler processes, 

such as milling with a thin overlay and slurry seals (with and without minor patching). 

The funding plan consists of the five phases, as summarized in Table 4, below.  In Phase 1 

through Phase 4 the City will fund, plan, and manage the construction and repair of public 

roads and drains.  Phases 1 through 3 provide funding for repair of the Residential roads 

and associated drains, including culverts close to the pavement surface.  Phase 4 focuses 

on the arterials, collectors, and school routes, plus major storm drain repairs, including 

larger, deeper culverts.  The final phase, Phase 5, will address the on‐going maintenance of 

the newly reconstructed roadways and drainage system. 

Phases 1, 2, and 3 are already fully funded, and are being used in parallel, to repair  the 

City’s Residential roads, starting with those that are used most frequently and are in the 

worst condition. Phase 1 is funded through the 1/2‐cent Orinda sales tax (Measure L), 

which was approved 2012, and continues through 2023.   This tax is estimated to generate 

approximately $1 million per year over the 10‐year life of the tax. Phase 2 is funded 

through the $20 million general‐obligation  bond approved in 2014 (Measure J).  Phase 3 is 

funded through the $25 Million general‐obligation  bond (Measure L) approved in 2016. 

Phase 4 is intended to provide the remaining funds required to complete the repair process 

for our public roads (primarily the arterials, collectors, and school routes ‐ see Attachment 

8) and major storm drains (see Attachment 7). 

A future revenue source, not presently specified, will be required, to perform these 

repairs.  The additional revenue  required for Phase 4 is estimated at $22 million.  The 

recommended funding includes $15 Million to perform a detailed engineering study of our 

drainage system and to accomplish the most critical repairs, including funding for a full‐

time Drainage Program Project Manager to manage and oversee drain projects, and $7 

G.7.a

Packet Pg. 112

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 19: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

18  

Million to complete repairs of our most‐used roads.  The amount of additional funding 

required to complete these repairs may be less than this, if final construction costs for the 

2018 and 2019 paving projects and for much ‐needed drainage improvements come in 

lower than present estimates. 

Table 4 – Multi‐Phase Approach to Fund Orinda’s Roads and Drainage Repairs 

Phase 1 Approved 2012 

2012 ‐ 

2021 

Funded through 2022, with annual increments Half‐Cent Sales Tax (Measure L)with a 10‐Year Sunset  

Appropriated Annually by the City Council 

Phase 2 Approved 2014 

2014 Fully Funded 

$20 Million General Obligation Bond  (Measure J) for Residential Roads repairs 

Phase 3 Approved 2016 

2016 Fully Funded 

$25 Million General Obligation Bond (Bond Measure L) for Residential Roads repairs 

Phase 4 2020 

 

Approximately $22 Million of new revenue for primarily for repairs of arterials, collectors, school routes and storm drains, to 

be  raised by a Bond, Parcel Tax, or other new  source 

Phase 5  2020 

Approximately $1 Million per year for maintenance of Arterials, Collectors and Bus Routes 

and  

Approximately $2.5 Million per year for maintenance of Residential Roads 

Extension of the Half‐Cent Sales Tax plus approximately 1.5 Million per year from other Revenue Sources, SB1, CCTA, Vehicle 

Impact fee

 

By early 2020, it will be essential that the City establish an ongoing funding stream to 

support maintenance of the public roadways.  Without additional funds for routine 

maintenance, the recently repaired roads will begin to degrade.  It is generally accepted 

that the costs to maintain a road are generally significantly lower than the cost of to repair 

the road once it has significantly degraded.  As a result, the long‐term interests of the city 

are best served by providing an adequate funding stream to support proper maintenance 

of our roads. If citizens of Orinda approve the recommended $22 million financing in 2018, 

the funds would be available in 2019 and the work on the most critical drains and needed 

repair for Arterial and Collectors can begin in year 2020 and continue thru year 2025. 

G.7.a

Packet Pg. 113

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 20: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

19  

Phase 5 is intended to provide the longer‐term funding stream to support routine 

maintenance of the roads and drains, to maintain the public roads at an average PCI of 70 

or greater, with no road having a PCI that falls below 50...  Based upon current material 

and labor costs, the annual cost of maintaining the roads has been estimated at $3.5 

million, though costs may increase beyond that level if there are unanticipated increases. 

Estimated revenues available from the Gas Tax and the Return‐to‐Source funds for the 

roads in 2022 are estimated to be approximately $1 million.  The Measure L ½‐cent sales 

tax, which currently generates approximately $1 million per year, will expire in 2023 As a 

result, the core of Phase 5 is proposed to be an extension of the ½  cent sales tax.   

It is possible that the City would able to commit additional funding to road maintenance 

from increased property tax  revenues, reducing the need for other new revenue  sources 

for Phase 5.  However, it is very likely that some level of additional funding will be 

required. Potential additional revenue sources include a real estate transfer tax, a parcel 

tax, or a general‐obligation bond, all of which would require voter approval. 

A caveat, regarding on‐going maintenance:  It is important to note that Orinda roads are 

built on soil that expands and contracts significantly during our cycle of wet winters and 

dry, hot summers.  Furthermore, the hillsides on which many of our roads are built are 

intrinsically unstable.  As a result, it is inevitable that the soil beneath our roads will move, 

no matter how well the road’s base is constructed.  We can, and do, mitigate this to some 

extent with careful design and robust construction. Nonetheless, some level of damage to 

many of our roads, due to underlying soil motion, is inevitable.  We must keep this in 

mind, as we plan our budgets.  

The following table summarizes the funding and expenditures associated with the city's 

completed, in progress, and planned road/drains repair projects, through 2019.     

G.7.a

Packet Pg. 114

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 21: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

20  

 

Funding Source  2014  2015  2016  2017  2018  2019  TOTAL 

Gas Tax  $490,000   $440,000   $578,005  $200,000  $600,000  $600,000   $2,908,005 

CCTA (Return to Source 

$240,000   $961,000   $939,771  $620,000     $450,000   $3,210,771 

CCTA (Grant)  $2,000,000                  $2,000,000 

2012 Measure L (1/2 cent sales tax) 

$750,000   $908,700   $1,079,126  $990,000  $1,046,953  $1,000,000   $5,774,779 

2014 Measure J ($20 Million Bond) 

   $4,697,900   $4,096,902  $10,488,047  $950,000     $20,000,000 

2016 Measure L ($25 Million Bond) 

            $12,166,607  $13,183,393   $25,350,000 

TOTALS  $3,480,000   $7,007,600   $6,693,804  $12,298,047  $14,763,560  $15,233,390   $59,476,401 

 

The table below shows the proposed time line and annual budget for the recommended 

$22 million dollar funding. 

 

Funding Source  2020  2021  2022  2023  2024  2025 

Future $22 M Funding  $6M  $4M  $4M  $3M  $3M  $2M 

 

   

G.7.a

Packet Pg. 115

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 22: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

21  

IMPLEMENTATION 

The 2016 approval of Phase 3 funding by the voters has permitted a substantial increase in 

the scope of each year's road‐repair project, beginning with the 2017 project. With the 

$25 Million bond measure L additional funds available, CIOC recommended a more 

aggressive approach to the paving repair project,  accelerating and expanding road 

pavement repairs to roughly $11 million per year (construction cost) from about $6 million 

per year with the prior schedule. The goal with this aggressive approach was to preserve 

favorable unit costs with larger‐scale contracts and take advantage of low oil prices, which 

is a major factor in the cost of asphalt. With this acceleration of the work, the impact on 

Orinda residents would also be shortened by approximately two years. 

The City has supplemented existing staff by hiring a full‐time project manager, responsible 

for planning and managing the expanded program. The project manager, reporting to the 

Director of Public Works and Engineering Services, monitors the plan and its 

implementation.  The project manager and public works director, in conjunction with the 

CIOC, forward to the City Council annual paving programs, with funding for repair of 

Residential roads from the 2012 Measure L Sales Tax, the 2014 Measure J Bond and the 

2016 Measure L Bond. 

Road repair and reconstruction is managed by the project manager and the City’s Public 

Works and Engineering Services Department, supplemented by outside engineering and 

construction management consultants. Road selection for each year's repair project 

includes discussion and recommendation in public hearings by the Citizens Infrastructure 

Oversight Commission, followed by review and authorization by the City Council at public 

meetings. Documents proposing changes in road repair policy or changes to specific roads 

to be repaired are distributed and are publicly available prior to the CIOC or Council 

meetings at which they will be considered. 

Repair and Maintenance Policies 

In general, the City expects to continue its existing policies regarding repair of the  public 

roads.  The selection of Arterials, Collectors, and School Routes will be based on 

recommendations of the StreetSaver program, modified by any special conditions,  such as 

planned work on roads by EBMUD, PG&E, the County, or other partners, as well as 

consolidating work on adjacent roads to obtain more favorable bids from contractors. 

G.7.a

Packet Pg. 116

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 23: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

22  

The selection of Residential public roads to be repaired follows the policies adopted 

previously, initially focusing repair on our worst Residential roads (those with PCI under 

25) until all of those roads have been repaired and there are no longer any Residential 

roads in “Very Poor” or  “Failed” condition. Within this group of roads, the more heavily 

traveled roads  are being repaired before less heavily traveled roads, but all of the public 

"worst roads"  are expected to be repaired within the 2018 paving project. 

Each year, the selection of Residential roads is based upon updated  information that is 

available at that time.  This updated information includes information on the condition of 

each Residential road, how it has deteriorated from its prior condition, and what 

treatments are appropriate, considering its current condition.  It also includes  the actual 

funding expected to be available for that year from gas tax and sales tax sources, and the 

actual schedule of drawdowns of the general‐obligation bonds. 

2017 Paving Program 

At the time of this report, the 2017 Paving Program is nearing completion.  The 2017 

annual pavement rehabilitation project for the City’s most heavily travelled roads, the 

Arterials, Collectors, and School Routes, is funded by Gas Tax and Countywide 

Transportation Sales Tax Return‐to‐Source (RTS) funds. This project is rehabilitating one 

arterial road (El Nido Ranch Road) with a mill and overlay and two School Route roads 

(Don Gabriel Way & El Camino Moraga) with Full Depth Reclamation (FDR).  

The 2017 annual paving project for the city's residential roads is funded through a 

combination of the Annual and Measure J & L programs.  Orinda voters approved the 

2012 Measure L ½‐cent sales tax and the 2014 $20 Million Measure J bond to fund repairs 

on the residential street network.  This project is rehabilitating approximately 60 

residential roads with Full Depth Reclamation. Drainage Improvements were performed 

first, including partial or full replacement of storm drain pipes under streets.  Also 

replaced were concrete curbs and road‐side lined ditches, asphalt dikes, and curbs. 

   

G.7.a

Packet Pg. 117

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 24: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

23  

 

Storm Drain Inspection, Cleaning, and Repair/Replacement (Linear Feet) for the 2017 

Residential Roads Paving Program  

Linear Ft 

Cleaning of Storm Drain Pipe  12,088

CCTV Inspection of Storm Drain Pipe  12,088

Repair and Replace with 10"‐36" HDPE Pipe  800

Repair and Replace Shallow w/ 6"‐24" HDPE  1000

New 12"‐18" HDPE Pipe  200

Centrifugally ‐ Cast Conc. Pipe Liner 32"‐36"  510

  Linear Ft 

Curb and Gutter  3,007

AC Dike (Compressed asphalt curb)  10,211

12" Deep V Ditch‐CD60  509

10” and 18” Valley Gutter  620

 

The map below shows the road segments planned for repair in the 2017 paving projects. 

 

G.7.a

Packet Pg. 118

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 25: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

  

 

G.7.a

Packet Pg. 119

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 26: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

  

G.7.a

Packet Pg. 120

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 27: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

27  

2018 Paving Program 

The City of Orinda plans to perform pavement rehabilitation in 2018 on 70 Street segments 

in 55 Streets within the city. A list of the streets selected for construction in 2018 is attached 

below as reference. Design work to prepare the plans, specifications and cost estimate 

started in July 2017. Currently, various activities are being performed throughout the City by 

the design consultant team, which include locating existing underground utilities, closed‐

circuit television reviews (CCTV) of storm drain pipes, deflection testing of pavement 

sections and taking core samples of pavement sections. These activities are being performed 

to assist with detailed design, to support contract bid packages. In addition, potholing the 

pavement surface for verifying depths of existing utilities is scheduled to begin in November. 

This pothole information will also be used by utility agencies such as PG&E, East Bay 

Municipal Utility District (EBMUD) and Central Contra Costa Sanitary District (CCCSD) to 

relocate facilities which are in conflict with the proposed pavement work, ahead of the start 

of construction. 

The scope of work consists of two types of pavement rehabilitation (i) Full Depth 

Reclamation (FDR) and (ii) Mill & Overlay. Full Depth Reclamation is an economical, in‐place 

recycling alternative to road reconstruction.  As with prior years, drainage Improvements 

will be performed first, including partial or full replacement of storm drain pipes under 

streets, where needed. 

A project map and a list of the streets selected for construction in 2018 are attached below 

for reference. 

As a part of the 2018 project, approximately $3.5 million dollars are budgeted for additional, 

larger‐scale drainage improvements. The listed projects below are based on the 2016 Storm 

Drain Plan, which identified storm drains that were under capacity for a 10 year storm event 

or were in poor condition. 

   

G.7.a

Packet Pg. 121

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 28: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

28  

 

Brookside Road  Crossing Brookside Road. NE 

of intersection with Moraga 

Way 

Replacement or Rehabilitation of a 96‐

inch CMP culvert under Brookside Road 

Canon Dr.  Crossing Canon Dr., approx. 

900’ before cul‐de‐sac 

Replace 42” and 60” CMP 

Coral Dr.  Crossing Coral Dr. Between 

Eastwood Dr. and Ivy Dr. 

Rehabilitate or Replace single 72‐inch 

CMP culvert under Coral Drive 

Daryl Drive   Crossing Daryl Dr., Just west 

of Glorietta Blvd. Intersection

Replace existing box with two new 36‐

inch culverts to add capacity 

Daryl Drive  Crossing Daryl Dr., approx. 

100’ south of Overhill Rd. 

Upsizing the existing 36‐inch CMP to a 

48‐inch RCP to add capacity 

Ranch Road  Crossing Ranch Rd. 300’ 

before cul‐de‐sac 

Rehabilitate 60‐inch CMP pipe

Various 

Locations 

  Construct Concrete V Ditch and Curb 

and Gutter to Control Surface Water 

runoff  

 

G.7.a

Packet Pg. 122

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 29: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

  

G.7.a

Packet Pg. 123

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 30: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

31  

2018 PAVEMENT REHABILITATION ‐ RESIDENTIAL STREETSSTREET #  Street Name  Begin Location End Location Length (FT) Treatment

1 ABBOT COURT  MORGA VIA CUL‐DE‐SAC  339 FDR2 ARDILLA ROAD  CAMINO PABLO NORTH LANE  1,800 FDR

3 ARDITH COURT  CORAL DRIVE CUL‐DE‐SAC  279 FDR

4 AUSTIN COURT  MUTH DR. CUL‐DE‐SAC  420 M & O

5 AVENIDA DE ORINDA  ORINDA WAY END 314 FDR

6 BARBARA ROAD  SPRING RD. OAK RD. 1,440 M & O

7 BATES BLVD  MUTH DR (N) TAHOS RD  1,020 FDR

8 BATES BLVD  DAVIS RD MUTH DR (S)  991 M & O

9 BATES BLVD  MUTH DR (S) WARFORD TERR  1,540 M & O

10 BATES COURT  TAHOS RD END 400 FDR

11 BEACONSFIELD COURT  ARDITH DRIVE CUL‐DE‐SAC  715 FDR

12 BROADVIEW TERRACE  OVERHILL RD. CUL‐DE‐SAC  840 FDR

13 BROOKSIDE ROAD  ESTATES DR ORCHARD RD  500 FDR

14 CANON DRIVE  211 CAONN DRIVE CUL‐DE‐SAC  800 FDR

15 CATHERINE COURT  OVERHILL RD. CUL‐DE‐SAC  565 FDR

16 CORAL DRIVE  MORAGA WAY IVY DR 1,770 FDR

17 COURTNEY LANE  DONALD DRIVE CUL‐DE‐SAC  845 FDR

18 DALEWOOD DRIVE  LOMBARDY LN AMBER VALLEY DR 1,600 FDR

19 DARYL DRIVE  GLORIETTA BLVD. OVERHILL RD.  1,080 FDR

20 DONALD DRIVE  ALICE LANE PRIVATE STREET  1,140 FDR

21 DOS ENCINAS  EL CAMINO MORAGA CUL‐DE‐SAC  1,180 FDR

22 DOUGLAS COURT  ROBERT RD. CUL‐DE‐SAC  180 M & O

23 DOVER COURT  DONALD DRIVE CUL‐DE‐SAC  455 FDR

24 EL TOYONAL  3000FT W/O VISTA DEL ORINDA END AT BARRICADE 1,112 FDR

25 EL TOYONAL  1500FT W/O VISTA DEL ORINDA 3000FT W/O VISTA DEL ORINDA 1,500 FDR

26 ESTATES DRIVE  BROOKSIDE ROAD SCENIC DRIVE  2,803 FDR

27 EVERGREEN DRIVE  TARABROOK DR. CUL‐DE‐SAC  1,660 FDR

28 HIDDEN VALLEY  PAVEMENT CHANGE CITY LIMIT  725 FDR

29 HIGHLAND COURT  OVERHILL RD. CUL‐DE‐SAC  410 FDR

30 HILLCREST DRIVE  OVERHILL ROAD END 1,820 M & O

31 ICHABOD LANE  SLEEPY HOLLOW LANE BERRY BROOK HOLLOW (PVT) 1,155 FDR

32 KEITH DRIVE  END EVANS PL  760 FDR

33 LA CRESTA  PICO COURT CARMEN COURT  1,450 FDR

34 LA VUELTA  LA ESPIRAL (S) LA ESPIRAL (N)  1,610 FDR

35 MEADOW COURT  MEADOW LN. CUL‐DE‐SAC  360 FDR

36 MEADOW LANE  GLORIETTA BLVD.  MEADOW VIEW RD.  1,350 M & O 

 

G.7.a

Packet Pg. 124

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 31: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

32  

2018 PAVEMENT REHABILITATION ‐ RESIDENTIAL STREETSSTREET #  Street Name  Begin Location End Location Length (FT) Treatment

37 MEADOW VIEW ROAD  CUL DE SAC EAST OF GLORIETTA BLVD GLORIETTA BLVD 1,325 FDR38 MORAGACOURT  MORAGA WAY CUL‐DE‐SAC  180 FDR

39 MUTH DRIVE  BATES BLVD (W) WARFORD TERR 2,340 FDR

40 MUTH DRIVE  WARFORD TERR WANDA LN  1,820 FDR

41 MUTH DRIVE  WANDA LN BATES BLVD (E)  1,145 FDR

42 NORTHWOOD DRIVE  MORAGA WAY DAVIS RD.  890 M & O

43 ORCHARD ROAD  BROOKSIDE ROAD GLORIETTA BLVD 2,165 FDR

44 ORCHARD ROAD  GLORIETTA BLVD CORTE BOMBERO 2,000 FDR

45 OVERHILL COURT  OVERHILL RD. CUL‐DE‐SAC  300 FDR

46 OWL HILL COURT  OWL HILL RD. CUL‐DE‐SAC  180 FDR

47 OWL HILL ROAD  OAK WOOD RD. ESTATES DR.  1,630 FDR

48 PARKWAY COURT  GLORIETTA BLVD. END 960 FDR

49 ROBERT ROAD  GLORIETTA BLVD. CITY LIMITS  1,125 M & O

50 SCENIC DRIVE  NORTHERLY PROP LINE 68 SCENIC ORCHARD ROAD 1,685 FDR

51 SCENIC DRIVE  OVERHILL ROAD NORTHERLY PROP LINE 68 SCENIC 2,995 FDR

52 SILVERWOOD COURT  TAHOS RD. CUL‐DE‐SAC  365 FDR

53 SNOW COURT  LOST VALLEY DR CUL‐DE‐SAC  600 FDR

54 SOUTHWOOD COURT  SOUTHWOOD DR. CUL‐DE‐SAC  310 M & O

55 SOUTHWOOD DRIVE  TARA RD CUL‐DE‐SAC  620 M & O

56 SPRING ROAD  BROOKWOOD RD. 132 SPRING ROAD 1,770 M & O

57 TAHOS ROAD  NORTHERLY PROP LINE 565 TAHOS CUL DE SAC  1,613 FDR

58 TARABROOK DRIVE  TARA RD. CUL‐DE‐SAC  1,340 FDR

59 TARRY LANE  53 TARRY LN. VAN TASSEL LN. 1,350 FDR

60 TARRY LANE  LOMBARDY LN SLEEPY HOLLOW LN. 500 M & O

61 UNDERHILL ROAD  SPRING RD. CAMINO ENCINAS 1,710 FDR

62 VALENCIA ROAD  DON GABRIEL WAY ALTAMOUNT DRIVE 1,730 FDR

63 VALLEY COURT  VALLEY DR. CUL‐DE‐SAC  200 FDR

64 VASHELL WAY  Moraga Way Davis Road  450 M & O

65 VIA HERMOSA  LA ESPIRAL LOOP END  2,000 FDR

66 VIANNE COURT  HILLCREST DR.  CUL‐DE‐SAC  300 FDR 

2018 PAVMENT REHABILITATION ‐ ARTERIAL STREETSSTREET#  Street Name  Begin Location End Location Length (FT) Treatment

67 MINER ROAD  CAMINO PABLO BIEN VENIDA  1,480 M & O68 MINER ROAD  BIEN VENIDA CAMINO DON MIGUEL 1,895 M & O

69 MINER ROAD  CAMINO DON MIGUEL LOMBARDY LN  2,130 M & O

70 MINER ROAD  PAVTCHANGE  GARDINER CT.  1,630 FDR 

G.7.a

Packet Pg. 125

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 32: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

33  

 

2019 Paving Program  

The scope of work for 2019 consists of rehabilitating 145 street segments in 125 streets 

using two types of pavement rehabilitation (i) Mill & Overlay (M&O) and (ii) Slurry Seal.  As 

with prior years, drainage Improvements will be performed prior to paving work, including 

partial or full replacement of storm drain pipes under streets, where needed.   

Mill & Overlay rehabilitation is used when the existing pavement shows signs of surface 

failures but the damage is not so severe that it warrants complete reconstruction of the 

pavement. The process involves removal of the top few inches of asphalt pavement by 

milling, and then replacing it with new asphalt overlay. Areas of pavement that show severe 

distress due to failure of the aggregate base layer will be removed and replaced prior to 

installing the final asphalt overlay. 

Slurry Seal is the application of a mixture of asphalt emulsion and very small crushed rock 

aggregates to the existing asphalt pavement surface. The process of placing this mixture 

(Slurry) on pavement surface is referred as “seal” because it is intended to seal the 

blemishes in the pavement surface. As with the Mill and Overlay method, areas of pavement 

that show severe distress due to failure of the aggregate base layer will be removed and 

replaced prior to applying the asphalt emulsion.   

Design work to prepare the plans, specifications, and estimates will begin in February of 

2018.  All the storm drains under the road will be cleaned and inspected prior to the 

preparation of the design plans.  The city plans to advertise the project in February 2019.  

A project map and a list of the streets selected for construction in 2019 are attached below 

for reference. 

As a part of the 2019 project, approximately $3.5 million dollars is budgeted to improve 

drainage components that were identified to be under capacity or in poor condition in the 

2016 Storm Drain Plan. The table below shows a list of potential drainage improvements.  

G.7.a

Packet Pg. 126

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 33: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

34  

Candle Terrace  Extending north along 

Candle Terrace from 

Dalewood 

Upsizing the existing 18‐inch pipe to a 24‐

inch RCP 

Easton Ct.  Along upper of Easton 

Ct, extending east 

towards Hall Dr. 

To improve capacity, Replace 4 sections of 

18‐inch pipe with 24‐inch RCP, and 3 

sections of 21‐inch with 30‐inch RCP 

El Caminito   Intersection of El 

Caminito and Camino 

Sobrante 

Replacing the existing arched CMP with a 

36‐inch RCP and a new Parallel 24‐inch 

RCP 

Haceinda Circle  Intersection of 

Hacienda Circle and 

Acacia Dr. 

Upsizing the existing 18‐inch CMP to a 24‐

inch RCP to improve capacity 

La Espiral Road  Crossing La Espiral Rd. 

approx. 1400’ NE of La 

Vuelta 

 

Upsizing the existing 12‐inch pipe to a 

new 18‐ inch RCP 

Sleepy Hollow Lane  Near 500’ South Of 

Normandy Lane 

Upsizing the existing 24‐inch CMP to a 36‐

inch RCP 

Various Locations     Construct Concrete V Ditch and Curb and 

Gutter to Control Surface Water Runoff 

 

G.7.a

Packet Pg. 127

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 34: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

35  

 

G.7.a

Packet Pg. 128

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 35: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

36  

G.7.a

Packet Pg. 129

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 36: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

37  

 

STREET #  Street Name  Begin Location End Location Length (FT) Width (FT) Area (SF) Current PCI Treatment

2019 PAVMENT REHABILITATION ‐ RESIDENTIAL STREETS

1  ACACIA DRIVE  MANZANITA DR.  CUL‐DE‐SAC 1,935  22 42,570 45 MILL AND THICK OVERLAY2  ALICE LANE  1000'W/ZANDER  DRIVE DONALD DRIVE 1,100  26 28,600 67 SLURRY SEAL & DIGOUTS

3  ALTARINDA CIRCLE  E. ALTARINDA DR.  CUL‐DE‐SAC 245  25 6,125 80 SLURRY SEAL & DIGOUTS

4  ARDITH DRIVE  WESTOVER COURT IVY DRIVE 846  33 27,918 47 MILL AND THICK OVERLAY

5  ARDITH DRIVE  CORAL DRIVE  TOTTERDELL  COURT 1,242  33 40,986 49 MILL AND THICK OVERLAY

6  ARDITH DRIVE  TOTTERDELL  COURT WESTOVER COURT 1,145  33 37,785 56 MILL AND THICK OVERLAY

7  ARDOR DRIVE  LOMA LINDA COURT  CUL‐DE‐SAC  971  22  21,362  45  MILL AND THICK OVERLAY 

8  ASPINWALL COURT  EASTWOOD DRIVE CUL‐DE‐SAC 610  25 15,250 41 MILL AND THICK OVERLAY

9  AVIS COURT  DONALD DRIVE  CUL‐DE‐SAC 166  26 4,316 91 SLURRY SEAL & DIGOUTS

10  BATES BLVD  WARFORD TERR  MUTH DR (N) 2,179  32 69,728 64 SLURRY SEAL & DIGOUTS

11  BEL AIR COURT  BEL AIR DR.  CUL‐DE‐SAC 120  22 2,640 85 SLURRY SEAL & DIGOUTS

12  BEL AIR DRIVE  PARKLANE DR.  CUL‐DE‐SAC 1,380  22 30,360 97 SLURRY SEAL & DIGOUTS

13  BRYANT WAY  CUL‐DE‐SAC  MORAGA WAY 276  29 8,004 65 SLURRY SEAL & DIGOUTS

14  CALIFORNIA AVE  PROPERTY LINE AT #65/61 END AT #39 CALIFORNIA AVE. 466  22 10,252 65 SLURRY SEAL & DIGOUTS

15  CALVIN COURT  CALVIN DRIVE  CUL‐DE‐SAC 396  30 11,880 31 MILL AND THICK OVERLAY

16  CALVIN DRIVE  CALVIN COURT  END 360  30 10,800 50 MILL AND THIN OVERLAY

17  CAMINO DON MIGUEL  MINER ROAD  CAMINO DON MIGUEL 4,485  20 89,700 41 MILL AND THICK OVERLAY

18  CAMINO ENCINAS  MORAGA WAY (N) MORAGA WAY (S) 2,100  30 63,000 41 MILL AND THICK OVERLAY

19  CAMINO SOBRANTE  EL RIBERO (SOUTH) LA ESPIRAL 2,460  21 51,660 55 MILL AND THIN OVERLAY

20  CANDLE TERRACE  NEW STREET SECTION CUL‐DE‐SAC 295  29 8,555 73 SLURRY SEAL & DIGOUTS

21  CARMEN COURT  LA CRESTA ROAD  CUL‐DE‐SAC 340  20 6,800 38 MILL AND THICK OVERLAY

22  CHAPPARAL PLACE  ELTOYONALRD  CUL‐DE‐SAC 350  20 7,200 33 MILL AND THICK OVERLAY

23  CHARLES HILL PLACE  END  CHARLES HILL RD. 487  21 10,227 28 MILL AND THICK OVERLAY

24  CHELTON COURT  WHITEHALL DRIVE CUL‐DE‐SAC 420  25 10,500 93 SLURRY SEAL & DIGOUTS

25  CIELO COURT  IVY DRIVE  CUL‐DE‐SAC 214  25 5,350 90 SLURRY SEAL & DIGOUTS

26  CLAREMONT AVE  CAMINO PABLO  HOLLY LANE 1,930  22 42,460 63 MILL AND THIN OVERLAY

27  COACHWOOD  TERRACE  DALEWOOD DR.  CUL‐DE‐SAC 670  32 21,440 26 MILL AND THICK OVERLAY

28  CORAL DRIVE  IVY DRIVE  FIESTA CIRCLE 1,115  26 28,990 42 MILL AND THICK OVERLAY

29  CORTE HOLGANZA  IVY DRIVE  CUL‐DE‐SAC 203  27 5,481 39 MILL AND THICK OVERLAY

30  CORTE SOMBRITA  IVY DRIVE  CUL‐DE‐SAC 270  27 7,290 52 MILL AND THIN OVERLAY

31  CRANE COURT  VAN TASSEL LANE  CUL‐DE‐SAC 315  16 5,040 85 SLURRY SEAL & DIGOUTS

32  CRESCENT DRIVE  CLAREMONT AVE.  PIEDMONT AVE. 896  19 17,024 75 SLURRY SEAL & DIGOUTS

33  CREST VIEW DRIVE  VALLEY VIEW DRIVE CRESTVIEW  COURT 1,901  22 41,822 95 SLURRY SEAL & DIGOUTS

34  CREST VIEW DRIVE  SOUTHERLY PROP LINE 199 VALLEY CUL DE SAC 914  22 20,108 97 SLURRY SEAL & DIGOUTS

35  CROSS RIDGE TERRACE  KITE HILL RD.  END 240  25 6,000 84 SLURRY SEAL & DIGOUTS

36  CROSSRIDGE  COURT  KITE HILL RD.  CUL‐DE‐SAC 160  23 3,680 68 SLURRY SEAL & DIGOUTS

37  CROSSRIDGE PLACE  KITE HILL RD.  CUL‐DE‐SAC 147  23 3,381 57 MILL AND THIN OVERLAY

38  CROWN COURT  IVY DRIVE  CUL‐DE‐SAC 285  25 7,125 53 MILL AND THIN OVERLAY

39  DALE COURT  ALTAMOUNT DRIVE CUL‐DE‐SAC 190  20 3,800 36 MILL AND THICK OVERLAY

40  DALEWOOD DRIVE  AMBER VALLEY DR SUNDOWN TERR. 1,047  36 37,692 32 MILL AND THICK OVERLAY

41  DALEWOOD DRIVE  PRIVATE STREET  LOMBARDY LN 843  36 31,350 39 MILL AND THICK OVERLAY

42  DALEWOOD DRIVE  SUNDOWN TERR.  CUL‐DE‐SAC (EAST) 950  36 35,000 41 MILL AND THICK OVERLAY

 

G.7.a

Packet Pg. 130

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 37: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

38  

STREET #  Street Name  Begin Location End Location Length (FT) Width (FT) Area (SF) Current PCI Treatment

43  DANZA COURT  IVY DRIVE  CUL‐DE‐SAC 208  27 5,616 58 SLURRY SEAL & DIGOUTS44  DAPHNE COURT  CHARLES HILL ROAD END 267  15 4,005 95 SLURRY SEAL & DIGOUTS

45  DAVIS ROAD  BRYANT WAY  SOUTHWOOD DR 2,167  22 47,674 50 MILL AND THIN OVERLAY

46  DIABLO VIEW DRIVE  MINER RD.  CHARLES HILL RD. 5,110  18 91,980 45 MILL AND THICK OVERLAY

47  DIAS DORADOS  CAMINO SOBRANTE LA CINTILLA 917  17 15,589 71 SLURRY SEAL & DIGOUTS

48  E. ALTARINDA DR  ORINDAWOODS DR. CUL‐DE‐SAC 1,090  29 31,610 27 MILL AND THICK OVERLAY

49  EASTON COURT  HALL DRIVE  CUL‐DE‐SAC 1,010  25 25,250 72 SLURRY SEAL & DIGOUTS

50  EASTWOOD DRIVE  CARISBROOK DRIVE CORAL DRIVE 1,031  33 34,023 45 MILL AND THICK OVERLAY

51  EASTWOOD DRIVE  MORAGA WAY  CARISBROOK DRIVE 565  33 18,645 55 MILL AND THIN OVERLAY

52  EL SERENO ROAD  LA ESPIRAL  CUL‐DE‐SAC 900  14 12,600 70 MILL AND THIN OVERLAY

53  EL SUENO  CAMINO SOBRANTE CUL‐DE‐SAC 525  15 7,875 89 SLURRY SEAL & DIGOUTS

54  EL TOYONAL  VISTA DEL ORINDA 1500FT W/O VISTA DEL ORINDA 1,500  18 27,000 41 MILL AND THICK OVERLAY

55  EL TOYONAL  LOMA VISTA (EAST) BONITA LN 1,106  18 19,908 46 MILL AND THICK OVERLAY

56  EL TOYONAL  LA ENCINAL  LOMA VISTA (WEST) 1,220  18 21,960 55 MILL AND THIN OVERLAY

57  EL TOYONAL  BONITA LN  LA ENCINAL 1,676  18 30,168 83 SLURRY SEAL & DIGOUTS

58  EL VERANO  LAS VEGAS  CUL‐DE‐SAC 620  18 11,160 42 MILL AND THICK OVERLAY

59  ESTABUENO  LAVENIDA  CUL‐DE‐SAC 387  24 9,288 82 SLURRY SEAL & DIGOUTS

60  ESTABUENO  LAVENIDA  MORAGA WAY 1,029  24 24,696 87 SLURRY SEAL & DIGOUTS

61  FAIRWAY DRIVE  HACIENDA CIR.  END 77  18 1,386 40 MILL AND THICK OVERLAY

62  FIESTA CIRCLE  IVY DRIVE  IVY DRIVE 2,434  33 80,322 97 SLURRY SEAL & DIGOUTS

63  FLEETWOOD COURT  HALL DRIVE  CUL‐DE‐SAC 723  25 18,075 35 MILL AND THICK OVERLAY

64  GLORIETTA COURT  GLORIETTA BLVD  CUL‐DE‐SAC 742  22 16,324 78 SLURRY SEAL & DIGOUTS

65  GREAT OAK CIRCLE  ORCHARD RD.  CUL‐DE‐SAC 120  22 2,640 60 SLURRY SEAL & DIGOUTS

66  GREYSTONE TERRACE  ORINDAWOODS DR. BULB BOTH ENDS 745  30 22,350 53 SLURRY SEAL & DIGOUTS

67  HACIENDA CIRCLE  HACIENDA CIRCLE  ACACIA DR (N) 1,200  22 26,400 52 MILL AND THIN OVERLAY

68  HACIENDA CIRCLE  ACACIA DR (S)  END 425  23 9,775 71 MILL AND THIN OVERLAY

69  HALL DRIVE  DONALD DR.  END 164  24 3,936 40 MILL AND THICK OVERLAY

70  HARRAN CIRCLE  E. ALTARINDA DR.  CUL‐DE‐SAC 267  26 6,942 77 SLURRY SEAL & DIGOUTS

71  HARTFORD ROAD  CHARLES HILL CIRCLE END 400  15 6,000 55 MILL AND THIN OVERLAY

72  HAWKRIDGE  TERRACE  ORINDAWOODS DR. BULB BOTH ENDS 510  29 14,790 43 MILL AND THICK OVERLAY

73  HILLCREST DRIVE  MARTHA RD.  OVERHILL ROAD 1,610  23 37,030 96 SLURRY SEAL & DIGOUTS

74  IDYLL COURT  MORAGA VIA  CUL‐DE‐SAC 230  31 7,130 53 MILL AND THIN OVERLAY

75  IRONBARK CIRCLE  ORINDAWOODS DR. (W) ORINDAWOODS DR. (E) 1,988  25 49,700 46 MILL AND THICK OVERLAY

76  IRONBARK COURT  IRONBARK CR.  CUL‐DE‐SAC 466  29 13,514 49 MILL AND THIN OVERLAY

77  IRONBARK PLACE  IRONBARK CR.  CUL‐DE‐SAC 365  29 10,585 35 MILL AND THICK OVERLAY

78  IRVING COURT  IRVING LANE  CUL‐DE‐SAC 208  21 4,368 54 MILL AND THIN OVERLAY

79  IRVING LANE  LOMBARDY LANE  VAN RIPPER LANE 1,296  19 24,624 72 SLURRY SEAL & DIGOUTS

80  KATRINA COURT  VAN TASSEL LANE  CUL‐DE‐SAC 275  23 6,325 39 MILL AND THICK OVERLAY

81  KELLIE ANN COURT  MEADOW VIEW RD. CUL‐DE‐SAC 280  29 8,120 64 SLURRY SEAL & DIGOUTS

82  KITTIWAKE ROAD  MANZANITA DR.  CUL‐DE‐SAC 335  18 6,030 46 MILL AND THICK OVERLAY

83  LA CAMPANA  LA ESPIRAL (E)  LA ESPIRAL (W) 2,600  16 41,600 46 MILL AND THICK OVERLAY

84  LA CUESTA  CAMINO SOBRANTE END 3,080  15 46,200 28 MILL AND THICK OVERLAY

85  LA ESPIRAL  VIA HERMOSA  CAMINO SOBRANTE NORTH 1,094  20 21,880 31 MILL AND THICK OVERLAY

86  LA ESPIRAL  CAMINO SOBRANTE SOUTH LAS VEGAS ROAD 4,500  20 90,000 44 MILL AND THICK OVERLAY

87  LA NORIA  CAMINO SOBRANTE (S) CAMINO SOBRANTE (N) 1,530  15 22,950 41 MILL AND THICK OVERLAY

88  LA SENDA  LA NORIA  CUL‐DE‐SAC 330  16 5,280 62 SLURRY SEAL & DIGOUTS

 

G.7.a

Packet Pg. 131

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 38: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

39  

STREET #  Street Name  Begin Location End Location Length (FT) Width (FT) Area (SF) Current PCI Treatment

89  LA SOMBRA COURT  ARDOR DRIVE  CUL‐DE‐SAC 505  25 12,625 35 MILL AND THICK OVERLAY

90  LAS VEGAS ROAD  MIRA FLORES  VIA LAS CRUCES 1,000  19 19,000 26 MILL AND THICK OVERLAY

91  LAS VEGAS ROAD  ST. STEPHENS DRIVE LA ESPIRAL ROAD 1,050  19 19,950 26 MILL AND THICK OVERLAY

92  LAS VEGAS ROAD  LA ESPIRAL  MIRA FLORES 1,189  19 22,591 44 MILL AND THICK OVERLAY

93  LAVENIDA DRIVE  MORAGA WAY  B.C. @ 90 DEGREE 932  24 22,368 53 MILL AND THIN OVERLAY

94  LONGVIEW TERRACE  ORCHARD ROAD FRONTAGE BULB BOTH ENDS 331  20 6,620 63 SLURRY SEAL & DIGOUTS

95  MANZANITA DRIVE  CAMINO PABLO  CREEK BRIDGE 580  22 12,760 35 MILL AND THICK OVERLAY

96  MARSTON ROAD  MONTE VISTA RD.  CUL‐DE‐SAC 1,025  16 16,400 25 MILL AND THICK OVERLAY

97  MARTHA ROAD  GLORIETTA BLVD.  HILLCREST RD. 500  33 16,500 76 SLURRY SEAL & DIGOUTS

98  MEADOW PARK COURT  GLORIETTA BLVD.  END 1,200  25 30,000 71 SLURRY SEAL & DIGOUTS

99  MEADOWLANDS  COURT  MORAGA WAY  CUL‐DE‐SAC 128  24 3,072 95 SLURRY SEAL & DIGOUTS

100  MORAGA VIA  RUSTIC WAY  RHEEM BLVD 834  19 15,846 81 SLURRY SEAL & DIGOUTS

101  NONIE ROAD  TARA RD  END 185  15 2,775 92 SLURRY SEAL & DIGOUTS

102  NORTHWOOD  COURT  NORTHWOOD DR.  CUL‐DE‐SAC 300  22 6,600 64 SLURRY SEAL & DIGOUTS

103  OAK DRIVE  1000' W/MORAGA WAY CUL‐DE‐SAC 1,421  18 25,578 66 MILL AND THIN OVERLAY

104  OAK DRIVE  MORAGA WAY  1000' W/MORAGA WAY 1,000  20 20,000 71 MILL AND THIN OVERLAY

105  OAK FLAT ROAD  CHARLES HILL RD.  CUL‐DE‐SAC 390  12 4,680 43 MILL AND THICK OVERLAY

106  OAK LANE  MINER RD.  END 230  13 2,990 96 SLURRY SEAL & DIGOUTS

107  OLD CAMINO PABLO  END ‐ WEST OF CLAREMONT EAST ‐ EAST OF CLAREMONT 394  18 7,092 57 SLURRY SEAL & DIGOUTS

108  OLD CAMINO PABLO  NORTH LANE  ARDILLA ROAD 1,139  20 22,780 93 SLURRY SEAL & DIGOUTS

109  ORCHARD ROAD  CORTE BOMBERO  MORAGA WAY 382  21 8,022 95 SLURRY SEAL & DIGOUTS

110  PARKLANE DRIVE  GLORIETTA BLVD. (W) GLORIETTA BLVD. (E) 1,800  22 39,600 96 SLURRY SEAL & DIGOUTS

111  PICO COURT  LA CRESTA ROAD  CUL‐DE‐SAC 285  20 5,700 41 MILL AND THICK OVERLAY

112  PIEDMONT AVENUE  CRESCENT DR.  CLAREMONT AVE. 365  18 6,570 58 SLURRY SEAL & DIGOUTS

113  PUEBLO COURT  IVY DRIVE  CUL‐DE‐SAC 247  24 5,928 77 SLURRY SEAL & DIGOUTS

114  RICHARD COURT  VALLEY VIEW DRIVE CUL‐DE‐SAC 278  15 4,170 74 SLURRY SEAL & DIGOUTS

115  RIDGE GATE ROAD  VILLAGE GATE ROAD CUL‐DE‐SAC 580  25 14,500 49 MILL AND THIN OVERLAY

116  RISA COURT  IVY DRIVE  CUL‐DE‐SAC 670  25 16,750 58 MILL AND THIN OVERLAY

117  RUSTIC WAY  MORAGA VIA  CUL‐DE‐SAC (ALSO END) 563  16 9,008 89 SLURRY SEAL & DIGOUTS

118  SAGER COURT  DONNA MARIA WAY CUL‐DE‐SAC 357  25 8,925 65 MILL AND THIN OVERLAY

119  SANTA LUCIA  CAMINO DON MIGUEL CUL‐DE‐SAC 435  20 8,700 91 SLURRY SEAL & DIGOUTS

120  SCENIC COURT  SCENIC DR.  CUL‐DE‐SAC 240  17 4,080 64 SLURRY SEAL & DIGOUTS

121  SILVEROAK TR  SUNDOWN TR.  CUL‐DE‐SAC 657  29 19,053 46 MILL AND THICK OVERLAY

122  SILVERWOOD  ROAD  TAHOS RD  CITY LIMIT 2,420  29 70,180 85 SLURRY SEAL & DIGOUTS

123  SLEEPY HOLLOW LANE  SOUTHERLY EDGE NORMANDY LANE TARRY LANE 1,693  22 37,246 67 MILL AND THIN OVERLAY

124  SNOWBERRY LANE  TARRY LN  CUL‐DE‐SAC 670  20 13,400 95 SLURRY SEAL & DIGOUTS

125  SOUTHWAITE  COURT  MORAGA WAY  CUL‐DE‐SAC 822  33 27,126 93 SLURRY SEAL & DIGOUTS

126  ST. JAMES COURT  VAN RIPPER LANE  CUL‐DE‐SAC 790  19 15,010 34 MILL AND THICK OVERLAY

127  STANTON AVE  STANTON CT.  CUL‐DE‐SAC 980  30 32,350 78 SLURRY SEAL & DIGOUTS

128  STANTON COURT  STANTON AVE.  CUL‐DE‐SAC 535  25 13,375 72 SLURRY SEAL & DIGOUTS

129  STEIN WAY  MORAGA WAY  OAK RD. 1,140  30 34,200 59 MILL AND THIN OVERLAY

130  STEIN WAY  OAK RD.  KNICKERBOCKER LN. 1,290  30 38,700 69 MILL AND THIN OVERLAY

131  SUNNYSIDE LANE  VAN TASSEL LANE  END 1,780  23 40,940 29 MILL AND THICK OVERLAY

132  TOTTERDELL  COURT  ARDITH DRIVE  CUL‐DE‐SAC 538  25 13,450 57 MILL AND THIN OVERLAY

   

G.7.a

Packet Pg. 132

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 39: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

40  

STREET #  Street Name  Begin Location End Location Length (FT) Width (FT) Area (SF) Current PCI Treatment

133  VAN TASSEL LANE  CENTERLINE VAN RIPPER CENTERLINE  SUNNYSIDE 1,271  20 25,420 36 MILL AND THICK OVERLAY

134  VAN TASSEL LANE  LOMBARDY LANE  CENTERLINE VAN RIPPER 1,635  20 32,700 49 MILL AND THIN OVERLAY

135  VAN TASSEL LANE  CENTERLINE  SUNNYSIDE TARRY LANE 874  20 17,480 53 MILL AND THIN OVERLAY

136  VIA CALLADOS  SUNNYSIDE LANE  CUL‐DE‐SAC 340  24 8,160 26 MILL AND THICK OVERLAY

137  VIA FLOREADO  VIA FLOREADO STA. 2890 LAS VEGAS 1,070  17 18,190 53 MILL AND THIN OVERLAY

138  VIA FLOREADO  ST. STEVENS DR.  VIA FLOREADO STA. 2890 2,890  25 72,250 57 MILL AND THIN OVERLAY

139  VILLAGE GATE ROAD  ORINDA WOODS DR. VILLAGE GATE/WATCHWOOD RD. 1,960  25 49,000 68 MILL AND THIN OVERLAY

140  VISTA DEL MAR  CAMINO DON MIGUEL DEL MAR COURT 815  25 20,375 93 SLURRY SEAL & DIGOUTS

141  WANDA LANE  HIDDEN VALLEY RD. MUTH DR. 1,020  25 25,500 82 SLURRY SEAL & DIGOUTS

142  WASHINGTON LANE  SLEEPY HOLLOW LANE END 533  21 11,193 44 MILL AND THICK OVERLAY

143  WATCHWOOD  COURT  WATCHWOOD RD. END OF WATCHWOOD CT. 270  25 6,750 78 SLURRY SEAL & DIGOUTS

144  WHITEHALL DRIVE  686' E/MORAGA WAY ARDITH DRIVE 686  33 22,638 44 MILL AND THICK OVERLAY

145  ZANDER DRIVE  RHEEM BLVD.  ZANDER COURT  979  29  28,391  26  MILL AND THICK OVERLAY 

  

2019 PAVMENT REHABILITATION ‐ ARTERIAL STREETS STREET #  Street Name  Begin Location End Location Length (FT) Width (FT) Area (SF) Current PCI Treatment

1  EL TOYONAL  CAMINO PABLO  LOMA VISTA (EAST)  1,781  18  32,058  41  MILL AND THICK OVERLAY 

2  LAS VEGAS ROAD  VIA LAS CRUCES  ST. STEPHENS DRIVE  320  19  6,080  38  MILL AND THICK OVERLAY 

3  LOMA VISTA DRIVE  EL DORADO LN  EL TOYONAL (EAST)  1,586  18  28,548  47  MILL AND THICK OVERLAY 

4  LOMBARDY LANE  MINER ROAD  TARRY LANE  1,136  23  26,128  50  MILL AND THICK OVERLAY 

5  ORINDA WAY  SANTA MARIA WAY  682FT N/O SANTA MARIA V  682  50  34,100  50  MILL AND THICK OVERLAY 

6  SOUTHWOOD  DRIVE  MORAGA WAY  TARA RD  1,600  20  32,000  54  MILL AND THIN OVERLAY 

7  VIA LAS CRUCES  HONEY HILL RD.  LAS VEGAS RD.  730  29  21,170  24  MILL AND THICK OVERLAY 

 

Residential Segments =  145 

Residential Streets =  125 

Arterial/Collector Segments =  7 

Arterial/Collector Streets =  7 

   

G.7.a

Packet Pg. 133

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n

Page 40: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

41  

Conclusion 

To conclude this report, there are a few key points that merit repeating for emphasis. While much has been accomplished, there are still several facets of the long‐range plan for Orinda’s roads, drainage, and related infrastructure that must be attended‐to over the next several years and beyond.  The current available funding sources will carry the residential road repair program to a very successful level of completion. It is forecast that by the end of the 2019 program, Orinda’s Pavement Condition Index will achieve an average level of close to 90, or “Very Good” to “Excellent” condition; one of the best city‐wide ratings in the area. Additionally, as stated in the report, the current funding will enable the engineering and repair of the storm‐drains under and adjacent to the residential road upgrades.  However, in spite of all the successes, it must be noted that the effort is not complete. Current funding does not address the repairs and rebuilding required for some remaining arterial and collector streets and associated storm drain systems. As described in this report, the Citizens Infrastructure Oversight Commission continues to recommend that Orinda pursue additional funding efforts to address this unmet need.  Additionally, the city must bear in mind that roads and drainage systems wear out over time. This report continues to note that Orinda must identify and develop a long‐term road and infrastructure program that creates sources of sufficient funds to maintain our road and drainage systems to a level that reflects the improvements achieved over the last several years. It would be extremely disappointing to every citizen of our city, if the money and effort that has been spent to date, were allowed to “wash away” due to lack of proper care and maintenance.  With respect, this report is submitted to the City Council by the Citizens Infrastructure Oversight Commission for your review and approval. 

   

G.7.a

Packet Pg. 134

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 41: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

42  

Attachments  

1. Attachment 1 – Pavement Condition Index (PCI) Ratings Definition with 

Images of Varying PCI Ratings and Impact of Drain Failure 

2. Attachment 2  –City  of Orinda Pavement Management Program  Policy  and 

Criteria  for  Selecting  Streets  for  Repair  Using Measure  L  Sales  Tax  Fund, 

Approved January 21, 2014 

3. Attachment 3 – CIOC Annual Report to the City Council, 2017 

4. Attachment 4 ‐‐ Glossary of Terms.  Summary of terms used in this report 

5. Attachment 5 ‐‐ Timeline Roads and Drains Milestones and Projects 

6. Attachment 6 ‐ ‐ Grants Applied for and Awarded, to Support Orinda Roads 

and Drains Projects 

7. Attachment 7 ‐‐ Storm Drains Likely to Need Near‐Term Repairs 

8. Attachment 8 ‐‐ Arterials, Collectors, and School Routes Sill in Need of Repairs 

9. Attachment 9 ‐‐ Full Depth Reclamation Overview  

G.7.a

Packet Pg. 135

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 42: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 1  

Attachment 1 

 

Pavement Condition Definitions  

 PCI Range  Condition  Description

90‐100  Excellent  Little or no distress. 

70‐89 Good to  Very Good 

Little or no distress, with the exception  of utility  patches  in  good condition, or minor to moderate  hairline  cracks;  typically  lightly weathered. 

50‐69  Fair 

Light to moderate weathering, light load‐related base failure, moderate linear cracking. 

25‐49  Poor 

Moderate  to  severe  weathering, moderate levels  of  base  failure, moderate to heavy linear cracking. 

0‐24  Very Poor Extensive weathering, moderate to heavy base failure, failed  patches, extensive network of moderate to heavy linear  cracking. 

  Please see the photographs below for examples roads at various PCI’s. 

 

G.7.a

Packet Pg. 136

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 43: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 1  

        

        

Charles Hill Road PCI = 8 

Ardith Drive at Darnby  PCI = 47

Greenwood Court PCI =15 

G.7.a

Packet Pg. 137

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 44: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 1  

      

  

Rheem Blvd PCI = 70

Claremont Avenue  PCI = 80

G.7.a

Packet Pg. 138

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 45: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 2 

Attachment 2 

 

City of Orinda Pavement Management Program (PMP) 

Policy and Criteria for Selecting Streets for Repair Using Measure L Sales  Tax Funds Approved January 21, 2014 

   Policy  With  the  adoption  of  the Measure  L,  .5%  Sales  tax,  the City has  an  additional  source of funds for road repair and reconstruction. This Measure represents the  first  phase  of a  multi‐year  plan  to  repair  all  the  City’s  streets.  Even  with  this  additional  funding, current  budgetary  constraints  and  the  poor  and  deteriorating  condition of Orinda’s roads require the City to apply budgeted funds only to those  residential roads where the most benefit for the most residents can be obtained. With the Measure L funds the City has  committed  to make  repair  of  the  residential  roads  a  priority.  The  goal  of  this program  is  to distribute  the  residential roads to be repaired throughout the City.  The Program  Annually, funds permitting, roads to be repaired will be selected as follows:  

1. The street segments must be classified as residential.  

2. The  street  segments must  be  among  the worst  residential  roads, which means the  Pavement  Condition  Index  (PCI)  for  that  segment  of  road  as  calculated by the  StreetSaver  program  is  less  than  or  equal  to  25,  and  with  ride  quality (roughness  of  ride)  considered  using  an  acceptable  objective  measure. 

 

3. The most heavily used  residential  road  segments, based on actual  traffic  counts, will be repaired first. The road segments will be rank in descending order of  traffic volume,  with  the  highest  volume  road  segments  forming  a  pool of candidate roads for the annual program. 

 4. Other  factors,  such  as  equitable  distribution  of  the  projects  throughout  the 

community  and  underground  utility  repair  schedules,  will  be  considered  in selecting the annual list of road segments to be repaired. 

 

G.7.a

Packet Pg. 139

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 46: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 3 

Attachment 3 

 

Citizens’ Infrastructure Oversight Commission 

Annual Report to the Orinda City Council 

2017 

Attached by Reference 

The Annual Report can be found on the City’s Web Site under the Roads and 

Infrastructure Tab. 

  

G.7.a

Packet Pg. 140

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 47: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 4 

Attachment 4 

Glossary of Terms  AC ‐ Arterials, Collectors and Bus Routes  Those public roads that have the greatest use and suffer the most wear and tear requiring more frequent service and repair. 

ADT ‐ Average Dally Traffic  This is a measure of the frequency of use of a road and is used to help determine which repair project will benefit the greatest number of residents. 

Annual Report  An annual report made by the CIOC to the Council detailing activities regarding the pavement management program over the past year. 

Associated Drainage This includes existing pipes, culverts and gutters under and adjacent to the roadway surface.  Note that the city has limited authority to address drainage that passes through private property (including PG&E property). 

Bond and Tax Measures  The sales tax [2012 Measure L] and bond measures [2014 Bond Measure J and 2016 Bond Measure L] approved by the voters to repair public residential roads. 

Drain ‐ Storm Drain  Any of the drains used to carry off surface water. 

CIOC ‐ Citizens Infrastructure Oversight Commission  A commission established by the City Council to recommend a long‐term infrastructure plan for their review and approval, monitor the pavement management program, and report achievements and plans, at least annually.  

City  The City of Orinda 

FDR‐Full Depth Reclamation  A process for rebuilding seriously damaged roads, in which the existing pavement is removed, pulverized and blended with cement to create a stable base for new pavement. 

Gas Tax   A portion of the taxes collected on each gallon of gas and returned to the City for our use. 

MTC  ‐ Metropolitan Transportation Commission  Transportation planning, financing, and coordinating agency for the nine‐county San Francisco Bay Area. 

Overlay  Process where new pavement [can be thick or thin] is placed over existing pavement, to repair the road and extend the service life. 

PCI ‐ Pavement Condition Index  Estimation of the overall condition of a portion 

G.7.a

Packet Pg. 141

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 48: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 4 

of a road, determined by inspection.  PCI issued by Staff, the CIOC and the Council to decide the order for work to be done and type of repair to be used.  

Pavement Management Plan The plan developed by city staff and the CIOC and approved by the City Council for the repair of all public roads, including the associated storm drains. 

PMP ‐ Pavement Management Program The program for the repair and maintenance of City roads. 

Roads Repair Policy  The policy recommended by the CIOC and adopted by the City Council and used to determine the selection of roads to be repaired. 

Private Roads  Roads owned by anyone other than the City of Orinda [except Hwy‐#24] where it is the responsibility of the owner(s) to repair and maintain both the road and any associated storm drains 

P‐TAP ‐ Pavement Management Technical Assistance Program  Reports prepared by an outside engineering firm, typically every two years on the odd‐numbered years.  The report includes assessments of pavement conditions for the city's roads, and projects repair and maintenance costs for the City's public roads.   

Public Roads  Any road owned and maintained by the City [except Hwy #24]. 

RTS‐Return to Source Funds from the Countywide Transportation Sales Tax returned to the City to fund transportation projects.  This 1/2‐cent sales tax program, managed by the Contra Costa Transportation Authority, is also known as CCT Measure J.  This sales tax is completely separate from the 1/2‐cent Orinda sales tax (Orinda's Measure L). 

Slurry and Crack Seal A process where existing pavement has any cracks sealed and a coat of slurry [asphalt emulsion] applied to prevent water intrusion and extend the service life. 

StreetSaver The software program developed for the Metropolitan Transportation Commission, to estimate remaining pavement lifetime and the cost to bring up to "very good" condition.  Allows staff to make informed decisions regarding the maintenance and repair of roads.  

 

G.7.a

Packet Pg. 142

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 49: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 5 

Attachment 5  

Timeline:  Roads and Drains Milestones and Projects  

1985  City of Orinda Incorporated   ‐ ‐ City inherits 92.5 miles of public roads 

Aug., 1990  City Council establishes policy regarding conversion of private roads to public roads Resolution Number 56‐90  

1992 ‐ 2012  City spent an average of $2.3 million per year on street maintenance and repairs. Approximately $0.8 million annually was drawn from the City’s General Fund and the Garbage Franchise Fees and used for routine street maintenance (potholes, striping, sweeping, drainage, etc.). Approximately $1.5 million annually was made available for pavement rehabilitation and reconstruction, drawn from dedicated sources of funds ‐‐ Gas Tax, the countywide transportation sales tax Return‐to‐Source funds, and grant revenues from county and federal sources averaged over the 10‐year period. 

October, 2004  City Council created the Citizen's Infrastructure Committee City Council Staff Report, Agenda Item G‐2 10/9/2004 Agenda Topic: Formation of Citizens’ Committee to Develop a Strategic Plan for Reconstruction and Maintenance Infrastructure 

July, 2006  Citizens Infrastructure Committee Report released.  Conclusions included:  ‐ 20–year cost of repairing all publicly owned roads in Orinda approximately $ 72million  ‐ Estimated cost to repair drains  ~$13 Million  ‐ Limiting repairs to the most frequently‐used roads (at least 500 average daily trips) and the most critical drains would still require ~ $60 Million, total. City Council Staff Report , Agenda Item G‐2 7/18/2006 Agenda Title: Roadway, Storm and Water main Improvements, Adopt Ordinance 06‐03 setting Election for Infrastructure Bond Measure City Council Passed and Adopted Ordinance 06‐03 on 7/18/2006 

Nov., 2006  Measure Q, $60 Million general‐obligation bond measure fails (64.4% in favor) City Council Staff Report , Agenda Item I‐2 12/19/2006 Agenda Title : Infrastructure Discussion 

March, 2007  City Council establishes the Citizen's Infrastructure Oversight Commission (CIOC) Resolution Number 04‐07, Passed and adopted by the City Council on 2/7/2007 

June, 2007  Measure E, $60 Million general‐obligation bond measure fails (63.4% in favor) City Council Staff Report , Agenda Item G‐5 6/19/2007 Agenda Title: Canvass of Votes for June 5,2007, Special Municipal Election Resolution 36‐07, Accepting Canvass of votes for the June 5, 2007, Special Municipal Election 

Dec., 2007  City Council updates and clarifies composition and charter of the CIOC Resolution Number 78‐07 In the Matter of : Policies Governing the Citizens’ Infrastructure Oversight Commission Adopted by the City Council of the City of Orinda at a meeting of Council Held on 12/18/2007 

Aug., 2010  City Council establishes Neighborhood Initiated Road Repair Policy City Council Staff Report , Agenda Item I‐2 , 8/7/2010 Agenda Title: Review and Approve the Neighborhood Initiated Road Repair Policy  

G.7.a

Packet Pg. 143

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 50: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 5 

May, 2012  Contract award for the Glorietta Storm Drain Improvements Project.  Total project cost $1.65 Million. City Council Staff Report, Agenda Item I‐1 Agenda Title: Award of the Construction Contract for the Glorietta Storm Drain Improvements Project No.3025 

July, 2012  10‐Year Roads Repair plan established.  ‐ Plan called for 4 funding phases, to raise a total revenue of $58.4 Million (2011 dollars)‐ Pavement Condition Index Goal:  Ave PCI =70      Gas Tax and Return‐To‐Source (Arterial s, etc.)   $10 Million, over 10 years       Phase 1 (2012):   1/2‐cent sales tax (estimated to be $6.7 Million, through 2022)       Phase 2 (2016):   $20M Bond or parcel tax       Phase 3 (2020):   $20M Bond or parcel tax        Phase 4 (2022):   Extension of 1/2‐cent sales tax (Approx. $0.7 Million/yr, starting 2024) City Council Staff Report: Agenda Item I‐2, 7/12/2012 Agenda Title: Proposed 10‐year Roads and Drains Repair and Maintenance Plan Resolution Number 38‐12, Approving a 10 Year Roads and Drains Repair and Maintenance Plan 

July, 2012  Contract awarded for repair of segments of Orinda Way, Rheem Blvd, Camino Sobrante, Overhill Road, and Valley View Drive.  Project total cost $ 1.64 Million. City Council Staff Report, Agenda Item G‐3, 7/17/2012 Agenda Title: Award of Construction Contract for the City of Orinda 2012‐2013 Pavement Rehabilitation Project Number 3098 to Bay Cities Paving & Grading Inc., of Concord 

July, 2012  Full‐depth reclamation (FDR) was introduced, with initial use on Camino Sobrante, Overhill Road, and Valley View Drive, to reduce cost while retaining high quality. 

Oct., 2012    

Manzanita Rd Bridge replacement project awarded.  Total Cost  $ 3, 275,800 Federal Fund : $2,849,823    Transportation Impact fees $274,393  Gas Tax: $63,801 EBMUD Reimbursement: $105,626 City Council Staff Report,  Agenda Item G‐3 10/16/2012 Agenda Title: Award of the Construction Contract for the Manzanita Drive Bridge Replacement Project Number 0043 

Nov., 2012  1/2‐cent sales tax approved by voters   ‐ Funds first available in April, 2013.    Sales tax authorization ends in 2023    ‐ Funds created ~ $1 Million per year Resolution Number 65‐12 , Adopted December 4, 2012 

Dec  2012   Condition of arterials and collectors continues to improve.  

  April, 2009  # of Arterial/Collector segments with ave PCI < 50  43 

  Dec., 2011  # of Arterial/Collector segments with ave PCI < 50  25 

  Dec., 2012  # of Arterial/Collector segments with ave PCI < 50  19 

G.7.a

Packet Pg. 144

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 51: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 5 

Dec., 2012  Tarabrook sinkhole developed December, 2012  ‐ ‐ Repair completed last 2013 at a cost of approximately $1.44 Million Resolution number 71‐12, Adopted by the City Council on 12/7/2012 Resolution number 74‐12 Adopted by the City Council on 12/18/2012 Resolution number 08‐13 Adopted by the City Council on 2/5/2013 Resolution number 12‐13 Adopted by the City Council on 2/19/2013 Resolution number 17‐13 Adopted by the City Council on 3/5/2013 Resolution number 26‐13 Adopted by the City Council on 4/9/2013 City Council Staff Report Agenda Item G‐5, May 20, 2014,  Project Acceptance of the Tarabrook Drive Storm Water Improvements, City Council Accepted the Project on 5/20/2014 

Jan., 2014  CIOC recommends, and City Council approves, a policy in which residential roads be repaired starting with the "Busiest and Worst First" City Council Staff Report, Agenda Item I‐3  1/21/2014 Agenda Title: Approve Policy and Criteria for Selecting Streets for Repair Using Measure L 0.5% Sales Tax Funds 

April, 2014  10‐Year Roads Repair plan updated and revised ‐ Plan called for 4 funding phases to raise a total revenue of $66 Million (2014 dollars)      Gas Tax and Return‐To‐Source (Arterial s, etc.)   $9.5 Million, over 10 years      Phase 1 (2012):    1/2‐cent sales tax   Approx. $10 Million thru 2022      Phase 2 (2014):   $20M Bond      Phase 3 (2018):   $25M Bond      Phase 4 (2022):   Extension of 1/2‐cent sales tax plus undefined additional funds                                     for maintenance    Approx. $1.3 Million in 2023 City Council Staff Report, Agenda Item I‐1 ,  4/22/2014 Agenda Title: Adopt Resolution Approving 2014‐10 Year Road and Drainage Repairs Plan Resolution Number 13‐14 Approving 2014‐10 Year Road and Drainage Repairs 

Nov., 2014  Bond Measure J, $20 Million General Obligation Bond approved 

Nov., 2014  2015 Paving Programs Approved  ‐  Length of roads repaired:      Residential   1.1 Miles  Arterials, etc.   2.9 Miles           Approved Plan        Final Cost   ‐ Arterials and Collectors    $1.21 Million     $ 0.69 Million      ‐ Measure L  1/2‐cent sales Tax   $0.98 Million     $ 0.91 Million      ‐ Measure J (2014) Bond    $5.05 Million     $ 5.02Million             TOTAL  $7.24 Million     $ 6.62 Million   City Council Staff Report I‐3 11/5/2104 Agenda Tile: Approval of list of Streets and Authorization to Proceed with Project Design for the FY 2015 Measure J Pavement Project 

Oct., 2015  2016 Paving Programs Approved ‐  Length of roads repaired:      Residential   8.1 Miles  Arterials, etc.   0.7 Miles           Approved Plan        Final Cost   ‐ Arterials and Collectors     $ 1.9 Million     $ 0.89 Million      ‐ Measure L  1/2‐cent sales Tax    $ 0.9 Million     $ 1.04 Million      ‐ Measure J (2014) Bond     $ 6.2 Million     $ 5.26 Million             TOTAL   $ 9.0 Million     $ 7.19 Million  City Council Staff Report, Agenda Item I‐2 10/6/2015 Agenda Title: Approval of List of Streets and Authorization with Project Design for FY 2016 Measure J and L Pavement Project  

G.7.a

Packet Pg. 145

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 52: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 5 

Nov., 2015  

Award of an Engineering Design Services Contract for the 2016 and 2017 Annual and Measure J & L Pavement Rehabilitation Projects City Council Staff Report Agenda Item I‐4 11/17/2017 Agenda Title: Award of an Engineering Design Services Contract for the 2016 and 2017 Annual and Measure J & L Pavement Rehabilitation Projects 

March, 2016  Storm Drain Plan completed, supported by Schaaf and Wheeler, Civil Engineers.  Report describes status of Orinda's storm drain system and details key storm drain repair requirements. City Council Staff Report, Agenda Item: G‐2   3/24/2016 Agenda Title: Presentation of Final Draft Storm Drain Plan 

March, 2016  

Roads and Drains Plan Update ‐ Plan now calls for 5 funding phases, to raise a total revenue of $88 Million (2014 dollars) ‐ In Nov., 2015 the City Council agreed to change goals to "Average PCI = 70, and no road with PCI < 50".  The staff report projected a cost increase of approx. $13 Million to support this change.  Further funding requirements were identified for repairs of key storm drains and conduits as well as remaining repairs to arterials, collectors, and school routes.  These funding requirements were combined into a new Phase 4.        Gas Tax and Return‐To‐Source (Arterial s, etc.)   $10 Million, over 10 years      Phase 1 (2012) 1/2‐cent sales tax  ‐ ‐ Funded      Phase 2 (2014)  $20M Bond  ‐ ‐ Funded      Phase 3 (2016) $25M Bond  ‐ ‐  Bond measure passed in Nov., 2016      Phase 4 (2018) $22 Million new revenue      Phase 5 (2022) Extension of 1/2‐cent sales tax plus undefined additional funds        for maintenance    Approx. $1.3 Million in 2023 City Council Staff Report, Agenda Item I‐1 3/15/2016 Agenda Title:  Adopt Resolution 21‐16 Approving Road and Drainage Repairs Plan ( As Updated in 2016), Dated March 15,2016 

May, 2016  Contract awarded for the North Lane Storm Drain Project in the amount of $2,298,827 ‐ Approximately 1,300 feet of 60inch reinforced concrete storm drain pipe installed ‐ The new pipe works in addition to the pre‐existing metal pipe/open‐channel system ‐ 75% of construction cost funded by the Federal Emergency Management Agency ‐ The remaining 25 % was split between the City of Orinda and EBMUD. City Council Staff Report, Item G‐3 5/17/2016 Agenda Title: Award of Construction Contract for the North Lane Storm Water Mitigation Project N. 4070 to Bay Cities Paving & Grading, Inc. of Concord 

Nov., 2016  CIOC status report:  Reduced estimate of total repair costs, from $47 Million prior estimate, to $45 Million new estimate 1) Low oil prices and savings from the economy of scale of our large project; 2) Accelerating the rehabilitation work to be done faster than originally scheduled; 3) Net savings on the bids from 2015 and 2016 Paving project. 

Nov., 2016  2017 Paving Programs approved:    Length of roads to be repaired:      Residential   10.5 Miles  Arterials, etc.   0.9 Miles           Approved Plan         Final Cost   ‐ Arterials and Collectors:        $  0.82  Million ‐ Measure L  1/2‐cent sales Tax       $  0.99 Million ‐ Measure J (2014) Bond     $ 10.49 Million         TOTAL   $ 12.30 Million          (Project in not complete, so final cost is not available) 

G.7.a

Packet Pg. 146

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 53: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 5 

Nov., 2016  2018 Paving Program ‐ Preliminary plan approved   ‐ Length of roads to be repaired:      Residential   13.7 Miles  Arterials, etc.   1.3 Miles           Preliminary Plan            ‐ Arterials and Collectors:        $ 0.60 Million  ‐ Measure L  1/2‐cent sales Tax      $  1.05 Million ‐ Measure J (2014) Bond      $ 0.95  Million ‐ Measure L (2016) Bond     $ 12.17 Million         TOTAL   $ 14.76 Million   City Council Staff Report, Agenda Item I‐1 11/1/2016 Agenda Title: Approval of list of Streets for Pavement Rehabilitation in 2018 and 2019 for the Annual, Measure J and Measure L Pavement Rehabilitation Projects and Status of the City’s Road and Drainage Repairs Plan 

Nov., 2016  2019 Paving Program ‐ Preliminary plan approved:   ‐  Length of roads to be repaired:      Residential   25.4 Miles  Arterials, etc.   1.5 Miles           Preliminary Plan ‐ Arterials and Collectors:       $  1.05 Million   ‐ Measure L  1/2‐cent sales Tax      $  1.00 Million ‐ Measure L (2016) Bond     $ 13.18 Million         TOTAL   $ 15.23 Million   City Council Staff Report, Agenda Item I‐1 11/1/2016 Agenda Title: Approval of list of Streets for Pavement Rehabilitation in 2018 and 2019 for the Annual, Measure J and Measure L Pavement Rehabilitation Projects and Status of the City’s Road and Drainage Repairs Plan 

March, 2017  Bond Measure L, $25 Million General Obligation Bond approved  Resolution No. 27‐17  3/21/2017 In the Matter of: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ORINDA AUTHORIZING THE ISSUANCE AND SALE OF GENERAL OBLIGATION BONDS IN AGGREGATE PRINCIPAL AMOUNTS NOT TO EXCEED $10,000,000 (ELECTION OF 2014, SERIES B) AND $25,000,000 (ELECTION OF 2016, SERIES A) BY NEGOTIATED SALE; APPROVING THE FORM OF AND EXECUTION AND DELIVERY OF ONE OR MORE PAYING AGENT AGREEMENTS, BOND PURCHASE CONTRACTS, CONTINUING DISCLOSURE AGREEMENTS, AND TAX-EXEMPT GOVERNMENTAL BONDS TAX COMPLIANCE AND CONTINUING DISCLOSURE COMPLIANCE GUIDELINES; APPROVING THE FORM OF AN OFFICIAL STATEMENT DESCRIBING THE BONDS AND DISTRIBUTION THEREOF; AND AUTHORIZING OFFICERS OF THE CITY TO TAKE NECESSARY ACTIONS AND TO PREPARE NECESSARY DOCUMENTS IN CONNECTION THEREWITH 

May, 2017  Award of Construction Contract for the 2017 Annual and Measure J & L Pavement Rehabilitation Project No. 4114/4115 to Bay Cities Paving & Grading Inc. City Council Staff Report, Agenda Item G‐5  5/16/2017 

G.7.a

Packet Pg. 147

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 54: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 6 

Attachment 6  

Grants Applied for and Awarded, to Support  Orinda Roads and Drains Projects 

 

Name  Agency  Date of Grant Amount of Grant(s) 

Crossroads Wayfinding & BART  CCTA  10/9/2014  $151,000 

    

Manzanita Bridge Rehab  DOT  5/4/2012  $2,514,097 

    

Camino Pablo/Santa Maria  CCTA  2/5/2011  $75,000 

  CCTA  9/17/2014  $371,463 

  Sub‐Total  $446,463 

    

Camino Pablo Paving  CCTA 3/19/2014 $100,000

  CCTA  11/17/2014  $1,943,000 

  Sub‐Total  $2,043,000 

    

North Lane Storm Water Mitigation  Cal EMA  12/30/2010  $145,125 

  EBMUD  1/1/2011  $45,687 

  Cal EMA  8/29/2011  $32,250 

  Cal EMA  12/17/2013  $1,088,105 

  Cal EMA  5/18/2015  $21,466 

  Cal EMA  9/9/2015  $883,112 

  EBMUD  11/17/2015  $365,000 

  Sub‐Total  $2,580.746 

    

Moraga Way Pedestrian School Pathway  DOT  6/1/2012  $166,000 

    

Ivy Dr/Coral Dr  MTC  7/3/2013  $70,000 

  DOT  5/18/2015  $100,000 

  Sub‐Total  $170,000 

    

Ivy Dr Pavement  DOT  5/18/2015  $552,000 

    

BART Access Ramp  BART  1/15/2015  $250,000 

  MTC  8/24/2016  $100,000 

  Sub‐Total  $350,000 

    

Citywide Bike Route Signage  MTC  7/30/2015  $40,000 

    

Santa Maria Park & Ride  CCTA  8/2/2016  $175,000 

    

Sidewalk Trip Hazard Mitigation  MPA  6/9/2016  $11,000 

    

  Total Grants  $9,199,305 

G.7.a

Packet Pg. 148

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 55: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 7 

Attachment 7 

Storm Drains Likely to Need Near‐Term Repairs  The criteria used to select storm drains for repairs were (1) storm drains that do not have adequate capacity for the 10 year storm runoff, or (2) storm drains in poor condition or (3) the storm drain is under an arterial or a collector which provides the only access to a large neighborhood    Budgetary cost estimate:  $15 Million.  Engineering cost estimates were prepared for each repair project.  Consistent with good engineering practice, a 20% contingency has been added to the combined project.  Any funds remaining after the completion of the listed projects would allow other storm drains to be identified for repair/replacement.  

Project Name  Project Location  

Reason for Improvement 

Imp. Pipe Diameter(in) 

Camino Pablo  near Camino Encinas Existing pipe is not in good condition 

 (72") 

Camino Pablo   near Bear Creek Road Existing Pipe is not in good condition 

 (72") 

Camino Pablo  near Orinda Way 

Existing Pipes are not in good condition 

 

(multiple 24”) 

Camino Pablo   near Ardilla Lane Existing Pipes are 

not in good condition 

 (multiple 18") 

Camino Pablo   near Los Amigos Ct. Lacks capacity to route the 10‐year design runoff  

 (24” to 36”) 

Charles Hill Circle 

 600' east of Charles Hill Road 

Existing 36” pipe is not in good condition 

(36") 

El Camino Moraga 

 near Dos Encinas/Del Rey Elementary 

Existing pipes are not in good 

condition and the road provides the only access to a neighborhood 

 

(two 96”) 

El Toyonal  near El Rincon 

Existing pipes are not in good 

condition and  the road provides the only access to a neighborhood 

 

(24” and 60”)   

G.7.a

Packet Pg. 149

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 56: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 7 

Glorietta Blvd.  near Rheem Blvd Existing 60” is not in good condition 

 (60”) 

Glorietta Blvd.  near Meadowview Road Lack Capacity to route the 10‐year design runoff 

(18” upsize 36”) 

Ivy Drive  near Descanso Drive The pipe systems are not in good 

condition 

(two 24” and 48”) 

Ivy Drive between Corte Sombrita and Ramona Drive 

72 –inch CMP is not in good condition 

(72") 

Ivy Drive  near Miramonte HS 144‐inch CMP is not in good condition 

(144”) 

Lombardy Lane  400’ east of Van Ripper Lane 

Existing system under Lombardy 

Lane Lacks capacity to route the 10‐year design runoff and this 

road provides the only access to a neighborhood. 

(36” to 54”) 

Lombardy Lane  near Van Tassel Lane Existing 72” CMP is not in good condition 

(72") 

Lost Valley Drive 

near Edgewood Ct 

The existing 48‐inch CMP is not in good condition and the road 

provides the only access to a 

neighborhood 

 (48") 

Miner Road  near Lombardy Lane 

32‐inch CMP is not in good condition 

  

(32”) 

Miner Road near 1,000’ south of Camino Don Miguel 

Existing  CMP pipe is not in good condition 

 

(72”)  

Miner Road near Camino Lenada to Lombardy Lane 

 Existing pipes are not in good condition 

(multiple 18") 

Miner Road  near Oak Arbor Road Lack capacity to route the 10‐year design run‐off for 

18” to 36”) 

Moraga Way  near Orchard Road (north) 144‐inch CMP is not in good condition 

(144”) 

G.7.a

Packet Pg. 150

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 57: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 7 

 

Moraga Way  near Overhill Road The existing pipes are not in good 

condition 

(multiple 24" to 36") 

Moraga Way  near Orinda Oaks Park 

Reinforced Concrete box is not in good condition  

(RC BOX) 

Orchard Road  near Great Oaks Circle 

60‐inch CMP is not in good condition 

  

(60") 

Orinda Way  near Community Park 

Lack capacity to route the 10‐year design run‐off 

 

(24” to 48”) 

Orinda Way  near Camino Pablo Lack capacity to route the 10‐year design runoff 

(36" to 42") 

Rheem Blvd  near Laura Way Existing pipe is not in good condition 

 (36") 

Tahos Road  near St. Stephens off ramp Lack Capacity to route the 10‐year design runoff 

(24” to 42”) 

G.7.a

Packet Pg. 151

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 58: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 8 

Attachment 8 

Arterials, Collectors, and School Routes Still in Need of Repairs  Listed below are the Arterials, Collectors, and School Routes that are expected to be in need of repairs after the completion of the 2018 and 2019 paving projects.  Budgetary cost estimate:  $7 Million.  Engineering cost estimates were prepared for each repair project.  Consistent with good engineering practice, a 20% contingency has been added to the combined project.  Any funds remaining after the completion of the listed projects would allow storm drains in addition to those listed in Attachment 7 to be identified for repair/replacement 

Street Name  Section Requiring Repair 

Bear Creek Road   

Brookwood Road   West of Camino Pablo 

Bryant Way   

Camino Pablo   Bear Creek Road to Miner Road 

Camino Sobrante   Camino Pablo to Orinda Way 

E. Altarinda Drive   Orindawoods to El Nido Ranch 

Glorietta Blvd Hall Drive   Moraga Way to Donald Drive 

Honeyhill Road   

Las Piedras    

Lomas Contadas   

Lombardy Lane   North of Tarry Lane 

Miner Road  North of Lombardy Lane 

Orindawoods Drive    

Rheem Blvd   

Santa Maria Way    

Tara Road   Southwood Drive to Nonie 

 NOTE:  Orinda Way is scheduled to be repaved in 2019 using $620,000 of federal funds from the One Bay Area Grant (OBAG) program administered by MTC.   

G.7.a

Packet Pg. 152

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 59: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 8 

Table below lists the complete history of maintenance and rehabilitation for Arterial and Collector streets for the past 20 years.  

St Name Beg Loc End Loc Treatment Date Description

TARA RD. (2744F) NONIE RD OVERHILL RD 11/1/2017 Crack Sealing

EL NIDO RANCH RD (2854) ST. STEVENS DR. CITY LIMITS 10/11/2017 Overlay with AC

IVY DRIVE RISA COURT DANZA COURT 10/31/2016 Reconstruct as AC

IVY DRIVE DANZA COURT PUEBLO COURT 10/31/2016 Reconstruct as AC

IVY DRIVE PUEBLO COURT MORAGA WAY 10/31/2016 Reconstruct as AC

CAMINO PABLO MORAGA WAY SANTA MARIA WAY 9/14/2016 Crack Sealing

CAMINO PABLO SANTA MARIA WAY CAMINO SOBRANTE 9/14/2016 Crack Sealing

CAMINO PABLO CAMINO SOBRANTE ORINDA WAY 9/14/2016 Crack Sealing

CAMINO PABLO ORINDA WAY MINER RD 9/14/2016 Crack Sealing

CAMINO PABLO MORAGA WAY SANTA MARIA WAY 12/31/2015 Overlay with AC

CAMINO PABLO SANTA MARIA WAY CAMINO SOBRANTE 12/31/2015 Overlay with AC

CAMINO PABLO MINER RD ARDILLA ROAD 12/31/2015 Overlay with AC

CAMINO PABLO CAMINO SOBRANTE ORINDA WAY 12/31/2015 Overlay with AC

CAMINO PABLO ORINDA WAY MINER RD 12/31/2015 Overlay with AC

OVERHILL RD. (2744G) MORAGA WAY WESTWOOD CT 12/31/2015 Reconstruct as AC

OVERHILL RD. (2744G) WESTWOOD CT HIGHLAND COURT 12/31/2015 Reconstruct as AC

OVERHILL RD. (2744G) HIGHLAND COURT BROADVIEW TERR 12/31/2015 Reconstruct as AC

OVERHILL RD. (2744G) BROADVIEW TERR TARA RD 12/31/2015 Reconstruct as AC

ST. STEPHENS DR. EL NIDO RANCH RD LA ESPIRAL 12/31/2015 Overlay with AC

BROOKWOOD RD.(2744A) CAMINO PABLO MORAGA WAY 7/1/2015 Overlay with AC

CAMINO PABLO MORAGA WAY SANTA MARIA WAY 7/1/2015 Overlay with AC

CAMINO PABLO SANTA MARIA WAY CAMINO SOBRANTE 7/1/2015 Overlay with AC

CAMINO PABLO CAMINO SOBRANTE ORINDA WAY 7/1/2015 Overlay with AC

CAMINO PABLO ORINDA WAY MINER RD 7/1/2015 Overlay with AC

TARA RD. (2744F) NONIE RD OVERHILL RD 10/1/2014 Overlay with AC

EL TOYONAL (2254) LOMA VISTA (WEST) PAVEMENT CHANGE 8/31/2014 Reconstruct as AC

EL TOYONAL (2254) PAVEMENT CHANGE CAMINO DEL CIELO 8/31/2014 Reconstruct as AC

EL TOYONAL (2254) CAMINO DEL CIELO VISTA DEL ORINDA 8/31/2014 Reconstruct as AC

ORINDAWOODS DR.(2545AM) ALTARINDA RD KITE HILL RD 8/31/2014 Reconstruct as AC

ORINDAWOODS DR.(2545AM) KITE HILL RD GREYSTONE TERR. 8/31/2014 Reconstruct as AC

RHEEM BLVD MORAGA VIA GLORIETA BLVD 8/31/2014 Reconstruct as AC

CAMINO SOBRANTE (2544C) ORINDA WAY EL RIBERO (SOUTH) 7/15/2012 Reconstruct as AC

ORINDA WAY SANTA MARIA WAY 682FT N/O SANTA MARIA WAY

7/15/2012 Surface Seal

ORINDA WAY 682FT N/O SANTA MARIA WAY

1700FT N/O SANTA MARIA WAY

7/15/2012 Surface Seal

OVERHILL RD. (2744G) TARA RD 241 OVERHILL RD 7/15/2012 Reconstruct as AC

OVERHILL RD. (2744G) 241 OVERHILL RD GLORIETTA BLVD 7/15/2012 Reconstruct as AC

RHEEM BLVD ZANDER DRIVE 1066' W/ZANDER DRIVE

7/15/2012 Surface Seal

RHEEM BLVD 1066' W/ZANDER DRIVE

CAROLYN COURT 7/15/2012 Surface Seal

CAMINO SOBRANTE (2544C) CAMINO PABLO ORINDA WAY 10/31/2011 Overlay with AC

G.7.a

Packet Pg. 153

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 60: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 8 

E. ALTARINDA DR(2545AC) ORINDAWOODS DR. EL NIDO RANCH RD. 10/31/2011 Overlay with AC

LOMBARDY LN. (2554) VAN RIPPER (S) VAN RIPPER (N) 10/31/2011 Overlay with AC

TARA RD. (2744F) SOUTHWOOD DR TARABROOK DR 10/31/2011 Overlay with AC

TARA RD. (2744F) TARABROOK DR NONIE RD 10/31/2011 Overlay with AC

BRYANT WAY MORAGA WAY DAVIS ROAD 12/31/2010 Overlay with AC

LOMA VISTA DR. (2345C) EL TOYONAL (WEST) EL DORADO LN 12/31/2010 Overlay with AC

LOMAS CANTADAS TRES MESAS LAS PIEDRAS 12/31/2010 Surface Seal

MINER RD. (2444C) SYCAMORE RD PAVT CHANGE 12/31/2010 Overlay with AC

MORAGA WAY CAMINO PABLO OVERHILL RD 12/31/2010 Overlay with AC

MORAGA WAY OVERHILL RD CAMINO ENCINAS (N) 12/31/2010 Overlay with AC

BEAR CREEK RD. CAMINO PABLO CITY LIMIT 9/17/2010 Crack Sealing

BROOKWOOD RD.(2744A) SPRING RD. CAMINO PABLO 9/17/2010 Crack Sealing

GLORIETTA BLVD (2731 B) MORAGA WAY SHADOW CREEK LN 9/17/2010 Crack Sealing

GLORIETTA BLVD (2731 B) SHADOW CREEK LN RHEEM BLVD 9/17/2010 Crack Sealing

GLORIETTA BLVD (2731 B) RHEEM BLVD. MARTHA RD. 9/17/2010 Crack Sealing

GLORIETTA BLVD (2731 B) MARTHA RD. OVERHILL RD. 9/17/2010 Crack Sealing

GLORIETTA BLVD (2731 B) OVERHILL RD CITY LIMITS 9/17/2010 Crack Sealing

ORINDA WAY SANTA MARIA WAY 682FT N/O SANTA MARIA WAY

9/17/2010 Crack Sealing

ORINDA WAY 682FT N/O SANTA MARIA WAY

1700FT N/O SANTA MARIA WAY

9/17/2010 Crack Sealing

ORINDA WAY 1700FT N/O SANTA MARIA WAY

CAMINO PABLO 9/17/2010 Crack Sealing

SANTA MARIA WY. CAMINO PABLO ORINDA WAY 9/17/2010 Crack Sealing

HONEY HILL RD. CHARLES HILL RD. MINER RD. 2/2/2010 Overlay with AC

CAMINO PABLO MINER RD ARDILLA ROAD 6/1/2009 Surface Seal

CAMINO PABLO ORINDA WAY MINER RD 6/1/2009 Surface Seal

LOMAS CANTADAS TRES MESAS LAS PIEDRAS 6/1/2009 Surface Seal

CAMINO PABLO MINER RD ARDILLA ROAD 5/31/2009 Crack Sealing

LOMAS CANTADAS TRES MESAS LAS PIEDRAS 5/29/2009 Crack Sealing

BROOKWOOD RD.(2744A) SPRING RD. CAMINO PABLO 5/1/2009 Overlay with AC

EL TOYONAL (2254) LOMA VISTA (WEST) PAVEMENT CHANGE 5/1/2009 Localized Treatment

EL TOYONAL (2254) PAVEMENT CHANGE CAMINO DEL CIELO 5/1/2009 Localized Treatment

GLORIETTA BLVD (2731 B) RHEEM BLVD. MARTHA RD. 5/1/2009 Overlay with AC

GLORIETTA BLVD (2731 B) MARTHA RD. OVERHILL RD. 5/1/2009 Overlay with AC

HALL DRIVE MORAGA WAY FLEETWOOD CT 5/1/2009 Overlay with AC

LAS PIEDRAS (2244B) VISTA DEL ORINDA LOMAS CANTADAS 5/1/2009 Overlay with AC

LOMBARDY LN. (2554) VAN RIPPER (N) DALEWOOD DR 5/1/2009 Overlay with AC

RHEEM BLVD ZANDER DRIVE 1066' W/ZANDER DRIVE

5/1/2009 Crack Sealing

EL TOYONAL (2254) LOMA VISTA (WEST) PAVEMENT CHANGE 4/30/2009 Crack Sealing

EL TOYONAL (2254) PAVEMENT CHANGE CAMINO DEL CIELO 4/30/2009 Crack Sealing

MORAGA WAY GLORIETTA BLVD ORCHARD RD 7/1/2008 Overlay with AC

MORAGA WAY CAMINO MORAGA CORAL DR 7/1/2008 Overlay with AC

MORAGA WAY ORCHARD RD VALLEY VIEW DR 7/1/2008 Overlay with AC

MORAGA WAY CORAL DR IVY DR (EAST) 7/1/2008 Overlay with AC

MORAGA WAY CAMINO ENCINAS LLOYD LN 7/1/2008 Overlay with AC

MORAGA WAY VALLEY VIEW DR WOODLAND RD 7/1/2008 Overlay with AC

G.7.a

Packet Pg. 154

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 61: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 8 

MORAGA WAY LLOYD LN BROOKSIDE RD 7/1/2008 Overlay with AC

MORAGA WAY WOODLAND RD IVY DR (WEST) 7/1/2008 Overlay with AC

MORAGA WAY BROOKSIDE RD GLORIETTA BLVD 7/1/2008 Overlay with AC

MORAGA WAY IVY DR (WEST) SOUTHWAITE CT 7/1/2008 Overlay with AC

MORAGA WAY SOUTHWAITE CT CAMINO MORAGA 7/1/2008 Overlay with AC

HIDDEN VALLEY ST STEPHENS DRIVE SR 24 ON RAMP 4/1/2008 Overlay with AC

HAPPY VALLEY RD.(2851) CITY LIMIT (SOUTH) CITY LIMIT (NORTH) 3/1/2008 Overlay with AC

LOMBARDY LN. (2554) TARRY LANE VAN RIPPER (S) 3/1/2008 Overlay with AC

GLORIETTA BLVD (2731 B) MORAGA WAY SHADOW CREEK LN 12/1/2007 Overlay with AC

GLORIETTA BLVD (2731 B) SHADOW CREEK LN RHEEM BLVD 12/1/2007 Overlay with AC

GLORIETTA BLVD (2731 B) OVERHILL RD CITY LIMITS 12/1/2007 Overlay with AC

HAPPY VALLEY RD.(2851) CITY LIMIT (SOUTH) CITY LIMIT (NORTH) 12/1/2007 Overlay with AC

RHEEM BLVD ZANDER DRIVE 1066' W/ZANDER DRIVE

12/1/2007 Crack Sealing

RHEEM BLVD 1066' W/ZANDER DRIVE

CAROLYN COURT 12/1/2007 Crack Sealing

CAMINO PABLO MONTE VISTA RD. BEAR CREEK RD. 6/1/2007 Overlay with AC

CAMINO PABLO SANTA MARIA WAY CAMINO SOBRANTE 6/1/2007 Surface Seal

CAMINO PABLO NORTH LN SOL BRAE WY 6/1/2007 Surface Seal

CAMINO PABLO SOL BRAE WY MONTE VISTA RD 6/1/2007 Surface Seal

EL NIDO RANCH RD (2854) ST. STEVENS DR. CITY LIMITS 6/1/2007 Surface Seal

HALL DRIVE FLEETWOOD CT DONALD DR 6/1/2007 Surface Seal

LOMA VISTA DR. (2345C) EL DORADO LN EL TOYONAL (EAST) 6/1/2007 Surface Seal

MINER RD. (2444C) LOMBARDY LN TIGERTAIL CT 6/1/2007 Surface Seal

ORINDA WAY SANTA MARIA WAY 682FT N/O SANTA MARIA WAY

6/1/2007 Surface Seal

SANTA MARIA WY. CAMINO PABLO ORINDA WAY 6/1/2007 Surface Seal

ALTARINDA RD. SANTA MARIA WY ORINDA WOODS DR 12/31/2006 Surface Seal

E. ALTARINDA DR(2545AC) ORINDAWOODS DR. EL NIDO RANCH RD. 12/31/2006 Surface Seal

EL TOYONAL (2254) PAVEMENT CHANGE CAMINO DEL CIELO 12/31/2006 Overlay with AC

ORINDAWOODS DR.(2545AM) ALTARINDA RD KITE HILL RD 12/31/2006 Surface Seal

ORINDAWOODS DR.(2545AM) KITE HILL RD GREYSTONE TERR. 12/31/2006 Surface Seal

ORINDAWOODS DR.(2545AM) GREYSTONE TERR. E. ALTARINDA 12/31/2006 Surface Seal

LOMBARDY LN. (2554) MINER ROAD TARRY LANE 8/30/2004 Localized Treatment

LOMBARDY LN. (2554) TARRY LANE VAN RIPPER (S) 8/30/2004 Localized Treatment

LOMBARDY LN. (2554) VAN RIPPER (S) VAN RIPPER (N) 8/30/2004 Localized Treatment

LOMBARDY LN. (2554) VAN RIPPER (N) DALEWOOD DR 8/30/2004 Localized Treatment

RHEEM BLVD ZANDER DRIVE 1066' W/ZANDER DRIVE

8/30/2002 Overlay with AC

RHEEM BLVD 1066' W/ZANDER DRIVE

CAROLYN COURT 8/30/2002 Overlay with AC

RHEEM BLVD CITY LIMITS ZANDER DRIVE 8/20/2002 Overlay with AC

SOUTHWOOD DR.(2745AZ) MORAGA WAY TARA RD 7/30/2002 Overlay with AC

ST. STEPHENS DR. HIDDEN VALLEY RD EL NIDO RANCH RD 8/30/2001 Localized Treatment

ST. STEPHENS DR. EL NIDO RANCH RD LA ESPIRAL 8/30/2001 Localized Treatment

EL TOYONAL (2254) CAMINO PABLO LOMA VISTA (EAST) 6/30/2001 Overlay with AC

EL TOYONAL (2254) LOMA VISTA (WEST) PAVEMENT CHANGE 6/30/2001 Overlay with AC

EL TOYONAL (2254) CAMINO DEL CIELO VISTA DEL ORINDA 6/30/2001 Overlay with AC

LOMBARDY LN. (2554) MINER ROAD TARRY LANE 11/25/1997 Surface Seal

G.7.a

Packet Pg. 155

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 62: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 8 

LOMBARDY LN. (2554) TARRY LANE VAN RIPPER (S) 11/25/1997 Surface Seal

LOMBARDY LN. (2554) VAN RIPPER (S) VAN RIPPER (N) 11/25/1997 Surface Seal

LOMBARDY LN. (2554) VAN RIPPER (N) DALEWOOD DR 11/25/1997 Surface Seal

SOUTHWOOD DR.(2745AZ) MORAGA WAY TARA RD 11/25/1997 Surface Seal

  

G.7.a

Packet Pg. 156

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 63: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 9 

Attachment 9  

Full Depth Reclamation   

Full Depth Reclamation (FDR) construction consists of four (4) phases:  

1) Pulverize and mix pavement in‐place 

2) Removal of the top few inches for grading; 

3) Re‐mix material with cement 

4) Paving new asphalt. 

1) Pulverizing and Mixing In‐Place: The existing roadway will be pulverized and 

mixed in place to a depth of 12 to 16 inches. Using large specialty FDR machines, 

the older and failed pavement surface will be mixed with underlying fill and native 

soil to develop a new base material for the reconstructed pavement. This “green” 

technology reduces the need to off‐haul dozens of truckloads of roadway material 

by reusing the existing pavement materials and underlying soils. This technology 

also substantially reduces the need for truckloads of new material. This recycled 

material is safe for cars to drive on shortly after the FDR machine has passed 

through the roadway section. Please drive slowly as there may be loose gravel‐

like material on the recycled surface.  

2) Material Removal: The next phase will remove some of the mixed recycled 

material to make room for the new asphalt. The amount of pavement to be 

removed will be 3 to 5 inches deep. The surface will be rough, please continue to 

drive slowly as there may be loose gravel‐ like material on the surface. Temporary 

rock ramps will be installed at each driveway to maintain access for all residents. 

3) Re‐Mixing with Cement: The remaining recycled material will then be‐re‐mixed 

with the addition of cement and water in order to stabilize and strengthen the 

material, making it a sturdy base for the new pavement section. The surface will 

be exposed generally up to one week before the first layer of new asphalt is 

placed. Also, the contractor will sweep any excess material and maintain 

temporary access to driveways. Although the surface will be fairly smooth at this 

G.7.a

Packet Pg. 157

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)

Page 64: CITY OF ORINDA - media.virbcdn.commedia.virbcdn.com/files/ea/11436f073f176eda-Roads... · CITY OF ORINDA Road and Drainage Repairs Plan (As Updated in 2017) February 6, 2018 (ORIGINALLY

ATTACHMENT 9 

point in the construction, please continue to drive slowly as there may be loose 

gravel‐like material on the recycled surface. 

4) Paving: The asphalt overlay is a liquid asphalt binder premixed with aggregate, 

which is placed and compacted on the street surface. To avoid tracking asphalt 

material onto your driveways and property, please pay attention to construction 

signs and wait until the street has been cleared for access. 

 

G.7.a

Packet Pg. 158

Att

ach

men

t: R

oad

an

d D

rain

age

Rep

airs

Pla

n U

pd

ated

2-6

-18

(14

12 :

CIO

C R

oad

an

d D

rain

age

Pla

n a

pp

rova

l)