CITY OF INDIANAPOLIS DEPARTMENT OF PUBLIC WORKS · A wealth of resources to master a common goal....
Transcript of CITY OF INDIANAPOLIS DEPARTMENT OF PUBLIC WORKS · A wealth of resources to master a common goal....
A wealth of resources to master a common goal.
CITY OF INDIANAPOLIS DEPARTMENT OF PUBLIC WORKS
Item 10—Supervisory Control and Data Acquisi)on (SCADA)
Monitoring System reloca)on
March 2, 2017
A wealth of resources to master a common goal.
7256 Company Drive, Indianapolis, IN 46237
Ph: 317-888-1177 - Toll Free: 800-289-1177
Fax: 317-887-8641 - www.commonwealthengineers.com
City of Indianapolis Department of Public Works Item 10 - Supervisory Control Data Acquisi)on (SCADA) Monitoring System Reloca)on
Toby Church, PE, CEA
Project Manager
Greg Bryan
Infrastructure (MBE) 15%
Lori Rushin, PE
Eilts (WBE) 8%
James R Gill
Precept Surveying (VBE) 3%
Rachel Wilson, PE
Dept. of Public Works
Senior Project Manager
Chris Means
Electrical Designer
A wealth of resources to master a common goal.
Toby Church, P.E., CEA
Senior Electrical Engineer
EXPERIENCE & EXPERTISE
Toby has been involved in the design and implementa1on of electrical and control systems for
over 25 years. With his educa1ons and work experience, he possesses exper1se in the
electrical and control field and is able to evaluate and design cost-effec1ve electrical and
control systems. He prides himself on being able to discuss with the owner their needs and
design a cost-effec1ve electrical/control system that meets those needs.
RELEVANT PROJECT EXPERIENCE:
• Newburgh Indiana—WWTP Improvements Design: Designed the improvements
including the mechanical screening, grit removal, and biosolids facili1es. The project
included the powering and control of 11 Centrifugal blowers with variable frequency
drives on Dissolved Oxygen control.
• Indianapolis Indiana—Buck Creek LiA Sta)on 313: This project included both the
evalua1on of and design upgrades to Li; Sta1on 313. The modifica1ons project
addressed exis1ng deficiencies of the li; sta1on and included the implementa1on of new
electrical and controls for the City of Indianapolis’ largest li; sta1on. The sta1ons capacity
was increased to approximately 60 million gallons per day.
• Indianapolis Indiana—Indianapolis Water Fall Creek Filter Control Replacement:
Replaced exis1ng relay and solenoid valve controls with new Allen Bradley PLC based
controls. Maintained plant opera1on during en1re construc1on project.
• Kokomo Indiana—VFD: The exiting antiquated reduced voltage motor starters were
replaced with new Variable Frequency Drives (VFD’s) providing the City of Kokomo with
needed energy savings motor speed control. The new VFD’s allow the City to control the
speed of the motors to maintain the needed dissolved oxygen and thus reducing energy
consumption. The VFD’s also increase the life expectancy of the blowers and their motors.
Current Limi1ng also allowed the re-use of exis1ng generator to save on capitol costs.
• Indianapolis Indiana—Belmont WWTP Plant Drain: New plant drain pump controls
networked to exis1ng Ethernet.
• Lowell Indiana—WWTP: New SCADA system with WWTP upgrades. Fiber op1c
Ethernet, PLC’s, and RS-View front end so;ware.
• Madison Indiana—WWTP: New SCADA System with remote sites via spread spectrum
radio and local Ethernet network.
• South Bend Indiana—CSO: Eight CSO monitoring sights communica1ng to SCADA via
spread spectrum radios.
• Terre Haute Indiana—LiA Sta)on Telemetry: Spread Spectrum communica1ons from li;
sta1ons to front end SCADA computer.
EDUCATION &
CREDENTIALS:
Electrical Engineer
B.S. Purdue
University, 1992
AEE Cer1fied Energy
Auditor
Licensed Master
Electrician
Power Quality
Analysis Training
REGISTRATION:
Indiana Professional
Engineer
PE 11300603
KEY SKILLS
Controls System
Design
Electrical System
Design
Blueprints &
Schema1cs
Generators &
Transformers
Switches & Circuit
Breakers
Electrical Code
Troubleshoo1ng
Tes1ng Instruments
Motors & Conduit
A wealth of resources to master a common goal.
• Fishers Indiana WWTP Energy Audit and Aera)on Evalua)on: The exis1ng Aera1on
System consists of three 250HP Mul1 Stage Centrifugal Blowers on Variable Frequency
Drives (VFD’s) and five 75HP Constant Speed Mul1 Stage Centrifugals. A plan was
developed to modify the exis1ng piping and header. These modifica1ons provide for a
common aera1on header allowing the control system to modulate the exis1ng blowers
and controls to maintain much 1ghter DO control lowering energy costs. Capitol costs are
$65,000 yielding annual savings of $48,000.
• Osgood Indiana WWTP Upgrades: The project consisted of wastewater collec1on
system rehabilita1on and wastewater treatment plant improvements directed toward
increasing opera1onal efficiency and increasing peak wet weather flow rate capability by
providing offline flow equaliza1on. The project included 7 PD blowers on variable
frequency drives with various control techniques implemented to op1mize energy
savings.
• Terre Haute Indiana WWTP Improvements Design: Designed the septage/grease
receiving facility and expanded and improved sludge treatment processes with the
addi1on of Centrifuges.
• Carmel Indiana WWTP Digester Gas Burner: New digester/burner control system
integrated into exis1ng SCADA.
• Evansville Indiana LiA Sta)on Controls: New controls and electrical for nine (9) li;
sta1on upgrades and replacement.
• Crown Point Indiana Water and Wastewater Electrical and Control Projects: Designed
electrical and control upgrades for various water and wastewater projects including CSO
redirec1on, li; sta1on replacement and upgrades, blower control, ter1ary filter electrical
control, and collec1on surcharging control.
Addi)onal projects can be provided upon request.
Toby Church, P.E., CEA
Senior Electrical Engineer EDUCATION &
CREDENTIALS:
Electrical Engineer
B.S. Purdue
University, 1992
AEE Cer1fied Energy
Auditor
Licensed Master
Electrician
Power Quality
Analysis Training
REGISTRATION:
Indiana Professional
Engineer
PE 11300603
KEY SKILLS
Controls System
Design
Electrical System
Design
Blueprints &
Schema1cs
Generators &
Transformers
Switches & Circuit
Breakers
Electrical Code
Troubleshoo1ng
Tes1ng Instruments
Motors & Conduit
A wealth of resources to master a common goal.
EXPERIENCE & EXPERTISE
Chris has over 7 years experience with Commonwealth Engineers in areas such as water
distribu1on systems, sanitary sewer collec1on systems, and wastewater treatment. As an
Electrical Designer, Chris is involved in Generator Sizing, Conduit/Wire Sizing, Instrumenta1on
and Control, and SCADA
RELEVANT PROJECT EXPERIENCE
• Nappanee, Indiana - Wet Weather Treatment Facility: Designer
• Terre Haute, Indiana - Wet Weather Treatment Facility: Designer
• Crown Point, Indiana - LTCP Improvements Project: Designer
• Fishers, Indiana - Allisonville Road LiA Sta)on Parallel Force Main Project: Designer
• Nappanee, Indiana - CSO Interceptor Project: Designer
• Madison, IN - Madison State Hospital Complex Wastewater Collec)on System
Improvements: Designer
• Logansport, Indiana - High Flow Wet Weather Abatement: Designer
EDUCATION:
Bachelor of Science
in Construc1on
Technology
Indiana State
University
Chris Means
Electrical Designer
A wealth of resources to master a common goal.
Sub Consultant Informa)on—Infrastructure Engineering
A wealth of resources to master a common goal.
Sub Consultant Informa)on—Eilts Consul)ng Services
LORIRUSHIN,P.E.
PROJECTMANAGER
AREASOFEXPERTISE:ProjectManagement,ConstructionInspection,Topographic
Survey&ConstructionEngineering,
Related Project Experience:
IAA-I-12-018 – Pavement Rehabilita�on New Indianapolis Airport, Indianapolis, IN
Design services included topographical survey data collec1on and pavement evalua1on of
perimeter roads at the New Indianapolis Interna1onal Airport.
IAA-11-014 Federal Express Cargo Apron Expansion –Indianapolis, IN
Inspec1on services included reinforcing & concrete pavement tes1ng services for Phase I as
well as stormwater inspec1on services for Phase II.
BL-33-053ASoutheastern/RaymondSTEPCitzensEnergyGroup,Indianapolis,IN
Inspector for the construction of sanitary sewers ranging from 8” to 18” in diameter
includingthelateralinstallationfor372homes.
CS-26-12BPoguesRunCSO143BasinSewerSeparation,.Indianapolis,IN
Review of the installation of storm sewers to separate stormwater runoff from the
combined sewers involving approximately 7,700 LF of storm sewer pipe, 12” to 54” in
diameter, storm inlets, and water quality basin & bioswale to treat stormwater before
dischargingintoPogue’sRun.
SS-28-003EastMarionCountyInterceptorManholeRehabilitation,Indianapolis,IN
InspectorfortherehabilitationofmanholesthroughoutMarionCountyincludingcement
liningexistingstructures,providingnewsealsandleaktesting.
INDOT R-30351 - Illinois St. Rehabilita�on, Indianapolis, IN
Project involved the inspec1on of new installa1on of curbs, islands, sidewalks, handicap ramps
coordinated with the Cultural Trail in downtown Indianapolis.
INDOT R-30159 - 10th & Shadeland Intersec�on Improvements, Indianapolis, IN
Project involved inspec1on for the new installa1on of curbs, ramps, driveways and new
intersec1on light poles and traffic signals.
INDOT R-30926 Canal Road Bridge Rehabilita�on Terre Haute, Indiana
Construction Engineering services included horizontal and vertical control including
stakingfortheroadwayaswellasallstructuresandmonuments.
INDOT RS-32856 ARRA Resurfacing-Franklin, Raymond & Southeastern, Indianapolis, IN
Inspection services for existing road reconstruction project included new asphalt overlay & handicap ramp installation.
BM-35-015 – Bridge Rehabilita�on Prospect St. over Grassy Creek, Indianapolis, IN
Inspection services included review of concrete bridge deck overlay and erosion control measures.
E i l t s C o n s u l t i n g S e r v i c e s
EDUCATION
B.S.C.E.Purdue
University
B.A.DePauw
University
CERTIFICATIONS
IWEAWater&
SewerConstruction
InspectionCerti<ied
INDOTNEPA&
Categorical
ExclusionTraining
INDOTSiteManager
INDOTPrequali<ied
Consultant8.1
PavementDesign;
13.1Construction
Inspection
INDOTProject
Engineer/Project
SupervisorTraining
INDOTStormwater
InspectionCerti<ied
ATSSATraf<ic
ControlSupervisor
&Technician
Certi<ied
ESSWICerti<ied
Erosion,Sediment&
Stormwater
Inspector
CPESCCerti<ied
Professionalin
Erosionand
SedimentControl
Professional
Engineer-IN
WBE-DBEIndiana,
Illinois,&Kentucky
A wealth of resources to master a common goal.
Sub Consultant Informa)on—Precept Surveying, LLC
A wealth of resources to master a common goal.
CLIENT City of Indianapolis
COMMONWEALTH
PERSONNEL Toby Church, P.E.
Project Responsibili1es:
System Design
Project Management
PROJECT HIGHLIGHTS • Rehab controls for 12 filters
• Exis1ng control panels had
become obsolete and needed
to be replaced
• Design build project with
Ci1zens Energy and Bowen
Engineering
PROJECT DESCRIPTION
The exis1ng control panels were beyond their useful life span, were
unreliable, difficult to find replacement parts for, and in need of
replacement. The exis1ng filter control panels had been modified
mul1ple 1mes over the years, and were built into the block walls,
which dictated the size of the replacement panels. Due to the
necessity to maintain produc1on in order to provide clean drinking
water to the City of Indianapolis, each filter had a maximum down 1me of one week.
As a solu1on to these challenges custom control panels were manufactured to fit into the exis1ng control panel
loca1ons, housed in the block walls. This provided an aesthe1cally pleasing solu1on that was func1onal and provided
for room to service the new controls.
The short down 1me required that the control panel be built, tested, and programmed before shut down. The conduit
and wire to the field instruments had to be complete, leaving only the final connec1ons to the new control panel when
it was set in place. Addi1onally, the new filter controls required wiring and programming modifica1ons to the exis1ng
blower control panel. An Ethernet network was installed to each filter and a new computer with Intellu1on Fix32 was
provided to display the status of each filter. The exis1ng SCADA computer was modified to communicate to the new
networked PLC's. PLC’s are Allen Bradley Micrologic with Allen Bradley HMI touch screens.
Similar Experience
Fall Creek Filters Control Upgrade - Indianapolis, Indiana
A wealth of resources to master a common goal.
CITIZENS FILTER PANEL REHAB
BEFORE AFTER
Fall Creek Filters Control Upgrade - Indianapolis, Indiana (Con)nued)
A wealth of resources to master a common goal.
CLIENT City of Indianapolis
COMMONWEALTH
PERSONNEL Toby Church, P.E.
Project Responsibili1es:
System Design
Project Management
PROJECT HIGHLIGHTS • New Electrical
• New Variable Frequency
Drives
• Redundant U1lity Services for
backup power
• New Allen Bradley Controls
• Redundant PLC Processors
• Redundant communica1ons
paths
• Redundant instrumenta1on
• Surge protec1on
PROJECT DESCRIPTION
This project included both the evalua1on of and design upgrades to Li; Sta1on
313. The modifica1ons project addressed exis1ng deficiencies of the li; sta1on
and included the implementa1on of new electrical and controls for the City of
Indianapolis’ largest li; sta1on. The sta1ons capacity was increased to
approximately 60 million gallons per day.
The project included five (5) new 380 HP Flygt pumps with the associated new
electrical and controls with the necessary backup and redundancy for such a cri1cal
Li; Sta1on.
The new electrical and control system consists of Allen Bradley (AB) PLC controls
with variable frequency drives on all pumps. The Allen Bradley ControlLogix system
consists of redundant PLC processors capable of hot backup. Backup instruments
include redundant level transmiNers and redundant bubbler level sensors. The AB
Control System is integrated into the City of Indianapolis SCADA System via MDS
radios capable of mul1ple communica1ons paths for redundancy. Flygt CAS pump
safety equipment is integrated into the control logic.
Buck Creek LiA Sta)on (LiA Sta)on 313) - Indianapolis, Indiana
A wealth of resources to master a common goal.
Newburgh Wastewater Treatment Plant Improvements - Newburgh, IN
CLIENT City of Newburgh
COMMONWEALTH
PERSONNEL Toby Church, P.E.
Project Responsibili1es:
System Design
Project Management
PROJECT DESCRIPTION
The waste water treatment plant was required to remain in service during the
en1re length of the project including the demoli1on of the exis1ng controls and
installa1on and startup of the new controls. Due to the new controls being
Ethernet-based and the project schedule dicta1ng the installa1on of new
controls being staged months apart, new PLC controllers on Ethernet and
exis1ng PLC controllers on DH+ had to be able to pass informa1on back and
forth to keep all systems opera1onal.
As a result of the system requiring con1nuous opera1on, temporary Operator Interface Touchscreens (OIT’s) were
added to new control panels that were not connected to the new SCADA system allowing the plant operators to have
full control of the new equipment. Temporary PLC’s had to be added in certain loca1ons to pass cri1cal informa1on
from the DH+ network to the new Ethernet network using the serial ports and message commands of the new and
exis1ng PLC’s. Since the new controls were replacing exis1ng PLC controls that were in service, all new control panels
had to be thoroughly tested with programming and graphics complete before replacing the exis1ng equipment. The
exis1ng SCADA computers were upgraded from Windows NT machines with Wonderware 7.0 graphics so;ware and
DH+ communica1ons. The new system was upgraded to Windows XP with Wonderware 10.1 graphics so;ware and
Ethernet communica1ons. Trending, alarming, and repor1ng had to be completely func1onal on the new SCADA
computers that were communica1ng with the new controls being installed in different stages.
PROJECT HIGHLIGHTS • The exis1ng Newburgh WWTP
consisted of five Sequence
Batch Reactor (SBR) tanks that
were designed to handle
14.4mgd.
• With the improvements project,
an addi1onal three SBR tanks
were added to the system to
increase the intake of the plant
to 19.2mgd.
• The improvements project also
replaced the exis1ng Allen
Bradley DH+ PLC network with
an Ethernet network with a
fiber op1c backbone providing
for faster and more reliable
SCADA Communica1ons.
A wealth of resources to master a common goal.
Blower VFD Upgrade - Kokomo, Indiana
CLIENT City of Kokomo
COMMONWEALTH
PERSONNEL Toby Church, P.E.
Project Responsibili1es:
System Design
Project Management
PROJECT DESCRIPTION
The VFDs were to be installed in the exis1ng Motor Control Center (MCC)
enclosure. Only one blower at a 1me could be out of opera1on during
the installa1on. The main supply power bus had to remain energized
throughout the equipment installa1on. Ven1la1on had to be added to
each motor control enclosure to ensure adequate cooling of the new
Variable Frequency Drives (VFD’s). The new VFD’s operate in conjunc1on with the exis1ng blower control panels and
the plant-wide SCADA system.
The exis1ng reduced voltage equipment was removed and the main control circuit breaker was moved to allow for
installa1on of the new Variable Frequency Drives. A dv/dt filter (electrical noise filter) was added to the load side of
the VFD to provide electrical noise reduc1on to extend the life expectancy of the exis1ng motors. The 700 Amp
power wiring was installed u1lizing flexible insulated busbar. The exis1ng control wiring was connected to the
exis1ng PLC and SCADA system and each blower was back in service within 48 hours.
PROJECT HIGHLIGHTS • The scope of the blower VFD upgrade
included the replacement of obsolete
reduced-voltage starters with new
variable frequency drives (VFD).
• With the exis1ng starters, the
blowers ran at full speed and the air
volume was controlled with inlet
dampers on each blower.
• The VFD replacement allows air
volume to be controlled by
modula1ng the blower speed. This
reduces wear on the motor and
blower bearings and has reduced the
electrical consump1on by an average
of 25-30%.