CITY OF BLOOMINGTON DIVISION S SPECIAL PROVISIONS S... · BLOOMINGTON DIVISION S SPECIAL PROVISIONS...
Transcript of CITY OF BLOOMINGTON DIVISION S SPECIAL PROVISIONS S... · BLOOMINGTON DIVISION S SPECIAL PROVISIONS...
CITY
OF
BLOOMINGTON
DIVISION S
SPECIAL
PROVISIONS
These Special Provisions are intended to modify and shall take precedence over the General
Specifications. The plans and the specifications accompanying them shall be considered as a
whole.
I hereby certify that the Special Provisions (Division S) contained in this proposal were
prepared by me or under my direct supervision and that I am a duly licensed Professional
Engineer under the laws of the State of Minnesota.
Nickolas VanGunst
Lic. No. 44683 Date 02/13/17
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Table of Contents
2-S
S-1 CONTACT INFORMATION .................................................................................................................................... 1
S-2 ENGINEER ........................................................................................................................................................... 4
S-3 SCOPE OF WORK ................................................................................................................................................. 4
S-4 ADD ALTERNATIVE BID ITEMS ............................................................................................................................ 5
S-5 STORAGE OF MATERIAL ...................................................................................................................................... 5
S-6 SHOP DRAWING ................................................................................................................................................. 6
S-7 VIBRATION ......................................................................................................................................................... 6
S-8 MINORITY BUSINESS .......................................................................................................................................... 6
S-9 PREVAILING WAGE ............................................................................................................................................. 7
S-10 SCHEDULE OF MATERIALS CONTROL .............................................................................................................. 7
S-11 GUARANTEE ................................................................................................................................................... 7
S-12 FINAL ESTIMATE............................................................................................................................................. 7
S-13 MOBILIZATION ............................................................................................................................................... 8
S-14 RESPONSIBLE CONTRACTOR ........................................................................................................................... 5
S-15 (1801) SUBLETTING OF CONTRACT ................................................................................................................. 5
S-16 COMPLIANCE WITH TAX LAW REQUIREMENTS .............................................................................................. 6
S-17 EMERALD ASH BORER COMPLAINCE .............................................................................................................. 7
S-18 (1203) ACCESS TO PROPOSAL PACKAGE ......................................................................................................... 7
S-19 (1205) EXAMINATION OF PLANS, SPECIFICATIONS, AND SITE OF WORK ...................................................... 11
S-20 (1206) PREPARATION OF PROPOSAL ............................................................................................................ 11
S-21 (1209) DELIVERY OF PROPOSAL.................................................................................................................... 12
S-22 (1210) REVISIONS OF PROPOSAL PACKAGE OR WITHDRAWAL OF PROPOSALS ............................................ 12
S-23 (1212) OPENING OF PROPOSALS .................................................................................................................. 13
S-24 (1305) REQUIREMENT OF CONTRACT BOND ................................................................................................ 13
S-25 (1306, 1806) DETERMINATION AND EXTENSION OF CONTRACT TIME .......................................................... 14
S-26 (1404) MAINTENANCE OF TRAFFIC, (1707) PUBLIC SAFETY, AND (2563) TRAFFIC CONTROL ......................... 15
S-27 (1407) FINAL CLEANUP ................................................................................................................................. 25
S-28 (1504) COORDINATION OF PLANS AND SPECIFICATIONS .............................................................................. 26
S-29 (1505) COOPERATION BY CONTRACTORS ..................................................................................................... 26
S-30 (1506) SUPERVISION BY CONTRACTOR ......................................................................................................... 26
S-31 (1507) EXISTING UNDERGROUND UTILITIES ................................................................................................. 27
S-32 (1513) RESTRICTIONS ON MOVEMENT AND STORAGE OF HEAVY LOADS AND EQUIPMENT ......................... 28
S-33 (1516) ACCEPTANCE OF WORK ..................................................................................................................... 29
S-34 (1601) SOURCE OF SUPPLY AND QUALITY .................................................................................................... 29
S-35 (1701) LAWS TO BE OBSERVED - CARGO PREFERENCE ACT; USE OF UNITED STATES - FLAGGED VESSELS ..... 31
S-36 (1702) PERMITS, LICENSES, AND TAXES ........................................................................................................ 31
S-37 (1704) TRENCH RESTORATION AND BACKFILL/SURFACE RESTORATION ....................................................... 33
Table of Contents
3-S
S-38 (1706) EMPLOYEE HEALTH AND WELFARE ................................................................................................... 34
S-39 (1707) PUBLIC CONVENIENCE AND SAFETY .................................................................................................. 36
S-40 (1710) TRAFFIC CONTROL ............................................................................................................................. 36
S-41 (1710) TRAFFIC CONTROL DEVICES ............................................................................................................... 39
S-42 (1712) TREE PROTECTION ............................................................................................................................. 40
S-43 (1714) RESPONSIBILITY FOR DAMAGE CLAIMS ............................................................................................. 40
S-44 (1717) AIR, LAND AND WATER POLLUTION .................................................................................................. 44
S-45 IMPLEMENTATION OF CLEAN AIR ACT AND FEDERAL WATER POLLUTION CONTROL ACT ............................ 45
S-46 (1803;1806) SCHEDULE, COMPLETION DATE, EXECUTION AND APPROVAL OF CONTRACT ........................... 45
S-47 (1807) FAILURE TO COMPLETE THE WORK ON TIME .................................................................................... 46
S-48 (1903) COMPENSATION FOR INCREASED OR DECREASED QUANTITIES ......................................................... 47
S-49 (1904) EXTRA AND FORCE ACCOUNT WORK ................................................................................................. 47
S-50 (1910) FUEL ESCALATION CLAUSE ................................................................................................................ 47
S-51 (2104) REMOVAL OF PAVEMENT AND MISCELLANEOUS STRUCTURES ......................................................... 47
S-52 (2105) SELECT TOPSOIL BORROW ................................................................................................................. 48
S-53 (2461) STRUCTURAL CONCRETE ................................................................................................................... 49
S-54 (3137) COARSE AGGREGATE FOR PORTLAND CEMENT CONCRETE ............................................................... 53
S-55 (2471) STRUCTURAL METALS ....................................................................................................................... 71
S-56 (2521) SIDEWALK ......................................................................................................................................... 56
S-57 (2573) STORM DRAIN INLET PROTECTION .................................................................................................... 74
S-58 (2575) SODDING, TYPE SALT RESISTANT ....................................................................................................... 74
S-59 EQUIPMENT ................................................................................................................................................. 75
S-60 WORKMANSHIP ........................................................................................................................................... 75
S-61 PROTECTION OF THE PUBLIC ........................................................................................................................ 76
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
4-S
DIVISION S
S-1. CONTACT INFORMATION
Questions regarding this Project shall be directed to Amy Marohn, City of Bloomington, at (952)
563-4532. S-2. ENGINEER
Questions regarding this Project shall be directed to Amy Marohn, City of Bloomington, at (952)
563-4532. S-3. SCOPE OF WORK
Included under this contract, the Contractor shall provide all labor, materials, tools, and
equipment to construct, complete in-place, underground conduits, cables, vaults, enclosures,
cabinets, walkways, foundations, traffic signal revisions, pavement patching, and turf restoration
work, repair, relocate, maintain and restore all subsurface, surface and overhead structures
directly or indirectly disturbed, injured, or affected by the Contractor’s operations, and furnish
all other appurtenant items and services necessary, as shown on the drawings and as specified
herein.
The Project shall consist of furnishing all of the materials, labor and equipment necessary to
perform the work detailed and construct the following approximate quantities:
1. Approximately 48 Square Feet of Remove Concrete Walk
2. Approximately 14 Cubic Yards of Select Topsoil Borrow
3. Approximately 48 Square Feet of Concrete Walk
4. Approximately 9 Each of Grounding Electrode
5. Approximately 2 Each of Cabinet Foundation
6. Approximately 18 Each of Fiber Optic Splice Vaults
7. Approximately 27 Each of Outdoor Fiber Optic Splice Enclosure
8. Approximately 6,235 Linear Feet of 1.5” Non-Metallic Conduit
9. Approximately 525 Linear Feet of 2” Non-Metallic Conduit
10. Approximately 70 Linear Feet of 3” Non-Metallic Conduit
11. Approximately 20 Linear Feet of 4” Non-Metallic Conduit
12. Approximately 375 Linear Feet of Power Cable 1 Conductor No. 6
13. Approximately 250 Linear Feet of CAT 6 Cable
14. Approximately 2 Each of Install Cabinet
15. Approximately 3 Each of Fiber Optic Splice/Patch Panel
16. Approximately 6 Each of Fiber Optic Pigtail Termination
17. Approximately 29 Each of Fiber Optic Cable Splicing
18. Approximately 21 Each of Fiber Optic Pull Vault
19. Approximately 18 Each of Core Drill Signal Pad
20. Approximately 2 Each of Modify Service Equipment
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
5-S
21. Approximately 995 Linear Feet of Fiber Optic Pigtail Cable (6SM)
22. Approximately 6,555 Linear Feet of Pre-Term/Armor Fiber Optic Pigtail (6SM)
23. Approximately 230 Linear Feet of Fiber Optic Trunk Cable (12SM)
24. Approximately 100 Linear Feet of Fiber Optic Trunk Cable (24SM)
25. Approximately 34,400 Linear Feet of Fiber Optic Trunk Cable (48SM)
26. Approximately 47,636 Linear Feet of 1.5” Bored Conduit
27. Approximately 520 Linear Feet of 3” Bored Conduit
28. Approximately 350 Linear Feet of Reroute Cable
29. Approximately 4 Systems of Traffic Monitoring Systems
30. Approximately 7 Systems of Revise Traffic Signal Systems
31. Approximately 125 Square Yards of Sodding Type Salt Resistant
In the following Specifications, reference is made to “Mn/DOT Specifications” which shall mean
the “STANDARD SPECIFICATIONS FOR CONSTRUCTION” of the Department of Transportation of
the State of Minnesota, 2016 edition including all supplemental specifications and other
updates. All materials and methods shall comply with that Specification and Supplemental
Specifications unless modified in these documents.
S-4. ADD ALTERNATIVE BID ITEMS
There are eight (8) add alternate bid items included in the project. The City shall select the
best bid based on the grand total bid on all of the items on the contract (including the Add
Alternatives) but may choose not to award one or more Add Alternate portions at the time of
the award of the rest of the project. By signing the proposal, the Contractor acknowledges that
the City may delete one or more Add Alternate portions of the bid without putting into effect
the provisions of Article 8 of the General Specifications regarding increase or decrease in
quantities. The Contractor shall review Article ix, Consideration of Bids, in the General
Specifications. The last paragraph of this article states "...the City reserves the right to award
the contract in whole or in part, whichever is in the best interests of the City." If a decision has
been made to award Add Alternate portions, the Add Alternates will be chosen in the order
listed in the plans and specifications. For example, the base bid and the acceptable Add
Alternate(s), in the order shown in the plans, will be accepted based on the available funds
allowed. Selection of the apparent low bidder will be based on a pre-determined dollar
amount, which will be disclosed prior to the bid opening. The apparent low bidder with the
most consecutive Add Alternatives beginning with Add Alternative 1 with a bid lower than the
pre-determined dollar value will be selected. If all bids are higher than the pre-determined
dollar amount, the lowest Base Bid will be selected.
S-5. STORAGE OF MATERIAL
On any corner formed by intersecting streets, the Contractor shall not permit the placement or
storage of materials and equipment or other obstructions to a height greater than three feet
above the level of the center of the adjacent intersection within the area of land formed on the
corner of the lot by measuring a distance of 50 feet along each curb line (or, if none, then each
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
6-S
boundary line of the roadways) from the intersection of such lines, as shown in the figure
below:
Site-specific conditions may require adjustments by the Engineer in the size and location of the
clear view area as described above.
In addition, no stock pile/staging areas are provided within the project work zone. It will be the
Contractor’s responsibility to find an area to use for this if it is determined to be necessary. Any
site used shall be submitted to the Engineer for approval and will be subject to all applicable code and ordinance requirements. No compensation will be provided for the stock pile/staging
area and it will be considered incidental to the various contract unit prices.
S-6. SHOP DRAWING
Shop drawings will be accepted and reviewed by the City, the acceptance, review and/or
subsequent comments shall not be construed as approval of the shop drawings. The
responsibility of the Contractor to supply materials that comply with the specifications and plans lies entirely with the Contractor. S-7. VIBRATION
The Contractor may need to make adjustments to their construction practices if damage to
adjacent facilities may result from their operations. It is the responsibility of the Contractor to
monitor and make necessary changes if any are needed. Any monitoring or changes in
operations will be at the Contractor’s expense. S-8. MINORITY BUSINESS
The City of Bloomington (City) has adopted and strictly enforces a nondiscrimination policy,
which must be included in all contracts and subcontracts. The Contractor is directed to review
these requirements in Article 39 of the General Specifications.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
7-S
S-9. PREVAILING WAGE
All work under this contract shall meet the requirements set forth by the Minnesota
Department of Transportation for prevailing wage (Payment of Predetermined Minimum Wage)
rates.
The minimum hourly rates of wages required to be paid for all hours worked to the various
laborers and mechanics employed by the Contractor and subcontractors under the Contract
shall be according to the schedule contained in the Prevailing Wages for State Funded
Construction Projects of the Minnesota Department of Labor and Industry (included in
Appendix). Overtime shall be paid after 8 hours per day. The overtime rate for hours worked in
excess of 8 hours per day on this Project may not be less than one and one-half the basic hourly
rate.
Pursuant to Minnesota Statutes 177.41 to 177.44 and corresponding Rules 5200.1000 to
5200.1120, this contract is subject to the prevailing wages as established by the Minnesota
Department of Labor and Industry. Specifically, all contractors and subcontractors must pay all
laborers and mechanics the established prevailing wages for work performed under the
contract. Failure to comply with the aforementioned may result in civil or criminal penalties
The 2001 Trucking Rules (effective on public works projects advertised after June 25, 2001) will
be enforced on this Project. An overview is located at
http://www.revisor.leg.state.mn.us/arule/5200/1106.html.
S-10. SCHEDULE OF MATERIALS CONTROL
Testing rates for materials used on this Project shall be at the rates set by MnDOT State Aid for
Local Transportation’s Schedule of Materials Control, which is included with these
specifications.
S-11. GUARANTEE
The Contractor shall be held responsible for any and all defects in workmanship and materials,
which may develop in any part of the entire installation furnished under this contract. Upon
written notice by the Engineer; the Contractor shall immediately replace, without expense to
the City, any such faulty parts and material installed not in accordance with these plans and
specifications until the date of Final Acceptance. “Final Acceptance” shall be defined as the
date of issue of the final estimate.
S-12. FINAL ESTIMATE
The final estimate cannot be processed until “Final acceptance of the Project” as defined in
Article 41 of the General Specifications has occurred.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
8-S
S-13. MOBILIZATION
Mobilization on this Project shall be in accordance with MnDOT 2021. The Contractor shall
anticipate that numerous remobilizations are common on this type of project.
S-14. RESPONSIBLE CONTRACTOR
REVISED 06/04/15
The Department cannot award a construction contract in excess of $50,000 unless the Bidder is
a “responsible contractor” as defined in Minnesota Statutes §16C.285, subdivision 3. A Bidder
submitting a Proposal for this Project must verify that it meets the minimum criteria specified in
that statute by submitting the “Responsible Contractor Verification and Certification of
Compliance” form. A company owner or officer must sign the “Responsible Contractor
Verification and Certification of Compliance” form under oath verifying compliance with each of
the minimum criteria. THE COMPLETED FORMS MUST BE SUMITTED WITH THE BID PROPOSAL.
A bidder must obtain a verification from each subcontractor it will have a direct contractual
relationship with. At the Department’s request, a bidder must submit signed subcontractor
verifications. A contractor or subcontractor must obtain an annual verification from each
motor carrier it has a direct contractual relationship with. A motor carrier must give immediate
written notice if it no longer meets the minimum responsible contractor criteria. The
requirement for subcontractor verifications does not apply to:
• Design professionals licensed under Minnesota Statutes §326.06; and
• A business or person that supplies materials, equipment, or supplies to a
subcontractor on the Project, including performing delivering and
unloading services in connection with the supply of materials, equipment,
and supplies. But, a business or person must submit a verification if it
delivers mineral aggregate such as sand, gravel, or stone that will be
incorporated into the Work by depositing the material substantially in
place, directly or through spreaders, from the transporting vehicle.
A bidder or subcontractor who does not meet the minimum criteria specified in the statute, or
who fails to verify compliance with the criteria, is not a “responsible contractor” and is
ineligible to be awarded the Contract for this Project or to work on this Project. Submitting a
false verification makes the bidder or subcontractor ineligible to be awarded a construction
contract for this Project. Additionally, submitting a false statement may lead to contract
termination. If only one bidder submits a bid, the Department may, but is not required to,
award a contract even if that bidder does not meet the minimum criteria.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
9-S
S-15. (1801) SUBLETTING OF CONTRACT
REVISED 6/4/15
The provisions of MnDOT 1801 are modified as follows:
S-15.1 For Projects in excess of $50,000, the Contractor may sublet work only to
subcontractors that meet the definition of “responsible contractor” in Minnesota
Statutes §16C.285, subdivision 3. The Contractor shall obtain verifications of
compliance with §16C.285 from subcontractors using a form provided by the
Department. The Contractor must provide such verifications to the Department upon
the Department’s request.
S-15.2 The third paragraph of MnDOT 1801 is modified to read:
On Contracts with Disadvantaged Business Enterprise (DBE), the Contractor's
organization shall perform Work amounting to not less than 30 percent of the total
original Contract Amount. The Department will deduct specialty items from the total
original Contract Amount before calculating the amount of Work that the Contractor
shall perform.
S-16. COMPLIANCE WITH TAX LAW REQUIREMENTS
The Department cannot make final payment to the Contractor until the Contractor
demonstrates that it and all its subcontractors have complied with the Income Tax withholding
requirements of Minnesota Statutes, section 290.92 for wages paid for work performed under
the contract. To establish compliance, the Contractor must submit a “Contractor Affidavit”
either online or in paper form (IC134) to the Minnesota Department of Revenue. The contractor
will receive written certification of compliance when the Department of Revenue determines
that all withholding tax returns have been filed and all withholding taxes attributable to the
work performed on the contract have been paid. The Contractor must then provide this written
certification to the Department to receive final payment.
Every subcontractor working on the Project must submit an approved “Contractor Affidavit”
from the Minnesota Department of Revenue to the Contractor before the Contractor can file its
own Contractor Affidavit. The Contractor is advised to obtain the certification from each
subcontractor as soon as the subcontractor completes work on the Project. Experience has
shown that waiting until the project is complete to obtain the forms from all subcontractors
is likely to result in significant additional work for the Contractor as it will be difficult or
impossible to collect all forms.
The Department of Revenue, in association with the Department of Employment and Economic
Development, offers a free seminar to help contractors understand tax law requirements. The
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
10-S
Department strongly urges the Contractor and all subcontractors to attend the “Employment
Taxes & Employer Responsibilities Seminar” or similarly offered classes. You can find a schedule
and more information on the Department’s website at:
www.revenue.state.mn.us/businesses/withholding/Pages/EducationandOutreach.aspx.
Complying with this requirement is considered part of the Work under this contract. The
Department will enforce this requirement equally with all other Contract requirements.
Contractor delay in complying with this requirement will cause the Department to delay final
payment and Contract Acceptance. The Department may also report non-compliance to the
Department of Revenue, which may result in enforcement action by the Department of
Revenue.
S-17. EMERALD ASH BORER COMPLIANCE
REVISED 01/08/16
All or part of this Project is located in a county which the Minnesota Department of Agriculture
(MDA) has placed under an Emerald Ash Borer Quarantine. Contractor may contact MDA at 1-
888-545-6684 or visit the Emerald Ash Borer website at
http://www.mda.state.mn.us/plants/pestmanagement/eab.aspx to find more information. The
Contractor must comply with the following requirements.
S-17.1 The Contractor will not:
(1) Offer any part of an Ash tree (Fraxinus spp.) from a quarantined area to any
industry or individual without an Emerald Ash Borer Compliance Agreement with
MDA; or
(2) Make available any part of an ash tree or any non-coniferous (hardwood) species
with bark from the quarantined area for use as firewood; or
(3) Transport any part of an ash trees, in any form, outside of a quarantined county
without complying with an Emerald Ash Borer Compliance Agreement with
MDA; or
(4) Transport any part of ash trees, in any form, outside the state of MN without
contacting [email protected] to obtain the United States
Department of Agriculture’s and the MDA’s joint approval of the Emerald Ash
Borer Compliance Agreement.
S-17.2 The Contractor will:
(1) Dispose of ash trees according to the Emerald Ash Borer Compliance Agreement;
and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
11-S
(2) Use the ash wood chips within the construction limits for erosion control,
construction exit pads, or other project related needs.
S-17.3 The Department will not directly compensate the Contractor for compliance with these
requirements.
S-18. (1203) ACCESS TO PROPOSAL PACKAGE
MnDOT 1203 is hereby deleted from the MnDOT Standard Specifications.
S-19. (1205) EXAMINATION OF PLANS, SPECIFICATIONS, AND SITE OF WORK
The provisions of MnDOT 1205 are hereby supplemented by the following:
No subsurface exploration on the Project shall be performed by prospective bidders
until a permit therefore has been obtained from the County and/or City (depending on
location of subsurface location).
Permits may be obtained at the County offices:
1600 Prairie Drive
Medina, MN
Or at the City office:
1700 West 98th Street
Bloomington, MN S-20. (1206) PREPARATION OF PROPOSAL
The provisions of MnDOT 1206 are supplemented and/or modified with the following:
S-20.1 MnDOT 1206.1 is hereby deleted from the MnDOT Standard Specifications.
S-20.2 MnDOT 1206.2 is hereby deleted from the MnDOT Standard Specifications and replaced
with the following:
1206.2 ALLOWABLE SUBSTITUTIONS
For all Proposals the Bidder shall use the following method:
(1) Submit a Proposal on the Bid Schedule forms provided by the Department. The
Bidder shall:
(1.1) Submit a Unit Price in numeric figures for each Pay Item for which a quantity is
shown. Assume a numeric quantity of “1” for each “Lump Sum” Pay Item, except
as not required in the case of alternate Pay Items,
(1.2) Show the extensions resulting from Unit Prices multiplied by the shown
quantities in the specified column, and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
12-S
(1.3) Add the extended Pay Item amounts to show the total amount of the Proposal.
The Bidder shall write the figures in ink or provide typed or computer printed figures. In
the case of a discrepancy between a Unit Price and extension in a Proposal, the Unit
Price will govern.
If a Bidder fails to provide a Unit Price for any Pay Item on the Bid Schedule, except for
“Lump Sum” Pay Items, the Department will reject the Proposal.
If a Pay Item in the Proposal requires the Bidder to choose an alternate Pay Item, the
Bidder shall indicate its choice in accordance with the Specifications for that Pay Item.
An authorized representative of the Bidder must sign the Proposal.
S-21. (1209) DELIVERY OF PROPOSALS
The provisions of MnDOT 1209 are modified with the following: When submitting a Proposal in accordance with 1206.2, “Allowable Substitutions,” of these Special Provisions, the Bidder shall deliver the Proposal and the Proposal Guaranty in a sealed envelope. The Bidder shall mark the sealed envelope with the name of the Bidder, the Project number, and the letting date. The Bidder shall deliver the sealed envelope to the Department as specified in the Advertisement for Bids as follows:
(1) To the address specified,
(2) In care of the official receiving the Proposals, and
(3) By the date and time for opening Proposals.
The Bidder shall return paper copies of the following with the submitted Proposal:
(1) Proposal title sheet;
(2) The complete “Schedule of Prices,” with all changes made in ink and initialed;
(3) Form 21126D, “Proposal Signature Page” attached to the back of the
Proposal, with signatures and all Addenda acknowledged;
(4) Form CM 32-34, “EEO Clause;” (5) Non-collusion affidavit; and (6) Any other forms included in the Proposal Package.
If the Department receives a Proposal after the date and time for opening Proposals, the Department will return the Proposal to the Bidder unopened.
S-22. (1210) REVISIONS OF PROPOSAL PACKAGE OR WITHDRAWAL OF PROPOSALS
The provisions of MnDOT 1210 are deleted and replaced with the following: When submitting a Proposal in accordance with 1206.2, “Allowable Substitutions,” of these Special Provisions, the Bidder may revise or withdraw its Proposal after delivery to the
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
13-S
Department if the Department receives the Bidder‘s written request for withdrawal or revision before the date and time for opening Proposals. The Department reserves the right to revise the Proposal Package at any time before the date and time for opening Proposals. The Department will issue a numbered and dated Addendum for any revision of the Proposal Package. The Department will post each Addendum as announced in an e-mail or other method of notification to each Bidder on the Department‘s list of Bidders.
The Department will include each Addendum with all Proposal Forms issued to the Bidder after the date of the Addendum. If revisions made by an Addendum require change to Proposals or reconsideration by the Bidder, the Department may postpone opening Proposals. If the Department postpones opening Proposals, the Department will specify the new date and time for opening Proposals in the Addendum. The Bidder shall acknowledge receipt of each Addendum in the proposal. S-23. (1212) OPENING OF PROPOSALS
The provisions of MnDOT 1212 are modified with the following:
S23.1 MnDOT 1212 is hereby deleted from the MnDOT Standard Specifications and replaced
with the following:
1212 OPENING OF PROPOSALS
The Department will open Proposals at the time, date, and place defined in the Proposal
Package and the Advertisement for Bids. S-24. (1305) REQUIREMENT OF CONTRACT BOND
The provisions of MnDOT 1305 are hereby deleted and replaced with the following:
The successful bidder shall furnish a payment bond equal to the contract amount and a
performance bond equal to the contract amount as required by Minnesota Statutes,
section 574.26. The surety and form of the bonds shall be subject to the approval of the
contracting authority.
The contracting authority shall require for all contracts less than or equal to five million
dollars ($5,000,000), that the aggregate liability of the payment and performance bonds
shall be twice the amount of the contract. All contracts in excess of five million dollars
($5,000,000) shall have an aggregate liability equal to the amount of the contract.
The Contractor is advised that the AIA 312 Performance Bond is not acceptable. An AIA
311 Performance Bond is included in the Appendix and is acceptable. The AIA 312
Payment and Materials bond is acceptable.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
14-S
The amount of the bonds shall be increased to reflect the amount of any change orders
and extra work awarded to the Contractor. The cost of the increased amount of the
bonds shall be incidental for which no direct compensation will be made. S-25. (1306, 1806) DETERMINATION AND EXTENSION OF CONTRACT TIME
The Contractor’s construction schedule, list of subcontractors, and list of suppliers shall be
presented for the Engineer’s approval at the Pre-construction Conference.
The Contract Time will be determined in accordance with the provisions of MnDOT 1806 and
the following:
S-25.1 Project Start Date, City Approval Period, Notice of Contract Approval
The Contractor shall have a maximum of seven (7) calendar days to sign the contract books and
submit bonds and insurance after the contract is awarded at the City Council. The City shall
have a maximum of five (5) calendar days (City Approval Period) to review the bonds and
insurance and sign the contract books after the Contractor has signed the books and submitted
the bonds. When the City approves the bonds and insurance and signs the contract books, a
Notice of Contract Approval will be issued. The Notice of Contract Approval will be mailed and
faxed to the Contractor within the 5-day City Approval Period. The date of the Notice of
Contract Approval shall be the date the notice is mailed and faxed to the Contractor. The
Contractor is required to start work on the contract within five (5) days after the date of the
Notice of Contract Approval. Working days will be assessed when Contractor operations result
in traffic restriction, or on the 5th day after the Notice of Contract Approval.
The award is dependent on MnDOT’s approval of the bids and Contractor’s DBE requirement
submittals. This contract is anticipated to be awarded March 21st, 2017.
S-25.2 Working Days
Add the following at the end of MnDOT 1806.2C:
(6) Delays caused by the ineffective, incomplete, or non-placement of erosion
control devices.
When determining Working Day charges in accordance with MnDOT 1806.3, the installation of
erosion control devices may be deemed a progress controlling operation by the Engineer.
The provision for elimination of working day charges between November 15 and April 15 stated
in 1806.3(3) shall not apply when the progress controlling operation is one of the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
15-S
(a) the effective placement of erosion control devices.
(b) the installation and energization of traffic control signal equipment.
Final Completion on this project shall be defined as completing the following items: concrete
walks, operational interconnect, signal and traffic monitoring systems, boulevard grading,
signing, and all underground utilities.
S-26. (1404) MAINTENANCE OF TRAFFIC, (1707) PUBLIC SAFETY, AND (2563) TRAFFIC
CONTROL
The provisions of 1404 are supplemented as follows:
S-26.1 General
The Contractor shall furnish, install, maintain, and remove all traffic control devices required to
provide safe movement of vehicular and/or pedestrian traffic passing through the work zone
during the life of the Contract from the start of Contract operations to the final completion
thereof. The Engineer will have the right to modify the requirements for traffic control as
deemed necessary due to existing field conditions.
Traffic control devices include, but are not limited to, barricades, warning signs, trailers,
flashers, cones, drums, pavement markings and flaggers as required and sufficient barricade
weights to maintain barricade stability.
Only drums, not cones, shall be utilized as the traffic control device for lane closures.
The Contractor shall furnish names, addresses, and phone numbers of at least three (3)
individuals responsible for the placement and maintenance of traffic control devices. At least
one of these individuals shall be "on call" 24 hours per day, seven days per week during the
times any traffic control devices, furnished and installed by the Contractor, are in place. The
required information shall be submitted to the Engineer at the Pre-construction Conference.
The Contractor shall also furnish the names, addresses, and phone numbers of those individuals
to the following:
1. City of Bloomington Public Works Department (952) 563-4581
2. City of Bloomington Police Department (952) 563-4900
3. City of Bloomington Fire Department (952) 563-4801
4. City of Bloomington Clerk (952) 563-4925
The Contractor shall, at the pre-construction conference, designate a Work Zone Safety
Coordinator who shall be responsible for safety and traffic control management in the Project
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
16-S
work zone. The Work Zone Safety Coordinator shall be either an employee of the Contractor
such as a superintendent or a foreman, or an employee of a firm which has a subcontract for
overall work zone safety and traffic control management for the Project. The responsibilities of
the Work Zone Safety Coordinator shall include, but not be limited to:
• Coordinating all work zone traffic control operations of the Project, including
those of the Contractor, subcontractors and suppliers.
• Establishing contact with local school district, government, law enforcement, and
emergency response agencies affected by construction before work begins.
• Maintaining a record of all known crashes within a work zone. This record should
include all available information, such as: time of day, probable cause, location,
pictures, sketches, weather conditions, interferences to traffic, etc. These
records shall be made available to the Engineer upon request.
The Contractor shall inspect, on a daily basis, all traffic control devices, which the Contractor
has furnished and installed, and verify that the devices are placed in accordance with the Traffic
Control Layouts, these Special Provisions, and/or the MN MUTCD. Any discrepancy between the
placement and the required placement shall be immediately corrected. The person performing
the inspection shall be required to make a daily log. This log shall also include the date and time
any changes in the stages, phases, or portions thereof go into effect. The log shall identify the
location and verify that the devices are placed as directed or corrected in accordance with the
Plan. All entries in the log shall include the date and time of the entry and be signed by the
person making the inspection. The Engineer reserves the right to request copies of the logs as
he deems necessary. Specific traffic control layouts are not shown in the plan. The Contractor shall submit traffic
control plans to the Engineer for approval before installing any traffic control device. Traffic
control plans must be submitted to the Engineer for review and approval two (2) weeks before
beginning construction or installing any traffic control. Traffic control along 24th Avenue (CSAH
1), France Avenue (CSAH 17), Penn Avenue (CSAH 32), Normandale Avenue (CSAH 34), Portland
Avenue (CSAH 35), and Nicollet Avenue (CSAH 52) will need to be reviewed and approved by
Hennepin County. Any changes in the traffic control layout or plan shall also be submitted to
the Engineer for review and approval.
The Contractor shall coordinate traffic control plans, including temporary pedestrian routing
and detours, with the traffic control plans for adjacent projects. This coordination shall include
the work by others described in Article S-29 of these Special Provisions.
Lane closures may be restricted to hours between 9 AM and 3 PM. Flag persons will be
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
17-S
required during these restrictions in traffic flow. Exclusive of these times, a minimum of two (2)
11’ wide lanes of traffic (or width stated on the plan) shall be kept open at all times.
Advanced warning signs, notifying the public of the pending construction and dates of closure
shall be placed in locations determined by the Traffic Engineer, and may change location and
message displayed at the changing of phases.
Messages shall be placed on these signs as approved by the Engineer.
Message Signs furnished and installed, as approved by the Engineer, shall be included under
Item 2563.601 “Traffic Control” at the Contract bid price. It shall be specifically noted that the traffic control discussed in these Special Provisions is not
all inclusive of the traffic control needed to complete this project. Additional traffic control
may be required. It is anticipated that one or more layouts from the MNUTCD Field Manual
dated January 2014, including but not limited to, Layout Nos. 25, 32, 33, 39, 40, 53, and 56 will
be needed by the Contractor. No additional compensation shall be afforded the Contractor for
this additional, incidental, traffic control.
The Contractor shall furnish, install, maintain, and remove all traffic control devices required to
provide safe movement of pedestrian and vehicular traffic through and around the project
during the life of the Contract from the start of Contract operations to the final completion
thereof. The Engineer will have the right to modify the requirements for traffic control as
deemed necessary due to existing field conditions. The roadways shall be kept open to traffic
at all times. All temporary pedestrian routing and detours for the project shall be coordinated
with the pedestrian detours of other area projects.
S-26.2 Traffic Control
(A) The Contractor shall notify the Engineer in writing at least 72 hours prior to the start of
any construction operation that will necessitate lane or sidewalk closure or internal
traffic control signing.
(B) The third sentence of paragraph 2 of MnDOT 1404.7 (Winter Suspension) is hereby
revised as follows:
“In the event that any Contractor-owned traffic control devices are damaged or
destroyed making them ineffective for their intended use, the Contractor will
receive payment in the amount of the value of the traffic control device as
determined by the Engineer.”
S-26.3 General Requirements
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
18-S
(A) The Contractor shall have an additional ten (10) extra retroreflective drums stored, at a
convenient location within the Project limits, to be used at the discretion of the
Engineer.
(B) No access to or from any public road or at-grade crossing of any public road will be
permitted for the Contractor's equipment, material deliveries, the hauling of excavated
materials of any kind, or employees' private vehicles, except at in place public road
intersections, or at locations and in such manner as approved by the Engineer.
S-26.4 Temporary Pedestrian Access Control (2563)
This work shall consist of providing Temporary Access Control Plan. This plan shall
consist of identifying a Temporary Pedestrian Accessible Route (TPAR) and features
needed to assist pedestrian, bicyclists and non-motorized vehicles safe movement
within and around the construction zone. This work shall be done in accordance with
Contract provisions and the following:
The Contractor shall develop and provide for a continuous Temporary Pedestrian
Accessible Route (TPAR) for this Project. The TPAR shall clearly address all non-
motorized users in the construction zone. The Contractor shall submit this plan to the
Engineer for acceptance at the pre-construction meeting.
PEDESTRIAN ACCESS
(A) The TPAR must have a minimum width of 48 inches (4 feet) and guide
pedestrians through and/or around the Project by using devices such as signage,
barricades, and temporary curb ramps or blended transitions. The Contractor
may provide an alternate route that is accessible and within 2 block(s) offset of
the closed construction area. To the maximum extent feasible, the TPAR shall be
provided on the same side of the street as the disrupted route. Where the TPAR
is exposed to adjacent construction, excavation drop-offs, traffic, or other
hazards, it shall be protected with a pedestrian barricade or channelizing device.
All TPARs must have a smooth, level, slip-resistant surface and shall meet the
applicable requirements of the Public Right-of-Way Accessibility Guidelines
(PROWAG).
(B) The Contractor shall schedule and coordinate the replacement of the pedestrian
access to accommodate the needs of the business and residences. Existing
sidewalks shall be left in-place until such time that it is required to remove them
to accommodate new construction. Pedestrian access may be provided to
businesses and homes through the use of any public access from adjacent
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
19-S
parking lots and side streets. Front door access must be provided to buildings
without alternate public entrances. Where disrupted by construction, the
Contractor must provide a continuous TPAR for all areas disrupted construction
throughout all phases of construction.
(C) For technical provisions on TPAR, the Contractor is directed to the Guidelines for
Accessible Public Rights-of-Way at: http://www.access-
board.gov/prowac/draft.htm and Chapter 6D of the MnMUTCD. The pedestrian
accessibility checklist is on page 6D-5 and 6D-6 of the MnMUTCD. The Contractor
shall complete MnMUTCD Fig. 6D-1, “Pedestrian Accessibility Considerations in
Temporary Traffic Control Zones Check List”. A copy shall be provided to the
Engineer at the pre-construction meeting.
(D) The Contractor shall notify the Engineer in writing at least 72 hours prior to the
start of any construction operation that will necessitate a change in pedestrian
access.
Traffic control devices must allow for an accessible route through the Project. TPAR
pedestrian barricades and channelizing devices shall be continuous, stable, and non-
flexible and shall consist of a wall, fence, or enclosures. The base of any traffic control
devices shall be a continuous raised barrier of no more than 6 inches in height and must
allow for drainage. The purpose of this barrier is to provide a continuous wayfinding
device for the visually impaired, therefore the barrier shall not have any points that
might catch a person who is using a cane for a guide. The Devices shall provide a
continuous surface or upper rail at a minimum 3 feet above the ground or walkway
surface. Support members shall not protrude into the path. Whenever possible the
TPAR shall only utilize in-place street crossings. TPAR must be regularly inspected and
updated depending on Project staging.
No pedestrian curb ramp or blended transition work shall occur concurrently at adjacent
intersections.
The Contractor shall be responsible for maintaining the TPAR within this Project. The
Contractor shall furnish the name, addresses, and phone number of at least one
individual responsible for the placement and maintenance of TPAR. This individual shall
be "on call" 24 hours per day, seven days per week during the times any devices,
furnished and installed by the Contractor, are in place. The required information shall be
submitted to the Engineer at the pre-construction meeting.
The Contractor shall be expected to answer calls immediately and begin corrective
measures needed within one hour. If the Contractor is negligent in correcting the
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
20-S
deficiency within one hour of notification the Contractor shall be subject to a monetary
deduction at the rate of $100.00 per hour when only one residence or location is
affected and at the rate of $500.000 per hour in all other cases that the Engineer
determines the Contractor has not complied.
The Contractor is advised that the corridor has Transit service. Re-locations of stops can
only be made with the approval of the Engineer.
Only one side of the roadway may be disrupted at a time for pedestrian curb ramp,
blended transition, or sidewalk construction. Where it is not feasible to provide a same-
side TPAR and pedestrians will be detoured, the alternate route must provide a similar
level of accessibility to the existing route. This may include the incorporation of
accessible pedestrian signals (APS), curb ramps, or other accessibility features.
All traffic control required under this Contract for pedestrian access shall be performed
as incidental work for which no direct payment will be made.
The Contractor may ban parking within the construction limits with the approval of the
Engineer. All necessary signing is the responsibility of the Contractor and shall be
installed, as directed by the Engineer, 24 hours prior to the parking ban. The Contractor
shall remove that signing as soon as the work or that part of the work, in the area has
been completed.
26.4.1 Traffic Control Inspection Log
During the time that any traffic control devices, furnished and installed by the
Contractor, are in place, the Contractor shall provide a person on a daily basis to inspect
and ensure that all traffic control devices required are installed properly and conform to the MnMUTCD. Any discrepancy between the actual devices in use and the required
devices shall be immediately rectified.
This log shall also include the date and time any changes in the stages, phases, or
portions thereof go into effect. The log shall identify the location and verify that the
devices are placed as directed or corrected in accordance with the Plan. All entries in the log shall include the date and time of the entry and be signed by the person making
the inspection. The person or persons performing the inspection shall be required to
make a daily log (including weekends and holidays) of these inspections.
Copies of these logs must be submitted to the Engineer each Monday while there is traffic control on the Project. No payment for Traffic Control will be made until these
logs have been received and approved by the Engineer.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
21-S
26.4.2 Traffic Control Maintenance
The Contractor shall be responsible for the immediate repair or replacement of all traffic
control devices that become damaged, moved or destroyed, of all lights that cease to
function properly, and of all barricade weights that are damaged, destroyed, or otherwise fail to stabilize the barricades. The Contractor shall further provide sufficient
surveillance of all traffic control devices at least once every 24 hours.
In the event of severe weather conditions, the Contractor shall provide additional
personnel and equipment to maintain all traffic control devices.
The Contractor shall be required to respond to any call from the City Engineer, Engineer
or other City Staff concerning any request for improving or correcting traffic control
devices within one (1) hour from the time of notification. The Contractor shall be
subject to an hourly charge assessed at a rate of $100.00 per hour for each hour or portion thereof where the Engineer determines that the Contractor has not responded.
The Contractor shall maintain all traffic control at all times but particularly after storms,
at night, and on weekends with or without notice by the Engineer.
26.4.3 Vehicle Warning Light Specification
All Contractors’, subcontractors’ and suppliers’ mobile equipment, which are working in
the lane closure or within 4.5 m [15 feet] of the lane closure, shall be equipped with operable warning lights which meet the appropriate requirements of the SAE
specifications. This would include any vehicle which enters the traveled roadway at any
time. The SAE specification requirements are as follows:
360 Degree Rotating Lights – SAE Specification J845
Flashing Lights – SAE Specification J595
Flashing Strobe Lights – SAE Specification J1318
Lights shall be mounted so that at least one light is visible at all times when at eye level
from an 18 m [60 foot] radius about the equipment. This specification is to be used for
both day and night time operations. All costs incurred to provide warning lights shall be
at no cost to the Department. These warning lights shall be operating and visible when a
vehicle decelerates to enter a construction work zone and again when a vehicle leaves
the work zone and enters the traveled traffic lane.
Any warning lights shall be on the list of approved lights which may be obtained by
contacting:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
22-S
Vehicle Warning Lights
Office of Construction MS650
Transportation Bldg. OR by calling (651) 366-4216
395 John Ireland Blvd. St. Paul, MN 55125
This list is updated periodically. Warning light suppliers and manufacturers may contact
the above for information on adding new products to the list.
26.4.4 Flag Person (Flaggers)
Any person acting as a flagger on this Project shall have attended a training session
taught by a Contractor’s qualified trainer. The Contractor’s qualified trainer shall have
completed a “Mn/DOT Flagger Train the Trainer Session” in the five years previous to
the start date of this Contract and shall be on file as a qualified flagger trainer in the
Department. The Flagger Trainer’s name and Qualification Number shall be furnished
by the Contractor at the pre-construction meeting. The Contractor shall provide all flaggers with the Mn/DOT Flagger Handbook and shall observe the rules and regulations
contained therein. This handbook shall be in the possession of all flaggers while flagging
on the Project. The Contractor shall obtain handbooks from the Department. Flaggers
shall not be assigned other duties while working as authorized flaggers. The “Checklist
for Flagger Training” form shall be furnished to the Engineer anytime a new flagger
reports to work on the Project. The “Checklist for Flagger Training” form can be found at: http://www.dot.state.mn.us/const/wzs/documents/flaggertrainingchecklist.pdf
The Contractor shall furnish flag persons as required to adequately control traffic on
local streets. Flag persons shall conform to the requirements set forth in the MnMUTCD.
All costs incurred to provide such flag persons shall be incidental to the lump sum of traffic control. The Contractor shall provide two-way radios for flag persons.
Flag persons shall wear high visibility retro-reflective safety vests, pants and hats at all
times while actively flagging on the Project. High visibility apparel shall comply with
current Minnesota OSHA Rules 5207.0100 and 5207.1000. The flag persons clothing shall be considered an incidental expense for which no direct compensation will be
made.
Flag persons shall be equipped with a “Stop-Slow” paddle on a seven foot staff while
directing traffic.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
23-S
The Contractor will be subject to a non-compliant charge for failure to adhere to the
clothing requirements as listed above. Non-compliant charges, for each incident, will be
assessed at a rate of $ 500.00 per incident that the Engineer determines that the
Contractor has not complied.
Except as otherwise authorized by the Engineer, the maximum length of the flagging
operation shall be no more than 1.6 km [1 mile].
The Contractor shall coordinate the flagging operations in a manner which causes as little delay to the traveling public as possible, and at no time shall the delay exceed five
(5) minutes. In the event that the Contractor is unable to meet the maximum delay
requirements, operations shall shut down until such time a new traffic control plan is
developed which does meet the maximum delay requirement.
If hauling operations create hazards for the traveling public, the Contractor will be
required to provide additional flaggers, as directed by the Engineer. All costs incurred to
provide the additional flaggers shall be incidental to the lump sum traffic control.
The Contractor shall furnish off-duty police officers in uniform with cars and an orange reflectorized vest to direct the traffic if deemed necessary and so ordered by the
Engineer. “Police Officer” means every officer authorized to direct or regulate traffic or
to make arrests for violations of traffic rules. No direct payment for police officers will
be made; this work shall be incidental to the lump sum traffic control.
The Engineer will have the right to waive the above requirements.
26.4.5 Temporary Lane Closure Requirements
Unless otherwise authorized by the Engineer, any temporary lane closure extending to or beyond 300 m [1000 feet] shall have a minimum of one, Type III barricade placed in
the closed lane for every 300 m [1000 feet] of extension.
All temporary lane closures used at night shall have Type B Channelizers (plastic drum-like channelizers, Type I or Type II barricade) or Direction Indicator Barricade in the lane
closure taper and also in any shifts in traffic alignment.
Temporary lane closures will not be permitted during inclement weather, nor any other
time when, in the opinion of the Engineer, the lane closure will be a greater than normal hazard to traffic.
Temporary lane closures or other restrictions by the Contractor, during work hours and
consistent with the time restrictions, will be permitted during those hours and at those
locations approved by the Engineer. Requests for temporary lane closures shall be
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
24-S
made at least 24 hours prior to such closures. When a temporary lane closure is used by
the Contractor, the closure shall be incidental work and no direct compensation will be
made therefore.
26.4.6 Signal And Lighting Systems
The Contractor shall not interfere with the operation of any traffic signal system, except
as required by the Contract. The Contractor shall notify the Engineer at least 48 hours
prior to beginning any work that will interfere with any traffic signal system or its detectors.
During periods when an existing signal system is de-energized and the new signal
system is energized (or existing system is re-energized), the Contractor shall furnish,
erect, and maintain “Stop Ahead” signs and “Stop” signs. The quantity and size of the temporary signs as well as their placement in the field shall be as directed by the
Engineer. The Contractor shall furnish and install materials to keep these signs upright
and stationary. The signs shall remain the property of the Contractor.
The Contractor shall maintain street lighting by means of the in-place lights, the newly constructed lights, or a combination thereof, except as otherwise authorized in writing
by the Engineer.
26.4.7 Measurement and Payment
No measurement will be made of the various Items that constitute Traffic Control but all such work will be construed to be included in the single Lump Sum payment under Item
2563.601 (Traffic Control).
Traffic Control will be measured and paid for as follows:
Payment for furnishing, installing, maintaining, relocating and subsequently
removing traffic control devices (including flag persons) as required will be made
as a lump sum under Item 2563.601 (Traffic Control) and according to the
following schedule:
1) When 5 percent of the Contract amount is earned, 25 percent of the
amount bid for traffic will be paid.
2) When 10 percent, or more, of the Contract amount is earned, an
additional 15 percent of the amount bid for traffic control will be paid. 3) When 20 percent, or more, of the Contract amount is earned, an
additional 15 percent of the amount bid for traffic control will be paid.
4) When 30 percent, or more, of the Contract amount is earned, an
additional 15 percent of the amount bid for traffic control will be paid.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
25-S
5) When 50 percent, or more, of the Contract amount is earned, an
additional 15 percent of the amount bid for traffic control will be paid.
6) When 80 percent, or more, of the Contract amount is earned, an
additional 10 percent of the amount bid for traffic control will be paid.
7) The remaining 5 percent bid for traffic control will be paid when all work has been completed and accepted.
8) In all items above, the original contract amount shall be the total value of
all Contract Items including the traffic control item, but the percentage
earned in each case shall be exclusive of the traffic control item.
The lump sum payment(s) shall be compensation in full for all costs of furnishing, installing, maintaining, relocating, and removing the individual traffic control devices as
shown on the Traffic Control Layouts in the Plans and/or as specified in the Special
Provisions. The lumps sum shall also include any extra signing needed to facilitate
traffic.
If the Contractor requests changes in traffic control as shown on the Traffic Control Layout(s), and these change are implemented, there will be no increase or decrease in
the lump sum payment(s) for the stage(s) of traffic control.
Deductions in payment due to lack of maintenance records, poor maintenance, poor
device quality, or any other reason the Engineer deems reasonable are at the discretion
of the Engineer.
S-27. (1407) FINAL CLEANUP
The provisions of MnDOT 1407 are supplemented as follows:
During the progress of the work, the area affected shall be kept clean and free of all rubbish
and surplus materials. All unneeded construction equipment shall be removed from the site
and all damage repaired so that the public and adjacent property owners are inconvenienced as
little as possible.
Where materials or debris have washed or flowed into or have been placed in water courses,
ditches, gutters, drains, catch basins, or elsewhere as a result of the Contractor’s operations,
such material or debris shall be removed and satisfactorily disposed of during progress of work.
All ditches, channels, drains, etc., shall be kept in a clean and neat condition.
On or before the completion of work, the Contractor shall, unless otherwise directed in writing,
remove all temporary works, tools and machinery or other construction equipment. All rubbish
shall be removed from any grounds occupied by the Contractor. The Contractor shall leave all
of the premises and adjacent property affected by the operation in a neat and restored
condition satisfactory to the Engineer.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
26-S
S-28. (1504) COORDINATION OF PLANS AND SPECIFICATIONS Replace the first and second paragraphs of 1504 with the following “In case of discrepancy,
calculated dimensions will govern over scaled dimensions; Special Provisions will govern over
City of Bloomington General Specifications, Mn/DOT Standard and supplemental Specifications
and Plans; Plans will govern over City of Bloomington General Specifications, Mn/DOT Standard
and supplemental Specifications; City of Bloomington General Specifications will govern over
Mn/DOT Standard and supplemental Specifications; supplemental Specifications will govern
over Mn/DOT Standard Specifications”.
S-29. (1505) COOPERATION BY CONTRACTORS
Cooperation and coordination with other Contractors, and Utility Companies, working in the
area of this construction will be necessary for the successful completion of this Project.
The provisions of MnDOT 1505 are supplemented as follows:
Bidders are hereby advised that the following projects either have been let or will be let during
the anticipated time this Contract will be in effect. The successful bidder shall coordinate its
operations with those of the other Contractors on these projects:
A. PMP Street Improvement Project (City Project 2016-101)
B. PMP Street Maintenance Project (City Project 2016-102)
S-30. (1506) SUPERVISION BY CONTRACTOR
The provisions of MnDOT 1506 are supplemented as follows:
The Contractor will be subject to an hourly charge for failure to comply with the requirements
of MnDOT 1506. Non-Compliance charges, for each incident, will be assessed at a rate of $100
per hour, for each hour or portion thereof, during which the Engineer determines that the
Contractor has not complied. No charge will be made if the deficiency is corrected within one
(1) hour of notification.
An incident of Non-Compliance will be defined as the receipt of a written work order by the
Contractor with instructions to correct a deficiency.
The Contractor shall designate, in writing, who the competent superintendent and the
competent individual (i.e.: construction team leader or foreperson) will be for the Project. These
persons can only be changed during the Project by submission of a written authorization request
to the Engineer by the Contractor. The submittal of information (including a personal resume
and listing of other projects of similar magnitude where each has worked in a position of similar
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
27-S
responsibility, and current contact information for a direct supervisor on the projects listed)
regarding these persons and one back-up individual shall be submitted at the preconstruction
conference. These persons shall not be an operator or laborer. The competent individual shall
be available to the Project at all times and the competent superintendent will be required to be
on the site at least daily while working days are being assessed. The Engineer may decide to require the Superintendent to be on the site more frequently if necessary.
The Contractor shall furnish names, addresses, and phone numbers of at least three individuals
responsible for all aspects of maintenance (including traffic control devices) on the Project.
These individuals shall be “on call” 24 hours per day, seven days per week. The individual “on
call”, upon receiving notification of any deficiency, shall dispatch people, materials, and equipment to correct the deficiency within one hour of notification.
All of the above information shall be submitted to the Engineer at the Pre-Construction
Conference.
S-31. (1507) EXISTING UNDERGROUND UTILITIES
Construction operations in the proximity of utility properties shall be performed in accordance
with the provisions of MnDOT 1507, except as modified below:
The plan will indicate the quality level of the subsurface utility information according to the
guidelines of CI/ASCE 38-2 entitled “Standard Guidelines for the Collection and Depiction of
Existing Subsurface Utility Data”. If no quality level is indicated, the Contractor shall assume it
is quality level D. Every effort has been made to position and dimension all existing
underground utilities on the Plans. This information was obtained from the respective utility
companies and the City record plans. The City of Bloomington does not guarantee the locations
as shown on the Plans. It is the Contractor’s responsibility to ascertain the final location of
these utilities (including municipal water and sewer lines and appurtenances) and to notify the
utility companies when construction commences in each area. The Contractor shall contact
Gopher State One-Call (651-454-0002) at least 48 hours (excluding Saturdays, Sundays and
holidays) prior to any excavation.
It is the intent of this project to avoid in-place public and private utilities. New utility
installations as part of this project will cross existing utilities. Where utility crossings are
anticipated, the Contractor shall expose (pothole) the utility in question to determine whether
there will be a conflict with the proposed work before that work has started. No payment shall
be made for time delays due to utility conflicts or for this exploration. Restoration of surfacing
disturbed by utility potholing excavations shall be in accordance with the requirements of these
Special Provisions and the required Excavation and Work within the Right-of-Way Permits
described elsewhere in these Special Provisions.
The Contractor is responsible for the protection of all underground utilities, which are located
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
28-S
in the field or are shown on the plans. All damage to existing manholes, gate valves, curb stops,
etc. must be reported. The report shall be a written list detailing the location of the utility and
the damage discovered by the Contractor. The listing must be submitted before any work
begins or the Contractor will be held responsible for repairs. The Contractor is encouraged to
inspect such items before construction begins and must inform the Engineer in writing.
Boulevard areas may contain buried underground utilities that are not located by the Gopher
State One Call system. The most common type of this is adjacent private lighting systems and
irrigation systems. The Contractor shall contact adjacent property owners to assist in locating
these facilities if they are not located with the One Call system and it is reasonable to assume
that they exist in the boulevard. The Contractor may need to provide and operate locating
equipment to facilitate the locating effort (incidental). The Contractor shall protect these
utilities (incidental) or the City shall issue a Work Order to move the facilities. If the Contractor
does not make a reasonable effort to contact the property owner and protect the facility,
damages caused by the Contractor will be the responsibility of the Contractor.
Cooperation and coordination with other Contractors, and Utility Companies, working in the
area of this construction will be necessary for the successful completion of this project.
S-32. (1513) RESTRICTIONS ON MOVEMENT AND STORAGE OF HEAVY LOADS AND
EQUIPMENT
The provisions of Mn/DOT 1513 are hereby deleted and replaced with the following:
The hauling or storage of materials and/or the movement and storage of equipment to and
from the Project and over completed structures, base courses, and pavements within the
Project that are open for use by traffic and are to remain a part of the permanent
improvement, shall comply with the regulations governing the operation of vehicles on the
highways of Minnesota, as prescribed in the Highway Traffic Regulation Act.
The Contractor shall comply with legal load restrictions, and with any special restrictions
imposed by the Contract, in hauling or storing materials, moving or storing equipment on
structures, completed subgrades, base courses, and pavements within the Project that are
under construction, or have been completed but have not been accepted and opened for use
by traffic.
The Contractor shall have a completed Weight Information Card in each vehicle used for
hauling bituminous mixture, aggregate, batch concrete, and grading material (including
borrow and excess) prior to starting work. This card shall identify the truck or tractor and
trailer by Minnesota or prorated license number and shall contain the tare, maximum
allowable legal gross mass, supporting information, and the signature of the owner. The card
shall be available to the Engineer upon request. All Contractor-related costs in providing,
verifying, and spot checking the cab card information (including weighing trucks on certified
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
29-S
commercial scales, both empty and loaded) will be incidental, and no compensation other
than for Plan pay items will be made.
Equipment mounted on crawler tracks or steel-tired wheels shall not be operated on or across
concrete or bituminous surfaces without specific authorization from the Engineer. Special
restrictions may be imposed by the Contract with respect to speed, load distribution, surface
protection, and other precautions considered necessary.
Should construction operations necessitate the crossing of an existing pavement, bridges or
completed portions of the pavement structure with equipment or loads that would otherwise
be prohibited, approved methods of load distribution or bridging shall be provided by the
Contractor at no expense to the Department.
Neither by issuance of a special permit, nor by adherence to any other restrictions imposed,
shall the Contractor be relieved of liability for damages resulting from the operation and
movement of construction equipment.
S-33. (1516) ACCEPTANCE OF WORK
Upon completion of the items of the Contract the Contractor shall notify the Engineer, in
writing, that the Work is “Substantially Complete”, as defined in S-46. If the Engineer agrees
that the Work is “Substantially Complete”, the Engineer will promptly make a thorough
inspection and prepare a punch list, setting forth items that are not acceptable or
incomplete. The Contractor shall coordinate all subcontractors to achieve prompt
completion of the punch list.
The Contractor shall not be relieved of the responsibility to provide Contract items left off of
the Engineer's punch list. When the punch list has been prepared, the Engineer will, when
requested by the Contractor, arrange a meeting with the Contractor to identify and explain
all punch list items and answer questions on work which must be done before final
acceptance.
The Engineer may revise the punch list, from time to time, to ensure that all items of work are
properly completed. The Contractor may make a request for additional releases of retainage
when portions of the Work listed on the Engineer's punch list have been satisfactorily
completed.
Assessment of calendar charges for the punch list will begin on the day following receipt of the
punch list. Liquidated damages will be assessed as per Section S-47 1807 (FAILURE TO
COMPLETE THE WORK ON TIME) of these Special Provisions.
S-34. (1601) SOURCE OF SUPPLY AND QUALITY
The provisions of MnDOT 1601 are supplemented as follows:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
30-S
In conformance with the provisions of the U.S. Code of Federal Regulations 23CFR635.410 the
Contractor will furnish and use only steel and iron materials that have been melted and
manufactured in the United States,. Foreign source materials are any domestic products taken
out of the United States for any process (e.g. change of chemical content, permanent shape or
size, or final finish of product).
All bids must be based on furnishing domestic iron and steel, which includes the application of
the coating, except where the cost of iron and steel materials incorporated in the work does
not exceed one-tenth of one percent of the total Contract cost or $2,500.00, whichever is
greater. The state may approve the use of foreign iron and steel materials for particular
Contract items, provided the bidder submits, a stipulation identifying the foreign source iron
and/or steel product(s) and the estimated invoice cost of the product(s), for one or more of the
Contract bid items. The Contractor shall submit a "Stipulation for Foreign Iron or Steel
Materials" form for each stipulation with the Contractor's proposal. If the Contractor chooses
to use ANY non-domestic iron or steel, the Contractor must submit a stipulation with the
proposal.
Prior to performing work the Contractor shall submit to the Engineer a certification stating that
all iron and steel items supplied are of domestic origin, except for non-domestic iron and steel
specifically stipulated and permitted in accordance with the paragraph above.
S-34.1 Source Supply and Quality
MnDOT 1604 is supplemented as follows:
All costs of shop inspection at plants outside the United States shall be borne by the Contractor.
Monies due or to become due the Contractor will be reduced according to these costs.
S-34.2 Partial Payment
All provisions for partial payments shall apply to domestic materials only. The Contractor will
not receive payment for materials manufactured outside of the United States until such
materials are delivered to the job site.
S-34.3 Alternative Bidding Process
Unless an alternate bidding process is specified, use of foreign steel and iron products in
quantities in greater than provided above is not permitted. When the alternate bidding process
is permitted the Contract may be awarded to the bidder who submits the lowest total bid
based on furnishing domestic iron or steel unless such total bid exceeds the lowest total bid
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
31-S
based on foreign materials by more than 25 percent.
S-35. (1701) LAWS TO BE OBSERVED - CARGO PREFERENCE ACT; USE OF UNITED STATES -
FLAGGED VESSELS
The provisions of 1701 are supplemented with the following:
S-35.1 The Contractor must utilize privately-owned United States-flag commercial vessels to
ship at least 50% of the gross tonnage whenever shipping any equipment, material, or
commodities pursuant to this Contract. This requirement applies only to the extent that
such U.S.-flag vessels are available at fair and reasonable rates. Compute gross tonnage
separately for dry bulk carriers, dry cargo liners, and tankers. The term “pursuant to this
Contract” means this provision applies to materials or equipment acquired for this
specific Project. Materials used for highway construction generally originate from
existing inventories rather than being acquired solely for a specific project. For
example, the requirements generally do not apply to shipments of Portland cement,
asphalt cement, or aggregates, as suppliers and contractors use these materials to
replenish existing inventories. But, the Cargo Preference Act does apply if any material
or equipment is acquired solely for this specific Project.
S-35.2 The Contractor must furnish a legible copy, in English, of a rated, “on-board”
commercial ocean bill of lading for each shipment of cargo described in clause S-35.1.
The Contractor must provide the bill of lading to the Department and to the following:
Division of National Cargo
Office of Market Development
Maritime Administration
Washington DC, 20590
The Contractor must provide the bills of lading no later than 20 days after the date of
loading for shipments originating within the U.S.A., or no later than 30 days after the
date of loading for shipments originating outside the U.S.A.
S-35.3 The Contractor must include or incorporate this provision in all subcontracts.
S-36. (1702) PERMITS, LICENSES, AND TAXES
The Contractor shall be required to obtain and pay for all permits for this project unless
otherwise specified in these Special Provisions. All permits required, shall be construed to be
part of the Special Provisions. The conditions, requirements and restrictions of these permits
shall be binding on the Contractor’s operation under this Contract.
The following permits are anticipated to be required for the project:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
32-S
S-36.1 Hennepin County
This project will require a permit(s) for work in the Hennepin County Right-of-Way.
The City shall be responsible for completing the permit application, obtaining final permit
approval, and providing all required permit fees, bonds, and supplemental information for the
Hennepin County Right-of-Way permit.
The Contractor is advised that Hennepin County may have additional conditions, requirements
and restrictions to complete the work. It shall be the Contractor’s responsibility to meet these
conditions. No additional compensation or project completion extension will be granted to
accomplish the conditions of the permits.
S-36.2 MnDOT
This project will require a permit(s) for work in the MnDOT Right-of-Way.
The City shall be responsible for completing the permit application, obtaining final permit
approval, and providing all required permit fees, bonds, and supplemental information for the
MnDOT Right-of-Way permit.
The Contractor is advised that MnDOT may have additional conditions, requirements and
restrictions to complete the work. It shall be the Contractor’s responsibility to meet these
conditions. No additional compensation or project completion extension will be granted to
accomplish the conditions of the permits.
S-36.3 Electrical Permits
The Contractor shall submit application(s) for electrical permit(s) that satisfy all State of
Minnesota and City of Bloomington laws, rules, and requirements. It shall be the Contractor’s
responsibility to meet all permit conditions.
Bidders are advised that compliance with the provisions of MnDOT Spec. No. 1702, MnDOT
Spec. No. 2545.2A, and the first paragraph of MnDOT Spec. 2545.3A will be enforced in
conjunction with the construction of any kind of electrical system, conduit, or conduit system
for the conveyance of electrical conductors, or the required portions thereof, as specified in the
Contract.
The Minnesota Electrical Act requires that a permit be obtained for the performance of all such
work, including the installation of conduits. Contact the City of Bloomington Building and
Inspection Department, Electrical Division (952-563-8930) for Bloomington requirements.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
33-S
When ready for energizing, the Contractor shall call the City of Bloomington Building and
Inspection Department, Electrical Division (952-563-8930) for inspection and approval.
The Contractor shall be responsible for completing all permit applications, obtaining final
permit approval, and providing all required permit fees, bonds, and supplemental information
for the Electrical Permits.
S-37. (1704) TRENCH RESTORATION AND BACKFILL/SURFACE RESTORATION
The Contractor is directed to Chapter 17, Article IV and Section 17.71 of the City of
Bloomington’s Code (amended by ordinance No. 98-54). This article and code section references certain street pavement restoration requirements for work in the right-of-way.
These requirements are made a part of this contract. To obtain a copy, contact City Offices or
visit the City’s website at www.ci.bloomington.mn.us.
Restoration Standards for the City of Bloomington streets are divided into four categories: Red,
Black, Blue and Green. The following table shows the restoration requirements for each category.
Red Black Blue Green
(Pavement
(Pavement 5 yrs
old (In 5 year project (Current year
0 to 5 yrs old) to plan) project plan)
5 yrs project plan)
Trench Hole Trench Hole Trench Hole Trench Hole
Restoration 1 or 2 7 3 or 4 8 5 9 6 10
Std. Plate No.
Length of Nearest Nearest Nearest Nearest 2' 2' Trench Trench
Restoration crack or crack or crack or crack or overcut overcut length length
2' 2' 2' 2' only only
overcut overcut overcut overcut
(City (City (City (City
Option) Option) Option) Option)
Width of Lane Lane Lane Lane 2' 2' Trench Hole
Restoration width to width to
width
to
width
to overcut overcut length length
nearest nearest nearest nearest only only
curb, curb, curb, curb,
joint or joint or joint or joint or
crown crown crown crown
Special Sealcoat Sealcoat None None None None None None
Modifications curb to curb to
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
34-S
curb for curb for
one one
block* block*
*The Contractor may elect to forgo the sealcoat and pay the fee to the City for the City Maintenance Forces to perform this sealcoat.
The compaction test requirement for all categories shall be one (1) test for any portion of the
initial 50 SF of excavated area and one (1) test for each 250 SF (or part thereof) beyond the
initial 50 SF. The test shall be performed once for every four (4) feet of vertical zone depth from
the bottom.
All edges shall be saw cut and tack sealcoat applied prior to the installation of plant mixed
bituminous pavement meeting the requirements elsewhere in this specification.
All costs for furnishing, placing, and shaping street patches as a result of Contractor damage
shall be at the Contractor’s expense.
Contact the City of Bloomington at (952) 563-4633 for a current copy of the map showing the
current color category status of each street.
S-38. (1706) EMPLOYEE HEALTH AND WELFARE
The provisions of Mn/DOT 1706 are supplemented with the following:
All construction operations shall be conducted in compliance with the applicable laws,
regulations, and industry standards as described in Mn/DOT 1706. The Contractor shall be
considered to be fully responsible for the development, implementation and enforcement of all
safety requirements on the Project, notwithstanding any actions the City of Bloomington may
take to help ensure compliance with those requirements.
A copy of the Contractor’s written safety program shall be submitted for review at the Pre-
Construction Conference. At a minimum, the Contractor must have an established
AWAIR/Safety Program containing the following:
• Right to Know • Personal Protective Equipment
• Respiratory Protection
• Hearing Conservation
• Lockout/Tagout
• Permit-Required Confined Space Entry
• Fire Protection • Blood Bourne Pathogens
• Trenching & Excavating
• Mobile Earth Moving Equipment
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
35-S
This safety program shall contain name(s) of person(s) responsible for all safety requirements
and/or the Contractor’s Designee(s) shall be available at all times that work is being performed.
The Contractor’s designee(s) shall be responsible for correcting violations on the Project as
observed by the Engineer or designated representative.
The Contractor is hereby advised that the City of Bloomington has determined that all existing
manholes, catch basins, and similar type enclosed structures on storm sewer systems, water
distribution systems, and sanitary sewer systems contained within the right of way of all
roadways and within the construction limits of this Project are confined spaces and access into
them shall be in accordance with the MINN.RULE5207.0300-0304. All new structures of the
same type and function of the aforesaid which are to be constructed as a part of this Project shall also be considered confined spaces and access into them shall be in accordance with the
OSHA Regulation 29 CFR 1910. Further, the Contractor shall be required to abide by the Permit-
Required Confined Space Policy and Contractor Safety and Health Policy of the City of
Bloomington, in addition to the 29 CFR 1910 Occupational Safety & Health Administration
(OSHA) and Minnesota Rules 5207.
It shall be the sole responsibility of the Contractor to have a confined entry program which
complies with OSHA. The Contractor’s program shall address, but need not be limited to,
access into manholes, catch basins, and similar type enclosed structures on storm sewers,
water distribution systems, and sanitary sewer systems that are to be constructed,
reconstructed, adjusted, repaired, or otherwise modified as part of this Project. The
Contractor’s program shall establish acceptable entry conditions for the various classifications of confined spaces (e.g. CLASS I, CLASS II.) identified in OSHA Regulation 29 CFR 1910.146. The
Contractor shall have an adequately trained individual who shall be responsible for classifying
each confined space in accordance with the Contractor’s confined space entry program, and
ensuring compliance with same by all of the Contractor’s employees and all other individuals
within the Contractor’s control entering confined spaces on this Project. The Contractor shall
develop and implement site-specific procedures to coordinate entry operations when employees of more than one employer are or will be working simultaneously in a confined
space.
The Contractor’s confined entry program shall clearly address its applicability to all
subcontractors and their employees that will be utilized for this Project. It shall be the
Contractor’s responsibility to ensure compliance with OSHA by all subcontractors and their employees on this Project either through the Contractor’s own program or through separate
programs established by the subcontractors working on this Project.
The Contractor shall be responsible for initiating, maintaining, and supervising all safety
precautions required in connection with their work on this Project, including regulations of the
Occupational Safety and Health Administration (OSHA) and other regulatory and governing agencies.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
36-S
The City of Bloomington assumes no responsibility or liability for the Contractor’s compliance
with applicable federal and state regulations and safe work practices. The Contractor shall
remain at all times solely responsible for the sufficiency of its safety program and its
compliance with applicable federal and state regulations.
The Contractor shall not use any motor vehicle equipment on this Project having an obstructed
view to the rear unless:
(A) The vehicle has a reverse signal alarm which is audible above the surrounding noise
level; or
(B) The vehicle is backed up only when an observer signals that it is safe to do so.
A $500.00 monetary deduction (per incident) will be assessed by the City of Bloomington Safety
Officer for violations of safety standards and requirements that have the potential for loss of
life and/or limb of Project personnel or the public. The areas of special concern include, but are
not limited to excavation stability protection, fall protection, protection from overhead hazards, vehicle backup protection, confined space safety, blasting operations, and personal safety
devices.
None of the monetary deductions listed above shall be considered by the Contractor as
allowance of noncompliance incidents of these safety requirements on this Project.
S-39. (1707) PUBLIC CONVENIENCE AND SAFETY
Metro Transit and Minnesota Valley Transit Authority (MVTA) have bus service in the area that
will be affected by this project. The Contractor shall notify the Engineer ten (10) days prior to
the date of any traffic changes that may affect transit service, and fifteen (15) days prior to the
date of requiring relocation of any transit facility.
S-40. (1710) TRAFFIC CONTROL
Transits stops, commercial property and other pedestrian generators exist in the South Loop
District and elsewhere within the project. Some of these pedestrians have special needs,
including some with disabilities. The Contractor is reminded that MnMUTCD Part 6 outlines the
various requirements for pedestrian and ADA requirements in temporary traffic control zones.
These requirement include, but are not limited to:
• Pedestrian facilities will need to be separated from the work site by appropriate
barriers that maintain the accessibility and detectability for pedestrians with
disabilities.
• Signs and other devices mounted lower than 7 feet above the temporary pedestrian
pathway should not project in to the accessible pedestrian facility.
• Barricade rail supports should not project into pedestrian circulation routes more
than 4 inches from the support between 27 inches and 80 inches from the surface.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
37-S
• Continuous edging may be required to delineate a pedestrian pathway throughout
the facility so a long cane can follow it, if the pedestrian pathway is not otherwise
distinguishable.
• A smooth, continuous hard surface that will not cause tripping or restrict wheel chair
use will need to be provided.
• A minimum width of 5 feet throughout the entire length of the pedestrian pathway
is required. If it is not possible to provide and maintain this width, a 5 foot x 5 foot
passing space should be provided at least every 200 feet to allow individuals in
wheelchairs to pass. In no case shall the width of the pedestrian pathway be less
than 3 feet.
S-40.1 Temporary Lane Closure Requirements
Work which will restrict or interfere with traffic shall not be performed between 12:00 noon
on the day preceding and 9:00 A.M. on the day following any consecutive combination of a
Saturday, Sunday and legal holiday.
Lane closures on City and County streets may be restricted to hours between 9 AM and 3 PM.
Unless otherwise approved by MnDOT, and the City of Bloomington, temporary lane closures
on MnDOT roadways shall be in accordance with allowable lane closures identified in the
current version of the Lane Closure Manual except as modified by this section of the special
provisions:
http://www.dot.state.mn.us/metro/trafficeng/laneclosure/index.html
For this project, the Lane Closure Manual shall be modified as follows:
- Where day time lane closures are allowed in the Lane Closure Manual, they shall occur
on Monday through Friday only for this project. No day time lane closures will be
allowed on MnDOT roadways on Saturdays and Sundays.
- Where night time lane closures are allowed in the Lane Closure Manual, they will be
limited to Sunday, Monday, Tuesday, and Wednesday nights of the week, in addition
to other restrictions specified in the Lane Closure Manual or in these Special
Provisions.
The Engineer will have the right to lengthen, shorten, or otherwise modify the foregoing
periods of restrictions as actual traffic conditions may warrant. If the Contractor is negligent in
adhering to the established time schedules, the Contractor shall be subject to an hourly
charge assessed at a rate of $500.00 per hour for each hour or any portion thereof with which
the Engineer determines that the Contractor has not complied.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
38-S
Temporary lane restrictions and/or closures for removing and/or erecting overhead structures
will only be permitted between the hours identified in the Lane Closure Manual and as
approved by the Engineer. If the Contractor requests to close the road and the Engineer
approves that it is necessary to temporarily detour traffic in order to remove or set the
structures, the Contractor shall furnish the detour as directed by the Engineer. The temporary
detour shall be incidental work for which no direct compensation will be made. If the
Contractor is negligent in adhering to the established time schedules, the Contractor shall be
subject to an hourly charge assessed at a rate of $500.00 per hour for each hour or any
portion thereof with which the Engineer determines that the Contractor has not complied.
The Contractor may stop all traffic on any road open to traffic to erect or remove overhead
structures for periods of time not to exceed fifteen minutes only from 1:30 A.M. to 5:00 A.M. or
as allowed in the Lane Closure Manual, whichever is more restrictive. The Contractor shall
allow sufficient clearance time between stopped periods so as to cause as little delay to traffic
as possible. If the Contractor is negligent in adhering to the established time schedules, the
Contractor shall be subject to an hourly charge assessed at a rate of $500.00 per hour for each
hour or any portion thereof with which the Engineer determines that the Contractor has not
complied.
No center lane closures will be permitted. Only double lane closures as shown in the Field
Manual of the MN MUTCD will be allowed at the times as directed by the Engineer. This may
require night lane closures if traffic volumes warrant.
The Contractor shall furnish off-duty police officers in uniform with cars and an orange
reflectorized vest to direct traffic if deemed necessary and so ordered by the Engineer. "Police
Officer" means every officer authorized to direct or regulate traffic or to make arrests for
violations of traffic rules. This shall be incidental work for which no direct payment will be
made.
Flag persons may be required during these restrictions in traffic flow. Exclusive of these times,
two minimum of 11’ wide lanes of traffic (or width stated on the plan) shall be kept open at all
times on city streets. Lane widths on MnDOT roadways shall match existing widths. No lane
width reduction will be allowed without prior approval by the Engineer.
S-40.2 Portable Changeable Message Signs
A Portable Changeable Message Sign (PCMS) shall be provided in advance of each temporary
lane closure on MnDOT roadways to communicate real time information.
(PCMS) Type C Trailer Mounted Message Signs will be permitted and shall be on the qualified
products list for portable changeable message signs as found at:
http://www.dot.state.mn.us/products/workzone/electronic.html. It is imperative that the
Contractor continually operate each PCMS at maximum legibility. Many factors, such as
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
39-S
mechanical problems, insufficient charging, incorrect intensity settings, or other factors can
degrade performance. If at any time the Contractor fails to operate a PCMS at maximum
legibility, as determined by the Engineer, no payment will be made for each day that the
Message Sign is deemed inadequate.
Except as approved by the Engineer, the message sign shall be stored off the shoulder when not
in use. In the event the Engineer allows the message board to remain on the shoulder the
message sign shall be delineated according to Layout 4 (Partial Shoulder Closure) in the field
manual, as determined by the Engineer.
All costs incurred to provide Portable Changeable Message Signs shall be incidental work for
which no direct compensation will be made.
S-40.3 Temporary Signs
All temporary rigid signs shall be fabricated with an approved retroreflective sheeting material
of the appropriate color, and be listed on the Qualified Product Listing (QPL) for either
“Sheeting for Rigid Signs” or “High Performance Sheeting for Rigid Signs”. Signs remaining in-
place that still apply during temporary operations need no change in sign sheeting.
To visually identify approved retroreflective sign sheeting on temporary rigid signs in the field
signs shall have an easily identifiable marking on the face. This marking verifies that the sign
sheeting is Approved for Rigid Sign Use as found on the APL. Although still required to meet
sheeting standards, temporary rigid signs 4 sq. feet and under in size and all barricades and
route markers will be exempt from this marking. The appropriate marking shall be used for
each type of the approved sheeting types, consisting of Type IX and Type HP (also marked as
DG3). Refer to the instructions for the marking of temporary signs which may be found on the
APL or directly at the following link:
http://www.dot.state.mn.us/products/signing/common/typelabel.pdf
The retroreflective sheeting types and qualified products used for temporary signs and
barricades can be found at: http://www.dot.state.mn.us/products/signing/sheeting.html.
S-41. (1710) TRAFFIC CONTROL DEVICES
All traffic control devices and methods shall conform to the Minnesota Manual on Uniform
Traffic Control Devices (MN MUTCD), Minnesota Standard Signs Manual Parts I and II, the
Traffic Engineering Manual, and the following:
On any roadway having a 45 mph or higher speed limit prior to construction, all Category I and
II temporary traffic control devices used after July 1, 2006 shall meet NCHRP 350 crash testing
criteria. This includes all new and used Category I and Category II devices. Category I devices
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
40-S
include tube markers, plastic drums and cones, etc. Category II devices include portable sign
supports, Type I ,II and III barricades, etc.
One any roadway having a speed limit between 0-40 mph, all Category II temporary traffic
control devices used after January 17, 2010 shall be considered crashworthy which is defined as
“a characteristic of a roadside appurtenance that has been successfully crash tested in
accordance with a national standard such as the National Cooperative Highway Research
Program Report 350, ‘Recommended Procedures for the Safety Performance of Highway
Features’” and meet the requirements of MN MUTCD.
The Contractor is hereby advised that the MN MUTCD requires that all signs shall meet the
NCHRP 350 crash testing criteria.
The Contractor shall provide the Engineer a Letter of Compliance stating that all of the
Contractors Category I and II Devices are NCHRP 350 approved as of July 1, 2006. The Letter of
Compliance must also include approved drawings of the different signs and devices and shall be
provided to the Engineer at the Pre-construction meeting.
All traffic signs requiring removal due to construction operations shall be neatly stored and
protected on site by the Contractor and remain until reinstalled by the Contractor. If the
Contractor damages any sign during the salvage operation, and the Engineer determines that
the damaged sign cannot be reused, the Contractor shall dispose of the damaged sign and
furnish a new replacement sign in accordance with the applicable fabrication specifications at
no cost to the City. No payment will be made for either the salvaging or reinstallation of the
signs unless specifically listed as a pay item.
S-42. (1712) TREE PROTECTION
When excavation for any reason is required near any trees, that excavation must be done by
hand methods so the damage to the roots is held to a minimum.
The Engineer may direct the Contractor to protect trees that remain in place within the
construction area with snow fencing placed at the outer limits of the branches (drip line) before
work begins.
If any roots are damaged they must be cut off cleanly and smoothly, and immediately painted
with an approved tree paint. If the trunk or a limb of a tree is inadvertently damaged, it must
immediately be repaired as directed by the Engineer.
There is no pay item for tree protection on this Project. All work shall be incidental work for
which no direct compensation will be made.
S-43. (1714) RESPONSIBILITY FOR DAMAGE CLAIMS
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
41-S
Responsibility for damage claims shall be in accordance with the provisions of MnDOT 1714,
except as modified as follows:
The Contractor shall indemnify, defend and save harmless the City of Bloomington, the
County of Hennepin, their officers, agents and employees from all suits, actions, and
claims of any character brought because of injuries or damages received or sustained by
any person, persons, or property on account of the operations of the said Contractor; or
on account of or in consequence of any neglect in safeguarding the work; or through use
of unacceptable materials in constructing the work; or because of any act or omission,
neglect, or misconduct of said Contractor; or because of any claims arising or amounts
recovered from infringements of patent, trademark, or copyright; or because of any
claims arising or amounts recovered under the Workers Compensation Act; or under
any other law, ordinance, order, or decree.
In addition to the insurance requirements listed in Section 36 of the General Specifications the
Contractor shall provide the following insurance coverage. If a discrepancy arises between the
General Specification and these Special Provisions, the higher limit or more restrictive condition
shall govern.
Responsibility for damage claims shall be in accordance with the provisions of MnDOT 1714,
except as modified as follows:
S-43.1 Commencement of Work
In the event any work to be performed under this Contract is further sublet, Contractor will
require the same insurance coverage, additional insured endorsements (ISO CG 20 10 1985
version or equivalent) and limits from its subcontractors, and will require said subcontractors
to certify insurance coverage to the City and County as outlined above (including at any time
certified copies of all insurance policies and endorsements), prior to the commencement of
any work.
Notwithstanding any other provision of this Agreement to the contrary, no officer, employee
or agent of the City is authorized to cause, suffer, or permit the Contractor or any of its
employees, guests, agents, subcontractors, or suppliers to commence or perform any work or
otherwise enter upon the project site unless and until all of the conditions of this Article have
been conformed to and performed.
The Contractor shall not commence work until it has obtained required insurance and filed
with the City a properly executed Certificate of Insurance which clearly evidences the required
insurance coverages. The certificate shall name City of Bloomington as the certificate holder,
and shall also name Hennepin County and the City of Bloomington as additional insureds for
the Commercial General Liability coverage with respect to operations covered under the
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
42-S
Contract. The certificate should also show that City of Bloomington will receive 30 days prior
written notice in the event of cancellation, nonrenewal, or material change in any described
policies.
The Contractor shall furnish to the City updated certificates during the term of the Contract as
insurance policies expire. If the Contractor fails to furnish proof of insurance coverages, the City
may withhold payments and/or pursue any other right or remedy allowed under the Contract,
law, equity, and/or statute.
S-43.2 Other Liability Policy Requirements
The Contractor shall maintain insurance with these provisions:
Except as to Workers’ Compensation, Employers’ Liability and Professional Errors & Omissions
insurance, the City and County shall be named as additional insured under ISO form CG 20 10
1985 version or the equivalent as approved by City. The City and County as an additional
insured shall have all the rights, coverages, and limits afforded the Contractor under the
policies. In the event that any insurer issues a reservation of rights for City and County as an
additional insured, City and County shall be entitled to employ independent counsel at
Contractor’s expense.
For all insurance policies required or referenced in this agreement, Contractor agrees to
waive and shall require all Contractors of every tier to waive all subrogation rights on behalf
of itself and it’s insurers (or in the alternative to secure the waiver of subrogation from its
insurers) against City and County and all of City and County’s employees and agents.
That Contractor’s insurance is primary and any insurance maintained by City or County is
considered excess and non-contributory. This provision in no way waves the tort liability
caps stated in Minn Stat. § 466, as may be amended from time to time.
Liability insurance policies (except for professional errors and omissions) must be a claims
occurrence policy form, and not a claims made type of policy.
The City must approve the insurance companies and all insurance companies shall maintain at
all times a rating of A- or higher by A.M. Best. It shall be considered a material breach of this
contract if at any time before, during or after completion of the project as required in this
agreement for Contractor or any of its subcontractor’s insurance to be cancelled, non-renewed,
reduced in coverage below that required in this agreement, or an insurance carrier rating is
reduced below an A- as rated by A.M. Best (and Contractor has not obtained qualifying
alternative insurance from an approved carrier).
S-43.3 Removal of Liens
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
43-S
Any liens filed on a project which are not promptly removed constitute a default. To remove
a lien the Contractor is required to post a bond, deposit money, or meet any other statutory
requirement.
S-43.4 Partial Occupation by Owner
Whenever it may be useful or necessary, Contractor, City or County shall be permitted to
occupy and use any portion of the work which has been either partially or fully completed by
Contractor before final inspection and acceptance there by City, but such use or occupation
shall not relieve Contractor of its guarantee of said work and materials nor of its obligation to
make good at its own expense any defect in materials and workmanship which may occur or
develop prior to Contractor’s release from responsibility to the City.
S-43.5 Right to Audit
As to all work which the Contractor may perform on a reimbursable basis or for which
Contractor makes a claim for additional compensation or for which a claim is asserted by any
third party or injured person the City will have the right at all reasonable times and places, to
inspect, copy and audit any of Contractor’s books, accounts, time cards, records of transactions,
estimates, schedules, correspondence or any other records or documents which may have a
possible bearing on the performance of such work of claim.
Further right of examination for all of Contractor’s work will include inspection at all reasonable
times of the Contractor’s plant, or such parts thereof as may be engaged in the performance of
the contract. All accounts, documents and records relevant to this contract will be retained by
the Contractor for three years after completion of the work, unless a longer period is required
by law.
S-43.6 Preservation of Evidence
Contractor should be required to give the City notice as soon as any type of accident, incident,
or claim is asserted against Contractor or Owner and to preserve all evidence and to allow the
City the opportunity to fully investigate all incidents prior to any evidence being moved,
altered, covered up or destroyed in any manner.
S-43.7 Contract Obligations To Survive Performance
Obligations, including but not limited to, construction defect claims, personal injury claims,
warranty claims and maintaining insurance, of the Contractor shall continue in place and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
44-S
shall survive as long as any contractual obligation exists.
S-44. (1717) AIR, LAND AND WATER POLLUTION
The provisions of MnDOT 1717 are supplemented and/or modified with the following:
S-44.1 Discovery of Contaminated Materials and Regulated Wastes
If during the course of the Project, the Contractor unexpectedly encounters any of the
following conditions indicating the possible presence of contaminated soil, contaminated
water, or regulated waste, the Contractor shall immediately stop work in the vicinity, notify
the Engineer, and request suspension of work in the vicinity of the discovery area, in
accordance with MnDOT 1803.4.
A documented inspection and evaluation will be conducted prior to the resumption of
work. The Contractor shall not resume work in the suspected area without
authorization by the Engineer.
(A) Indicators of contaminated soil, ground water or surface water include, but are not
limited to the following:
i. Odor including gasoline, diesel, creosote (odor of railroad ties),
mothballs, or other chemical odor.
ii. Soil stained green or black (but not because of organic content), or with a
dark, oily appearance, or any unusual soil color or texture.
iii. A rainbow color (sheen) on surface water or soil.
(B) Indicators of regulated wastes include, but are not limited to the following:
i. Cans, bottles, glass, scrap metal, wood (indicators of solid waste and a
possible dump)
ii. Concrete and asphalt rubble (indicators of demolition waste).
iii. Roofing materials, shingles, siding, vermiculite, floor tiles, transite or any
fibrous material (indicators of demolition waste that could contain
asbestos, lead or other chemicals).
iv. Culverts or other pipes with tar-like coating, insulation or transite
(indicators of asbestos).
v. Ash (ash from burning of regulated materials may contain lead, asbestos
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
45-S
or other chemicals).
vi. Sandblast residue (could contain lead).
vii. Treated wood including, but not limited to products referred to as green
treat, brown treat and creosote (treated wood disposal is regulated).
viii. Chemical containers such as storage tanks, drums, filters and other
containers (possible sources of chemical contaminants).
ix. Old basements with intact floor tiles or insulation (could contain
asbestos), sumps (could contain chemical waste), waste traps (could
contain oily wastes) and cesspools (could contain chemical or oily
wastes).
S-45. IMPLEMENTATION OF CLEAN AIR ACT AND FEDERAL WATER POLLUTION CONTROL
ACT
By signing this bid form, the bidder will be deemed to have stipulated as follows:
(A) That any facility to be utilized in the performance of this Contract, unless such Contract
is exempt under the Clean Air Act, as amended (42 U.S.C. 1857 et seq., as amended by
Pub. L. 91-604), and under the Federal Water Pollution Control Act, as amended (33
U.S.C. 1251 et seq., as amended by Pub. L. 92-500), Executive Order 11738, and
regulations in implementation thereof (40 C.F.R. Part 15), is not listed on the U.S.
Environmental Protection Agency (EPA) List of Violating Facilities pursuant to 40 C.F.R.
15.20.
(B) That the City of Bloomington shall be promptly notified prior to Contract award of the
receipt by the bidder of any communication from the Director, Office of Federal
Activities, EPA, indicating that a facility to be utilized for the Contract is under
consideration to be listed on the EPA List of Violating Facilities.
S-46. (1803;1806) SCHEDULE, COMPLETION DATE, EXECUTION AND APPROVAL OF
CONTRACT
The first sentence of the third paragraph of 1803.5 shall hereby be deleted and replaced with
‘No work shall be performed on Sundays or Legal Holidays of the City of Bloomington without
permission from the Engineer.
The Contractor's construction schedule, list of subcontractors, supervision resumes and references,
and list of suppliers shall be presented for the Engineer's approval at the Pre-construction
Conference.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
46-S
S-46.1 Project Start Date, City Approval Period, Notice of Contract Approval
The Contractor shall have a maximum of seven (7) calendar days to sign the contract books and
submit bonds and insurance after the contract is awarded at the City Council. The City shall have a
maximum of five (5) calendar days (City Approval Period) to review the bonds and insurance and sign
the contract books after the Contractor has signed the books and submitted the bonds. When the
City approves the bonds and insurance and signs the contract books, a Notice of Contract Approval
will be issued. The Notice of Contract Approval will be mailed and e-mailed to the Contractor within
the 5-day City Approval Period. The date of the Notice of Contract Approval shall be the date the
notice is mailed and e-mailed to the Contractor. The Contractor is required to start work on the
contract within five (5) days after the date of the Notice of Contract Approval.
S-46.2 Completion Dates
This Contract shall be a completion date contract.
Substantial Completion
All work under this Contract, including: underground conduits and cables, vaults, enclosures,
cabinets, foundations, traffic signal revisions, sign panels, walkways, traffic barrier, patching of
bituminous and concrete surfaces, and turf restoration work, shall be substantially completed by
September 15, 2017.
Final Completion
All work under this Contract, including final cleanup, shall be completed by September 29, 2017.
S-47. (1807) FAILURE TO COMPLETE THE WORK ON TIME
In lieu of making a precise determination of actual damages incurred, the Contractor will be
assessed a daily charge in the amount stipulated, not as a penalty but as liquidated damages to
compensate for the additional costs incurred.
Should the Contractor fail to complete all work by the required Intermediate and Substantial completion dates allowed, the appropriate amount listed in MnDOT Table 1807-1 shall be
deducted from monies due. This amount will continue to be assessed until the work is
substantially complete. These amounts shall be deducted as liquidated damages for each day
exclusive of Sundays and US Government Holidays.
Fourteen (14) calendar days shall be allowed for final clean up. Should the Contractor fail to complete final clean up work within fourteen calendar days of the substantial completion date,
the appropriate amount listed in MnDOT Table 1807-1 shall be deducted from monies due.
This amount will continue to be assessed until final clean up is complete to the satisfaction of
the Engineer. These amounts shall be deducted as liquidated damages for each day exclusive of
Sundays and US Government Holidays.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
47-S
S-48. (1903) COMPENSATION FOR INCREASED OR DECREASED QUANTITIES
The provisions of MnDOT 1903 are modified as follows:
The provisions of MnDOT 1903 are modified to the extent that Contract unit prices for the
following items shall not be modified for increased or decreased quantities.
• Remove Concrete Walk
• 4” Concrete Walk
• 1.5” Non-Metallic Conduit
• 2” Non-Metallic Conduit
• 3” Non-Metallic Conduit
• 4” Non-Metallic Conduit
• Power Cable 1 Conductor No. 6
• CAT 6 Cable
• Fiber Optic Pigtail Cable (6SM)
• Pre-term/Armor Fiber Optic Pigtail (6SM)
• Fiber Optic Trunk Cable (12SM)
• Fiber Optic Trunk Cable (24SM)
• Fiber Optic Trunk Cable (48SM)
• 1.5” Bored Conduit
• 3” Bored Conduit
• Reroute Cable
• Sodding Type Salt Resistant • Select Topsoil Borrow
S-49. (1904) EXTRA AND FORCE ACCOUNT WORK
Extra and force account work shall be in accordance with MnDOT 1904. The provisions of
MnDOT 1904 are supplemented and/or modified with the following:
The Contractor is required to submit force account work itemized statements of costs in accordance with MnDOT 1904 to the Engineer on MnDOT form TP-21659 (Summary of Daily
Force Account). Copies of this form can be obtained from the Engineer.
S-50. (1910) FUEL ESCALATION CLAUSE
The provisions of MnDOT 1910 are hereby deleted and replaced with the attached Fuel
Escalation Clause.
S-51. (2104) REMOVAL OF PAVEMENT AND MISCELLANEOUS STRUCTURES
This work shall consist of removing structures, such as sidewalks and other miscellaneous
structures. Abandoned structures and other obstructions shall be removed from the Right of
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
48-S
Way and disposed of in accordance with the provisions of MnDOT 2104, except as modified
below:
All material specified to be salvaged and not reinstalled on the Project shall be carefully
removed and hauled to the City of Bloomington property at 10500 Hampshire Avenue South
within 24 hours of removal. It is required that a City of Bloomington Engineering Division
Representative be present when items are delivered to verify delivery, storage location, and
handling care of the Contractor. If an item specified to be salvaged and reinstalled cannot be
reused due to damage caused by the Contractor, the Contractor shall notify the Engineer
before proceeding with the reinstallation. The Contractor shall notify the City of Bloomington
Engineering Division (952-563-4914) at least three (3) normal working days in advance of the
time the Contractor intends to deliver the salvaged materials.
All traffic signs requiring removal due to construction operations shall be neatly stored and
protected on site by the Contractor and remain until reinstalled by the Contractor. If the
Contractor damages any sign during the salvage operation, and the Engineer determines that
the damaged sign cannot be reused, the Contractor shall dispose of the damaged sign and
furnish a new replacement sign in accordance with the applicable fabrication specifications at
no cost to the City. No payment will be made for either the salvaging or reinstallation of the
signs unless specifically listed as a pay item.
Sawing of sidewalks needed for removal shall be incidental.
The Contractor shall dispose of all waste material and debris, and shall notify the Engineer of
the disposal area prior to the work. No waste material or debris shall be deposited on any
public or private property within the City limits of Bloomington without written permission of
the Engineer. Waste material and debris shall include, but not be limited to, trees, stumps, pipe,
concrete, asphalt concrete, cans, or other waste material from the construction operations.
When excess suitable material is mixed with waste material, the Contractor shall segregate
these materials and dispose of them separately when directed by the Engineer or as other
guidelines govern.
Measurement and payment for the removal and disposal of materials will be made only for
those Items of removal work specifically included for payment as such in the Proposal and as
listed in the Plans. The removal of any unforeseen obstruction requiring in the opinion of the
Engineer equipment or handling substantially different from that employed in excavation
operations, will be paid for as Extra Work as provided in MnDOT 1403.
S-52. (2105) SELECT TOPSOIL BORROW
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
49-S
S-52.1 Select Topsoil Borrow
Select topsoil borrow shall be in accordance with the provisions of 2105 and the following:
Topsoil shall meet the requirements of Mn/DOT Specification 3877 for Select Topsoil Borrow.
In addition, topsoil shall be pulverized and free of heavy clay, coarse sand, stones, plants, roots,
sticks and other foreign materials.
A test report from an approved reputable testing company will be required prior to delivery of
any topsoil and shall include an analysis of soil nutrient levels and recommendations for plant
nutrient applications (the University of Minnesota Soils Testing Laboratory provides an
excellent nutrient analysis and recommendation). The analysis and recommendations shall
include soil gradation and texture, pH, percent of organic matter, extractable Phosphorus
(P2O5) (lbs/acre), exchangeable Potassium (K20) (lbs/acre) and soluble salts (M hos). Imported
topsoil not meeting pH requirements will not be accepted.
Fertilizers (incidental) shall be applied and tilled into the 4” of topsoil, as required by the test
report, in place before sodding. No sod shall be placed on chemically treated soil until sufficient
time has elapsed to permit dissipation of all toxic material.
Topsoil salvaged on site for use on this Project shall meet all the requirements set forth herein
for Select Topsoil Borrow. Even if salvaged topsoil is used, the Contractor shall be paid the
amount placed for Select Topsoil Borrow, given that it passes the requirements specified
herein.
S-52.2 Measurement and Payment
Furnishing and installing Select Topsoil Borrow as contained in these Specifications and in the
Plans will be measured and paid in accordance with the provisions of MnDOT 2105.526, Select
Topsoil Borrow (LV).
S-53. (2461) STRUCTURAL CONCRETE REVISED 02/07/17
MnDOT 2461 is hereby modified as follows: S-1.1 MnDOT 2461.2.A.5 shall be added:
A.5 Ternary Mixes
Ternary mixes are defined as portland cement or Type IL and two other supplementary cementitious materials, or blended cement and one other supplementary cementitious material with a maximum replacement of 40% by weight.
S-1.2 MnDOT 2461.2.B shall be deleted and replaced with the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
50-S
B Aggregates
Provide aggregates from sources listed on the MnDOT Concrete Aggregate Properties list.
B.1 ............................................................................................................................................................. Fine
Aggregate................................................................................................................................................................ 3126
B.2 ............................................................................................................................................... Intermediate
Aggregate................................................................................................................................................................ 3131
B.3 ......................................................................................................................................................... Coarse
Aggregate................................................................................................................................................................ 3137
S-1.3 MnDOT 2461.2.C shall be deleted. S-1.4 MnDOT 2461.2.D shall be modified to include the following:
Provide water from potable sources.
The Concrete Engineer will allow clarified water as a substitution for potable water in accordance with the following:
(1) From the Approved/Qualified Products list, (2) In any concrete defined as MnDOT Grades B, F, G, M, P, and R, (3) Up to a maximum of 50.0% of total mix water by weight, (4) Provided the clarified water is identified separately on the Certificate of Compliance.
S-1.5 MnDOT 2461.2.E shall be deleted and replaced with the following:
E ........................................................................................................................................................ Concrete
Admixtures ............................................................................................................................................................. 3113
Provide admixtures from the Approved/Qualified Products list for all concrete grades shown in Table 2461-6 and Table 2461-7.
Use of any of the following admixtures are at the Contractor’s discretion:
(1.1) Type A, Water Reducing Admixture (1.2) Type B, Retarding Admixture (1.3) Type D, Water Reducing and Retarding Admixture (1.4) Type F, High Range Water Reducing Admixture (1.5) Type G, High Range Water Reducing and Retarding Admixture (1.6) Type S, Specific Performance Based Admixture
Use of the following accelerating admixtures require approval of the Concrete Engineer, in
conjunction with the Engineer, unless otherwise allowed in the Contract:
(2.1) Type C, Accelerating Admixture (2.2) Type E, Water Reducing and Accelerating Admixture
The Engineer will permit the use of Type C or Type E accelerating admixtures when all of the
following conditions exist:
(3.1) The ambient temperature is below 36 °F, (3.2) An Engineer approved cold weather protection plan is in-place, and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
51-S
(3.3) Cold weather protection materials are on-site and ready for use. S-1.6 Table 2461-1 of MnDOT 2461.2.F.1 shall be deleted and replaced with the following:
Table 2461-1
Mix Number Identification
First Digit Second
Digit Third Digit Fourth Digit
Additional
Digits
Type Designation
Grade Designation
Maximum Slump
Coarse Aggregate Gradation
Designation
Additional Digits Allowed or as
Specified S-1.7 MnDOT 2461.2.F.1.b shall be deleted and replaced with the following:
F.1.b Grade Designation
The Department will designate concrete grade in accordance with Table 2461-6 and Table 2461-7 using a letter designating the following:
(1) Intended Use (2) Maximum water/cement (w/c) ratio (3) Maximum Cementitious Content (4) Maximum Supplementary Cementitious Substitution (SCM) (5) Slump range (6) Minimum 28-day compressive strength, f’c (7) Coarse Aggregate Quality in accordance with 3137
S-1.8 MnDOT 2461.2.F.1.d shall be deleted and replaced with the following:
F.1.d Coarse Aggregate Gradation Designation
Select the appropriate coarse aggregate gradation designation in accordance with Table 2461-3 based on the intended use and the gradation requirements in 3137, “Coarse Aggregate for Portland Cement Concrete.”
Table 2461-3
Coarse Aggregate Designation for Concrete
Designation Coarse Aggregate Gradation
0 Job Mix Formula (JMF) combination of fine and coarse aggregate
Table 3137-4, “Coarse Aggregate Designation for Concrete”
1 ASTM #467
2 ASTM #67
3 ASTM #7
4 ASTM #89
7 CA-70
8 CA-80 S-1.9 MnDOT 2461.2.F.1.e shall be deleted and replaced with the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
52-S
F.1.e Additional Concrete Mix Designation Digits
Specialty concrete mixes require additional concrete digits in accordance with Table 2461-6. Use “EX” for exposed aggregate mixes and “CO” for colored concrete mixes. The Contractor may add additional digits to the right of the required digits in the concrete mix number.
S-1.10 MnDOT 2461.2.F.2, 2461.2.F.2.a, and 2461.2.F.2.b shall be deleted and replaced with the following:
F.2 Concrete Mix Design Requirements
The Engineer determines final acceptance of the concrete for payment based on test results, satisfactory field placement and performance.
F.2.a Department Designed Concrete Mixes
The Department will provide mix designs for the concrete defined in Table 2461-4 and Table 2461-5.
F.2.a(1) Department Designed Concrete Requirements
No additional submittal is required for Table 2461-4 mix designs.
Table 2461-4
Department Designed Concrete Mixes
Type of Concrete Mix Number Specification Mix Design Location
Field Batched Patching Mix 3U18 2302 Table 2302-1 Low Slump Concrete 3U17A 2404 Weekly Report of Low Slump Concrete Bagged Patching Mix 3U18 and 3U58M 3105 Table 3105-1
F.2.a(2) Grout and Lean Mix Backfill
Submit final mix design proportions on the General Concrete Mix Design Submittal for Grout and Lean Mix Backfill in accordance with Table 2461-5.
Table 2461-5
Concrete Mix Design Requirements for Grout and Lean Mix Backfill Mixes
Mix
Number
Maximum
w/c ratio
Water
Content
(pounds)
Cement
Content
(pounds)
Fly Ash
Content
(pounds)
Fine
Aggregate
Calculation (pounds)
Coarse
Aggregate
Calculation
(pounds)
%Air
Content
Slump
Range
Minimum
28-day
Compressive
Strength, f’c
1AGROUT* 0.50 379 758 0 100% † 0 3.0% As
needed 4000 psi
3AGROUT * 0.44 379 865 0 100% † 0 10.0
% As
needed 4000 psi
Lean Mix ǁ 1.00 375 125 250 50% † 50% † ǂ N/A 10 in ± 1 in 75 – 400 #
* Do not provide grout containing coarse aggregate or fly ash. ǁ Coarse Aggregate Quality meets requirements of 3137.2.D.1, “Coarse Aggregate for General Use” † After adding the specified quantities of cement, fly ash, and water, provide the remaining aggregate to an
absolute volume of 27.00 – 27.27 cu. ft. ǂ Meeting ASTM #67 gradation as shown in Table 3137-4. # Unconfined compressive strength range.
F.2.b Contractor Designed Concrete Mixes
The Contractor will provide concrete mix designs for concrete defined in Table 2461-6 and Table 2461-7 and elsewhere as specified in the Contract.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
53-S
The Contractor assumes full responsibility for the mix design and performance of the concrete.
F.2.b(1) General Concrete Mix Design Requirements
The Department defines the concrete mix design requirements for Contractor Designed Mixes in accordance with Table 2461-6.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
54-S
Table 2461-6
Concrete Mix Design Requirements (Not applicable to Mass Concrete)
Concrete Grade
OLD
Mix
Number
NEW
Mix
Number
Intended Use *
Maximum
w/c ratio
†
Maximum
Cementitious
Content (lbs/yd3)
Maximum %SCM
(Fly Ash/
Slag/Ternary)
Slump
Range
Minimum 28-day
Compressive
Strength, f’c
3137
Spec.
B
Bridge
Substructure
3Y43 3B52 ‡ Abutment, stems, wingwalls, paving brackets, pier columns and caps, pier struts 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.1
F
Flatwork
3A22 3Y22 3F32 ‡ Slipform curb and gutter 0.42 750 30/35/0 ½ - 3” # 4500 psi 2.D.1
3A32 3Y32 3A34
3F52 ‡ 3F52EX 3F53EX
3F52CO ║
Sidewalk, curb and gutter, slope paving, median sidewalk, driveway entrances, ADA pedestrian
sidewalk
0.45 750 25/30/0 2 - 5” 4500 psi 2.D.1
G
General Concrete
1A43 1G52 ‡ Footings and pilecap 0.55 750 30/35/40 2 - 5” 4500 psi 2.D.1
3A43 3B42 3Y43
3G52 ‡
Footings, pilecap, walls, cast-in-place manholes and catch basins, fence posts, signal bases, light pole
foundations, erosion control structures, cast-in-place box culverts, culvert headwalls, open flumes, cast-in-
place wall stems
0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1
M
Median Barrier
3Y12 3M12 Slipform barrier, Median barrier, non-bridge 0.42 750 30/35/40 ½ - 1” # 4500 psi 2.D.1 3Y32 3M52 Barrier, Median barrier, non-bridge 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1
P
Piling 1C62 1P62 ‡ Piling, spread footing leveling pad 0.60 750 30/35/40 3 - 6” 3000 psi 2.D.1
R
Pavement
Rehabilitation
3A32 3B42 3R52 ‡ CPR - Full depth concrete repairs, concrete base 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.3
S
Bridge
Superstructure
3Y16 3S12 Slipform bridge barrier, parapets, end post 0.42 750 30/35/40 ½ - 1” # 4000 psi 2.D.2 3A32 3A42 3Y43 3Y46
3Y46A
3S52 Median barrier, raised median, pilaster, curb,
sidewalk, approach panel, formed bridge barrier, parapet, end post, collar
0.45 750 30/35/40 2 - 5” 4000 psi 2.D.2
X
Miscellaneous
Bridge
1X62 1X46 1X62 Cofferdam seals, rock sockets, drilled shafts 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1
3X46 3X62 Drilled shafts above frost line 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1
Y
Bridge Deck
§
3Y33 3Y33A 3Y36
3Y36A
3Y42-M 3Y42-S
Bridge decks, integral abutment diaphragms, pier continuity diaphragms, expansion joint replacement
mix
0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2
3A37 3Y37 3Y47 ** Deck patching mix 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2
* If the intended use is not included elsewhere in the Specification or Special Provisions, use mix 3G52, unless otherwise directed by the Engineer. ║ Identify specific color used on the certificate of compliance. Colored concrete is only allowed when specified in the plans or the Contract. † The minimum water/cement (w/c) ratio is 0.30. ‡ The Contractor may choose to use the Coarse Aggregate Designation “1” for the 4th digit in accordance with Table 2461-3. # Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement. § The “-S” indicates a bridge deck with a structural slab and “-M” indicates a monolithic bridge deck. ** Mix 3Y47 requires the use of Coarse Aggregate Designation “7” or “3” for the 4th digit in accordance with Table 2461-3.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
55-S
F.2.b(2) High-Early Concrete Mix Design Requirements
The Department defines High-Early (HE) concrete as concrete designed to achieve the minimum strength of 3000 psi for opening at 48 hours. Unless otherwise included in the plans, all HE concrete requires approval of the Engineer prior to incorporation into the work.
The Engineer will allow one of the following methods to determine minimum time to opening:
(1) Field control cylinders in accordance with 2461.3.G.5.c, “Field Control Strength Cylinders.” (2) Maturity method in accordance with 2461.3.G.6, “Estimating Concrete Strength by the Maturity
Method.”
The Department defines the concrete mix design requirements for High-Early concrete in accordance with Table 2461-7.
Table 2461-7
High-Early (HE) Concrete Requirements
(Not applicable to Bridge Superstructure or Mass Concrete)
Mix
Number
Concrete
Grades
Allowed
Minimum
Time to
Opening
Maximum
w/c ratio
Maximum
Cementitious
Content
(lbs/ yd3) *
Slump
Range
Minimum
Strength
to
Opening
Minimum
28-day
Compressive
Strength, f’c
3137
Spec.
3HE32 F 48 hrs 0.42 750 1 – 3” ║ 3000 psi 4500 psi 2.D.1
3HE52 B, F, G 48 hrs 0.42 750 2 – 5” 3000 psi 4500 psi 2.D.1
3YHE52 Y
(Repairs Only)
48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.2
3RHE52 R
(Repairs Only)
48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.3
* Supplementary Cementitious Materials allowed. ║ Adjust slump in accordance with 2461.3.G.7.a,”Concrete Placed by the Slip-form Method.”
F.2.b(3) Project Specific Mix Design Requirements
Submit project specific contractor designed mixes on the Project Specific Mix Design Submittal forms in accordance with Table 2461-8 and the Contract.
Table 2461-8
Project Specific Contractor Designed Mixes
Concrete
Grade Intended Use Specification 3137 Spec.
A Concrete Pavement 2301 2.D.3 W and Y Precast Concrete 2462 Varies
HPC High Performance Concrete Special Provision 2401 2.D.2 MC Mass Concrete Special Provision 2401 Varies
CLSM Cellular Concrete Grout 2519 None
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
56-S
S-1.11 MnDOT 2461.2.F.3 shall be deleted and replaced with the following:
F.3 Submittal Requirements
At least 21 calendar days before initial placement of the concrete, submit the appropriate General Concrete
Mix Design Submittal form to the Concrete Engineer for approval. The Contractor Mix Design Forms are available from the MnDOT Concrete Engineering Website.
Design the concrete mix to an absolute volume of 27.00 – 27.27 cu. ft.
The Concrete Engineer will:
(1) Provide specific gravity and absorption data using oven dry (OD) weights for mix design
calculations. (2) Review the mix design submittal and approve the materials and mix design for compliance with
the Specifications.
Table 2461-8 defines the mix design submittal requirements for Level 1 and Level 2 Mixes.
Table 2461-9
Mix Design Submittal Requirements
SCM Substitution Limits
Fine Aggregate
Limit
Gradation Requirements
Preliminary Test Data
Requirements Submittal Package
Level 1 Mixes
*
Fly Ash: 0 – 15% Slag: 0 – 35%
40 – 45% of total aggregate
by volume 3126 and 3137 None General Concrete Mix
Design
Level 2 Mixes
Fly Ash: > 15% Ternary: Any
None
Use Either: • 3126 and 3137 • Job Mix
Formula (JMF)
2461.2.F.3.a
Use Either: • General Concrete
Mix Design • General Concrete
Mix Design (JMF) * High Early concrete in accordance with Table 2461-7 is defined as a Level 1 Mix.
S-1.12 MnDOT 2461.2.F.3.a, 2461.2.F.3.a(1) and 2461.2.F.3.a(2) shall be deleted and replaced with the following:
F.3.a Preliminary Test Data Requirements for Level 2 Mixes
For Level 2 Mixes, submit the proposed Mix Design Proportions on the General Concrete Mix Design
Submittal based upon either a suitable experience record or conventional trial mixtures not to exceed the limits specified in Table 2461-6 or 2461-7.
F.3.a(1) Suitable Experience Record
A suitable experience record consists of at least 30 consecutive tests, or two groups of consecutive tests totaling at least 30 tests, within the previous 18 months. If the Contractor does not have 30 tests, the Concrete Engineer will consider a minimum of 10 test results representing a time period of at least 45 days.
The Concrete Engineer considers a suitable experience record to have the following characteristics as
compared to the proposed mix:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
57-S
(1) Average compressive strength (f’cr) meeting the required 28-day compressive strength and no greater than 1000 psi above the required 28-day compressive strength,
(2) Same type or grade of cementitious materials, (3) Same class of coarse aggregate, (4) Aggregate weights within 10% of the proposed, (5) Water/Cement ratio no greater than the maximum allowed, (6) Cementitious or SCM material weights within 5% of proposed, and (7) Batching conditions and testing procedures similar to those expected for the proposed work.
Submit all test results on the Strength Test Data sheet as part of the Contractor Mix Design Submittal.
The Concrete Engineer reserves the right to request batching data representing the suitable experience
record submittal.
F.3.a(2) Conventional Trial Mixtures
If the Contractor does not have a suitable experience record as required in 2461.2.F.3.a(1) above, establish concrete proportions from trial mixtures, utilizing an AMRL accredited laboratory in accordance with the following:
(a) Use proportions and consistencies required for proposed work at the w/c ratios or cementitious
materials content that will produce a strength meeting or exceeding the required 28-day compressive strength (f’c) in accordance with Table 2461-6 or 2461-7;
(b) Design trial mixtures to produce slump within ± 0.75 in. of maximum permitted; (c) For air-entrained concrete, design trial mixtures to produce air content within ± 0.5 percent of
maximum allowable air content; (d) For each w/c ratio or cementitious materials content, make and cure at least three test cylinders for
28-day breaks in accordance with ASTM C 192. For HE concrete mixes, in addition to the 28-day cylinders, make a set of three test cylinders for 48-hour breaks in accordance with ASTM C 192.
Submit all test results for the trial mixtures, certified by the AMRL accredited laboratory, in addition to the
Contractor Mix Design Submittal. S-1.13 Table 2461-11 of MnDOT 2461.2.F.4 shall be deleted and replaced with the following:
Table 2461-11
Mix Design Adjustments Requirements
Type of Change or Adjustment Mix Design Resubmittal Requirements
Level 1 Mixes
• Cementitious Sources • Admixture Sources • Admixture Dosage Rate
No resubmittal required
• Aggregate Sources • Aggregate Proportions • Any cementitious or SCM proportion (≤ 15% max
fly ash)
Resubmittal of Mix Design
• Any cementitious or SCM proportion (> 15% max fly ash)
Resubmittal in accordance with 2461.2.F.3.a
Level 2 Mixes
• Admixture Dosage Rate • Cement or SCM sources
No resubmittal required
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
58-S
• Aggregate Source, no change in Aggregate Class • ≤ 5% in any cementitious or SCM proportion* • ≤ 10% in Aggregate Proportions
Resubmittal of Mix Design
• Aggregate source and Class of Coarse Aggregate • > 5% in any cementitious or SCM proportion • > 10% Aggregate Proportions • Admixture Sources
Resubmittal in accordance with 2461.2.F.3.a
* Only one (1) increase in cementitious or SCM allowed per mix design, next adjustment requires resubmittal in accordance with 2461.2.F.3.a, “Preliminary Test Data Requirements for Level 2 Mixes”
S-1.14 MnDOT 2461.2.G shall be deleted. S-1.15 The first paragraph of MnDOT 2461.3.A.9 shall be deleted and replaced with the following:
Provide horizontal axial-revolving blade type mixers (single or multiple shaft) in accordance with the applicable requirements for conventional type mixers in accordance with 2461.3.A.1 through 2461.3.A.7 and this subsection.
S-1.16 The first sentence of MnDOT 2461.3.D.1.c shall be deleted and replaced with the following:
Separately measure each type of mixing water on scales or water metering devices containing the following:
S-1.17 The fifth paragraph of MnDOT 2461.3.D.2 shall be deleted and replaced with the following:
Provide and use only sacked cement in the original mill containers unless the Contractor calibrates the mixer for the specific materials in use. Do not use previously opened sacks.
S-1.18 MnDOT 2461.3.F.1.a(2) shall be deleted and replaced with the following:
(2) The Producer will complete MnDOT Form 2163, Concrete Plant Contact Report, prior to the on-site inspection with the Department Representative. (2.1) A MnDOT Certified Concrete Plant Level 1 or 2 Technician, representing the Producer,
signs the Concrete Plant Contact Report certifying compliance with the Certified Ready Mix requirements and continual maintenance of the plant to assure that the plant can produce concrete meeting MnDOT Specifications.
(2.2) A MnDOT Certified Concrete Plant Level 1 or 2 Technician, representing the Department, signs the Concrete Plant Contact Report signifying that the plant complies with all requirements prior to concrete production.
S-1.19 MnDOT 2461.3.F.1.a(3) shall be deleted and replaced with the following:
(3) Include a site map showing stockpile locations identified with the MnDOT pit number. S-1.20 MnDOT 2461.3.F.1.b shall be deleted and replaced with the following:
F.1.b Maintaining Plant Certification
The Producer will maintain plant certification by:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
59-S
(1) Displaying the current Contact Report and site map in plain sight at all times; (2) Updating the Contact Report with any material or equipment changes and submitting to the
Department; (3) Sampling and testing the materials in accordance with this section and the requirements of the
Schedule of Materials Control; (4) Documenting the production and testing of the materials used in the certified ready-mix concrete
in the QC Workbook; (5) Making Producer Plant QC Workbook and QC charts available electronically at all times; (6) Supplying the following information at the request of the Engineer:
(6.1) Approved mix design sheets, (6.2) Agency cementitious and admixture test results, (6.3) Agency verification gradation test results, (6.4) Aggregate quality test results.
Any procedural changes that cause non-compliance with this program may result in de-certification of the
plant and cessation of further production of Department concrete as determined by the Concrete Engineer in accordance with 2461.3.F.4.h, “Certified Ready-Mix Plant Decertification.”
S-1.21 MnDOT 2461.3.F.2 shall be modified to include the following:
(21) For colored concrete, final color S-1.22 The definition for “Mix design water” and “Batch water” in Table 2461-13 of MnDOT 2461.3.F.3 shall be deleted and replaced with the following:
Table 2461-13
Certified Ready-Mix Terminology
Term Definition
Mix design water The maximum allowable water content for 1 cu. yd of concrete.
Batch water Water actually batched into the truck by the batcher. Batch water includes potable water and clarified water.
S-1.23 MnDOT 2461.3.F.4(7) shall be deleted and replaced with the following:
(7) Take cementitious and admixtures samples per Schedule of Materials Control. (8) Document the following samples in the appropriate Sampling Log:
(8.1) Cementitious Materials (8.2) Admixtures (8.3) Verification Gradations (8.4) Coarse Aggregate Quality
S-1.24 MnDOT 2461.3.F.4.b. 2461.3.F.4.c, 2461.3.F.4.d, and 2461.3.F.4.e shall be deleted and replaced with the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
60-S
F.4.b Sampling and Testing
Take all samples randomly in accordance with ASTM D 3665, Section 5, at a rate defined in accordance with the Schedule of Materials Control. Perform all sampling and testing in accordance with the Concrete Manual. The Engineer may oversee the QC sampling and testing process.
Perform QC gradation and moisture testing at the certified ready-mix plant site. Use mechanical shakers
for sieve analysis. Determine the moisture content using the oven-dry method in all fractions of the aggregate.
Provide equipment and perform calibrations meeting the requirements of the following:
(1) AASHTO T 27, “Sieve Analysis of Fine and Coarse Aggregates,” (2) AASHTO T 255, “Total Moisture Content of Aggregate by Drying,” (3) AASHTO M 92, “Wire-cloth Sieves for Testing Purpose,” and (4) AASHTO M 231, “Weighing Devices Used in the Testing of Materials.”
F.4.c QC Gradations
Complete the Concrete Aggregate Worksheet for each aggregate size and source:
(1.1) QC gradations; (1.2) Verification Companion Gradations; The Engineer will not allow a Verification Companion
Gradation as a substitute for a QC Gradation.
Identify QC companion samples with the following information:
(2.1) Date, (2.2) Test number, (2.3) Time, (2.4) Type of material, (2.5) Plant, and (2.6) Sampling location.
F.4.d Aggregate Gradation QC Charts
Complete the MnDOT Aggregate Gradation Control Charts for each aggregate size and aggregate source:
(1) Record Producer QC gradation and Department Verification Companion gradation results. These results are included in the moving average calculation.
(2) Record Department Verification Gradation results. These results are not included in the moving average calculation.
F.4.e Moisture Content
Complete the Batching Report for each aggregate size and source. S-1.25 MnDOT 2461.3.F.4.g shall be deleted and replaced with the following:
F.4.g Signing the Certificate of Compliance
The Producer’s MnDOT Certified Plant Level 1 or Level 2 technician will:
(1) Review the first Certificate of Compliance for each mix type, each day, for accuracy; and (2) Legibly hand sign the Certificate of Compliance at a location designated for Producer signature
signifying agreement to the terms of this program and to certify that the materials comply with the requirements of the Contract; and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
61-S
(3) Write their MnDOT Technical Certification Number next to their signature. S-1.26 MnDOT 2461.3.F.4.h shall be deleted and replaced with the following:
F.4.h Certified Ready-Mix Plant Decertification
The Concrete Engineer, with coordination from the Engineer, may decertify the plant and halt production of concrete under any of the following conditions:
(1) Unauthorized procedural, material, or equipment changes made after the completion of the
Concrete Plant Contact Report, (2) Failure to meet the required testing rates, (3) Failure to complete required documents, (4) Disregards any of the requirements of this section, and (5) Falsification of test records or certificates of compliance.
S-1.27 MnDOT 2461.3.F.5 shall be deleted and replaced with the following:
F.5 Quality Assurance (QA)
The Engineer’s responsibilities include the following:
(1) Confirm the Producer’s QC Workbook and aggregate gradation quality charts are accurate and up-to-date;
(2) Check Certificate of Compliance for completeness and accuracy; (3) Spot check the actual batching of concrete to verify batch weights and tolerances; (4) Check the bins and stockpiles for segregation, contamination, and interblending of the aggregates; (5) Obtain Aggregate Quality samples per Schedule of Materials Control; (6) Observe Producer’s Certified Technician obtain aggregate samples and run gradation and moisture
tests when possible; (7) Verify cement, fly ash, and admixtures are certified and approved; (8) Obtain cement, fly ash, and admixtures samples per the Schedule of Material Control; (9) Provide the following test results to the Producer in a timely manner:
(9.1) Cementitious Materials (9.2) Admixtures (9.3) Verification Gradations (9.4) Coarse Aggregate Quality
S-1.28 The first paragraph of MnDOT 2461.3.G.1 shall be deleted and replaced with the following:
Notify the Engineer at least 24 h before beginning concrete production to allow the Engineer time to provide inspection forces needed for the work and to approve preparations for concrete placement. If the Contractor fails to provide 24 h notice, the Engineer may delay concrete placement and will consider any concrete incorporated into the work as unauthorized in accordance with 1512.2, “Unauthorized Work.” The Engineer will consider any delays to the Contract resulting from unauthorized work as non-excusable in accordance with 1806.2.C, “Non-Excusable Delays.”
S-1.29 MnDOT 2461.3.G.2 shall be deleted and replaced with the following:
G.2 Placement Temperatures
Maintain concrete temperature from 50 °F to 90 °F until placement.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
62-S
Unless Engineer approved cold weather protection plans are in –place, do not place concrete when the air temperature is either of the following at the point of placement:
(1) Below 36 °F, or (2) The National Weather Service predicts the temperature to fall below 36 °F within the following 24
h period. S-1.30 MnDOT 2461.3.G.4 shall be deleted and replaced with the following:
G.4 Field Adjustments
Mix the load a minimum of 5 min or 50 revolutions at mixing speed after addition of admixture or water.
G.4.a Water Adjustments
The Engineer will allow water adjustments in accordance with all the following:
(1) Prior to discharging approximately 1 cubic yard of concrete, (2) Water available to add stated on the Certificate of Compliance, and (3) Concrete is within 60 min from the initial batch time stated on the Certificate of Compliance.
G.4.b Water Adjustments for Concrete Placed by the Slip-Form Method
The Engineer will allow water adjustments for all grades of concrete placed by the slip-form method, except Grade A paving concrete, in accordance with all of the following:
(1) If water is available to add as stated on the Certificate of Compliance. (2) Concrete is within 60 min from the initial batch time stated on the Certificate of Compliance.
G.4.c Admixture Adjustments
Approved admixture additions are allowed within 90 min from the initial batch time stated on the Certificate of Compliance. If the load of concrete has no available water to add, or the load is greater than 60 minutes old, the Engineer will allow one admixture adjustment diluted with up to 2 gallons of water.
G.4.d Consistency and Air Content Adjustments
The Engineer will test the concrete for compliance with 2461.3.G.7, “Consistency,” and 2461.3.G.8, “Air Content,” in accordance with the following:
(1) If the first test taken by the Engineer passes, the Engineer will continue verification testing in
accordance with the Schedule of Materials Control. (2) If the test taken by the Engineer fails, make adjustments and perform any quality control testing
before the Engineer performs a final test. Acceptance or rejection of the truck is based on the Engineer’s final test result.
(3) The Engineer will test up to two additional trucks in accordance with items (1) and (2) above, and (4) If the concrete does not meet the specification after those three trucks, the Engineer will reduce
their verification testing rate to once per truck for acceptance for the remainder of the pour.
For concrete mixes 3U17A and 3U18, allow mix to hydrate 5 min before slump test to assure all cement is saturated.
S-1.31 MnDOT 2461.3.G.5, 2461.3.G.5.a, 2461.3.G.5.b and 2461.3.G.5.c shall be deleted and replaced with the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
63-S
G.5 Test Methods and Specimens
Perform random sampling and testing in accordance with the Concrete Manual and determine testing rates meeting the requirements of the Schedule of Materials Control.
The Engineer performs random sampling and testing in accordance with the Concrete Manual, determines
testing rates meeting the requirements of the Schedule of Materials Control.
Anyone fabricating concrete cylinders or beams is required to hold either a current ACI Field 1 Technician Certification or a MnDOT Field 1 Technician Certification.
Anyone performing concrete strength testing of cylinders is required to hold one of the following current
certifications:
(1.1) ACI Strength Testing Technician Certification, (1.2) MnDOT Strength Testing Technician Certification, or (1.3) WisDOT Strength Testing Technician Certification.
The Engineer will furnish molds based on the maximum size aggregate for the test specimens in
accordance with the following:
(2.1) 4 in × 8 in cylinder molds, (2.2) 6 in × 12 in cylinder molds for maximum aggregate sizes greater than 1¼ in, and (2.3) 6 in × 6 in × 20 in beam molds; use other beam mold sizes as approved by the Engineer.
The Engineer will transport the cylinders in accordance with the following:
(3.1) A minimum of at least 16 hours after casting. (3.2) A minimum of at least 12 hours after casting for high early strength (28-day) cylinders. (3.3) With securely placed tight fitting plastic caps on plastic molds, or by other methods to prevent
moisture loss. (3.4) Protected from jarring, bouncing, and freezing. (3.5) No greater than 4 hours, unless cylinders are maintained in the moistened condition at ambient
temperature of 60 °F to 80 °F.
G.5.a Moist Curing Environments
At least 24 hours prior to concrete placement, provide moist curing environment(s) of adequate size and number, including all ancillary equipment and materials, necessary to maintain moist curing environment(s) in accordance with ASTM C31, 2031.3.C, “Special Requirements,” and the following:
For each separate moist curing environment:
(1) Provide a calibrated waterproof digital temperature recording device that records the daily
maximum and minimum ambient temperatures for the previous 7 days. (2) Maintain the standard (28-day) strength cylinders or beams in an ambient temperature range from
60 °F to 80 °F during the initial and intermediate curing periods.
The Engineer will monitor the daily temperatures of the curing environments. Agency monitoring does not relieve the Contractor of the responsibility to maintain the water temperature as specified herein.
If the Contractor fails to comply with the requirements shown here-in, the Engineer may delay concrete
placement and will consider any concrete incorporated into the work as unauthorized in accordance with 1512.2,
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
64-S
“Unauthorized Work.” The Engineer will consider any delays to the Contract resulting from unauthorized work as non-excusable in accordance with 1806.2.C, “Non-Excusable Delays.”
All costs related to providing and maintaining moist curing environments is considered incidental.
G.5.b Standard (28-day) Strength Cylinders
The Engineer will perform the following for standard strength cylinders:
(1.1) Cast cylinders (sets of 3) for testing at 28 days in accordance with the Schedule of Materials Control.
(1.2) Mark cylinders for identification of the represented unit or section of concrete in accordance with the following: (1.1, 1.2, 1.3/ 2.1, 2.2, 2.3/ 3.1, 3.2, etc.). In order to differentiate between portions of a project, prefixes and suffixes are allowed.
(1.3) Cure the cylinders meeting the requirements of the 2461.3.G.5.a, “Moist Curing Environments.” (1.4) Complete the MnDOT Concrete Cylinder Identification Card including the results for air content,
slump (if required), concrete, and air temperature testing from the same load.
The Concrete Engineer defines the curing period as the following:
(2.1) Initial curing period as immediately after final finishing for a period of up to 48 hours. After the initial curing period, the Engineer will both transport and further cure the cylinders in the provided curing tanks for intermediate curing up to 7 days from the day of casting or deliver directly to the laboratory for final curing.
(2.2) Intermediate Curing Period as the time between specimen pickup from the initial curing site and delivery to the laboratory for final curing, not to exceed 7 days from the day of casting.
(2.3) Final Curing Period as the time when cylinders are cured in the laboratory within 7 days of casting.
S-1.32 MnDOT 2461.3.G.5.c shall be deleted and replaced with the following:
G.5.c Field Control Strength Cylinders
The Engineer will use field control cylinders to determine when the sequence of construction operations is dependent upon the rate of concrete strength development. The Engineer will cast field control cylinders to determine when the concrete attains the required strength for all desired field control limitations.
The Engineer will perform the following for field control strength cylinders:
(1) Cast up to three (3) field control cylinders per structure. The Contractor is responsible for any
additional field control cylinders. (2) Mark field control cylinders for identification of the represented unit or section of concrete in
accordance with 2461.3.G.5.a(2). (3) Cure the cylinders in the same location and under the same conditions as the concrete structure or
unit involved meeting the requirements of the Concrete Manual, (3.1) For High-Early (HE) Concrete as defined in Table 2461-7, the Engineer will allow the
Contractor to cure field control cylinders using insulated cylinder storage compartment. Provide insulated storage compartments and any equipment necessary to continually monitor temperatures of both the newly poured concrete structure and the insulated cylinder storage compartment. Maintain the insulated storage compartment at a temperature no greater than 5 °F above the newly poured concrete structures temperature. When the temperature exceeds 5 °F or the temperature monitoring system fails, the Engineer will not accept field control cylinder results.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
65-S
(4) Complete the MnDOT Concrete Cylinder Identification Card including the results for air content, slump (if required), concrete, and air temperature testing from the same load.
During the Departments normal laboratory operating hours, the Engineer will perform compressive strength
testing on the field control cylinders. If Project scheduling requires testing outside of the Departments’ laboratories normal operating hours or the Department’s nearest laboratory is greater than 30 miles from the project; Provide certified and calibrated hydraulic cylinder-testing machine within 30 miles of the project and at a location approved by the Engineer. Test the field control cylinders in the presence of the Engineer in accordance with ASTM C39.
The Engineer will allow the Contractor to submit a strength-maturity relationship curve for use in lieu of
field control cylinders in accordance with 2461.3.G.6, “Estimating Concrete Strength by the Maturity Method.” S-1.33 MnDOT 2461.3.G.5.e, 2461.3.G.5.e(1), 2461.3.G.5.e(2), 2461.3.G.5.e(3), and 2461.3.G.5.e(4) shall be deleted and replaced with the following:
G.5.e Concrete Compressive Strength
The Concrete Engineer defines a single strength test as the average (28-day) strength of three (3) cylinders fabricated from a single sample of concrete and cured in accordance with the Concrete Manual.
If 1 of the set of 3 cylinders shows a strength variability of greater than 10% outside of the initial calculated
three cylinder average strength, the Engineer will average the remaining two cylinders and report as the 28-day compressive strength.
If 2 or more of the set of 3 cylinders shows a strength variability greater than 10% outside of the initial
calculated average strength, the Engineer will use all three cylinder results to calculate the 28-day compressive strength.
The Engineer will consider concrete acceptable in accordance with Table 2461-17 provided both the single
strength test and the moving average of 3 consecutive strength tests are met for a required f’c.
Table 2461-17
Acceptance Criteria for Standard 28-day Cylinders
Single Strength
tests Moving average of 3 consecutive strength tests *
f’c ≤ 5000 psi > (f’c – 500 psi) ≥ f’c
f’c > 5000 psi > 0.90 * f’c ≥ f’c * If a project does not establish a moving average of 3 consecutive strength tests, use the average of 2 strength tests to determine acceptance. If there is only a single strength test, contact the Concrete Engineer for recommendation.
S-1.34 MnDOT 2461.3.G.5.f, 2461.3.G.5.f(1), 2461.3.G.5.f(2), 2461.3.G.5.f(3), and 2461.3.G.5.f(4) shall be added:
G.5.f Non-Conforming Material
If the Contractor places concrete not meeting the strength requirements of 2461.3.G.5.e, “Concrete Compressive Strength” into the work, the Engineer may not accept nonconforming concrete at the contract unit price. The Engineer will evaluate non-conforming strength results in accordance with the following:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
66-S
G.5.f(1) Single Strength Test ≤ 500 psi Below f’c If any single strength test (3 cylinders) shows a strength ≤ 500 psi below f’c and is not deficient due to
erroneous/invalid strength tests as defined in 2461.3.G.5.f(4), “Moving Average Below f’c”, no additional investigation will occur and the Engineer will include the low strength test result in the moving average.
G.5.f(2) Single Strength Test > 500 psi Below f’c
If any single strength test (3 cylinders) shows a strength > 500 psi below f’c and is not deficient due to erroneous/invalid strength tests as defined in 2461.3.G.5.f(4), “Moving Average Below f’c”, the Engineer, in conjunction with the Concrete Engineer, will investigate to determine if the concrete has attained the critical load-carrying capacity.
The investigation may consist of, but is not limited to reviewing the following:
(1) Sampling and testing plastic concrete (2) Handling of cylinders (3) Cylinder curing procedures (4) Compressive strength testing procedures (5) Certificate of Compliances (6) Evaluation using Rebound Hammer (ASTM C803), Penetration Resistance (ASTM C805), or
other method approved by the Concrete Engineer (7) Review of the design calculations for the concrete in question
If it is determined that the concrete represented by the single strength test has attained the critical load
carrying capacity, the Engineer will include the strength test in the moving average calculation.
If it is determined that the concrete has not attained the critical load carrying capacity, the Engineer will direct the Contractor to remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work.” The Contractor may dispute the remove and replace order within 7 days of written notification by the Engineer. If the Contractor disputes the order, follow the dispute resolution coring procedure in accordance with 2461.3.G.5.f(3), “Dispute Resolution Coring for Single Strength Test Failure.”
G.5.f(3) Dispute Resolution Coring for Single Strength Test Failure
The Engineer and Contractor will mutually agree on an Independent Third Party to core and test the concrete in accordance with ASTM C42.
(1) The Engineer will identify a minimum of three (3) locations for the Independent Third Party to
core. (2) The Independent Third Party will take one (1) core at each location. (3) The Independent Third Party will complete all coring within 14 days of notification of the low
strength concrete. (4) The Contractor is responsible for ensuring the core holes are repaired.
The Engineer, in conjunction with the Concrete Engineer, will review the core test results and evaluate in
accordance with Table 2461-18, providing all other concrete tests meet requirements.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
67-S
Table 2461-18
Evaluation of Core Test Results Core (average
of 3 cores)
Test Results:
Engineer considers
concrete:
Cost of Coring
and Testing: Resolution:
≥ 85% of f’c and
No individual core is < 75%
of f’c
Acceptable to remain in place Agency No monetary reduction for single
strength test failure.
< 85% of f’c Unacceptable Contractor
Remove and replace concrete in accordance with 1503, “Conformity
with Contract Documents,” and 1512, “Unacceptable and
Unauthorized Work,” as directed by the Engineer.
G.5.f(4) Moving Average Below f’c
If the moving average of three (3) consecutive strength tests < f’c, the Concrete Engineer will review the strength test results and determine if a new mix design is required in accordance with Table 2461-6 or Table 2461-7.
The Engineer will remove any strength test results from the moving average if the following occurs:
(1.1) After investigation the deficient concrete strength is found to be an erroneous/invalid strength test (1.2) The suspect concrete was removed and replaced (1.3) Dispute resolution coring identified the concrete acceptable to remain in place
Reasons for finding erroneous test results as determined by the Concrete Engineer:
(2.1) Cylinders kept in the field longer than 7 days, (2.2) Improper handling/curing of the cylinders, and/or (2.3) Improper testing of the cylinders
For the quantity of non-conforming concrete not meeting the moving average of three (3) consecutive
strength tests, the Engineer will make determinations regarding the disposition, payment, or removal of the concrete in accordance with Tables 2461-19.
Table 2461-19
All Concrete Grades
Moving average of 3
consecutive strength tests
Monetary Reduction for Moving Average Failure *
> 93.0% of f’c $20.00 per cubic yard or 10% of the Contractor-provided
invoice for quantity represented by test that brought moving average into non-conformance
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
68-S
Table 2461-19
All Concrete Grades
Moving average of 3
consecutive strength tests
Monetary Reduction for Moving Average Failure *
≥ 87.5% and ≤ 93.0% of f’c $50.00 per cubic yard or 25% of the Contractor-provided
invoice for quantity represented by test that brought moving average into non-conformance
< 87.5% of f’c
Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512,
“Unacceptable and Unauthorized Work,” as directed by the Engineer.
If the Engineer, in conjunction with the Concrete Engineer, determines the concrete can remain in place, the Engineer will adjust the concrete at a reduction of $100.00 per cubic
yard or 50% of the Contractor-provided invoice for quantity represented by test that brought moving average
into non-conformance. S-1.35 MnDOT 2461.3.G.6.a and 2461.3.G.6.a(1) shall be deleted and replaced with the following:
G.6.a Development of Maturity-Strength Relationship
The Engineer will allow development of the maturity curve in either the laboratory or in the field, provided
the precautions for field curing and testing are followed, as described in the Concrete Manual. Test the concrete strength specimens for development of the maturity curve.
Determine the strength development criteria based on the type of concrete in accordance with the
following:
(1) For concrete pavement: 2301.3.O, “Opening Pavement to Traffic,” (2) For concrete pavement repairs: 2302.3.B.4, “Opening to Construction Equipment and Traffic,” (3) For concrete structures: 2401.3.G, “Concrete Curing and Protection” (4) For sidewalks, driveway entrances and curb and gutter, a minimum of 3000 psi [20.6 MPa] is
required.
Until an acceptable strength-maturity relationship is established, verify strength using concrete beams or cylinders.
G.6.a(1) Procedure
Estimate the in-place concrete strength using the maturity method as described in ASTM C 1074, except as noted in this specification as follows:
(a) Fabricate 15 cylinders plus 2 additional cylinders to embed temperature sensors or 15 beams; (b) The Nurse-Saul method of computing maturity; (c) A datum temperature of -10°C (14°F); (d) Maintain specimens at temperatures greater than 50° F for the duration of the maturity curve
development.
Test three (3) strength specimens at five different ages specified in Table 2461-20 for the type of concrete work.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
69-S
Table 2461-20
Chronological Testing Ages of Strength Specimens
Type of Concrete Testing Ages *
Concrete Pavement as defined in 2301 Determined by the Contractor ║
Normal Strength Concrete as defined in 2461 1, 2, 3, 7 and 28 days
High-Early (HE) Concrete as defined in 2461 12 hours, 1, 2, 7 and 28 days
Ultra High-Early (UHE) Concrete as defined in 2302 3, 4 and 8 hours, 1 and 14 days * The Contractor may adjust the testing ages if approved by the Engineer, in conjunction with the Concrete Engineer. ║ Test at least two (2) sets of strength specimens before the anticipated opening strength.
S-1.36 The first paragraph of MnDOT 2461.3.G.6.c shall be deleted and replaced with the following:
Perform a verification strength test to ensure the in-place concrete strength correlates with the maturity-strength relationship as follows:
(1) Notify the Engineer at least 24 hours in advance of the time and location of both the verification
specimen’s casting and strength testing. (2) When the maturity curve is developed prior to the start of construction or in a laboratory, perform
a verification strength test on the first day of concrete placement. (3) Perform a verification strength test at least once every seven (7) calender days during normal plant
production for concrete paving. For all other concrete, perform a verification strength test at least once every thirty (30) calendar days during normal plant production.
(4) If the plant has not supplied concrete to the project for a period of greater than thirty (30) calendar days, perform a verification strength test.
(5) Cast 3 cylinders plus one additional cylinder to embed the temperature sensor or 3 beams for each verification strength test.
(6) The Engineer will test the concrete strength specimens for verification of the maturity curve as close to the maturity value determined to represent the opening, loading or form removal strength criteria in accordance with the Concrete Manual.
(7) Record the results of verification test on the Concrete Maturity-Strength Verification form and submit an updated copy with the newest test result to the Engineer the day that the verification test is completed.
(8) The Engineer may direct additional verification testing as necessary. (9) Submit electronic data from the maturity meters or temperature loggers in a comma-delimited (.txt
or .csv) file format to the Engineer, which includes at least the project number, date and location of the meters or loggers.
S-1.37 MnDOT 2461.3.G.6.d(4), 2461.3.G.6.d(5) and 2461.3.G.d(6) shall be deleted. S-1.38 MnDOT 2461.3.G.7.b, Table 2461-25 and Table 2461-26 shall be deleted and replaced with the following:
G.7.b Non-Conforming Material
Only place concrete meeting the slump requirements in the work. If the Contractor places concrete not meeting the slump requirements into the work, the Engineer will not accept non-conforming concrete at the contract unit price.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
70-S
For the quantity of non-conforming concrete not meeting the required slump, the Engineer will make determinations regarding the disposition, payment, or removal of the concrete in accordance with Tables 2461-23 and 2461-24.
Table 2461-23
All Concrete Grades
> 1 in slump
Outside of Slump Range Monetary Reduction
Below slump range * No deduction for materials placed as approved by the Engineer.
≤ 1½ in above slump range $20.00 per cubic yard or 10% of the Contractor-provided invoice for quantity represented by the materials placed
> 1½ in above slump range $50.00 per cubic yard or 25% of the Contractor-provided invoice for quantity represented by the materials placed
* The Engineer will not reduce contract unit price for low slump concrete placed with the slip-form method as approved by the Engineer.
Table 2461-24
Low Slump Concrete
From ½ in to 1 in
Outside of Slump Range Monetary Reduction
Below slump range * No deduction for materials placed as approved by the Engineer
≤ ½ in above slump range $20.00 per cubic yard or 10% of the Contractor-provided invoice for quantity represented by the materials placed
≥ ¾ in above slump range $50.00 per cubic yard or 25% of the Contractor-provided invoice for quantity represented by the materials placed
* The Engineer will not reduce contract unit price for low slump concrete placed with the slip-form method as approved by the Engineer.
S-1.39 MnDOT 2461.3.G.8.a shall be deleted and replaced with the following:
G.8.a Non-Conforming Material
Only place Type 3 concrete meeting the air content requirements in the work. If the Contractor places Type 3 concrete not meeting the air content requirements into the work, the Engineer will not accept non-conforming concrete at the contract unit price.
For the quantity of non-conforming concrete not meeting the required air content, the Engineer will make
determinations regarding the disposition, payment, or removal in accordance with Table 2461-27.
Table 2461-27
All Concrete (Target Air Content 6.5%)
Air Content, % Monetary Reduction
> 10.0 $50.00 per cubic yard or 25% of the Contractor-provided invoice for quantity represented by the materials placed
>8.5 – 10.0 $20.00 per cubic yard or 10% of the Contractor-provided invoice for quantity represented by the materials placed
5.0 – 8.5 The Engineer will pay 100 percent of the contract unit price for the concrete represented, for material placed as approved by the Engineer.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
71-S
Table 2461-27
All Concrete (Target Air Content 6.5%)
Air Content, % Monetary Reduction
>4.0 – <5.0 $50.00 per cubic yard or 25% of the Contractor-provided invoice for quantity represented by the materials placed
>3.5 – ≤4.0
The Engineer, in conjunction with the Concrete Engineer will determine the concrete suitability for the intended use in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work.” This may include testing on the hardened concrete as required by the Engineer, in conjunction with the Concrete Engineer.
≤ 3.5
Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work,” as directed by the Engineer. This may include testing on the hardened concrete as required by the Engineer, in conjunction with the Concrete Engineer. If the Engineer, in conjunction with the Concrete Engineer, determines the concrete can remain in place, the Engineer may not pay for the concrete and may require coating with an approved epoxy penetrant sealer from the Approved/Qualified Products List.
S-1.40 MnDOT 2461.3.G.9 shall be deleted and replaced with the following:
G.9 Allowable Testing Tolerances
Allowable tolerances are based on the results from two different testers and two different pieces of equipment from the same sample. Perform the test within the allowable tolerances in accordance with Table 2461-28.
Table 2461-28
Allowable Testing Tolerances
Test Allowable Tolerance
Air content, % volume of concrete 1.0 % Average slump:
< 4 in 1.0 in 4 in – 6 in 1.5 in > 6 in 2.0 in Unit weight, per cu. ft, calculated to an air-free basis 1.0 lb/cu. ft Compressive strength 3,000 psi – 8,000 psi, average of 3 tests 500 psi
S-54. (2471) STRUCTURAL METALS REVISED 01/08/16
The provisions of MnDOT 2471 are modified with the following: S-55.1 The entire section of MnDOT 2471.3.B.3, "Submittal for Engineer’s Review and Approval," is deleted and replaced with the following:
Submit shop drawings from the Fabricator directly to Amy Marohn
at: City of Bloomington Public Works 1700 West 98th Street Bloomington, MN 55431
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
72-S
Submit two sets of prints of required shop detail drawings, meeting 2471.3.B.2, “Format,” from the
fabricator to the Engineer for review and release for fabrication. Shop drawings must comply with the contract documents. Provide written authorization from the design EOR (Engineer of Record) for any deviation from the contract documents. Incorporate all contractor comments into shop drawings prior to submittal to reviewer. The reviewer will return one set of prints of the shop detail drawings to the Fabricator with comments.
Submit only checked drawings, in complete collated sets, from the fabricator for review. The Contractor
may submit details such as ice-breakers, anchorages, bearing plates, and castings, separately to facilitate the work.
Fabricator may submit the shop drawings to the Contractor. Stamp these drawings with "For Contractor Use Only". Do not forward these stamped drawings to MnDOT.
Submit a schedule showing the submission dates of shop drawings and anticipated dates for shop
fabrication from the fabricator, as directed by the Engineer. Arrange the schedule to avoid delay in completing the work. If constructing a structure composed of several units, consider submitting shop detail drawings of the separate units in proper order to expedite the review and release for fabrication of the details.
If the Engineer requests changes to the submitted drawings or if the fabricator makes additional changes not
required by the Engineer, provide revised drawings, with revision control, from the fabricator with circles, underscores, or other marks to distinguish the changes from unchanged details or dimensions.
The Engineer will release shop detail drawings for fabrication after corrections are completed. Provide six
sets of corrected drawings and additional copies as required by the contract or requested by the Engineer from the fabricator at no additional cost to the Department. Mark the corrected drawings as Revision 0 and remove all comments and marks to make clean drawings for approval, stamping and distribution for use.
The shop drawings approved by the Engineer will become part of the Contract. Do not make changes on
approved drawings unless otherwise approved by the Engineer in writing. Mark changes approved by the Engineer on the approved shop drawings with revision version in number sequence next to all changes and resubmit them for approval, stamping as revised sheet and distributing to replace the superseded version of drawings.
The Engineer‘s approval of shop drawings will not relieve the Contractor of full responsibility for
submission of complete and accurate drawings and for the accurate assembly and fitting of all structural members. S-55.2 The entire section of MnDOT 2471.3.M.1.d, "Radiographic Testing (RT)," is deleted and replaced with the following:
Provide Computed Radiography (CR) or Digital Radiography (DR) in lieu of conventional radiography. The Department will retain ownership of radiographic images provided by the Contractor. Name image files with bridge number and weld identification shot number.
Electronic Radiography method(s) consist of CR utilizing Storage Phosphor Imaging Plate (SPIP) or DR
utilizing a Digital Detector Array (DDA).
Ensure CR complies with ASTM E2033, "Standard Practice for Computed Radiology (Photostimulable Luminescence Method)," and ASTM E2445, "Standard Practice for Performance Evaluation and Long-Term Stability of Computed Radiography Systems". Ensure DR complies with ASTM E2698, "Standard Practice for Radiological Examination Using Digital Detector Arrays," and ASTM E2737, "Standard Practice for Digital Detector Array Performance Evaluation and Long-Term Stability".
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
73-S
Ensure SPIP and DDA widths are sufficient to depict all portions of the weld joint, including the HAZs, and provide sufficient additional space for the required hole-type or wire-type IQIs and radiograph identification without infringing upon the area of interest.
Ensure all radiographs radiographic images are free from mechanical, chemical, or other blemishes to the
extent that they cannot mask or be confused with the image of any discontinuity in the area of interest in the radiograph. Such blemishes include, but are not limited to the following:
(1) False indications due to defective plates or internal faults; and (2) Artifacts due to non-functional pixels.
Ensure the contrast and brightness range that demonstrates the required sensitivity be considered valid
contrast and brightness values for interpretation. When multiple IQIs are utilized to cover different thickness ranges the contrast and brightness range that demonstrates the required IQI image of each IQI is determined. Intervening thicknesses may be interpreted using the overlapping portions of the determined contrast and brightness ranges. When there is no overlap, additional IQI(s) are to be used.
When performing CR or DR, ensure a measuring scale is utilized to serve as a length reference. The scale
is to be attached to the SPIP holder or DDA prior to exposure. As an alternative, when using SPIPs a transparent scale with opaque gradations may be placed on the SPIP prior to processing. In any case, the reference comparator cannot interfere with interpretation of the image.
Provide a work station monitor for evaluating images equipped with a display resolution with a pixel count
which is at least equal to the pixel count of the direct imaging plate.
Archive images using a reproducible electronic medium. Provide data file format and storage that comply with ASTM E2339, "Standard Practice for Digital Imaging and Communication in Nondestructive Evaluation (DICONDE)" format. Documented and prove the image archival method (at system installation). Include the image file nomenclature to enable the retrieval of images at a later date. Archived image files must maintain the bit depth and spatial resolution of the original image. Image data compression is not allowed. Preserve (store) the initial image presented by the CR or DR system without altering the original spatial resolution and pixel intensity. Preserve (store) the final image used for disposition when additional image processing is applied (excluding window/level and digital image zoom) to achieve the required image quality level. Store annotations made to the image in a manner which will not mask or hide diagnostic areas of the image.
S-55. (2521) SIDEWALK
The sidewalk may be curved and/or raised if necessary to save trees or other improvements as
determined by the Engineer.
Contraction joints shall be placed in the sidewalk at five-foot typical intervals and shall align with like
joints in the adjoining or neighboring work. Contraction joints shall be approximately 1/8” in width and
shall be cut to a depth of at least 1/3 the structure thickness, but not less than 3/4”.
Expansion joints shall be in sidewalk at the beginning and end of all radii, and shall align with like joints
in adjoining work. Expansion joints shall also be placed against all existing fixed objects.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
74-S
As soon as the concrete has attained sufficient strength, the area in front and back of the concrete
shall be backfilled with suitable material. The amount of concrete in place, but not completely
backfilled at any time, shall be limited to 4000 lineal feet. The backfill material behind the concrete
must be approved by the Engineer. Where sod or seed is to be installed, a minimum of four inches of
topsoil must be placed.
Concrete walk of each thickness will be measured by area and paid for at the Contract unit price per
square foot which shall be compensation in full for all costs incidental to construction, including (but
not limited to) excavation not included in roadway excavation quantities, granular base when required,
expansion fillers, and application of curing compound.
S-56. (2573) STORM DRAIN INLET PROTECTION
Storm sewer inlets shall be protected. Sediment Filter Sacks and Metal Basket Type options shall be
used. Other Engineer approved means may be used to prevent the entry of eroded material into the
storm sewer system; however, the Contractor must obtain approval for an alternate option before
installing any erosion control.
On streets where utility companies (eg: Xcel Energy, etc) are replacing facilities in conjunction with and
to necessitate work required under this Contract, inlet protection shall be installed, as approved by the
Engineer, before the utility company begins work and left in place until after work under this contract
is complete or removal is approved by the Engineer.
Storm Drain Inlet Protection, whether it be one of the above listed options or another Engineer
approved product, will be paid for under the lump sum Item 2575.601 “Erosion Control”. Lump sum
shall be considered to include all materials and labor as necessary to provide proper inlet protection
over the life of the contract regardless of quantities required. Under this provision, no measurement
will be made of any individual device or inlet location.
S-57. (2575) SODDING, TYPE SALT RESISTANT
Peat grown sod will not be accepted; only salt resistant sod shall be used on this Project. During the
pre-construction conference, the Contractor shall supply the name and contact information of their
sod subcontractor, certification from the grower stating the grass varieties contained in the sod and
the location where the sod will be harvested. The Engineer reserves the right to request a sample of
the sod to be used on the Project for approval prior to laying any sod.
Sod removal along with 4” of excavation necessary to install the sod and provide a neat edge will be
considered incidental work for which no direct compensation will be made. The 4” of select topsoil
borrow including material and placement required for sod shall be measured and paid for at the unit
bid price for 2105.526 “Select Topsoil Borrow” per cubic yard of material furnished, placed, and
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
75-S
compacted.
The Contractor shall use full width rolls of sod wherever possible. No sod shall be placed less than 1.5’
wide or 2.5’ long. The Engineer, at his or her discretion, may reject a sodded area for the use of too
many small pieces
Landscaping shall be done in locations designated on the Plans or at other locations as directed by the
Engineer. The work shall include the replacing of all sod that has been disturbed or uprooted by other
phases of the Contract.
Prior to placing any topsoil, the slopes shall be cut uniformly, such that the finished sodded slope shall
conform to the designated section. The topsoil shall be raked and all lumps and irregularities
removed prior to placing the sod or seed. All sod and seed shall be placed on a minimum of four
inches of topsoil regardless of the previous condition of the lawn. Care shall be taken to insure that
the topsoil does not contaminate the subgrade or base of the street driving surface. Topsoil
remaining on the finished street shall be cleaned up immediately following the seeding or sodding
operation.
The Contractor shall install a “New Sod Notice” on each property where new sod is planted. The
notices will be furnished by the Engineer, and supplied to the Contractor to install. Each notice
consists of a 12” wire, flag type notice with a description of how to care for new sod. Care should be
taken while watering the new sod to not damage or displace the New Sod Notices. Installing the
notices shall be incidental work for which no direct compensation will be made.
The Contractor shall be responsible for maintaining sod in conformance with the requirements of
MnDOT 2575.
S-58. EQUIPMENT
The Contractor shall not park equipment on the street overnight or on weekends unless approved by
the Engineer. If parking is approved, the Contractor shall place and maintain the necessary Traffic
Control as required and specified in the MMUTCD.
S-59. WORKMANSHIP
It is the intent and purpose of the specifications and plans to obtain good workmanship throughout,
with the completed work complying with the specifications and plans and in full working order upon
completion. The work will not be accepted until this result is obtained.
The cost of all material and labor required to complete this Project as specified and shown on the
plans, but not specifically included as a pay item, shall be merged with the various unit prices bid.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
Special Provisions, Division S
76-S
S-60. PROTECTION OF THE PUBLIC The Contactor shall provide all necessary barricades, fences, and other protection as required for the
proper execution of the work, protection of Contractor’s work, protection of the public, and for the
protection of Contractor’s employees, employees of the City, and other personnel according to all
Federal, State and Local regulations. This provision shall be incidental to the construction and no direct
compensation will be paid therefore, except where specific pay items are included in the contract for
certain protective fences, etc.
SPECIFICATIONS
AND
SPECIAL PROVISIONS
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
February 13, 2017
CITY OF BLOOMINGTON
ENGINEERING DIVISION
CITY
OF
BLOOMINGTON
DIVISION SS
SPECIAL
PROVISIONS
These Special Provisions are intended to modify and shall take precedence over the City of
Bloomington General Specifications. The plans and the specifications accompanying them shall
be considered as a whole.
I hereby certify that the Special Provisions (Division SS) contained in this proposal were
prepared by me or under my direct supervision and that I am a duly licensed Professional
Engineer under the laws of the State of Minnesota.
_________________________________________
Nickolas VanGunst
Lic. No. 44683 Date 02/13/17
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON ITS FIBER PROJECT
STANDARD SPECIFICATIONS
FOR
TRAFFIC SIGNAL CONTROL DEVICES
TABLE OF CONTENTS
Article Page
No. No.
1. DESCRIPTION .............................................................................................................................. 1
2. (1802) QUALIFICATION OF WORKERS ................................................................................... 3
3. SPECIFICATIONS/CODES/PERMITS ........................................................................................ 4
4. CONSTRUCTION SCHEDULE ................................................................................................... 4
5. (1507) UNDERGROUND UTILITIES.......................................................................................... 5
6. SURFACE RESTORATION ......................................................................................................... 5
7. HAUL SALVAGED MATERIALS .............................................................................................. 6
8. SUBMITTALS ............................................................................................................................... 6
9. (2445, 2465) BONDING AND GROUNDING ............................................................................. 6
10. (2565, 3801) CONDUIT ................................................................................................................ 7
11. (2550) REMOVE CABLE ............................................................................................................. 8
12. (2550) REROUTE CABLE ............................................................................................................ 8
13. (2550) FIBER OPTIC CABLE .................................................................................................... 11
14. (2550) FIBER OPTIC CABLE TESTING ................................................................................... 13
15. (2550) OUTDOOR FIBER SPLICE ENCLOSURE .................................................................... 15
16. (2550) FIBER OPTIC SPLICE/PATCH PANEL ........................................................................ 17
17. (2550) FIBER OPTIC PIGTAIL TERMINATION ..................................................................... 19
18. (2550) FIBER OPTIC CABLE SPLICING ................................................................................. 20
19. (2550) 334 SERIES FIBER CABINET, FOUNDATION MOUNTED ...................................... 22
20. (2550) FIBER OPTIC SPLICE VAULT...................................................................................... 25
21. (2550) FIBER OPTIC PULL VAULT ......................................................................................... 25
22. (2550) CABINET FOUNDATION CORE DRILLING .............................................................. 26
23. (2550) MODIFY SERVICE EQUIPMENT ................................................................................. 26
24. INSTALLATION OF ETHERNET NETWORK SWITCHES ................................................... 27
25. (2565) GENERAL TRAFFIC SIGNAL OPERATIONS ............................................................. 27
26. (2565) INPLACE SIGNAL SYSTEM - REMOVAL AND SALVAGE ..................................... 28
27. (2565) TRAFFIC CONTROL SIGNAL MATERIALS AND CONSTRUCTION ..................... 29
27.1 CONTROLLERS AND CABINETS ............................................................................ 29
27.2 SIGNAL MOUNTING ................................................................................................... 30
27.3 SIGNAL HEADS AND HOUSINGS ............................................................................ 31
27.4 VEHICLE SIGNAL FACES ......................................................................................... 31
27.5 EMERGENCY VEHICLE PREEMPTION (EVP) EXTENSION HARDWARE ... 32
27.6 TRAFFIC SIGNAL CONTROL CABLES AND CONDUCTORS ........................... 32
27.7 MEASUREMENT AND PAYMENT ........................................................................... 34
28. (2565) ACTIVATING SIGNALS ................................................................................................ 34
29. (2564) TRAFFIC SIGNS AND DEVICES .................................................................................. 35
29.1 GENERAL ...................................................................................................................... 35
29.2 MOUNTING SIGN PANELS ....................................................................................... 36
29.3 FABRICATION STICKERS ........................................................................................ 36
29.4 MEASUREMENT AND PAYMENT ........................................................................... 36
30. (2565) TRAFFIC MONITORING SYSTEM .............................................................................. 36
30.1 CCTV CAMERA ........................................................................................................... 37
30.2 CCTV MOUNTING BRACKET .................................................................................. 37
30.3 CAT5E ETHERNET CABLES ..................................................................................... 37
30.4 CCTV POWER .............................................................................................................. 37
30.5 OUTDOOR SURGE PROTECTIVE DEVICE FOR POE++ ................................... 37
30.6 MEASUREMENT AND PAYMENT ........................................................................... 37
31. (3831) LUMINAIRE EXTENSION ............................................................................................ 37
32. (2478, 2565) PAINTING ............................................................................................................. 38
33. AS-BUILTS ................................................................................................................................. 39
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
1-SS
1. DESCRIPTION This work shall consist of the following:
A. Base Bid
Furnishing and installing conduit, fiber optic cable, fiber optic splice/patch panels; installing 334 series
fiber cabinets, Ethernet Network Switches, fiber bulkhead drawers, materials and electrical equipment
as shown in the plans; all to provide Traffic Signal Interconnect System at the following intersections:
1. At the intersection of Killebrew Dr. and 20th Ave. S in Bloomington, Hennepin County.
2. At the intersection of Killebrew Dr. and 22nd Ave. S in Bloomington, Hennepin County.
3. At the intersection of 24th Ave. (CSAH 1) and American Blvd. in Bloomington, Hennepin County.
4. At the intersection of 24th Ave. (CSAH 1) and 79th St. W in Bloomington, Hennepin County.
5. At the intersection of 24th Ave. (CSAH 1) and I-494 in Bloomington, Hennepin County.
6. At the intersection of American Blvd. and Lyndale Ave. S in Bloomington, Hennepin County.
7. At the intersection of American Blvd. and Nicollet Ave. S (CSAH 52) in Bloomington, Hennepin
County.
8. At the intersection of American Blvd. and Portland Ave. S (CSAH 35) in Bloomington, Hennepin
County.
9. At the intersection of American Blvd. and Chicago Ave. S in Bloomington, Hennepin County.
10. At the intersection of American Blvd. and 12th Ave. S in Bloomington, Hennepin County.
11. At the intersection of American Blvd. and Thunderbird Rd. in Bloomington, Hennepin County.
12. At the intersection of Lyndale Ave. S and 82nd St. W in Bloomington, Hennepin County.
13. At the intersection of Lyndale Ave. S and 84th St. W in Bloomington, Hennepin County.
14. At the intersection of Lyndale Ave. S and 86th St. W in Bloomington, Hennepin County.
15. At the intersection of Lyndale Ave. S and 90th St. W in Bloomington, Hennepin County.
16. At the intersection of Lyndale Ave. S and 94th St. W in Bloomington, Hennepin County.
17. At the intersection of Lyndale Ave. S and 95th St. W in Bloomington, Hennepin County.
18. At the intersection of 86th St. W and Portland Ave. S (CSAH 35) in Bloomington, Hennepin County.
19. At the intersection of 86th St. W and 12th Ave. S in Bloomington, Hennepin County.
20. At the intersection of 86th St. W and Old Cedar Ave. S in Bloomington, Hennepin County.
21. At the intersection of 90th St. W and Portland Ave. S (CSAH 35) in Bloomington, Hennepin County.
22. At the intersection of 90th St. W and 12th Ave. S in Bloomington, Hennepin County.
23. At the intersection of 90th St. W and Old Cedar Ave. S in Bloomington, Hennepin County.
24. At the intersection of 98th St. W and Normandale Blvd. (CSAH 34) in Bloomington, Hennepin
County.
25. At the intersection of 98th St. W and Toledo Rd. in Bloomington, Hennepin County.
26. At the intersection of 98th St. W and Little Rd. in Bloomington, Hennepin County.
27. At the intersection of 98th St. W and Collegeview Rd. in Bloomington, Hennepin County.
28. At the intersection of 98th St. W and France Ave. S (CSAH 17) in Bloomington, Hennepin County.
29. At the intersection of 98th St. W and Logan Ave. S in Bloomington, Hennepin County.
30. At the intersection of 98th St. W and James Ave. S in Bloomington, Hennepin County.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
2-SS
31. At the intersection of 98th St. W and Old Shakopee Rd. (CSAH 1) in Bloomington, Hennepin
County.
32. At the intersection of Bush Lake Rd. W and Marth Rd. in Bloomington, Hennepin County.
33. At the intersection of Bush Lake Rd. W and 78th St. W in Bloomington, Hennepin County.
B. Add Alternative 1
Furnishing and installing an additional 1.5” non-metallic conduit to be installed with the conduit in the
Base Bid as shown in the plans, all to provide a Traffic Signal Interconnect System along American
Blvd. from Lyndale Ave. S to 24th Ave. S (CSAH 1).
C. Add Alternative 2
Furnishing and installing an additional 1.5” non-metallic conduit to be installed with the conduit in the
Base Bid as shown in the plans, all to provide a Traffic Signal Interconnect System along 98th St. W
from Normandale Ave. S (CSAH 34) to France Ave. S (CSAH 17).
D. Add Alternative 3
Furnishing and installing Flashing Yellow Arrow (FYA) upgrades, materials and electrical equipment
as shown in the plans; all to provide five (5) Revised Signal Systems –
1. Signal System A – at the intersection of Lyndale Ave. S and 94th St. W in Bloomington, Hennepin
County.
2. Signal System B – at the intersection of Lyndale Ave. S and 90th St. W in Bloomington, Hennepin
County.
3. Signal System C – at the intersection of Lyndale Ave. S and 86th St. W in Bloomington, Hennepin
County.
4. Signal System D – at the intersection of Lyndale Ave. S and 84th St. W in Bloomington, Hennepin
County.
5. Signal System E – at the intersection of 98th St. W and Toledo Rd. in Bloomington, Hennepin
County.
E. Add Alternative 4
Furnishing and installing Flashing Yellow Arrow (FYA) upgrades, materials and electrical equipment
as shown in the plans; all to provide one (1) Revised Signal System –
1. Signal System F – at the intersection of 98th St. W and James Ave. in Bloomington, Hennepin
County.
F. Add Alternative 5
Furnishing and installing CCTV camera, mounting hardware, materials and electrical equipment as
shown in the plans; all to provide three (3) Traffic Monitoring Systems –
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
3-SS
1. Traffic Monitoring System A – at the intersection of American Blvd. and Penn Ave. S (CSAH 32)
in Bloomington, Hennepin County.
2. Traffic Monitoring System B – at the intersection of American Blvd. and Lyndale Ave. S in
Bloomington, Hennepin County.
3. Traffic Monitoring System C – at the intersection of American Blvd. and Portland Ave. S (CSAH
35) in Bloomington, Hennepin County.
G. Add Alternative 6
Furnishing and installing CCTV camera, mounting hardware, materials and electrical equipment as
shown in the plans; all to provide one (1) Traffic Monitoring Systems –
1. Traffic Monitoring System D – at the intersection of 98th St. W and Collegeview Rd. in
Bloomington, Hennepin County.
H. Add Alternative 7
Furnishing and installing Flashing Yellow Arrow (FYA) upgrades, materials and electrical equipment
as shown in the plans; all to provide one (1) Revised Signal System –
1. Signal System G – at the intersection of 98th St. W and Logan Ave. in Bloomington, Hennepin
County.
I. Add Alternative 8
Furnishing and installing conduit, fiber optic cable, fiber optic splice/patch panels; installing Ethernet
Network Switches, fiber bulkhead drawers as shown in the plans; all to provide Traffic Signal
Interconnect System at the following intersection –
1. At the intersection of 98th St. W and Penn Ave. S (CSAH 32) in Bloomington, Hennepin County.
2. (1802) QUALIFICATION OF WORKERS
The provisions of Mn/DOT Spec. No.1802 are hereby supplemented with the following:
Signal and Lighting Certification II will be required for all Contractors, Supervisors or Foremen involved
in the field installation of the Traffic Signal and/or Lighting portion of this Project. Signal and Lighting
Certification, Level II, is available through the Mn/DOT Technical Certification Program. Questions
regarding certification or past certification may be directed to the Technical Certification Specialist at
telephone (651) 366-4201.
Certified Contractor personnel shall be on the Project work site at all times to perform or directly
supervise the installation of a Traffic Signal System or a Lighting System.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
4-SS
3. SPECIFICATIONS/CODES/PERMITS The contract work shall comprise the work shown on the respective Plan Sheets for each system, complete,
in place, and in operation, all in accordance with the 2016 Edition of the Minnesota Department of
Transportation “Standard Specifications for Construction”, and all supplements thereto, except as
shown and noted in the Plans and modified in these documents.
Throughout these Standard Specifications, references made to “Mn/DOT Spec.” shall mean the
“STANDARD SPECIFICATIONS FOR CONSTRUCTION” of the Department of Transportation of the
State of Minnesota, 2016 Edition. All materials and methods shall be in accordance with the Mn/DOT
Spec. and Supplemental Specifications unless modified in these documents, except all references to the
“Department” shall be designated as the City of Bloomington, Minnesota.
All applicable provisions of the current edition of the National Electrical Code shall apply to this project.
Bidders are advised that compliance with the provisions of Mn/DOT Spec. No. 1702, Mn/DOT Spec. No.
2545.2A, and the first paragraph of Mn/DOT Spec. No. 2545.3A will be enforced in conjunction with the
construction of any kind or type of electrical system, conduit, or conduit system for the conveyance of
electrical conductors, or the required portions thereof, as specified in the Contract.
The Minnesota Electrical Act requires that a permit be obtained for the performance of all such work,
including the installation of conduits. Contact the City of Bloomington Building and Inspection
Department, Electrical Division (952-563-8930) for Bloomington requirements.
Materials and equipment shall be the standard products of a manufacturer regularly engaged in the
manufacture of the products. All materials and equipment furnished shall be new of first quality, of the
latest design, and be completely free from defects in material and poor workmanship. All like pieces of
equipment shall be of the same type and manufacturer to assure uniformity, interchangeability of
components, single responsibility, and most satisfactory service.
4. CONSTRUCTION SCHEDULE Under each location of contract work, the Contractor shall observe that all work proceeds in an orderly and
efficient manner. Scheduling of contract work shall coincide with equipment delivery in such a manner
that intersections are not unduly left unsignalized for extended periods.
For example, delivery of City-furnished signal-related items, if any, may be several weeks into the project.
Therefore, the Contractor shall schedule initial work activities that are not dependent upon such material
delivery, and/or the Contractor shall schedule work that prepares the site for the material delivery.
However, such work shall not unduly force the shut-down of current signal operation until system change-
out is ready and all material and equipment are delivered.
Any excavations including, but not limited to cabinet foundations, hand holes, pull vaults and boring pits
shall be backfilled and/or constructed within five (5) working days from commencement of excavation.
Final restoration including but not limited to sodding, concrete walk, and landscaping shall be completed
within fifteen (15) days from commencement of excavation.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
5-SS
The Contractor shall make reasonable efforts to maintain existing operations of traffic signal systems to the
extent possible. The Contractor shall notify the Engineer at least 48 hours in advance of planned signal
system outages. The Contractor shall provide the Engineer an estimated duration of the outage at the time
of notification and shall update the Engineer daily until the signal system is returned to normal operation.
The Engineer has final authority to approve or deny Contractor requests for signal system outages. The
Engineer will take into consideration the number of concurrent signal system outages within the project
area; the time of day and day of week; duration of outage; whether there are any planned special events
during the outage; impacts to adjacent projects; etc. in making the determination. The Contractor is
encouraged to communicate the construction schedule and any changes in the schedule regularly with the
Engineer.
Construction of all traffic signal related work shall be coordinated with the construction of the roadways.
The Contractor shall schedule placement of conduit, handholes, loop detectors, bases, etc. in coordination
with operations involving the construction of the area roadways.
5. (1507) UNDERGROUND UTILITIES Contractor operations in the proximity of existing underground utilities shall be performed in accordance
with the provisions of Mn/DOT Spec. No. 1507.
From start of construction and until time the traffic signal interconnect, revise traffic signals, and traffic
monitor systems are placed in operation in its final configuration as shown in the plans, the Contractor shall
be responsible for locating both the new and existing traffic signal interconnect, revise traffic signals, and
traffic monitor systems in accordance with the Minnesota State Statute 216D “Gopher State One Call”.
Upon receipt, City Traffic Maintenance staff will forward Gopher State One Call tickets to the Contractor
for locating as noted above. The Contractor shall coordinate with City Traffic Maintenance staff, (1) 952-
292-6336 or (2) 952-563-8760, so that utility locating performed by the Contractor is completed within the
timeframes established for the ticket. The Contractor shall notify the City when locating is completed so
that City staff can respond to the locate request (clear, located, etc.) within the timeframes established for
the ticket. All costs associated with locating shall be incidental work to the traffic system pay item.
6. SURFACE RESTORATION All resulting excavation shall be backfilled and the backfilling and compaction shall be like in kind to
approximately the same density as the adjoining ground. If, at any time, the surface of a roadway (concrete
pavement, bituminous surface, or gravel surface, including underlying base courses), sidewalks, curb and
gutters, sod, etc., is damaged or removed due to traffic signal construction, the surface must be repaired or
replaced in kind to its original cross-section by the Contractor, all at the Contractor’s own expense,
according to the Special Provisions, and as directed by the Engineer.
All costs associated with excavations, backfilling, removals, and disposition, and surface restoration, shall
be considered incidental work to each Revise Signal System or Interconnect pay item(s).
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
6-SS
7. HAUL SALVAGED MATERIALS When specified in the plans and Division SS Special Provisions or as directed by the Engineer, traffic
signal system material and equipment shall be delivered by the Contractor to the City of Bloomington
Western Maintenance Area, 10500 Hampshire Avenue South. The Contractor shall notify the City of
Bloomington Engineering Division (952-563-4914) at least three (3) normal working days in advance of
the time the Contractor intends to deliver the salvaged materials.
City staff must be present at the Western Maintenance Area to verify that the correct items are being
delivered and to direct the Contractor where to unload the materials. The contractor is responsible for
unloading the materials to the location(s) at the Western Maintenance Area as directed by City staff.
8. SUBMITTALS The Contractor shall provide shop detail drawings for materials and electrical equipment for review by the
City. The acceptance, review and/or subsequent comments to the shop drawings shall not be construed as
approval of the shop drawings. The responsibility to supply and install materials that comply with the
specifications and plans lies entirely with the Contractor.
Below is a listing of submittals required for this project. Other submittals may be requested by the Engineer
as necessary.
• Documentation of Material Orders and Anticipated Delivery Dates
• Specification Sheet(s) for Closed Circuit Television Equipment
• Specification Sheet(s) for Fiber Optic Cable (6SM, 12SM, 24SM and 48SM)
• Specification Sheet(s) for Pre-Term/Armor Fiber Optic Pigtail (6SM)
• Specification Sheet(s) for Fiber Equipment including termination panels, patch panels, patch
cables, terminators, connectors, etc.
• Fiber Optic Cable Testing Documentation and Results
• Construction Plan As-Builts
• Fiber Routing and Network As-Builts
9. (2445, 2465) BONDING AND GROUNDING All bonding and grounding shall be in accordance with the National Electrical Code; with the Plans; and
with the applicable provisions of Mn/DOT Spec. No. 2565.3H and 3815. All required ground rods shall
be UL Listed. The provisions of Mn/DOT 2565 are modified with the following:
Delete the paragraph of MnDOT 2565.3H.5 staging “If installing non-metallic conduit for future use, the
Contractor may omit the equipment grounding conductor” and substitute the following:
Where non-metallic conduit is to be installed for future use, a No. 6 Type XHHW green, equipment
grounding conductor shall be installed in the conduit run.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
7-SS
10. (2565, 3801) CONDUIT The Contractor shall furnish and install rigid steel conduit (RSC) and fittings, or non-metallic conduit
(NMC) where shown approved, as shown in the Plans. The size of the conduit shall be as indicated in the
Plan. Conduit shall be placed by the Contractor in accordance with the provisions of these specifications,
Mn/DOT Spec. No. 2565.3D, and with the following:
Rigid steel conduit shall conform to the requirements of Mn/DOT Spec. No. 3801. Intermediate metal
conduit shall not be used in lieu of rigid steel conduit.
Rigid Non-Metallic Conduit (NMC) shall be in accordance with Mn/DOT Spec. No. 3803, except:
a. Shall be Schedule 80 conduit and fittings for all installations.
b. Shall be capable of being installed by stitching, plowing, trenching, or directional boring methods
as required for the Project.
c. Shall be marked on the outside of conduit indicating manufacturer’s name, size of conduit, type of
conduit, ASTM F 2160, UL Listing, and any other markings required by the N.E.C.
d. Before the cables and conductors are installed, non-metallic conduit bell ends shall be installed to
prevent damage to the cables and conductors
e. Shall contain an equipment grounding conductor as specified in Article 8 of these specifications.
Where conduits are required under existing roadway pavements, the conduit shall be placed by directional
boring or other method approved by the Engineer. The Contractor shall install appropriate long line
couplings when NMC is installed under existing roadway surfaces. Applied PVC joint cement for NMC
conduit shall be allowed to set-up for six (6) hours before pulling the conduit through a directional bored
channel. Conduits shall not be placed under existing roadway pavements by trenching unless authorized in
writing by the Engineer.
All costs associated with placing conduit below existing roadway pavements (no matter at which location
or what method used) shall be considered incidental to the bored conduit pay item.
Maximum permissible depth of conduit at the handholes shall be 30 in., as measured from top of handhole
to the bottom of the conduit, except as noted in the Plans.
Trenches for conduit shall be true in line and grade. The trench bottom, prior to placing the conduit, shall
be of uniform density throughout the length of a run. Trench bottoms shall be smoothed and compacted as
necessary to establish the grade and density. Trenches in bituminous roadways shall be made with a cutting
wheel, jackhammer, or similar approved tools. Edges shall be smooth and vertical.
Tracer wire shall be placed in all Non-Metallic Conduit that is installed and to remain empty for future use.
Duct seal, or another Engineer approved material, shall be furnished and installed to seal all pole base,
controller cabinet and service cabinet entrances as necessary in accordance with Mn/DOT Spec. No.
2565.3D2b.
The material for all conduit bushing-grounding lugs shall consist of stainless steel, copper, brass, or bronze.
Existing conduits to be used inplace shall be cut or extended as required in the Plans.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
8-SS
End Bells shall be furnished and installed by the Contractor on all ends of non-metallic conduit entering a
handhole.
Conduit abandoned inplace shall be blown full with sand and capped at each end as directed by the
Engineer. All costs associated with this work and material shall be incidental to the traffic signal system
pay item.
All RSC terminating near the top of a wood pole shall utilize a metal weatherhead service entrance type
fitting with knockouts (knockouts shall not be opened if not used).
Conduit attached to a wood pole shall be attached using galvanized RSC straps spaced 3 feet apart, or as
directed by the Engineer.
All appurtenant materials, equipment, and labor required to make any connection or relocation to in-place
components, shall be considered incidental to traffic signal, EVP, interconnect, or lighting system to which
it relates.
For conduit containing interconnect cable, a 3-inch wide permanent orange, stretchable, non-biodegradable,
plastic warning tape shall be placed above the interconnect cable (or conduit containing the interconnect
cable), at 12 inches below the surface. The tape shall be imprinted with the inscription, “CAUTION-
SIGNAL COMMUNICATION CABLE”, or other legend approved by the Engineer.
Warning tape shall be placed above all conduit runs containing the interconnect cable (except over conduits
that are to be installed under roadways by directional bore).
11. (2550) REMOVE CABLE This work shall consist of Removing Cables, which shall be in accordance with the Mn/DOT Standard
Specifications, Mn/DOT Standard Plans/Plates, the Plans, and the following:
11.1 REMOVE CABLE
Remove Cables from termination or splice location to termination or splice location by extracting
designated cables from existing conduit and end equipment in a manner that is harmless to the cables that
shall remain intact.
11.2 MEASUREMENT AND PAYMENT
No measurement will be made of the various Items that constitute Remove Cables but all such work will
be construed to be included in the single Lump Sum payment under Item 2550.601 (Remove Cables).
12. (2550) REROUTE CABLE This work shall consist of Reroute Cable, which shall be in accordance with the Mn/DOT Standard
Specifications, Mn/DOT Standard Plans/Plates, the Plans, and the following:
12.1 REROUTE CABLE A. Disconnect and terminate cables unless otherwise directed by the Plans.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
9-SS
B. Pull back cables prior to rerouting as directed by the Plan.
C. Existing conduit and cables shall be removed to adjust to the proposed design.
D. Protect cable to ensure it is not damaged when exposed. The Contractor shall be responsible for any
damage incurred during the Reroute Cable operation.
12.2 FO CABLE INSTALLATION REQUIREMENTS
The FO Cable Installation Requirements shall comply with Mn/DOT 2550.3 and the following
provisions:
A. The following lengths of outer jacket and armor shall be removed from field terminated FO Cable
for fiber management:
a. Remove eight to 15 feet of the outer jacket of cable terminating an Outdoor FO Splice Enclosure.
b. Remove 33 feet of the outer jacket of cable terminating in a ground mounted control Cabinet or
Signal Cabinet.
FO Cable shall be placed a minimum of 36 inches below finished grade.
B. FO cable shall be placed a minimum of 60 inches below finished grade when it is placed under a
road.
C. For lengths of FO Cable over 600 feet the Contractor shall employ the Air Assisted method for
installation.
D. Expected tension on the FO Cable and pulling tape shall be calculated prior to installing the FO
Cable in conduit runs. The pulling force shall be distributed between the inner strength member
and the aramid fibers by securing both to the main pulling device.
E. A “break-away” type pulling attachment shall be utilized to protect against over stressing the FO
Cable. A cable grip that pulls only on the outer jacket to pull FO Cable shall not be allowed.
F. Damage to the FO Cable from any source or exceeding the manufacturer’s recommended tensile
strength limits or cable-bending radius is cause for the cables to be rejected. The Contractor shall
ensure a minimum bend radius of ten inches during installation (loaded cable) and minimum bend
radius of eight inches after installation (static cable).
G. Often, FO Cable is pulled through conduit/handhole networks. Using the 24 inches diameter
handholes as a fiber pull box, may exceed the minimum loaded bend radius and cause damage to
the cable fibers. The Contractor shall take protective measures when pulling fiber back to a
handhole.
H. Slack FO cable shall be provided for FO cables spliced within vaults. Provide 50 feet of slack FO
Cable coiled in these vaults per each vault entrance/exit. Provide other lengths of Slack FO Cable
if called for in the Plan.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
10-SS
I. Backfill open trench installations with granular material six inches over the FO Cable conduit
elevation.
J. Air Assisted FO Cable
a. Long radius bends shall be utilized in equipment foundations and other situations requiring the
negotiation of sharp angles.
b. The duct system shall be properly installed utilizing pressure tight splices.
i. Seal one end of the duct and pressurize the duct utilizing a sealed blowing machine.
ii. The duct shall maintain 130 psi without realizing significant pressure loss
iii. Use care near pressurized ducts.
c. High air speed blowing shall require the front end of the FO Cable to be endcapped to prevent the
cable from getting hung up in the duct.
d. Utilize proper air seals to fit the OD of the FO Cable.
e. Provide proof that the duct is properly spliced and not crushed by blowing a hard mandrel
through the duct.
f. Clean and dry the duct utilizing the following procedures
i. Blow a tight fitting foam carrier through the duct at high pressure. The foam shall travel at
approximately 100 fps.
ii. If excess water and/or dirt is expelled from the duct, repeat the process until minimal water
and/or dirt is observed.
iii. Dry the duct with airflow.
g. For high speed air machines (no missile), inject the recommended amount of approved lubricant
and spread it with a foam carrier. For piston type machines, inject the majority of the lubricant in
front of the missile with some placed behind the missile.
h. For push/pull machines, attach the piston to the FO Cable and insert the piston into the duct.
i. For high air speed machines, hand push approximately 100 feet of FO Cable into the duct prior to
activating the machine.
j. Use caution in bringing up the air and hydraulic pressure.
12.3 MEASUREMENT AND PAYMENT
Measurement will be made by the affected length of Cable Rerouted as specified. If groups of cable
pulled to the same location are designated for rerouting within the Plan, measurement shall apply to an
average length for the group of cables not individual cable lengths. Installation of the rerouted cable shall
be considered incidental. Payment will be made under Item 2550.603 (REROUTE CABLE) at the
Contract bid price per linear foot, which shall be compensation in full for all costs incidental thereto,
including but not limited to Disconnecting and Terminating cables, FO Cable Installation Requirements,
rerouting the cable, removing and relocating existing conduit as necessary, protecting the cable,
Grounding, Labeling, and all materials and labor necessary to construct the Reroute Cable.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
11-SS
13. (2550) FIBER OPTIC CABLE Where specified in the Plans, 6SM, 12SM, 24SM or 48SM fiber optic cable and pre-terminated armored
fiber optic pigtail cable shall be furnished and installed in accordance with the applicable provisions of
Mn/DOT Spec. No. 2550, with the Plans and as follows:
Materials and equipment shall be the standard products of a manufacturer regularly engaged in the
manufacture of the products. All materials and equipment furnished shall be new of first quality, of the
latest design and be completely free from defects in material and poor workmanship. All like pieces of
equipment shall be of the same type and manufacturer to assure uniformity, interchangeability of
components, single responsibility, and most satisfactory service.
Trained and experienced personnel shall supervise the fiber optic cable installation. Qualified technicians
shall do the cable terminations.
The fiber optic installation shall be in accordance with or exceed all minimal requirements of State codes,
National codes NEMA standards and manufacturer codes as applicable.
13.1 FIBER OPTIC CABLE The fiber optic cable shall be a fiber-outside plant six (6), twelve (12), twenty-four (24) or forty-eight (48)
single mode, graded index, six (6), twelve (12), twenty-four (24) or forty-eight (48) optical fibers stranded
with a minimum of one non-metallic strength member. It shall also be loose tube, individual buffered, all
dielectric construction, gel filled buffers, suitable for outdoor use in conduit or on aerial supports. The fiber
optic cable shall be constructed with Kevlar braid and outer polyethylene jackets as a minimum. If the
inner jacket is used, it shall be PVC.
Cable and connectors shall conform to the applicable provisions of Mn/DOT Spec. No. 3815.2.
Each fiber shall be continuous with no factory splices except for joining standard length cables to form
longer, continuous jacketed cable to fit installation requirements. The cable shall have standard nylon rip
cords. Kevlar ripcords will not be accepted.
13.2 PRE-TERMINATED ARMORED FO PIGTAIL CABLE
The following provisions shall apply Pre-terminated armored FO Pigtail Cable:
A. The Pre-terminated armored FO Pigtail Cable shall be constructed with the following Material
requirements:
a. The Manufacturer’s operational temperature rating range shall include -40 to +70 degrees C (-40
to 158 degrees F). The range may be larger but shall include the previously mentioned range.
b. Connector assemblies shall be ultra-polished FC/PC design with zirconia ceramic ferrules and
sleeves. These must meet or exceed the requirements of the Telcordia GR-326 CORE Issue 3
document.
c. Rated for outdoor use.
d. Includes a factory terminated patch panel,
e. Typical dimensions shall be as follows:
i. 6 fibers: 9 inches long x 1.75 inches wide x 1.75 inches deep
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
12-SS
ii. 12 fibers: 13 inches long x 1.75 inches wide x 1.75 inches deep
B. The Patch enclosure of the Pre-terminated armored FO Pigtail Cable shall not contain any Potting
material. The Contractor shall notify the Manufacturer of this requirement when ordering the parts.
13.3 CONNECTORS Connectors shall be compatible, field installable, and self-aligning and centering. Fiber optic equipment
shall use the same type of connectors. White or clear epoxies shall not be used when making connections.
The cable shall be terminated at each controller cabinet utilizing a splice box with a splice tray. Splice box
with a splice tray shall provide for suitable termination of the fiber with the fiber optic connector(s) as
specified.
The splice box with a splice tray shall be used to terminate each fiber cable in the controller cabinet. Patch
cables shall be used to feed through unused fibers if necessary.
13.4 INSTALLATION The Fiber Optic and Pigtail cables shall be installed in continuous run as indicated on the Plans. Splices
shall be allowed only in controller cabinets, 334 fiber cabinets and in fiber optic splice vaults, as indicated
on the Plans, between the end of the fiber optic interconnect cable and a splice box with a splice tray. The
cable shall be terminated at each interconnect cabinet utilizing splice box with a splice tray and compatible
connectors. All fibers shall be terminated with a connector. The connectors on unused fibers shall be
protected with a plastic cap. The Contractor shall use caution to avoid premature cutting of any excess cable
length.
A 3-inch wide permanent orange, stretchable, non-biodegradable, plastic warning tape shall be placed
above the interconnect cable (or conduit containing the interconnect cable), 12 inches below the surface.
The tape shall be imprinted with the inscription, “CAUTION-SIGNAL COMMUNICATION CABLE”, or
other legend approved by the Engineer.
A suitable cable feeder guide shall be used between the cable reel and the face of the conduit to protect the
cable and guide it into the conduit off the reel. It shall be carefully inspected for jacket defects. If defects
are noticed, the pulling operation shall be stopped immediately and the Engineer notified. Precautions shall
be taken during installation to prevent the cable from being "kinked" or "crushed". A pulling eye shall be
attached to the cable and used to pull the cable through the conduit system. A pulling swivel shall be used
to eliminate twisting of the cable. As the cable is played off the reel into the cable feeder guide, it shall be
sufficiently lubricated with a type of lubricant recommended by the cable manufacturer. Dynamometers or
breakaway pulling swing shall be used to ensure that the pulling line tension does not exceed the installation
tension value specified by the cable manufacturer. The mechanical stress placed on a cable during
installation shall not be such that the cable is twisted or stretched. The pulling of cable shall be hand assisted
at each controller cabinet. The cable shall not be crushed, kinked or forced around a sharp corner. If a
lubricant is used it shall be of water based type and approved by the cable manufacturer. Sufficient slack
shall be left at each end of the cable to allow proper cable termination. Additional slack cable shall be left
in each handhole at an intersection corner and at the top of each conduit riser. The minimum slack amounts
shall be as follows:
Handhole - 10 feet
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
13-SS
Conduit Riser - 50 feet
Support Poles 50 feet
Storage of additional slack cable in handholes shall be coiled. The slack coils shall be bound at a minimum
of 3 points around the coil perimeter and supported in their static storage positions above the handhole floor
by handhole shoulder eyebolts. Storage of additional slack cable adjacent to conduit risers shall be as
detailed on the plans. At each controller cabinet and handhole, the cable shall be visibly marked/tagged as
"CAUTION-FIBER OPTIC CABLE". Maximum length of cable pulling tensions shall not exceed the
cable manufacturer's recommendations.
For static storage, the cable shall not be bent at any location to less than ten times the diameter of the cable
outside diameter or as recommended by the manufacturer. During installation, the cable shall not be bent
at any location to less than twenty times the diameter of the cable outside diameter or as recommended by
the manufacturer.
Termination shall be made using the method recommended by the connector manufacturer.
13.5 MEASUREMENT AND PAYMENT
Measurement will be made by the length of Fiber Optic Cable furnished and installed as specified.
Payment for FIBER OPTIC CABLE of each size and type will be made in accordance with the schedule
set forth below at the appropriate Contract unit bid price for each separate item of work, which shall, in
each instance, be compensation in full for all costs incidental thereto, including but not limited to FO
Cables, break-out kits, connectors, pigtail assemblies, mechanical splices, splice boxes, splice trays, patch
cables, warning tape and all other materials, hardware, and labor to complete the installation of the fiber
optic cable for the interconnect.
Item No. Description Unit
2550.603 Fiberoptic Trunk Cable ___ ___ linear foot
2550.603 Fiber Optic Pigtail Cable ___ ___ linear foot
2550.603 Pre-terminated/Armored Fiber Optic Pigtail Cable___ ___ linear foot
14. (2550) FIBER OPTIC CABLE TESTING The Contractor shall provide all personnel, equipment, instrumentation and supplies necessary to perform
all testing, which shall be in accordance with the Mn/DOT Standard Specifications, Mn/DOT Standard
Plans/Plates, the Plans, and the following:
14.1 FIBER OPTIC CABLE TESTING
All testing shall be performed in an accepted manner and in accordance with the testing equipment
manufacturer's recommendations. All data shall be recorded and submitted to the Engineer.
Each section of the fiber optic cable shall be tested at a minimum for continuity and attenuation. If the
attenuation is found not to be within the acceptable nominal values, the contractor shall use an Optical Time
Domain Reflectometer (OTDR) to locate points of localized loss caused by bends or kinks and try to relax
these bends or kinks. If this is not successful the Contractor shall replace the damaged section of the cable
with no additional payment. Splices will not be allowed to repair the damaged section. The Contractor
shall provide the Engineer with a written report showing all of the values measured during these tests.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
14-SS
The end-to-end attenuation test shall be measured for each link after installation by insertion loss testing.
The launch reference cable shall be connected to the light source and the receive reference cable to the
power meter. The two reference cables shall then be connected via a patch panel. A reference power
reading (P1) shall then be taken and recorded.
The system link to be tested shall then be inserted between the launch and receive reference cables using 2
patch panels. A test power reading (P2) shall then be taken and recorded.
The link attenuation (A) in dB shall be recorded as the mathematical difference between the reference power
(P1) and the test power (P2).
Link attenuation (A) = P1 - P2
where P1 = Reference Power
where P2 = Test Power
This test shall be performed in both directions along the link. The direction of the test shall be recorded in
the documentation.
Transmitter/Receiver Power Levels--The output power levels at the network hardware transmitters and
receivers shall be measured and recorded for system documentation.
The power meter shall be connected to the transmitter side of the equipment with a system jumper. The
transmit power level shall then be read and recorded. The transmitter is then reconnected to the cable link
and the power meter connected to the receive side of the equipment. The receive power level shall then be
read and recorded.
Continuity-- tests shall be used to determine whether a test or system jumper does or does not pass light. A
continuity test shall also be used to assure that fibers have not been crossed over in the jumper and that the
transmit fiber goes to the receive fiber.
To perform continuity tests, a high-intensity flashlight shall be aimed into the connector at one end, while
an observer watches for a flicker or light at the other end.
OTDR Testing--An Optical Time Domain Reflection meter (OTDR) shall be used to evaluate the quality
and length of cable reels prior to their use on the project. The fiber loss in dB/Km and the length of each
reel shall be recorded in the documentation.
A hardcopy of OTDR signature traces for all system links shall be made and provided in the documentation.
The results of all testing shall be recorded along with date of test, name of person performing test, brand
name, model number, serial number of equipment used during test, and any other pertinent information and
data.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
15-SS
14.2 MEASUREMENT AND PAYMENT
No measurement will be made of the various Items that constitute Fiber Optic Cable Testing but all such
work will be construed to be included in the single Lump Sum payment under Item 2550.601 (FIBER
OPTIC CABLE TESTING).
15. (2550) OUTDOOR FIBER SPLICE ENCLOSURE This work shall consist of furnishing and installing an Outdoor Fiber Splice Enclosure, which shall be in
accordance with the MnDOT Standard Specifications, MnDOT Standard Plans/Plates, the Plans, and the
following:
15.1 ENCLOSURE
The following provisions shall apply to the Enclosure part of the Outdoor Fiber Optic Splice Enclosure:
A. The enclosure shall have the following characteristics:
a. A temperature rating of -30 to +60 C (-22 to 140 ºF).
b. Sufficient desiccant (packaged silica) inside to reduce possible damage from moisture.
c. FO Cables enter and exit from the same end of the Outdoor Fiber Splice Enclosure.
d. Expands to allow for up to 8 FO cables and/or FO pigtails to enter through one end.
e. Pressurized to 20 kPa (3 psi).
f. Permits selective fiber splicing (FO cable can loop in and out with only the selected fibers cut).
g. Is compatible with the splice trays and FO cables.
h. Protects splices from damage.
i. Composed of salt corrosion resistant, compatible materials not supporting galvanic cell action.
j. Splicing can be completed without circuit disruption.
k. Provides for FO cable (trunk and pigtail) strain relief.
l. FO Cables may be inserted without exceeding the minimum bending radius.
m. Includes a grounding lug.
n. Includes two grounding posts.
o. Provides for termination of up to two trunk FO cables and armored FO pigtails.
p. Includes a cable clamp for bonding to the armor of the FO cable.
q. Provides for re-entry of future FO cable.
r. Able to accommodate the following combinations of FO cables, FO cable addition kits, and bolt
adapter kits:
i. Two FO cables without a FO cable addition kit.
ii. Four FO cables with one FO cable addition kit and butt adapter bolt kit.
iii. Six FO cables with two FO cable addition kits and double butt adapter bolt kit.
iv. Eight FO cables with three FO cable addition kits and triple butt adapter bolt kit.
B. Non-oxidizing coating shall be applied to all connections.
Tape the FO Cables together as necessary near the Outdoor FO Splice Enclosure and throughout the slack
length.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
16-SS
15.2 SPLICE TRAY
The following provisions shall apply to the Splice Tray part of the Outdoor Fiber Optic Splice Enclosure:
A. The splice tray shall have the following characteristics:
a. Provides for entry of individual fibers.
b. Is stackable.
c. Capable of holding 24 splices and 48 fibers.
d. FO Cables may be inserted without exceeding the minimum bending radius.
e. Accommodates splice identification on the cover.
f. Includes Polyethylene tubes to protect the fibers and ethylene vinyl acetate sleeves with stainless
steel rods to protect the splices.
g. Has a manufacturer provided label on the cover for fiber identification.
B. Splices shall be mounted on the splice chip.
15.3 MOUNTING
The following provisions shall apply to Mounting of the Outdoor Fiber Optic Splice Enclosure:
A. Mounting the Outdoor Fiber Splice Enclosure in the splice vault requires a bracket to be
constructed to fit the opening to the splice vault per plan detail. The objective of this bracket is to
keep the splice enclosure off the floor of the vault. The bracket is constructed as follows:
a. The main support member is one inch x 1.5 inches variable “C” channel and may be perforated
with web-centered holes. The length dimension varies with the diameter of the access cover.
b. The ends of the main support member have “Z” brackets constructed of 0.1875 inch stainless
steel 1.5 inches wide. The “Z” brackets rest on the vault lip for the round access cover.
c. The outdoor fiber splice enclosure is hung from the bracket assembly with 0.125 inch stainless
steel cable.
15.4 PRESSURE TEST
To ensure that the outdoor fiber splice enclosure is properly sealed, the Contractor shall utilize the
following test procedure:
A. Testing shall be performed in the presence of the TMS Integrator when the Outdoor Fiber Splice
Enclosure is in its final hanging position.
B. Pressurize the enclosure to between 8 to 10 psi and wait 45 seconds. During the 45 second wait,
spray soapy water around the seal to check for leaks.
C. Recheck the pressure. The enclosure should not have lost more than 2.5 psi.
D. If the pressure loss is not greater than 2.5 psi and no leaks were detected when soapy water was
sprayed around the seal, the enclosure requires no further testing.
E. If the pressure loss is greater than 2.5 psi or leaks were detected when soapy water was sprayed
around the seal, the Contractor shall repair any leaks and retest the enclosure.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
17-SS
15.5 MEASUREMENT AND PAYMENT Measurement will be made by the each constructed as specified. Payment will be made under Item
2550.515 (OUTDOOR FIBER SPLICE ENCLOSURE) at the Contract bid price per each, which shall be
compensation in full for all costs incidental thereto, including but not limited to, the enclosure, grounding,
FO cable addition kits, butt adapter bolt kits, hanger hardware, splice tray, mounting, pressure testing, and
all materials and labor necessary to construct the Outdoor Fiber Splice Enclosure.
16. (2550) FIBER OPTIC SPLICE/PATCH PANEL This work shall consist of furnishing and installing a Splice/Patch Panel, which shall be in accordance with
the MnDOT Standard Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
16.1 FIBER OPTIC SPLICE/PATCH PANEL A. FO Splice/Patch Panel shall be a combination FO Splice Panel and FO Patch Panel unit.
B. The Contractor shall furnish and install a flush mounting kit for FO Panels with the following features:
a. Shall be compatible with 19 inch wide and 14 inch tall racks.
b. Allows for one, two, or three inch recess mounting.
c. Includes vertical cable guide and mounting flanges.
C. The Contractor shall mount 127 mm (five-inch) recess rack mounting.
D. The Contractor shall submit shop drawings for each patch/splice panel to the City for approval as
required in Section 8.
E. Fiber Optic Splice Panel
The following provisions shall apply to the FO Splice Panel or FO Splice/Patch Panel for FO Splice,
Patch, or Splice/Patch Panel:
The FO Splice Panels shall include the following features:
a. Splice Wheels, locks, and cable clamps.
b. Splicing protections and associated pigtail/fiber storage shall be provided to comply with bend
radius requirements.
c. Compatible splice wheel or splice deck.
d. Splice capacity as needed.
e. Front loading.
f. Accommodations for a 483 mm (19-inch) EIA rack or a 584 mm (23-inch) rack and brackets
shall be installed to accommodate a 584 mm (23-inch) rack as needed.
g. Hinges located on the bottom front corner for access to both the front and back of the front
plate and the interior of the panel.
h. Accommodations for 127 mm (five-inch) recess rack mounting.
i. Splice wheels with bend radius control that provide for roll-up of pigtail and buffer tube
lengths.
F. Fiber Optic Patch Panel
The following provisions shall apply to the FO Patch Panel or FO Splice/Patch Panel for FO Splice,
Patch, or Splice/Patch Panel:
a. The Contractor shall splice the armored pigtails to the indoor pigtails.
b. The FO Patch Panel shall include the following features:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
18-SS
i. Provides accessibility to single fibers for maintenance.
ii. Composed of high-strength aluminum.
iii. Metal doors with Plexiglas windows.
iv. Termination capacity as needed.
v. Accommodates front loading.
vi. Accommodates a 483 mm (19-inch) EIA rack or a 584 mm (23-inch) rack and brackets
shall be installed to accommodate a 584 mm (23-inch) rack as needed.
vii. Hinged on the left front side for access to both the front and back of the front plate and the
interior of the panel.
viii. Storage for pigtails shall be available to allow enough slack to fully open the door.
ix. 127 mm (five-inch) recess rack mounting.
x. Equipped with designation labels.
xi. 6-pak adapter plug-ins as required for proposed fibers.
G. The Contractor shall mount 127 mm (five-inch) recess rack mounting.
H. Fiber Optic Splice/Patch Panel (6 Position)
The following provisions shall apply to the FO Splice/Patch Panel (6 Position):
a. Patch and Splice Module
• The Contractor shall splice the armored pigtails to the indoor pigtails.
• The FO Patch Panel shall include the following features:
i. Provides accessibility to single fibers for maintenance.
ii. Accommodates a minimum of 6 fibers/connectors
iii. Adapter plug-ins as required for proposed fibers.
iv. Accommodates Ultra-Polished LC connectors
v. Accommodates single-mode fiber
• Wall mount enclosure
i. Composed of steel with roll-formed hinges
ii. Compatible with the Patch/Splice Panel (6 Position)
iii. DIN rail mounting
I. Indoor Pigtails
The following provisions shall apply to the Indoor Pigtails for FO Splice, Patch, or Splice/Patch Panel:
a. Indoor Pigtails consisting of 6 individual fibers bundled into a single sheath are required for
field splicing method of terminating Armored FO Pigtails and Trunk FO Cable.
b. Minimum lengths shall be two meters in a Cabinet and five meters in a FDF.
c. Complies with ITU-T recommendation G.952, TIA/EIA-492CAAA, IEC Publication 60793-2
and GR-20-CORE requirements.
d. Manufactured using the Outside Vapor Deposition (OVD) process.
e. The connector return loss shall be greater than or equal to 57dB.
f. SM Indoor Pigtail jackets shall be yellow and MM Indoor Pigtail jackets shall be orange.
g. Thickness of secondary buffer shall be 250 µm to 900 µm thickness.
h. Individually constructed.
i. LC Fiber Connectors shall be utilized for SM.
j. Boots shall be secured to the jacket with a pliable adhesive.
k. Land connectors on Patch Panel Bulkhead Adapters.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
19-SS
J. Fiber Bulkhead Adapters
The following provisions shall apply to the LC Fiber Bulkhead Adapters for FO Splice, Patch, or
Splice/Patch Panel:
i. The Fiber Bulkhead Adapters shall include the following features:
a. One-piece construction.
b. Metallic bodies.
c. Zirconia ceramic sleeves.
16.2 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed design as specified. Payment will be made under
Item 2550.602 (FIBER OPTIC SPLICE/PATCH PANEL) at the Contract bid price per each, which shall
be compensation in full for all costs incidental thereto, including but not limited to Fiber Optic Splice
Panel, Splice Wheels, Splice Decks, Locks, Cable Clamps, Fiber Optic Patch Panel, and all materials and
labor necessary to construct the Fiber Optic Splice, Patch, or Splice/Patch Panel.
17. (2550) FIBER OPTIC PIGTAIL TERMINATION This work shall consist of Fiber Optic Pigtail Termination, which shall be in accordance with the Mn/DOT
Standard Specifications, Mn/DOT Standard Plans/Plates, the Plans, and the following:
17.1 FIBER OPTIC PIGTAIL TERMINATION A. Fiber Bulkhead Adapters
The following provisions shall apply to the LC Fiber Bulkhead Adapters for FO Splice, Patch, or
Splice/Patch Panel:
a. The Contractor shall utilize the field termination method.
b. Indoor Pigtails
The following provisions shall apply to the Indoor Pigtails for FO Pigtail Termination:
i. Indoor Pigtails consisting of 6 individual fibers bundled into a single sheath are
required for field splicing method of terminating Armored FO Pigtails and Trunk FO
Cable.
ii. Minimum lengths shall be two meters in a Cabinet and five meters in a FDF.
iii. Complies with ITU-T recommendation G.952, TIA/EIA-492CAAA, IEC Publication
60793-2 and GR-20-CORE requirements.
iv. Manufactured using the Outside Vapor Deposition (OVD) process.
v. The connector return loss shall be greater than or equal to 57dB.
vi. SM Indoor Pigtail jackets shall be yellow.
vii. Thickness of secondary buffer shall be 250 µm to 900 µm thickness.
viii. Individually constructed.
ix. LC Fiber Connectors shall be utilized for SM.
x. Boots shall be secured to the jacket with a pliable adhesive.
xi. Land connectors on Patch Panel Bulkhead Adapters
c. Fiber Connectors
The following provisions shall apply to the SM LC Fiber Connectors for FO Pigtail
Termination:
i. Comply with “Generic Requirements for Optical Fiber Connectors”, Telcordia
Document No. GR-326, most recent issue, and the following additional features:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
20-SS
ii. Indoor pigtail fibers shall be mated to Fiber Connectors at a facility specializing in this
operation.
iii. Include the following features:
i. One-piece construction
ii. Metallic coupling nuts and bodies.
iii. Zirconia ceramic ferrules.
iv. Factory installed.
v. Yellow or blue boots for SM fibers when used inside Patch Panels.
d. Fiber Bulkhead Adapters
The following provisions shall apply to the SM LC Fiber Bulkhead Adapters for Pigtail
Termination:
i. One-piece construction.
ii. Metallic bodies.
iii. Zirconia ceramic sleeves.
17.2 MEASUREMENT AND PAYMENT
Measurement will be made by each end of the FO cable terminated in the cabinet splice/patch panel
constructed as specified. Payment will be made under Item 2550.602 (FIBER OPTIC PIGTAIL
TERMINATION) at the Contract bid price per each, which shall be compensation in full for all costs
incidental thereto, including but not limited to Indoor Pigtails, Fiber Bulkhead Adapters, FO Cable splicing,
and all materials and labor necessary to construct the Fiber Optic Pigtail Termination.
18. (2550) FIBER OPTIC CABLE SPLICING This work shall consist of Fiber Optic Cable Splicing, which shall be in accordance with the MnDOT
Standard Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
18.1 INDOOR PIGTAILS The following provisions shall apply to the Indoor Pigtails for FO Cable Splicing within Cabinets:
A. The Contractor shall not use existing Indoor Pigtails.
B. Indoor Pigtails consisting of 6 individual fibers bundled into a single sheath are required for field
splicing method of terminating Armored FO Pigtails and Trunk FO Cable.
C. Minimum lengths shall be two meters in a Cabinet and five meters in a FDF.
D. Complies with Corning SMF-28 for optical fiber.
E. The connector return loss shall be greater than or equal to 57dB.
F. SM Indoor Pigtail jackets shall be yellow.
G. Thickness of secondary buffer shall be 250 µm to 900 µm thickness.
H. Individually constructed.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
21-SS
I. LC Fiber Connectors shall be utilized for SM.
J. Boots shall be secured to the jacket with a pliable adhesive.
K. Land connectors on Patch Panel Bulkhead Adapters
18.2 FIBER BULKHEAD ADAPTERS
The following provisions shall apply to the LC Fiber Bulkhead Adapters for FO Cable Splicing within
Cabinets:
A. The Fiber Bulkhead Adapters shall include the following features:
a. One-piece construction.
b. Metallic bodies.
c. Zirconia ceramic sleeves.
Fusion type splices shall be utilized. Mechanical splices shall be prohibited.
FO Cable Splicing shall be allowed in locations denoted in the Plan. Additional locations shall require
the approval of the Engineer and TMS Integrator.
FO Cable Splicing locations shall be within cabinets and splice vaults.
The Contractor shall adhere to the FO cable manufacturer’s methods, recommendations, materials, and
techniques for splicing. All splicing equipment shall be in good working order, properly calibrated, and
meet all industry standards and safety regulations.
The FO cable preparation, splice enclosure installation, and splicing shall be accomplished in accordance
with industry standards. Mechanical stress and splicing locations shall be minimized by training the FO
cable into final position, concurrently observing the minimum bending radii of the FO cable. The
minimum bending radii of the FO cable shall be 20 times the diameter of the cable or as per the
manufacturer’s requirements, whichever is greater.
Cleanliness and freedom from contamination shall be strictly observed with respect to splicing materials
and joint construction. Upon completion of the splicing operation, all waste material shall be deposited in
suitable containers, removed from the job site, and disposed of in an environmentally acceptable manner.
18.3 EXISTING OR INSTALLED OUTDOOR FIBER SPLICE ENCLOSURE
The following provisions shall apply when the Contractor is required to enter an Existing Outdoor Fiber
Splice Enclosure for FO Cable Splicing:
A. Cables
a. FO Cables enter and exit from the same end of the Outdoor Fiber Splice Enclosure.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
22-SS
B. Testing
b. The Contractor shall be responsible for all existing and proposed splices within an Existing
Outdoor Fiber Splice Enclosure.
C. Adjustments
a. The Contractor shall make adjustments to the size of Existing Outdoor Fiber Splice Enclosures to
accommodate additional cables. The contractor shall utilize cable addition kits, butt adapter bolt
kits, and splice trays as required to complete the installation.
D. Pressure Test
a. When FO Cable Splices are to be placed within an existing Outdoor Fiber Splice Enclosure, the
Contractor shall ensure that the Outdoor Fiber Splice Enclosure is properly sealed after
placement. The Contractor shall utilize the following test procedure:
i. Testing shall be performed in the presence of the TMS Integrator when the Outdoor Fiber
Splice Enclosure is in its final hanging position.
ii. Pressurize the enclosure to between 8 to 10 psi and wait 45 seconds. During the 45 second
wait, spray soapy water around the seal to check for leaks.
iii. Recheck the pressure. The enclosure should not have lost more than 2.5 psi.
iv. If the pressure loss is not greater than 2.5 psi and no leaks were detected when soapy water
was sprayed around the seal, the enclosure requires no further testing.
v. If the pressure loss is greater than 2.5 psi or leaks were detected when soapy water was
sprayed around the seal, the Contractor shall repair any leaks and retest the enclosure.
18.4 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed as specified per location. Payment will be made
under Item 2550.602 (FIBER OPTIC CABLE SPLICING) at the Contract bid price per each, which shall
be compensation in full for all costs incidental thereto, including but not limited to Indoor Pigtails, Fiber
Bulkhead Adapters, Existing or Installed Outdoor FO Splice Enclosure, and all materials and labor
necessary to construct the Fiber Optic Cable Splicing.
19. (2550) 334 SERIES FIBER CABINET, FOUNDATION MOUNTED The City of Bloomington furnishes 334 Series Fiber Cabinets for mounting on foundations and installation
by the Contractor. The cabinets are weatherproof, fully wired, comply with UL 508 and CSA inspected.
The Contractor shall be responsible for the following:
A. The Contractor notifies the TMS Integrator or TMS construction pager (612) 640-6815, a minimum of
48 hours before transporting a Control cabinet, or components, from the storage site to the installation
site. The storage site shall be on City of Bloomington property in the Metro-area. The Contractor
inspects the cabinets, in the presence of the TMS Integrator, before the cabinets leave the storage site.
B. The 334 Cabinet has a City of Bloomington furnished one piece dense neoprene gasket. The Contractor
installs the gasket between the cabinet and the foundation.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
23-SS
C. The Contractor accepts responsibility for any damage to the cabinets and its components during loading
and transporting from the storage site to the installation site. The Contractor supplies all equipment
and personnel needed to load, transport, and unload the cabinets.
D. Handling and security of the cabinets until installed.
19.1 SHEATH GROUNDING UNIT
The SGU is provided by the City of Bloomington with new City of Bloomington Furnished 334 Series
Fiber Cabinets for mounting on foundations only.
Grounding
The following provisions shall apply to the grounding of 334 Series Fiber Cabinet, Ground Mounted:
A. Ground the cabinet ground buss to the ground rod with a bare 1/C No. 6 solid copper wire.
B. Connect the Sheath Grounding Unit between the cabinet equipment ground buss and the fiber optic
pigtail armor.
C. The Sheath Grounding Unit is provided with new City of Bloomington furnished Ground mounted
Control cabinets.
D. Route each ground conductor to the ground buss via the straightest route that does not hinder
maintenance or installation activities.
19.2 12 FIBER BULKHEAD (SPLICE/PATCH PANEL) DRAWERS
The City of Bloomington furnishes the rack mounted, 12 Fiber Bulkhead Drawer with the 334 series fiber
cabinet. The 12 Fiber Bulkhead Drawer is pre-loaded with adapters/receptacles and does not include indoor
pigtails. It does provide the following:
A. Pigtail storage, splice protection, and termination.
B. Storage, splice protection, and termination of up to 12 fibers.
C. Access to splices and the back of the splice panel.
D. 483 mm (19 inch) EIA rack compatibility.
19.3 FOUNDATIONS
Foundations shall be shall be in accordance with MnDOT 2565.3, other applicable MnDOT Standard
Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
A. Foundations are located as required by the City of Bloomington Construction inspector. The City of
Bloomington Construction Inspector will stake foundation locations for the Contractor on request.
Provide the City of Bloomington Construction Inspection with 48 hours notice.
B. Concrete Mix 3A32 or equal shall be utilized unless otherwise noted on a MnDOT Standard Plan/Plate,
the plan, or within these provisions.
C. Conduits internal to the foundation shall be constructed per Plan.
D. Conduits within foundations shall be NMC.
E. Grout all openings around conduits as per Plan details.
F. Typically concrete foundations shall be constructed 150 mm (six inches) above and below the finished
grade unless otherwise noted on a MnDOT Standard Plan/Plate, the Plan, or within these Specifications.
G. The Contractor shall furnish and install ground rods as per Plan details. Where multiple items are
located on the same pad it is acceptable to utilize a common ground rod.
H. Precast foundations are allowed.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
24-SS
I. Precast sidewalks are allowed. Remove any lifting loops if installed.
J. Sidewalks shall be constructed as required per plan detail.
K. The Contractor shall grade foundations, provide fill, and haul spoil as needed.
19.4 INSTALLATION Installation of 334 Series Fiber Cabinets shall be shall be in accordance with MnDOT Standard
Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
A. The 334 Series Fiber Cabinet for foundation mounting shall be furnished by the City of Bloomington.
B. The 334 Series Fiber Cabinet foundation shall comply with the Plan detail.
C. Conductors internal to the foundation shall be constructed per Plan.
D. The 334 Series Fiber Cabinet shall be secured to the foundation by utilizing 103 mm (4 inch) long, 10
mm (3/8 inch) diameter, Stainless Steel Quick Bolts (wedge bolts).
E. Provide rodent control poison packets for all 334 Series Fiber Cabinets.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
25-SS
19.5 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed as specified. Payment for INSTALL CABINET for
each type will be made in accordance with the schedule set forth below at the appropriate Contract unit
bid price for each separate item of work, which shall, in each instance, be compensation in full for the
costs incidental thereto, including but not limited to conductors internal to the foundation, mounting on a
foundation, rodent control packets, Racks, and all materials, equipment, and labor required to complete
the work as specified, to the satisfaction of the Engineer.
20. (2550) FIBER OPTIC SPLICE VAULT This work shall consist of furnishing and installing a Fiber Optic Splice Vault, which shall be in accordance
with the MnDOT Standard Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
20.1 SPLICE VAULT
A. Shall be placed on a 300mm (12 inch) thick layer of coarse filter aggregate per Mn/DOT 3149.2H.
B. Cover
The following provisions shall apply to the Cover part of the Splice Vault:
a. Provide one ferrous device to lift the cover from the body of the Splice Vault for every three
Splice Vaults. The ferrous device must be >28 inches in length.
C. The Contractor shall furnish and install a locator ball in the Splice Vault.
D. Near the Splice Vault, the FO Cables sweep up to meet the conduit entrance to the Splice Vault. Take
care not to exceed minimum bend radius.
E. Clean Splice Vaults after installation. All areas shall be cleaned including the flange that the cover
rests on the bolt holes for the cover.
F. The Splice Vault shall be grounded per the detail shown in the Plan. The ground rod shall be in
accordance with MnDOT 3818.
G. APL
MnDOT approved Splice Vault is listed on the following Website:
http://www.dot.state.mn.us/products/index.html
20.2 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed as specified. Payment will be made under Item
2550.514 (FIBER OPTIC SPLICE VAULT) at the Contract bid price per each, which shall be
compensation in full for all costs incidental thereto, including grounding requirements, cover, and all
materials and labor necessary to construct the Splice Vault.
21. (2550) FIBER OPTIC PULL VAULT This work shall consist of furnishing and installing a Fiber Optic Pull Vault, which shall be in accordance
with the MnDOT Standard Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
21.1 PULL VAULT
A. Shall be placed on a 300mm (12 inch) thick layer of coarse filter aggregate per Mn/DOT 3149.2H.
B. Cover
The following provisions shall apply to the Cover part of the Pull Vault:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
26-SS
b. Provide one ferrous device to life the cover from the body of the Pull Vault for every three Pull
Vaults. The ferrous device must be >28 inches in length.
C. The Contractor shall furnish and install a locator ball in the Pull Vault.
D. Near the Pull Vault, the FO Cables sweep up to meet the conduit entrance to the Pull Vault. Take care
not to exceed minimum bend radius.
E. Clean Pull Vaults after installation. All areas shall be cleaned including the flange that the cover rests
on the bolt holes for the cover.
F. APL
MnDOT approved Pull Vault is listed on the following Website:
http://www.dot.state.mn.us/products/index.html
21.2 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed as specified. Payment will be made under Item
2550.602 (FIBER OPTIC PULL VAULT) at the Contract bid price per each, which shall be
compensation in full for all costs incidental thereto, including the cover and all materials and labor
necessary to construct the Pull Vault.
22. (2550) CABINET FOUNDATION CORE DRILLING Provide core drilling in accordance with the applicable provisions of MnDOT 2565.3D2b, and as modified
below:
22.1 CORE DRILLING
Where indicated in the Plans, core drill a hole for installation of the new conduit in the existing concrete
foundation. Use the appropriate core drill size to accommodate the required conduit to be installed as indicated
on the plan. Take measures to ensure that the core drilling operation does not damage any in place equipment
or cables all to the satisfaction of the Engineer.
22.2 MEASUREMENT AND PAYMENT
Measurement will be made by the each constructed as specified. Payment will be made under Item
2550.602 (CORE DRILL SIGNAL PAD) at the Contract bid price per each, which shall be compensation
in full for all costs incidental thereto, including but not limited to, Requirements, Construction
Requirements, and all materials and labor necessary to construct Core Drilled Hole.
23. (2550) MODIFY SERVICE EQUIPMENT This work shall consist of Modify Service Equipment, which shall be in accordance with the Mn/DOT
Standard Specifications, Mn/DOT Standard Plans/Plates, the Plans, and the following:
23.1 LOCATION This work shall be located at American Blvd & Lyndale Ave, and at American Blvd at 12th Ave S. The
Contractor to furnish and install a 15A 1-pole breaker at each location.
23.2 MEASUREMENT AND PAYMENT
Measurement will be made by the each installed as specified. Payment will be made under Item 2550.602
(MODIFY SERVICE EQUIPMENT) at the Contract bid price per each, which shall be compensation in
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
27-SS
full for all costs incidental thereto, including but not limited to Items shown on the Plan Details,
Construction Requirements, and all materials and labor necessary to construct Modify Service Equipment.
24. INSTALLATION OF ETHERNET NETWORK SWITCHES The City of Bloomington furnishes the shelf mounted, Ethernet Network Switches.
24.1 CITY PROVIDED ITEMS
The City shall:
A. Furnish the Ethernet Network Switch. The Ethernet Network Switch will be pre-configured with
necessary network settings such as IP address(es), port settings, etc. It is not anticipated that the
Contractor will need to make configuration changes to the Ethernet Network Switch.
B. Furnish Small Form-Factor Pluggable (SFP) transceivers drivers for fiber optic connections. Please
note that the City of Bloomington does not use bi-directional SFPs.
C. Furnish an appropriate AC power supply for the Ethernet Network Switch.
24.2 CONTRACTOR PROVIDED ITEMS
The Contractor shall:
A. Provide the City 60 day notice prior to when Ethernet Network Switches will be required for
installation.
B. Install the City provided Ethernet Network Switch, SFPs, rack mount kit (if applicable) and power
supply within the cabinet.
C. Furnish and install indoor pigtails for fiber optic connections to the Ethernet Network Switch.
D. Furnish and install Ethernet patch cables for copper connection to the Ethernet Network Switch.
E. Furnish and install appropriate surge suppression for all cables entering the cabinet prior to making the
physical connection(s) to the Ethernet Network Switch.
24.3 MEASUREMENT AND PAYMENT
INSTALLATION OF ETHERNET NETWORK SWITCHES includes but shall not be limited to the
installation of the switches, SFPs, and power supplies, and furnish and installation of indoor pigtails,
Ethernet patch cables, surge suppression, and all materials and labor necessary to complete the installation
and make operational the Ethernet Network Switches. INSTALLATION OF ETHERNET NETWORK
SWITCHES shall be considered incidental for which no direct compensation will be made.
25. (2565) GENERAL TRAFFIC SIGNAL OPERATIONS Location of poles, handholes, pull vaults, and other signal components are shown in the Plans in their
approximate location and will be determined in the field by the Engineer prior to installation.
Within ten (10) days after the date of mailing to the Contractor a notice that the Contract has been approved,
the Contractor shall furnish evidence to the Engineer of having placed orders for the Signal Cable, Signal
Equipment, and Signal hardware. The Contractor shall furnish a list of material and equipment suppliers
and proposed delivery dates. Any items to be used from the Contractor’s stock shall be noted.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
28-SS
The Contractor shall ensure that the existing traffic control system is kept in operation (including loop
detectors where applicable) at all times. The Contractor shall not turn-off an existing traffic control signal
system without the specific approval of, and only in the presence of, the Engineer. The Contractor shall
notify the Engineer at least 48 hours in advance of scheduled turn-offs and before performing work on the
existing traffic control signal system.
During signal and luminaire rewiring and construction phasing requiring the all-way stop control condition,
the Contractor shall keep the signal downtime to a minimum, or at the duration specified by the Engineer,
always with approved traffic control.
During any periods of authorized work suspension, the City will provide and maintain the existing traffic
signal cabinet and control equipment and will maintain the existing control signal system.
The controller phases utilized shall be as shown in the Plans. Cabinet components shall correspond to these
phases.
26. (2565) INPLACE SIGNAL SYSTEM - REMOVAL AND SALVAGE Electrical cables and conductors and all other items of the existing traffic control signal system (including
signs) deemed non-salvageable by the Engineer shall be removed entirely and disposed of outside the right-
of-way in any manner that the Contractor may elect, subject to the provisions of Mn/DOT Spec. No.
2104.3C3.
Where required by the Contract or directed by the Engineer, the Contractor shall remove and deliver to the
City items of the existing traffic control signal system in accordance with Article No. 7 of these
specifications, Division SS Special Provisions, the applicable provisions of Mn/DOT Spec. No. 2565.3U,
and the following:
A. After the controller cabinet and the control equipment are de-energized and power conductors
disconnected, the Contractor shall prevent damage to the cabinet and control equipment as follows:
a. Unplug and remove all removable control equipment (i.e., controller unit, detector amplifier units,
conflict monitor, load switches, etc.) from the cabinet. The equipment removed from the cabinet
shall be suitably packed to prevent damage to the equipment during transportation.
b. Connecting harnesses for the equipment shall be coiled or grouped together and secured to a shelf
in the cabinet. The harnesses can be taped, wired, or tie wrapped, but shall be done by a method
that will prevent the harnesses from being pinched in a door when a door is closed, or from dropping
below the bottom of a cabinet when lifted off a foundation.
c. The cabinet shall be secured in an upright position at all times (removing from foundation,
transporting, loading, and unloading) to ensure that the cabinet will not tip and be damaged.
B. Salvaged items shall be disassembled before being delivered to the City as follows:
a. Vehicle and pedestrian signal faces shall be removed and left intact.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
29-SS
b. Background shields shall be removed from vehicle signal faces without damaging shields or signal
faces.
c. Signal bracketing and pipefittings shall be removed and disassembled without damaging signal
bracketings and signal faces.
d. All other salvable items shall be removed and disassembled as directed by the Engineer.
All costs associated with the removal and salvaging of materials of the existing signal system, hauling of
removed and salvaged materials, and the disposal of non-salvageable materials, all in accordance with the
foregoing, shall be incidental to the unit bid price for the Revise Signal System pay item(s).
27. (2565) TRAFFIC CONTROL SIGNAL MATERIALS AND CONSTRUCTION The revise traffic control signal system(s) shall comprise all of the work shown on the respective plan sheets
for each system, complete, in-place, and in operation, all in accordance with the 2016 Edition of the
Minnesota Department of Transportation "Standard Specifications for Construction", and all supplements
thereto except as shown and noted in the Plans and modified in these specifications and Division SS of the
Special Provisions.
27.1 CONTROLLERS AND CABINETS The city provided controllers, cabinets and all other traffic control signal equipment and components shall
be installed by the Contractor for the signal system as directed by the Engineer. The controller phases
utilized shall be as shown in the plans. Cabinet components shall correspond to these phases.
The Contractor shall pick up the controllers, cabinets and all components thereof for the system from the
Signal Shop of the City of Bloomington Public Works, 1700 W 98th Street, Bloomington, Minnesota, haul
them to the job site and install these control equipment at the project as directed by the Engineer. The
Contractor shall notify the Engineer 14 days before picking up signal equipment.
Each cabinet shall be secured in an upright position when transporting to the job site to insure that the
cabinets will not tip and be damaged.
Anchor rods, nuts and washers for traffic signal cabinets shall be furnished and installed by the Contractor
in accordance with the provisions of Mn/DOT Spec. Nos. 2565.2F, 3385 and 3392.
The Contractor shall install field wiring in the cabinet terminals as directed by the Engineer. Detector
locations and identifications are shown in the plans. Detector numbering and identification shall be as
shown therein. The vehicle detector connector cables in the controller cabinet shall be permanently labeled
with the plan detector numbers to be connected thereto.
The Contractor shall salvage the in-place controller cabinet, controller, and all equipment inside the
controller cabinet.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
30-SS
27.2 SIGNAL MOUNTING
Signal head mounts and all required appurtenances for mounting vehicle and pedestrian signal faces to mast
arms, vertical pole shafts, and pedestal shafts shall be in accordance with these specifications and as detailed
in the Plans.
All vehicle and pedestrian signal faces shall be installed in accordance with Mn/DOT Spec. No. 2565.3L,
except as follows:
Vehicle and pedestrian signal faces to be mounted on vertical pole shafts, on pedestal shafts, or on mast
arms shall utilize approved straight or angle mounts and required appurtenances as detailed below.
The Contractor shall furnish and install the required through-bolts for connecting the individual sections.
In all cases, two sections of the vehicle signal head shall be mounted below the straight or angle mount with
the remaining sections mounted above the straight or angle mount. The indications above or below the
straight or angle mount shall be fastened together by means of a noncorrosive 3-bolt mounting assembly.
The 3-bolt mounting assembly shall utilize locknuts to prevent the assembly from loosening.
The installation of the vehicle and pedestrian signal faces shall be to the satisfaction of the Engineer.
A. Straight and Angle Mount Plumbizers:
The Contractor shall furnish and install straight or angle mount plumbizers at locations as indicated in the
Plans. The straight and angle mount plumbizers shall be Mn/DOT approved straight or angle mount
plumbizers as listed on the Mn/DOT Approved/Qualified Products List Web site for Signals:
http://www.dot.state.mn.us/products/index.html
B. Straight and Angle Mount Caps:
The Contractor shall furnish and install straight or angle mount caps at locations as indicated in the Plans.
The straight and angle mount caps shall be Mn/DOT approved straight or angle mount caps as listed on the
Mn/DOT Approved/Qualified Products List Web site for Signals:
http://www.dot.state.mn.us/products/index.html
C. Threaded Hub and Flange Pole Adaptor:
The Contractor shall furnish and install threaded hub and flange pole adaptors at locations as indicated in
the Plans. The threaded hub and flange pole adaptors shall be Mn/DOT approved threaded hub and flange
pole adaptors as listed on the Mn/DOT Approved/Qualified Products List Web site for Signals:
http://www.dot.state.mn.us/products/index.html
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
31-SS
D. Indications:
All unused or conflicting indications shall be covered with an Engineer approved material that does not
allow indications or reflected light from the indications to be viewed
27.3 SIGNAL HEADS AND HOUSINGS
All vehicle and pedestrian signal heads shall be standard ITE black poly-carbonate. Qualified Poly
Carbonate signal heads are listed on the Mn/DOT Qualified Products List Web site for signals:
http://www.dot.state.mn.us/products/index.html
27.4 VEHICLE SIGNAL FACES
All vehicle signal faces shall be in accordance with the provisions of Mn/DOT Spec. No. 3834, except as
noted. The Contractor shall install, aim, and tilt each signal indication as directed by the Engineer.
The installation of the vehicle signal faces shall be to the satisfaction of the Engineer. All "Red", "Yellow",
and "Green" signal indications shall utilize light-emitting diode (LED) units. Mn/DOT approved LED
Signal Indications are listed on the Mn/DOT Approved/Qualified Products Lists WEB site for Signals:
http://www.dot.state.mn.us/products/index.html
Vehicle signal faces shall utilize either straight or angle mounts. The mounts shall be in accordance with
Article No. 12.2 of these specifications and as detailed in the plans.
The Contractor shall furnish and install a metal support plate (supplied by the signal head Manufacturer)
on the inside of the signal indication at the attachment point of the straight or angle mount plumbizer (one
plate each for inside the upper and lower signal housing at the attachment point).
The Contractor shall also furnish and install the required through-bolts for connecting the individual
sections. In all cases, two sections of the vehicle signal head shall be mounted below the straight or angled
mount with the remaining sections mounted above the straight or angled mount. The indications above or
below the straight or angled mount shall be fastened together by means of a noncorrosive 3-bolt mounting
assembly. The 3-bolt mounting assembly shall utilize locknuts to prevent the assembly from loosening.
The Contractor shall install, aim, and tilt each signal indication as directed by the Engineer
For each LED signal indication, the Contractor shall submit prior to procurement to the Engineer, for
approval, four copies of all warranty information indicating the required 5-year warranty period (from date
of installation), shop drawings, product invoice, manufacturer, a Manufacturers’ Certificate of
Conformance to this specification, model number, and serial number.
The Contractor shall, to the satisfaction of the Engineer, affix to the back of each “LED” signal
indication, a permanent label indicating the date of installation.
All standard vehicle signal indications and faces, pedestrian signal indications, and signal mountings shall
be designed to withstand the dead load, plus a wind load of approximately 30lbs/ft2, plus a normal ice load,
plus an appropriate safety factor.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
32-SS
27.5 EMERGENCY VEHICLE PREEMPTION (EVP) EXTENSION HARDWARE
The Contractor shall provide extension hardware for the in-place EVP confirmation indication and
detector, as shown in the Plan. The extension hardware shall be the same O.D. as the traffic signal
bracketing framework; a reducer conduit fitting shall be used to attach the detector and indicator light
assembly to the appropriate surface.
All extension hardware shall be painted the same color as the surface to which it is attached. The detector
and indicator light assembly shall not be painted.
All hardware shall be tightened securely.
The detector and indicator light shall be installed and mounted in such a way so as to ensure the
watertight integrity of the complete assembly.
The Contractor shall be responsible for determining if there is enough slack in the in-place EVP cables to
all for the appropriate extension to be installed prior to disconnecting the in-place EVP equipment. There
shall be no detector cable splices from the EVP detector to the traffic signal cabinet.
If necessary, the Contractor shall furnish and install a new EVP cable (3/C#20) continuous without
splices or terminals from the EVP detector to the traffic signal cabinet via existing conduit, handholes,
etc. 3/C#20 cables shall be pulled into the controller cabinet labeled (by cable number and phase number)
by the Contractor, and shall be installed and made operational by the Contractor.
27.6 TRAFFIC SIGNAL CONTROL CABLES AND CONDUCTORS
New traffic signal control cables for the permanent signal systems (to be furnished and installed by the
Contractor), except loop lead-in cables, shall be Type B (ICEA-NEMA Type B Control Cable), in
accordance with Mn/DOT Spec. No. 3815, installed as a continuous run without splices from the signal or
the detector to the controller except where the cabling shown in the Plans specify a terminal block, tap, or
splice. All cable installed in conduit shall be pulled by hand.
Not less than 3 feet of slack cable for each cable shall be left in each handhole through which a run of cable
passes, except that a minimum of slack cable and conductors for detector loop lead-ins shall be left in the
handholes through which they pass to prevent the formation of secondary loops. Slack cable in each
handhole shall be stored above the handhole floor, utilizing handhole shoulder eyebolts for support.
Not less than 24 inches of slack cable for each cable shall be left in each mast arm pole base, light standard
base, and traffic signal pedestal base. The Contractor shall make connections of all conductors in pedestal
and mast arm bases with grease filled wire nuts (pre-filled custom sealant that locks out moisture and air,
no on-site assembly or multi-piece kits). Wire nuts shall point upwards in the mast arm pole vertical shaft
to prevent water collection and intrusion.
The contractor shall label all cables as designated below and in accordance with applicable provisions of
MnDOT Spec. No. 2565.3J, or as directed by the Engineer. In addition to the information provided below,
the contractor shall provide and install labels on all wires within pole bases, handholes, and controller
cabinet meeting the following requirements:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
33-SS
a. Self-adhering label.
b. Machine printed numbers and letters
c. Suitable for placement in damp locations
d. Paper based labels are not acceptable.
Cable Markings:
All electrical cables, except Loop Detector Lead-in Cable - IMSA 50-2 and the 3/C #20 Emergency Vehicle
Preemption (EVP) Detector Cable used in signal system construction shall have the jacket surface ink
printed with the following information:
a. Manufacturer Name
b. Year of Manufacture (Date Code)
c. Type of Wire or Cable (i.e. TC, XHHW-2, THWN)
d. Size and Number of Conductors
e. Voltage Rating
f. Conductor Insulation Rating
g. Nationally Recognized Testing Laboratory (NRTL) Certification Mark indicating the cable
is listed. [i.e. UL, ITSNA (ETL), CSA]
h. Labeled as sunlight resistant (Sun Res), direct burial (Dir Bur), Oil Resistant 1 (Oil Res 1)
Signal Control Cable shall have additional markings as follows.
a. Traffic Signal Cable
b. Foot Markers
c. -35º C Cold Bend
Emergency Vehicle Preemption (EVP) Detector Cable ( 3C # 20) shall be surface marked in accordance
with the National Electrical Code (NEC) and shall have additional markings as follows:
a. Labeled as sunlight resistant, direct burial
b. Year of Manufacture ( Date Code)
c. Conductor Insulation Rating
d. Foot Markers
All cable markings shall be repeated at intervals not exceeding 24 inches on the jacket surface.
All field wiring terminations shall be as indicated on the field wiring diagram included in the Plan
set.
The following cables are not required to be listed by a Nationally Recognized Testing Laboratory
(NRTL):
2/c #14 (Loop Detector Lead-in Cable)
3/C #20 (EVP cable)
Conductors within a signal pedestal, or mast arm pole, from the cabled conductors in the base to the terminal
block in the signal head shall be Type THWN, No. 14 A.W.G., with stranded conductors. Each optical unit
of the signal head shall be wired separately to the cable conductors in the corresponding pedestal or mast
arm base. Cross wiring for heads will not be permitted.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
34-SS
Neutral conductors smaller than No. 4 A.W.G. shall be color-coded white at the time of production. Field
painting or taping will not be accepted from conductors smaller than No. 4 A.W.G.
Insulated spade lugs furnished and installed by the Contractor shall be used for terminal block connection
of all conductors in the controller cabinet.
All wiring shall be installed in accordance with the Plan and Mn/DOT 2565.3J, except as indicated in these
specifications or in Division SS Special Provisions.
The Contractor shall pull cables and conductors through non-metallic conduit (NMC) with a pull strap, as
approved by the Engineer, in such a manner as to not split or otherwise damage the NMC conduit due to
“pull rope abrasion”. If the Contractor damages the NMC conduit, the Contractor shall replace the
damaged portion of the NMC conduit to the satisfaction of the Engineer.
27.7 MEASUREMENT AND PAYMENT
Furnishing and installing Signal Mounting, Signal Heads and Housing, Vehicle Signal Faces, EVP
extension hardware, and Traffic Signal Control Cable and Conductors and installing City provided Traffic
Cabinets and Controllers, specifically to provide for the revision of signal systems, as contained in these
Specifications and in the Plans will be considered incidental to the REVISE SIGNAL SYSTEM pay item
and no direct compensation will be paid thereto.
28. (2565) ACTIVATING SIGNALS Mn/DOT Spec. No. 2565.3AA is hereby deleted and replaced with the following:
A. Prior to Activating Signals
Prior to the day of signal activation, the Contractor shall perform testing and verification of equipment and
materials of the traffic signal system to prevent delays and minimize malfunctions during signal activation.
The Contractor shall notify the Engineer at least 24 hours in advance of the schedule pre-activation testing.
The pre-activation test shall include:
a. Verification that all required equipment in controller cabinet is present.
b. Testing of installed equipment, inside and outside of controller cabinet (conflict monitor,
pushbuttons, vehicle detectors, EVP light and detector, interconnect, railroad interface, etc.).
c. Verification that all signal and pedestrian indications, video cameras, EVP detectors and indicator
lights are operational and properly aimed.
d. Verification that cables are labeled and controller assembly has been checked to fully operate all
required timing functions and resolve any wiring conflicts.
e. Verification that power supply is active.
B. Activating Signals
When the signal system is to be placed in operation, all vehicle signal faces and pedestrian indications shall
be unbagged and aimed, as directed by the Engineer. The Contractor shall notify the Engineer at least 48
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
35-SS
hours in advance of the scheduled traffic signal turn-on and notify the Engineer if there are any changes to
the timeline.
The traffic control signal system will be turned on by City personnel, unless otherwise authorized by the
Engineer. The Contractor shall be present at time of turn on to provide assistance to ensure the traffic
control signal system is operating correctly and in a safe manner.
The Contractor shall provide all necessary parts and labor to rectify any malfunctioning components of the
traffic control signal system installed by the Contractor. This requirement would not include Department
furnished material/components, except if the Department furnished material/components were
malfunctioning, or damaged, due to Contractors operations.
All components of the signal system, including the emergency vehicle preemption (EVP) and the traffic
control interconnection, must be completely operational to the satisfaction of the Engineer before the actual
signal system turn on is performed.
The Contractor shall not turn the signal system ON or OFF, or place in flashing mode of operation, without
the specific approval of, and in the presence of the Engineer.
At the time of signal activation, the Contractor shall have on hand at each site:
• two spare indications and two spare lamps of each color and type (for vehicle, pedestrian indications
and EVP)
• workers and equipment to reach overhead indications
Activation of the traffic signal shall be in accordance with MMUTCD 4D.31 for red-red flashing mode. A
steady red clearance interval of 6 seconds shall be provided during changes from red-red flashing mode to
steady (stop-and-go) mode unless otherwise directed by the Engineer.
The Engineer may require the erection of “Signal Ahead” signs or “Traffic Control” signs in advance of
the intersection. When required, these signs shall be furnished and installed by the Contractor, incidental
to the cost of the signal system pay item.
Activation of new or revised traffic signal systems shall occur in conjunction with the scheduled road
opening unless otherwise directed by the Engineer. The activation may not be scheduled on Fridays,
weekends, holidays or the day before a holiday because of possible malfunction of the revised traffic signal.
29. (2564) TRAFFIC SIGNS AND DEVICES
29.1 GENERAL
The Contractor shall furnish and install new Type C Sign Panels on traffic signal mast arms, on mast arm
pole shafts, or on pedestal pole shafts as indicated in the Plans. This work shall consist of furnishing and
installing new Type C Sign Panels at the locations indicated in the Plans, in accordance with the applicable
provisions of Mn/DOT Spec. No. 2564, with the details shown in the Plans, and as follows:
Each Type C Sign Panel shall be in accordance with the Standard Sign Drawings of the Mn/DOT Standard
Signs Manual.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
36-SS
29.2 MOUNTING SIGN PANELS
The Contractor shall install the mast arm mounted signs at the locations indicated in the Plans; to the
satisfaction of the Engineer; and as follows:
The structural details for signal mast arm mounted signs shall be installed in accordance with the
Mn/DOT Standards Signs Manual, Page 105A. Each mast arm mounted sign panel shall be provided
with the Ultra-Lok Mounting Bracket System. Approval shall be obtained by submitting product
specifications and strength calculations, demonstrating compliance with the 2001 Edition of the
"AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and
Traffic Signals."
29.3 FABRICATION STICKERS
The Contractor shall furnish and install a fabrication sticker and affix to the lower right corner of the
backside of each new Type C sign panel in accordance with the following:
The sticker shall have the month and year of fabrication of the sign panel punched out prior to installation
of the sticker on the sign panel. The Contractor shall provide a full size mockup (minimum 1 ½-inch x 3-
inch) of the sticker (black legend on a white reflectorized background) to the Engineer for approval. No
fabrication stickers shall be produced prior to written approval.
29.4 MEASUREMENT AND PAYMENT
The payment for furnishing and installing each new Type C sign panel at the locations indicated in the
Plans and also as specified herein shall be considered incidental to each Revise Signal System pay item.
30. (2565) TRAFFIC MONITORING SYSTEM The Contractor shall remove in-place Closed Circuit Television (CCTV) Camera, cables and associated
equipment; and furnish and install CCTV hardware in accordance with the MnDOT Standard
Specifications, MnDOT Standard Plans/Plates, the Plans, and the following:
The Contractor shall remove in-place CCTV Camera, mounting bracket, cables, cabinet, foundation and
service equipment as indicated in the Plan. The Contactor shall coordinate with Xcel to de-energize the
cabinet at Traffic Monitoring System B. The Contactor shall notify the Project Engineer 72 hours prior to
the de-energizing of the cabinet at Traffic Monitoring System B.
CCTV hardware shall include all materials and labor necessary to construct a camera surveillance system
including, but not limited to, CCTV Camera, CCTV Mounting Bracket, CAT5E Ethernet Cables, and
associated equipment.
The Contractor shall be responsible for furnishing, installing, terminating and splicing all cables to provide
an operational camera surveillance system.
Ten (10) feet of all camera related cables shall be neatly coiled and stored in cabinets. Three (3) feet of all
camera related cables shall be neatly coiled and stored in Junction Boxes and Handholes.
The Contractor shall be responsible for properly grounding all CCTV Hardware and related equipment.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
37-SS
30.1 CCTV CAMERA The Contractor shall furnish and install a Cohu Electronics 4260HD CCTV Camera (model number 4261-
1000) which includes an HDTV/H.264 IP67 camera positioning system, HDTV 1080p camera with 30x
optical zoom lens and IP67 housing with heater.
30.2 CCTV MOUNTING BRACKET
The Contractor shall furnish and install four (4) Cohu Electronics Large Pedestal Plate (p/n 8481-9) for
installation of the camera on top of the CCTV pole as shown in the Plans.
The Contractor shall furnish and install all hardware necessary to mount the CCTV Camera to the
satisfaction of the Engineer.
30.3 CAT5E ETHERNET CABLES
The Contractor shall furnish and install CAT5E Ethernet cables.
30.4 CCTV POWER
The CCTV specified in section 13.1 is powered through the CAT5E Ethernet Cable. The City provided
switches at the CCTV locations will include the capacity to provide Power over Ethernet (PoE) to the
CCTVs.
30.5 OUTDOOR SURGE PROTECTIVE DEVICE FOR POE++
The Contractor shall furnish and install a Surge Protective Device, Power over Ethernet (PoE++): PD-
OUT/SP11 or equivalent, CohuHD p/n 7412009-001.
The Contractor shall install the Surge Protective Device for PoE++ in the signal system controller cabinet
or 334 fiber cabinet as shown in the Plans, or as directed by the Engineer.
30.6 MEASUREMENT AND PAYMENT
Removal of in-place CCTV Camera, mounting bracket, cables, cabinet, foundation and service equipment;
and furnishing and installing CCTV Camera, mounting bracket, cables, Outdoor Surge Protective Device
and all other materials and electrical equipment, specifically to provide for a Traffic Monitoring System, as
contained in these Specifications and in the Plans will be considered incidental to the TRAFFIC
MONITORING SYSTEM pay item and no direct compensation will be paid thereto.
31. (3831) LUMINAIRE EXTENSION The Contractor shall provide a luminaire extension as part of a Traffic Monitoring System, as shown in the
Plan.
31.1 LUMINAIRE POLE SHAFT EXTENSION
The luminaire pole shaft extension shall be as shown in the plans and in accordance with Mn/DOT Spec.
No. 3831 and as indicated in these specifications and Division SS Special Provisions.
Extensions shall be fabricated from high strength, low alloy structural steel conforming to the requirements
of 3309, and shall provide the dimensions, clearances, details, and general configurations shown in the
Plans.
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
38-SS
The luminaire pole shaft extensions shall be designed to withstand the loadings of the CCTV hardware
where shown in the Plans, including the normal and torsional stresses produced thereby. The specific
dimensions or loadings, if shown in the Plans, shall be taken into account for design of particular units to
be furnished under the Contract. Each extension shall be designed and constructed in accordance with the
latest requirements of the 2001 AASHTO standard with 90 mph wind load and fatigue category 3 and less
galloping and less truck gusts.
The interior and exterior surfaces of the extension shall be given a shop coat of rust inhibitive metal primer.
The metal components shall be painted in accordance with Article No. 32 of these specifications and
Mn/DOT Spec. No. 2565.3T.
Semi-blind flanges shall be continuously welded into the pole shafts at the angles and elevations shown in
the Plans. Threading of these flanges shall be for nominal 1.5 inch steel pipe fittings.
All anchor bolts shall be uniform 2” diameter X 90” X 6”L ASTM F1554, grade 105, with 2 nuts spaced
on 12”centers with 17” bolt circle.
Anchor bolts, nuts, and washers shall conform to the requirements of ASTM F1554 Grade 105 for high
strength bolts. Top 10 inches of the anchor bolts, nuts, and washers, if any, shall be hot dip galvanized in
accordance with ASTM A153. Anchor bolts shall be adequate for the loadings produced by the structure.
Dimensions shown in the Plans shall be minimums.
31.2 MEASUREMENT AND PAYMENT
Furnishing and installing the luminaire extension all other materials, specifically to provide for the traffic
monitoring system, as contained in these Specifications and in the Plans will be considered incidental to
the Traffic Monitoring System D pay item and no direct compensation will be paid thereto.
32. (2478, 2565) PAINTING Painting metal structures and metal components of a traffic control signal system, when required, shall
conform to all applicable provisions of Mn/DOT Spec. No. 2565.3X, and Mn/DOT Spec. No. 2478
except:
The luminaire extension shall be painted at the manufacturer. The Contractor shall touch up any damaged
painted surfaces to the satisfaction of the Engineer using touch up paint as supplied by the pole
manufacturer. The luminaire extension furnished by the Contractor shall be delivered with touch up paint
as supplied by the pole manufacturer.
Field painting of luminaire extension, other than touch up painting, shall not be permitted, unless
specified in the plans.
The interior and exterior of the luminaire extension shall have a shop coat of rust inhibitive metal primer.
The metal components shall have one of the following color schemes as identified by the Engineer in the
contract documents:
City Proj. No. 2016-202
S.P. 107-030-006
CITY OF BLOOMINGTON TRAFFIC SIGNAL UPGRADES
Special Provisions, Division SS
39-SS
A. “Dark Bronze” baked-on finish on the luminaire extension, and related metal components; Finish
shall be as noted above on hot-dipped galvanized poles.
SIGNAL SERVICE CABINETS AND CITY FURNISHED TRAFFIC SIGNAL CABINETS SHALL
NOT BE FIELD PAINTED.
33. AS-BUILTS
The Contractor shall provide construction as-builts for any constructed location that deviates from the
Plans. Furthermore, the Contractor shall provide construction as-builts for any inaccuracies shown in the
plans for existing infrastructure discovered during construction.
The Contractor shall furnish four (4) copies of as-built plans that contain any changes in the following:
• Types of foundations;
• Signal bracketing or signal mounts;
• Conduit sizes;
• Conduit runs;
• Number of pull vaults
• Number of splice vaults;
• Vault locations;
• Wiring;
• Cable path; and
• Other items as required by the Engineer.
The Contractor shall provide as-builts of the communication cable testing for all CAT 6 and Fiber Optic
Cables.
The Contractor shall provide an as-built fiber map. The as-built fiber map shall document schematic
routing and links between end devices, device IP addresses, device MAC addresses, fiber strands used
along each link, and network switch port utilization. This submittal must be made in an editable
electronic format (e.g. Microsoft Visio, AutoCAD, etc.) so that the City can update the document at a
later date.
All as-builts shall be in a form that is satisfactory to the Engineer.