Citizens’ Bond Oversight Committee Update...Citizens’ Bond Oversight Committee Update . Board of...
Transcript of Citizens’ Bond Oversight Committee Update...Citizens’ Bond Oversight Committee Update . Board of...
Citizens’ Bond Oversight Committee Update
Board of Education September 10, 2015
Littleton Public Schools
Update on Summer Work ●Schools/facilities:
○Arapahoe (roofing), Centennial, ESC, Goddard, Littleton (including tennis courts), LPS Stadium, Newton, Peabody, Runyon, Sandburg, The Village at North, TSC, and Wilder.
●Host schools/facilities:
○Ames, ESC, Euclid, Field, Heritage, Highland, Lenski, Moody, Twain, and Whitman.
2
Summer Work: Arapahoe High School
3
Roof
New chiller
Additional photos accessible on Bond website.
Summer Work: Centennial Academy
4 Additional photos accessible on Bond website.
Fine arts room
Roof
Vertical air handler in the classroom
Summer Work: Education Services Center
5 Additional photos accessible on Bond website.
Security command center IT distribution room
Summer Work: Goddard Middle School
6 Additional photos accessible on Bond website.
Gym floor
Summer Work: Littleton High School
7 Additional photos accessible on Bond website.
Performance center addition Theatre upgrade construction
Pool Roof
Summer Work: LPS Stadium
8 Additional photos accessible on Bond website.
Ramp
New stadium handrails
Summer Work: Newton Middle School
9 Additional photos accessible on Bond website.
Vertical air handler and ducting
Roof
Main Office Entrance
Summer Work: Peabody Elementary School
10 Additional photos accessible on Bond website.
Roof
Running cable
Main distribution frame room
Vertical air handler
Clock and integrated fire alarm/voice/intercom
Summer Work: Runyon Elementary School
11 Additional photos accessible on Bond website.
Summer Work: Sandburg Elementary School
12 Additional photos accessible on Bond website.
Addition interior and exterior
Donation brick placement
IT main distribution frame room
Summer Work: The Village at North
13 Additional photos accessible on Bond website.
IT main distribution frame
Ventilation ducting
New fire alarm panel
Summer Work: Transportation Services Center
14 Additional photos accessible on Bond website.
Entrance
Bus wash
Summer Work: Wilder Elementary School
15 Additional photos accessible on Bond website.
Grounds
Main hallway carpeting
Additional Information ●Vertical air handlers (unit ventilator replacements) are
much quieter. o Getting good feedback!
●Budget reconciliation. o Costs continuing to come in high.
●Project deferrals to conserve funds for “major elements” and to ensure schools designated for Years 3 and 4 still have funding. o Deferrals include new fire sprinklers (not required by
code), all but most-needed flooring and restroom/locker room improvements, and most
non-instructional space upgrades. 16
Questions?
17