CIP Work Session #2FY 2015‐2024 Non‐Capacity
Project PlanJanuary14,2014
SchoolBoardWorkSession
www.acps.k12.va.uswww.acps.k12.va.us2
Essential Questions
• WhataretheproposedFY2015‐2024non‐capacityprojects?
• Whatfactorscontributedtotheprojectprioritization?
• WhatisthefundinggapwiththeCityCouncil’sFY2014‐2023ApprovedCIP?
www.acps.k12.va.uswww.acps.k12.va.us3
6 Project Categories1.AssetLossPrevention:
– Projectsthatpreventthelossofexistingassets.– Ex:AccessControl&SecurityManagement,UpgradeTransportationFacility
2.EcoCity:– “Greenovation”projectsthatreduceenergyuseandtheACPScarbonfootprint.
– Ex:Majorgreenroofmaintenance
3.EquipmentandSystemsReplacement:– Replacementofexistingbuildinginfrastructureandequipmentinexistingfacilities.
– Ex:HVACReplacement,ElevatorReplacement,Stormwatermanagement
www.acps.k12.va.uswww.acps.k12.va.us4
6 Project Categories
4.FacilityMaintenance:– Projectsbasedonindustry‐widemaintenancestandards.– Ex:Plumbing/RestroomUpgrades,SiteHardscapeRepairs,BuildingEnvelopeRepair
5.InstructionalEnvironment:– Projectstoimprovetheinstructionalenvironmentateachsite.– Ex:Interiorrenovations,ProjectPlanning
6.SharedProgramPriorities:– ProjectsundertakenincollaborationwithCityDepartmentssuchasRecreation,ParksandCulturalActivitiesandGeneralServices.
– Ex:ReplacebleachersatCoraKellyRecreationCenter
www.acps.k12.va.uswww.acps.k12.va.us5
Project Prioritization• Tier1
• BuildingEnvelope• HVAC/ClimateControl• Elevator• RoofReplacement
• Tier2• AccessControl• MasterKey• Stormwatermanagement• CodeCompliance• ProjectPlanning
• Tier3• Painting• Flooring• Playgrounds/SportsArea• Plumbing
www.acps.k12.va.uswww.acps.k12.va.us6
FY 2015‐2019 CIP Non‐Capacity BudgetFY2015$11.99millionFY2016$11.81millionFY2017$12.08millionFY2018$11.86millionFY2019$11.84millionTotal$59.58million
www.acps.k12.va.uswww.acps.k12.va.us7
CIP Funding‐ Non‐CapacityFY 2015‐2024
• FY2014‐2023SchoolBoardapprovednon‐capacitybudgetexceededtheCityCouncil’sallocationtoACPSby$38.9million
• Appliedprioritizationmethodologyandlevel‐loadingtomeetCityCouncilapprovedtotalnon‐capacityfortheten‐yearprogram
• Note:Forprojectionpurposes,theCityCouncil’sFY2024fundingisestimatedatthesamelevelasFY2023.
FY2014-2023 Final School
Board CIP- Non-Capacity
FY2014-2023 Final City
Council CIP-Non-Capacity
FY2015-2024 Resource-
Constrained CIP-Non-Capacity
Difference in FY15 RC Non‐Capacity and FY14 City Council Approved
Non‐Capacity CIP
FY 2015 8,011,387 6,956,000 11,985,452 (5,029,452)
FY 2016 6,665,781 4,808,000 11,808,279 (7,000,279)
FY 2017 44,296,403 33,258,000 12,077,457 21,180,543
FY 2018 24,020,735 21,229,533 11,875,094 9,354,439
FY 2019 24,030,973 17,648,000 11,839,966 5,808,034
FY 2020 14,313,842 10,360,000 14,874,892 (4,514,892)
FY 2021 9,898,484 7,049,000 14,977,281 (7,928,281)
FY 2022 19,344,555 14,133,000 14,867,962 (734,962)
FY 2023 13,582,237 9,812,000 14,988,176 (5,176,176)
FY 2024 - - 15,416,455 (15,416,455)
Grand Total 164,164,397 125,253,533 $ 134,711,015 (9,457,482)
www.acps.k12.va.uswww.acps.k12.va.us8
FY 2015 Non‐Capacity Project SummaryFY 2015 Project Description/Site Project Budget
SchoolBusesandVehicles $1.28MEmergencyRepairs/Asbestos/Renovations/CodeCompliance
$0.41M
FF&E $0.30MLongRangePlanning $0.32MProjectPlanning $0.40MAccessControl&KeyReplacement $0.45MElevator FrancisC.Hammond $1.13MParkingExpansion JohnAdams;
TransportationFacility$2.20M
BuildingEnvelope CB,GW,JA,LC,MM,MV,Rowing,T.C.W.:MH
$2.91M
HVACReplacement CB,DM,GM,GW,MV,ST,JKP $1.98MRoofReplacement GeorgeWashingtonAnnex $0.34MMaintenanceUntilBuildingReplacement
PatrickHenry,CoraKelly $.013M
BleacherReplacement CoraKelly $0.04MStormwater Management JohnAdams $0.01MPressBoxReplacement T.C.Williams:KingStreet $0.07M
GrandTotal $11.99M
www.acps.k12.va.uswww.acps.k12.va.us9
Major Building Envelope Projects• CharlesBarrettFY2015$0.71million
– Repairexistingbuildingfenestrationtopreventwaterinfiltrationtothebuildinginterior.
– Repairexteriormasonrycladding.
www.acps.k12.va.uswww.acps.k12.va.us10
Major Building Envelope Projects• GeorgeMasonFY2015$0.2millionandFY2019$0.78million– Repairexistingbuildingfenestrationtopreventwaterinfiltrationtothebuildinginteriorandwaterproofsubsurfacewallsatbasementlevelelectricalroom.
– Replaceexteriorwindowswithnewenergyefficientassemblies.
www.acps.k12.va.uswww.acps.k12.va.us11
Major Building Envelope Projects• JohnAdamsFY2015$0.17million– Repoint/repairexteriorbrickmasonryandinstall/replaceexteriorsealants
• MountVernonFY2015$0.23million– Repoint/repairexteriorbrickmasonryandinstall/replaceexteriorsealants
– Remediatewaterinfiltrationandreplaceexteriordoors.
JohnAdams
www.acps.k12.va.uswww.acps.k12.va.us12
Major Building Envelope Repair
• RowingFacilityFY2015$0.42million– Replacefailingexteriorsiding.
www.acps.k12.va.uswww.acps.k12.va.us13
Major Building Envelope Projects• T.C.WilliamsMinnieHowardFY2015$0.14million– Repairexistingbuildingfenestrationtopreventwaterinfiltrationtothebuildinginterior.
www.acps.k12.va.uswww.acps.k12.va.us14
Major HVAC Projects • GeorgeMasonFY2015$0.13millionandFY2016$0.25million– Replacechillerand“Univent”wallunit– CurrentDeficiencies:
• Increasingvolumeof“DownTime”• Partsforrepairslessavailable• 85%ofschooldoesnothaveautomatedcontrols
• On‐goingcontrollerfailuresforthechillerpump
www.acps.k12.va.uswww.acps.k12.va.us15
Major HVAC Projects• MountVernonFY2015$0.17million:
– ReplaceRTU#6and#9whichhaveexceededtheirlifeexpectancy.
– CurrentDeficiencies:• Compressorfailures• Substantialrusting• Controlsnotintegrated
www.acps.k12.va.uswww.acps.k12.va.us16
Major HVAC Projects• DouglasMacArthurFY2015$1.03million:– ReplaceoutdatedengineeredairunitsRTUs#1through#5
– ReplaceRTUs#8,#9,#14,#15whichhaveexceededtheirlifeexpectancy
– CurrentDeficiencies• Constantleakrepairs• Compressorsfailing• Condensationrusting• Controlsoutdated• Partsforrepairsnolongeravailable
www.acps.k12.va.uswww.acps.k12.va.us17
Major HVAC Projects
• FrancisC.HammondFY2016$0.29million– ReplaceYorkAHU‐1,AHU‐3andAHU‐6– Replacechilledwaterpumps
• JamesK.PolkFY2018$0.32million– ReplacelibraryRTUs– UpgradeiVu controlsystemandintegratewithexistingcontrolsystem
FrancisC.Hammond
www.acps.k12.va.uswww.acps.k12.va.us18
Major Elevator Projects
• FrancisC.HammondFY2015$1.13million– AddsasecondADAelevatortoprovidedirectaccessfromthemainlobbytoalltheclassroomsandthemediacenter(deferredfromFY12)
• CharlesBarrettFY2017$0.27million– Replaceexistingelevator– Currentdeficiencies:
• Controllerisoutdated• HigherVolumeof“DownTime”• Approximately20ServiceCallsduring2012
www.acps.k12.va.uswww.acps.k12.va.us19
Major Roof Projects• GeorgeMasonFY2016$0.26millionandFY2019$0.95million– GymRoofReplacement– MainBuildingRoofReplacement
• GeorgeWashingtonFY2016$1.24million– Replaceoutofwarrantyexistingroofsystemtoincreaseinsulationandlowerenergyuse
GeorgeWashington
www.acps.k12.va.uswww.acps.k12.va.us20
Major Roof Projects• JohnAdamsFY2016$2.1million
– Replaceoutofwarrantyexistingroofsystemtoincreaseinsulationandlowerenergyuse
www.acps.k12.va.uswww.acps.k12.va.us21
Transportation Facility Project• UpgradeTransportationFacility
– FY2015$1.98millionforparkinglotexpansion
– FY2017$6.50millionforbuildingupgradeandphase2ofparkinglotexpansion
www.acps.k12.va.uswww.acps.k12.va.us22
Division‐Wide Projects
• ProjectPlanning$0.40millionannually– Improveprojectplanningforprojectsatleast1 to2yearspriortotheexecutionofthework.Allowstimeforproperscoping,costestimating,coordinationandpermitting
• EmergencyRepairsFY2015‐2024$0.96million– System‐widerepairstobuildingsystemsthataffectsafetysuchasbrokenpipes,hotwatersystems,roofleaks,andbrokenwindows
www.acps.k12.va.uswww.acps.k12.va.us23
Division‐Wide Projects• CodeComplianceRequirementsFY2015‐2024$1.06million– System‐wideupgradestoexistingfirealarmsystemsorotherregulatoryupgradesasrequiredtocomplywithnewfirecodesordirectivesfromtheCityFireMarshal/CodeEnforcement
• Furniture,Fixtures&EquipmentFY2015‐2024$4.05million– Additionandreplacementoffurniture,fixturesandequipmentaspartoftheroutinereplacementcycleorasnecessaryforemergencies
• SchoolBusesandVehiclesFY2015‐2024$6.62million
www.acps.k12.va.uswww.acps.k12.va.us24
Key Decisions
• Provideconcurrencewithprojectpriorities.• ProvideconcurrencewiththelevelfundingstrategytoaddressthegapbetweentheSchoolBoardandCityCouncil.
www.acps.k12.va.usInterimSuperintendent SchoolBoard
KarenA.Graf,ChairmanKellyC.BoozRonnieCampbellWilliamE.CampbellPatriciaAnnHennig
StephanieA.KapsisChristopherJ.LewisMarcWilliamsJustinKeating,ViceChairman
Dr.AlvinL.Crawley
Staff Contact Information
EducationalFacilitiesWilliamFinn,Director
TraceyArmah,FinancialAnalyst
Planning,Design&ConstructionAndreaFeniak,Director
LaurelHammig,Planner&GISSpecialistAlexAlexander,FacilitiesEngineer
703‐461‐4168