Cicil Translate

24
4.5 ADDITIONAL TECHNICAL REQUIREMENTS FOR PHOTOVOLTAIC SOLAR POWER PLANT Connection and parallel operation of Photovoltaic Solar Power Plant must meet the requirements of the protection function and interference prevention function of the system, as well as specific technical requirements for PLT EBT-based inverter as described in sub-chapter 4.1, 4.2 and 4.3.3. Figure 4.5 shows a simplified block diagram Photovoltaic Solar Power Plant is connected to the Distribution System. In addition to Solar Photovoltaic modules, the system's main components include the inverter, step-up transformer, and control devices as well as protection. Technology and design of Photovoltaic Solar Power Plant has undergone very rapid development in recent years. Four common types of configuration Photovoltaic Solar Power Plant is described in the following sections. Figure 4.5. Simplified diagram of Photovoltaic Solar Power Plant Connection 4.5.1 CONFIGURATION CENTRALIZED INVERTER Figure 4.6 shows Centralized Inverter configuration which is relatively simple for Solar Power Generation Photovoltaics. This type of connection topology generating the most expensive, because it only has one centralized DC to AC inverters for photovoltaic panel strings which are connected in series and parallel to produce a certain voltage and DC current. Another weakness is system reliability problem, in the presence of interference or damage to the inverter, it will cause the entire plant stops operating. PV Arra Inver ter Control Panel & Protecti Distribu tion System Traf o

Transcript of Cicil Translate

Page 1: Cicil Translate

4.5 ADDITIONAL TECHNICAL REQUIREMENTS FOR PHOTOVOLTAIC SOLAR POWER PLANTConnection and parallel operation of Photovoltaic Solar Power Plant must meet the requirements of the protection function and interference prevention function of the system, as well as specific technical requirements for PLT EBT-based inverter as described in sub-chapter 4.1, 4.2 and 4.3.3. Figure 4.5 shows a simplified block diagram Photovoltaic Solar Power Plant is connected to the Distribution System. In addition to Solar Photovoltaic modules, the system's main components include the inverter, step-up transformer, and control devices as well as protection. Technology and design of Photovoltaic Solar Power Plant has undergone very rapid development in recent years. Four common types of configuration Photovoltaic Solar Power Plant is described in the following sections.

Figure 4.5. Simplified diagram of Photovoltaic Solar Power Plant Connection

4.5.1 CONFIGURATION CENTRALIZED INVERTERFigure 4.6 shows Centralized Inverter configuration which is relatively simple for Solar Power Generation Photovoltaics. This type of connection topology generating the most expensive, because it only has one centralized DC to AC inverters for photovoltaic panel strings which are connected in series and parallel to produce a certain voltage and DC current. Another weakness is system reliability problem, in the presence of interference or damage to the inverter, it will cause the entire plant stops operating.

Figure 4.6: Centralized Configuration Photovoltaic Inverter(Transformer between Centralized Inverter and network is not shown, as well as Figure 4.7 and 4.9)

PV Array

Inverter

Control Panel & Protection

Distribution System

TrafoStep Up

Centralized Inverter

Page 2: Cicil Translate

4.5.2 INDIVIDUAL CONFIGURATION STRING INVERTERFigure 4.7 illustrates the Inverter String array where single series circuit of Photovoltaic panels are connected in series and string connected to single inverter and a single inverter for each string. Advantage of this configuration is that the string inverter has a maximum power point tracking capabilities. Maximum Power Point Tracking (MPPT) separately from each string of Photovoltaic used for reducing the loss of mismatch and partial shadows so it can increase energy production. The weakness of this configuration is required more inverter.

Figure 4.7. Individual String Inverter configuration

4.5.3 MULTI - STRING INVERTER CONFIGURATIONFigure 4.8 illustrates of Photovoltaic Solar Power Plant with Multi-String Inverter configuration. Some string with a separate MPP tracking system (using DC / DC converter) is connected to DC / AC general inverter for producing AC to the distribution system. This configuration makes it possible to optimize the efficiency of the operation of each string separately, and integration of various solar orientation to maximize energy production.

Figure 4.8. Multi-string Inverter configuration

String 1 String 2

Page 3: Cicil Translate

4.5.4 AC MODULES INVERTER CONFIGURATIONFigure 4.9 shows the configuration of the AC modules inverter where each Photovoltaic module has DC / AC inverter and Maximum Power Point Tracking (MPPT). Advantage of this configuration is very flexible design, so it can be easy to add more inverters in order to increase power generation capacity. Moreover, this configuration increases energy production by reducing energy losses from inverter mismatch and improve reliability. Weakness in this configuration is required additional charges for inverter and more complex maintenance.

Figure 4.9. AC module Inverter configuration

4.5.5 ADDITIONAL TECHNICAL REQUIREMENTS FOR PHOTOVOLTAIC SOLAR POWER PLANTBecause of the intermittent nature of Photovoltaic Solar Power Plant and potential adverse impact on voltage feeder profile, especially in low load conditions and quickly covering cloud conditions, Photovoltaic Solar Power Plant with an installed capacity of 2 MW or higher have the ability to:i. Limiting the inverter ramp (up or down) at the rate 10% per minute of the inverter capacity, applicable

for start up and shut down, normal operation, and limitation order, except when solar radiation decreaseii. Setting the restart time for a double inverter at 15 seconds or more for each block of 1 MW.

4.6 METERING, MONITORING AND TELEMETERING4.6.1 General RequirementsAll PLT EBT must be measured with the measuring / metering equipment in accordance with the applicable PLN standards, Measurements rules of Electric Power Distribution Regulation, and the terms of the PPA.4.6.2 Metering of Non PLN Party

Page 4: Cicil Translate

Ownership, installation, operation, reading and testing of revenue metering equipment must be in accordance with SPLN or Electric Power Distribution Regulation (Chapter VIII Measurement rules).

4.6.3 TELEMETERINGIf PLT EBT connected to a distribution system which operates at a voltage of 20 kV, Telemetering equipment needed on PLT EBT facility which has capacity of 200 kW or more. PLN will only ask Telemetering, when options with smaller adverse effects and more effective cost for the real time data provision is not available.

4.6.4 METERING LOCATIONTransaction metering equipment must be installed near Connecting Point, the location of where PLN receives electrical power from PLT EBT. If the metering location is different from Connecting Point, the mechanism for calculating energy losses must be negotiated and agreed between PLN and Developer, and noted in the PPA. In the case of metering PLN must be located in a location which is owned by developer, developer must provide proper location for all the metering equipment without any fees charged to PLN.

4.6.5 METERING COSTDevelopers have to bear all the required metering cost, including additional costs caused by the operation and maintenance of metering equipment by PLN. Metering specifications must comply with SPLN or Electric Power Distribution Regulation

4.7 COMMUNICATIONS REQUIREMENTSPLT EBT with an installed capacity of less than 1 MW must have at least one communication channel such as a telephone or radio, etc., which are used for communication between the PLT EBT and DCC PLN or other PLN authorized Unit. If PLT EBT installed capacity greater than 1 MW, the PLT EBT should have at least provided two communication channels for voice and data.

5. TESTING, CERTIFICATION AND COMMISSIONINGThis chapter describes the requirements of the testing, certification and commissioning which only for equipment and PLT EBT connection facilities. Testing, certification, and commissioning of renewable energy generating units of proposed PLT is outside scope of the Guidelines.Tests and described criteria in this chapter is taken from IEEE, IEC, UL and California Model Electric Rule 21 About power plant interconnection facilities along with Testing Standards, Certification and Equipment Commissioning from ESDM and PLN validity.Tests which are performed on the PLT EBT connection equipment include :

(i) Type Test(ii) Production Test(iii) Commissioning Test(iv) Periodic Test

These test have to be done for checking compliance within technical standard described in Chapter 4, and then to make sure that PLT- EBT equipment and parallel operation are not adverse to PLN Distribution System. Tests carried out on assumption that PLT-EBT has low penetration level on PLN Distribution System. If the level of penetration is PLT EBT increased in the future, it would require additional requirements and corresponding test procedures.

This chapter also provides a connection device certification criteria on PLT EBT. Once the equipment is certified with predetermined criteria, PLT EBT installation can be connected to the PLN Distribution System. Unless specified in this Chapter that PLN do not need to repeat a design review or retest any certified equipment.

Page 5: Cicil Translate

5. 1 CERTIFIED & NOT CERTIFIED CONNECTION EQUIPMENT 5.1.1 CERTIFIED EQUIPMENTType test must be performed by an accredited testing agency approved by PLN to determine whether the equipment meets PLT EBT connectivity specifications for being considered as a Certified Equipment to be connected to Distribution System (set in Regulation No. 5 / ESDM / 2014 on "Procedures for the Accreditation and Certification of Electricity ").Certification can be applicable for pre-packaged system or assembly component which are intended for the protection and control functions. Type test can be done at manufacture or testing laboratory. When the equipment is certified by an accredited testing agency, the testing agency at least provide a certificate to the manufacturer with the following information on each equipment piece :

Administrative:i. Effective date of certification or serial number of valid certificate or other evidence regarding to validity.ii. Model number of certified equipmentiii. Version of used software in the equipment, if usediv. Certain test procedures (including the date or revision number)v. Laboratory Accreditation (Name of Laboratory and Used Standards).

Technical :i. Equipment capacity (kW or kWp, kVA, Volt, Ampere, etc.)ii. The maximum fault current in ampereiii. In-Rush currents in Ampereiv. Trip point, if specified by the manufacturer / fixed (value and tripping time)v. Trip point and time range for adjustable (setting)vi. Nominal power factor or its Range, if it can be arrangedvii. If the equipment has a non-islanding Certification.

Equipment manufacturer is responsible for ensuring that the information in the certification should be made available to the public, laboratory testing, or by a third party.

5.1.2 NOT CERTIFIED EQUIPMENTFor not certified equipment, some or all the tests described in this guide can be requested by PLN for each PLT EBT or Connecntion facilities. Manufacturer or an accredited testing agency which are acceptable by PLN can perform this test. The test results for non-certified equipment must be submitted to the PLN for additional review. PLN approval for connecting equipment which used for certain PLT EBT and connection facilities, it does not mean PLN approval use same equipment in PLT EBT or other Connection facilities.

5. 2 TEST TYPEType test performed to determine that the equipment meets PLT EBT Connection Specification as Certified Equipment. Requirements described in this chapter only covers issues related to the function of protection and control equipment which are connected to PLT EBT and is not to overcome equipment safety or other problems.

Table 5.1 shows the type testing and certification requirements for connecting equipment to the three types of PLT technology EBT:

(i) Synchronous Generator(ii) Induction Generator, and(iii) Inverter.

Page 6: Cicil Translate

Accredited testing institution shall comply with the testing procedures of ISO and PLN, and IEEE 1547.1-2005, UL 1741, IEC also necessary to test the function of the control and protection equipment which are connected to PLT EBT. Type test for abnormal frequency response should be based on nominal frequency 50 Hz of electric power system as shown in Table 4.2.

The testing procedure should be able to measure connection equipment accurately for each protection and control functions in accordance with the technical standards set out in Chapter 4. The testing procedure must be agreed upon by the manufacturer and approved by PLN.

Table 5.1: Type Testing and Certification Requirements for Equipment Connection

Test Type Synchronous generator

Induction Generator Inverter

Response to distribution abnormal voltage

x x x

Response to distribution abnormal frequency

x x x

Anti-islanding x x xLoss of control circuit x x xSynchronization x О ОReset relay x x xShort Circuit x x xPower Factor x x xConnection integrity x x x

Surge withstand capability x x x

Harmonic distortion x x xFlicker x x xInrush current - x -DC injection - - xDC isolation - - xX: Required O: Required for all self-excitation induction generator and inverter which operates as a voltage source when connected to Distribution System.

5. 3 PRODUCTION TESTProduction test conducted to verify the operation of manufactured connection equipment to be used in the field. Specific protection standards (set out in Chapter 4) allows adjustment of the set point, production test is done to confirm the setting of the manufacturer of the specific requirements of the standard. In the Production Testing assumed that the type test was to verify equipment connection suitability with protection standards. Therefore, the production test only covers about :

(i) Abnormal voltage response in distribution system,(ii) Abnormal frequency response in distribution systems, and (iii) The synchronization

Page 7: Cicil Translate

This protection function test should be based on the settings and specifications of the manufacturer. Production test can be done in a factory or being part of Commissioning Tests.

5. 4 COMMISSIONING TEST5.4.1 GENERALThe commissioning test must be performed after connection equipment is installed and ready to operate. The purpose of commissioning tests is to verify that the connection of PLT EBT equipment has been fully euipped and installed in accordance with the technical standards set out in Chapter 4. Accredited testing agency which approved by PLN, must perform or directly supervise the commissioning test. Where the operation of the connecting equipment is integrated and dependent on the operation of the Distribution System PLN, commissioning test must be coordinated and approved by the DCC PLN or authorized PLN unit. if it is required, DCC PLN or Authorized PLN Unit can witness the commissioning testing as described in this section. Commissioning for the outside scope of connection equipment is regulated separately.Testing agency must prepare a commissioning test report that contains results of all tests and list of last setting equipment. Commissioning tests need to be repeated until the report is completed and approved by PLN.

5.4.2 TESTING PROCEDURECommissioning tests conducted by written procedure. The testing procedure is provided by the manufacturer and must be approved by the owners of equipment and PLN. Writting procedure for commissioning tests report should include:

Verification and Inspection Test Functions in the Field Function Test of a cease-to-energized Unintentional islanding function tests, and Test for revised settings

This procedure is summarized as follows:

5.4.2.1 VERIFICATION AND INSPECTIONa. Verify the connection and equipment installation in accordance to SPLNb. Setting data usedc. Visual inspection of grounding system implementation according to SPLNd. Visual inspection and verification of isolation device implementation, if necessarye. Ensuring that the polarity, the load, and the CT and VT Ratio installation is correct and in accordance

with the designf. Visual inspection, continuity test or insulation resistance test is done to ensure wiring and control are in

accordance with the manufacturer's drawings and requirements.g. Connection device protection test with related breaker devices (for example, contactors or CB), Or, it

can be tested during production test to verify that the device is able to open when related breaker protection devices work, as well as interlocking circuit test between protection devices and breakers if not tested during Production Test

h. In the three-phase systems, phase sequence in PLT EBT and Distribution System should be inspected, and it must be ensured both appropriate as it mounted

i. Ensure the functionality of all monitoring provisions as set out in Chapter 5.

5.4.2.2 FIELD FUNCTIONS TESTField Functions Test is a production test (included in 5.3) that has not been done at the factory, it must be done in the field. Production test should be repeated for any change in software or hardware equipment, as required in Section 5.3.

Page 8: Cicil Translate

5.4.2.3 FUNCTION TEST FOR CEASE-TO-ENERGIZEThis test is to ensure that load breakers can be operated, or PLT EBT cease to energize the output terminal which is connected at all phases to PLN Distribution System when unintended island conditions occured, and not be tied back to a certain time delay set out in Chapter 4.

5.4.2.4 FUNCTION TEST FOR UNINTENDED ISLANDIn terms of reverse power or minimum power functionality, those are used to prevent unintended island. PLT EBT Connection system should be tested to verify that the function of unintended island is fulfilled and PLT EBT cease to energize. Testing should be done by adjusting PLT EBT output and local load, signal injection method, or other method approved by PLN.

5.4.2.5 REVISION SETTINGS TEST Field verification is required if Protection Function Setting (eg, response to abnormal voltage and frequency) has been changed after the Production Testing (Section 5.3). Verification can be done by :

(i) Using injected signals into voltage and current sensing circuit (ii) Applying waveforms(iii) A variety of set point to show tripping equipment on frequency and voltage distribution system which

being measured, or (iv) Other specified method by written procedure or manufacturer.

5. 5 PERIODIC TEST Periodic test and calibration of connectivity protection functions must be done as specified by the manufacturer at the interval in accordance with SPLN. Specified tests by the manufacturer must be done to verify all related connectivity protection function and battery functions. Written test reports or records / logs for the inspection should be kept well by developers.

Page 9: Cicil Translate

Several standard for recommended techniques and connection equipment testing in guidelines adopted or modified from a standards or following international practices :

1. IEEE 1547-2003 (Revised 2008): Standard for Interconnecting Distributed Resources with Electric Power Systems

2. IEEE 1547.1-2005:Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems

3. IEEE 1547.2-2008: Application Guide for IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power System

4. IEEE 1547.3-2007: Guide for Monitoring, Information Exchange, and Control of Distributed Resources Interconnected with Electric Power Systems

5. IEEE 519-1992: IEEE Recommended Practices and Requirements for Harmonic Control in Electric Power Systems

6. IEC 62109-2: Safety of Power Converters for used in Photovoltaic Power Systems – Particular Requirements for Inverters

7. IEC 61727: Photovoltaic Systems – Characteristics of the Utility Interface8. IEC 62446: Grid Connected Photovoltaic Systems – Minimum Requirements for System

Documentation,Commissioning Tests and Inspection9. IEC 61000-3-7: Limits – Assessment of Emission Limits for the Connection of Fluctuating Installations

for MV, HV, and EHV Power Systems10. IEC 61000-4-15: Testing and Measurement Techniques – Flicker Meter11. IEC 61683: Photovoltaic System – Power Conditioners – Procedure for Measuring

Efficiency.12. IEC 61400 – 21: Measurement and Assessment of Power Quality Characteristics of Grid Connected

Wind Turbines13. UL 1741: Inverters, Converters, Controllers and Interconnection System Equipment for Use with

Distributed Energy Resources14. IEC 62116: Test Procedure for Islanding Prevention15. California Electric Rule 21: Generation Facility Interconnection, California Public Utilities

Commission Decision 00-12-037, December 200016. Small Generator Interconnection Procedure, Federal Energy Regulatory Commission, July 2006

Page 10: Cicil Translate

Appendix A: Application of PLT EBT Connection (For Power Plant Capacity no larger than 10 MW)

Instruction and General Information

The developer who plans to build PLT EBT (Renewable Energy Power Plant) and sell generated power to PLN must submit a valid application for PLT EBT connection and parallel operated with PLN Distribution System. Before delivering the application, developers are advised to understand about "Guidelines for connection between PLT EBT and PLN Distribution System" (Guidelines). Developers are also advised to obtain information about the closest connection point to PLN Distribution Systems, distribution feeder, and substation to propose Connection Point. Developers have to fill about forms " Connection Planning Application for Renewable Energy Power Plant" (Application) and submit to closest PLN Region or distribution for the proposed PLT EBT. Submission does not include instructions and general information.

This application also requires certain documents, including, but not limited to, Pre-Feasibility Study Reports, Environmental Studies and permits from local governments and other authorities to PLT EBT. This information is required PLN Region or Distribution to conduct a review / study for determining the feasibility of proposed connection and also recommend appropriate measures to ensure proposed connection and parallel operation do not have a negative impact on safety, reliability and quality of PLN Power Distribution System.

This application is designed for small and medium PLT EBT (with installed capacity not greater than 10 MW) and is eligible to sell electricity to PLN at specified price in The Regulation of the Energy and Mineral Resources Minister (ESDM), including Regulation No. 04 ESDM / 2012 on "Purchase Price of Electricity by PT. PLN (Persero) from Small and Medium Scale PLT EBT or Excess Power ", Regulation No. 17 EMR / 2013 on "Purchase of Electricity by PT. PLN (Persero) from Photovoltaics Solar Power Generation", and Regulation No. 19 EMR / 2013 on "Purchase of Electricity by PT. PLN (Persero) from Municipal Solid Waste-Based Power Plants ", Regulation No. 12 EMR / 2014 regarding the "Power Purchase by PT. PLN (Persero) from Hydroelectric Power Plants ". Regulation of Energy and Mineral Resources Minister are also arranged for small and medium-scale of PLT EBT which connected to PLN 20 KV Distribution System or lower voltage levels.

Developers can choose Process whether " PLN Fast-Track Review " or "PLN Standards Review" in the appropriate box of the application form. The proposed PLT EBT will be qualified PLN Fast-Track Review Process, if it has an installed capacity as follows:

2 MW or less connected to 20 KV Distribution System in Java - Bali, or 200 KW or less connected to 20 KV Distribution System outside Java - Bali, or 30 KW or less connected to the Distribution System 400 V.

Developers can contact PLN Region or Distribution for more information about Application Form Filling. Incomplete applications will be returned to Developer by PLN Region or distribution. All of the information in the applications submitted will be kept confidential by PLN. A review / study by PLN Region or distribution can only be done after the submitted application is complete and valid.

Page 11: Cicil Translate

Appendix A: Application of PLT EBT Connection (For Power Plant Capacity no larger than 10 MW)

1. The Applicant who undersigned hereby request to connect the PLT EBT to PLN in accordance with the Distribution System Code of Connection PLT EBT to PLN Distribution System for (mark √ on one box): Fast-Track Review Process Standards Review Process

2. Application Connection is for (mark √ on one box) Plan a new PLT EBT. Installed Capacity additions or major modification to the existing PLT EBT.

3. COD date of proposed PLT EBT: ___________ (dd / mm / yr)

4. Does the developer already has permission from the Local Government (Permit Principle): Yes No

5. Principle PermitIssued date : __________________________Expiry date : __________________________Number : __________________________

6. Does the developer already has the Environmental Management Efforts Report (UKL) and Environmental Monitoring (UPL) or Environmental Studies: Yes No

7. Does the developer already has the Environmental Permit for the project: Yes No

8. Does the developer already has Pre-Feasibility Study Report / Feasibility Study for proposed PLT EBT: Yes No

9. Does the developer already has scaled drawing which show Plant Site and Connection point to PLN Distribution System? Yes No

10. Does the developer already has One Line Diagram of the system: Yes No

Page 12: Cicil Translate

Note: One line diagram should indicate installed equipment, including but not limited to generating units, step-up transformers, own use transformer, swiching tool, breakers, and necessary protective equipment. For Photovoltaic Solar Power and Wind Energy, one line diagram should include distribution line which connect to various generating units, capacitor banks for generating units, step-up transformers, power transformers and capacitor banks on the proposed connection Point. One line diagram of the proposed PLT EBT with capacity greater than 50 kW must be signed and stamped by a professional engineer (qualified professional engineer) who qualify and be accepted by PLN.

11. Does Developers already have a principles license of Local Government : Yes No

12. Developer Name: __________________________

13. Project Name: ______________________________

14. Holder of Principles LicenseCompany Name : __________________________Company owner : __________________________

15. Contact Person Project:Owner Name: ____________________________________Degree: _________________________________________Postal Address: ___________________________________

___________________________________ Phone: _________________________________________

No. HP: ________________________________________ Fax: ___________________________________________ E-mail: _________________________________________

Authorized Representative (if different): Name: ____________________________________ Degree: ____________________________________ Postal Address: ______________________________ ______________________________ Phone: ____________________________________ No. HP: ____________________________________ Fax: _______________________________________ E-mail: ____________________________________

Engineering Design Consultants (Optional): Company / Individual:

Name: ____________________________________ Postal Address: _____________________________ _____________________________ Phone: ____________________________________ No. HP: ____________________________________ Fax: _______________________________________ E-mail: ____________________________________

Page 13: Cicil Translate

16. Location of the proposed PLT EBT:Address: ____________________________________________Administration Location: _______________________________

_______________________________ PLN Official office: __________________________________ GPS Coordinates: _____________________________________

17. Proposed Connecting Point Location to PLN Distribution System:Address: ________________________________________Administration Location : ___________________________GPS Coordinates: _________________________________a. Connection Voltage to PLN Distribution System: _______ kVb. Does developer aware about Distribution System conditions (such as voltage fluctuations level of

daily, weekly, and annual, short circuit current level, interruption ammount per year and per week, distance to the proposed Connecting Point) on proposed connection point: Yes No

18. Developer Status:Is developers a PLN Regular customer at the moment :If yes, PLN Account Number: _________________________________Name of Account Holder *: _______________________________(* must be the same name as Applicant)

19. PLT EBT Energy Sources: Mini or Micro Hydro (Smaller than 1 MW) Small scale hydro (1 up to10 MW) Biomass Biogas Biofuel Municipal waste-based plant Gas Landfill Solar Photovoltaic Wind Geothermal Other, please specify: ____

20. General Information of Generation Facilities:Power Type: Synchronous Induction Inverter-Based

Number of Units: ____

Installed capacity of each unit: ____kW ____KVAR ____Voltage (V)

Generator Connected to: Single Phase Three phase

Proposed Installed Capacity: ____kW

Power Factor Range of Generating Unit :

Page 14: Cicil Translate

____Maximum Leading

____Maximum Lagging

Visible switch size: ____Amp ____kV Is not required

Maximum short-circuit currents on PLT EBT Generator terminal : ____Amp

PLT EBT nominal output current at HV side of transformer : ____Amp

21. Step-up transformers interface belong to Developer (if any):a. Transformer Capacity : ____kVAb. Transformer Voltage :

Primary ______ Volt

Secondary ______ Volt

c. Rolls connection to PLN Voltage: Delta Star

Star grounding method is connected to the neutral point of the secondary windings:

Solid Ungrounded Through Impedance: R____ X____ ohms

d. Rolls connection to PLT-EBT Voltage :

Delta Star

Star grounding method is connected to the neutral point of the primary winding:

Solid Ungrounded Through Impedance: R____ X____ ohms

The term of “PLN Voltage” refers to connection voltage to PLN distribution system and “PLT-EBT Voltage” refer to generator / inverter output voltage.

22. Circuit Breaker (PMT) (if any):Manufacturers: _______ Type: ________ Current Rating: _____ Amps

Breaker Rating: _______ Trip Speed: ____ cycles

23. Relay Protection Splicing (if any)Mention any functions and give Set Point (maximum and minimum) to any protection equipment or software

24. Additional information for Synchronous Generator :Short Circuit Duty information : for each generator, please provide reactance which is expressed in PU units on Generator basis value :Xd - Direct Axis Synchronous Reactance: __ pu

X ' D - Direct axis transient reactance: ___ pu

X "d - Direct axis subtransient reactance: ___ pu

Page 15: Cicil Translate

X2 - Negative sequence reactance: ___ p.u.

X0 - Reaktansi Zero Sequence: ___ p.u.

25. Additional information for Induction GeneratorRotor resistance, Rr: ____ Rotor reactance, Xr: ____

Stator resistance, Rs: ____ Stator reactance, Xs: ____

Magnetizing reactance, Xm: ____ Short-circuit reactance, Xd ": ____

Exciting current : _____ Temperature Rise: ____

Frame size: _____

Total Rotation Inertia , H : _____ p.u. on KVA basis

Reactive power is needed in VARs (no load)

Reactive power is needed in VARs (full load)

Motoring power: _____ KW, if applicable

26. Additional information for Wind Turbine GeneratorsWind turbines Manufacturer and No. Series: _________

Number of wind turbines: _______

Wind turbine hub height and rotor diameter: ________

Type of wind turbine (choose one), see the explanation of the type of wind turbines in this Code

Type I (Generator Induction Squirrel - cage)

Type 2 (Wound rotor induction machine with variable rotor resistance)

Type 3 (Generator AsinkronDoubly - fed)

Type 4 (Full converter interface)

The installed capacity for each wind turbine: ____ KW ____KVA

Terminal voltage nominal : ____ KV

For wind turbines of type 1 or type 2 :

Compensated power factor at full load: ___

Power factor of corrective capacitors at full load: ___ MVAR

Number of stages and size of the shunt: ___

Capacity curve that describes the range of reactive power or power factor of no load to full load

condition.

For wind turbines of type 3 or type 4:

Maximum under-excited power factor at full load: ___

Page 16: Cicil Translate

Maximum over-excited power factor at full load: ___

Control mode (voltage control or fixed power factor)

Capacity curve that describes the range of reactive power or power factor of no load to full load

condition.

The characteristics of short circuit: provide manufacturers short circuit test data which shows a three-

phase fault and line-to-ground fault conditions

Wind Data

Average of annual wind speed in meters per second hub height

If on-site wind measurements have been done, give details of measurement (duration and height).

If there is no on-site measurements, then give wind speed data source

Give monthly wind speed profile, the diurnal wind speed and wind rose (wind speed against the wind

direction)

Turbine power production curve (Power against the wind speed)

Annual average production of energy in MWh (Gross, Net, Losses)

27. Additional information for PLT-based EBT Invertera. Manufacturer: _____________

b. No Series: _____________

c. Inverter number: __________

d. Number of phases: Single Phase Three Phase

e. Installed capacity: _______ kW

f. Inverter output voltage: _______Volt (AC)

g. Maximum inverter current: ______ Amp

h. Maximum design of fault current contributions ___Ampere, ____ instantaneous, or ____ rms

i. Harmonic characteristics: frequency switching inverter; harmonic characteristics for each unit until

the switching frequency; harmonic characteristics for facilities generating aggregate

j. Short circuit characteristics: provide test data that shows the condition manufacturer disturbance in

the AC side of the three-phase inverter for interference and one phase to ground

k. Start-up power requirements:

l. Is inverter certified, select one:

Certified to IEC 62 109

Certified UL 1741

Other Certificate, please specify: ________________

Page 17: Cicil Translate

28. This joint application filed by:

Legal Name of Applicant: ______________________

Name (block letters): ______________________

Signature : ______________________

Position: ______________________ Date: ___________________

Appendix B: Comparison of Requirements Engineering Guidelines and Rules Indonesia Electric Power

Distribution Electric Power Distribution Regulation issued by EMR in 2009 to establish general rules and requirements for security, reliability and power quality of the power distribution system. The rules governing the planning, operation, and connection of distribution system as well as the requirements of metering and billing settlement. This rule was drawn up with a focus primarily on conventional power plants without any special requirements for Renewable Energy Power Plant. Since then, a number of policies and government regulations have made its laws to promote and accelerate the development of renewable energy PLT small and medium scale.These guidelines are based on Electric Power Distribution Regulation to provideprotection and control functionality requirements are more detailed and specific in order to ensure the connection and parallel operation of PLT EBT does not adversely affect PLN Distribution System. Table B-1 is the ratio of grafting techniques PLT EBT requirements set out in this Code and Electric Power Distribution Regulation.

Page 18: Cicil Translate