Chris Golightly February 2014; Offshore Wind Foundation Capabilities and Limitations

download Chris Golightly February 2014; Offshore Wind Foundation Capabilities and Limitations

of 31

description

Presentation at Offshore Wind Optimisation Seminar, 3rd and 4th February 2014

Transcript of Chris Golightly February 2014; Offshore Wind Foundation Capabilities and Limitations

  • Foundation Capabilities and LimitationsOffshore Wind Turbine Optimisation Seminar3rd - 4th February 2014 Dexter House, London

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Dr. Chris Golightly GO-ELS Ltd.Geotechnical & Engineering Geology Consultant

    Source: Univ. Mass. 1974

    Source: WINDFLOAT Website

    Sources from top left clockwise: Arup, BIFAB, COWI, RAVE Alpha Ventus

    Source: BELWIND Website

  • Summary - Offshore Wind Turbine Foundationsy Introduction Global Offshore Wind Energyy Differences; Oil & Gas Platforms Wind Turbinesy Types of Foundation for Offshore Wind Turbines [OWT]y Codes and Standards; DNV, GL IEC, USy Environmental, Geophysical & Geotechnical Site Investigationsy Monopiles Design & Installationy 4 Leg Piled Jackets OWEC, BIFAB, Truss Towers, Twisted Jackety Tripods Weserwind Alpha Ventus & OGN-Aquindy BARD Tripiley Gravity Base Structures [GBS] Gravitas, Vici Ventus, Gifford-Vinci, Seatowery Suction Caisson UF Monopod, Tripods, Quadrapodsy Others: Guyed Tower - A-Framed Monopile - TITAN Jack Upy Foundation Costs - Comparisonsy Foundation Issues & Problems (1); Early Refusals & Piling Noisey Pile Foundation Issues & Problems (2); Vibro Installation & Scoury Pile Foundation Issues & Problems (3); Grouted Connectionsy Pile Foundation Issues & Problems (4); Monopile Resonance, Cyclic Friction Degradation & Long Term Tilt in Sandsy Offshore Floating Solutions Huge Potential Offshore Wind Resourcey Fabrication Costs (Early 2010)y Maps: UK Round 3 & German North Sea Sitesy Offshore Wind Cost Trends Need for Reductiony Seabed Anchored Foundation Templates [SAFT]y Conclusions, References, Contact Details

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Introduction Global Offshore Wind Energy

    Clean & abundant energy on global scale should accelerate as fossil fuel costs rise & renewables gain economies of scale and innovation occurs The Crossover

    First offshore windfarm Denmark 1991. Proportion of RE in several European countries is increasing.

    But: as OW industry goes large scale, developers & lenders are conservative and risk averse. Stated liking for Creative innovation but also proven technnology.

    European focus is on Germany, Denmark, Sweden, Belgium & UK. France, USA, China, Japan developing rapidly Meditteranean, India, Brazil, S. Africa & others in future.

    Bigger, higher larger conventional 3 blade Siemens/VestasHAWT turbines dominant. Several 8 MW versions could be twin blade and VAWT in future (Sandia Labs. Studies).

    Move offshore from monopiles [15 - 30 m WD] jackets(UK) & tripods (Germany) [30-45 m WD] eventually to spar and TLP floaters [40-60 m +WD]

    In UK, offshore wind developers registered interest in deploying 46 GW of capacity & 10 GW has been progressed to consent determination, construction and operation.

    UK governments Renewables Roadmap aims to cut cost of wind power to 100 per megawatt hour (MWh), with 18 GW capacity off UK coast by 2020.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Moustafaeipour, 2009

  • LCOE Ranges and Averages [IRENA, 2013]

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Differences; Oil & Gas Platforms Wind Turbines

    Oil & Gas Platformsy Relatively stiff structures, usually

    founded on long driven piles and mudmats

    y Axial loads dominate due to high structure weights

    y Structural dynamics are not critical with weight >>> bending moments

    y Wave loads tend to dominate design in high energy areas such as North Sea

    y Straightforward Force Response relationship

    y Each design is one-off Prototype at a single location

    Offshore Wind Turbinesy Relatively flexible towers on variety of

    foundation types, monopiles 4 to 9 m diameter, tripods/4 leg jackets, GBS.

    y Structural dynamics always critical. 3P Eigenvalue resonance

    y Bending moment and lateral response more important than axial load

    y Wind and wave loads both very important

    y Complex uncorrelated/uncoupled loading

    y Large Nos. of OWT in arrays (80 [German AV Tripods] to 2000 [FOREWIND Statoil UK])

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Types of Foundation for Offshore Wind Turbines [OWT]

    Choice of foundation solution influenced by: Water depth and seabed conditions,

    especially depth to rockhead Environmental loading (wind, wave, tidal) Onshore fabrication, storage and

    transportation requirements. Offshore vessel & equipment spread costs

    & availability Installation & Construction methodology

    available. Developer CAPEX investment appetite and

    OPEX (Repair & Maintenance) predictionsSmarter solutions available (suction caissons, GBS, lighter jackets/trusses, hybrids, seabed anchored templates)Foundations 30 to 40% of overall CAPEX & rising. Cost reductions essentialSmarter lighter hybrid foundations needed & move away from riskier costly conventional driven tubular steel piling.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: UPWIND Project Final Report 2011

    Source: NREL

  • Codes and Standards; DNV, GL IEC, US

    Codes and Standards Hierarchy Offshore German Windfarms

    A. Bundesamt fur Seeschifffahrt und Hydrographie [BSH, Federal Regulator]

    B1. Germanischer Lloyd [GL]

    B2. Det Norsk Veritas [DNV]

    B3. IEC

    B4. DIN (German National Standards)

    C1. API-RP2A (Oil & Gas Offshore Structures)

    C2. DIBt

    C3. Norsok (Norwegian Offshore)

    C4. DASt Richtlinie

    D. Other Specific Standards where above do not cover technical design in sufficient detail

    Most Relevant Codes and Standardsy Det Norske Veritas DNV Offshore Standard DNV-OS-J101,

    Design for Offshore Wind Turbine Structures, Norway, 2004.y Germanischer Lloyd Rules and Guidelines, IV Industrial

    Services, Part 2 Guideline for the certification of offshore wind turbines, Germanischer Lloyd Windenergie GmbH Hamburg, 2005.

    y BSH Standard: 2007-06, Design of Offshore Wind Turbinesy API RP 2A Recommended Practice for Planning, Designing

    and Constructing Fixed Offshore Platforms LRFD Load and Resistance Factor Design, First Edition, July 1993.- WSD Working stress design, 21st edition, December2000.

    y EN 1997-1:2009-09: Eurocode 7: Geotechnical Deisgn; Parts 1, 2 and 3.

    y RECOFF Recommendations for Design of Offshore wind turbines (RECOFF), European Energy, Environment and Sustainable Development Programme

    y Norsok Standard N-003 Marine Actions, 2007.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Foundation Concepts 2012 2020 [Roland Berger Study 2013]

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Environmental, Geophysical & Geotechnical Site InvestigationsEnvironmental Surveys

    y Biogenic reefs & Benthic communitiesy Marine archaeology, wrecks and seabed obstructionsy Grab and gravity core sampling of Seabed surface sediments, for scour, plumes and cable burialy Seabed mobility, sand waves and shoals

    Geophysical and Geotechnical Surveys

    y Swath bathymetry, side scan sonar imageryy Seismic reflection profiling for geological shallow stratigraphy and shallow gas presencey Magnetometer for pipelines, cables, metal objects and seabed junk & unexploded ordnance [UXO]y Boreholes, vibrocores and cone penetration testing for geotechnical engineering parameters and soil

    layering

    Guidance Notes

    Society for Underwater Technology (SUT)/ Offshore Site Investigation and Geotechnics (OSIG) Committee (2005). Guidance Notes on Site Investigation for Offshore Renewable Projects, Rev. 02, March 2005.

    Bundesamt fur Seeschifffahrt und Hydrographie [BSH], (2008). Ground Investigations for Offshore Windfarms. BSH Standard No. 7004, p. 40.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Monopiles Design & Installation

    Not a Pile but Driven Tubular Steel Thin Walled Shell.

    Typically 4.5 - 9 m diameter, sometimes tapered

    Wall thicknesses 30 - 80 mm. D/t ratio very high ~ 80 120.

    WD cut-off 20 to 35 m > pile lateral & seabed soil stiffnesses & layering.

    Weights up to 900 tonnes, limited by float out & crane capacities

    Driven or drive-drill-drive (UK) or even drilled and grouted (France)

    Transition piece glued onto monopilewith brittle high strength cement ~ very strong granite > problems

    Simple, quick, suited to shallow water: problems - driving refusals & weight.

    Structure frequency limitations & fabrication, handling and installation constraints.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • 4 Leg Piled Jackets OWEC, BIFAB, Truss Towers, Twisted Jacket

    Usually driven tubular steel piles up to 2.5 m Dia.

    Reasonably well understood design and drivability methods with offshore track record / experience

    Flexible & adaptable to:- different/varying soil conditions- water depth- scour conditions (no protection vs protection/mitigation

    Variable diameter and wall thickness permitted on same project

    Acts in tension & compression Different penetrations and number Flexibility in installation methods

    vessels (pre-piling Vs through sleeve).

    Allows for drilling out and redriving if necessary (but expensive & to be avoided)

    Move to SCs for jackets (DONG, Statoil, Dudgeon trials)

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    BIFAB Jacket Beatrice. Source: SSE Renewables

    Source: OWEC Tower

  • Tripods Alpha Ventus & OGN-Aquind

    Weserwind - ALPHA VENTUS German federal funding 2001 2007 6 OWEC jackets/6 OWT tripods EPCI Contract value EUR 32m Client consortium: Vattenfall, Eon & EWE

    (DOTI) 1st offshore us of seabed template pre-

    piling (IHC) Adopted by Borkum West 2, Globaltech 1

    OGN-Aquind Newcastle based Oil & Gas fabricator TRITON 3 leg truss jacket for use in WD

    over 30 m & up to 80 m Major UK Govt. funding in 2012 for

    development and design of prototype jacket

    Steel savings, planning to be able to fabricate 150 jackets per year at Hadrians Yard in Wallsend

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • BARD Tripile

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Gravity Base Structures [GBS] Gravitas, Vici Ventus, Gifford-Vinci, Seatower

    Simplicity: Certainty of delivery, increased programme opportunities with fewer constraintsMinimal Seabed Preparation: Installed directly onto seabed whenever possible avoiding need to remove or disturb surface sedimentsSelf-Floating: No heavy lift or specialist towing or installation vessels required. Reduced supply chain & weather constraints. Improved cost certainty, increased supplier base & lower costsFlexibility: Can be relocated, repowered and removed at end of operational life. RC non-piled ballasted GBS with skirt option

    best solution in WD up to 60 m Large OWT up to 8 MW & standardised

    design Collar designs can accommodate ~ 2 deg

    vertical alignment tolerance Loading situation different to piled

    foundations & substantial vertical loading required to ensure stability

    But: Generally impractical for OWT in relatively shallow (< 15 m) water

    Bad publicity: German Strabag BSH rejection & over-designed Thornton Bank GBS.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Suction Caisson UF Monopod, Tripods, Quadrapods

    Suitable for all sand densities and intermediate strength clay

    Installation relatively simple & extensive oil & gas experience from GoM, North Sea, W.Africa

    Installation/capacity prediction analyses well developed. Scour protection design essential

    Highest quality geotechnical data and analyses necessary for stability assessment. Cyclic loading assessment critical

    Monopods installed successfully for Horns Rev Met Masts in 2009 & adopted in 2012 for UK Forewind/Firth of Forth Met Masts (Universal Foundation Monopod).

    SPT in NL developing tripod SC solution funded by Carbon Trust. Dudgeon full field SC jackets planned for 2016.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Oxford University Civil Engineering

    Source: SLP Engineering

    Source: DONG

    Source: DONG

  • Guyed Tower and A-Framed Monopile

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: WA Design Ltd.Source: Bunce and Carey EWEA 2001

  • TITAN 200 FWSS Jack Up Concept

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: http://offshorewindpowersystemsoftexas.com/titan_200_deep_offshore_platform

  • Pile Foundation Issues & Problems (1); Early Refusals & Piling Noise

    Piling Refusals

    Heavy long large diameter monopiles and jacket piles increasingly being over-driven and drilled out in glacial deposits and bedrocks: Expensive and risky.

    Pile Tip Buckling

    (cf. Valhall Norwegian Aker/BP problems in 2004, Oil & Gas platform expensive repair and claim). Over driving in very dense and /or cemented glacial materials in S. North Sea may lead to buckling failures if the industry continues to adopt conservatively long piles

    Piling Noise

    2011 rules in Germany 160 Dba @ 750 m. restricted working periods & expensive mitigation measures. In UK soft start up piling and observations required. Helical piles considered in Scotland. Germany Air Bubble Curtains [ABC] & Hydro Sound Dampers [HSD] London Array, Baltic Sea tests.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Pile Foundation Issues & Problems (2); Vibro Installation & Scour

    Vibro-Installation

    Tripods levelled using seabed vibro-installation to ~8 15 m using vibrohammers to reduce conventional hammer noise, allowing sequential levelling. Newish technique used on several large projects.

    Accepted commercially viable offshore Germany for partial pile installations through pile sleeves or pre-installed groups or monopiles.

    Scour Prediction & Mitigation

    Scour prediction according to DNV; S=1.3-1.6 * D. depends upon WD, soil type and grading and seabed current.

    May be allowed to develop (longer piles) or gravel and rock dump protection required (~ 500 -700 k Euros per monopile)

    Alternatives include frond mats (plastic seaweed), rock mats, pile eddy breaking fins or diversion berms and fences

    Accurate and cheap acoustic direct scour monitoring now possible (e.g. Alpha Ventus). Available commercially.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Thyssen-Krupp.Source: SLP Engineering

    Source: CEFAS Travelling Sand Waves @ Monopiles

  • Pile Foundation Issues & Problems (3); Grouted Connections

    For OWT monopiles, the transition piece [TP] transmits high bending moments. Brittle rock-like grouted connections were adopted for most European projects for speed & cost savings.Most excluded reinforcing shear keys due to design code omission. These have settled, cracked and failed on 70% UK monopiles. Systemic design fault. Variety of extensive and costly repairs have been required on many European projects.Oil & gas platform jackets used API designed grouted connections for decades, but grout connection in jackets hold a large mass so are always in compression. OWTs are light & subjected to long term cyclic bending, so complex vertical + bending force coupling & tensile stresses.Ability to transfer large moment is not fully understood & design theories have limitations & shortfalls. The use of conical TP sections as a solution [controlled failure] is uncertain in the long term.Industry best practice and code guidelines review on reliability of grouted connections. DNV guidelines were revised in 2011 (new Code 2014), but still anomalies in predicting behaviour. Research ongoing to understand size and fatigue effects.Many developers reverting to bolted flange connections (Scroby Sands, North Hoyle and Blyth 12 years ago), with some considering pile swaging or even slip joints as a more reliable long term solution. Requires verticality, careful driving.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Harding et al 2012

    Source: Lotsberg 2012

  • Pile Foundation Issues & Problems (4); Monopile Resonance, Cyclic Friction Degradation & Long Term Tilt in Sands

    Monopile Resonance

    Selection of dynamic properties essential for cost effective/reliable design. Affects rotor and support structure interaction & soil-foundation dynamic response.

    Design solutions depend upon ratio between fundamental structure eigenfrequency fo, rotor frequency fR and blade passing frequency fb = Nb* fR choice between soft-soft [fo< fR], soft-stiff [fR < fo < fb] and stiff-stiff [fB < fo].

    Cyclic Friction Degradation

    Substantial reductions in axial pile friction and lateral P-Y response may occur due to the cyclic long term loading experienced by monopiles supporting large heavy 3-bladed 5 MW + HAWT turbines

    Long Term OWT Tower Tilt in Sands

    Settling of towers/monopiles embedded in sands but not keyed into bedrock may be large, leading to excessive tilt and shutdown & resetting for gearbox turbines.

    Tilt of 0.5 deg is usual for OWT. Permanent tilt due to Construction tolerance permanent tilt is subtracted, with typical values 0.20 to 0.25 deg. Allowable operational rotational stiffness is typically 25 to 30 GNm/radians.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Cyclic Displacement Accumulation in Sands. Source: Achmus, Abdel-Rahman & Kuo (2007)

  • Foundation Costs Comparisons

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: UPWIND Project Final report

  • Offshore Floating Solutions Huge Potential Offshore Wind resource

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: The Offshore Valuation, 2010.

  • Future Offshore Wind Tethered Floating Structures 2 Examples

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Maine Int. Consulting, 2013.

  • Fabrication Costs (early 2010)

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: Ballast Nedam, 2010.

  • Maps: UK Round 3 & German North Sea Sites

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Offshore Wind Cost Trends Need for Reductions

    Cost increases since 2005 due to commodity price rises (mainly steel) and installation

    Monopile costs per kW flat-lining 1991 2008

    Deeper waters:- heavier and longer over-designed monopiles- more extensive and expensive equipment and vessel spreads- higher downtime and weather standby costs

    Insistence on known technology leading to lack of innovation, conservatism, risk aversion on the part of developers and lenders.

    Lack of experience in developer organisations; general skills shortage.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

    Source: van der Zwaan et al, 2011

    Source: The Offshore Valuation, 2010

  • Main Conclusions (1)

    1. Initially this new offshore industry has understandably used conservative monopile and piled tripod (Germany) & 4-leg jacket (UK) solutions. CAPEX and investment still limited compared to other energy industries.

    2. European Offshore Wind Industry has developed several foundation solutions, steel /concrete, monopiles, AV piled tripods, BARD tripiles, triple & 4-leg jackets, truss towers, twisted jacket, guyed & A-frame monopiles, monopod suction caisson, triple/quad suction caissons.

    3. Main Foundation Risks: Grouted connections, piling noise mitigation, over-conservative long, stiff, heavy pile design, pile tip buckling, unplanned drilling/re-driving, tilt and settlement.

    4. As more difficult rocky, irregular sites are encountered in deeper water, innovative and creative thinking necessary at an earlier stage (c.f. Atlantic and Argyll Array cancellations due to challenging seabed conditions)

    5. Grouted connections fiasco -70% UK MPs failed. To be avoided if possible. Use bolted flanges or other direct connections. If unavoidable use shear keys & robust grout seals. Are non shear keyed conical [1o-3o] sections and/or elastomeric spring bearings valid for fatigue design life?

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Main Conclusions (2)

    6. Industry as a whole needs more realistic offshore turbine tilt criteria, based upon sound engineering analysis. Big impact on structure costs, influencing business cases. Development of tilt-tolerant DD turbines can reduce costs.

    7. New foundation solutions [e.g. Carbon Trust] slowly & patchily embraced (Met. Masts) in UK/Germany. Concrete GBS, twisted jackets & suction caissons more suited to some sites. Solutions extensive in offshore oil & gas.

    8. For foundation costs to reduce [halved acc. US DoE], innovative solutions needed, selected/tailored to specific site conditions. Conservative risk averse attitudes in a relatively new industry should change as experience is gained.

    9. The current plans to move to ~10 m dia., 1200 Tonne, 60 m + length monopiles in ~40 m WD may be questionable & should be challenged.

    10. Globally, early development of floating alternatives increasing, HYWIND [Statoil], Principle Power [WINDFLOAT], Wave Hub [Glosten], Blue H, Offshore Japan [Various], France [IDEOL, WINFLO, VERTIWIND].

    11. Gyro-stabilised floaters, fully submerged concrete/composites, tension tethered damped synthetic mooring line, FPSO template, vertical axis turbines [VAWT] in WD > 50 m hold out most promise. Hybrid wind/tidal?

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • References & Links

    Referencesy Douglas-Westwood (2013), World Offshore Wind Market Forecast 2013 -2022, 5th Edition.y Golightly, C.R. (2014), Tilting of Monopiles; Long, Heavy and Stiff; Pushed Beyond Their Limits, Ground

    Engineering; 2014, vol 47, No. 1, pp 20-23.y van der Zwaan, R., Rivera-Tinoco, R., Lensink, S. & van den Oosterkamp, P., (2010) Evolving Economics of Offshore

    Wind Power: Cost Reductions from Scaling and Learning , Amsterdam 2010, p. 9.y The Offshore Evaluation Group (2010), The Offshore Valuation Report; A Valuation of the UKs Offshore Renewable

    Energy Resource, Public Interest Research Centre, p. 108.y Maine International Consulting (2013), Floating Offshore Wind Foundations; Industry Consortia and Projects in the

    United States, Europe and Japan; An Overview, May 2013, p. 45y Roland Berger (2013), Offshore Wind Toward 2020; On The Pathway to Cost Competitiveness, April 2013, p. 25.

    Linksy EWEA Offshore Statistics 2013 ewea.org/fileadmin/files/library/publications/statistics/EWEA_OffshoreStats_July2013.pdfy EC Marine Knowledge 2020 Database

    ec.europa.eu/maritimeaffairs/policy/marine_knowledge_2020y Global Wind Energy Council Country & Global Reports

    www.gwec.net/publications/country-reportsy IRENA Costs Database; irena.org/costsy UK Govt. Offshore Wind Industrial Strategy

    https://www.gov.uk/government/uploads/system/uploadsy USA Offshore Wind Database: offshorewind.nety 4C Offshore Wind Database: 4coffshore.comy UPWIND EWEA Project Final Report: upwind.eu

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014

  • Contact Details

    Dr.C.R. Golightly, BSc, MSc, PhD, MICE, FGS.Geotechnical and Engineering Geology ConsultantRue Marc Brison 10G, 1300 Limal, BelgiumTel. +32 10 41 95 25Mobile: +44 755 4612888Email: [email protected]: chrisgolightly;Linked In: www.linkedin.com/pub/5/4b5/469

    YouPayforaSiteInvestigationWhetherYoudoOneorNot Coleetal,1991.

    IgnoreTheGeologyatYourPeril Prof.JohnBurland,ImperialCollege.

    Dr. C. R. Golightly GO-ELS Ltd. - Offshore Wind Turbine Optimisation Seminar 3rd - 4th February 2014