Chr-A320 Family Heavy Maintenance Project Management

26
Highlight A: Heavy maintenance w orking schedul e and control 1) Preparation and work package analysis for Heavy Maintenance ( C check) 2) Pre-inspection for aircraf t condition ( Preliminary check) If applicable. 3) Communication and Liaison before C check incoming 4)  Aircraft input to the C check a. Phase 01----incoming b. Phase 02---- removal/access c. Phase 03---- inspection d. Phase 04/05 ---- repair/modification/Non-r outine handling e. Phase 06---- Re-installation f. Phase 07---- Functional test and final assembly g. Phase 08---- close up and redelivery 1 of 26 Pekamco T echnologies Pekamco.com

Transcript of Chr-A320 Family Heavy Maintenance Project Management

Page 1: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 1/26

Highlight A: Heavy maintenance working schedule and control

1) Preparation and work package analysis for Heavy Maintenance ( C check)

2) Pre-inspection for aircraft condition ( Preliminary check) If applicable.

3)Communication and Liaison before C check incoming

4)  Aircraft input to the C check

a. Phase 01----incoming

b. Phase 02---- removal/access

c. Phase 03---- inspectiond. Phase 04/05 ---- repair/modification/Non-routine handling

e. Phase 06---- Re-installation

f. Phase 07---- Functional test and final assembly

g. Phase 08---- close up and redelivery

1 of 26 Pekamco TechnologiesPekamco.com

Page 2: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 2/26

Highlight B: A320 aircraft heavy maintenance potential risk

1)  A320 family both wing top skin corrosion

2)  A320 family rib 5 inspection and modification

3)  A320 family SB A320-57-1154 and A320-57-1155 inspection and

modification.4)  A320 family lavatory floor pan heavy corrosion in the lavatory wet zone

 When above major inspection/modification items affect to each AIRBUS

 A320 aircraft, it risks raising C check turn around time (T.A.T)

1 of 26 Pekamco Technologies Pekamco.com

Page 3: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 3/26

Highlight C: A320 aircraft heavy maintenance cost saving and re-

adjustment of T.A.T.

1) Detailed analysis of GTA details, such as the cap of Non-routinemanhours, materials, and obligations of both parties.

2) Deep, specific analysis of the work package, such as customized MP

tasks and work scope.3) Combine work schedules and make materials delivery a priority. Closely

monitor milestones and benchmarks along the duration of the entireproject.

4) Negotiate the final division of non-routine labor and additional work

requests.5) In case outstanding issues will impact delivery target, the schedule

sequence and milestone will be movable and match the final target.

1 of 26 Pekamco Technologies Pekamco.com

Page 4: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 4/26

 

Highlight A:Heavy maintenance working schedule and control

1 of 26 Pekamco Technologies Pekamco.com

Page 5: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 5/26

 1.Preparation and work package analysis for Heavy Maintenance ( C check)

• Deeply review the datum aircraft heavy maintenance work package. clearly

catch key points

a. major routine tasks

b. major access zones

c. major repair /modifications

d. open Non-routine/ADD

e. closed or open loop components repair ( LDG,ENG or APU, THS).

• Materials status control.

a. Routine materials status

b. Non-routine/ADD materials statusc. Modification /repair kit or special tooling required if any.

d. Off wing OCCM or major components repair /OVH T.A.T or redelivery

schedule.

1 of 26 Pekamco Technologies Pekamco.com

Page 6: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 6/26

• GTA (contract) review

a. The fixed price and cap of non-routine labor, consumable materials,expendable and peculiar materials ( BFE etc)

b. Obligations of both parties understood; Attention to responsibility of

materials purchase , special tooling loan and T.A.T.

c. Attention to how well the aircraft is leasing - which will impact the PMA parts

usage or reimbursement requirement. It is very important issue forcustomers.

•  Aircraft basic information

a. share and provide airplane technical data and information,

such as type of oil, fluid, MTOW, BFE data etc.

• Review the C check flow chart. ( It applicable for MRO PM or on-site rep)a. Milestone set up.

I b. initial inspection phase and due date. Important for entire schedule.

c. Repair/ mod due date and re-installation start

d. Power on/hydraulic on/weighting/engine run/test flight

1 of 26 Pekamco TechnologiesPekamco.com

Page 7: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 7/26

 2. Pre-inspection for aircraft condition ( Preliminary check) If applicable.

• Depends on operators or MRO experience, mainly focuses on structure andcabin issues. Improves the layover quality and avoids significant structuraldamage, the pre-inspection is necessary.

• Obtain accurate part numbers and quantities to order peculiar materials.

• Consider the layover increase risk

• Order necessary materials/tooling if structural damage is found.

The pre-inspection is not applicable for every C check. It is better for 6Y or 12 Y

check or cabin refurbishment.

1 of 26 Pekamco Technologies Pekamco.com

Page 8: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 8/26

 3. Communication and Liaison preceding C check

• C check working schedule discussion and correction with Planning or MRO

( It applicable for MRO project Manager and on-site rep as well).

•  Account for layover information such as materials, tooling, T.A.T etc. Veryimportant for MRO PM or Airline On-site rep. Technically, it is the finalopportunity to brief the project before aircraft are incoming.

•  If Airline on-site rep, you may pay careful attention to the following:

a. Minimum fuel quantity and outstation fuel agency handling.

b. Contact MRO for first working day arrangement

c. Update airlines Non-routine and ADD status and inform MRO.

1 of 26 Pekamco Technologies Pekamco.com

Page 9: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 9/26

4. Aircraft input to the C check

• Phase 01----Aircraft incoming

a. Share technical information with project team in first daily meeting

b. Acquire the working schedule and emphasize key points ( Milestone or

potential points)

c. Fix both parties materials resource coordinator agenda and

communication paths.

• Phase 02 ---- Removal and Access

a. Based on the work package analysis , trace the process and focus on the

key working zone ( Fwd, Aft galley aisle floor beam, top skin, rear spar,floor pan of LAV. Floor beam under cargo ball mat etc. )

Note: Important! Based on your knowledge and experience, you may

catch key points and push our MRO to follow them in its priorities.

b. Key working zone inspection without removal/access. - Such as both wing

top skin, rear spar , T/R surface or wiremash corrsoion and de-lamination.1 of 26 Pekamco TechnologiesPekamco.com

Page 10: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 10/26

• Phase 03----- Inspection

a. Continue following and monitoring key area working processes. Request report

on daily basis.

b. in case of any outstanding finding, especially for structures, immediately

 work with team for measurement, report, and liaison with vendor.

Moreover, attention to whether the entire schedule will be impacted.

c. Attention to materials request.

Note: Important! Have to review item by item. First of all, you may

know if the missing materials are critical or not, next to verify theleading time will match the schedule.

d. We will Work closely with your QC and Materials resource to identify the

critical missing parts, leading time, delivery date, any re-installation

impact etc.

1 of 26 Pekamco Technologies Pekamco.com

Page 11: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 11/26

  e. Meanwhile, both parties should consider two solutions for missing

materials, one way is to order anew, one way is to repair. It is better for timeand cost savings. Moreover, the schedule will not be impacted due to missingmaterials.

• Phase 04 and 05----- Repair/modification/non-routine handling

a. Attention to the major repair /modification process and to avoid any impact

for final hydraulic on and power on.

b. Pay more attention to the interface between major modification or repairs. It

always happens in ageing aircraft’s heavy maintenance. Major repair

interface may change the jacking CG or affect jacking procedure.

Note: Important! Jacking loan need 5 days at least from HAM airbus. It

represents potential risk for T.A.T

1 of 26 Pekamco Technologies Pekamco.com

Page 12: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 12/26

  c. Set up the deadline for materials delivery and feedback materials status

 with your team.

Note: Technically, the mass of missing materials requests will be reported

from production after the inspection phase is done. - Especially forChina mainland MRO’s. The phase 04/05 is a good opportunity to

follow and trace the missing materials.

• Phase 06----- Reinstallation and Non-routine handling

a. Push the materials availiability and fulfill the milestone.

Note: Delayed materials cause cost waste.

b. Attention and monitoring key non-routine task processing, it will impact

reinstallation schedule.

1 of 26 Pekamco Technologies Pekamco.com

Page 13: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 13/26

• Phase 07----functional test and final assembly

a. Fulfill the power on and hydraulic on.

b. Technical logic for final test sequence. - Especially for aircraft

LDG swing, weighting, fuel on-board check, engine run.

Note: At C check final phase, you need to with an MRO PM for key

issues, not only consideration for materials supply. Final working flow

also needs be discussed and reviewed. If applicable, the key workflow

 will be enhanced.

• Phase 08----- close up and redelivery

a. If on-site rep for airlines, inform flight operation of delivery date and requestfor ferry flight schedule in advance.

b. Ask flight dispatch for ballasting and fuel quantity.

c. make a cross index for incoming non-routine and inform MCC in advanced.

d. Make a ADD records and extention records , inform MCC and planningdepartment in advance if applicable.

1 of 26 Pekamco Technologies Pekamco.com

Page 14: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 14/26

 

Highlight B:

 A320 aircraft heavy maintenance potential risk

1 of 26 Pekamco Technologies Pekamco.com

Page 15: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 15/26

1.A320 family both wing top skin corrosion

• Inspection and findings must be as earlier as possible.1) No extra access required for such inspection zone, the inspection

must be done once aircraft is incoming.

2) If in case finding, polish and blend out will be followed and

measured. The step shall be finished at first day.

3) If corrosion is out of limits, a structural engineer needs to be involved

immediately, make a grid for the damage area, and report to

 AIRBUS promptly.

1 of 26 Pekamco Technologies Pekamco.com

Page 16: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 16/26

  Note: Long delays will be incurred If the top skin corrosion cannot

not be found at first phase. Major impacts as following:

a. damage report and AIRBUS inquiry.

b. oversized fasteners seeking and order

c. special jacking procedure and jacks loan if reinforce plate

required.

In summary, the top skin corrosion is a major issue leading to long delay.

Early inspection/report and fasteners estimate/ordering are important. If

advice is followed, the entire repair T.A.T can be deducted 5 days at least.

1 of 26 Pekamco Technologies Pekamco.com

Page 17: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 17/26

2.A320 family rib 5 inspection and modification

• This is AD requirement for each AIRBUS aircraft. For ageing aircraft, it isa potential risk for aircraft redelivery

a. Inspection must be first priority once LDG removed.

b. Bore inspection and blend out must be careful. If crack found,

structural engineer must be involved immediately and report to AIRBUS.

c. Special tooling and reamer need be loaned from AIRBUS. Someairlines also need AIRBUS on-site advisor to support.

Note: reamer goes in slowly and controls size carefully to ensure

the crack is eliminated and the bore inner diameter is withinlimit.

d. If crack remains and the bore’s inner diameter is out of limit, thefitting must be replaced by AIRBUS working party. Entire repair T.A.T is

14 days.1 of 26 Pekamco Technologies Pekamco.com

Page 18: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 18/26

 3.A320 family SB A320-57-1154 and A320-57-1155 inspection and

Modification.

• This is recommended for each aircraft , especially ageing aircraft.

a. special NDT tooling must be prepared before C check layover.

b. modification kits must be available before C check.

c. No more extra access inspection area, the inspection has to beperformed once aircraft is incoming.

d. If found, the concerned area damage limits need to be

 verified immediately. If out of limit, oversized fasteners need be

estimated and ordered. Meanwhile, structural engineers need to beinvolved and report to AIRBUS.

Note: If above findings happened, you may coordinate with MRO to readjustthe schedule. Because Top skin repair and Two SBs repair

 Will be seriously interfered.

1 of 26 Pekamco Technologies Pekamco.com

Page 19: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 19/26

4.A320 family lavatory floor pan heavy corrosion in the lavatory wet

zone

• The floor pan heavy corrosion will incur extra removal or access andimpact cabin restoration process.

a. If floor pan leading time is long it will impact entire T.A.T.

b. If corrosion or crack heavy, the underlying f loor beam will incurcorrosion. The extra removal and access is required.

1 of 26 Pekamco Technologies Pekamco.com

Page 20: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 20/26

 

Highlight C:

 A320 aircraft heavy maintenance cost saving and re-

adjustment of T.A.T.

1 of 26 Pekamco Technologies Pekamco.com

Page 21: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 21/26

1.Detailed analysis of the GTA details, such as the cap of Non-routine

manhour, materials, and obligation of both parties.

•  Attention to the cap of Non-routine manhour definitions, It is better todiscuss the above charges in the final phase. Only if you carefully reviewthe routine task card and understand the contract may you know thenon-routine resource and how much labor you should pay for.

•  Attention to the cap of materials price and routine task cards involvedzone or area, you may know how much materials cost need to be paid.

•  Attention to the obligation of both parties, you may know the keyobligations such as tooling loans, warranty, redelivery etc.

1 of 26 Pekamco Technologies Pekamco.com

Page 22: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 22/26

2.Deeply understand and analyze the work package, such as customized

MP tasks and major work scope.

•  Attention to the major access and major routine task cards, such asLDG,ENG,THS removal, Cargo loading removal, cabin floor panel etc,

 you may clearly figure out the work sequence and milestones.

 Attention for preliminary check, especially for structure inspection andCPCP tasks ( MRB5,8 or CMR) , you may estimate the potential risk andeasily trace the key points.

•  Attention for Off-wing ( OCCM or hard time control) componentsrequirement, one way you can follow the materials status, another way

 you will find close or open loop repair T.A.T.•  Attention to routine task cards working zone, you may know how much

the above charge would be incurred.

1 of 26 Pekamco Technologies Pekamco.com

Page 23: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 23/26

3.Combine work schedule processing, make materials delivery a priority

and closely monitor milestones of the entire project.

•  Whatever C check duration, you have to give attention to the materialsdelivery time and schedule. It can save operator cost directly and cansave the layover time.

 Attention to the schedule process, provides enough stress to MRO andcontrols the non-routine materials raise. Based on your knowledge andexperience, you may focus on the key missing materials who will impactentire project milestones.

• If any key missing materials cannot match the milestone, you mayconsider moving the schedule sequence and try to fulfill the finaldelivery target or reduce delay time. For example, If top skin arefasteners missing, you need to move the final phase tasks forward toavoid time waste.

1 of 26 Pekamco Technologies Pekamco.com

Page 24: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 24/26

4. Negotiate the final labor of non-routine and additional work requests.

•  You have to have figure out or estimate what non-routine or additionaltasks will occur above charge. The handling process and result needs tobe closely monitored. Finally you will catch up the key point andnegotiate with MRO.

1 of 26 Pekamco Technologies Pekamco.com

Page 25: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 25/26

5.In case outstanding issues will impact delivery targets, the schedule

sequence and milestone could be movable and match the final target.

• It depend on your experience and knowledge. If outstanding issueoccurred, you may clearly figure out what’s major work zone or task will

be postponed. What tasks can be moveable or adjusted. The time needmust be carefully reviewed and estimated. In this phase , taskcombination is first priority.

1 of 26 Pekamco Technologies Pekamco.com

Page 26: Chr-A320 Family Heavy Maintenance Project Management

8/11/2019 Chr-A320 Family Heavy Maintenance Project Management

http://slidepdf.com/reader/full/chr-a320-family-heavy-maintenance-project-management 26/26

Technically, this is general instruction for AIRBUS A320 family common C

check. This instruction is a little bit different with leasing aircraft delivery or

redelivery check. Major requirement will be as followed:

1) Work package analysis and estimate

2) Materials status confirmation and follow up

3) Enough stress for MRO and control key milestone4) Any schedule arrangement or adjustment will fulfill final redelivery

target.