Chptr 4 Project Analysis and Evaluation

32
Chapter 4 Project Analysis and Evaluation McGraw-Hill/Irwin Copyright © 2010 by The McGraw-Hill Companies, Inc. All rights reserved.

description

Project analysis

Transcript of Chptr 4 Project Analysis and Evaluation

Page 1: Chptr 4 Project Analysis and Evaluation

Chapter 4

Project Analysis and Evaluation

McGraw-Hill/Irwin Copyright © 2010 by The McGraw-Hill Companies, Inc. All rights reserved.

Page 2: Chptr 4 Project Analysis and Evaluation

Evaluating NPV Estimates

• NPV estimates are just that – estimates• A positive NPV is a good start – now we

need to take a closer look– Forecasting risk – how sensitive is our NPV to

changes in the cash flow estimates; the more sensitive, the greater the forecasting risk

– Sources of value – why does this project create value?

11-2

Page 3: Chptr 4 Project Analysis and Evaluation

Scenario Analysis

• What happens to the NPV under different cash flow scenarios?

• At the very least, look at:– Best case – high revenues, low costs– Worst case – low revenues, high costs– Measure of the range of possible outcomes

• Best case and worst case are not necessarily probable, but they can still be possible

11-3

Page 4: Chptr 4 Project Analysis and Evaluation

• You are considering a new product launch. The project will cost RM1,700,000, have four year life, and have no salvage value; depreciation is straight line to zero. Sales are projected at 190 units per year; price per unit will be RM18,000, variable cost per unit will be RM11,200, and fixed costs will be RM410,000 per year. The required return on the project is 12 percent, and the tax rate is 35 percent.

Page 5: Chptr 4 Project Analysis and Evaluation

• Company thinks the unit sales, variable cost, and fixed cost are projections given are probably accurate to within ±10 percent. Calculate the Net Present Value (NPV) for base case, best case and worst case.

Scenario Unit sales Variable cost (RM)

Fixed costs (RM)

Base 190 11,200 410,000

Best 209 10,080 369,000

Worst 171 12,320 451,000

Page 6: Chptr 4 Project Analysis and Evaluation

OCFbase = [(18,000 – 11,200)(190) – 410,000](0.65) + 0.35(1,700,000/4)

OCFbase = $722,050

 

NPVbase = –1,700,000 + 722,050 x 1- (1/ (1 + 0.12)4 ) 0.12

NPVbase = 493,118.10

• Calculate for the 2 scenarios

Page 7: Chptr 4 Project Analysis and Evaluation

• Evaluate the sensitivity of base case Net Present Value

(NPV) to changes in fixed costs.• To calculate the sensitivity of the NPV to changes in fixed costs

we choose another level of fixed costs. We will use fixed costs of RM420,000. The OCF using this level of fixed costs and the other base case values with the tax shield approach, we get:

OCF = [(18,000 – 11,200)(190)–420,000](0.65) + 0.35(1,700,000/4)

OCF = 715,550

 NPV = –1,700,000 + 715,550 x 1- (1/ (1 + 0.12)4 ) 0.12

NPV = 473,375.32

Page 8: Chptr 4 Project Analysis and Evaluation

• The sensitivity of NPV to changes in fixed costs is:

NPV/FC = (493,118.10 – 473,375.32)/(410,000 – 420,000)

NPV/FC = –1.974

For every value increase in fixed costs, net present value falls by RM1.974

Page 9: Chptr 4 Project Analysis and Evaluation

Sensitivity Analysis• What happens to NPV when we change

one variable at a time• This is a subset of scenario analysis

where we are looking at the effect of specific variables on NPV

• The greater the volatility in NPV in relation to a specific variable, the larger the forecasting risk associated with that variable, and the more attention we want to pay to its estimation

11-9

Page 10: Chptr 4 Project Analysis and Evaluation

Summary of Sensitivity Analysis for New Project

Scenario Unit Sales Cash Flow NPV IRR

Base case 6,000 59,800 15,567 15.1%

Worst case 5,500 53,200 -8,226 10.3%

Best case 6,500 66,400 39,357 19.7%

11-10

Page 11: Chptr 4 Project Analysis and Evaluation

Simulation Analysis

• Simulation is really just an expanded sensitivity and scenario analysis

• Monte Carlo simulation can estimate thousands of possible outcomes based on conditional probability distributions and constraints for each of the variables

• The output is a probability distribution for NPV with an estimate of the probability of obtaining a positive net present value

• The simulation only works as well as the information that is entered, and very bad decisions can be made if care is not taken to analyze the interaction between variables

11-11

Page 12: Chptr 4 Project Analysis and Evaluation

Making a Decision• Beware “Paralysis of Analysis”• At some point you have to make a decision• If the majority of your scenarios have

positive NPVs, then you can feel reasonably comfortable about accepting the project

• If you have a crucial variable that leads to a negative NPV with a small change in the estimates, then you may want to forego the project

11-12

Page 13: Chptr 4 Project Analysis and Evaluation

Break-Even Analysis

• Common tool for analyzing the relationship between sales volume and profitability

• There are three common break-even measures– Accounting break-even – sales volume at which

NI = 0– Cash break-even – sales volume at which OCF

= 0– Financial break-even – sales volume at which

NPV = 0

11-13

Page 14: Chptr 4 Project Analysis and Evaluation

Example: Costs• There are two types of costs that are important in

breakeven analysis: variable and fixedTotal variable costs = quantity * cost per unit

–Fixed costs are constant, regardless of output, over some time period

Total costs = fixed + variable = FC + vQ

• Example:–Your firm pays $3,000 per month in fixed costs. You also pay $15 per unit to produce your product.

• What is your total cost if you produce 1,000 units?

• What if you produce 5,000 units?

11-14

Page 15: Chptr 4 Project Analysis and Evaluation

Average vs. Marginal Cost• Average Cost

TC / # of units–Will decrease as # of units increases

• Marginal Cost–The cost to produce one more unit–Same as variable cost per unit

• Example: What is the average cost and marginal cost under each situation in the previous example–Produce 1,000 units: Average = 18,000 / 1000 = $18–Produce 5,000 units: Average = 78,000 / 5000 = $15.60

11-15

Page 16: Chptr 4 Project Analysis and Evaluation

Accounting Break-Even

• The quantity that leads to a zero net income

• NI = (Sales – VC – FC – D)(1 – T) = 0

• QP – vQ – FC – D = 0

• Q(P – v) = FC + D

• Q = (FC + D) / (P – v)

11-16

Page 17: Chptr 4 Project Analysis and Evaluation

Using Accounting Break-Even

• Accounting break-even is often used as an early stage screening number

• If a project cannot break-even on an accounting basis, then it is not going to be a worthwhile project

• Accounting break-even gives managers an indication of how a project will impact accounting profit

11-17

Page 18: Chptr 4 Project Analysis and Evaluation

Accounting Break-Even and Cash Flow

• We are more interested in cash flow than we are in accounting numbers

• As long as a firm has non-cash deductions, there will be a positive cash flow

• If a firm just breaks even on an accounting basis, cash flow = depreciation

• If a firm just breaks even on an accounting basis, NPV will generally be < 0

11-18

Page 19: Chptr 4 Project Analysis and Evaluation

Example• Consider the following project

– A new product requires an initial investment of $5 million and will be depreciated to an expected salvage of zero over 5 years

– The price of the new product is expected to be $25,000, and the variable cost per unit is $15,000

– The fixed cost is $1 million– What is the accounting break-even point each

year?• Depreciation = 5,000,000 / 5 = 1,000,000• Q = (1,000,000 + 1,000,000)/(25,000 –

15,000) = 200 units

11-19

Page 20: Chptr 4 Project Analysis and Evaluation

Sales Volume and Operating Cash Flow

• What is the operating cash flow at the accounting break-even point (ignoring taxes)?

OCF = (S – VC – FC - D) + DOCF = S – VC – FC

OCF = (200*25,000 – 200*15,000 – 1,000,000 - 1,000,000) + 1,000,000 = 1,000,000

• What is the cash break-even quantity?Q = FC / (P – v)

Q = (0 + 1,000,000) / (25,000 – 15,000) = 100 units

11-20

Page 21: Chptr 4 Project Analysis and Evaluation

Three Types of Break-Even Analysis

• Accounting Break-even

Q = (FC + D) / (P – v)• Cash Break-even

Q = FC / (P – v)• Financial Break-even

Q = (FC + OCF) / (P – v)• Cash BE < Accounting BE < Financial BE

11-21

Page 22: Chptr 4 Project Analysis and Evaluation

Example: Break-Even Analysis

• Consider the previous example– Assume a required return of 18%– Accounting break-even = 200– Cash break-even = 100– What is the financial break-even point?

• Similar process to that of finding the bid price• What OCF (or payment) makes NPV = 0?

– N = 5; PV = 5,000,000; I/Y = 18; CPT PMT = 1,598,889 = OCF

• Q = (1,000,000 + 1,598,889) / (25,000 – 15,000) = 260 units

11-22

Page 23: Chptr 4 Project Analysis and Evaluation

Operating Leverage• Operating leverage is the relationship

between sales and operating cash flow• Degree of operating leverage measures

this relationship– The higher the DOL, the greater the variability

in operating cash flow– The higher the fixed costs, the higher the DOL– DOL depends on the sales level you are

starting fromDOL = 1 + (FC / OCF)

11-23

Page 24: Chptr 4 Project Analysis and Evaluation

Example: DOL• Consider the previous example• Suppose sales are 300 units

– This meets all three break-even measures– What is the DOL at this sales level?– OCF = (25,000 – 15,000)*300 – 1,000,000 =

2,000,000– DOL = 1 + 1,000,000 / 2,000,000 = 1.5

• What will happen to OCF if unit sales increases by 20%?

Percentage change in OCF = DOL*Percentage change in Q

– Percentage change in OCF = 1.5(.2) = .3 or 30%– OCF would increase to 2,000,000(1.3) = 2,600,000

11-24

Page 25: Chptr 4 Project Analysis and Evaluation

Capital Rationing• Capital rationing occurs when a firm or division

has limited resources– Soft rationing – the situation that occurs when

units in a business are allocated a certain amount of financing for capital budgeting.

– Hard rationing – the situation that occurs when a business cannot raise financing for a project under any circumstances.

• The profitability index is a useful tool when a manager is faced with soft rationing

11-25

Page 26: Chptr 4 Project Analysis and Evaluation

Comprehensive Problem

• A project requires an initial investment of $1,000,000 and is depreciated straight-line to zero salvage over its 10-year life. The project produces items that sell for $1,000 each, with variable costs of $700 per unit. Fixed costs are $350,000 per year.

• What is the accounting break-even quantity, operating cash flow at accounting break-even, and DOL at that output level?

11-26

Page 27: Chptr 4 Project Analysis and Evaluation

SolutionAccounting break-even:•Q = (FC + D) / (P – V)

= ($350,000 + $100,000) / ($1,000 - $700)

= 1,500 units•OCF = ( S – VC – FC – D) + D

= ([1,500 x $1,000] – [1,500 x $700]

- $350,000 - $100,000) + $100,000

= $100,000•DOL = 1 + (FC / OCF)

= 1 + ($350,000 / 100,000)

= 4.5

Page 28: Chptr 4 Project Analysis and Evaluation

CLASS EXERCISE

• Olin Transmissions, Inc., has the following estimates for its new gear assembly project: price RM1,900 per unit: variable costs = RM240 per unit; fixed costs = RM 4.8 million; quantity = 95,000 units. Suppose the company believes all of its estimates are accurate only within ± 15%. What values should the company use for the four variables given here when it performs its best case scenario analysis? What about the worst case scenario?

Page 29: Chptr 4 Project Analysis and Evaluation

• A project has the following data:Price = $57 per unit

Variable cost = $32 per unit

Fixed cost = $9,000

Required return = 12%

Initial Investment = $18,000

Life= 4 years

Depreciation = straight line method

Calculate:

Page 30: Chptr 4 Project Analysis and Evaluation

• Accounting break even

• Cash break even

• Financial break even

Page 31: Chptr 4 Project Analysis and Evaluation

Boh Valley is a company produces tea. The company recently change its packing machine. The machine's initial cost is RM2,000, and the depreciation value is RM250 per year. The machines have 4 years project life. The fixed costs of the machine RM2,000 per year and variable cost is RM6 per unit. A packet of tea is selling at RM20. Boh Valley required rate of return is 10 percent. Calculate:

•Accounting break even.•Financial break-even point for the project.•Cash break even

Page 32: Chptr 4 Project Analysis and Evaluation

Tutorial

• Ross, Westerfield, Jordon (2010). Fundamental of Corporate Finance, 9th Edition

• Q: 1, 5, 9, 13, 19

• Pages: 360 - 362