Chptr 4 Project Analysis and Evaluation
-
Upload
sivaranjini-kaliappan -
Category
Documents
-
view
89 -
download
14
description
Transcript of Chptr 4 Project Analysis and Evaluation
Chapter 4
Project Analysis and Evaluation
McGraw-Hill/Irwin Copyright © 2010 by The McGraw-Hill Companies, Inc. All rights reserved.
Evaluating NPV Estimates
• NPV estimates are just that – estimates• A positive NPV is a good start – now we
need to take a closer look– Forecasting risk – how sensitive is our NPV to
changes in the cash flow estimates; the more sensitive, the greater the forecasting risk
– Sources of value – why does this project create value?
11-2
Scenario Analysis
• What happens to the NPV under different cash flow scenarios?
• At the very least, look at:– Best case – high revenues, low costs– Worst case – low revenues, high costs– Measure of the range of possible outcomes
• Best case and worst case are not necessarily probable, but they can still be possible
11-3
• You are considering a new product launch. The project will cost RM1,700,000, have four year life, and have no salvage value; depreciation is straight line to zero. Sales are projected at 190 units per year; price per unit will be RM18,000, variable cost per unit will be RM11,200, and fixed costs will be RM410,000 per year. The required return on the project is 12 percent, and the tax rate is 35 percent.
• Company thinks the unit sales, variable cost, and fixed cost are projections given are probably accurate to within ±10 percent. Calculate the Net Present Value (NPV) for base case, best case and worst case.
Scenario Unit sales Variable cost (RM)
Fixed costs (RM)
Base 190 11,200 410,000
Best 209 10,080 369,000
Worst 171 12,320 451,000
OCFbase = [(18,000 – 11,200)(190) – 410,000](0.65) + 0.35(1,700,000/4)
OCFbase = $722,050
NPVbase = –1,700,000 + 722,050 x 1- (1/ (1 + 0.12)4 ) 0.12
NPVbase = 493,118.10
• Calculate for the 2 scenarios
• Evaluate the sensitivity of base case Net Present Value
(NPV) to changes in fixed costs.• To calculate the sensitivity of the NPV to changes in fixed costs
we choose another level of fixed costs. We will use fixed costs of RM420,000. The OCF using this level of fixed costs and the other base case values with the tax shield approach, we get:
OCF = [(18,000 – 11,200)(190)–420,000](0.65) + 0.35(1,700,000/4)
OCF = 715,550
NPV = –1,700,000 + 715,550 x 1- (1/ (1 + 0.12)4 ) 0.12
NPV = 473,375.32
• The sensitivity of NPV to changes in fixed costs is:
NPV/FC = (493,118.10 – 473,375.32)/(410,000 – 420,000)
NPV/FC = –1.974
For every value increase in fixed costs, net present value falls by RM1.974
Sensitivity Analysis• What happens to NPV when we change
one variable at a time• This is a subset of scenario analysis
where we are looking at the effect of specific variables on NPV
• The greater the volatility in NPV in relation to a specific variable, the larger the forecasting risk associated with that variable, and the more attention we want to pay to its estimation
11-9
Summary of Sensitivity Analysis for New Project
Scenario Unit Sales Cash Flow NPV IRR
Base case 6,000 59,800 15,567 15.1%
Worst case 5,500 53,200 -8,226 10.3%
Best case 6,500 66,400 39,357 19.7%
11-10
Simulation Analysis
• Simulation is really just an expanded sensitivity and scenario analysis
• Monte Carlo simulation can estimate thousands of possible outcomes based on conditional probability distributions and constraints for each of the variables
• The output is a probability distribution for NPV with an estimate of the probability of obtaining a positive net present value
• The simulation only works as well as the information that is entered, and very bad decisions can be made if care is not taken to analyze the interaction between variables
11-11
Making a Decision• Beware “Paralysis of Analysis”• At some point you have to make a decision• If the majority of your scenarios have
positive NPVs, then you can feel reasonably comfortable about accepting the project
• If you have a crucial variable that leads to a negative NPV with a small change in the estimates, then you may want to forego the project
11-12
Break-Even Analysis
• Common tool for analyzing the relationship between sales volume and profitability
• There are three common break-even measures– Accounting break-even – sales volume at which
NI = 0– Cash break-even – sales volume at which OCF
= 0– Financial break-even – sales volume at which
NPV = 0
11-13
Example: Costs• There are two types of costs that are important in
breakeven analysis: variable and fixedTotal variable costs = quantity * cost per unit
–Fixed costs are constant, regardless of output, over some time period
Total costs = fixed + variable = FC + vQ
• Example:–Your firm pays $3,000 per month in fixed costs. You also pay $15 per unit to produce your product.
• What is your total cost if you produce 1,000 units?
• What if you produce 5,000 units?
11-14
Average vs. Marginal Cost• Average Cost
TC / # of units–Will decrease as # of units increases
• Marginal Cost–The cost to produce one more unit–Same as variable cost per unit
• Example: What is the average cost and marginal cost under each situation in the previous example–Produce 1,000 units: Average = 18,000 / 1000 = $18–Produce 5,000 units: Average = 78,000 / 5000 = $15.60
11-15
Accounting Break-Even
• The quantity that leads to a zero net income
• NI = (Sales – VC – FC – D)(1 – T) = 0
• QP – vQ – FC – D = 0
• Q(P – v) = FC + D
• Q = (FC + D) / (P – v)
11-16
Using Accounting Break-Even
• Accounting break-even is often used as an early stage screening number
• If a project cannot break-even on an accounting basis, then it is not going to be a worthwhile project
• Accounting break-even gives managers an indication of how a project will impact accounting profit
11-17
Accounting Break-Even and Cash Flow
• We are more interested in cash flow than we are in accounting numbers
• As long as a firm has non-cash deductions, there will be a positive cash flow
• If a firm just breaks even on an accounting basis, cash flow = depreciation
• If a firm just breaks even on an accounting basis, NPV will generally be < 0
11-18
Example• Consider the following project
– A new product requires an initial investment of $5 million and will be depreciated to an expected salvage of zero over 5 years
– The price of the new product is expected to be $25,000, and the variable cost per unit is $15,000
– The fixed cost is $1 million– What is the accounting break-even point each
year?• Depreciation = 5,000,000 / 5 = 1,000,000• Q = (1,000,000 + 1,000,000)/(25,000 –
15,000) = 200 units
11-19
Sales Volume and Operating Cash Flow
• What is the operating cash flow at the accounting break-even point (ignoring taxes)?
OCF = (S – VC – FC - D) + DOCF = S – VC – FC
OCF = (200*25,000 – 200*15,000 – 1,000,000 - 1,000,000) + 1,000,000 = 1,000,000
• What is the cash break-even quantity?Q = FC / (P – v)
Q = (0 + 1,000,000) / (25,000 – 15,000) = 100 units
11-20
Three Types of Break-Even Analysis
• Accounting Break-even
Q = (FC + D) / (P – v)• Cash Break-even
Q = FC / (P – v)• Financial Break-even
Q = (FC + OCF) / (P – v)• Cash BE < Accounting BE < Financial BE
11-21
Example: Break-Even Analysis
• Consider the previous example– Assume a required return of 18%– Accounting break-even = 200– Cash break-even = 100– What is the financial break-even point?
• Similar process to that of finding the bid price• What OCF (or payment) makes NPV = 0?
– N = 5; PV = 5,000,000; I/Y = 18; CPT PMT = 1,598,889 = OCF
• Q = (1,000,000 + 1,598,889) / (25,000 – 15,000) = 260 units
11-22
Operating Leverage• Operating leverage is the relationship
between sales and operating cash flow• Degree of operating leverage measures
this relationship– The higher the DOL, the greater the variability
in operating cash flow– The higher the fixed costs, the higher the DOL– DOL depends on the sales level you are
starting fromDOL = 1 + (FC / OCF)
11-23
Example: DOL• Consider the previous example• Suppose sales are 300 units
– This meets all three break-even measures– What is the DOL at this sales level?– OCF = (25,000 – 15,000)*300 – 1,000,000 =
2,000,000– DOL = 1 + 1,000,000 / 2,000,000 = 1.5
• What will happen to OCF if unit sales increases by 20%?
Percentage change in OCF = DOL*Percentage change in Q
– Percentage change in OCF = 1.5(.2) = .3 or 30%– OCF would increase to 2,000,000(1.3) = 2,600,000
11-24
Capital Rationing• Capital rationing occurs when a firm or division
has limited resources– Soft rationing – the situation that occurs when
units in a business are allocated a certain amount of financing for capital budgeting.
– Hard rationing – the situation that occurs when a business cannot raise financing for a project under any circumstances.
• The profitability index is a useful tool when a manager is faced with soft rationing
11-25
Comprehensive Problem
• A project requires an initial investment of $1,000,000 and is depreciated straight-line to zero salvage over its 10-year life. The project produces items that sell for $1,000 each, with variable costs of $700 per unit. Fixed costs are $350,000 per year.
• What is the accounting break-even quantity, operating cash flow at accounting break-even, and DOL at that output level?
11-26
SolutionAccounting break-even:•Q = (FC + D) / (P – V)
= ($350,000 + $100,000) / ($1,000 - $700)
= 1,500 units•OCF = ( S – VC – FC – D) + D
= ([1,500 x $1,000] – [1,500 x $700]
- $350,000 - $100,000) + $100,000
= $100,000•DOL = 1 + (FC / OCF)
= 1 + ($350,000 / 100,000)
= 4.5
CLASS EXERCISE
• Olin Transmissions, Inc., has the following estimates for its new gear assembly project: price RM1,900 per unit: variable costs = RM240 per unit; fixed costs = RM 4.8 million; quantity = 95,000 units. Suppose the company believes all of its estimates are accurate only within ± 15%. What values should the company use for the four variables given here when it performs its best case scenario analysis? What about the worst case scenario?
• A project has the following data:Price = $57 per unit
Variable cost = $32 per unit
Fixed cost = $9,000
Required return = 12%
Initial Investment = $18,000
Life= 4 years
Depreciation = straight line method
Calculate:
• Accounting break even
• Cash break even
• Financial break even
Boh Valley is a company produces tea. The company recently change its packing machine. The machine's initial cost is RM2,000, and the depreciation value is RM250 per year. The machines have 4 years project life. The fixed costs of the machine RM2,000 per year and variable cost is RM6 per unit. A packet of tea is selling at RM20. Boh Valley required rate of return is 10 percent. Calculate:
•Accounting break even.•Financial break-even point for the project.•Cash break even
Tutorial
• Ross, Westerfield, Jordon (2010). Fundamental of Corporate Finance, 9th Edition
• Q: 1, 5, 9, 13, 19
• Pages: 360 - 362