18 May 2017 HYDRO CHILE’S RÍO COLORADO POWER PLANT CONNECTED TO GRID UNDER HIGH VOLTAGE e Chilean utility company “Gestión de Proyectos Eléctricos” (GPE) began operating a new hydropower plant in the Región del Maule in March 2017. e plant, which is equipped with two Francis turbines, utilises the potential energy from the Río Colorado, which has its source close to the national border with Argentina. e Austrian manufacturer Global Hydro Energy GmbH was able to supply a complete electromechanical package and in so doing add another perfectly implemented hydropower plant to its extensive list of international reference projects. In addition, the turbine manufacturers gained valuable know-how for future projects by implementing compact high-voltage switchgear for the first time. A s the world’s longest range of moun- tains above ground, the Andes extend along the west coast of the South Ame- rican continent through Colombia, Ecuador, Peru, Bolivia, Argentina and Chile. ey ex- tend for a vast 7,500 km from north to south. Together with the Amazon, the river cont- aining the most water in the world, the huge mountain range forms the backbone of the potential for hydropower in South America. “In Chile, for example, the region in the cen- tral area of the country in which the Río Colorado rises is the source of around 20% of the hydropower which is generated across the country,” remarks omas Schweiger, GPE project manager for the new hydropower plant which was completed in spring 2017. Although the amount of water available at the location naturally fluctuates with the different seasons, the operators expect a comparatively high capacity utilisation factor of between 50 and 70%. CLASSIC DIVERSION PRINCIPLE e plant in the Chilean Región del Maule was implemented using the classic diversion principle; the construction work lasted for a total of around 2.5 years. A transverse struc- ture constructed with a solid concrete design dams the Río Colorado and guides it into an open weir channel. According to the official specifications, the prescribed delivery rate will fluctuate in a range of at least 1.5 to no more than 3 m³/s. According to project ma- nager Schweiger, the construction of the open weir channel stretching over many kilometres required a great deal of structural After around 2.5 years of construction, the newly built diversion power plant on the Río Colorado began operating normally in March 2017. All the hydroelectric equipment at the power plant was supplied and installed by the Austrian company Global Hydro Energy GmbH. photo credit: GPE In the Región del Maule in the central region of the country, clean green electricity is produced at a whole host of hydropower plants. photo credit: GPE

Transcript of CHILE’S RÍO COLORADO POWER PLANT CONNECTED TO · PDF fileCHILE’S RÍO...

18 May 2017

HYDRO

CHILE’S RÍO COLORADO POWER PLANT CONNECTED TO GRID UNDER HIGH VOLTAGEThe Chilean utility company “Gestión de Proyectos Eléctricos” (GPE) began operating a new hydropower plant in the Región del Maule in March 2017. The plant, which is equipped with two Francis turbines, utilises the potential energy from the Río Colorado, which has its source close to the national border with Argentina. The Austrian manufacturer Global Hydro Energy GmbH was able to supply a complete electromechanical package and in so doing add another perfectly implemented hydro power plant to its extensive list of international reference projects. In addition, the turbine manufacturers gained valuable know-how for future projects by implementing compact high-voltage switchgear for the first time.

As the world’s longest range of moun-tains above ground, the Andes extend along the west coast of the South Ame-

rican continent through Colombia, Ecuador, Peru, Bolivia, Argentina and Chile. They ex-tend for a vast 7,500 km from north to south. Together with the Amazon, the river cont-aining the most water in the world, the huge mountain range forms the backbone of the potential for hydropower in South America. “In Chile, for example, the region in the cen-tral area of the country in which the Río Colorado rises is the source of around 20% of the hydropower which is generated across the country,” remarks Thomas Schweiger, GPE project manager for the new hydropower plant which was completed in spring 2017. Although the amount of water available at the location naturally fluctuates with the different seasons, the operators expect a comparatively high capacity utilisation factor of between 50 and 70%.

CLASSIC DIVERSION PRINCIPLEThe plant in the Chilean Región del Maule was implemented using the classic diversion principle; the construction work lasted for a total of around 2.5 years. A transverse struc-ture constructed with a solid concrete design dams the Río Colorado and guides it into an

open weir channel. According to the official specifications, the prescribed delivery rate will fluctuate in a range of at least 1.5 to no more than 3 m³/s. According to project ma-nager Schweiger, the construction of the open weir channel stretching over many kilometres required a great deal of structural

After around 2.5 years of construction, the newly built diversion power plant on the Río Colorado began operating normally in March 2017. All the hydroelectric equipment at the power plant was supplied and installed by the Austrian company Global Hydro Energy GmbH.

pho

to c

redi

t: GP

E

In the Región del Maule in the central region of the country, clean green electricity is produced at a whole host of hydropower plants.

pho

to c

redi

t: GP

E

May 2017 19

HYDRO

The electrical and control technology was also provided by the Austrian hydroelectric power specialists.

Technical Data

• Flow Rate: 2 x 5,5 m3/s

• Net Head: 168,70 m

• Turbine: 2 x Francis

• Nominal Output: 2 x 8.402 kW

• Runner speed: 750 rpm

• Manufacturer: Global Hydro Energy GmbH

• Generator: 2 x Synchronous

• Total avarage capacity: ca. 79 GWh

and organisational effort and outlay. The rocky terrain meant that there was no option but to use explosives on multiple occasions. Following an open-air section of around 5 km, the waterway transitions into a closed penstock made from steel pipes laid largely above ground. The final section of pipework has a consistent dimension of DN2200 and extends for a length of 530 m. Shortly before the water is turned into power in the power-house, the penstock is divided by a Y-branch pipe which is laid underground.

TURBINES IN THE MEDIUM POWER RANGE“The bid for the ‘Río Colorado’ project fitted our technical portfolio precisely from a hydro mechanical point of view. Although the two Francis turbines with a spiral casing were not the biggest machines that we have ever manufactured, with a power output of

around 8.4 MW each they still fall within the medium power range of what is offered by GLOBAL Hydro. The benefit that this produces for the end customers is that they can rely on a well-developed product that is manufactured at a very high technical level as standard. All machines are subjected to our tried-and-tested quality procedure both during and before construction, and ultima-tely arrive at their intended destinations as highly effective suppliers of electricity,” says GLOBAL Hydro project manager Dietmar Lehner. The company delivered this contract as what is known as a “water to wire” project – all of the electromechanical components were fully manufactured or provided by GLOBAL Hydro, properly installed and commissioned. For the new power plant on the Río Colorado, two completely identical Francis machines with a horizontal shaft and

a design discharge capacity of 5.5 m³/s each were manufactured. The turbines are provi-ded with a net drop height of 168.7 m, which allows a maximum power output of 8,402 kW to be achieved by each of them. Each of the hydraulically controlled turbines has a rotational speed of precisely 750 rpm. The energy converters used are two synchro-nous generators, which also have exactly the same design and are each coupled directly to the turbine shafts. A high-voltage power line stretching for around three kilometres above ground was constructed to feed the power into the public power grid.

SWITCHGEAR WITH HYBRID DESIGN“When it came to the electrical part of the assignment, we opted for a special solution that we had never before implemented in this form,” explains GLOBAL Hydro project

pho

to c

redi

t: GP

E

pho

to c

redi

t: GP

E

pho

to c

redi

t: GP

E

Up to 11 m3/s are diverted at the weir and are transported through an open weir channel and a penstock to the powerhouse to be turned into energy.

The two Francis spiral turbines of completely identical design are provided with a net drop height of almost 170 m, their design discharge capacity is 5.5 m3/s each.

20 May 2017

HYDRO

manager Thomas Stütz: “And specifically for the first time we supplied high-voltage switchgear with extremely compact dimensions. To be more precise, the equipment has a hybrid design – the switchgear consists of both air-insulated and gas-insulated components and is fully preassembled during the manufacturing stage. This design, which we implemented together with the manufacturer ABB, won over the clients primarily thanks to its comparatively small dimensi-ons. As only a limited amount of space was available on the back of the powerhouse, compact high-voltage switchgear was the ideal solu-tion for the end customer. By implementing switchgear of this design for the first time, we also acquired very substantial know-how. This means we are now also able to offer our customers a 110 kV high-vol-tage output on the electrical side.” Another new aspect for GLOBAL Hydro in the Río Colorado project was the size of the transformer. As this could not be transported in one piece due to its size, the transfor-

mer was dismantled into individual parts capable of being transpor-ted and then reassembled on site.

EVERYTHING INTERLINKEDAccording to Thomas Stütz, another challenge of the project was meeting the control requirements of the Chilean grid operator. For example, to do this it was necessary to set up a communication control system which is based on the “DNP 3.0 protocol” (software protocol for network communication) and enables a constant trans-fer of data between the hydropower plant and the grid operator. “Implementation of the system in consultation with the grid opera-tor on site was extremely complicated in organisational terms. Thomas Schweiger from GPE was a big help to us when it came to interacting and clarifying matters with the companies and local contacts on the ground,” states Dietmar Lehner. In terms of network ing, apart from the connection to the grid operator’s system, further electrical components and substations belonging to the client were also integrated into the plant control system.

POWER PLANT SCADA SYSTEMFor turbine control, GLOBAL Hydro supplied the intelligent “heros 3” control software which it developed itself. Thomas Stütz adds: “When it comes to the turbine controller, the term ‘power plant SCADA system’ is really more accurate. Starting with the generator and turbine control, the entire medium-voltage and high-voltage system and a separate high-voltage station of the end customer several kilometres away was also added to the visualisation of the control system. With “heros 3” electricity is produced in fully automated fashion and, thanks to online connection, there are extensive options for remote control and maintenance. Incidentally, last year we installed a control system of similar complexity at the “Oxec I” hydropower plant in Guatemala in Central America.”

ON THE GRID SINCE THE SPRINGWith regular operation having commenced in March 2017, GPE project manager Thomas Schweiger can now draw a positive conclusion: “The plant is running very satisfactorily and effectively, which at the present time is down to the high quality of the machi-nery equipment and software. The project was definitely also boos-ted by the excellent collaboration and communication with the companies involved.” In a normal year, the new power plant on the Río Colorado will generate around 79 GWh of green electricity, with all of the power going into the public power grid. During the course of this year, GPE is planning to complete another 27 MW hydropower plant on a reservoir in the Región del Maule.

pho

to c

redi

t: GP

E

pho

to c

redi

t: GP

E

pho

to c

redi

t: GL

OBAL

Hyd

ro

Ideally each turbine can generate a maximum power output of more than 8.4 MW.

For the hydropower project on the Río Colorado, GLOBAL Hydro supplied compact high-voltage switchgear with a hybrid design in cooperation with a partner company for the first time.

After passing through the turbine, the works water which is removed is guided back into the natural course of the waterway.