Cheshire Elementary Cheshire Elementary SchoolSchool
Sanitary Sewer Sanitary Sewer ImprovementsImprovements
Preliminary Informational Preliminary Informational MeetingMeeting
April 13, 2009April 13, 2009
Background InformationBackground Information• The Olentangy Local School District will open the new Cheshire Elementary School on Gregory Road The Olentangy Local School District will open the new Cheshire Elementary School on Gregory Road
in fall, 2010. in fall, 2010.
• Delaware County has committed to provide sanitary sewer service to the new school.Delaware County has committed to provide sanitary sewer service to the new school.
► The Delaware County Board of Commissioners has committed to provide sanitary sewer service to The Delaware County Board of Commissioners has committed to provide sanitary sewer service to the new school.the new school.
Locations of Proposed School Locations of Proposed School & Existing Sanitary Sewer& Existing Sanitary Sewer
Existing sanitary Existing sanitary sewer sewer
is located at theis located at theintersection ofintersection ofCheshire Road Cheshire Road and S. Old State and S. Old State
Road. Road.
Preliminary Sewer Alignment Preliminary Sewer Alignment StudiesStudies
► The County has evaluated several possibilities for The County has evaluated several possibilities for the alignment of the sewer, keeping in focus:the alignment of the sewer, keeping in focus:
Maximizing Sewer Service Maximizing Sewer Service
Overall CostOverall Cost
ConstructabilityConstructability
► Pump stations and force mains are not desirable Pump stations and force mains are not desirable due to energy costs & short and long term due to energy costs & short and long term maintenance issues.maintenance issues.
General Path of PreliminaryGeneral Path of PreliminarySanitary Sewer AlignmentSanitary Sewer Alignment
Preliminary Sanitary Sewer Preliminary Sanitary Sewer Alignment OptionsAlignment Options
Proposed Cheshire Elementary School
Site
CHESHIRE ROAD
GR
EG
OR
Y R
OA
D
RA
ILRO
AD
TR
AC
KS
LAC
KEY O
LD S
TA
TE
RO
AD
LEGEND
Sanitary Sewer Option
A
Sanitary Sewer Option
B
Common Portion of
Sewer Options A &
B
Existing County
Sanitary Sewer
EXISTING COUNTY SANITARY SEWER
SANITARY SEWER OPTION A
SANITARY SEWER OPTION B
COMMON PORTION OF SANITARY SEWER OPTIONS A AND B
► The preliminary alignment has been narrowed to 2 options, A & B.The preliminary alignment has been narrowed to 2 options, A & B.
Upcoming Studies & EventsUpcoming Studies & Events
► The final alignment of the sewer will be determined The final alignment of the sewer will be determined by Delaware County following completion of the by Delaware County following completion of the work by surveyors and other technical consultants.work by surveyors and other technical consultants.
► The surveyors and consultants will need to enter The surveyors and consultants will need to enter properties along the preliminary alignment to properties along the preliminary alignment to perform their studies.perform their studies.
► Per Ohio Revised Code Section 6117.01(F), Per Ohio Revised Code Section 6117.01(F), Delaware County has already mailed letters to Delaware County has already mailed letters to property owners whose land is along the path of the property owners whose land is along the path of the preliminary alignment.preliminary alignment.
Upcoming Studies & EventsUpcoming Studies & Events(Continued)(Continued)
► The surveyors and other consultants will begin their The surveyors and other consultants will begin their work starting this week. work starting this week.
► It is anticipated that the studies will be completed It is anticipated that the studies will be completed in approximately 2 months.in approximately 2 months.
► Once the County determines the final alignment, Once the County determines the final alignment, easement negotiations with property owners will easement negotiations with property owners will begin.begin.
► Construction of the sewer is anticipated to begin in Construction of the sewer is anticipated to begin in late 2009. late 2009.