Chapter: South Dakota State University Project: Drinking Water for UAC...
Transcript of Chapter: South Dakota State University Project: Drinking Water for UAC...
Document 525 Pre-Implementation Report Chapter: South Dakota State University Country: Bolivia Community: Unidad Academica Campesina, Carmen Pampa Project: Drinking Water for UAC-CP Travel Dates: August 9-22, 2015
Prepared By Joseph Abrahamson Deidre Beck Jacob Davidson
Luis Duque May 17, 2015
ENGINEERS WITHOUT BORDERS USA www.ewb-usa.org
Pre-Implementation Report Part 1 – Administrative Information
1.0 Contact Information (correspondence regarding report reviews will be sent to the listed President, Project Leads, Mentors and Faculty Advisors)
Project Title Name Email Phone Chapter Name or
Organization Name
Project Leads
Luis Duque
Deidre Beck
305-965-1363
605-280-8548
EWB- SDSU
President Claire
Eggleston
claire.eggleston@jacks,sdstate,edu 952-456-1009 EWB -SDSU
Responsible Engineer in Charge
Bruce
Berdanier
[email protected] 605-415-3237 EWB-SDSU
Traveling Mentor
Brad Wermers [email protected] 605-592-6202 EWB-SDSU
Additional Mentor
Faculty Advisor
Kyungnan Min [email protected] 605-688-4918 EWB- SDSU
Health and Safety Officer
Ben Waletzko [email protected] 612-532-5186 EWB -SDSU
Assistant Health and Safety Officer
Claire
Eggleston
claire.eggleston@jacks,sdstate,edu 952-456-1009 EWB- SDSU
Education Lead
Luis Duque [email protected] 305-965-1363 EWB-SDSU
Planning, Monitoring, Evaluation and Learning (PMEL) Lead
Luis Duque [email protected] 305-965-1363 EWB-SDSU
In-country Community Contact
Sister
Christina
Cullen
[email protected] (591) 73220804
UAC-CP
In-country NGO Contact
Sarah Berman [email protected] (591) 68101458
UAC-CP
In-country Local Government Contact
Don Lucho Aliaga
NA 591-671-75211
Community of Carmen Pampa Water Board
2.0 Travel History
Dates of Travel Assessment or Implementation Description of Trip
August 10-17, 2011 Assessment Pre Assessment
March 4-10, 2012 Assessment Determine Treatment
December 16-23, 2012 Implementation Construction
August 5-13, 2013 Post Assessment Monitoring and Modification
August 4-12, 2014 Implementation Build and Install Chlorinator
3.0 Travel Team (Should be 8 or fewer): # Name E-mail Phone Chapter Student or
Professional
1 Claire
Eggleston
[email protected] 952-
456-
1009
SDSU Student
2 Luis Duque [email protected] 305-
965-
1363
SDSU Student
3 Ben Waletzko
[email protected] 612-532-5186
SDSU Student
4 Brad Wermers
[email protected] 605-592-6202
SDSU Professional
5
6
7
8
4.0 Health and Safety The travel team will follow the site-specific HASP that has been prepared for this specific
trip and has been submitted as a stand-alone document along with this pre-trip report.
EWB-SDSU and the Drinking Water for UAC-CP project have no history of health and
safety incidents.
5.0 Planning, Monitoring, Evaluation and Learning 5.1 The travel team has reviewed the 901B – Program Impact Monitoring
Report template and has assigned travel team members to complete this report during the upcoming trip. We acknowledge that the completed 901B is required with the eventual submittal of the 526 – Post-Implementation Trip Report. X Yes ___No
5.2 The team has selected monitoring indicators from the 906 - Project Monitoring Indicators charts. These will be assessed on this trip and reported on in the 526 – Post-Implementation Trip report. X Yes ___No
The team has chosen the red boxed items as monitoring indicators for this project.
5.3 Is the signed 903 - Implementation Agreement included as an appendix to
this report? _X_Yes ___No (An equivalent Letter of Commitment is included in Appendix 5. EWB-SDSU will be implementing the 902 and 903 versions of the community agreements during this trip)
6.0 Budget
Item Description Cost Basis Total Cost
1 Airfare+Travel Agent Fee
$ 1200.00 per person
$ 4800.00
2 Food and Lodging $ 280.00 per person
$ 1120.00
3 In-Country Transportation
$ 87.50 per person
$ 350.00
4 Travel Insurance (through SDSU)
$ 40.00 per person
$ 160.00
5 QA/QC $ 1210.00 per trip $ 1210.00
6 Project Supplies/Materials
$ 1000.00 total $ 1000.00
Total: $ 8640.00
*The costs associated with acquiring appropriate travel documents (visas, passports) and medical preparation (shots, medications) are the responsibility of the individual travelers.
7.0 Project Discipline(s): Check the specific project discipline(s) addressed in this report. Check all that apply.
Water Supply ____ Source Development ____ Water Storage ____ Water Distribution X _ Water Treatment ____ Water Pump Sanitation ____ Latrine ____ Gray Water System ____ Black Water System Structures ____ Bridge ____ Building
Civil Works ____ Roads ____ Drainage ____ Dams Energy ____ Fuel ____ Electricity Agriculture ____ Irrigation Pump ____ Irrigation Line ____ Water Storage ____ Soil Improvement ____ Fish Farm ____ Crop Processing Equipment Information Systems ____ Computer Service
8.0 Project Location Longitude: 67°41’30.3” W Latitude: 16°15’29.7”S
The Unidad Academica Campesina (UAC) is a branch of the Catholic University of Bolivia. The
UAC is located in the rural community of Carmen Pampa in the Nor Yungas province in the
department of La Paz, Bolivia. In addition to the approximately 700 university students at the
UAC, Carmen Pampa is also home to 500 high school students who attend a local boarding high
school and 250 community members. Carmen Pampa is located approximately 15 km from the
town of Coroico and 115 km from the Bolivian capital of La Paz.
9.0 Number of People Number of persons directly affected: 700-800 (Students of the UAC-CP Campus Manning). Number of persons indirectly affected: 1150 (Entire community including both schools)
10.0 Professional Mentor Resume(s) - Please see document 405 - Mentor Qualifications for the requirements for the Responsible Engineer in Charge (REIC) and the overall Professional Mentor Team. This can be found in the Sourcebook Downloads on the Member Pages of the website.
Dr. Bruce Berdanier- Responsible Engineer In Charge (Not Traveling):
Vita for Bruce W. Berdanier
Dr. Berdanier is currently Professor and Dean of the School of Engineering
(SOE) at Fairfield University. As the chief academic officer for the School of
Engineering, he recently led the development of a new BS degree in
Bioengineering, relocation of the Computer Science program from the
College of Arts and Sciences to the SOE, and development of multiple 5-year
BS/MS options. He has complete responsibility for developing and
implementing the school’s budget which was approximately $7M income and
$2M direct expenses for FY17. During 2013-14, Dr. Berdanier led the
development of the School’s strategic plan for the next five years including
SWOT analysis, development of vision, mission and values statements, as well
as strategic goals and activities. Dr. Berdanier also led the planning and
relocation of the SOE to new offices, classrooms, and laboratories in the
Bannow Science Center during 2013-14. He successfully acquired external
funding for a new machine laboratory in 2013, a Materials Characterization laboratory and a Network
Systems laboratory in 2014. He is currently implementing an Applied Research Laboratory and is
collaborating with the School of Business in development of an Entrepreneurship Center. Dr.
Berdanier has served on the University Steering Committee for Strategic Planning and has been Co-
Chair of the task force for Graduate and Professional Schools since 2013.
Dr. Berdanier’s main research and consulting interests have been related to the distribution and
interactions of various chemical compounds in studies of surface water quality and in municipal
wastewater treatment. His most recent research efforts have related to the distribution of metals in
surface water, soils, sediments, and plants. Dr. Berdanier is a registered professional engineer and
surveyor in both South Dakota and Ohio and has been involved in water and environmental
development projects in the Artibonite Valley of Haiti since 1995. He has directed an Engineers
Without Borders program in Bolivia since 2009.
Academic Experience:
▪ July 2013 to Present – Dean of Engineering, Fairfield University, Fairfield, CT.
▪ August 2008 to July 2013 – Professor and Head of Civil and Environmental Engineering,
South Dakota State University, Brookings, South Dakota.
▪ August 2003 to August 2008 – Associate Professor of Civil Engineering, Ohio Northern
University, Ada, Ohio.
▪ August 2000 to August 2003 – Assistant Professor of Civil Engineering, Ohio Northern
University, Ada, Ohio.
▪ August 1996 to August 2000 - Assistant Professor of Civil and Environmental Engineering,
South Dakota School of Mines and Technology, Rapid City, South Dakota.
Education/Registration:
▪ Ph.D.- Environmental Engineering and Hydrogeology, The Ohio State University, 1995
▪ MSCE- Environmental Engineering, Purdue University, 1983
▪ BSCE- Water Resources, The Ohio State University, 1980
▪ Registered Professional Engineer- Ohio #49339, South Dakota #6197
▪ Registered Professional Surveyor- Ohio #6991, South Dakota #6197
Professional Membership:
▪ American Society for Engineering Education
▪ American Society of Civil Engineers
▪ Engineers Without Borders USA
Professional Service ▪ ABET Program Evaluator, 2009 - Present
▪ American Society of Civil Engineers, Region 7 Governor, October 2010 – May 2013.
▪ American Society of Civil Engineers, National Comm. on Scholarship, Sept. 2007 - 2011
▪ South Dakota Water Environment Association, Vice President, Sept.1997- Aug.1999.
▪ South Dakota Water Environment Association, President, Sept. 1999 – Aug. 2000.
Recent Publications
▪ Kant, J.A., Larson, G.E., Burckhard, S.R., Berdanier, B.W., and Meyers, R.T., (2015)
“Contemporary Use of Wild Fruits by the Lakota in South Dakota: Implications to Cultural
Identity, Great Plains Research, University of Nebraska Press, Lincoln, NE, in press.
▪ Ande, S., Berdanier, B.W., and Ramakrishnan, V., (2013), “Surface Morphology of Reactive
Powder Concrete Containing Soil,” Journal of Environmental Science and Engineering, 2(4),
250-255.
▪ Bielefeldt, A.R., Dewoolkar, M.M., Caves, K.M., Berdanier, B.W., Paterson, K.G., (2011),
“Diverse Models for Incorporating Service Projects into Engineering Capstone Design
Courses,” International Journal of Engineering Education, 27(6), 1206-1220.
▪ Ande, S., Berdanier, B.W., and Ramakrishnan, V., (2011), “Performance of Reactive Powder
Concrete Containing Arsenic,” Journal of Water Resource and Protection, 3(5), 335-340,
doi:10.4236/jwarp.2011.35042.
▪ Sundareshwar, P.V., Upadhayay, S., Abessa, M., Honomichl, S., Berdanier, B.W., Spaulding,
S.A., Sandvik, C., and Trennepohl, A., (2011), “The Paradox of Algal Blooms in
Oligotrophic Waters,” Geophysical Research Letters, Vol. 38, L10405,
doi:10.1029/2010GL046599.
Recent Funding
▪ September 2014, Materials Characterization Laboratory at Fairfield University; Equipment
Funding: $75,000 Alden Family Trust; $72,000 Brinkman Family Foundation; $42,000
Fairfield Capital Improvements; $10,000 Robert Sobolewski.
▪ September 2013, Machine Laboratory at Fairfield University; Equipment funding of $90,000
Brinkman Family Foundation.
▪ September 2010, National Science Foundation, “Collaborative Research:
OLC/SDSU/SDSMT Pre-Engineering Education Collaborative,” $825,000.
▪ September 2009, Berdanier, B.W., and DeBoer, D., National Science Foundation,
“Acquisition of Inductively Coupled Plasma – Optical Emission Spectrometer,” $118,944.
Brad Wermers- Travel Mentor *Mentor Paperwork will be included in submittal.
BRAD WERMERS, PE Associated with Banner since 1989, Brad serves as the Head of the Civil/Transportation Department. With over twenty years of experience in civil/municipal/transportation planning and design, Brad understands the many complexes of municipal street design, which include project management, project coordination with local government and contractors, site grading, utility design and storm design.
Education
B.S. Civil Engineering,
South Dakota State University, 1989
Professional Registration
Professional Engineer SD
Professional Affiliations
National Society of Professional Engineers
South Dakota Engineering Society
Planning, design, plans and specifications, bidding, construction engineering and contract administration phases of
municipal projects for streets; highways, airports, water distribution; wastewater collection; storm drainage systems;
land/site development and land acquisitions. Field observations for compliance with design, drawings and
specifications during construction, including earthwork, underground pipelines and utilities.
SDSU Projects
SDSU Alumni Green, Brookings, SD
SDSU Indoor Practice Facility, Brookings, SD
SDSU Dana J. Dykhouse Stadium, Brookings, SD
SDSU Southeast Residence Halls, Brookings
SDSU Headhouse, Brookings, SD
SDSU Architecture, Mathematics and Engineering Hall, Brookings;
SDSU Student Enrollment Center, Brookings, SD
Residential Subdivisions
Windermere Pointe Addition - Site Development, Brookings, SD
South Main & 26th Avenue Improvements, Brookings, SD
Moriarty-Edgebrook Addition - Site Development, Brookings, SD
Moriarty Fourth Addition - Site Development, Brookings, SD
Timberline Addition - Site Development, Brookings, SD
Prairie Hills Addition - Site Development, Brookings, SD
Reserve Addition - Site Development, Brookings, SD
West Timberline - Site Development, Brookings, SD
Milparc Addition - Site Development, Brookings, SD
Municipal Street Projects
32nd Ave Street Construction, Brookings, SD
Volga Street Improvements, Volga, SD
34th Avenue Reconstruction, Brookings, SD
Main Avenue and 26th Avenue South, Brookings, SD
Lake Norden Truck Route, Lake Norden, SD
20th Street Reconstruction, Brookings, SD
Bulldog Avenue Reconstruction, Baltic, SD
Arlington Streets Improvements, Arlington, SD
Medary Avenue Reconstruction, Brookings, SD
Milbank Storm Sewer Evaluation, Milbank, SD
Pierre Storm Sewer Evaluation, Pierre, SD
57th Street Reconstruction, Sioux Falls, SD
Highway Projects SD County Highway 23 Reconstruction, Brookings County, SD SD Highway 19 Construction from Vermillion, SD to Newcastle, NE Brookings County Road Reconstruction, Brookings County, SD US Highway 14 Reconstruction, Haakon County, Haakon County, SD US Highway 18 Reconstruction, Canton, SD US Highway 14A Reconstruction, Lead, SD Interstate 229 / Western Avenue Interchange Reconstruction, Sioux Falls, SD Interstate 229 / Louise Avenue Interchange, Sioux Falls, SD
Pre-Implementation Report Part 2 – Technical Information 1.0 Executive Summary
Engineers Without Borders USA (EWB -USA) is a national organization dedicated to
engineering investigation, assessment, design and implementation to solve problems in
communities typically in the developing world. The student chapter of EWB at South Dakota
State University (EWB-SDSU) initiated a program with Unidad Academica Campesina de
Carmen Pampa (UAC – CP) in Bolivia in the fall of 2010. The location of UAC – CP is shown in
Figure 1.
The Unidad Academica Campesina de Carmen Pampa (UAC-CP) is a rural university founded to
provide a BS-level education to young women and men who do not have that opportunity due to
unequal access to education by the poor. This university currently has over 700 students, having
grown from 53 students when its first program started in 1994. Due to this expansive growth,
potable water systems for each of two campuses, human waste and wastewater management had
not always been adequately considered, leading to the need for improved water quality, as well as
sanitation related to animal waste and human wastewater management. The mission of the EWB-
SDSU program at the UAC-CP is to provide the university with consistent potable water and
waste and wastewater management solutions. The fulfillment of this proposed program will
eliminate problems with student illnesses resulting from poor water quality, and will protect
down-stream communities from the waste generated by the university.
During the past 5 years of collaboration, EWB-SDSU has traveled 4 times to the UAC-CP. The
first trip took place in August 2011 and was to conduct a pre – assessment investigation at the
site. A second trip was made in March 2012 to continue the assessment with additional focus for
the drinking water project. Implementation of the first chlorination system was completed in
December 2012. This system is a CTI-8 chlorinator that treats water for Campus Leahy (the upper
of two university campuses). This implementation was followed up with a post-assessment trip
was made in August 2013. This trip was also used as a preliminary assessment for the next trip. In
August 2014 a second implementation trip was made in order to install a second CTI-8
chlorinator for Campus Manning. During this trip, the community of Carmen Pampa and
university personnel reached an agreement to collaborate on a joint chlorinator that would treat
not only Campus Manning, but also local community members. It was decided to move the
location of the chlorinator to a shared reservoir. In August 2015, the goal of EWB-SDSU will be
to install this shared CTI-8 chlorinator. Additionally, the team will implement educational
activities in order to increase awareness of the project throughout the community and the
university.
The purpose of this document is to describe the design of this chlorinator and its implementation
to take place in August 2015.
2.0 Program Background Water Systems Background
Figure 2 shows the conceptual location and relationship of the original five (5) water distribution
systems in the UAC-CP watershed. Systems 1 and 2 are the most northerly as well as the highest
elevation water collection systems and are the least affected by surface water runoff. System 3 is
was a localized system adjacent to the mid system tanks of system 2 and was highly contaminated
by agricultural and roadway runoff at that level in the watershed. System 3 was taken off-line
and abandoned. The source for system 4 is not as high in elevation as systems 1 and 2 in the
watershed but is currently above agricultural activities as well as the upper roadway. Therefore,
system 4 is relatively unaffected by surface water runoff. System 5 was the lowest system in the
watershed and is highly impacted by agricultural and roadway runoff. System 5 collection was
abandoned and it’s storage reservoir was connected to System 4 distribution for additional storage
capacity for the Manning campus and lower community. Table 1 indicates the ownership of each
of the water collection and distribution systems.
Figure 2. Conceptual Diagram of Water Systems at Carmen Pampa, Bolivia.
Table 1. Water system ownership in Carmen Pampa, Bolivia.
System Owner
1 Community
2 UAC
3 Abandoned
4 Community/UAC
5 Collection Abandoned, Storage Combined
Water Quality Study
Samples of water were taken at four of the sources and analyzed in the field for turbidity
and NO3 concentrations using a field spectrophotometer and a turbidimeter. Samples
were also analyzed in the UAC laboratory for pH. Additionally, samples were collected
and acidified to be analyzed at the SDSU laboratory for arsenic. Results of the 2011
bacterial analysis along with the 2012 field and laboratory analyses are shown in Table 2.
Numbers presented for each source are averages based on a minimum of 3 samples at
each source.
Table 2. Water Quality Assessment – Carmen Pampa sources.
Source Coliform, # 1,2
Turbidity,
NTU
NO3, mg/L pH Arsenic,
ug/L5
1 1 2.7 2.8 7.5 10
23 2 14.5 20 7.6 10
4 7 6.2 1.3 7.0 20
54 4 28 2.2 6.0 20
Notes: 1Number of coliform forming colonies per 100 mL 2 No e-coli were identified in the sources. Community doctor has identified giardia,
amoeba, and helminth (Ascaris lumbricoides) issues believed to be related to source
water quality. 3 System 2 reservoir is currently contaminated by system 3 surface water source resulting
in high turbidity and NO3. 4 System 5 is open channel surface water source downstream of system 4 capture. 5 Arsenic numbers are consistent with the HNO3 grade that was available at UAC-CP for
preservation of the samples. Appendix 1 contains a map showing that no arsenic
concerns have been identified in the project area to date.
Alternatives Analysis Summary
The alternatives considered for improving the drinking water system included the
following:
1. Disconnect perennially contaminated collection systems from the general distribution
system. This alternative would disconnect systems 3 and 5 from the residential and
school drinking water systems and direct them to agricultural use.
2. Install one disinfection system for each collection system. This alternative would consist
of installing simple robust tablet chlorination systems at collection reservoirs in each of
the numbered system to allow for development of reasonable Ct values for reduction of
bacteria, nematodes and some protozoans (5 systems @ $1,000 per system for material
and labor).
3. Install one disinfection system for each distribution system. This alternative is similar to
alternative 2, but rather than installing tablet chlorinators at reservoir storage locations in
each of the five systems, liquid metered disinfection systems would dose the distribution
system prior to entry points to distribution at both the upper and lower UAC – CP
campuses and the high school (3 systems @ $2,000 per system for material and labor).
4. Install Individual filter systems for house/dormitory drinking water. This alternative
would consist of constructing individual sand filter systems for use at each of the
homes/dormitories for filtration of drinking and cooking water only. The sand filters at
the dormitories could be larger unit to serve multiple rooms. All other water used in the
home/dormitory for activities other than drinking and cooking would not be filtered (40
houses @ $100 each; 2 campuses and 1 high school @ $1,000 each).
5. Abandon current collection systems and install a new well and storage system. This
alternative would develop one or more deep wells along with elevated storage to supply
both of the campuses and the community with treated ground water. Current surface
water systems could be used for agricultural use and for other than drinking and cooking
water activities in the schools and homes. (2 deep wells with pumps @ $25,000 ea., 2 -
50,000 gallon storage tanks @ $75,000 each for material and labor including connecting
piping, valves, and appurtenances).
6. Install surface water treatment plant. This alternative would develop a slow sand surface
water treatment plant with disinfection for the treatment of the current surface water
systems prior to distribution to the campuses, community and high school. ($500,000 for
surface water treatment plant, $150,000 for storage tanks, for material and labor
including connecting piping, valves, and appurtenances).
7. Install individual filter systems in the village and disinfection or treatment for the
university campuses and high school. This alternative would consist of constructing
individual sand filter systems for use at each of the homes for filtration of drinking and
cooking water only. All other water used in the home for activities other than drinking
and cooking would not be filtered. Additionally, surface water treatment and disinfection
would be selected for the university campuses and the high school. This is a combination
of alternatives 3 and 4 with a more expanded treatment concept for the schools.
8. Install roof water collection systems at college campuses and high school. Substantial
water collection could be accomplished at each of the campuses and the high school due
to the large roof areas. This water could be untreated and used to replace agricultural
water, toilet and shower water, or could be treated and used for drinking and cooking (2
systems at $50,000 each).
9. Do Nothing. Continue in current operational mode.
Individual alternative systems were compared based on evaluation of their impact on the
local society, the local economy, and the local environment. Preliminary capital and
operation and maintenance costs were determined for each alternative.
The overall rankings determined by the group analysis averages indicate that alternative
number one is the preferred alternative. Alternative one is the disconnection of the
perennially contaminated collection systems from the general distribution system. This
alternative would disconnect systems 3 and 5 from the residential and school drinking
water systems and direct them to agricultural use. It is not surprising that this alternative
was selected first in the sustainability analysis due to its low capital and maintenance
costs. Ideally this alternative can be accomplished in conjunction with some of the more
structurally intensive alternatives.
The second ranked project was alternative number four which is the construction and use
of individual filter systems at each of the village residences and dormitories. This
alternative also yielded positive results for low capital and operation and maintenance
costs. Low cost individual filters capable of filtering approximately 20 L/d (5 gal/d +/-)
for individual homes to use for drinking water could be constructed. Larger systems
could be built for the dormitories. The project could be completed for the village
residents for approximately $4,000 using locally acquired materials and components.
$1,000 was budgeted for each campus and the high school. The filters could be built in
cooperation with local residents and students within a two-week construction period.
Educational, operational training could also be conducted in the two week project trip.
Alternatives 2, 3, and 8 were each scored the same overall average ranking by the group
resulting in the overall third place ranking. Alternatives 2 and 3 both represent the
installation of a disinfection system. Although both alternatives received the same
average overall score from the team evaluation, it would be the easiest and most cost
effective to install tablet chlorinators (alternative number 2) on some of the existing
collection and storage reservoirs which would operate based on a certain percentage of
the flow coming into the tank and achieve the necessary Ct product for inactivation of
bacteria, viruses, nematodes, and some protozoans. The tablet chlorinators could be
assembled from locally purchased piping materials, are robust and simple to operate, and
have lower capital cost than the liquid chlorinators in alternative 3.
The SDSU EWB team met with UAC Vice Director Smeltekop, Tito Ticona, and UAC
Director Father Freddy del Villar Zúñiga during the March 2012 trip to discuss historical
context, results of the feasibility analysis, and future plans for the drinking water system.
An extensive conversation was held with Director Villar to vette ideas for proceeding
with UAC drinking water system improvements. Concurrence was reached on
chlorinating system 2 in 2012 to demonstrate that chlorination can be properly operated
and maintained to safely improve drinking water. Director Villar also concurred with
pursuing additional or improved filtration for systems 2 and 4 in the future. Site selection
for filtration installation will be a critical component requiring a combination of analysis
of systems 2 and 4 locations along with private/UAC property locations.
The preferred alternative for the next trip to UAC-CP was chosen to be the separation of
the most contaminated systems from the water supply in conjunction with the
development of disinfection for the water collection/storage reservoir to serve the upper
campus. As of May 2015, the most contaminated water supply has been separated from
the drinking water system and one CTI-8 chlorinator has been implemented to serve
Campus Leahy (the upper of two campuses at the UAC-CP). During the August 2015
trip, the second chlorinator will be installed to serve Campus Manning and the
community of Carmen Pampa. Filtration options for individuals and/or groups are
currently being evaluated for future implementation. The entire feasibility analysis is
included as Appendix 2.
3.0 Facility Design
3.1 Description of the Proposed Facilities
The proposed design is to install four CTI 8 chlorinators in parallel on top of storage
reservoir 4 (see figures 3 and 4) to treat the water flowing to the lower Manning campus
of UAC-CP and the nearby community of Carmen pampa.
Figure 4: Reservoir 4, Proposed Chlorinator Site
3.2 Description of Design and Design Calculations
The average available flow rate in water system 2 has been observed at 65 gpm. The CTI 8 chlorinators are rated for 20 gpm each, so that four chlorinators in parallel can handle up to 80 gpm. The lower campus currently serves 350-400 students per day with lower numbers on the weekends and during school breaks. The community is estimated at approximately 200 members. Maximum service is estimated at 600 people. The system design will allow for flexibility to supply the required amount of treated water each day. The design of the system includes throttling valves which will be adjusted after installation is complete to allow the correct total flow of water into the system as well as to develop the desired free chlorine concentration. Additionally, the four parallel systems allow for redundancy in operation at normal operating flows. This redundancy will allow one of the chlorinators to be taken off – line for cleaning and maintenance while the system remains in operation. A chlorine supplier has been identified in La Paz that can provide chlorine tablets at 90% available chlorine for $ 2.72 per tablet. The tablets weigh 200 grams. Each tablet will have the ability to treat approximately 240,000 gallons of water at a finished water
concentration of 0.2 mg/L of free chlorine (Equation 1). The final concentration may be adjusted to a lower value depending on local conditions and population preferences. Equation 1: (200 g/tablet) x (0.90 g Cl/g) x (L/0.2 mg Cl) x (1000mg/g) x (gal/3.785L) ≈ 240,000 gal. The actual operational flow rate will be determined by the university. However, to treat the entire source at the flow rate of 65 gpm, the chlorine cost would be approximately $32 dollars per month (Equation 2). For 600 people at 25 gpcd, the cost would be about $ 5.10 per month (Equation 3). Equation 2: (65 gal/min) x (1440 min/day) x (30 day/month) x ($2.72/240,000 gal) ≈ $31.90/month Equation 3: (600 people) x (25 gal/person·day) x (30 day/month) x ($2.72/240,000 gal) ≈ $5.10/month Finally, 600 people students could be adequately supplied chlorinated water from two of the chlorinators up to a flow rate of 96 gal/person·day (Equation 4). Equation 4: [2(20 gal/min) x (1440 min/day)] / 600 people ≈ 96 gal/student·day Information and schematics for the CTI 8 chlorinator are included in the CTI 8 manual which is Appendix 3 of this design report.
3.3 Drawings The site plan and profile for chlorinator installation are shown in Appendix 4. Figure 5 shows a conceptual schematic of the chlorinator installation.
Figure 5: Schematic of Proposed Dual CTI-8 Chlorinator System
3.4 Names and Qualifications of Designers
Name Student or
Professional
Qualifications Work Done
Andrew Lampy Student Graduating Senior
CEE Student
System Design
Christopher
Jankowski
Student Graduating Senior
CEE Student
System Design
Christopher McGaw Student Graduating Senior
CEE Student
System Design
Tom Strubel Student Graduating Senior
CEE Student
System Design
Dr. Bruce Berdanier Professional PhD, PE Design Supervision
Dr. Kyungnan Min Professional PhD, PE Design Supervision
*The chlorinator system was designed as part of a senior Capstone project by a group of SDSU students. These students were supervised by Dr. Bruce Berdanier and Dr. Kyungnan Min
4” PVC Line
from Air Break
Box
Flow Enters
into Reservoir
2” PVC Ball Valves
CTI-8 Chlorinators
3.5 524 - Draft Final Design Report Comments 4.0 Project Ownership
The UAC-CP and the community of Carmen Pampa will jointly own and operate the CTI
8 chlorination systems. The water system is currently jointly owned and maintained by
the university. The UAC-CP has a permanent staff with the capabilities and funds to
maintain the added chlorination systems. The community will contribute to the system
and appoint a volunteer to help with O&M. A memorandum of agreement between the
university and the community will be signed.
5.0 Construction Plan
Day Work Description Participants
1 • Leave USA; Arrive La Paz; Meet UAC-CP
representative at airport and stay in La Paz
• EWB-SDSU, UAC-CP
representative
2 • Acquire piping, valves, and other appurtenant
materials and hand tools as necessary
• Travel to UAC-CP
• EWB-SDSU, UAC-CP
representative
3 • Meet with community and university
representatives to finalize plan for
construction and education activities
• Prepare for construction
• EWB-SDSU
• UAC-CP
workers/representative
• Community
workers/representatives
4 • Layout chlorinator boxes
• Initiate chlorinator box construction
• Fabricate CTI Chlorinators *
• EWB-SDSU
• UAC –CP workers
supervised by EWB-
SDSU
5 • Finish up activities from Day 4:
o Layout chlorinator boxes
o Initiate chlorinator box construction
o Fabricate CTI Chlorinators *
• EWB-SDSU
• UAC –CP workers
supervised by EWB-
SDSU
6 • Complete construction of chlorinator boxes
• Install CTI Chlorinators
• EWB-SDSU
• UAC –CP workers
supervised by EWB
SDSU
7 • Finish up construction/installation activities • EWB-SDSU
• UAC –CP workers
supervised by EWB-
SDSU
8
• Start up adjustment, sampling and analysis for
initial evaluation, monitoring all day
• Initiate Education
• EWB-SDSU and UAC-
CP
• EWB-SDSU directed
9 • Continue adjustment, sampling, and analysis
• Education/community relations activities
• EWB-SDSU
• UAC –CP workers
supervised by EWB-
SDSU
10 • Continue adjustment, sampling, and analysis
• Education/community relations activities
• EWB SDSU
• UAC –CP workers
supervised by EWB
SDSU
11 • Continue adjustment, sampling, and analysis
• Education/community relations activities
• EWB-SDSU
• UAC –CP workers
supervised by EWB-
SDSU
12 • Complete education and evaluation
• EWB SDSU
• UAC –CP workers
supervised by EWB
SDSU
13 • Travel to La Paz • EWB-SDSU
14 • Travel to USA • EWB-SDSU
Notes: EWB-SDSU students have demonstrated that they can fabricate and build CTI
Chlorinator in approximately one hour using power saw. We have allocated ½ day for each
chlorinator as contingency time using hand saw.
6.0 Materials List and Cost Estimate
Part Quantity Unit Unit Price (Bs) Total Price (BS)
4 in PVC Pipe Schedule 40
6 m 19.5 117
2 in PVC Pipe Schedule 40
12 m 56.8 681.6
PVC Tee 4 in (M) x 4 in (F) x 2 in (M) Schedule 40
8 ea 48 384
PVC Tee 4 in. (M) x 4 in. (F) x 4 in. (F) Schedule 40
5 ea 55 275
Reducer 4 in.(F) a 2 in. (M) Schedule 40
12 ea 35 420
90 de Elbow for 2 in. PVC, male-female, Schedule 40
12 ea 18 216
90 deg Elbow for 2 in. PVC, female-female, Schedule 40
14 ea 18 252
90 deg Elbow for 4 in PVC, female-female, Schedule 40
2 ea 95 190
Female-female connection for 2 in. PVC Schedule 40
2 ea 12.5 25
Cap for 4 in PVC 4 ea 15 60
Cap for 2 in. PVC 1 ea 15 15
Cutting Board 4 ea 21 84
2 in Ball Valve 6 ea 220 1320
Cement 4 bolsa 70 280
Sand 7 caradito 15 105
Bricks 240 ea 1.35 324
PVC Glue 1 ea 55 55
PVC Primer (Thinner)
1 ea 50 50
Metal Lid for Chlorinator
2 ea 680 1360
Metal Lid for Pressure Relief Box
1 ea 400 400
Metal Lid for Tank opening
1 ea 3200 3200
Pad locks 4 ea 28 112
TOTAL 9925.60 Bs
$1389.584 USD
7.0 Operation and Maintenance Once installed, the CTI 8 needs to be checked regularly and new chlorine tablets must be
added on a weekly basis. A color comparison chlorine meter will be used to measure the
free chlorine in the water. Chlorine residuals in the drinking water will need to be tested
weekly during the first ninety days and regularly afterward to ensure that proper
disinfection is taking place. Additionally, the units should be flushed clean quarterly.
Periodically, the chlorinators will need to be cleaned by shutting off the water supply and
disassembling the chlorinators. Since all of the parts are available in La Paz,
replacements should be readily available.
The UAC-CP has staff that currently maintains the water system. These staff will be
trained in maintenance procedures. Compatible Technology International has also
provided operations and maintenance material in Spanish (See Appendix 3), so that the
material will be understandable to the staff in charge of maintenance. Operations and
maintenance personnel for the lower campus will be trained by those who perform O&M
on the upper campus chlorinator.
8.0 Sustainability 8.1 Background
Since the operation and maintenance on this project is within the capabilities of
the UAC-CP and the community of Carmen Pampa, the project is sustainable for
the long-term. All piping and valve components are available off the shelf from
plumbing stores in La Paz.
One societal issue for ensuring sustainability will be making sure that regular
monitoring of the treated water is accomplished to ensure that the proper chlorine
residual is being maintained and that the chlorinator remains in working
condition. This will ensure acceptability of the system to the local people both
from a health improvement and aesthetic (taste) standpoint. In order to ensure
that regular monitoring takes place a maintenance schedule will be implemented
with weekly checks for chlorine and quarterly cleaning of the system.
A second issue for sustainability is the economic affordability of the chlorine
tablets. The chlorine tablets are available through La Paz suppliers and the
university has committed to the annual cost. Current chemical cost is projected at
$0.0001/gal.
The proposed chlorination system is similar to the upper campus chlorinator
system, implemented in December of 2012. The UAC-CP has sustained this
system for 3 years
8.2 Organizational Capacity of The Community
This project will serve both the lower campus of the UAC-CP and the community
of Carmen Pampa. Since the UAC-CP is a university that already employs staff to
care for the water system, the organizational capacity of this group is considered
very good. The university has already shown itself capable of organizing to
support the implementation of the upper campus chlorinator and sustain this
system for over 3 years.
The community of Carmen Pampa has created a water board to support
implementation of water treatment in the community. They have met with
representatives of EWB-SDSU and the UAC-CP and agreed to the proposed
project. A MOA detailing their contributions to system construction and operation
and maintenance will be signed. The organizational capacity of the community is
less than that of the university, but is still considered good. Overall, the joint
organizational capacity of the community and the UAC-CP is sufficient to ensure
the sustainability of the project.
8.3 Financial Capacity of The Community
The cost of the proposed chlorination system is quite low. Materials are estimated
at $1400. The UAC-CP has already earmarked approximately $700 for the
purchase of materials. Additionally, both the UAC-CP and the community of
Carmen Pampa will be contributing labor to the construction of the system. The
cost of chlorine is estimated at $5.10 per month for 600 people, or approximately
$0.11 per person per year. Maintenance costs are also low for the system. The
financial capability of the UAC-CP and the community of Carmen Pampa are
more than sufficient to cover the costs of this project. Community contributions
to materials purchase, as well as non-monetary contributions (such as labor)
exceed the required 5% community contribution. Additionally, chlorine tablets
and on-going O&M costs will be paid for by the UAC-CP and the community of
Carmen Pampa.
8.4 Technical Capacity of The Community The chosen chlorination system is the same as the upper campus chlorination
system installed in December 2012. The design, a CTI-8, chlorinator is easy to
operate, maintain, and repair. It is not technically difficult, and the success of the
first chlorinator has shown that the technology is appropriate with regards to the
technical capacity of the community.
8.5 Education During this trip, EWB-SDSU team members will lead education sessions on both
the upper and lower campus. They will conduct two or three education sessions
for a general audience, including students, staff, and community members who do
not work with the chlorinator, as well as more specific educational/training
activities for the O&M personnel and water system staff. The general educational
activities will focus on the proper use and benefits of chlorinated water, the
importance of good personal hygiene, the scope of the EWB-SDSU project in the
community, and the importance of beneficiary involvement and support for this
project. Educational posters will also be created and hung in public areas of the
university and community to promote awareness year-round. O&M
education/training will include involving system staff in the construction and
implementation process, explanation of system O&M procedures, and
familiarization with O&M material (including system manual). Current UAC-CP
staff that performs O&M on the upper campus will assist with training of lower
campus staff. Luis Duque, the education lead for EWB-SDSU, is a native
Spanish-speaker and will be leading the educational activities.
9.0 Site Assessment Activities No assessment activities for this project will be carried out during this trip.
10.0 Professional Mentor Assessment
10.1 Professional Mentor Name and Role Dr. Bruce W. Berdanier, PE, LS
10.2 Professional Mentor Assessment
The EWB USA SDSU chapter has matured their capacity to work with the
Carmen Pampa Community members over the past year. The chapter met with
the community members at the time we were installing the Manning Campus
chlorinator in Summer 2014. The community asked and the UAC-CP agreed to
have the chlorinator built above the Leahy campus at Reservoir 4 to provide
chlorination to both the campus and the community. The location at Reservoir 4
is easier to maintain, sample and operate as it is close to the existing Chlorinator
at Reservoir 2, and close to the university laboratory on Leahy campus.
10.3 Professional Mentor Affirmation
I have been involved in all of the assessment, evaluation, and design of this
program and all of the individual projects to date. This proposed implementation
is in accord with the original assessment and feasibility study recommendations
completed by the SDSU chapter. I support the implementation of this project as
proposed herein.
May 14, 2015
APPENDIX 1: Arsenic Map of Bolivia
PDF is included with submittal.
APPENDIX 2: Feasibility Analysis
Document 523
ALTERNATIVES ANALYSIS REPORT
CHAPTER: EWB SDSU
COUNTRY: Bolivia
COMMUNITY: Universidad Academica
Campesina, Carmen Pampa
PROJECT: Drinking Water for UAC - CP
PREPARED BY Rebecca Hofmeister Sarah McMahon Bruce Berdanier Greg Tanner
Brett Hankerson Emily Sumner Matt Auch Jaclyn Clark
November 10, 2011
ENGINEERS WITHOUT BORDERS-USA
www.ewb-usa.org
Document 523 – Alternatives Analysis Rev. 09-2011
Chapter Name: EWB SDSU
Community, Country: Universidad Academica Campensina, Carmen Pampa
Project Name: Drinking Water for UAC - CP
28
Alternatives Analysis Report Part 1 – Administrative
Information
1.0 Contact Information
Name Email Phone Chapter
Name
or
Organization
Name
Project Leads Sarah
McMahon
[email protected] 605-359-7713 EWB SDSU
President Gregory
Tanner
[email protected] 605-254-8591 EWB SDSU
Mentor #1 Bruce
Berdanier
605-415-3237 EWB SDSU
Mentor #2
Faculty
Advisor (if
applicable)
Bruce
Berdanier
605-415-3237 EWB SDSU
Health and
Safety Officer
Emily
Sumner
[email protected] 402-321-9697 EWB SDSU
Assistant
Health and
Safety Officer
Rebecca
Hofmeister
.edu
507-317-7729 EWB SDSU
Education
Lead
Brett
Hankerson
507-317-7729 EWB SDSU
NGO/Commu
nity Contact
Hugh
Smetelkop
[email protected] 011-591-2213-
7293 UAC CP
2.0 Travel History
Dates of Travel Assessment or
Implementation
Description of Trip
August 10-17, 2011 Assessment Assessment
Document 523 – Alternatives Analysis Rev. 09-2011
Chapter Name: EWB SDSU
Community, Country: Universidad Academica Campensina, Carmen Pampa
Project Name: Drinking Water for UAC - CP
29
3.0 Project Discipline(s): Check the specific project discipline(s) addressed in this
report. Check all that apply.
Water Supply
____ Source Development
__X_ Water Storage
__X_ Water Distribution
__X_ Water Treatment
____ Water Pump
Sanitation
____ Latrine
____ Gray Water System
____ Black Water System
Structures
____ Bridge
____ Building
Civil Works
____ Roads
____ Drainage
____ Dams
Energy
____ Fuel
____ Electricity
Agriculture
____ Irrigation Pump
____ Irrigation Line
____ Water Storage
____ Soil Improvement
____ Fish Farm
____ Crop Processing Equipment
Information Systems
____ Computer Service
Document 525 - Pre-Implementation Report Rev. 09-2011
Chapter Name: EWB SDSU
Community, Country: Unidad Academica Campesina, Carmen Pampa,
Bolivia
Project Name: Drinking Water for UAC - CP
1
4.0 Project Location Longitude: 67°41′30.3″W
Latitude: 16°15′29.7″S
Alternatives Analysis Report Part 2 – Technical Information
5.0 INTRODUCTION
Engineers Without Borders USA (EWB USA) is a national organization dedicated to engineering
investigation, assessment, design and implementation to solve problems in communities typically
in the developing world. The student chapter of EWB at South Dakota State University (EWB
SDSU) initiated a program with Unidad Academica Campensina de Carmen Pampa (UAC – CP)
in Bolivia in the fall of 2010. A team of EWB SDSU members traveled to UAC – CP in August
2011 to conduct a pre – assessment investigation at the site. This report will detail the feasibility
analysis completed to evaluate the alternatives for addressing the health problems currently
encountered by UAC – CP and the village of Carmen Pampa.
6.0 PROGRAM BACKGROUND
The Unidad Académica Campesina de Carmen Pampa (UAC-CP) is a rural university founded to
provide a BS-level education to young women and men who do not have that opportunity due to
unequal access to education by the poor. This university currently has 700 students, having
grown from 53 students when its first program started in 1994. Due to this expansive growth,
potable water systems for each of two campuses, human waste and wastewater management have
not always been adequately considered, leading to the need for improved water quality, as well
as sanitation related to animal waste and human wastewater management. The mission of the
program is to provide the university with consistent potable water and waste and wastewater
management solutions at the UAC-CP. The fulfillment of this proposed program will eliminate
problems with student illnesses resulting from poor drinking water quality, and will protect
down-stream communities from the waste generated by the university. The assessment trip in
2011 provided us with additional information regarding the community of Carmen Pampa and
how the citizens of the community are interconnected in the UAC-CP water system
considerations.
The alternatives being considered for improving the drinking water system include the following:
1. Disconnect perennially contaminated collection systems from the general distribution system.
2. Install one disinfection system for each collection system.
3. Install one disinfection system for main points of entry for each distribution system.
4. Install Individual filter systems for house/room drinking water.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 2 of 40
5. Abandon current collection systems as drinking water sources and install a new well and storage
system.
6. Install surface water treatment plant.
7. Install individual filter systems in the village and a treatment system for the university.
8. Install roof water collection systems.
9. Do Nothing
Figure 1 shows the conceptual location and relationship of the five (5) water systems in the UAC-CP
watershed. Systems 1 and 2 are the most northerly as well as the highest elevation water collection
systems and are the least affected by surface water runoff. System 3 is a localized system adjacent to the
mid system tanks of system 2 and is highly contaminated by agricultural and roadway runoff at that level
in the watershed. System 4 is not as high in elevation as systems 1 and 2 in the watershed but is currently
above agricultural activities as well as the upper roadway. Therefore, system 4 is relatively unaffected by
surface water runoff. System 5 is the lowest system in the watershed and is highly impacted by
agricultural and roadway runoff.
Figure 1. Conceptual Diagram of Water Systems at Carmen Pampa, Bolivia.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 3 of 40
7.0 DESCRIPTION OF COMPARISON METHODOLOGY
Individual alternative systems were compared based on evaluation of their impact on the local
society, the local economy, and the local environment. Impacts on society were based on the
various systems’ impact on health plus system complexity to operate and maintain. Immediate
impact on the economy was based on initial cost to build, while long term costs were based on
ongoing cost to operate and maintain including increased energy costs. Preliminary capital and
operation and maintenance costs were determined for each alternative as shown in Table 1 in
Section 4. Impact on local environment was based on increase in population that could result
from improved drinking water along with temporary construction impacts.
Each member of the SDSU EWB team evaluated the impacts for each project in each of the
categories described above. A range of values were used to score impact (-5 was the most
negative impact, +5 was the most positive impact, and 0 was a neutral impact). Each member’s
evaluation of impact for each category was summed for each system proposal. Theoretically, the
highest positive score would represent the highest rank project, and the projects could be
assigned a rank value based on decreasing summation score from most positive to most negative.
An example of one member’s evaluation matrix is shown in Table 2 in Section 5.
Rank scores were assigned to each project by each evaluator and the average rank score was
determined for each alternative proposed. Table 3 in Section 5 shows the average rank value
determined by taking the average of all ranks determined for each system alternative proposal
from each member’s Table 2 scoring.
8.0 DESCRIPTION OF ALTERNATIVES
8.1 Disconnect perennially contaminated collection systems from the general distribution
system. This alternative would disconnect systems 3 and 5 from the residential and
school drinking water systems and direct them to agricultural use. 8.2 Install one disinfection system for each collection system. This alternative would consist
of installing simple robust tablet chlorination systems at collection reservoirs in each of
the numbered system to allow for development of reasonable Ct values for reduction of
bacteria, nematodes and some protozoans (5 systems @ $1,000 per system for material
and labor). 8.3 Install one disinfection system for each distribution system. This alternative is similar to
alternative 2, but rather than installing tablet chlorinators at reservoir storage locations in
each of the five systems, liquid metered disinfection systems would dose the distribution
system prior to entry points to distribution at both the upper and lower UAC – CP
campuses and the high school (3 systems @ $2,000 per system for material and labor). 8.4 Install Individual filter systems for house/dormitory drinking water. This alternative
would consist of constructing individual sand filter systems for use at each of the
homes/dormitories for filtration of drinking and cooking water only. The sand filters at
the dormitories could be larger unit to serve multiple rooms. All other water used in the
home/dormitory for activities other than drinking and cooking would not be filtered (40
houses @ $100 each; 2 campuses and 1 high school @ $1,000 each).
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 4 of 40
8.5 Abandon current collection systems and install a new well and storage system. This
alternative would develop one or more deep wells along with elevated storage to supply
both of the campuses and the community with treated ground water. Current surface
water systems could be used for agricultural use and for other than drinking and cooking
water activities in the schools and homes. (2 deep wells with pumps @ $25,000 ea., 2 -
50,000 gallon storage tanks @ $75,000 each for material and labor including connecting
piping, valves, and appurtenances). 8.6 Install surface water treatment plant. This alternative would develop a slow sand surface
water treatment plant with disinfection for the treatment of the current surface water
systems prior to distribution to the campuses, community and high school. ($500,000 for
surface water treatment plant, $150,000 for storage tanks, for material and labor
including connecting piping, valves, and appurtenances). 8.7 Install individual filter systems in the village and disinfection or treatment for the
university campuses and high school. This alternative would consist of constructing
individual sand filter systems for use at each of the homes for filtration of drinking and
cooking water only. All other water used in the home for activities other than drinking
and cooking would not be filtered. Additionally, surface water treatment and disinfection
would be selected for the university campuses and the high school. This is a combination
of alternatives 3 and 4 with a more expanded treatment concept for the schools. 8.8 Install roof water collection systems at college campuses and high school. Substantial
water collection could be accomplished at each of the campuses and the high school due
to the large roof areas. This water could be untreated and used to replace agricultural
water, toilet and shower water, or could be treated and used for drinking and cooking (2
systems at $50,000 each). 8.9 Do Nothing. Continue in current operational mode.
Table 1 shows a summary of the alternatives and their preliminary cost estimates for construction
and operation and maintenance which were used for comparison.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 5 of 40
Table1. Preliminary Construction and Monthly Maintenance Cost Estimates.
Alt US$
Capital
Cost
US$
Monthly
Maint. Cost
1 250 87
2 5,000 200
3 6,000 200
4 7,000 137
5 200,000 500
6 650,000 1,000
7 500,000 1,500
8 100,000 125
9 0 87
9.0 ANALYSIS OF ALTERNATIVES
Individual alternative systems were compared based on evaluation of their impact on the local
society, the local economy and the local environment as described in Section 3. Table 2 is an
example of one of EWB SDSU member’s evaluation of the alternatives using the impact scoring
system described in Section 3. Table 3 is a listing of the alternatives along with their final
ranking and their average ranking score developed by the EWB SDSU team as described in
Section 3.
Table 2. Alternatives Evaluation Matrix Example.
Social Impacts Economic Impacts Environmental Impacts Sum Rank
Alt
Health
System
Complexity
Capital
Cost
Operation/
Maintenance/
Energy
Population
Increase
Construction
Impacts
1 -3 3 3 3 -2 -2 2 2
2 0 -1 0 -1 1 0 -1 7
3 2 -2 -1 -2 2 1 0 5
4 -1 0 -2 1 -1 3 0 5
5 4 2 -3 -3 4 -3 1 3
6 3 -4 -4 -4 3 -4 -10 9
7 1 -3 1 0 0 2 1 3
8 -2 1 2 2 -3 -1 -1 7
9 -4 4 4 4 -4 4 8 1
Table 3. Final Ranking of Alternatives Based on Matrix Evaluation Average Score.
Rank Alt. No. Avg
Score
1 1 1.71
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 6 of 40
2 4 3.67
3 2 4.00
3 3 4.00
3 8 4.00
6 9 5.16
7 5 6.16
8 7 6.50
9 6 8.50
10.0 DESCRIPTION OF PREFFERED ALTERNATIVE
The overall rankings determined by the group analysis averages indicate that alternative number
one is the preferred alternative. Alternative one is the disconnection of the perennially
contaminated collection systems from the general distribution system. This alternative would
disconnect systems 3 and 5 from the residential and school drinking water systems and direct
them to agricultural use. It is not surprising that this alternative was selected first in the
sustainability analysis due to its low capital and maintenance costs. Ideally this alternative can
be accomplished in conjunction with some of the more structurally intensive alternatives.
The second ranked project is alternative number four which is the construction and use of
individual filter systems at each of the village residences and dormitories. This alternative also
yields positive results for low capital and operation and maintenance costs. This project lends
itself to the construction of low cost individual filters capable of filtering approximately 20 L/d
(5 gal/d +/-) for individual homes to use for drinking water. Larger systems could be built for
the dormitories. The project could be completed for the village residents for approximately
$4,000 using locally acquired materials and components. $1,000 has been budgeted for each
campus and the high school. We anticipate the filters could be built in cooperation with local
residents and students within a two-week construction period in 2012. If all materials are
acquired before the team arrives in Carmen Pampa, the team could work with local residents and
students to construct approximately five filters per day. Educational, operational training could
also be conducted in the two week project trip. This alternative would increase current
operational costs for the maintenance of the filters over current system costs, but most of these
costs would become part of individual efforts by each home to maintain their own filter.
Alternatives 2, 3, and 8 were each scored the same overall average ranking by the group resulting
in the overall third place ranking. Alternatives 2 and 3 both represent the installation of a
disinfection system. Although both alternatives received the same average overall score from the
team evaluation, we believe it would be the easiest and most cost effective to install tablet
chlorinators (alternative number 2) on some of the existing collection and storage reservoirs
which would operate based on a certain percentage of the flow coming into the tank and achieve
the necessary Ct product for inactivation of bacteria, viruses, nematodes, and some protozoans.
The tablet chlorinators can be assembled from locally purchased piping materials, are robust and
simple to operate, and have lower capital cost than the liquid chlorinators in alternative 3.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 7 of 40
Alternative number 2 would require the purchase of liquid chlorine dosing pump and a
continuous supply of liquid chlorine. The system is more complicated to operate, calibrate and
maintain and a significant percentage of the components would have to be purchased off-the-
shelf. Alternative 8 is the establishment of roof water collection systems which could be done in
addition to alternative number 2 and would extend the available water during the dry season.
However, this alternative would require additional design and planning, and should be
considered for another future trip.
The preferred alternative for the next trip to UAC-CP is the separation of the most contaminated
systems from the water supply in conjunction with the development of disinfection for the water
collection/storage reservoirs and the implementation of individual filter systems for the
residences and dormitories.
11.0 PROFESSIONAL MENTOR/TECHNICAL LEAD ASSESSMENT
The SDSU – EWB team completed the feasibility assessment and evaluation based on the
assessment trip in August 2011 at the UAC – CP site. The team worked together to develop a
matrix evaluation system using both short and long term considerations for environmental,
economic and social impact. The final product was the development of a scoring and ranking
system to evaluated nine separate delineated alternatives. The final ranking points to the choice
of three of the alternatives that can be completed with local products for reasonable capital costs
and reasonable long term maintenance and operation costs in the near future. Long term
alternatives such as rainwater and groundwater can be considered further in the future following
more research and community discussions. Expensive surface water treatment plants are
probably not feasible for this community to build or to operate and maintain.
11.1 Professional Mentor/Technical Lead Name (who wrote the
assessment)
Bruce W. Berdanier, PE, LS
11.2 Professional Mentor/Technical Lead Assessment
I believe the next steps for this program as the team has discussed involve the design and
installation of simple, cost effective disinfection systems on the main water collection systems
and the construction of small in-house and in-dormitory drinking water filter systems as soon as
practicable. Some of the existing systems need to be separated in conjunction with the
construction work so that a fairly clean system can be maintained for drinking water purposes
while commonly contaminated systems are used for irrigation only.
11.3 Professional Mentor/Technical Lead Affirmation
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 8 of 40
I have been involved in the UAC – CP, Carmen Pampa project planning continuously since its
inception in 2010, traveled with the team to Bolivia during 2011, and accept responsibility for
the course that the project is taking.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 9 of 40
APPENDIX 3: Operation and Maintenance
PDFs of the CTI-8 Chlorinator Manual in English and Spanish, as well as O&M sheets are
included with this submittal.
APPENDIX 4: Design Drawings
PDFs of the project design drawings are included with this submittal.
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 10 of 40
APPENDIX 5: Letter of Commitment
525 - Pre-Implementation Report Revised 09/2014 EWB-SDSU Unidad Academica Campesina, Carmen Pampa, Bolivia Drinking Water for UAC-CP
© 2014 Engineers Without Borders USA. All Rights Reserved Page 11 of 40
Translation of letter of commitment:
Carmen Pampa- Coroico, May, 15 2015
Engineers Without Borders
South Dakota State University
South Dakota, USA
RE: Collaboration with Engineers Without Borders
Dear EWB-SDSU,
I am writing on behalf of the Unidad Academica Campesina-Carmen Pampa, the beneficiary of a
chlorinator on one of our two campuses (which serves approximately 400 students, teachers, and
staff) and which signed a Memorandum of Agreement in 2009 with EWB-SDSU. This
chlorinator has been successfully managed by a student under the supervision of our laboratory
manager, maintaining in the water a level of free chlorine of 0.2 to 0.4 mg/L in order to
guarantee potable water for campus Leahy. The beneficiaries of this treated water have been
satisfied, believing that the water has contributed to better health and have confidence in this
precious resource.
We are aware that there are other alternatives to treat the water, and our university is in
agreement that the chlorinator proposed for our second campus (Camups Manning) is the best
option due to its design, ease of use and maintenance, and cost. We agree to accept total
responsibility for this project once it has finished, including budgeting funds in order to buy the
materials needed to treat and test the water, as well as maintain the chlorinator. As was the case
previously, we are going to co-finance this project, approximately $200 dollars for materials
(principally the concrete security box that will contain the new chlorinator) and another $1100
dollars for travel costs, food, and lodging for the EWB group that plans to come in August of this
year. The university will also contribute with the equivalent of 80 hours of skilled and unskilled
labor (approx. value: 140 dollars). Let it be known that the university has the rights to the water
that is going to be treated.
We are very enthusiastic about the scheduled August trip. We can offer similar lodging as last
year, in a dormitory with bunk beds and a private bathroom. Food will be provided on the
university campus, and precautions will be taken to guarantee your health and safety.
With the hope that this project will be approved, we send our greetings and desires to continue
our collaboration.
Sincerely,
Father Emilio Medrano Toro
Director General
UAC-Carmen Pampa